石料场开采工程施工设计方案

石料场开采工程施工设计方案
石料场开采工程施工设计方案

石料场开采施工方案

目录

1、工程概况................................................................................................1...

2、工程特点、难点及措施.........................................................................1..

3、施工布置................................................................................................1...

4、开采分层规划........................................................................................2...

4.1 开采范围确定..................................................................................2..

4.2 开采分层.........................................................................................2...

4.3 开采施工程序..................................................................................2..

4.4 料场开采方式..................................................................................3..

5 、施工准备及场地清理...........................................................................4..

6、开采施工................................................................................................4...

7、开采质量控制........................................................................................8...

8、爆破安全控制........................................................................................9...

8.1 炸药用量控制..................................................................................9..

8.2 飞石控制.......................................................................................1..0

8.3 安全防护.......................................................................................1..0

石料场开采施工方案

1、工程概况

国道318 线林芝至拉萨公路改造工程拉萨段第一合同起于墨竹工卡县城以

东(k4554+800)经过墨竹工卡县城、甲玛乡、达孜县章多乡、终于达孜县塔杰

乡(k4590+000),路线全长35.2 公里。我部因施工料源不足,需在k4581+000 (章多乡章多村)增设石料场一处,该料场储存量约30 万方,面积约 1.5 万平米,原设计中无,已开采约 1.5 万方。根据有关部门要求,该石料场开采有用料

只能为13 万方。

k4581+000石料场位于章多乡章多村,往拉萨方向318 国道左侧约2500m,料场北面有少量残留砂岩盖顶,东南面有大片基岩裸露,山坡基本无生长植被。

上石料场施工临时道路从料场东面经过,开采运输条件好。岩性分析:颗粒密度

ρP=2.64g/cm3,饱和块体密度ρS=2.60g/cm3,天然块体密度ρ0=2.60g/cm3,烘干块体密度ρd=2.58g/cm3,自然吸水率Wa=0.44%,孔隙率n=2.31%,饱和单轴抗压强度RS=155MP,a烘干单轴抗压强度Rd=176MP,a 软化系数0.87 ,SO3含量QS=0.016%。

2、工程特点、难点及措施

该料场在318 国道旁边,露天进行开采,开采时存在以下几个难点:

(1)料场位于318 国道旁边,为避免山体大面积破坏,保护当地环境,开

采施工较困难。前期开采临时道路均已修通,拟定从采石场背面即从318 国道进

入采石场,绕道山体背面,从背面进行采石,避免了从318 国道正面开采施工,

影响当地环境。

(2)爆破作业较困难:因西藏地区炸药管理严格,使用困难;且山体爆破

区域距山脚碎石加工厂、山下居民区较近,存在安全隐患。为保证碎石加工厂、

营地及邻近建筑物的安全,采用多打孔、孔外分段、孔内微差、孔口保护等措施

进行爆破。

3、施工布置

石料场内梯段爆破采用900mm潜孔钻机、270mm潜孔钻机钻孔,采用13m3/7

空压机二台供风。孤石解炮拟采用YT-26 手风钻钻孔破解。

4、开采分层规划

4.1 开采范围确定

根据现场所定,石场开采范围主要为该山体背面,避免破坏正对318 国道一侧山体,影响当地环境。具体布置见附图。

4.2 开采分层

石料场开采边坡分层放坡,最高一层开采层基本为覆盖层,坡比为1:0.5 ,下面采层边坡坡比为1:0.3 ,分层开采设计高度为10~15m。先修通通上山顶的道路,从山顶打开开采面,从上往下分层爆破开采。

4.3 开采施工程序

石料场开采按“分区、分块,自上而下”的原则开采,每个台阶规划前、后

2 个作业面,每个工作面按50.0m×10.0~14.0m(长×宽)。采场分区同步下降。台阶高度按10m-15m控制(局部岩层较薄部位视岩层厚度适当调整)。工作面爆破梯段台阶与场内临时道路相结合。

石料钻爆开采施工程序为:施工准备→修筑施工便道→基础设施安装→覆盖

层剥离(挖运、弃渣)→工作面清理→台阶钻爆→石料挖运。

因道路高差过大,为保障石料能顺利外运,拟采用石料爆破与道路修筑结合

进行,及按预订的马道高程控制爆破后,石料先不外运,用于道路填筑,从西向

东推进,待道路填筑至各级马道高程后,料场自上而下进行梯段爆破,随台阶高程降低,相应石料运输及道路挖除、外运随之同步进行。道路随石场边采边降,

直至降到设计开采高程。

4.4 料场开采方式

为了保证开采石料粒经的均匀性,和爆破施工的安全、当地环境的保护考虑,同时满足长时间高强度开采,主爆孔以较大孔径的高风压潜孔钻机为主,靠近边坡部位的爆破孔辅以中大孔径造孔,采取大孔距,小排距的钻孔方式,采用人工装药,微差爆破,既降低作业人员的劳动强度和生产成本,又可提高工作效率和机械化作业程度,且可大幅度地减少二次解炮率和加快开采施工进度。

石料场分层开采程序及方法见下图:

5 、施工准备及场地清理

石料场北面有少量残留砂岩盖顶,东南面有大片基岩裸露,仅顶部剥离层较厚。在料场相应采层开采施工前,需进行剥离施工。

(1)测量放样

安排具有丰富经验的测量人员,负责本标段的测量放样任务。现场放样采用

放样单进行放样交底,计算机校核测量网点,对现场测控网加密。

边坡钻爆前,均需进行边线检查,合格后方进行下一台阶施工。

(2)场地清理

开挖区边线放样后,采用人工对开挖范围内的无用料、杂草、弃料、有害物

等进行全面清理,至少清理至开采边线以外 3.0m 范围,并按指定的方法进行处理。

①施工准备:设备进场后,用人工配合反铲分段清理表层植被,再形成主

干道至各层开采的施工便道,准备工作完成后开始石料的开采。

②植被清理:目前杂草等植被清理在前期施工时已基本完成。

6、开采施工

(1)覆盖层剥离

首先将开采范围的轮廓线由测量定位,在上开口轮廓线以上清出3m 宽范围内的覆盖层形成平台,并将2m 以外山坡上的危石清除。由上而下采用人工配合

4.5m反铲和手风钻爆破,挖掘机进行表土和覆盖层剥离。

开挖施工过程中,在边坡地质条件较差部位设置变形观测点,定时观测边坡

变形情况,如出现异常,立即采取应急处理措施。

(2)石料开采

料场边坡设计坡比为1:0.3 ,每10~15m设一个台阶,中间设3m宽马道,根据工程特点,结合进度要求和资源配置等因素,采取按台阶高度分层开挖的施工方案,施工中主爆孔采用深孔微差爆破技术,边坡采取密集型钻预裂孔及缓冲孔。

