FIDIC分包合同范本

CONDITIONS OF SUBCONTRACT

FOR WORKS OF CIVIL

ENGINEERING COSNTRUCTION

Part I- General Conditions

Part II- Guidance for the Preparation of Condition of Particular Application

With Forms of Offer and Agreement

(For use in conjunction with the Conditions of Contract for Works of Civil Engineering Construction, Forth Edition 1987 Reprinted 1992 with further amendments)

1st Edition 1994

ACKNOWLEDGEMENTS

FIDIC extends special thanks to Christopher R. Seppala and Maurizio Ragazzi, White & Case, Paris, for acting as the principal drafter of this document. This contribution to FIDIC and the profession is highly appreciated.

The draft was reviewed initially by Mario Asin of TAMS, USA and Edward Corbett of Corbett & Co., UK and subsequently by the World Bank, European International Contractors, the International Bar Association and ConSpec, all of whom provided valuable comments. Advice on insurance matters was provided by Martyn J. Nixon of Willis Corron, London.

The preparation was carried out under the general direction of the FIDIC Contracts Committee comprising K.B (Tony) Norris, Consulting Engineer, UK; Michael Mortimer-Halwkins of SwedPower, Sweden; and John Bowcock of Sir Alexander Gibb & Partner Ltd. UK.

FIDIC wishes to record its appreciation of the time and effort devoted by all the above.

The ultimate decision on the form and content of the document rests with FIDIC.

CONTENTS

PART I:GENERAL CONDITIONS

Definitions and Interpretation

1.1 Definitions

1.2 Headings and Marginal Notes

1.3 Interpretation

1.4 Singular and Plural

1.5 Notices, Consents, Approvals, Certificates, Confirmation and

Determinations

1.6 Instructions in Writing

General Obligations

2.1 Subcontractor’s General Responsibilities

2.2 Performance Security

2.3 Programme to be submitted by Subcontractor

2.4 Assignment of Subcontract

2.5 Sub-contracting

Subcontract Documents

3.1 Language/s

3.2 Governing Law

3.3 Subcontract Agreement

3.4 Priority of Subcontract Documents

Main Contract

4.1 Subcontractor’s Knowledge of Main Contract

4.2 Subcontractor’s Responsibilities in Relation to Subcontract Works 4.3 No Privity of Contract with Employer

4.4 Possible Effects of Subcontractor’s Breaches of Subcontract

Temporary Works, Contractor’s Equipment and/or Other Facilities (if Any)

5.1 Subcontractor’s Use of Temporary Works

5.2 Subcontractor’s Use of Contractor’s Equipment and/or Other

Facilities (if any) in Common with Other Subcontractors

5.3 Subcontractor’s Exclusive Use of Contractor’s Equipment and/or

Facilities (if Any)

5.4 Indemnification for Misuse of Temporary Works, Contractor’s

Equipment and/or Other Facilities (if Any)

Site Working and Access

6.1 Working Hours on Site; Subcontractor’s Compliance with Rules and

Regulations

6.2 Availability of Site to Subcontractor and Access to Site

6.3 Subcontractor’s Obligation to Permit Access to Subcontract Works

Commencement and Completion

7.1 Commencement of Subcontract Works;

Subcontract’s Time for Completion

7.2 Extension of Subcontractor’s Time for Completion

7.3 Contractor’s Obligation to Notify

Instructions and Decision

8.1 Instruction and Decision under Main Contract

8.2 Instruction under Subcontract

Variations

9.1 Variation of Subcontract Works

9.2 Instructions for Variation

Valuation of Variations

10.1 Manner of Valuation

10.2 Assessment of Value of Variation

10.3 Valuation by Reference to Measurement under Main Contract

10.4 Quantity Estimated and Quantity Executed

10.5 Daywork

Notices and Claims

11.1 Notices

11.2 Claims

11.3 Effects of Failure to Give Notice

Subcontractor’s Equipment, Temporary Works and Materials

12.1 Incorporation by Reference

Indemnities

13.1 Subcontractor’s Obligation to Indemnify

13.2 Contractor’s Obligation to Indemnify

Outstanding Work and Defects

14.1 Subcontractor’s Obligation before Taking-Over

14.2 Subcontractor’s Obligation after Taking-Over

14.3 Defects Caused by Contractor’s Act or Default

Insurance

15.1 Subcontractor’s obligation to Insure

Contractor’s Obligation to Insure; Subcontract Works at Subcontractor’s Risk

Evidence of Insurance; Remedy on Failure to Insure

Payment

16.1 Subcontractor’s Monthly Statements

16.2 Contractor’s Monthly Statements

16.3 Payment Due; Payment Withheld or Deferred; Interest

16.4 Payment of Retention Money

16.5 Payment of Subcontract Price and Other Sums Due

16.6 Cessation of Contractor’s Liability

Termination of Main Contract

17.1 Termination of Subcontractor’s Employment

17.2 Payment after Termination

17.3 Termination of Main Contract in Consequence of Breach of Subcontract

Default of Subcontractor

18.1 Termination of Subcontract

18.2 Contractor’s and Subcontractor’s Rights and Liabilities upon

Termination

18.3 Contractor’s Powers

Settlement of Disputes

19.4 Amicable Settlement and Arbitration

19.2 Dispute in Connection with or Arising out of Main Contract Touching

or Concerning Subcontract Works

Notices and Instructions

20.1 Giving of Notices and Instructions

20.2 Change of Address

Changes in Cost and Legislation

21.1 Increase or Decrease of Cost

21.2 Subsequent Legislation

Currency and Rates of Exchange

22.1 Currency Restriction

22.2 Rates of Exchange

REFERENCE TO PART II

PART II:

GUIDANCE FOR THE PREPARATION OF CONDITIONS OF PARTICULAR APPLICATION

1 Definitions and Interpretation

2 General Obligations

3 Subcontract Document

4 Main Contract

5 Temporary Works, Contract’s Equipment and/or Other Facilities (if

Any)

6 Site Working and Access

7 Commencement and Completion

12 Subcontractor’s Equipment, Temporary Works and Materials

14 Outstanding Work and Defects

15 Insurances

16 Payment

19 Settlement of Disputes

22 Currency and Rates of Exchange

SUBCONTRACTOR’S OFFER

APPENDIX TO SUBCONTRACTOR’S OFFER SUBCONTRACT AGREEMENT

PART I – GENERAL CONDITIONS

Definitions and Interpretation

1.1 In the Subcontract (as hereinafter defined) all words and

expression shall have the same meanings as are respectively

assigned to them in the Main Contract (as hereinafter

defined), except where the context otherwise requires and

except that the following words and expressions shall have

the meanings hereby assigned to them:

(a)(i) “Employer”means the person named as such in Part

II of the Conditions of Subcontract and the legal

successors in title to, or assignees of, such person,

as the Contractor shall notify the Subcontractor from

time to time.

(ii) “Contractor” means the person named as such in

Part II of the Conditions of the Subcontract and the

legal successors in title to such person, but not

(except with the consent of the Subcontractor) any

assignee of such person.

(iii) “Subcontractor” means the person whose offer

has been accepted by the Contractor and the legal

successors in title to such person, but not (except with

the consent of the Subcontractor) any assignee of such

person.

(iv) “Engineer” means the person appointed by the

Employer to act as Engineer for the purposes of the Main

Contract and named as such in Part II of the Conditions

of Subcontract.

(b)(i) “Main Contract” means the contract entered into

between the Employer and the contractor, Particulars

of Which are given in Part II of the Conditions of

Subcontract.

(ii) “Subcontract”means the Conditions of

Subcontract (Part I and II), the Subcontract

Specification, the Subcontract Drawings, the

Subcontract Bill of Quantities, the Subcontract’s

Offer, the Contract’s Letter of Acceptance, the Subcontract Agreement (if completed) and such further documents as may be expressly incorporated in the Contractor’s Letter of Acceptance or Subcontract Agreement (if competed).

(iii) “Subcontract Specification”means the specification of the Subcontract Works included in the Subcontract and any modification thereof or addition thereto made pursuant to Clause 9.

(iv) “Subcontract Drawings”means all drawings, calculations and technical information of a like nature under the Subcontract.

(v) “Subcontract Bill of Quantities”means the priced and completed bill of quantities forming part of the Subcontractor’s Offer.

(vi) “Subcontractor’s Offer”means the Subcontractor’s priced offer to the Contractor for the execution and completion of the Subcontract Works and the remedying of any defects therein in accordance with the provisions of the Subcontract, as accepted by the Contractor’s Letter of Acceptance.

(vii) “Contractor’s Letter of Acceptance”means the formal acceptance by the Contractor of the Subcontractor’s Offer.

(viii) “Subcontract Agreement”means the subcontract agreement (if any) referred to in Sub-Clause 3.3.

(ix) “Appendix to Subcontractor’s Offer” means the appendix comprised in the form of Subcontractor’s Offer annexed to the Conditions of Subcontract.

(x) “Conditions of Subcontract”means Parts I and II of the FIDIC “Conditions of Subcontract for Works of Civil Engineering Construction (for use in conjunction with the Conditions of Contract for Works of Civil Engineering Construction, Forth Edition 1987 Reprinted 1922 with further amendments)”, 1994, as adapted by the Contractor and the Subcontractor and forming part

of the Subcontract.

(xi) “Conditions of Main Contract” means Part I of the FIDIC “Conditions of Contract for Works of Civil Engineering Construction, Forth Edition 1987 Reprinted 1922 with further amendments”, and Part II such Conditions as adapted by the Employer and the Contractor, which form part of the Main Contract.

