110kV钢管杆组立施工作业指导书

110kV钢管杆组立施工作业指导书
110kV钢管杆组立施工作业指导书

句容郭庄110kV 线路工程钢管杆组立作业指导书

句容市新源电业发展有限公司

句容郭庄110kV 线路工程施工项目部

2014 年 2 月

批准:年月日审核:年月日编写:年月日

目录

一、工程概况................................................... -..1. -

二、施工依据................................................... -..2. -

三、施工准备................................................... -..2. -

四、塔材运输................................................... -..3. -

五、钢管杆组立................................................. -..4. -

六、质量要求................................................... -..6. -

七、安全健康和环境管理要求 ..................................... -..6 -

八、主要工器具................................................. -..9. -

横担方向

一、工程概况

1、线路概况:

工程110kV 线路位于句容市南部,起于

110kV 天后887线10#?11#间新立分支塔,止于

110kV 郭庄变,路径总长22.41km ,其中双回架空线路 22.29km ,双回架设;双回电缆线路0.12km 。 本工程导线采用铝合金绞线

2JLHA3-335,地线采用两根24芯OPGW ;新立杆塔87基,其中

螺栓式铁塔75基,钢管杆12基;本工程采用 C25灌注桩基础及 C20台阶式基础;电缆采用 YJLW03-64/110-1*1000mm2 ;新建16孔电缆排管20m ,四通道电缆井 2座。本线路所经地区 处于镇江句容市最西侧,较为偏远,大部分通道主要为乡镇级道路抵达,施工运输条件一般, 运行检修条件一般。

高 呼

量 数

桩 k

z(\

r

「 皋

直线杆

9

2

O : 99TT T T 33 78>TT T 、

2 ⑺

T8

耐张杆

4 4 2

3

6

8

T

5

24 4

4

2

5

3

7

24

4

4

2

5

3

6

计 合

2

2、钢管杆施工计划:

本工程立钢管塔12基,其中耐张杆5基,直线杆7基。部分钢管塔靠近路边可以采用吊

车立塔

3、线路前进方向:

本工程测量以110kV 天后887线10#?11#间新立分支塔为起点,止于 110kV 郭庄变,线路

转角以此方向来确定为左转或右转。线路前进方向示意如下:

郭庄变

110kV天后887线10#?11#间新立

二、施工依据分支塔为起点

1. 《110—500kV架空电力线路施工及验收规范》(GB5023?2005)、《国家电网公司输变电工程达标投产评选办法》 (国家电网基建[2011]146号、《110kV—500kV 架空

电力线路工程施工质量及评定规程》 (DL/T5168—2002))

2. 《电力建设安全工作规程》(DL5009.2- 2004)

3. 本工程设计文件、相关施工图及会检纪要、本工程施工组织设计及本作业指导书。《钢结构工程施工质量验收规范》GB50205-2001《输电线路钢管杆制造技术条件》DL/T646-2006、《国家电网公司基建安全管理规定》国家电网基建[2011]1753号、

《架空输电线路钢管塔组立施工工艺导则》Q/GDW346-2009

三、施工准备

1.

2.参加杆塔施工人员必须经过安全教育、具备上岗条件且安全考试合格并经过

技术交底;

3. 参加施工的民工,在施工前由施工负责人讲解工作范围、安全注意事项和操作方

法,宣讲安全施工作业票和安全监护制度,并做好安全监护工作;

4. 组立操作的重要岗位必须由送电技工担任。不得由临时工指挥立塔,不得由

未取得高处作业合格证的人员登塔作业。重要岗位由非送电技工顶岗时,必须经公司

培训并取得相应合格证;

5. 特殊作业、特种作业人员必须经培训合格、持有效证件上岗;

6. 民工必须在技工带领下操作,不得独立作业;

7. 施工前准备所需的工器具及运输设备,必须检查其性能和完好性,符合要求并齐全后方可施工。

四、钢管杆运输

① 钢管杆运输前的检查

1、钢管杆运到现场后必须进行质量检查及配基,本工程钢管杆由厂家直接发往各施工桩位。

2、质量检查内容:

1)、塔材、螺栓、垫圈等是否符合设计图纸及相应的专业技术标准的要求;

2)、每一构件上应有明显的编号;

3)、主杆、横担、螺栓、垫圈、爬梯等都必须按设计规定进行热镀锌防腐。镀锌后的外观质量检查应符合规定。如因运输造成局部锌层磨损时,应补刷防锈漆,其表面在涂刷银粉漆;

3、钢管杆配基的内容:

1)、依照杆塔明细表的桩号、塔型对构件及螺栓、脚钉、垫圈等按基配置;

2)、注意识别塔型代号,不同代号的构件不得混放;

3)、构件配置后,如有缺件,应登记好缺件的编号及数量,同时汇报项目部。

② 塔材的运输

1、钢管杆运至现场时,项目部材料部门应按公司程序文件的要求进行验证。铁塔运输前,材料部门依照杆塔明细表的塔型对构件、螺栓、爬梯和垫片等按基配套,作好发货记录;

2、由于已考虑将塔材下在桩位,所以下货时应充分考虑施工的方便性。

3、钢管杆运输必须遵守《电力建设安全工作规程》DL5009.2-2004 中第六章的规定。小运时,重大物件不得用肩直接扛运;如抬小构件时,应步调一致,且同肩同起同落。

4、钢管杆构件在运输过程中,严禁损坏构件、使构件变形,运到桩位后应加强看管,

谨防遗失和被盗。

五、钢管塔组立

钢管杆全部采用汽车吊起吊,全部分段起吊,起吊钢丝绳的选择:100D2=F X K1 X K2,其中F=12860, K仁5, K2=1.2, D=27.7,起吊钢丝绳不得小于此数值。

1 、排杆组装及作业要求

⑴排杆组装时应在熟悉钢管塔图纸、施工作业指导书等基础上进行,且须保证钢管塔(或吊装段)的重心在杆根部位距基础中心偏移0.5m左右,以利于起吊。

⑵螺栓穿向同一般铁塔组装时要求一致。

⑶钢管塔爬梯统一装在顺线路的小号侧。

⑷防盗装置:15 米以下都采用防盗螺丝。

⑸防松:下横担下2米处至塔顶进行点漆防松。

⑹底段法兰盘向上 2 米处或爬梯下端的位置,设置一块常规使用的白底红字警示牌,竖写“有电危险禁止攀登”。

⑺钢管塔左右两边下横担的下平面,距塔身1米处各增设1个悬挂相色牌的?