由于料场山脚处东边距离50m左右为碎石加工区,为了保证附近建筑物的安全,

山顶从上至下采用5m 左右预留保护层的两级边坡防护,设计边坡线采用预裂爆

破技术,主爆孔采用同排同段炮孔外等间隔控制延时起爆技术,单孔单向,严格控制爆破振速,为了预防爆破飞石,同时对预裂爆孔采取孔外表面覆盖防护,确保周围建筑物的安全。

(3)钻孔施工

钻孔施工前,应定准开孔的位置。测量人员认真配合,及时准确的给出开口线的位置、坡度。钻机要调整好角度,做一个同坡度相同的木制三角架,控制钻

机的大架。钻孔施工人员在测量人员的配合下,按照设计所确定的预裂孔孔网参数沿设计预裂线精确的标出孔位,要求按设计钻出“平”“直”“齐”高质量的孔。

①预裂钻孔参数料场的前期属常规开采,根据现场的资源配置,以及岩石的坚硬,选择高性能钻机,钻孔孔径d=115mm,预裂孔距a=(8~12)D。

②炮孔布置

预裂孔按孔距为1m 沿边坡设计开口线钻孔,钻孔角度为73°,为了减少消除主爆孔对预裂面的损伤,采用缓冲爆破技术。缓冲孔布置与预裂孔平行,排距为2m。钻预裂孔时孔的方向同台阶坡面倾向要保持一致。孔口的位置要落在本台阶设计外轮廓线上,孔底的位置应落在下一个台阶平面的设计轮廓线上。

主爆孔参数如下:

台阶高度钻孔直孔深孔网单耗堵塞长度装药结构(m)径(mm)(m)(m)(kg/m3)(m)

10-15 115 3-8 3.5 × 2 0.5 2.5-3.5 间隔装药炮孔平面布置见下图:

深孔预裂爆破炮孔平面布置示意图(单位:m)

深孔预裂爆破炮孔剖面示意图

(4)装药施工

预裂(光面)爆破单位体积耗药量q=0.25kg /m~0.35kg /m,线装药密度应该进行严格控制,以防药量过大而损伤边坡。为了克服孔底较大的夹制作用,

确保孔底预裂缝的形成和贯通,适当地加大孔底装药量,孔底1米采取并排装 2 节,药径为?32mm的乳化炸药,孔的其余部分采用不偶合连续装药,孔口 1.5 米不装药,用钻孔时排出的岩屑充填,装药前,首先用黑胶布捆扎在竹片上,同时

把导爆索捆扎在其上,捆扎时必须注意,放入孔底端的竹片上末端及导爆索末端

都不允许超过此处的炸药,以保证炸药与孔底的密切接触,捆扎好后,慢慢地把炸药放入孔内,并尽量使炸药紧贴主爆孔一侧,以尽可能减少炸药爆炸能量,对预留壁面的影响。为了防止充填的岩屑落入孔的下部,在充填岩屑之前,预先在回填区域内用编织袋塞实。导爆索的长度要超过孔的长度,并且在孔口之上有一

定的长度。主爆孔采用间隔装药结构,控制同段起爆药量。

主爆孔、预裂孔装药结构示意图见图 3

(5)网络连接起爆

精心设计主爆孔的网络及引爆顺序和延发时间,使预裂面的第二次损伤减少

到最低程度。预裂孔超前与主爆孔起爆,为了确保主爆孔对预裂面的降震作用,

预裂孔起爆的超前时间不得小于100ms。但是不许超前太长时间,以免出现预裂

缝被充填,降低了降震效果。

炮孔外等间隔控制延时起爆网路,是指炮孔外用同一段别的毫秒管先把附近

的3个炮孔的导爆管并联(9段),然后再用9段管串联起来,使各个炮孔按一定的顺序先后起爆,而且每个炮孔的起爆间隔时间都在90ms以上,达到单孔单响,而且每个孔的起爆时间不重叠,爆破振动不叠加。爆破起爆网路如下图:

(6)预裂孔爆破覆盖

为了保护爆破区域周围建筑物的安全,施工中采用两层编织袋覆盖,先在编织袋内装入砂土,覆盖后将排间的编织袋用绳子连成一片,编织袋覆盖时要注意保护好起爆网络。

7、开采质量控制

7.1 施工方法控制

(1)严格按爆破设计进行钻爆作业,以满足要求。

(2)安排专人现场监督挖装设备装料上车,保证有次有序,顺利进行。

(3)有用料和弃料分开装运,运输车辆相对固定并编号,做上明显的标志。

(4)严格按风化土和完全弃料分开来堆放,以便采石场达到终采平台后,

及时恢复场地进行绿化。各类渣料的堆渣范围和高程严格按照规范要求实施。

(5)作好料场的边坡保护和排水工作,保持渣料堆体周边的边坡稳定。

(6)作好料场照明工作。

7.2 减少超径石的控制

(1)在保证挖掘机械设备作业面安全施工的基础上,选择高梯段进行装药

爆破,梯段高度10-15m。

(2)通过爆破试验获取满足石料级配要求的最佳爆破参数,采用孔间微差

挤压爆破施工技术,增加爆破块体相互碰撞和挤压,降低超径石百分率。

(3)用钻孔岩粉填塞孔口,确保堵塞质量,防止冲孔。

(4)严格按爆破设计进行钻孔施工,露天液压钻机孔位误差±20cm,孔深误差±20cm;

(5)适当增加钻爆规模,减少临空面产生的超径石。

(6)对少量超径石,在挖装过程中用挖掘机械分选集中,采用啄木鸟进行

二次解炮破碎后进行装运。

8、爆破安全控制

8.4 炸药用量控制

同段起爆最大药量计算设计根据《爆破安全规范》将爆破震动速度严格控

制在2.5cm/s ,根据中华人民共和国“爆破安全规程”GB6722-2003中爆破安全震动速度V =K(Qm/R)a推导出Qmax=R3(V/K)3/α:

式中:

R--- 爆破振动安全允许距离,单位为米,本工程R取43M。

Q--- 炸药量,齐发爆破为总药量,延时爆破为最大一段药量,单位为千克

V--- 保护对象所在地质点振动安全允许速度,单位为厘米每秒,对本工程取2.5cm。

K、a--- 与爆破点至计算保护对象间的地形、地质条件有关的系数和衰减指

数。

表二爆区不同岩性的K、a 值

岩性K a

坚硬岩石50-150 1.3-1.5

中硬岩石150-250 1.5-1.8

软岩石250-350 1.8-2.0

取V=2.5cm/s k=250 a=1.8 经计算单孔最大起爆药为Q=36.9Kg

4.6 飞石控制

按钻孔爆破施工的飞石距离公式计算:

R=40d,(m);

R=100K1 K2(r/w ),(m)。

Smax出=260×D2/3

式中:R—安全距离(m);

d—孔径(m,);

K1—深孔密集系数(取1);

r —深孔半径(cm);

K2—炸药爆能与抵抗线相关的系数(取0.9 ~1.1);

W—第一排炮孔的最小抵抗线(m)。

计算出露天深孔的爆破飞石距离在60~150m(钻孔直径为115mm)。在考虑减少爆破飞石的同时,还考虑到为了达到爆破石料的充分破碎,拟在爆破台阶的

前沿,预留一定厚度的爆碴,用来进行微差挤压爆破,这样即可防止飞石,又可

达到岩石充分破碎的效果。

由于爆破工程本身的诸多不确定性,飞石的可能性总是存在的,对爆破区域附近必须严加防范,设置警戒标志和信号,不留死角,人员必须撤离到300m以外,机械必须撤离到200m以外,对不能撤离的设备,必须进行遮盖防护。

4.7 安全防护

本项目施工中主要安全防护对象有:进场道路以及附近设施等。为保障炸药库、营地、变压器等重要建筑物及人身安全,拟定采用主动防护与被动防护措

施进行预防;