(c)(i) “Subcontractor’s Commencement Date” means the

time for completion of the Subcontract Works or any section thereof as stated in the Appendix to Subcontractor’s Offer (or as extended under Clause 7) calculated from the Subcontractor’s Commencement Date.

(ii) “Subcontractor’s Time for Completion” means the time for completion of the Subcontract Works or any Section thereof for the execution and completion of the Subcontract Works and the remedying of any defects therein in accordance with the provisions of the Subcontract.

(d)“Subcontract Price”means the sum stated in the

Contractor’s Letter of Acceptance as payable to the Subcontractor for the execution and completion of the Subcontract Works and the remedying of any defects therein in accordance with the provisions of the Subcontract.

(e)(i) “Main Works” means the Works as defined in the

Main Contract.

(ii) “Subcontract Works” means the Works described in Part II of the Conditions of Subcontract.

(iii) “Subcontractor’s Equipment”means all appliances and things of whatsoever nature (other than Temporary Works) required for the execution and completion of the Subcontract Works and the remedying of any defects therein, but dose not include Plant, materials or other things intended to form or forming part of the Subcontract Works.

Headings and Marginal Notes

1.2

The headings and marginal notes in the Conditions of Subcontract shall not be deemed part thereof or be taken into consideration in the interpretation or construction thereof or of the Subcontract. Interpretation 1.3

Words importing persons or parties shall include firms and corporations and any organization having legal capacity. Singular and Plural

1.4 Words importing the singular only also include the plural

and vice versa where the context requires. Notices,

Consents,

Approvals,

Certificates,

Confirmations

and

Determinations

1.5 Whatever in the Subcontract provision is made for the giving or issue of any notice, consent, approval, certificate, confirmation or determination by any person, unless otherwise specified such notice, consent, approval, certificate, confirmation or determination shall be in writing and the words “notify”, “certify ”, “confirm ” or determine ” shall be construed accordingly. Any such notice, consent, approval, certificate, confirmation or determination shall not unreasonably be withheld or delayed. Instruction in

Writing

1.6 Instructions given by the Contractor shall be in writing, provided that if for any reason the Contractor considers it necessary to give any such instruction orally, the Subcontractor shall comply with such instruction. Confirmation in writing of such oral instruction given by the Contractor, whether before or after carrying out of the instruction shall be deemed to be an instruction within the meaning of this Sub Clause. Provided further that if the Subcontractor, within 7 days, confirms in writing to the Contractor any oral instruction of the Contractor and such confirmation is not contradicted in writing within 7 days by the Contractor, it shall be deemed to be an instruction of the Contractor.

General Obligations Subcontractor’

s General

Responsibilitie

s 2.1 The Subcontractor shall, with due care and diligence, design (to the extent provided for by the Subcontract), execute and complete the Subcontract Works and remedy any

defects therein in accordance with the provisions of the

Subcontract. The Subcontractor shall provide all

superintendence, labor, materials, Plant,

Subcontractor’s Equipment and all other things, whether of a temporary or permanent nature, required in and for such design, execution, completion and remedying of any defects, so far as the necessity for providing the same is specified in or is reasonably to be inferred from the Subcontract, and except as otherwise agreed in accordance with Clause 5 and set out in Part II of the Conditions of Subcontract.

The Subcontractor shall give prompt notice to the Contractor of any error, omission, fault or other defect in the design of or specification for the Subcontract Works which he discovers when reviewing the Subcontract and/or the Main Contract or executing the Subcontract Works.

Performance

Security 2.2 If the Subcontract requires the Subcontractor to obtain

security for his proper performance of the Subcontract, he

shall obtain and provide to the Contractor such security

in the sum stated in the Appendix to Subcontractor’s

Offer. Such security shall be in the form annexed to the

Conditions of the Subcontract or in such form as may be

agreed between the Contractor and the Subcontractor. The

institution providing such security shall be subject to the

approval of the Contractor. The cost of complying with the

requirements of this Clause shall be borne by the

Subcontractor, unless the Subcontract otherwise provides.

The performance security shall be valid until the

Subcontractor has executed and completed the Subcontract

Works and remedied any defects therein in accordance with

the Subcontract. No claim shall be made against such

security after the issue of the Defects Liability

Certificate in respect of the Main Works and such security

shall be returned to the Subcontractor within 28 days of

the issue of the said Defect Liability Certificate.

Prior to making a claim under the performance security the

Contractor shall, in every case, notify the Subcontractor

stating the nature of the default in respect of which the

claim is to be made.

Programme to be Submitted by

Subcontractor 2.3 The Subcontractor shall, within the time stated in Part II

of the Conditions of Subcontract after the date of the

Contractor’s Letter of Acceptance, submit to the

Contractor for his consent a programme, in such form and detail as the Contractor shall reasonably prescribe, for the execution of the Subcontract Works. The Subcontractor shall, whenever required by the Contractor, also provide in writing for his information a general description of the arrangements and methods which the Subcontractor proposes to adopt for the execution of the Subcontract Works.

If at any time it should appear to the Contractor that the actual progress of the Subcontract Works does not conform to the programme to which consent has been given, the Subcontractor shall produce, at the request of the Contractor, a revised programme showing the modifications to such programme necessary to ensure completion of the Subcontract Works within the Subcontractor’s Time for Completion.

Assignment of Subcontract 2.4 The Subcontractor shall not, without the prior consent of

the Contractor (which consent, notwithstanding the

provisions of Sub-Clause 1.5, shall be at the sole

discretion of the Contractor), assign the Subcontract or

any part thereof, or any benefit or interest therein or

thereunder, otherwise than by:

(a)a charge in favour of the Subcontractor’s bankers of

any monies due or to become due under the Subcontract,

or

(b)assignment to the Subcontractor’s insurers (in cases

where the insurers have discharged the

Subcontractor’s loss or liability) of the

Subcontractor’s right to obtain relief against any

other party liable.

Sub-

sub contracting 2.5 The Subcontractor shall not subcontract the whole of the

Subcontract Works, nor shall he subcontract any part of the

Subcontract Works without the prior consent of the

Contractor. Any such consent shall not relieve the

Subcontractor from any liability or obligation under the

Subcontract and the Subcontractor shall be responsible for

the acts, defaults and neglects of any of his

subcontractors, including such subcontractor’s agents,

servants or workmen as fully as if they were the acts,

defaults or neglects of the Subcontractor, his agents,

servants or workmen.

Provided that the Subcontractor shall not be required to

obtain such consent for:

(a)the provision of labor, or

(b)the purchase of materials which are in accordance with

the standards specified in the Subcontract and/or the

Main Contract.

In the event of a subcontractor having undertaken towards

the Subcontractor in respect of the work executed, or the

goods, materials, Plant or services supplied by such

subcontractor, any continuing obligation extending for a

period exceeding that of the Defects Liability Period under

the Main Contract in respect of the Main Works or of the

Section or Sections or part or parts thereof in which the

Subcontract Works are comprised, as the case may be, the

Subcontract shall at any time, after the expiration of such

Period, assign to the Contractor, at the Contractor’s

request and cost, the benefit of such obligation for the

unexpired duration thereof.

Subcontract Documents

Language/s 3.1 Unless otherwise stated in Part II of the Conditions of

Subcontract:

(a)the language or languages in which the Subcontract

documents shall be drawn up shall be the same as the

language or languages in which the Main Contract

documents have been drawn up, and

(b)if the Subcontract documents are drawn up in more than

one language, the Subcontract shall be construed and

interpreted according the Ruling Language of the Main

Contract.

Governing Law 3.2 Unless otherwise stated in Part II of the Conditions of

Subcontract, the law of the country or state which applies

to the Main Contract and according to which the Main

Contract is construed shall also apply to the Subcontract

and be the law according to which the Subcontract shall be

construed.

Subcontract Agreement 3.3 The Subcontractor shall, if called upon so to do, enter into

and execute the Subcontract Agreement, to be prepared and

completed at the cost of the Contractor, in the form annexed

to the Conditions of Subcontract with such modification as

may be necessary.

Priority of Subcontract Documents 3.4 The several documents forming the Subcontract, listed in

the Contractor’s Letter of Acceptance or the Subcontract

Agreement (if any), are to be taken as mutually explanatory

or one another. Unless otherwise provided in the

Subcontract, the priority of documents forming the

Subcontract shall be as follows:

(1)The Subcontract Agreement (if any);

(2)The Contractor’s Letter of Acceptance;

(3)The Subcontractor’s Offer

(4)Part II of the Conditions of Subcontract;

(5)Part I of the Conditions of Subcontract; and

(6)Any other document forming part of the Subcontract.

Main Contract

Subcontractor’s Knowledge of

the Main

Contract 4.1 The Contractor shall make the Main Contract (other than the

details of the Contractor’s prices thereunder as stated

in the bill of quantities or schedules of rates and prices

as the case may be) available for inspection to the

Subcontractor and, if so requested by the Subcontractor,

shall provide the Subcontractor with a true copy of the Main

Contra ct (less such details of the Contractor’s prices),

at the cost of the Subcontractor. The Contractor shall, in

any event, provide the Subcontractor with a copy of the

Appendix to Tender to the Main Contract together with Par

t II of the Conditions of Main Contract and details of any

other contract conditions which apply to the Main Contract

which differs from Part I of the Conditions of Main

Contract. The Subcontractor shall be deemed to have full

knowledge of the provisions of the Main Contract (less such

d etails of th

e Contractor’s prices).