17.5螺孔。在底段6米处左右横担侧各设置1个悬挂杆号牌的? 17.5螺孔。

⑻钢管塔每段长为7-12m 左右,段与段采用法兰螺栓方式进行连接,因此在整体(或有 2 段以上)起吊时需用加工的特制紧螺栓的工具将螺栓拧紧。

⑼钢管塔在起吊前需对基础基面进行操平或预高,并事先测量其根部直径及地脚螺栓的数量,防止运错。

⑽采用吊车进行吊装的施工场地应平整,进场道路需密实,对软弱场地可初压后,采用路基箱供吊车行驶。

(11)起吊绑扎处应包麻布片,以保护镀锌层。中间法兰对接处,上下法兰预先做好相应标记,以便于空中对接。

(12)对接法兰处的操作平台,在下段吊离地面1.5米左右时进行安装。

(13)解除吊绳前,应将吊段校正至满足设计要求,并将螺栓紧好。

2、技术措施

2.1 运到现场的钢管杆的杆段的规格、数量、尺寸和螺栓位置应符合要求。

杆塔组立作业指导书(1)

目录 编制依据 (2) 第一章杆塔组立工程概况 (3) 一、工程简述 (3) 二、工程参建单位 (3) 三、地质、地貌状况 (3) 四、杆塔型号简介 (4) 第二章现场作业准备及布置 (6) 第三章主要施工方法及要求 (9) 一、施工工艺流程 (9) 二、施工准备: (9) 三、现场布置 (10) 四、塔腿组立 (13) 五、竖立扒杆 (14) 六、提升扒杆 (14) 七、构件的绑扎 (16) 八、构件的吊装 (17) 九、扒杆拆除: (18) 十、螺栓复紧与缺陷处理: (19) 第四章安全技术措施 (20) 作业人员职责 (20) 安全技术措施 (22) 第 1 页共26 页

编制依据 1 施工项目部对本工程施工现场和周围环境的勘察; 2 《110kV良塘输变电线路新建工程施工组织设计》及施工图纸和文件;设计变更 3 《110~500KV 架空送电线路施工及验收规范(GB 50233-2005)》; 4 《110kV~500kV架空电力线路工程施工质量及评定规程(DL/T5168-2002)》; 5 《电力安全工作规程》; 6 《标准化施工作业手册(送电工程分册)》; 7 《国家电网公司输变电工程标准工艺》(一)施工工艺示范手册》 8 《国家电网公司输变电工程典型施工方法(第一辑)》 9 《国家电网公司电网工程施工安全风险识别、评估及控制办法(试行)》[2011]1758号 第 2 页共24 页

第一章杆塔组立工程概况 一、工程简述 九江修水县110kV良塘变输变电线路新建工程,分为110kV叶家山至良塘送电线路工程及110kV修渣线破口进良塘线路工程两段。 110kV叶家山至良塘送电线路工程,自叶家山变电站110KV构架出线,止于新建110KV良塘变电站进线构架,线路亘长约29.8公里,导线采用LGJ-300/40型钢芯铝绞线;地线采用一根JLB20A-80铝包钢地线,另一根采用OPGW-24芯光缆,全线新建直线塔78基,耐张塔33基。 110kV修渣线破口进良塘线路工程,自修渣线21#-22#杆处起,止于新建110KV良塘变电站进线构架线,线路亘长约1.2公里,导线采用LGJ- 300/40型钢芯铝绞线;地线采用一根JLB20A-80铝包钢地线,另一根采用OPGW-24芯光缆,新建铁塔5基。 二、工程参建单位 建设单位:九江供电公司 设计单位:九江电力勘察设计院 监理单位:江西诚达工程咨询监理有限公司 施工单位:九江巨能实业总公司 三、地质、地貌状况 110kV叶家山至良塘送电线路工程,地形比例:平地7%,丘陵22%,山地71%,运输较困难,人力运距600米,汽车运输12公里。 110kV修渣线破口进良塘线路工程,地形比例:山地100%,运输较困难,人力运距500米,汽车运输5公里。 各地形所占比例表 第 3 页共24 页

110kV钢管杆作业指导书

钢管杆组立作业指导书 110kV 临时用电线路工程 钢管杆组立作业指导书 2012年6月

批准:日期:审核:日期:编制:日期:

目录 第一章工程概况 (1) 1.1、适用范围 (1) 1.2、引用标准及编制依据 (1) 1.3、概述 (1) 第二章作业准备及条件 (3) 2.1、组立方法的选择 (3) 2.2、吊装机械设备的选择 (3) 2.3、技术准备和条件 (3) 2.4、人员配置 (5) 2.5、机具配置 (5) 第三章作业方法及施工要求 (7) 3.1、钢管塔的结构特性 (7) 3.2、钢管塔的安装工艺要求 (7) 3.3、施工操作方法 (7) 3.4、钢管塔组立现场布置图 (8) 第四章作业质量标准及检验要求 (9) 4.1、作业质量应符合如下标准 (9) 4.2、材料检验要求 (9) 4.3、施工质量检验要求 (9) 4.3、检验要求 (10) 第五章安全施工注意事项 (11) 第六章文明施工及环境保护 (15) 第七章作业人员的职责及权限 (16)

钢管杆组立作业指导书 第一章工程概况 1.1、适用范围 1.1.1本标准适用于绵阳电铁皂角铺牵引变电站110kV临时用电线路工程的钢管杆组立的施工。 1.1.2本标准规定了钢管杆组立的施工工艺和吊装方法,明确了施工时的安全、质量注意事项、文明施工及环境保护的要求。 1.2、引用标准及编制依据 《110—500kV架空送电线路施工及验收规范》(GB50233-2005) 《110—500kV架空电力线路工程施工质量及评定规程》DL/T5168-2002 《高压架空输电线路施工技术手册》(杆塔组立部分) 《电力建设安全工作规程》(架空电力线路部分)(DL 5009·2—2004) 有关设计图纸、铁塔施工图会审纪要。 1.3、概述 1.3.1本工程起于110kV兴高Ⅱ线N12塔“T”接点起,至于110kV变电站进线构架止,全长0.581km的110kV单回架空线路本体设计。 线路名称: 导线型号:LGJ-240/30 地线型号:LBGJ-50-20AC 本工程建设单位: 设计单位:、 施工单位: 1.3.2杆塔型号及数量: 1.3. 2.1本工程共有杆塔7基,其中单回路转角塔4基,占57.1%;单回路转角钢管杆2基,占28.6%;双回路终端塔1基,占14.3%。 使用塔型及数量见下表:表1