(1)主动防护与被动防护

①主动防护主要以控制爆破规模,调整起爆方向(临空面背向营地方向),

减少爆破次数,设计合理的爆破方案,保证爆破孔堵塞质量等。

②为确保起爆顺序按事先设计的起爆,应加强连线的检查和设计合理起爆段位。

③预裂爆破时在爆破孔上采用编织带装砂进行覆盖,减少冲孔飞石危害。

④对于附近的碎石场、变压器等设施以采取被动防护为辅,主要设施的迎炮

面采取搭设高排架(采用脚手架钢管及竹排搭设 6.0m 高的排架),并在高排架

前沿采用编织带装粘土筑一道 1.0m 高的防冲击柔性堤,以确保设备的安全,同

时在炸药库内雷管存储箱上设置多层纸盒,以确保炸药库安全。

⑤严格控制爆破震动速度,确保邻近建筑物的安全。

(2)坡脚道路滚石防护措施

①采石场外侧爆破采用浅孔减弱爆破,同时精心安排爆破顺序,控制爆破

方向,以最大限度减少爆破后落向山下的滚石。

②靠外侧边坡开挖以液压反铲为主,由外向内开挖,尽可能减少滚石。

③加强爆破警戒,每次爆破均根据实际情况对爆破飞石、滚落石、冲击波

可能危及到的范围进行预测并实施警戒,各道口设置警戒哨卡,派专人值守,警戒区线内人员、设备及时撤离,对无法撤离的设施设置保护屏障。

④尤其是在雨后,爆破前后全面对料场山体坡面进行检查,及时清理浮石。

⑤必要时,马道带一定坡度向内倾斜,当开采达到一定高程后,适当加大

马道宽度,以防止滚石直接落到坡脚。

(3)边坡稳定

料场顶部碎石土层边坡按1:0.5 ,碎石土层以下边坡按1:0.3 设置,每10~15m 设置一个3.0m 宽台阶( 马道) 。边坡采用预裂爆破技术,保护边坡岩石稳定,局

部岩层不稳定部位进行适当锚杆支护。

在开挖施工过程中,在边坡地质条件较差部位设置变形观测点,定时观测边

坡变形情况,如出现异常,立即采取应急处理措施,避免意外发生。

(4)警戒措施与信号

①装药时,安全警戒范围为爆区外周20m处设岗;起爆时,警戒范围为以爆点为中心,向外200m设岗。爆破信号拉响后,爆破前所有人员和机械、车辆、

器材一律撤至指定的安全地点。

②爆破警戒范围执行《爆破安全规程》(GB6722-2003)的规定,在危险区边界,设置明显标志,并派出岗哨。核定警戒点和警戒标志的位置,确保能够封

闭一切通道。

③各岗哨由项目部指挥部统一编号,岗哨之间和岗哨与指挥部之间应建立通

讯联络,警戒人员应将本岗位警戒情况随时向指挥部报告。

④执行警戒的人员,应提前一小时到达指定地点,封闭通往爆区的道路,使所有通向爆区的道路处于被监视之下,并坚守岗位直至警戒信号解除。

⑤加强与临近单位、居民的沟通工作,建立定时爆破时段,起爆前出示起爆信号,并在安全距离内派人把守各个通道口。在各通道口设立通告牌上标明爆破

的范围、时间、地点以及警戒范围。

⑥信号标志流程为:预告信号→准备信号→起爆信号→解除信号,接收爆破解除信号前,警戒人员需坚守岗位,确保不放任何人进入警戒区域内。

工程部维修工的岗位职责1、严格遵守公司员工守则和各项规章制度,服从领班安排,除完成日常维修任务外,有计划地承担其它工作任务; 2 、努力学习技术,熟练掌握现有电气设备的

原理及实际操作与维修; 3、积极协调配电工的工作,出现事故时无条件地迅速返回机房,听从领班的指挥; 4 、招待执行所管辖设备的检修计划,按时按质按量地完成,并填好记录表格; 5 、严格执行设备管理制度,做好日夜班的交接班工作; 6 、交班时发生故障,上一班必须协同下一班排队故障后才能下班,配电设备发生事故时不得离岗; 7 、请假、补休需在一天前报告领班,

并由领班安排合适的替班人.

石料场开采施工方案

石料场开采施工方案

目录 1、工程概况 (1) 2、工程特点、难点及措施 (1) 3、施工布置 (1) 4、开采分层规划 (2) 4.1开采范围确定 (2) 4.2开采分层 (2) 4.3开采施工程序 (2) 4.4料场开采方式 (3) 5 、施工准备及场地清理 (4) 6、开采施工 (4) 7、开采质量控制 (8) 8、爆破安全控制 (9) 8.1炸药用量控制 (9) 8.2 飞石控制 (10) 8.3 安全防护 (10)

石料场开采施工方案 1、工程概况 国道318线林芝至拉萨公路改造工程拉萨段第一合同起于墨竹工卡县城以东(k4554+800)经过墨竹工卡县城、甲玛乡、达孜县章多乡、终于达孜县塔杰乡(k4590+000),路线全长35.2公里。我部因施工料源不足,需在k4581+000(章多乡章多村)增设石料场一处,该料场储存量约30万方,面积约1.5万平米,原设计中无,已开采约1.5万方。根据有关部门要求,该石料场开采有用料只能为13万方。 k4581+000石料场位于章多乡章多村,往拉萨方向318国道左侧约2500m,料场北面有少量残留砂岩盖顶,东南面有大片基岩裸露,山坡基本无生长植被。上石料场施工临时道路从料场东面经过,开采运输条件好。岩性分析:颗粒密度ρP=2.64g/cm3,饱和块体密度ρS=2.60g/cm3,天然块体密度ρ0=2.60g/cm3,烘干块体密度ρd=2.58g/cm3,自然吸水率Wa=0.44%,孔隙率n=2.31%,饱和单轴抗压强度RS=155MPa,烘干单轴抗压强度Rd=176MPa,软化系数0.87,SO3含量QS=0.016%。 2、工程特点、难点及措施 该料场在318国道旁边,露天进行开采,开采时存在以下几个难点: (1)料场位于318国道旁边,为避免山体大面积破坏,保护当地环境,开采施工较困难。前期开采临时道路均已修通,拟定从采石场背面即从318国道进入采石场,绕道山体背面,从背面进行采石,避免了从318国道正面开采施工,影响当地环境。 (2)爆破作业较困难:因西藏地区炸药管理严格,使用困难;且山体爆破区域距山脚碎石加工厂、山下居民区较近,存在安全隐患。为保证碎石加工厂、营地及邻近建筑物的安全,采用多打孔、孔外分段、孔内微差、孔口保护等措施进行爆破。 3、施工布置 石料场内梯段爆破采用900mm潜孔钻机、270mm潜孔钻机钻孔,采用13m3/7

砂石料场建设方案

遵义市乐理至冷水坪高速公路项目 (K43+500~K53+505.677) 碎石加工场建设施工方案 (K50+100) 编制人:____________________ 审核人:____________________ 批准人:____________________ 实施日期: 遵义市乐理至冷水坪高速公第四分部

