5. Equipment which require special storage or safe-keeping at Site. • Scope of equipment? • Make? • Type? • Instructions about the storage or safe-keeping?
Grinding Rollers and Center Yoke
Mill Housings
Nozzle Ring
Densit Lining On Reject Cone
Densit Lining on Mill Housing Bottom Plate
Densit Lining on Separator Bearing Shaft Assy.
• Separator drive • Hydraulic and • Rollers lube systems
ATOX Mill, Circuit of Grinding Force
ATOX Mill, Grinding Mode with Material
ATOX Mill, Grinding Mode with Material
Mill Foundation
Mill Base Frame
Mill Base Frame
Mill Gear Plate
Main Gear Unit
Grinding Table
Grinding Table Wear Liners
Joint Head
Grinding Rollers and Center Yoke
Questions ?
End of Presentation…..
Running site office
Time Sheet, Model copy
Note: This is reference only
Running site office
Final Acceptance certificate, Model Copy
Note: This is reference only
Mill Feed Chute
Hydraulic Cylinder
Hydraulic Room
Water spray Unit
Accumulators
Mill Installation Complete
Mill Installation Before and After
Things to do before proceeding to site
ATOX Raw Mill, Size 50
Atox Mill Components and It’s Installation
• Foundation • Base frame • Gear unit • Grinding table • Grinding rollers • Mill Housings • Nozzle ring • Separator housings
6. Equipment delivered which requires sub-suppliers presence • at commissioning and first start up. • Scope of equipment? • Make? • Type?
RUNNING SITE- OFFICE
Atox mill components and its Installation
• Densit lining • Separator parts • Joint head • Hydraulic cylinder • Pull rod • Torque arm • Accumulators
Atox mill components and its Installation
- Memo to Client
Running site office
REPORTS • The site office is responsible that reporting based on and if
necessary documented by the current site files is prepared and sent to FLS at the times agreed upon or as normal practice to send once in a week. • Time sheet, every week/Month
Things to do, before proceeding to site
1. Assignment.
• Turn-key? • BasiБайду номын сангаас?
2. Project organization.
• Who is the PM (project or contract manager)? • Meeting with PM? • Special training required? • Site Manual? • Safety and security briefings - ?
• Current files: - Diary including: Arrival and departure of site-employed personnel. Number and type of main erection equipment used. Arrival and internal flow of equipment. Type, extent and location of performed progress. Obstacles, interruptions , tests performed. Stoppage of work specifying the cause. Accidents Weather conditions, site conditions (access) Specific directions or instructions from client or others. etc.
Things to do, before proceeding to site
• Visa ? • Work permit? • Forex? • Air ticket? • Medical insurance? • Vaccinations? • Time sheet? • FQR’s? • Airport pick-up? • Contact persons? Telephone numbers?
Running site office
- Minutes of meetings from site meetings - Time schedules. - As shipped drawings and equipment - Instruction manuals covering the total scope of supply - As built drawings and equipment instruction manuals. - Packing lists (shipping document) - Project error reports (FQR's) - Deviation orders - Site instruction manuals - Site rules covering organisation, accidents,safety,fire protection,protection against burglary and vandalism, housekeeping, - FLS Installation Manual - List of names of all site assigned persons. - Site progress reports.
Running site-office
• The site office is responsible that information is prepared about all important decisions and events on Site from the day of mobilisation and until the day of final Field Acceptance Document
Things to do, before proceeding to site
4. Sundri equipment which require specialists at Site. • Scope of equipment? • Make? • Type? • Calculate number of persons and estimated time at Site. • Supervisor at lump sum price or hourly paid
Separator Housings
Separator Housings
Separator Guide Vanes
Separator Rotor
Separator Rotor
Separator Top Section
Separator Bearing Assembly
Separator Drive Units
3. Documentation
• Study the scope of documentation – every department, every type, make a list or get a list from the PM/ENGG and tick off.
• If our FLS scope is a part delivery (basic) who is then making the complete documentation ?