钢管塔吊装组立施工案及措施

10kV镇东线、10kV莲新线架空线改电缆工程 钢 管 塔 吊 装 组 立 施 工 方 案 及 措 施 批准: 审核: 编写: 高要南兴公司新桥工程部 2016年2月2日

本工程为10kV镇东线、10kV莲新线架空线改电缆工程,新建杆塔1基,考虑到钢管塔高度计重量,决定采用分段起吊组装的方案。为保证施工安全迅速地组立钢管塔,特制定以下措施。 一、工程概况: 1、本工程为10kV镇东线、10kV莲新线架空线改电缆工程,新建杆塔1基, 2、钢管塔交通运输情况: 本线路杆塔分布于马路边及田中,全线地形平坦,交通便利。 3、危险点情况及对应措施: 1)、由于钢管塔施工现场过往行人车辆,因此需在交叉路口上设置专人监护并设立安全警示牌如:前方施工车辆绕行等。 2)、在起吊钢管塔前应进行试吊作业,在每一段钢管塔起吊约10cm时应暂停,检查制动装置,确认完好后方可继续起吊。 4、施工时间及要求: 施工队定于2016年1月30日进行钢管塔组立工作,进行组立钢管塔前,施工项目经理部应组织施工员及聘用的专业起吊人员一同进行安全技术交底,明确任务、职责。 二、施工组织机构:(见下页)

各级人员现职: 项目经理:具体负责工程的组织领导工作,全面负责工程安全、质量、财务费用工作。 施工队长:负责施工现场的组织管理安全生产、施工进度安排、文明施工、协调以及在起吊过程中配合起吊指挥员的工作等。 技术负责人:全面负责钢管塔组立过程中的工程技术管理和施工质量管理及具体负责施工技术管理、钢管塔专项组立措施及现场技术指导和督查等工作。 专职安监员:具体负责工程的安全监督管理、组织安全学习、督查和指导规程、措施的落实,参加事故的调查、处理以及消防、保卫和环境保护管理工作,对安全文明施工进行考核与奖惩。整理并保管好安全资料。 兼职安全员:负责组织施工队安全学习、监督施工现场的安全文明施工,检查施工措施的落实,做好安全活动记录,整理有关安全资料并妥善保管,做好消防、保卫、环境保护等工作。 质检员:具体负责组立钢管塔的施工质量、计量、测量、试验等工作。

电杆组立施工作业指导书讲解

冕宁大田光伏电站35kV送出工程 一般施工方案 四川强光电力工程有限公司 2015年10月14日

批准:年月日审核:年月日编写:年月日

总则 一、基础工程施工结束并经监理和运行单位代表验收合格或同意后方可进行杆塔组 立施工;杆塔工程结束并经监理和运行单位代表验收合格或同意后方可进行放紧线施工。 二、严格执行GB/T19001-IS09001-2000质量体系标准编制的《质量手册》有关质量 要求;严格按施工设计图施工,如有疑问,必须报项目经理部并得到肯定答复后才能施工;严把材料关,严禁不合格材料进入施工现场。 三、严格执行各种有关安全生产的规程、规范、条例和制度;严禁不合格工机具进 入施工现场。

一、工程基本概况 本工程电杆双杆12基,铁塔17基。8至9号跨高速公路一次。 2至3号,5至6号,18至19号,20至21号,穿越110kv,共四次。13至14号,28至29号跨安宁河二次。有十基耐张塔。 工程区属于高山峡谷地貌,,线路沿线高程为3800~4500m。 沿线地形划分:丘陵 10%,山地30%,高山60%。 地质划分为:松沙石30%,岩石70%。 第一部分砼杆组立 电杆组立施工流程图

第一章砼杆组立 一、砼杆的组装 1、水泥电线杆焊接方法与焊接质量要求 1.水泥杆的连接方式等径的分段水泥杆尽长为9米,经过不同长度的连接可以配成各种长度的电线杆。近年来也对分段的环形电杆,均必须在施工现场进行连接,焊接方式所用的材以下几种: (1)螺栓连接。用法兰盘和螺柱连接。此对方法对交通不便地区使用比饺方便,但耗钢量较大,创造上也比较麻烦,连接质量也较焊接差,故目前采用此法连接的较少。 (2)钢图(钢箍)焊接。钢阉焊接。目前施工中经常使用的为气焊和电焊焊接。 1)气焊(又称风焊)是用可燃气体和易燃气体混合燃烧形成的火焰加工焊接。线路上通常使用电石加水发生的乙炔气作可燃气体,以氧气助瓶火焰的最高温度可达20 00一30 00℃。气焊需用的设备为乙炔发生器一只,氧气瓶,可以分散搬运,携带较轻便。气焊的特点是加热均匀和缓慢;缺点是被焊件容易迟火,气体火焰易受外界气流影响。 2)电焊(又称电弧焊),线路上常用的为手工电弧焊,它是利用手工操作,在工件和焊条问引燃电弧,利用电弧高温熔化焊条和焊件进行焊接。所需没备为弧焊机l台,使用简单方便,焊接成本低,被焊件不易退火,其缺点是野外施工电源困农只能采用直流弧焊发电机,比较笨兔设备成本乱还需经常维修管理。 现在线路施工的水泥杆焊接,绝大多数均采用气焊。该项工作应由焊工负责焊接,作为协助工作的外线施工人员,也应当对焊接工艺的质量要求和安全措施,有所了解。 2.水泥电杆焊接的质量要求 (1)焊接的钢箍焊口上的污物进行消除干净。 (2)焊接前应允、排杆是否符合焊接的要求。 (3)钢箍焊口应对齐,电杆拼间隙应将合规定。 (4)先在全助长点焊三、四处,然后分段交叉进行焊接。 钢箍限度8毫米以反复焊两层。电焊焊条应与正式焊接用的规格相同。 (5)焊缝表面应平沿美巩鳞纹折皱细致均匀,不得有焊缝个断,咬边、焊痫、失渣、气泡、陈格和尺寸偏差等欧阳,无法纠正补焊时,此匿去重焊。焊缝如合裂纹,必须凿去运行施焊。 (6)钢因焊接后的思维尺小规定。 2、吊杆焊巴:直线杆,两侧吊杆焊巴朝小号,中间面向大号,左侧吊杆放在小 号侧,焊巴朝大号,右侧吊杆放在大号侧,焊巴朝小号。 耐张杆,焊巴并列朝内,中间面向大号,左侧吊杆放在小号侧,右