第一章总则--------------------------------------------------------------------------4 1.1目的------------------------------------------------------------------ --------------4 1.2适用范围------------------------------------------------------------------------4 1.3编制依据------------------------------------------------------------------------4 1.4基本规定------------------------------------------------ 4 第二章碎石加工场建设总体方案------------------------------------------- 5 2.1场地选址------------------------------------------------ 5 2.2场地规划-------------------------------------------------------------------------5 2.3.场地清表、硬化处理-----------------------------------------------------6 2.4碎石加工设备基础----------------------------------------------------------- 6 2.5集料堆放料仓搭建----------------------------------------------------------- 6 2.6办公区板房搭建---------------------------------------------------------------- 7 2.7洗车池、储水池--------------------------------------------------------------7 2.8施工用水及用电--------------------------------------------------------------7 2.9地镑及控制室-----------------------------------------------------------------7 2.10排水沟及边坡防护---------------------------------------------------------7 2.11门卫、大门及围墙---------------------------------------------------------- 8 2.12污水处理和抑尘降噪-------------------------------------------------------- 8 2.13场内及场外排水------------------------------------------------------------- 8 第三章碎石场施工流程------------------------------------------------------ 9 3.1采石工艺流程------------------------------------------------------------------- 9 3.2石料生产线基本流程介绍---------------------------------------------------- 9 3.3石料生产线性能介绍--------------------------------------------------------- 9

石料开采工程施工组织设计方案

南水北调沙河渡槽2标施工项目部 大营料场爆破开采施工方案 1.工程概况 1.1工程简介: 大营石料场位于宝丰县大营乡乔岭村东南,距本施工段约53km,料场北部紧靠大营镇~观音堂乡级公路。勘察区位于伏牛山低山区,山脚处高程一般266~274.0m,山顶高程348.0m,产地面积约1.12km2。该石料场有用层为寒武系中统张厦组(∈2zh)灰岩:灰色、深灰色灰岩,微致密灰岩,局部夹含泥灰岩,厚几厘米,弱风化,薄层、中厚层~厚层状构造,单层厚度一般0.1~0.4m,厚者1.5m, 灰岩层中的溶沟溶槽发育,断层破碎带不良地质存在;溶沟、溶槽部分为黄色粘土半充填及全充填。节理裂隙十分发育,以垂直甚多,裂隙面上附有大量铁锰膜,厚达0.3~0.5mm,方解石脉及方解石结晶段较发育。可开采厚度一般35~46m,岩层倾向北东,倾角一般约5°~16°,表层黄色粘土夹碎石及强~全风化层,厚度2.0~5.0m。开采最低高程266.0m。 岩石试验成果与《水利水电工程天然建筑材料勘察规程》(SL251-2000)质量要求对比见表1-1。 表1-1 岩石试验成果与《规程》(SL251-2000)质量要求对比表 料场名称试验项目 岩性 饱和抗压 强度 软化系数 冻融 损失率 干密度 硫酸盐及硫 化物含量 (换算成 SO3) 碱活性质量评价 MPa - % g/cm3% - 按照地域、设计 要求与使用目的确定 <1 >2.4 <0.5 - 大营灰岩(∈2zh)69.3 0.84 0.02 2.72 合格非活性既可作块石料,又可作混凝土骨料。 料场石料储量见表1-2。 表1-2 石料场统计储量表 料场名称岩性储量(万m3)碱活性建议用途 大营灰岩(∈2zh)588.0 非活性岩石混凝土人工粗、细骨料

1#砂石料加工场建设实施方案

贵州省紫云至望谟高速公路1#砂石料加工场建设方案 MCC-CETC 中冶交通紫望项目第二分部 编制:____________ 审核:____________ 二零一六年十月

目录 1 编制依据及原则 (1) 1.1 、编制依据 (1) 1.2 、编制原则 (1) 2 工程概况 (1) 3 修建标准 (1) 3.1 、人工加工砂石料依据. (1) 3.2 、砂石料加工场标准. (2) 3.3 、标识标志 (2) 4 1# 砂石料加工场选址及安全评估. (2) 4.1 、地理位置 (2) 4.2 、地形、地貌、地质,水文情况. (3) 4.3 、地质灾害危险性现状评估. (3) 4.4 、建设场地适宜性评估及防治措施. (3) 5 施工准备 (3) 5.1 、方案准备 (3) 5.2 、技术准备 (4) 6 资源配置 (4) 6.1 、作业人员计划 (4) 6.2 、材料计划 (5) 6.3 、设备计划 (5) 7 砂石料加工场施工方案. (6) 7.1 、取、弃土石方 (6) 7.2 、场地开挖 (6) 7.3 、场地填筑和碾压. (6) 7.4 、场地硬化 (6)

7.5 、料仓隔墙 (7) 7.6 、设备基础 (7) 7.7 、挡墙 (7) 7.8 、防排水 (7) 7.9 、设备安装 (7) 7.10 、防雷与接地 (8) 7.11 、消防与通风 (9) 7.12 、加工工艺 (9) 7.12.1 、石料生产线基本流程介绍 (9) 7.12.2 、石粉含量的控制. (10) 7.12.3 、细骨料的含水率控制. (10) 8 生产线工艺流程图 (10) 8.1 、质量控制标准 (11) 9 场内生产、生活用电. (11) 9.1 、电源负荷计算 (11) 9.2 、配电箱与开关箱. (11) 9.3 接地与接零保护系统 (13) 9.4 、漏电保护器 (14) 9.5 、现场照明 (14) 10 生产能力计算 (15) 10.1 、人工砂石料加工系统生产任务. (15) 10.2 、系统生产能力要求. (16) 11 砂石料加工场组织机构. (16) 11.1 、组织机构 (16) 11.2 、砂石加工场职责、各工作岗位职责 (17) 11.2.1 、砂石料加工场职责. (17) 专业知识分享

砂石料场建设方案设计

市乐理至冷水坪高速公路项目 (K43+500~K53+505.677) 碎石加工场建设施工方案 (K50+100) 编制人:____________________ 审核人:____________________ 批准人:____________________ 实施日期: 市乐理至冷水坪高速公第四分部

第一章总则--------------------------------------------------------------------------4 1.1目的------------------------------------------------------------------ --------------4 1.2适用围------------------------------------------------------------------------4 1.3编制依据------------------------------------------------------------------------4 1.4基本规定------------------------------------------------ 4 第二章碎石加工场建设总体方案------------------------------------------- 5 2.1场地选址------------------------------------------------ 5 2.2场地规划-------------------------------------------------------------------------5 2.3.场地清表、硬化处理-----------------------------------------------------6 2.4碎石加工设备基础----------------------------------------------------------- 6 2.5集料堆放料仓搭建----------------------------------------------------------- 6 2.6办公区板房搭建---------------------------------------------------------------- 7 2.7洗车池、储水池--------------------------------------------------------------7 2.8施工用水及用电--------------------------------------------------------------7 2.9地镑及控制室-----------------------------------------------------------------7 2.10排水沟及边坡防护---------------------------------------------------------8 2.11门卫、大门及围墙---------------------------------------------------------- 8 2.12污水处理和抑尘降噪-------------------------------------------------------- 8 2.13场及场外排水------------------------------------------------------------- 8 第三章碎石场施工流程------------------------------------------------------ 9 3.1采石工艺流程------------------------------------------------------------------- 9 3.2石料生产线基本流程介绍---------------------------------------------------- 9 3.3石料生产线性能介绍--------------------------------------------------------- 9