Subcontractor’s Responsibiliti es in Relation to Sub-contract

Works 4.2 Save where the provisions of the Subcontract otherwise

require, the Subcontractor shall so design (to the extent

provided for by the Subcontract), execute and complete the

Subcontract Works and remedy any defects therein that no

act or omission of his in relation thereto shall constitute, cause or contribute to any breach by the Contractor of any of his obligations under the Main Contract. The Subcontractor shall, save as aforesaid, assume and perform hereunder all the obligations and liabilities of the Contractor under the Main Contract in relation to the Subcontract Works.

No Privity of Contract with the Employer 4.3 Nothing herein shall be construed as creating any privy of

contract between the Subcontractor and the Employer.

Possible Effect s of Subcontrac tor’s Breaches

of

Subcontract 4.4 If the Subcontractor commits any breaches of the

Subcontract, he shall indemnify the Contractor against any

damages for which the Contractor becomes liable under the

Main Contract as a result of such breaches. In such event,

the Contractor may, without prejudice to any other method

of recovery, deduct such damages from monies otherwise

becoming due to the subcontractor.

Temporary Works, Contractor’s Equipment and/or

Other Facilities (if Any)

Subcontractor’s

Use of Temporary

Works 5.1 Unless otherwise stated in Part II of the Conditions of

Subcontract, the Contractor shall not be required to

provide or retain any Temporary Works for the

Subcontractor. However, the Contractor shall permit the

Subcontractor, in common with the Contractor and/or such

other subcontractors as the Contractor may allow, for the

purpose of executing and completing the Subcontract Works

and remedying any defects therein, to use such Temporary

Works as are from time to time provided by the Contractor

in connection with the Main Works. No such permission shall

impose any liability upon the Contractor in respect of the

use of such Temporary Works by the Subcontractor, his

agents, servants or workmen, nor relieve the Subcontractor

of any statutory or other obligation to test or inspect the

Temporary Works to be used by his agents, servants or

workmen or to provide suitable Temporary Works for their

use.

Subcontractor’s

Use of Contractor’s 5.2 The Contractor shall provide at the Site the Contra ctor’s

Equipment and/or other facilities (if any) specified in

Part II of the Conditions of Subcontract and shall permit

the Subcontractor, in common with the Contractor and/or

Equipment and/or Other Facilities (if Any) in Common

with Other Subcontractors such other subcontractors as the Contractor may allow, to have the use thereof for the purposes of executing and completing the Subcontract Works but not of remedying any defects therein, upon such terms and conditions (if any) as specified in Part II of the Conditions of Subcontract.

Subcontractor’s

Use of Contractor’s

Equipment 5.3 The Contractor shall also provide for the exclusive use by

the Subcontractor of the Contractor’s Equipment and/or

other facilities (if any) specified in Part II of the

Conditions of Subcontract upon such terms and conditions

(if any) as are specified therein.

Subcontractor’s

Exclusive Use o f Contractor’s Equipment and/o r Other Facilit

ies

(if Any) 5.4 The Subcontractor shall indemnify the Contractor against

any damages arising from the misuse by the Subcontractor,

his agents, servants or workmen, of Temporary Works,

Contractor’s Equipment and /or facilities provided for

his use by the Contractor.

Site Working and Access

Working Hours

on Site; Subcontractor’s Compliance with Rules and Regulations 6.1 The Subcontractor shall observe the working hours of the

Contractor as contained in Part II of the Conditions of

Subcontract, unless otherwise agreed, and shall comply

with all rules and regulations governing the execution of

the work, the arrival at and the departure from the Site

of materials and Subcontractor’s Equipment and storage

materials and Subcontractor’s Equipment on the Site.

Availability

of Site to Subcontractor and Access to

Site 6.2 The Contractor shall, from time to time, make available to

the Subcontractor so much of the Site and such access as

may be required to enable the Subcontractor to proceed with

the execution of the Subcontract Works with due dispatch

in accordance with the Subcontract.

The Contractor shall not be bound to make available

exclusively to the Subcontractor any part of the Site,

unless otherwise stated in Part II of the Conditions of

Subcontract.

Subcontractor’s Obligation to 6.3 The Subcontractor shall permit the Contractor, the

Engineer, and any person authorized by either of them, to

have reasonable access, during working hours, to the

Permit Access of Subcontract

Works Subcontract Works and to the places on the Site where any work or materials therefor are being executed, prepared or stored. The Subcontractor shall also permit or procure reasonable access for the Contractor, the Engineer, and any person authorized by either of them, to such places off the Site where work is being executed or prepared by or on behalf of the Subcontractor in connection with the Subcontract Works.

Commencement and Completion

Commencement of Subcontracts

Works; Subcontractor’

s Time for

Completion 7.1 The Subcontractor shall commence the Subcontract Works

within 14 days, or such other period as may be agreed in

writing, after the receipt by him of a notice to this effect

from the Contractor, which notice shall be issued within

the time stated in the Appendix to Subcontractor’s Offer

after the date of the Contractor’s Letter of Acc eptance.

Thereafter, the Subcontractor shall proceed with the

Subcontract Works with due expedition and without delay,

except such as may be expressly sanctioned or instructed

by the Contractor. The Subcontract Works and, if

applicable, any Section required to be completed within a

particular time as stated in the Appendix to

Subcontractor’s Offer shall be completed within the time

for completion stated in the Appendix to Subcontractor’s

Offer for the Subcontract Works or the Section (as the case

may be), calculated from the Subcontractor’s Commencement

Date, or such extended time as may be allowed under

Sub-Clause 7.2.

Extension of Su bcontractor’s Time for Comple

tion 7.2 If the Subcontractor shall be delayed in the execution of

the Subcontract Works or, if applicable, any Section

thereof by any:

(a)circumstance in regard to which the Contractor is

entitled to receive from the Engineer an extension of

his time for completion of the Main Works under the Main

Contract,

(b)instruction pursuant to Sub-Clause 8.2 to which

paragraph (a) of this Sub-Clause does not apply, or

(c)breach of the Subcontract by the Contractor or for which

the Contractor is responsible,

then in any such event that Subcontractor shall be entitled to such extension of the Subcontractor’s Time for Completion of the Subcontract Works or such Section thereof as may in all the circumstances be fair and reasonable.

Provided that the Subcontractor shall not be entitled to such extension of time unless he has submitted to the Contractor notice of the circumstances which are delaying him within 14 days of such delay first occurring together with detailed particulars in justification of the extension of time claimed in order that the claim may be investigated at the time and, in any case to which paragraph (a) of this Sub-Clause applies, the extension shall not in any event exceed the extension of time to which the Contractor is entitled under the Main Contract.

Provided also that, where an event has a continuing effect such that it is not practicable for the Subcontractor to submit detailed particulars within the period of 14 days referred to in this Sub-Clause, he shall nevertheless be entitled to an extension of time provided that has submitted to the Contractor interim particulars at intervals of not more than 14 days and final particulars within 14 days of the end of the effects resulting from the event.

Contractor’s Obligation to

Notify 7.3 The Contractor shall promptly notify the Subcontractor of

all extensions of time obtained under the provisions of the

Main Contract which affect the Subcontract.

Instructions and Decisions

Instructions an d Decisions und

er

the Main

Contract 8.1 Subject to Clause 9, the Subcontractor shall in relation

to the Subcontract Works comply with all instructions and

decisions of the Engineer which are notified and confirmed

to him as an instruction by the Contractor, irrespective

of whether such instructions and decisions were validly

given under the Main Contract. The Subcontractor shall have

the like rights (if any) to payment from the Contractor in

respect of such compliance as the Contractor has against

the Employer under the Main Contract. Further, if any such

instruction or decision notified and confirmed as

aforesaid is invalidly or incorrectly given by the Engineer

under the Main Contract, then the Subcontractor shall be

entitled to recover such costs as may be reasonable (if any) from the Contractor of complying therewith to the extent that such costs were not caused or contributed to by any breach of the Subcontract by the Subcontractor.

Instructions un der Subcontract 8.2 The Subcontractor shall take instructions only from the

Contractor. The Contractor shall have the like authority

in relation to the Subcontract Works to give instructions

as the Engineer has in relation to the Main Works under the

Main Contract. The Subcontractor shall have the like

obligations to abide by and comply therewith and the like

rights in relation thereto as the Contractor has under the

Main Contract. The said authority of the Contractor shall

be exercisable in any case irrespective whether the

Engineer has exercised like authority in relation thereto

under the Main Contract.

Variations

Variations of S ub-contract Wor

ks 9.1 The Subcontractor shall only make such variations of the

Subcontract Works, whether by way of alteration,

addition ,or omission, as may be instructed by:

(a)the Engineer under the Main Contract and notified and

confirmed as an instruction to the Subcontractor by the

Contractor, or

(b)the Contractor

Any instruction relating to the Subcontract Works which is

given by the Engineer under the Main Contract and

constitutes a variation thereunder shall be deemed to

constitute a variation of the Subcontract Works, if

notified and confirmed by the Contractor in accordance with

paragraph (a) of this Sub-Clause.