钢管杆吊装作业指导书(施工方案)

***电力工程有限责任公司********工程 ***电力工程有限责任公司 ********工程项目部

年月 批准:时间:年月日审核:时间:年月日编制:时间:年月日

一般施工方案(措施)报审表 工程名称:编号:SJSX2-SG01-005

注本表一式3份,由施工项目部填报,监理项目部、施工项目部各存1份。 目录 一、工程概况及适用范围............................................................................................................................ - 5 - 1.1工程概况.................................................................................................................................. - 5 - 1.2地质、地形地貌及水文状况.................................................................................................. - 5 - 1.3交通运输情况.......................................................................................................................... - 6 - 1.4自然环境.................................................................................................................................. - 6 - 1.5铁塔配置.................................................................................................................................. - 7 - 二、编制依据................................................................................................................................................ - 8 - 三、作业流程................................................................................................................................................ - 8 - 四、工艺流程及主要质量控制点................................................................................................................ - 8 - 4.1作业准备.................................................................................................................................. - 9 - 4.2施工准备................................................................................................................................ - 10 - 4.3技术准备................................................................................................................................ - 10 - 4.4吊车就位................................................................................................................................ - 10 - 4.5地面组装................................................................................................................................ - 10 - 4.6构件吊装................................................................................................................................ - 11 - 4.7钢管杆检修............................................................................................................................ - 11 -

电力工程大跨越钢管塔组立施工简述

电力工程大跨越钢管塔组立施工简述 【摘要】近年来,输电线路在设计大跨越选择塔形时,越来越多地选择钢管塔来实现跨越;即便是普通线路在500千伏设计选择双回路、四回路用塔时,也偏好选择钢管塔――钢管塔施工机械的选择就显得比较重要了。本文就大跨越钢管塔施工主要施工方法进行简要分析及比较,对普通线路钢管塔施工方案的确定和机械的选择、注意事项也有一定的借鉴价值。 【关键词】输电线路;大跨越钢管塔;组立方法 1 引言 输电线路在设计大跨越选择塔形时,要根据塔位的地质和荷载情况来决定大跨越杆塔采用高强度杆塔,设计往往采取钢管塔。其特点是根开大、塔型重、高,需高空作业,受天气影响大。以往的跨越高塔组立中,曾采用座腿式小抱杆、悬浮双摇臂抱杆、座地四摇臂抱杆、塔式起重机分解组立的方式,以上的组立方式抱杆操作、拆解工艺较为复杂,施工周期长。现就某输电线路新建工程500千伏台电钢管塔为例,以JCT293型座地双平臂抱杆做为两基跨越塔组立施工的主要机械。如何保证安全、按期、优质完成高塔的组立,将是钢管塔施工工程的重中之重。笔者长期从事电力系统钢管塔施工工程,以此作为课题展开探讨是最好不过了,下文仅供同行参考。 2 组立方式的比较 输电线路高塔的组立方式主要有摇臂抱杆分解组立、塔式起重机分解组立、双平臂座地抱杆分解组立等几类方式。 2.1 摇臂抱杆分解组立 摇臂抱杆分解组立图示: 图1 摇臂抱杆分解组立塔 摇臂抱杆顾名思义是由座落于地面或悬浮于承托钢丝绳系统上的主抱杆上部对称布置四付或两付摇臂而成。抱杆是立于吊装作业中心的一根立柱,摇臂是则是吊装用的吊臂,吊臂的上下摆动形象的定义为摇臂。各摇臂端的顶面与主抱杆顶间连于起伏滑车组,当牵引设备收卷或松放起伏滑车组钢丝绳时,摇臂便可绕主抱杆上的支座作仰俯运动,以调整塔构件的空间位置。各摇臂端部的底面又连于提升滑车组,当牵引设备收卷或松放提升滑车组钢丝绳时,便可使塔构件作升降运动。座地摇臂抱杆的工作原理将抱杆底脚落地,杆顶通出塔头,吊臂高出铁塔施工面最小2m,利用多层腰环稳定直立于塔位正中抱杆,在主抱杆上的摇臂支座处还设有4根拉线与已组塔身顶端四角主材节点相连,以稳定抱杆,用小吊臂及起吊滑车组进行吊装作业。抱杆可随组塔高度而任意接续杆段而增高。吊

钢管杆组立作业指导书

第1部分:输电线路 钢管杆组立作业指导书 编码:SDXL-ZW-06

SDXL-ZW-06 钢管杆组立作业指导书 目次 1 工程概况及适用范围···································································································································· 61 2 编写依据····································································································································· (61) 3 作业流程····································································································································· (62) 4 安全风险辨析与预控···································································································································· 63 5 作业准备····································································································································· (64) 6 作业方法····································································································································· (65) 7 质量控制措施及检验标准 (67)

钢管塔组立施工工艺

钢管塔组立施工工艺 Final revision by standardization team on December 10, 2020.