砂石料加工场建设方案

砂石料加工场建设方案 Document number【980KGB-6898YT-769T8CB-246UT-18GG08】

目录

砂石料加工场施工方案 1.编制依据及原则 编制依据 ⑴新建丽江至香格里拉铁路站前工程施工设计图纸; ⑵《铁路混凝土工质量验收标准》(TB10424-2010); ⑶《铁路混凝土工程施工质量验收补充标准》(铁建设【2005】160号); ⑷《关于印发<铁路混凝土工程施工质量验收补充标准>混凝土分项工程原材料标准局部修订条文的通知》(铁建设【2009】152号); ⑸砂石料加工场严格按照滇西铁路建设指挥部关于印发《利用隧道洞碴生产混凝土用粗细骨料的管理规定》的通知(滇西指物资〔2014〕45号); ⑹地方政府对临建工程的相关管理文件及标准。 编制原则 ⑴安全适用、经济合理的原则; ⑵节约用地、节省投资、环保节能、防灾减灾的原则; ⑶因地制宜、综合利用的原则; ⑷充分利用场地条件,尽可能减少洞渣中转环节,缩短工艺流程线路; ⑸为了施工、运行管理的方便,各环节之间均考虑有道路相联; ⑹生产附属设备施工就近布置,以便于生产运行管理。 2.工程概况 本单位承建新建XXX站前工程,地点位于云南省丽江市龙蟠乡境内,负责的主要工作面为XXX隧道1号、2号横洞、达落双线中桥、XXX隧道1号横洞。 砂石料加工场设在1号混凝土拌合站附近。 3.修建标准 砂石料加工场标准 (1) 有给料设备、颚式破碎机、反击式破碎机、分层振动筛、清洗设备; (2) 储料区按待检区和合格区设置,料仓按4个设置。

(3) 有配套的环保设施设备,如沉淀池、洗车池等; (4) 砂石料加工场场地排水坡度按2%设置,料仓排水坡度按3%设置。 (5)砂石料加工场内要分区硬化,按重载区、一般重载区、普通区区域来处理。砂石料加工场料场、料仓及进、出料主车道为重载区,该区域先采用土石混碴硬化压实,然后采用C20混凝土硬化25cm。底板混凝土浇筑模板采用钢模板或木模加工,模板安装必须牢固,并预留料仓隔墙基础位置及水沟位置;底板坡度由测量组现场测量,按照3%坡度来控制,坡度方向为从料仓底部向料仓口倾斜。 (6) 砂石料加工场设备基础应高出硬化地面30cm。 标识标志 (1) 材料:标志应采用坚固耐用的材料制作。可根据具体情况选用铝合金板、薄钢板、合成树脂类板材等材料,有触电危险场地应采用绝缘材料。 (2) 形状:标志牌形状主要为矩形和圆形。 (3) 尺寸:矩形标志牌尺寸(长×宽)一般为30×40cm、40×30cm、60×80cm、80×60cm、150×100cm、150×200cm、200×150cm、250×200cm;圆形标志牌直径一般为30cm~50cm,按现场实际需要选用。 4.砂石料加工场选址及安全评估 砂石料加工场选址在1号混凝土拌合站附近,地势平坦开阔。 地理位置 砂石料加工场地处云南省丽江市,处于XXX隧道进口上方。 地形、地貌、地质,水文情况 工程选址在山坡上,地形条件较为平坦,根据临建工程的设置原则及技术要求,工程选址满足“安全适用,经济合理”的要求,同时体现“节约用地,节省投资,节能环保,合理适用”的原则,重视防灾减灾。选址避开了易积水和不良地质段。 工程所处位置地表为米左右腐殖土,其下碎块石土,下伏基岩为凝灰岩,白云质灰岩。周围汇水面较小且附近水沟排水畅通,不存在水文问题。地质灾害危险性现状评估

砂石料场建设方案

遵义市乐理至冷水坪高速公路项目 (K43+500 ?K53+ 碎石加工场建设施工方案 (K50+100 ) 编制人:________________________ 审核人:________________________ 批准人:________________________ 实施日期:______________________ 遵义市乐理至冷水坪高速公第四分部

第一’章总贝 y 4

附件: 遵义南环二标碎石加工厂平面布置 1#碎石加工场建设施工方案 第一章总则 目的 本项目设置符合标准化要求、满足生产需要的标准化碎石加工场一座,对本项目一号搅拌站需要的各种粒径的碎石进行集中加工、配送,保证混凝土加工与现场施工的正常进行。为规范碎石加工场的场地建设、管理制度、业务流程、工序工艺、设备操作规程,特制定本方案。 适用范围 本方案适用于中建股份有限公司遵义市乐理至冷水坪高速公路项目第四分部碎石加工场的规划建设、管理和运营。 编制依据 1、贵州省遵义市乐理至冷水坪高速公路第四合同段两阶段施工图设计文件; 2、《高速公路建设标准化管理指南(工地建设)》相关条款要求; 3、现场调查所获得的有关资料、数据及现场情况; 4、国家有关方针政策和国家、交通部有关标准规范、规程和验标等; 5、本标段工程投入的施工管理、专业技术人员、硬件设施和交通工具等资源。

基本规定 遵义市乐理至冷水坪高速公路项目K50+060右侧设置1处符合业主和总监办标准化要求的碎石加工场,场地面积为7400m2采用封闭式管理,配备专门的技术人员 及管理人员,对搅拌站需要的碎石进行集中加工配送。 碎石加工场的规模及功能符合投标文件承诺的有关要求及满足施工需要。功能区划分生产区、办公区和生活区。而生产区包括碎石加工设备、临时存料区、集料堆放区、洗车设施、配电房、储水池等。生活区设施分住宿、食堂、厕所、浴室、办公区设值班室、办公室。 第二章碎石加工场建设总体方案 场地选址 通过对沿线环境条件的调查研究,结合本工程的实际情况,依据《高速公路施工标准化技术指南》和《贵州省高速公路建设标准化指南》要求,遵循“以人为本、统筹规化、合理布局、因地制宜、节约资源、保护环境、交通便利、安全实用、规范有序、功能完备、方便生活、满足生产”的原则,选取三岔镇高山村肇兴组狮子山旁K50+060右侧作为碎石加工场地。此位置场地较为宽广,较适合作为碎石加工场地,且距离K50+200-K50+400段路堑(原材料供料场)较近,方便运输的同时也节约了成本,预计本段落弃方量约为5 万立方米。 选址原则及要求: 1)以满足项目碎石需求为前提; 2)坚持科学性、先进性、经济性、合理性与实用性相结合的原则; 3)靠近路基开挖施工现场。 本项目碎石加工场位置靠近桌泥坝大桥,且远离地质自然灾害区域。周围无塌方、滑坡、落石、泥石流、洪涝、台风等自然灾害隐患,无高大树木及油、气、化工等其他污染,避开了取土、弃土场用地,满足安全、环保、水保的要求,是较为合理的碎石加工场地。 场地规划 根据交通运输公路局《高速公路施工标准化技术指南》(第一分册工地建设)及《贵州省高速公路项目实施工程的管理规定》(黔交质[2014]183 号)以及乐理至冷水坪高速公路上级主管单位相关条文要求,经项目部结合现场综合考虑后,选取三岔镇高山村肇兴组狮子山旁边作为碎石加工场地,预计生产碎石万m3。