Instructions for Variation

s 9.2 The Subcontractor shall not act upon an unconfirmed

instruction for the variation of the Subcontract Works

which is directly received by him from the Employer or the

Engineer. If the Subcontractor shall receive any such

direct instruction, he shall forthwith inform the

Contractor thereof and shall supply the Contractor with a

copy of such direct instruction, in given in writing. The

Subcontractor shall only act upon such instruction as

植筋承包合同协议书范本标准版

植筋承包合同 甲 方: ________________________ 乙 方: ________________________ 签订日期: ___ 年 _____ 月 ____ 日 编号 号:

发包方(简称甲方): 承包方(简称乙方): 按照《中华人民共和国合同法》、《中华人民共和国建筑法》和编号为项目(合)字第号本工程《建设工程施工合同》以下简称为“总合同”)的条款及本工程施 工现场具体情况,甲方将本工程植筋专业工程分包给乙方施工,经双方协商一致,达成以下合同 条款: 一、工程概况 建设单位名称: 工程名称:项目施工。 建设地点:市。 建筑面积:m2 结构类型:。 层数:层 二、质量要求: 合格,经检测达不到合格按合同价款的%支付违约金。 三、工期要求:该合同内容按甲方要求进度按时完成。由于乙方原因造成的工期延误,按元/天支付违约金,累计计算。 四、承包范围及工作内容:施工图、补充施工图、设计变更范围内中所有的墙体 拉筋、构造柱、过梁、门边柱等需要植筋的工作。 五、承包方式:包工、包料(钢筋除外)、包工具、包质量、包工期、包安全、包文明施工。 六、合同价款:按实结算

植筋规格(mm单价(元/个)植筋规格(mm单价(元/个)$ 6.5$ 18 $ 8$ 20 $ 10$ 22 $ 12$ 25 $ 14$ 28 $ 16 2、以上单价均包括完成该项目的电钻、电线、吹风、建力得胶水、人工费、生产工人劳动保护 费、保险费、工伤人员工资、病假人员工资、管理费及税金、乙方的管理费及税金、利润、风险 费、措施费、政策性人工调差等所有费用。包括工期要求、质量要求、地理位置、现场情况、现 场材料运输、材料堆放地点、工人食宿、现场机械配备变化、不同施工季节、安全文明施工要求 等所涉及的一切费用。 七、工程付款 1、工程付款:第一次支付工程款同时满足有地下室的部分施工至地下室顶板混凝土浇筑完成, 无地下室的部分施工至首层地面混凝土浇筑完成后支付已完工程量价款的%以后按完成 进度付款%余款于交工验收合格后(工程总体验收)在半年内付清 2、乙方按规定缴纳结算总价%的个人所得税,由甲方在每次付款时按付款额扣除(如遇国 家及地方税收政策调整按调整后的税率扣除),乙方的管理费和税金由乙方自行交纳。 3、为了保证民工工资的发放,由乙方按进场人员花名册造工资表(花名册必须附身份证复印件 后送甲方备案,工资表人员必须与经过备案的花名册上人员一致)后送甲方,由甲方财务人员根

第十章 fidic工程施工合同条件_secret_修正版

第十章 FIDIC工程施工合同条件 第一节 FIDIC合同条件概述 一、 FIDIC组织简介 FIDIC是“国际咨询工程师联合会”的缩写。该组织在每个国家或地区只吸收一个独立的咨询工程师协会作为团体会员,至今已有60多个发达国家和发展中国家或地区的成员,因此它是国际上最具有权威性的咨询工程师组织。我国已于1996年正式加入FIDIC组织。 二、 FIDIC合同条件简介 为了规范国际工程咨询和承包活动,FIDIC先后发表过很多重要的管理性文件和标准化的合同文件范本。目前作为惯例已成为国际工程界公认的标准化合同格式有适用于工程咨询的《业主~咨询工程师标准服务协议书》;适用于施工承包的《土木工程施工合同条件》、《电气与机械工程合同条件》、《设计~建造与交钥匙合同条件》和《土木工程分包合同条件》。1999年9月,FIDIC又出版了新的《施工合同条件》、《工程设备与设计~建造合同条件》、《EPC交钥匙合同条件》及《合同简短格式》。这些合同文件不仅被FIDIC成员国广泛采用,而且世界银行、亚洲开发银行、非洲开发银行等金融机构也要求在其贷款建设的土木工程项目实施过程中使用以该文本为基 础编制的合同条件。

这些合同条件的文本不仅适用与国际工程,而且稍加修改后同样适用于国内工程,我国有关部委编制的适用于大型工程施工的标准化范本都以FIDIC编制的合同条件为蓝本。 (一)土木工程施工合同条件 《土木工程施工合同条件》是FIDIC最早编制的合同文本,也是其它几个合同条件的基础。该文本适用于业主(或业主委托第三人)提供设计的工程施工承包,以单价合同为基础(也允许其中部分工作以总价合同承包),广泛用于土木建筑工程施工、安装承包的标准化合同格式。土木工程施工合同条件的主要特点表现为,条款中责任的约定以招标选择承包商为前提;合同履行过程中建立以工程师为核心的管理模式。 (二)电气与机械工程合同条件 《电气与机械工程合同条件》适用于大型工程的设备提供和施工安装,承包工作范围包括设备的制造、运送、安装和保修几个阶段。这个合同条件是在土木工程施工合同条件基础上编制的,针对相同情况制定的条款完全照抄土木工程施工合同条件的规定。与土木工程施工合同条件的区别主要表现为:一是该合同涉及的不确定风险的因素较少,但实施阶段管理程序较为复杂,因此条目少款数多;二是支付管理程序与责任划分基于总价合同。这个合同条件一般适用于大型项目中的部分工程。

植筋承包合同协议书范本 标准版

编号:_____________植筋承包合同 甲方:________________________________________________ 乙方:___________________________ 签订日期:_______年______月______日

发包方(简称甲方): 承包方(简称乙方): 按照《中华人民共和国合同法》、《中华人民共和国建筑法》和编号为项目(合)字第号本工程《建设工程施工合同》以下简称为“总合同”)的条款及本工程施工现场具体情况,甲方将本工程植筋专业工程分包给乙方施工,经双方协商一致,达成以下合同条款: 一、工程概况 建设单位名称: 工程名称:项目施工。 建设地点:市。 建筑面积:m2, 结构类型:。 层数:层 二、质量要求:合格,经检测达不到合格按合同价款的%支付违约金。 三、工期要求:该合同内容按甲方要求进度按时完成。由于乙方原因造成的工期延误,按元/天支付违约金,累计计算。 四、承包范围及工作内容:施工图、补充施工图、设计变更范围内中所有的墙体拉筋、构造柱、过梁、门边柱等需要植筋的工作。 五、承包方式:包工、包料(钢筋除外)、包工具、包质量、包工期、包安全、包文明施工。

六、合同价款:按实结算 1、包干单价: 2、以上单价均包括完成该项目的电钻、电线、吹风、建力得胶水、人工费、生产工人劳动保护费、保险费、工伤人员工资、病假人员工资、管理费及税金、乙方的管理费及税金、利润、风险费、措施费、政策性人工调差等所有费用。包括工期要求、质量要求、地理位置、现场情况、现场材料运输、材料堆放地点、工人食宿、现场机械配备变化、不同施工季节、安全文明施工要求等所涉及的一切费用。 七、工程付款 1、工程付款:第一次支付工程款同时满足有地下室的部分施工至地下室顶板混凝土浇筑完成,无地下室的部分施工至首层地面混凝土浇筑完成后支付已完工程量价款的%,以后按完成进度付款%,余款于交工验收合格后(工程总体验收)在半年内付清 2、乙方按规定缴纳结算总价%的个人所得税,由甲方在每次付款时按付款额扣除(如遇国家及地方税收政策调整按调整后的税率扣除),乙方的管理费和税金由乙方自行交纳。 3、为了保证民工工资的发放,由乙方按进场人员花名册造工资表(花名册必须附身份证复印件

FIDIC合同条件下的施工管理

FIDIC合同条件下的施工管理 (总分:71.00,做题时间:90分钟) 一、{{B}}单项选择题{{/B}}(总题数:35,分数:35.00) 1.FIDIC合同条件规定当颁发部分工程移交证书时,( )。 (分数:1.00) A.不应返还保留金 B.应退还一半保留金 C.应退还该部分工程占合同工程相应比例保留金的一半√ D.应全部退还保留金 解析: 2.某采用FIDIC《施工合同条件》的合同,工程师审查承包商提交的施工组织设计和进度计划时,认为承包商使用的施工设备数量不够而不能保证工程进度,则工程师( )。 (分数:1.00) A.有权要求增加施工设备,增加的费用由承包商承担 B.有权要求增加施工设备,增加的费用由业主承担 C.无权要求增加施工设备,但有权要求加快施工进度√ D.无权要求增加施工设备,也无权要求加快施工进度 解析: 3.某采用FIDIC《施工合同条件》的工程,未经竣工检验,业主提前占用工程。工程师应及时颁发工程接收证书,但应当( )。 (分数:1.00) A.以颁发工程接收证书日为竣工日,承包商不再对工程质量缺陷承担责任 B.以颁发工程接收证书日为竣工日,承包商对工程质量缺陷仍承担责任 C.以业主占用日为竣工日,承包商不再对工程质量缺陷承担责任 D.以业主占用日为竣工日,承包商对工程质量缺陷仍承担责任√ 解析: 4.按照FIDIC分包合同条件规定,分包商的施工受到业主原因的干扰后向承包商提出索赔要求,承包商收到索赔报告后( )。 (分数:1.00) A.认为由于不属于自己的责任拒绝索赔要求 B.认为索赔成立,自己垫付赔偿款后再向业主索要 C.不预先支付任何款项,以自己的名义代替分包商向工程师递交索赔报告√ D.不预先支付任何款项,向工程师转交分包商的索赔报告 解析: 5.按照FIDIC《施工合同条件》规定,施工中遇到( )影响,属于承包商应承担的风险。 (分数:1.00) A.不利的气候条件√ B.招标文件未说明的污染 C.不利于施工的外界自然条件 D.其他承包商的干扰 解析: 6.依据FIDIC《施工合同条件》,当工程师发现承包商使用的施工设备不能保证工程质量时,要求承包商更换,则( )。 (分数:1.00) A.增加的费用和工期延误责任都由发包人承担 B.增加的费用由发包人承担,工期延误责任由承包人承担 C.增加的费用由承包人承担,工期延误责任由发包人承担