110KV竹园民官联线路工程 钢管塔组立施工工艺批准: 审核: 编写: 桂林漓昇电力建设有限责任公司 2005年5月18日 钢管塔组立施工工艺 1、针对竹园民官联线路联湖线段钢管塔组立施工而编制; 2、本次施工采用吊车组立和人工组立方法进行施工; 吊车组立施工: 根据地形情况好坏可以选择分段吊装组立和整体吊装,由于吊车组立工序简单,本次钢管塔吊车组立施工不作详细介绍。 人工组立施工: (1)挖好地锚,地锚距离塔中心为大于塔全高,以保证防绳对地夹角小于等于45°;

(2)起吊抱杆为15米以上口400钢抱杆,提升木抱杆9~12米,滑车为5T铁滑车,磨绳为一条200米Φ14钢丝绳,防绳为四条60米Φ16钢丝绳,机动绞磨一台,四把3T手扳葫芦; (3)人工组立施工步骤: a、立抱杆,打好四方防绳;布置好起吊滑车组和机动绞磨;(如图一所示) b、绑好起吊钢管塔第一段位置,起吊离地时,要进行冲击实验,检查四方防绳地锚,确无问题,方可起吊;起吊前注意脚钉方向和起吊绑套位置方向。 c、就位时注意脚钉方向和横担方向,特别是转角塔的方向。(如图二所示) d、倒提升木抱杆注意四方防绳控制以及缆腰麻绳控制,此点是提升木抱杆的关键。固定木抱杆位置至少3米以上,绑固木抱杆要牢靠,收紧四方防绳要保持木抱杆的垂直状态。 e、用木抱杆提升钢抱杆,同样固定钢抱杆位置至少3米以上,固定前要先固定两块垫木,要保持钢抱杆处于垂直状态;钢抱杆底坐所绑钢丝套要紧固,缆腰钢丝套要收紧固定好;收紧四方防绳;将木抱杆拆除松至地面。(如图三所示) f、吊立第二段钢管时,起吊点位置最好在滑车组的垂直下方;起吊前注意脚钉方向和起吊绑套位置方向,绑好起吊点钢管塔第二段位置,起吊离地时,要进行冲击实验,检查四方防绳地锚,确无问题,方可起吊。(如图四所示) g、起吊到位,检查四方防绳以及各部位安全后,操作人员方可上塔工作就位收紧螺丝,就位时注意脚钉方向和横担方向。(如图五所示) h、同样按(d)方法提升木抱杆;

钢管塔组立施工工艺

110KV竹园民官联线路工程 钢管塔组立施工工艺 批准: 审核: 编写: 桂林漓昇电力建设有限责任公司 2005年5月18日

钢管塔组立施工工艺 1、针对竹园民官联线路联湖线段钢管塔组立施工而编制; 2、本次施工采用吊车组立和人工组立方法进行施工; 吊车组立施工: 根据地形情况好坏可以选择分段吊装组立和整体吊装,由于吊车组立工序简单,本次钢管塔吊车组立施工不作详细介绍。 人工组立施工: (1)挖好地锚,地锚距离塔中心为大于塔全高,以保证防绳对地夹角小于等于45°; (2)起吊抱杆为15米以上口400钢抱杆,提升木抱杆9~12米,滑车为5T铁滑车,磨绳为一条200米Φ14钢丝绳,防绳为四条60米Φ16钢丝绳,机动绞磨一台,四把3T手扳葫芦; (3)人工组立施工步骤: a、立抱杆,打好四方防绳;布置好起吊滑车组和机动绞磨;(如图一所示) b、绑好起吊钢管塔第一段位置,起吊离地时,要进行冲击实验,检查四方防绳地锚,确无问题,方可起吊;起吊前注意脚钉方向和起吊绑套位置方向。 c、就位时注意脚钉方向和横担方向,特别是转角塔的方向。(如图二所示)

d、倒提升木抱杆注意四方防绳控制以及缆腰麻绳控制,此点是提升木抱杆的关键。固定木抱杆位置至少3米以上,绑固木抱杆要牢靠,收紧四方防绳要保持木抱杆的垂直状态。 e、用木抱杆提升钢抱杆,同样固定钢抱杆位置至少3米以上,固定前要先固定两块垫木,要保持钢抱杆处于垂直状态;钢抱杆底坐所绑钢丝套要紧固,缆腰钢丝套要收紧固定好;收紧四方防绳;将木抱杆拆除松至地面。(如图三所示) f、吊立第二段钢管时,起吊点位置最好在滑车组的垂直下方;起吊前注意脚钉方向和起吊绑套位置方向,绑好起吊点钢管塔第二段位置,起吊离地时,要进行冲击实验,检查四方防绳地锚,确无问题,方可起吊。(如图四所示) g、起吊到位,检查四方防绳以及各部位安全后,操作人员方可上塔工作就位收紧螺丝,就位时注意脚钉方向和横担方向。(如图五所示) h、同样按(d)方法提升木抱杆; i、同样按(e)方法提升钢抱杆; j、同样吊立第三段钢管塔时按(f)方法进行操作; k、同样按(g)方法进行操作; 以此类推,直至吊立安装完毕。以上方法未考虑其它因素影响;施工队在确保安全情况下施工时,要因地制宜,不要盲目施工;应该多看多想,最终完成施工任务。

角钢铁塔分解组立施工工艺

架空输电线路施工工艺库 工艺编号项目/工艺 名称 工艺要求施工工艺要点成品示例 020******* 杆塔组立工程020******* 杆塔分解组立 020******* 角钢铁塔 分解组立 (1)塔材、螺栓、脚钉及垫片等应有出 厂合格证。塔材无弯曲、脱锌、变形、错 孔、磨损。 (2)螺栓的螺纹不应进入剪切面。 (3)螺栓应逐个紧固,扭力矩符合规范 要求,且紧固力矩的上限不宜超过规定值 的20%。 (4)自立式转角塔、终端塔应组立在倾 斜平面的基础上,向受力反方向预倾斜, 预倾斜符合规定。 (5)片装吊装时应采取适当补强措施。 (6)不得强行安装。 (7)铁塔组立后,各相邻节点间主材弯 曲度不得超过1/800。 (8)每腿均设置接地孔,接地孔位置应 保证接地引下线联板顺利安装 (1)铁塔组装前应根据塔型结构图仔细地分段核 对塔材,对塔材进行外观检查,不符合规范要求的 塔材不得组装。 (2)角钢铁塔分解组立可采用座地抱杆、悬浮抱 杆等工器具,宜采用专用夹具安装抱杆承托绳、腰 箍拉线等。 (3)铁塔组立应有防止塔材变形、磨损的措施, 临时接地应连接可靠,每段安装完毕铁塔辅材、螺 栓应装齐,严禁强行组装。 (4)抱杆每次提升前,须将已组立塔段的横隔材 装齐,悬浮抱杆腰箍不得少于2道。 (5)吊片就位应先低后高,严禁强拉就位。 (6)塔身分片吊装,吊点应选在两侧主材节点 处,距塔片上段距离不大于该片的1/3,对于吊点 位置根开较大、辅材较弱的吊片应采取补强措施。 (7)防盗螺栓的防盗销应安装到位,扣紧螺母安 装齐全,防盗螺栓的防盗帽位置、开口方向应统 一。 (8)铁塔组立后,塔脚板应与基础面接触良好, 有空隙时应垫铁片,并应浇注水泥砂浆。铁塔经检 查合格后,可随即浇筑混凝土保护帽。 (9)脚钉弯头朝向向上,并应保持一致 020*******-T1角钢铁塔分解组立(一) 020*******-T2角钢铁塔分解组立(二)