石料场开采安全专项施工方案

目录 1 工程概况 (1) 1.1 石料场概况 (1) 1.2 水文气象资料 (1) 1.3 地形地质 (1) 1.4 开采规划 (2) 1.5 施工设备及道路布置 (4) 2 编制依据 (5) 3 施工计划 (5) 3.1 拟投入主要施工设备进场计划 (5) 3.2 进度计划 (6) 4 施工工艺技术 (6) 4.1 施工程序及爆破施工方法 (6) 4.2 爆破开采石料方案 (8) 4.3 钻孔爆破作业设计 (8) 5 施工安全保证措施 (16) 5.1 危险源分析 (16) 5.2 土石方开挖安全技术措施 (16) 5.3 确保S207省道通行安全技术措施 (20) 5.4 安全事故应急措施 (20) 6 劳动力计划 (23) 7 爆破控制计算及布孔图及验算 (24) 7.1 爆破振动控制 (24) 7.2 爆破飞石控制 (25) 7.3 爆破参数控制 (25)

1工程概况 1.1石料场概况 本标段石料场位于拟建的上存坝址上游,河流右岸公路边,距上存坝址1.2km,料场沿安溪至长泰的207省道公路右侧山坡分布,高程在EL140~240m 之间,料场面积7.84万㎡,根据初步设计对石料场的地质勘测可知,平均剥离层7.14m,无用层体积56万m3,有用层平均厚度30.7m,石料储量240.7万m3,岩性为流纹质晶悄凝灰熔岩。 承包人参考福建省水利水电勘测设计研究院提供石料场勘测成果资料,结合承包人补充钻孔探测的资料,对料场进行重新规划,石料储量按坝体约50万m3乘以1.5损耗系数为75万m3进行规划,实际开采过程中若遇到料场中存在弱风化软弱夹层等不可用料,料场具备继续往下开采有条件,经对料场按75万m3有用料进行开采计算,可知料场无用料约为61万m3。 1.2水文气象资料 工程所在流域属福建省沿海南部,属亚热带海洋性季风气候区,温暖湿润,气候温和,冬短夏长,降雨充沛,降雨量年内和年际变化较大,年降雨集中于梅雨和台风雨季节,每年4-10月降雨量约占全年的3/4。多年平均降雨量1500~1900mm;从上游向下游递减。多年平均气温21C°,极端最高气温38 C°,极端最低气温-1.7 C°,多年平均风速1.7m/s;多年平均相对湿度80%。 1.3地形地质 工程区位于福建省东南部长泰县及同安县境内,区域总的地势是西北高,东南低,呈阶梯状下降。西部、北部为中低山、丘陵,中部多为低山、丘陵,沿海为丘陵、台地、平原,东部为台湾海峡。西部以戴云山为主体,走向主要呈北东向,峰顶海拔多在千米以上。沿海一带表现为丘陵山地、红土台地、沿海平原、滨海岛链带及台湾海峡盆地的地貌景观。

料场开采专项施工方案

料场开采施工方案 1、工程概况 1.1工程简介 xxxx水库坝址位于xxxx乡和xx乡的交界处,所属河流为xx。xx 为三岔河的一级支流,水库坝址位于距xx与三岔河的汇口以上大约750m处,xx水库供水工程是以工业供水为主,兼有发电的一项综合性水利工程。工程建成后,P=95%工业供水毛供水量为1976万m3/a,年发电量1406万KW,并下放环境水量2050万m3/a。xx水库工程坝址以上流域集水面积257.3km2,多年平均径流量 2.05亿m3,多年平均流量5.84m3/s。水库建成后为季节性调节,水库总库容为1305万m3,正常蓄水位为1242m。规模属中型,工程等别为Ⅲ类等。 工程建设内容由工程建设内容包括:水源工程、供水工程,其中:水源工程建筑物主要包括:大坝(常态混凝土坝拱坝,最大坝高74m)、溢洪道、引水系统(含泵站和电站)、水电站(装机规模为3500KW)等;供水工程建筑物主要包括:泵站、隧洞(长4189.47m)、输水管道(长8764.05m)等。 1.2料场基本情况 根据设计文件大箐石石料场为主料场,河垭口左右岸石料场为备用料场,本工程石料场按照业主要求选在坝轴下游右岸备用料场。 (1)料场的选择 根据现场地质调查及测绘,工程区T1yn3 和T1yn1-2 灰岩是较好的建筑材料,尤其是T1yn1-2 灰岩,纯度高,硬度大,不易产生碱骨料活性反应。根据技术上可行、经济上合理、尽可能减少对周边村寨及环境产生不利影响的原则,选取右岸备用料场为本阶段石料场。该料场有R4公路与坝址连通,距坝址较近。 (2)料场质量与储量 右岸石料场位于大坝下游约600m,为T1yn3和T1yn1-2中厚层~

采石场建筑石料用灰岩矿资源开发利用方案设计(新)

XXXX采石场建筑石料用灰岩矿资源 开发利用方案 一、概述 1.1矿山位置和企业性质 1.1.1矿区位置与交通 矿区位于XXXXX三湾村和尚岭地段。采石场地理坐标为东经112°46′31″~112°46′37",北纬25°21′19″~25°21′23″。行政隶属XXXX三湾村管辖。矿区交通条件较好,修简易公路400m与梅(田)麻(田)公路相连。采场距XXXX政府所在地2.5km,距梅田镇政府所在地约7km (见交通位置图)。 1.1.2矿山批准开采范围和开采现状 XXXX人民政府麻政字[2007]5号文《关于申办采石场的请示》,经县政府主管领导批示,有关部门派人到现场核查,按“四堂会审”要求,各主管部门审核确认,县政府领导批准,决定按程序立项开办该采石场。拟定该采石场开采范围由5个坐标拐点圈定而成。 点号 X坐标 Y坐标 1 280608 2 38376733 2 2806157 38376834 3 2806157 38376905

4 2806027 38376905 5 2806027 38376780 矿区拟定开采范围面积为0.1847km2。允许开采标高从+271m至+215m。 1.1.3与邻近矿山的关系 该采石场东北角145m处设立有XXXX三湾村顺发采石场。除此之外,在周边300m内未设立其他采矿权和探矿权。拟采范围与最近村庄、厂矿、公路相距达200m。除此之外,在爆破安全距离内还有一些农田、旱土和林地(见《XXXX 采石场位置图》)。 1.2方案编制依据 其编制依据主要有: (1)《中华人民共和国矿产资源法》 (2)《中华人民共和国安全生产法》 (3)《中华人民共和国矿山安全法》 (4)《矿山安全监察条例》 (5)《金属非金属矿山安全规程》 (6)《乡镇露天矿场安全生产规定》 (7)《民用爆炸物品安全管理条例》 (8)《郴州市矿产资源开发利用方案编写评审实施规则》(9)XXXX国土资源局批准的XXXX邓家采石场开采范围 (10)XXXX邓家采石场地形地质图 -2-

《砂石料场项目计划书》

目录 第一章总论 ---------------------------------------- 2 1.1 项目名称、建设性质及建设地点---------------------- 2 1.2 项目效益------------------------------------------ 2 第二章背景及必要性 ------------------------------------ 3 2.1本行业及关联产业发展现状--------------------------- 3 2.2 新疆砂石发展机遇---------------------------------- 3 2.3 黎明重工砂石发展的经验介绍------------------------ 4 2.4 关联产业发展状况---------------------------------- 5 2.5 项目建设的必要性---------------------------------- 5 第三章砂石料市场分析----------------------------------- 6 3.1产品市场供求现状及前景分析------------------------- 6 3.2市场竞争优势分析----------------------------------- 6 3.3全国现有砂石矿产资源市场需求分析------------------- 6 第四章建设方案 ---------------------------------------- 9 4.1开采方案 ------------------------------------------ 9 4.2设备方案 ------------------------------------------ 9 4.3采石工艺流程 ------------------------------------- 10 4.4人工砂生产工艺流程-------------------------------- 12 第五章结论和建议 ------------------------------------- 13 5.1结论 --------------------------------------------- 13