钢筋工程劳务分包合同

钢筋分项工程劳务分包合同甲方:乙方:工程地址:工程名称:甲方将承建的后亭茅洲山工业厂房工程钢筋分项工程承包给乙方,根据《经济合同法》、《建筑法》、《劳动法》有关条款,本着公平、互利的原则,甲、乙双方经协商达成以下协议:一、分包范围及方式(一)分包范围 1、茅洲山工业园厂房所有工程按结施、建施图纸(包括构造柱、过梁、女儿墙、看台、窗头台板、空调板、桩芯、消防水池、门卫室、化粪池等所有钢筋工程)的图纸及变更工程所有钢筋制作与安装全过程。 2、钢筋制作、安装及焊接钢筋、铁件预埋、操作架安拆、施工余物杂物的清理、施工用机械设备、工具、材料的清理及堆放。短筋按现场管理人员安排尽量焊接使用,不准浪费材料。 3、负责制安钢筋保护层垫块。 4、负责插柱、构造柱的预留筋(如乙方不及时插预留筋,或甲方派人插筋和以后植筋发生的工资在乙方工资中扣除)。如属模板工未及时钻孔的要马上通知现场施工员,否则也属钢筋班责任。 5、包电焊、压力焊及螺纹套筒连接费用。 6、乙方焊接的钢筋,要按验收规范要求的数量,制作试验件,并保证接头全部合格。如发现送检不合格,甲方每次对乙方处以500元罚款。(二)分包方式 1、按结构施工图、建筑施工图、图纸会审、变更通知、现行国家施工规范及操

作规程等的质量要求进行制作、安装、清理等技术施工。包施工用的劳动保护用品及钢筋制作机械(包括钢筋绑扎的扎线)。包工作面围墙内的所有材料周转和人力运输,包楼层所属钢筋工施工遗留杂物(如垫块等)淸理工作,包箍筋制作工具、劳保用品、自我安全及文明施工。 2、包质量、包工期、包安全及文明施工、包施工措施费、包工本合同其它有关工作内容。 3、各部位钢筋绑扎时,为保证施工进度,乙方必须保持足够的施工人员,如乙方人员不足,由甲方调动增加,则工资由乙方支付。 4、绑扎:施工现场内成型材料的转运,成型钢筋场内的垂直水平运输,模内零星杂物的清理,按设计图纸,施工规范及技术交底进行绑扎(含上人屋面冷拉丝的绑扎),安放垫块,搭拆必要的绑扎架。绑扎结束后剩余钢筋分规格、分型号、回收到加工棚内指定地点,绑扎丝的清理回收。零星构件的绑扎。浇砼时的钢筋保护等工作。砼标号不同时(梁、柱、墙交接处安装钢丝网片);废钢筋的清理。 5、钢筋制作:施工现场内原材料及成型材料的转运,分规格、型号堆码整齐、挂牌、标号、捆扎、钢筋加工机械的安装、调试、保养,含钢筋配料(翻样)在内。 6、钢筋调直、切断、对焊(80CM以上的钢筋全部对焊并利用)、加工成型

砌体分包合同

砌体施工班组劳务分包合同 发包方(甲方) : 承包方(乙方) : 根据《中华人民共和国合同法》、《中华人民共和国建筑法》及其他有关法律、法规,遵循公平公正、平等自愿、诚实信用的原则,双方就建设工程劳务作业合作事项协商一致,签订本劳务作业分包合同,双方共同遵照执行。 一、工程概况: 1、工程名称: 2、工程地点: 3、工程工期:年月日至年月日 二、承包范围及方式: 1、承包范围: 2、承包方式:包人工、包小型机具(手提式工具)、包质量、包工期、包安全生产和包文明施工的方式。 3、工作内容:砌体工程:砌体为填充墙,因此在结构施工阶段必须做好拉结筋、构造柱插筋(或拉结筋、构造柱预埋)的预埋工作(如现场施工条件及通常工地施工做法应该可以预留而不预留的植筋发生的一切费用由乙方承担)。砌体所需材料计划,拌制砂浆、砌块润水、砌筑脚手架及脚手架板搭拆,填充墙砌筑、拉结筋制作、砖墙勾缝,现场材料运输,进场材料的摆放清理。 三、合同价款 1、合同单价为:按实砌体积元/M3。此单价为综合含税包干价格,且本单价不受材料价格及国家政策影响,综合单价不再做任何调整。 2、承包范围外的零星用工单价为元/工日,以项目部开出工日数为准并附有详细施

工部位的签证资料、派工单、项目经理、预算员、质检员、工长签字为准。 四、工程结算与支付 1、工程量计算规则依据施工图纸、设计变更和现场签证,按实砌体积以立方米计算。 2、工程量验收依据施工图、设计变更和本合同规定的质量标准验收工程量。 3、乙方承担的施工项目按合同单价计算,按实际完成的工程量,由总包方项目具体主管人员对质量、进度、完成情况进行验评,有关人员逐一签字后,根据甲方劳务结算程序按合同单价进行结算。 4、甲方每月按乙方实际上班人数付生活费元/人,饭票由财务会计领取。 5、乙方应在结构验收合格后20天内提交预算书,由现场施工管理人员初步审核,交经营层审核,双方办理结算手续。同时扣除乙方所付生活费、甲方代缴的各种费用、保留5%工程质量保修金,结算工程款的70%,余款年底(农历)一次付清。 (总价款=实际完成工程量×综合单价+零星用工单价×签证工日数量) 6、工程款支付条件 1)所有施工人员每天上午下班前和下午上班前分两次签到考勤。考勤表由甲方保存并报总包方一份。 2)每名工人须与甲方签订劳动用工协议,由总包方监督执行。 3)每次工程付款由分包方依据考勤表和劳务用工协议编制工人工资表,工资表上由总承包方、甲方项目经理签字、分包方班组长签字、工人本人签字并按上指印方可对照身份证予以领取工资。以上三条作为支付工程款的依据,缺一不可。只有当完成工人工资发放,且无任何争议下,才能结算支付给分包人的工程款(扣除已发放的工人工资与甲方代乙方交纳的所有主管部应征收的或罚款等剩余部分支付给承包人)。 6、若因业主资金不能及时到位而影响甲方付款时,乙方应予以理解。 五、双方责任

植筋合同协议书范本 通用版

编号:_____________植筋合同 甲方:________________________________________________ 乙方:___________________________ 签订日期:_______年______月______日

甲方:_ 乙方:_ 经双方友好协商,甲方将工程的植筋工作分包给乙方施工。为明确甲乙双方在合作施工过程中的权利和义务,按照《中华人民共和国合同法》、《中华人民共和国建筑法》以及相关法律、法规,本着自愿、公平、诚实信用的合作原则,签订以下协议书: 一、工程名称:_ 二、承包工作内容: 构造柱钢筋、砌体拉结筋、窗台钢筋、过梁钢筋、其他植筋工作。 三、承包方式: 包工包料,(钢筋、电源由甲方提供)其余均由乙方负责。 四、工程质量: 1、所有植筋均应经拉拔试验合格,拉结长度、植筋深度均应符合设计要求及规范规定。 2、所有植筋部位须按照甲方指令和技术交底进行施工(打孔、清孔、涂胶、除锈、植筋),乙方不得擅自做主任意修改。 3、植筋部位的各个点必须保持在同一面、同一线上、不能偏出构件。 五、承包价格: 价格组成:钻孔用机械工具、植筋胶,植筋人工费等。

六、甲乙双方职责: 1、甲方职责: (1)提供乙方职工的住宿宿舍; (2)提供植筋施工用电电源,提供植筋施工用脚手架或人字梯; (3)对乙方进行植筋施工书面技术交底和施工进度交底; (4)各层结构墙体上全部弹好建筑标高控制线和楼面平面定位线; (5)将所植筋用钢筋及时提供; (6)及时组织对植筋的拉拔试验。 2、乙方职责: (1)根据甲方要求及时组织施工人员进场,确保工期,未按甲方的进度完成任务,承担一切费用。(2)乙方进入施工现场服从甲方管理人员的管理,并执行甲方的各项规章制度。有事必须提前通知甲方,不能随意停工,如有上述行为,每发生一次将处罚款元整。 (3)按照甲方书面的技术交底和结构墙体上建筑标高控制线及楼面平面定位线进行植筋工作,未按图纸或未按技术交底施工,发生一切费用你班组承担。 (4)按照甲方进度要求完成植筋工作。 (5)按照协议质量要求完成植筋工作。 (6)所有植筋拉拔试验必须合格。如拉拔试验不合格,承担其一切经济损失。 (7)材料计划:乙方必须提前天上报所植钢筋材料计划。 (8)做好工完场清工作,剩余拉结筋及时清理利用,否则发生费用你班组承担; 七、工程款结算: 1、工程量签认:按照甲方技术人员现场验收签认的工程量确认单为准; 2、工程量结算:已签认单中各植筋直径数量分别计算合价; 3、工程款支付:按照完成量的总价的 %已现金支付,全部工程完成办理结算后一个月内全部以现金结清。 八、协议份数:

土建工程劳务分包合同

土建工程劳务分包合同 甲方:合同编号: 乙方: 依照《中华人民共和国合同法》、《中华人民共和国建筑法》及其他有关法律、行政法规,遵循平等、自愿、公平和诚实信用的原则,甲方将广场项目的基础工程、主体结构工程及初装修工程的劳务、周转材料及小型施工机械分包给乙方施工,为了明确双方职责、权利、义务,确保施工安全、工程质量,加快施工进度,达到协议规定的预期目标,在平等互利的基础上,经甲、乙双方协商一致,订立本合同。 第一条工程概况 一、工程名称: 二、工程地点: 三、结构类型:框架结构 四、工程承包内容: 1、土建工程 本工程从基础到结构封顶及屋面土建全过程:细部放线,钢筋工程(不包含直螺纹板丝及保护、套筒、电渣压力焊),模板工程,混凝土工程,预埋铁件工程(不含幕墙),墙体砌筑工程,粉刷工程(内墙、内隔断、外墙等粉刷)楼地面工程,屋面工程(不包括卷材防水工程、包括屋面保温、找坡、砂浆找平),吊塔、施工电梯、井架、楼梯间、电梯间、卫生间及设备间的基础施工和塔吊基础拆除清理。相关材料的场内二次搬运,不包括汽车坡道施工。各项工程主要内容如下: 1)基础工程:从基础清土到±0.000的全部工程量。 包括但不限于基础细部放线,人工配合钎土、坑内余土人工清理、人工修坡、覆盖塑料布、积水抽除、清理杂物;外墙防水保护层施工;砖砌基础胎模、胎模粉刷(含阴、阳小圆角),按图纸的混凝土的浇筑及其养护;斜支撑下少量余土开挖;传力带施工(含回填黄沙、浇砼);地面找平,室内电缆沟,下水道至室外井口、施工洞口的开砌、封堵、施工缝、伸缩缝、后浇带的施工(包括橡胶止水带连接)、楼层清洁以及整个施工场地内的道路清扫,卫生等全过程,包括各设备用房,大型设备基础的按图施工等。 2)模板工程:按照模板专项方案包工包料规范施工,包括但不限于模板材料的计量(配料),配料装卸、标高及尺寸控制,模板支撑系统的搭拆、模板安装与拆除及清理等。 3)钢筋工程:包括但不限于钢筋的制作、安装、绑扎(直螺纹项目、电渣压力焊、植筋不含在内),含盘元的调直、钢筋配料翻样,现场的轴线定位,钢材的型号、规格申报、预埋件安装(幕墙埋件除外)。材料进场卸货、并按规格、型号,按成品和原材料分类堆放,做好标识、放样制作,合理利用,且大于50厘米的短钢筋不得浪费等。 4)混凝土工程:包括但不限于混凝土浇筑前的相关准备工作(混凝土泵车就位、泵管的安装、拆卸、清洗等),结构工程柱,梁,板砼的施工,混凝土浇筑、养护,

植筋工程施工合同协议书

植筋工程施工合同协议 书 文件编号TT-00-PPS-GGB-USP-UYY-0089

植筋工程施工合同 甲方:惠州市东江物业开发有限公司 乙方:深圳市固特建筑加固科技有限公司 由惠州市东江物业开发有限公司投资新建的“东江明珠花园”1#2#楼工程,为满足裙楼的使用功能,在裙楼南向增加外挑工程。根据《中华人民共和国合同法》和《建筑安装工程承包条例》,甲乙双方本着平等互利、公平公正的原则,经双方协商,甲方同意将本工程的植筋分项工程委托给乙方包工包料(其中不含钢筋、脚手架、施工用水、试验费用),为保证工程质量,明确双方责任,特订本合同,双方共同遵照执行。 一、工程概况 1、工程名称:惠州市东江明珠花园1#2#楼。 2、工程地点:麦地东路1号。 3、承包内容:1#2#楼裙楼北面增加工程植筋植筋。 4、工期:二十天(从甲方通知进场之日起计算工期)。 二、承包形式及合同价款 1、本合同为包干价(不含钢筋、脚手架、施工用水、抗拨试验费,如发生则由甲方按实承担)。 2、工程量以实际完成的植筋数量来结算工程价款。 3、结构胶名称:±0.000以下采用国产胶(上海诚果),其它采用喜利得(RE—500)。 4、本工程承包范围外的甲方设计变更或其它增加工程,本合同涉及到的可参照本合同单价执行,无参照的可按有关定额或甲方确认单价执行。 5、植筋价格见《1#2#楼北面植筋数量及价格统计表》。 三、工程款支付方式

本工程工期短,不作预付款,由乙方垫资支付材料费,工程完工经有关单位验收合格后十五天内一次性付清。 四、甲方的责任 1、负责提供外脚手架。 2、提供施工临时水电驳接位置,电费由乙承担。 3、负责组织图纸会审及技术交底,指派专业工程师现场协调工作。 4、向施工单位提供施工图纸壹份。 5、负责组织隐蔽工程验收,对乙方的工程质量、进度及安全进行监督。 6、协调安排施工现场各分包单位的工序搭接,负责移交土建施工单位,协调解决土建施工单位按植筋要求进行钢筋制作。 五、乙方责任 1、按甲方通知的时间进场施工,提供合法的施工许可证及相关资料。 2、按甲方要求编制施工组织设计及技术方案,报监理及甲方审批,严格按设计图纸及相关规范施工,配合好其它兄弟单位的施工,做好工地的成品保护工作,对施工人员自身的安全及行为负责。 3、乙方采购的植筋胶(喜利得RE-500),必须一次性进场,经监理及甲方现场代表验收合格后方可投入本工程使用。 4、在施工过程中的工序流程:钻孔深度→清孔→注胶的饱满程度→植筋深度等工序必须经监理及甲方现场工程师验收确认后,方可进行下道工序施工。 5、工程完工后,乙方的施工成果必须经监理、甲方现场工程师及相关部门验收,并取得书面认可。 6、在施工现场内乙方施工人员应服从监理及甲方工程师指挥,工程所需加工场地、施工设施、工程材料的周转仓库和现

土木工程施工分包合同条件(FITIC)

FIDIC 土木工程施工分包合同条件 FIDIC 国际咨询工程师联合会 土木工程施工分包合同条件 (第1版1994年) 第一部分通用条件 第二部分特殊应用条件编制指南 附报价书及协议书格式 (与1992年再次修订重印的《土木工程施工合同条 件》1987年第4版配套使用) 刘英刘尔烈李长燕译 何伯森周可荣张水波校 中国建筑工业出版社 FIDIC授权书 FIDIC authorizes Prof.Bosen He, Chairman, Management Engineering Department, Tianjin University.Tianjin City, P.R.China,to translate into Chinese and to publish the following FIDIC documents: Conditions of Subcontract for Works of Civil Engineering Construction 1994 (for use in conjunction with the Conditions of Contract for Works of Civil Engineering Construction,4th edition 1992 reprint) The responsibility for the quality of the Chinese translation remains with the Translators and Revisors The English version of the Conditions of Contract is the official version and copies of that copyrighted version can be obtained from FIDIC.FIDIC accepts no responsibility for the Chinese translation.

植筋承包合同书模板

万和花园工程 植筋工程劳务分包施工合同 工程名称:万和花园工程植筋工作 发包方(简称甲方): 云南工程建设总承包公司直管工程管理部承包方(简称乙方):杨刚 合同签定日期: 2012年 6月 29日 合同签定地点:云南工程建设总承包公司直管工程管理部办公室

劳务分包施工合同条款 发包方(简称甲方): 云南工程建设总承包公司直管工程项目管理部 承包方(简称乙方): 杨刚(身份证号码:422431************) 按照《中华人民共和国合同法》、《中华人民共和国建筑法》和编号为云投万和花园项目(合)字第2011-018号本工程《建设工程施工合同》以下简称为“总合同”)的条款及本工程施工现场具体情况,甲方将本工程植筋专业工程分包给乙方施工,经双方协商一致,达成以下合同条款: 一、工程概况 建设单位名称:云南省城市建设投资有限公司万和花园工程建设指挥部 工程名称:万和花园项目施工。 建设地点:昆明市前卫镇太河社区,东南接太和社区城中村,西临清水河、北接前卫西路。 建筑面积:121109.9 m2, 结构类型:框-剪结构。 层数:-1~3/8层 二、质量要求:合格,经检测达不到合格按合同价款的5%支付违约金。 三、工期要求:该合同内容按甲方要求进度按时完成。由于乙方原因造成的工期延误,按200元/天支付违约金,累计计算。 四、承包范围及工作内容:万和花园施工图、补充施工图、设计变更范围内中所有的墙体拉筋、构造柱、过梁、门边柱等需要植筋的工作。 五、承包方式:包工、包料(钢筋除外)、包工具、包质量、包工期、包安全、包文明施工。 六、合同价款:按实结算。

1、包干单价: 2、以上单价均包括完成该项目的电钻、电线、吹风、建力得胶水、人工费、生产工人劳动保护费、保险费、工伤人员工资、病假人员工资、管理费及税金、乙方的管理费及税金、利润、风险费、措施费、政策性人工调差等所有费用。包括工期要求、质量要求、地理位置、现场情况、现场材料运输、材料堆放地点、工人食宿、现场机械配备变化、不同施工季节、安全文明施工要求等所涉及的一切费用。 七、工程付款 1、工程付款:第一次支付工程款同时满足有地下室的部分施工至地下室顶板混凝土浇筑完成,无地下室的部分施工至首层地面混凝土浇筑完成后支付已完工程量价款的80%,以后按完成进度付款70%,余款于交工验收合格后(工程总体验收)在半年内付清 2、乙方按规定缴纳结算总价1%的个人所得税,由甲方在每次付款时按付款额扣除(如遇国家及地方税收政策调整按调整后的税率扣除),乙方的管理费和税金由