混凝土杆及钢管塔组立施工四措概论

混凝土杆及钢管塔组立施工四措 批准: 审核: 编制: 编制单位: 编制时间:年月日

一、工程概况 二、组织措施 (一)施工现场组织机构 工程负责人:负责本工程的全部领导工作,为本工程的第一安全负责人。 技术负责人:负责本工程的技术及质量工作,保证工程质量达到合格标准。 安全负责人:协助班长做好安全按监督工作。 安全监督员:现场安全监督。 施工班组:随班民工已正式员工相同的职务和义务。 (二)任务分工 检修队:杆塔的安装。运行对:负责验收。汽车队:负责运输。 (三)施工的进度计划 根据XX局停电计划安排,综合各工序,确定工作时间。 三、技术措施 (一)输电线路施工执行技术标准 (1)GBJ233—1990《110~500kv架空电力线路是公共及验收规范》 (2)《架空送电线路检修工艺及质量标准》 (二)主要施工器具、材料(见表1~表2) 表1 组立杆塔工器具一览表

表2 材料一览表 (1)开工前,技术负责人组织现场工作人员认真学习本方案和《电业安装规程》有关部门及《架空送电线路检修工艺及质量标准》,并介绍工程情况,做好技术交底工作。 (2)工程处材料管理员参照施工措施和工程实际情况准备好工器具,并检查其状态、性能,保证其处于良好的工作状态;按照要求发放足够的工器具,并做好记录。 (3)各班组按工作任务准备相应的材料、工具准备好的材料和工器具应妥善存放,班组材料管理员负责。 (4)班组负责人按工程处的方案,合理安排本班组的人员分工和施工进度。 (5)汽车班负责热准备好吊车,保证其处于良好的共工作状态。 (6)施工前班组负责人员应现场了解设备及基础的实际情况,落实是公共设备布置场所,按照安规和现场工作实际需要检查安措是否完备,如有疑问向施工技术负责人反馈。 (四)施工现场布置 (1)现场设置隔离栏,施工工具、材料按规定摆放在帆布上(大型塔材除外),严禁随地乱放。 (2)施工现场物品摆放合理整齐,现场无多余的杂物。 (五)杆塔组装及混凝土杆焊接(见表3) 表3 杆塔组装及混凝土杆焊接

杆塔组立施工作业指导书

目录 1.工程概况 (1) 2.编制依据及说明 (3) 2.1编制依据 (3) 2.2施工说明 (3) 2.2.1线路方向及塔腿编号 (3) 2.2.2杆塔基础腿编号 (3) 3.工艺要求 (4) 3.1铁塔脚钉安装位置 (4) 3.2铁塔防盗、防松螺栓安装要求 (5) 3.3螺栓穿向规定 (5) 4.保护帽施工 (5) 5.质量及技术要求 (6) 6.材料装卸、运输及存放要求 (9) 7.内拉线悬浮抱杆分解立塔施工技术措施 (9) 悬浮抱杆施工布置图 (9) 7.1工作原理 (9) 7.2抱杆系统 (10) 7.3内悬浮抱杆立塔施工 (10) 7.3.1单插下部塔段 (10) 7.3.2起立抱杆 (10) 7.3.3上拉线安装 (11) 7.3.4提升抱杆 (11) 7.3.5抱杆的拆除 (12) 7.3.6吊装塔身 (12) 7.3.7直线塔横担吊装 (13) 7.3.8干字型转角塔横担吊装 (15) 8.安全及文明施工补充措施 (18) 9. 接地施工工艺要求 (18)

工程概况 1.西气东输三线管道工程西段古浪压气站110kV外电工程三标段 新建古浪330kV变~古浪压气站一、二回110kV架空线路(简称古气一二回)2X53公里。起点:古浪330kV变;落点:古浪压气站。额定电压:110kV; 本标段10包概况:工程A回从330kV古浪变出线自同塔双回AG0号塔,再到原有双回路塔AG1号塔右侧挂线;B回从330kV古浪变出线自同塔双回BG0号塔,再到原有双回路塔BG1号塔左侧挂线。 1)新建AG2至AG46+1终至,共计53基,其中转角塔18基;直线塔35基。 2)新建BG2至BG45终至,共计51基,其中转角塔19基;直线塔32基。 3)A回线路总长15.856千米;B回线路总长15.723千米;双回线路总长31.579千米。 2. 地质及地貌状况 ⑴沿线地貌单元大部分为低中山和山前洪积扇,局部为阶地,地层结构相对简单,无不良地质作用发育,工程地质条件较好,可以建线。 (2)本线路走径内,黄土、黄土状粉土为Ⅱ~Ⅳ级自重湿陷性场地,目前河流阶地及冲洪积扇地段(长约16.3km),具备上水条件,低中山地段不具备上水条件。 (3)沿线路黄羊川河阶地阶地(长约0.5km)地下水埋深3.0~5.0m,年变化幅度1.5m;民权乡阶地(长约1.5km)地下水埋深6.0~7.0m,年变化幅度1.5m;需采取相应的防、排水措施。其余地段地下水埋深均大于10m。 (4)依据《中国地震动参数区划图》判定,线路走径区地震基本烈度为8度,地震动峰值加速度,为0.30g。 (5)本地区冻土深度为138cm。 (6) 根据现场实地勘察并参考临近工程的建筑经验,线路沿线河流阶地及山前冲积扇地段地基土对混凝土结构、钢筋混凝土结构中的钢筋具有弱腐蚀性,对钢结构具有微腐蚀性;低中山区地基土对混凝土结构、钢筋混凝土结构中的钢筋及钢结构均具有微腐蚀性。 3.交通情况:全线交通条件一般。张家窝铺~民权乡西侧段(约10.0km)以及民权乡东侧~马家槽段(5.0km),交通条件相对较差。