大面积平整砂石料场土地复垦方案

积石峡水电站甘河滩砂石料场区土地复垦方案报告书 项目单位:甘肃同舟工程建设有限责任公司 项目负责人: 编制单位:甘肃省土地开发整理中心 编制负责人: 编制人: 编制日期:二零零九年十二月

目录 前言 (5) 1 总则 (6) 1.1编制目的和内容 (7) 1.2编制指导思想和原则 (8) 1.3编制依据 (9) 1.4设计水平年及目标 (10) 1.5服务年限 (10) 2 项目及项目区概况 (11) 2.1项目概况 (11) 2.2项目所在地区自然环境和社会经济概况 (15) 2.3项目区水土流失及水土保持现状 (20) 3 土地复垦可行性分析 (21) 3.1已破坏土地现状 (21) 3.2拟破坏土地预测 (21) 3.3生态环境的影响分析 (26) 3.4复垦土地适宜性评价 (26) 4 预防控制和复垦措施 (33) 4.1设计原则和目标 (33) 4.2复垦标准 (34) 4.3预防控制措施 (41) 4.4工程技术措施 (42) 4.5生物化学措施 (42)

5 土地复垦工程施工组织设计 (44) 5.1土地复垦工序流程 (44) 5.2复垦规划 (45) 5.3渠系工程 (45) 5.4工期目标 (47) 5.5复垦工程总布置 (47) 5.6土地复垦工期计划 (48) 5.7土地复垦图例划分 (52) 5.8适宜草树种 (52) 5.9土地复垦工程设计及施工时间安排 (52) 5.10灌溉及排洪系统 (54) 6 土地复垦投资测算 (55) 6.1投资测算概述 (55) 6.2测算依据 (55) 6.3复垦费用预算结果 (55) 7 土地复垦效益分析 (56) 7.1生态效益 (56) 7.2社会效益 (57) 8 保障措施 (58) 8.1组织领导和管理措施 (58) 8.2技术保障措施 (59) 8.3资金来源及管理措施 (59) 8.4公众参与 (60) 8.5竣工验收与监督管理 (60) 9 附件 (62) 9.1附图 (62)

石料开采施工方案(工程科)

南水北调沙河渡槽标施工工程部 大营料场爆破开采施工组织技术指导文件 .工程概况 工程简介: 大营石料场位于宝丰县大营乡乔岭村东南,距本施工段约,料场北部紧靠大营镇~观音堂乡级公路。勘察区位于伏牛山低山区,山脚处高程一般~,山顶高程,产地面积约。该石料场有用层为寒武系中统张厦组(∈)灰岩:灰色、深灰色灰岩,微致密灰岩,局部夹含泥灰岩,厚几厘米,弱风化,薄层、中厚层~厚层状构造,单层厚度一般~,厚者, 灰岩层中的溶沟溶槽发育,断层破碎带不良地质存在。溶沟、溶槽部分为黄色粘土半充填及全充填。节理裂隙十分发育,以垂直甚多,裂隙面上附有大量铁锰膜,厚达~,方解石脉及方解石结晶段较发育。可开采厚度一般~,岩层倾向北东,倾角一般约°~°,表层黄色粘土夹碎石及强~全风化层,厚度~。开采最低高程。 岩石试验成果与《水利水电工程天然建筑材料勘察规程》()质量要求对比见表。表岩石试验成果与《规程》()质量要求对比表 料场石料储量见表。 表石料场统计储量表 工程内容 在业主提供的石料场开采范围内开采石料进行砂石骨料加工。具体施工内容包括大营料场宝丰至郏县段鲁山北段砂石料场砂石加工原料开采,钻孔、爆破、开挖、装

运、破碎加工,砂石加工系统安装等施工项目。 工程特点 石料采用钻爆开采方式进行,浅灰色,弱风化。整个开采区(Ⅰ区)靠冲沟内侧,道路需沿冲沟修筑。周边居民建筑距开采区相对较远,也无其他建筑物。 .施工程序及技术要求 施工布置 ()施工道路 进场道路路基宽,路面宽,泥结石路面结构。 ()施工用水、用电 采用打井取水,再铺设管路引至各需用水地点,部分地点采用水车供水。 施工用电由宋坪变电站引线路至砂石加工系统,再根据施工需求引至各作业区。 ()施工照明 采用碘钨灯和碘钨灯对夜间施工进行照明。 ()施工供风 在进场道路内侧靠近采石区现场布置台-()电动空气压缩机,在砂石加工系统布置台()柴油空气压缩机进行施工供风。 ()通讯 在施工现场通过对讲机和手机进行爆破指挥。 施工主要程序 修筑出料场道路→料场清理→料场覆盖层开挖→爆破实验→钻孔→装药起爆→石料的装运→完工清场 施工方法及技术要求 石料的开采,拟采用大孔距、小排距、深孔梯段爆破的施工方法进行爆破设计。采用间隔装药、排间毫秒微差爆破技术控制爆破后的石渣粒径,并根据现场爆破试验结果适当调整爆破参数,使爆破后的石渣粒径和不同粒径的含量尽量符合要求,减少石料的二次爆破和材料的浪费。 修筑出料场道路

砂石料加工场建设方案

目录 1.编制依据及原则 (1) 1.1编制依据 (1) 1.2编制原则 (1) 2.工程概况 (1) 3.修建标准 (1) 3.1砂石料加工场标准 (1) 3.2标识标志 (2) 4.砂石料加工场选址及安全评估 (2) 4.1地理位置 (2) 4.2地形、地貌、地质,水文情况 (2) 4.3地质灾害危险性现状评估 (2) 4.4建设场地适宜性评估及防治措施 (3) 5.施工准备 (3) 5.1方案准备 (3) 5.2技术准备 (3) 5.3临建队伍准备 (4) 6.资源配置 (4) 6.1作业人员计划 (4) 6.2 材料计划 (4) 6.3设备计划 (4) 7.砂石料加工场施工方案 (4) 7.1取、弃土石方 (4) 7.2场地开挖 (5) 7.3场地填筑和碾压 (5) 7.4场地硬化 (5) 7.5料仓隔墙 (5) 7.6设备基础 (5) 7.7挡墙 (5) 7.8防排水 (6) 7.9设备安装 (6) 7.10防雷与接地 (6) 7.11消防与通风 (7) 7.12加工工艺 (8) 7.12.1石料生产线基本流程介绍 (8) 7.12.2石粉含量的控制 (8) 7.12.3细骨料的含水率控制 (8) 7.13质量控制标准 (8) 8.场内生产、生活用电 (9) 8.1电源负荷计算 (9) 8.2配电箱与开关箱 (9) 8.3接地与接零保护系统 (11) 8.4漏电保护器 (11) 8.5现场照明 (12) 9.生产能力计算 (13)