• Finished Erection certificate
• Final Acceptance certificate
Running site office
Finished Erection certificate, Model copy
Note: This is reference only
Grinding Rollers and Center Yoke
Mill Housings
Nozzle Ring
Densit Lining On Reject Cone
Densit Lining on Mill Housing Bottom Plate
Densit Lining on Separator Bearing Shaft Assy.
• Separator drive • Hydraulic and • Rollers lube systems
ATOX Mill, Circuit of Grinding Force
ATOX Mill, Grinding Mode with Material
ATOX Mill, Grinding Mode with Material
Mill Foundation
Mill Base Frame
Mill Base Frame
Mill Gear Plate
Main Gear Unit
Grinding Table
Grinding Table Wear Liners
Joint Head
Grinding Rollers and Center Yoke
Questions ?
End of Presentation…..
Running site office
Time Sheet, Model copy
Note: This is reference only
Running site office
Final Acceptance certificate, Model Copy
Note: This is reference only
Mill Feed Chute
Hydraulic Cylinder
Hydraulic Room
Water spray Unit
Accumulators
Mill Installation Complete
Mill Installation Before and After
Things to do before proceeding to site
ATOX Raw Mill, Size 50
Atox Mill Components and It’s Installation
• Foundation • Base frame • Gear unit • Grinding table • Grinding rollers • Mill Housings • Nozzle ring • Separator housings
6. Equipment delivered which requires sub-suppliers presence • at commissioning and first start up. • Scope of equipment? • Make? • Type?
RUNNING SITE- OFFICE
Atox mill components and its Installation
• Densit lining • Separator parts • Joint head • Hydraulic cylinder • Pull rod • Torque arm • Accumulators
Atox mill components and its Installation
- Memo to Client
Running site office
REPORTS • The site office is responsible that reporting based on and if
necessary documented by the current site files is prepared and sent to FLS at the times agreed upon or as normal practice to send once in a week. • Time sheet, every week/Month
Things to do, before proceeding to site
1. Assignment.
• Turn-key? • BasiБайду номын сангаас?
2. Project organization.
• Who is the PM (project or contract manager)? • Meeting with PM? • Special training required? • Site Manual? • Safety and security briefings - ?
• Current files: - Diary including: Arrival and departure of site-employed personnel. Number and type of main erection equipment used. Arrival and internal flow of equipment. Type, extent and location of performed progress. Obstacles, interruptions , tests performed. Stoppage of work specifying the cause. Accidents Weather conditions, site conditions (access) Specific directions or instructions from client or others. etc.
Things to do, before proceeding to site
• Visa ? • Work permit? • Forex? • Air ticket? • Medical insurance? • Vaccinations? • Time sheet? • FQR’s? • Airport pick-up? • Contact persons? Telephone numbers?
Running site office
- Minutes of meetings from site meetings - Time schedules. - As shipped drawings and equipment - Instruction manuals covering the total scope of supply - As built drawings and equipment instruction manuals. - Packing lists (shipping document) - Project error reports (FQR's) - Deviation orders - Site instruction manuals - Site rules covering organisation, accidents,safety,fire protection,protection against burglary and vandalism, housekeeping, - FLS Installation Manual - List of names of all site assigned persons. - Site progress reports.
Running site-office
• The site office is responsible that information is prepared about all important decisions and events on Site from the day of mobilisation and until the day of final Field Acceptance Document
Things to do, before proceeding to site
4. Sundri equipment which require specialists at Site. • Scope of equipment? • Make? • Type? • Calculate number of persons and estimated time at Site. • Supervisor at lump sum price or hourly paid
Separator Housings
Separator Housings
Separator Guide Vanes
Separator Rotor
Separator Rotor
Separator Top Section
Separator Bearing Assembly
Separator Drive Units
3. Documentation
• Study the scope of documentation – every department, every type, make a list or get a list from the PM/ENGG and tick off.
• If our FLS scope is a part delivery (basic) who is then making the complete documentation ?
• Finished Erection certificate
• Final Acceptance certificate
Running site office
Finished Erection certificate, Model copy
Note: This is reference only