钢管杆作业指导书

新村变~车河工业园10-35千伏线路工程钢管杆组立作业指导书 批准: 审核: 编写:李文辉 广西广能工程有限公司 河池供电局配网工程项目部 二0一一年六月

目录 No table of contents entries found. 1、工程概况及适用范围 工程简述 1.线路改造起于110kV新村变,南丹车河镇工业园区金山厂附近(将10kV龙马线23、24号开Ⅱ接入新双回10kV线路)。架空线路导线型号LGJ-240/30,全长为,四回杆塔设计,本期架设10kV、35kV线路各架设2回;电缆线路型号YJV22-3×300-26/35,全长2×;YJV22-3×15,全长2×。 2本工程使用的铁塔共使用10基型号分别为:JGUS1-12、JGUS1-15、JGUS3-12、JGUS3-15、JGUS3-18、ZGUS-15、ZGUS-20;钢管杆共使用10基

型号分别为:SGJ1-12、SGJ3-12、SGJ3-15、SGJZ-12;水泥杆共使用1基型号为:NJ1-15。 2、编写依据 序号引用资料名称 1 GBJ 50233-2005《110kV~500kV架空送电线路施工及验收规范》 2 GB 50017-2003《钢结构设计规范》 3 JGJ 82-1991《钢结构高强度螺栓连接的设计、施工及验收规范》 4 DL/T 875-2004《输电线路施工机具设计、试验基本要标》 5 DL 409-1991《电业安全工作规程电力线路部分》 6 DL 《电力建设安全工作规程第2部分:架空电力线路》 7 DL/T 5092-1999《110kV~500kV架空送电线路设计技术规程》 8 Q/CSG 《100kV~500kV送变电工程质量检验及评定标准第1部分:送电工程 9 《电网建设安全健康与环境管理办法实施细则(计[2004]27号)》 10 本工程的相关设计图纸 11 本工程的施工组织设计 12 本单位的质量管理体系、职业健康安全管理体系、环境管理体系的相关文件 13 现场调查情况 3、作业流程 3.1吊车吊装钢管杆作业(工序)流程图

最新整理钢管塔技术交底

最新整理钢管塔技术交底 20xx年11月25日下午在110KXX变进线(220kV线路部分)工程项目部召开了立塔工程安全技术会议。参加单位:XXXXXXXXXXXXXXXXXXX。纪要如下: 一、钢管塔组立注意事项: 1、抱杆四角浪风对地夹角不应大于45度,托根对地夹角不应大于30度,以确保施工安全。 2、采用抱杆起吊时,其根部应用千斤套和双钩锁根。 3、抱杆根部支立于软土质处时,其根部须垫防沉木。 4、起吊钢丝绳与铁件接触应垫软物,防止锌层破坏。 5、起立抱杆时,在1.2倍抱杆高度范围内不得有人。 6、钢管塔在分段起吊上部带横担段时,在其稍部与根部均需带控制绳进行控制,以使其横担不碰浪风,且帮助其就位。 7、所有吊点绳绑扎均采用单绳兜绳捆绑法,即将千斤套中间兜于主杆上,两头单头都挂于吊钩上(双绳受力)。 8、吊装说明中,重心位置均从该段下法兰向上法兰量起。 9、抱杆座落点使用的抱杆需要安装牢固,上下段对接法兰处的工作平台应安装牢固。 二、质量要求 严格执行《110-500kV架空电力线路施工及验收规范》(GBJ20233- 20xx)、设计图纸、施工图会审会议纪要等。 1、钢管塔组立后应全面复紧横担及法兰连接等处的螺栓,其扭矩值应符合《规范》要求。 2、钢管塔在组立结束后地脚螺栓的丝扣须打毛,防止被盗。

3、吊装前必须检查法兰面是否平整,清除毛刺,以保证对接后接触面良好。 4、吊立后的塔身,整体偏斜度应满足《规范》要求,做好施工记录。 5、螺栓应与构件垂直,螺头平面与构件间不得有空隙。螺栓紧固以后,露出的丝扣长度为:单螺母不应少于两个螺距;双螺母允许与螺杆平齐。对加装扣紧螺母等螺栓单帽螺栓出牙不应少于三个螺距。加垫片处每端不超过两个垫片。 6、滑牙和棱角的螺栓应予跟换。 三、安全健康和环境管理要求 为了确保铁塔组立的安全施工,贯彻执行“安全第一、预防为主”的安全生产方针。铁塔组立时需注意以下安全事项: 1、认证学习并严格执行《电力建设安全工作规程》(DL5009.2-20xx)、《电业安全工作规程》(DL409-91)、《电力建设安全健康与环境管理工作规定》以及国家和上级部门对安全生产方面的规定。 2、钢管塔运输需确保安全和快捷。搬运材料时应注意四周是否有人,两人以上搬运时应同肩同起同落;组装人员应戴手套,不得将手指伸入螺孔内找正;传递工器具和材料不得抛扔;组装和起吊在同处进行时,起吊件下方不得有人,如因地形限制应待构件就位后再进行组装。 3、施工人员进入施工现场必须正确佩戴安全帽。登高作业人员必须正确使用安全带及安全绳,安全带应挂在法兰加劲板凳孔上。高处作业所用的连接螺栓,工具等应放在工具袋内,上下传递物品应使用吊绳,严禁高空抛物。非施工人员不得进入施工现场。 4、施工现场除必要的工作人员外,其他人员应离开塔高1.2倍的范围以外,任何人不得在受力钢丝绳内测逗留。 5、工器具应符合技术检验标准要求,并附有许用荷载标志;使用前必须进行外观检查,不合格者不得使用,并不得以小代大。