9.1人工砂石料加工系统生产任务 (13) 9.2系统生产能力要求 (13) 10.砂石料加工场组织机构 (13) 10.1组织机构 (13) 10.2砂石加工场职责、各工作岗位职责 (14) 10.2.1砂石料加工场职责 (14) 10.2.2砂石加工场生产负责人岗位职责 (14) 10.2.3质量负责人岗位职责 (15) 10.2.4安全员岗位职责 (15) 10.2.5试验员岗位职责 (15) 10.2.6设备管理员岗位职责 (16) 10.2.7操作员岗位职责 (16) 10.2.8运输司机岗位职责 (16) 10.2.9装载机操作人员岗位职责 (17) 10.2.10机修电工岗位职责 (17) 10.2.11工人岗位职责 (17) 11.施工保证措施 (17) 11.1施工进度保证措施 (17) 11.2环境保证措施 (18) 11.3 质量保证措施 (18) 11.3.1母材质量控制 (18) 11.3.2生产过程控制 (19) 11.3.3成品检查验收制度 (19) 11.4安全保证措施 (20) 11.4.1安全目标 (20) 11.4.2安全管理组织机构 (20) 11.4.3安全管理职责 (21) 11.4.4安全生产保证措施 (21) (1)碎石场安全操作规定 (24) (2)作业与运输的要求 (24) (3)用电作业安全措施 (25) (4)电气控制安全 (26) (5)劳动防护用品管理措施 (26) (1)砂石加工场安全应急救援预案 (27) ①可能出现的应急事故 (27) ②应急管理措施 (27) (2)防洪渡汛应急救援措施 (27) (3)机械事故应急救援措施 (27) (4)不可抗力自然灾害应急措施 (27) 12.环境保护措施 (28) 12.1 给水系统 (28) 12.2 废水处理系统 (28) 12.3废水处理设计 (29) 12.4噪声污染防治措施 (29) 13.其他 (30)

砂石料场开采专项方案

一、工程简况 二、料场复查 在工程开工后,根据规范要求对料场进行全面复查,并根据施工实际情况进一步调整各料源开采量,及时上报监理人审批。 三、石料场复查 1、复查内容 石料场在开采前,首先进行石料场复查,复查根据本工程所需各种石料的使用要求,对本合同指定的石料场进行复勘核查,其复查内容包括: (1)各类填筑料的数量和开采范围; (2)料场的剥离层厚度、有效开采层厚度和软弱夹层分布情况; (3)根据设计文件要求,对各种材料进行物理力学性能(如比重、容重、含水量、压缩系数、渗透系数、抗剪强度等)取样试验; (4)料场的开采、加工、储存和装运条件; (5)料场的工程地质和水文地质条件。 在料场复查完成后,及时将复查结果和报告提交监理人审核。 2、复查目的 (1)通过进行料场原始断面的测量,为复核料场总储量提供开采依据; (2)进一步探明料场地质及分布情况,为规划不同品质料的开采分区、优化开采爆破参数、布置规划料源平衡及对开采、装运设备等的资源配置提供依据; (3)对所需各品种的开采料和不同高程段的岩石进行物理力学性能的取样复核试验,进一步确定岩石界面,复核分布情况,指导施工; 3、复查方法料场复查采用地质钻机进行钻孔,取岩芯的方式进行复。地质钻孔孔径90mm,孔深30~40米,孔位按100m×100m的方

格网控制,对重点部位,可加密地质钻孔进行勘查。 通过料场复查,确定石料场开采范围、储量、开采深度等参数,并在开采时适时调整开采爆破参数,力求在开采石料满足上坝填筑要求的前提下,工程造价最低。 四、土料场复查 1、复查工作内容土料场在开采前,首先进行料场复查,其复查内容包括: (1)坝体填筑采用的防渗土料的开采范围和数量; (2)土料场开采区表土开挖厚度及有效开采层厚度; (3)根据施工图纸要求对土料进行物理力学性能复核试验; (4)土料场的开采、加工、储存和装运条件; (5)土料场的工程地质和水文地质条件; 2、复查要求 (1)重点复查土料天然含水量及其随季节的变化情况、颗粒组成、土层情况、储量、覆盖层厚度和可开采土层的厚度; (2)压实特性,即最大干密度、最优含水量、碎石土料的破碎率; (3)物理力学性质,如天然干密度、比重、液塑性、压缩性、渗透性、抗剪强度等; 3、复查方法采用坑探取样进行复查,首先施工人员在平面上建立50m×50m的方格网,并在网点上埋设基桩确定探坑位置,采用反铲配合人工挖坑,沿坑深每1m测定土料含水量一组,同时测定土料颗粒级配,了解颗粒级配在平面和立面上的变化特点,其它复查项目通过取代表样进行试验。对颗粒级配符和要求的土料在进行取样试验以了解土料的物理力学性质。通过料场复查,确定长河坝料场开采范围、储量、开采深度等参数,并在开采时适时调整开采和加工方法,力求在开采料满足上坝填筑要求的前提下,工程造价最低。

砂石料开采与加工方案

砂石料开采与加工方案 The manuscript was revised on the evening of 2021

编号:NN5-ZSSJ-022 引水发电系统的土建和相关金结工程 砂石料开采与加工方案 中国水电建设集团十五工程局有限公司 2009年12月20日

老挝南俄5水电站BOT项目施工技术方案 目录 南俄5水电站引水发电系统 砂石料开采与加工方案

一、工程简况 南俄5水电站引水发电系统工程主要包括进水口、引水洞、调压井、压力管道、发电厂房和尾水洞工程,目前各工程均处于开挖和支护阶段(其中进水口开挖还剩4m至设计高程;隧洞(包括尾水洞)开挖及支护完成45%;调压井上室开挖支护完成,井筒反井钻导孔完成),除已完成部分开挖支护工程外,上述工程剩余砼111581m3,浆砌石工程7520m3(详见表1),需要砂石料约万m3(其中砂子89844m3,碎石83838m3,具体见《砂石料采购计划》承包[2009]报告048号文件),块石9200 m3。 根据我部上报的《关于再次报送牛棚河滩天然砂砾料品质检测结果及相关补充资料的报告》(编号:承包[2009]报告113号)文件及贵部对该文件的批复,我部也进行了相应的现场探坑取样,经计算,该料场储量满足工程需要。按施工总体安排,我部已于2009年11月29日开始砂石料加工设备基础砼浇筑,12月4日砂石料加工设备进场。 表1 砼及浆砌石工程量统计表

二、砂石料开采方案 料场开采按照先主河道后河漫滩顺序分区,依次从下游向上游、从右至左次序依次开采,开采深度为3m。开采前先将河水改道,并对表层杂物及覆盖层进行清理。料场布置详见《牛棚砂石料场平面布置示意图》,砂石料场开采特性详见表2。 1、开采分区 该料场为天然砂石料场,由于天然砂石级配在深度和平面上相差较大,而实际情况是下游以中细料为主,上游则以中粗料为主,并有少量出露的孤石。而本工程砂料用量较大,为保证砂石骨料生产的级配平衡,减少弃料,在料场开采时采用分区开采。即先从下游向上游连续沿主河道开采,挖深3m,最后开挖河漫滩部分。该料场共分六个区,分别 为Ⅰ 1、Ⅰ 2 、Ⅱ 1 、Ⅱ 2 、Ⅲ 1 、Ⅲ 2 。 表2 砂石料场开采特性 注:Ⅰ、Ⅱ、Ⅲ区开采前,先修围堰,将河水靠左侧截流以后开采右侧河床裸露砂砾石;后进行覆盖层剥离,弃入已开采的河床,再进行开采。 2、覆盖层剥离 为了保证有用层原料的质量,在正式开采前先将覆盖层剥离干净,对于裸露的原料,开采前先清除河道树枝、杂草;对于有覆盖层的河漫滩,先进行植被砍伐清理,再通过机