同期系统调试方案(chs & eng)
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
TURKEY BURSA CEMENT CO., LTD.
2200t/d+1850t/d WHR POWER GENERATION PROJECT
Commissioning Plan
Of
Generator Synchronization System
Report No.:
Starting Time:
Project Leader:
Staff Members:
Compiler:
Verifier:
Approver:
摘要
Abstract
本措施依据火电工程启动调试工作规定,主要针对土耳其BURSA 2200t/d + 1850t/d余热发电工程1×9MW机组启动调试工作提出具体方案。依据相关规定,结合本工程具体情况,给出了土耳其BURSA余热发电工程发电机同期系统启动调试需要具备的条件、调试程序、注意事项等相关措施。
This plan is compiled according to thermal power project commissioning specification. It is special for 1*9MW commissioning of BURSA 2200t/d+1850t/d WHR Project. It gives required conditions, commissioning procedures, attentions, and other measures for generator synchronization of this project in line with related regulations and specific circumstance.
关键词:电气系统;发电机;同期系统;调试措施
Keywords: Electric system; Generator; Synchronous system; Commissioning measures
目录Contents
1、编制依据Basis of compilation (3)
2、调试目的The purpose of commissioning (3)
3、同期装置介绍The introduction of synchronization equipment (3)
4、调试范围Debugging scope (4)
5、调试应具备的基本条件The basic conditions of debugging (4)
6、调试中的安全注意事项The commissioning safety precautions (4)
7、调试方法与步骤Debugging methods and procedures (4)
8、调试的质量及检验标准The debugging quality and inspection standards (6)
9、调试过程中应记录的项目和内容The projects and contents recorded during the commissioning. .. 6
10、项目的组织与分工Project organization and task distribution (6)
1、编制依据Basis of compilation
1.1《火力发电厂基本建设工程启动及竣工验收规程》电力部电建[2009版] “Thermal power plant basic construction project start and completion acceptance specification”Ministry of electrical power [The 2009 version]
1.2《火电工程启动调试工作规定》电力部建设协调司建质[1996版]
“Thermal power project start commissioning specification”Ministry of electric power and construction coordination department [The 1996 version]
1.3《火电工程调整试运质量检验及评定标准》电力部建设协调司建质[1996]版“Thermal power project regulating commissioning quality inspection and evaluation standards”Ministry of electric power and construction coordination department [The 1996 version]
1.4《火电施工质量安装工程施工及验收规程(电气专业)》
“Thermal power construction quality installation project construction and accepta nce specification (Electrical major)”
1.5《火电机组达标投产考核标准(1998年版)》电力工业部
“Thermal power unit standard production inspection standard (The 1998 version)” Ministry of electricity and industry
1.6《电力建设安全工作规程(火力发电厂部分)》DL5009.1-92能源部能源基[1992]129
号
“Electric power construc tion safety work procedures (Thermal power construction)”DL5009.1-92 of [1992]129 of Ministry of energy
1.7《电气装置安装工程电气设备交接试验标准》(GB50150-91)
“Electrical equipment commissioning test standards of el ectrical equipment installation project” (GB50150-91)
1.8设备制造厂家的技术文件和设计院设计图纸
The technical documents of manufacturers and drawings of designing institute
2、调试目的The purpose of commissioning
2.1保证发电机同期系统及其回路的正确性、完整性。Guarantee the validity and completion of generator synchronous system and circuits.
2.2保证发电机并网过程的正确性,防止非同期并网。Guarantee the validity of generator synchronization and prevent accidents from non-synchronization
3、同期装置介绍The introduction of synchronization equipment
本项目采用西门子同期屏,其主要技术特点如下:The project utilizes SIEMENS synchronization screen, which has following characteristics:
3.1 具有独立的合闸出口;It has an independent switch-on output;