植筋分包合同

砌体植筋工程分包合同 承包单位(甲方): 劳务单位(乙方): 依照《中华人民共和国合同法》《中华人民共和国建筑法》《建筑工程施工合同》及有关规定,为明确双方的权利义务,本着自愿互利、权益平等的原则,经协商一致签订本合同。 第一条、工程概况:车库为框架结构、主楼为剪力墙结构。______________ 1.1.工程名称:盛世新城小区13#~14#娄 1.2.工程地点:乌兰察布市集宁区盛世新城小区110国道362公里处北侧 1.3.工期: 1.3.1 开工日期:2013 年05月L日 1.3.2竣工日期:配合工程进度进行 1.3.3承包方已按主体总包方要求认真考察了工地并充分了解了工地现场条件,充分认识到各种不利因素所占用时间,如现场施工场地狭小、各专业交叉作业、图纸调整、现场测试等等。承包方理解工地上会有其他施工单位作业,不会独占工作面和工作空间以及施工现场; 理解应当对其他施工单位的施工给予充分配合;理解交叉施工对工期的影响;理解政府管理部门对施工作业方式和时间可能的影响或限制等上述因素等对工期的不利影响。承包方保证在约定工期内将符合质量标准的工程交付发包方。 1.4.发包形式:甲方将本工程的砌体工程植筋分项工程分包给乙方,包括工人、胶结材料、机具等费用均由乙方自理。 1.5工程内容:所有地上主体及地下室墙体砌筑植筋。 1.6.工程量计算:按照砌体植筋方案要求以实际根数计算数量。

第二条:合同单价、工程总价及付款方式:

本工程单价为一次闭口价,本单价中已充分考虑了市场价格波动因素,合同一经签订价格价格不予调整。承包方不得以任何理由拖延工期和要求增加工程款。 2.2.工程总价:工程总造价约为元人民币(¥元)工程结算时以合同单价乘以经双方认证的工程量为准。 2.3.付款方式:本工程无预付,发包方按植筋工程进度全部完毕后,向承包方拨付工程进度款。拨款额度为已完成工程量70%二结构砌体工程全部完工一个月内拨付至合同总价款的95%余额在工程竣工后一次付清。 2.4.承包方不需要提供合同有效发票。 第三条、质量标准及检查依据: 3.1.工程质量标准:满足设计规范要求。达到甲方监理及项目管理员验收 3.2.质量检查依据:根据现行建筑工程相关分项工程验收规范,现行建筑工程质量 检验评定标准,以及其他地方性相关规定。 3.3.检查项目: 3.3.1植筋胶的品牌、质量、现场检查报告; 3.3.2植筋钻孔深度、内径、间距; 3.3.3植筋孔洞吹扫、植胶饱满度; 3.3.4钢筋的品种、数量、规格、间距 第四条、双方权利、责任和义务 4.1.发包方权利、责任及义务: 4.1.1向承包方提出工程进度、安全文明施工及必要的工序穿插要求。 4.1.2审批承包方提供的《砌体植筋施工专项施工方案》。 4.1.3指定承包方为完成合同内容所选用材料的品牌、生产厂家、规格。

植筋施工承包合同协议书范本 通用版

甲方:_ 乙方:_ 依据<<中华人民共和国合同法>>、<<中华人民共和国建筑法>>及当地人民政府的有关法律、法规、遵循平等、互利、公平的原则,双方就本建筑工程分项承包事项,订立本合同。 一、承包范围:。 二、承包内容:框架柱墙砌砖植筋。 三、承包方式:包清工(乙方带植筋胶)。按实际发生接头数量,以元/根进行结算。 四、付款方式:按每月完成产值的%给付人工费(付款时间以甲方进度款到位为准、付款时带工人发放工资表)。 五、工期:按土建进行(配合土建)。 六、质量要求:达到国家有关验收规范合格标准。乙方按规定做拉拔实验,第一次试验费用由甲方负责,如不合格试验费用由乙方承担。 七、乙方负责材料、设备进场和材料质量。甲方负责工人宿舍及现场电源安排。乙方必须按图纸和规范施工,如发生返工,甲方以材料的倍罚款。 八、安全方面:

1、承包负责人为安全第一责任人,应对本承包范围内的安全工作负总责,因此必须对职工加强法制教育,安全教育,树立安全是首位的思想意识,做到“安全为了生产,生产必须安全”,所有作业人员必须严格执行安全操作规程和治安条例及甲方所制订的安全生产管理制度。 2、甲方负责提供安全生产防护设施的所需材料,乙方应对本施工范围内的机械设备、安全设施、工用具经常检查,发现隐患及时整改或向项目部安全员汇报。 3、在施工过程中发现有违章操作和野蛮施工,按甲方规定进行处罚,乙方人员如有无理取闹、打架斗殴,按情节轻重由甲方进行处罚(每人次罚款元)或送司法部门处理,施工中如因乙方或个人违章指挥、违章操作造成自身或他人安全事故的一切责任和费用均由乙方负担。 九、如乙方在施工中没有达到建设单位的质量和节点要求,建设单位要求乙方撤出现场,乙方必须无条件撤出,所完成的工程量按 %结算,余款作为甲方停工损失费用。 十、本合同签订后,乙方不允许转包,如果发生,甲方不负责乙方的任何费用。由此发生的一切经济责任及法律责任,甲方不承担。 甲、乙双方都必须严格履行本合同。任何一方违约,向对方赔偿5%的违约金(合同价款)。 本合同未尽事宜,由双方协商解决,签订补充协议。本合同双方签字后生效,受法律保护。 本合同一式份,甲、乙双方各执份。 甲方: 乙方: 年月日

fidic施工分包合同条件

fidic施工分包合同条件 篇一:FIDIC条款《土木工程施工分包合同条件》摘要 FIDIC编制的《土木工程施工分包合同条件》是与《土木工程施工合同条件》配套使用的分包合同文本。分包合同条件可用于承包商与其选定的分包商,或与业主选择的指定分包商签订的合同。分包合同条件的特点是,既要保持与总包合同条件中分包工程部分规定的权利义务约定一致,又要区分负责实施分包工作当事人改变后两个合同之间的差异。 一、分包工程的合同责任 分包工程属于总包合同内承包商对业主承担义务承包范围内的工作,双方在合同中约定相互之间的权利义务,但它又是承包商与分包商签订合同的标的物,分包商仅对承包商承担合同责任。由于分包工程同时存在于总包、分包两个合同内的特点,承包商又居于两个合同当事人的特殊地位,因此承包商会将总包合同中对分包工程承担的风险合理地转移给分包商。 1.分包工程的合同价格 承包商采用邀请招标或议标方式选择分包商时,通常要求对方就分包工程进行报价,然后与其协商而形成合同。分包合同的价格应为承包商发出“中标通知书”中指明的价格。 2.分包合同的订立 在邀请分包商报价及签定合同时,为了能让分包商合理

预计分包工程施工中可能承担的风险,以及分包工程的施工满足总包合同要求顺利进行,应使分包商充分了解在分包合同中应承担的义务。承包商除了提供分包工程的合同条件、图纸、技术规范和工程量清单外,还应提供总包合同的投标书附录、专用条件的副本及通用条件中任何不同于标准化范本条款规定的细节。承包商应允许分包商查阅总包合同,或应分包商要求提供一份总包合伺副本。但以上允许查阅和提供的文件,不包括总包合同中承包商的工程量报价单及报价细节。因为在总包合同中分包工程的价格是承包商合理预计风险后,在自己的施工组织方案基础上对业主进行的报价,而分包商则应根据对分包合同的理解向承包商报价。此外,承包商在分包合同履行过程中负有对分包商的施工进行监督、管理、协调的责任,应收取相应的分包管理费,并非将总包合同中该部分工程的价格都转付给分包商,因此分包合同的价格不一定等于总包合同中所约定的该部分工程价格。 3.划分分包合同责任的基本原则 (1)保护承包商的合法权益不受损害。分包合同条件中包括了以下条款: 1)分包商应承担并履行与分包工程有关的总包合同规定承包商的所有义务和责任,保障承包商免于承担由于分包商的违约行为,业主根据总包合同要求承包商负责的损害赔偿或

钢筋植筋施工合同协议书范本 正式版

发包方(全称):(以下简称甲方) 承包方(全称):(以下简称乙方) 根据《中华人民共和国经济合同法》、《建筑安装工程承包合同》,结合本工程具体情况,双方达成如下合同约定: 一、分包工程概况 分包工程名称: 分包工程地点: 分包工程承包范围: 二、工期 1、开工日期:本分包工程定于年月日开工;竣工日期:本分包工程定于 年月日竣工;合同工期总日历天数为:天。若因乙方人员、材料、设备不能满足甲方工期要求造成工期延误,则对乙方处以每天元的罚款。 2、乙方若中途退场或提前离开,按完成合格工作量的结算。施工过程中必须严格服从项目部指令,与其他工种积极配合,以便于其他相关工程顺利施工。 三、工程质量标准:符合适应相关的验收规范及行业标准 1、乙方承包范围内的工程质量按相关的验收规范及行业标准进行验收。 2、乙方承包范围内的施工质量按验收要求进行现场拉拔试验检测,检测费用由甲方支付;如拉拔检测试验不合格,所发生的一切费用由乙方支付且承担其他相关责任。 3、对于施工质量不符合图纸要求植筋偏位的,乙方无条件拆除,且偏位的植筋数量不得进行结算,另处以每根元的累计罚款。 四、甲方的工作与责任 1、指派现场代表:

2、为乙方正常展开工作提供必要的施工条件:包括现场工作面、水、电的供应,临时设施。负责钢筋下料,提供电源箱至乙方施工楼层,乙方负责电源箱以外设备电源电缆及加班用的照明灯具。 3、及时审查批准乙方提交的施工组织设计、施工进度计划(或施工方案)。 4、对乙方施工完成的内容及时组织验收并确认(签字)。 5、负责现场设备进出施工现场的及时吊运。 五、乙方的工作与责任 1、指派现场代表: 2、开工前提供承包范围内的施工组织设计和施工进度计划(或施工方案)、资质证书、施工许可证、安全许可证等相关资料。 3、保质保量完成承包范围内的施工任务和按规定做好相应的工程资料,及时提供国家规定的检验报告原件,必须保证工程进度所需的设备、相关材料、施工人员的数量、身份证复印件及体格检查表,提供现场施工人员上岗证(原件交甲方核验,复印件加盖公章交甲方存档)及相关材料的质量标准保证书。 4、施工期间遵守甲方的有关规章制度。 5、做好自身人员的安全工作,建立健全安全管理制度。 6、按有关规范要求施工,并达到合同规定的质量等级。 7、各层施工任务完成后及时提请甲方进行验收以及确认工程量。 8、乙方不得再将该分项工程另行转包;如因乙方原因造成的施工质量问题(含拉拔试验)及其引起的损失均由乙方承担。 9、乙方所提供的相关资料须经业主、监理及甲方审查确认后,方可施工。 六、合同价款及支付方式 1、各规格接头单价如下:

植筋工程分包合同

- 精品文档- 植筋工程分包合同 甲方:成都东升兴旺建设有限公司乙方:四川中耀建设特种工程有限公司依照《中华人民共和国合同法》、《中华人民共和国建筑法》及相关法律、法规、行业规章,遵循自愿、公平和诚实信用的原则,经双方协商达成一致意见,签订本工程钢筋植筋分项工程分包合同,双方共同遵守。 一、工程名称:和裕?欧景三期 二、工程地址:金堂县三星镇 三、承包栋号3# 楼、4# 楼 四、承包工作内容: 乙方负责植筋的全过程所包含的工作内容,即:人工、机具、钻孔、植筋所使用的材料,不包括钢筋制作。 五、工程质量 1、钢筋植入深度满足相关规范、规程、标准规定要求,抗拉拔力必须满足标准要求。拉拔测试费用用乙方自负,检测单位由甲方指定。 2、构造墒拉筋0 6.5 0 10以上钻孔深度为10d深度。如甲方 巡食,抽点发现不合格者一次性罚款1000元。 3、结构植筋、钻孔深度严格按照最新施工规范要求进行施工,胶质材料严格按照结构胶进行填缝施工。 4、施工过程中,应严格按照施工图纸和甲方所确定的部位、孔位、 - 精品文档- 规格正确安装植筋。若甲方钢筋不能满足乙方工作需要,而影响工程进度,造

成工期延误由甲方自行负责。 5、施工过程中,自觉接受建设、监理、甲方的质量检查,对植筋安装按甲方的施工进度施工,确保工程进度。若因乙方进度缓慢影响甲方总体进度计划,由此造成的工期延误:延误一天将罚款500?1000 元/天,以此类推。因人为而影响下道工序施工者,甲方有权请乙方退场,工程款不予结算。 六、安全生产、文明施工 1 、乙方工作人员进入施工现场必须按甲方技术交底要求上,正确佩戴安全帽,高空作业人员必须栓安全带。施工中未进行安全防护,每人次按100 元对班组进行罚款处理,乙方施工中由于自身原因造成安全事故由乙方负责。 2、施工临时用电,必须由专业电工搭设、接电,严禁私自乱拉、乱接电源。必须搞好班组的配合协调工作,搞好团结,相互谅解,发扬互助友爱精神,严禁打架斗殴、偷窃、赌博,严禁野蛮施工,违者返款1000?5000 元,工人住宿由乙方自行解决。 3、乙方不得使用无手续人员,不得使用18 周岁以下和55 周岁以上的人员作业,做好职工的安全教育和新工人入场的安全生产教育。不得带小孩和家属以及无关人员进入施工现场。所有进场人员必须购买人身意外保险,否则不能进入施工现场作业,如甲方发现,一次性罚款乙方1000元/ 人,在工程款中扣 除。如操施人员未购买保险者,造成的一切安全赔偿,由乙方公司承担。 -精品文档- 七、植筋单价

砌体分包合同范本(完整版)

合同编号:YT-FS-1392-33 砌体分包合同范本(完整 版) Clarify Each Clause Under The Cooperation Framework, And Formulate It According To The Agreement Reached By The Parties Through Consensus, Which Is Legally Binding On The Parties. 互惠互利共同繁荣 Mutual Benefit And Common Prosperity

砌体分包合同范本(完整版) 备注:该合同书文本主要阐明合作框架下每个条款,并根据当事人一致协商达成协议,同时也明确各方的权利和义务,对当事人具有法律约束力而制定。文档可根据实际情况进行修改和使用。 发包方(甲方): 承包方(乙方): 根据《中华人民共和国合同法》、《中华人民共和国建筑法》及其他有关法律、法规,遵循公平公正、平等自愿、诚实信用的原则,双方就建设工程劳务作业合作事项协商一致,签订本劳务作业分包合同,双方共同遵照执行。 一、工程概况: 1、工程名称: 2、工程地点: 3、工程工期:年月日至年月日 二、承包范围及方式: 1、承包范围: 2、承包方式:包人工、包小型机具(手提式工具)、

包质量、包工期、包安全生产和包文明施工的方式。 3、工作内容:砌体工程:砌体为填充墙,因此在结构施工阶段必须做好拉结筋、构造柱插筋(或拉结筋、构造柱预埋)的预埋工作(如现场施工条件及通常工地施工做法应该可以预留而不预留的植筋发生的一切费用由乙方承担)。砌体所需材料计划,拌制砂浆、砌块润水、砌筑脚手架及脚手架板搭拆,填充墙砌筑、拉结筋制作、砖墙勾缝,现场材料运输,进场材料的码放清理,圈梁、构造柱、窗台压顶、过梁的钢筋、模板、砼工程。 三、合同价款 1、合同单价为:按实砌体积元/M3。此单价为综合含税包干价格,且本单价不受材料价格及国家政策影响,综合单价不再做任何调整。 2、承包范围外的零星用工单价为元/工日,以项目部开出工日数为准并附有详细施工部位的签证资料、派工单、项目经理、预算员、质检员、工长签字为准。 四、工程结算与支付

FIDIC条款《土木工程施工分包合同条件》摘要

FIDIC编制的《土木工程施工分包合同条件》是与《土木工程施工合同条件》配套使用的分包合同文本。分包合同条件可用于承包商与其选定的分包商,或与业主选择的指定分包商签订的合同。分包合同条件的特点是,既要保持与总包合同条件中分包工程部分规定的权利义务约定一致,又要区分负责实施分包工作当事人改变后两个合同之间的差异。 一、分包工程的合同责任 分包工程属于总包合同内承包商对业主承担义务承包范围内的工作,双方在合同中约定相互之间的权利义务,但它又是承包商与分包商签订合同的标的物,分包商仅对承包商承担合同责任。由于分包工程同时存在于总包、分包两个合同内的特点,承包商又居于两个合同当事人的特殊地位,因此承包商会将总包合同中对分包工程承担的风险合理地转移给分包商。 1.分包工程的合同价格 承包商采用邀请招标或议标方式选择分包商时,通常要求对方就分包工程进行报价,然后与其协商而形成合同。分包合同的价格应为承包商发出“中标通知书”中指明的价格。 2.分包合同的订立 在邀请分包商报价及签定合同时,为了能让分包商合理预计分包工程施工中可能承担的风险,以及分包工程的施工满足总包合同要求顺利进行,应使分包商充分了解在分包合同中应承担的义务。承包商除了提供分包工程的合同条件、图纸、技术规范和工程量清单外,还应提供总包合同的投标书附录、专用条件的副本及通用条件中任何不同于标准化范本条款规定的细节。承包商应允许分包商查阅总包合同,或应分包商要求提供一份总包合伺副本。但以上允许查阅和提供的文件,不包括总包合同中承包商的工程量报价单及报价细节。因为在总包合同中分包工程的价格是承包商合理预计风险后,在自己的施工组织方案基础上对业主进行的报价,而分包商则应根据对分包合同的理解向承包商报价。此外,承包商在分包合同履行过程中负有对分包商的施工进行监督、管理、协调的责任,应收取相应的分包管理费,并非将总包合同中该部分工程的价格都转付给分包商,因此分包合同的价格不一定等于总包合同中所约定的该部分工程价格。 3.划分分包合同责任的基本原则 (1)保护承包商的合法权益不受损害。分包合同条件中包括了以下条款: 1)分包商应承担并履行与分包工程有关的总包合同规定承包商的所有义务和责任,保障承包商免于承担由于分包商的违约行为,业主根据总包合同要求承包商负责的损害赔偿或