10kV铁塔(钢管塔)组立标准化作业指导书

PP Q/GDW 10kV铁塔(钢管塔)组立 标准化作业指导书 江苏省电力公司发布

Q/GDW-10-338-2007 目次 前言.................................................................................................................................................... II 1 范围 (1) 2 引用文件 (1) 3 人员要求 (1) 4危险点预控 (2) 5工器具及耗材准备 (2) 6作业流程图 (3) 7 施工工序及技术要求 (4) 8 施工报告 (7) 附录A (规范性附录)10kV铁塔(钢管塔)组立现场标准化作业指导书(范本) (8) I

Q/GDW-10-338-2007 II 前言 本标准是根据国家电网公司《关于在县供电企业全面开展现场标准化作业工作的指导意见》的有 关要求,结合江苏省电力公司的实际情况而制定。本标准是同时编制的9个标准化作业指导书之一,这9个标准化作业指导书分别是: 10kV架空线路全线检修标准化作业指导书 10kV电缆线路全线检修标准化作业指导书 400V线路导线架设(更换)标准化作业指导书 10kV铁塔(钢管塔)组立标准化作业指导书 10kV单相配电变压器安装标准化作业指导书 10kV线路环网柜安装(更换)标准化作业指导书 10kV交联电缆敷设(更换)标准化作业指导书 10kV电缆分支箱更换标准化作业指导书 10kV带电T接用户标准化作业指导书 本标准的编写格式和规则符合GB/T 1.1《标准化工作导则第1部分:标准的结构和编写规则》及DL/T 600-2001《电力行业标准编写基本规定》的要求。 本标准附录A为规范性附录。 本标准由江苏省电力公司生产技术部提出并解释。 本标准由江苏省电力公司生产技术部归口。 本标准起草单位:江苏省电力公司生产技术部、淮安供电公司。 本标准主要起草人:王洪波、潘朝贤、许明生、刘华

杆塔组立作业指导书

目录 一、引用标准及编制依据 (2) 二、适用范围 (2) 三、工程概况 (2) 四、作业工序流程 (3) 五、作业准备及条件 (4) 六、杆塔组立作业要求 (5) 七、工程本体材料 (8) 八、杆塔组立 (9) 九、安全职业健康保证措施 (12) 十、文明施工及环境保护 (14) 十一、作业人员的职责及权限 (15) 十二、杆塔组立工序的安全责任制 (15)

一、引用标准及编制依据 《110~500kV架空电力线路施工及验收规范》(GBJ233—50233-2005) 《110~500kV架空电力线路工程质量及评定规程》 《高压架空输电线路施工技术手册》(杆塔组立部分) 《电力建设安全工作规程》(架空电力线路部分)(DL 500922—94) 110kV大黑山一期线路工程设计文件 注:施工过程中如有设计变更,变更部分以《设计变更通知单》为准。 二、适用范围 2.1本标准适用于110kV大黑山一期线路工程杆塔组立分部工程的施工。本标准有效日期为发布之日起至工程竣工为止。 2.2本标准规定了杆塔组立的施工工艺和方法,明确了施工时的安全、质量注意事项、文明施工及环境保护的要求。 三、工程概况 3.1线路概况 1、本工程为110kV大黑山一期线路工程,起点为110kV骑马坝电站,终点为110kV 绿春变,全线为单回路架设,线路长度为40.115km。 2、本工程全线新建各型杆塔90基,其中直线塔为49基,转角或承力塔41基。 3、本线路导线采用LGJ-240/30钢芯铝绞线,一根地线采用GJX-50稀土铝合金镀层钢绞线,另一根地线采用的12芯OPGW光缆,全线采用LXP-70钢化玻璃绝缘子,钢材总计80.402吨,混凝土总计838.574立方米。 4、基础钢筋混凝土标号为C20,保护帽的混凝土标号为C10。 3.2 杆塔型号及数量 杆塔 90基,直线塔49基;承力塔41基,铁塔具体使用明细见下表:直线塔49基

钢管塔吊装组立施工方案及措施

外部供电工程潭松~金川双回路220kV线路工程 钢 管 塔 吊 装 组 立 施 工 方 案 及 措 施 批准: 审核: 编写: 外部供电工程潭松~金川双回路220kV线路工程项目部 2013年03月21日 我公司承建的外部供电工程潭松至金川双回路220kV线路工程,全线采用55基钢管铁塔,单基钢管塔全重吨至吨不等,杆塔全高米至米不等,考虑到钢管塔高度计重量,决定采用分段起吊组装和整体吊装的方案。为保证施工安全迅速地组立钢管塔,特制定以下措施。 一、工程概况: 1、根据施工说明本工程分A线和B线,其中A线线路长度为,双分裂架设;B线线路长度为2×,双分裂架设,折合单回路总长度为。导线采用LGJ-500/45型钢芯铝绞

线,架空地线,A线采用两根24芯复合光缆;B线双回路段线路采用一根24芯复合光缆,另一根采用JLB40-120铝包钢绞线;B线四回路段一根采用24芯复合光缆,另外一根留给同杆架设的110kV线路架设一根A线共用双回路杆塔27基,其中其中耐张杆8基,直线杆19基;B线共用双回路杆塔21基,四回路杆塔7基,其中双回路耐张杆塔10基,双回路直线杆塔11基,四回路耐张杆塔3基,四回路直线杆塔4基。工程总计55基钢管塔,共计重吨。 2、钢管塔交通运输情况: 本线路杆塔全部在在建规划路上,全线地形平坦,交通便利。 3、危险点情况及对应措施: 1)、由于钢管塔施工现场过往行人车辆过多,因此需在赤沙中路与玉石滩大道交叉路口上设置专人监护并设立安全警示牌如:前方施工车辆绕行等。 2)、在起吊钢管塔前应进行试吊作业,在每一段钢管塔起吊约10cm时应暂停,检查制动装置,确认完好后方可继续起吊。 4、施工时间及要求: 施工队定于2013年03月22日至03月31日进行钢管塔组立工作,进行组立钢管塔前,施工项目经理部应组织施工员及聘用的专业起吊人员一同进行安全技术交底,明确任务、职责。 二、施工组织机构:(见下页)