PMP第六版作业-相关方管理

相关方管理

1、The project’s chief architect and the key client representative cannot cooperation on the project this adversely impact the project’s progress.

How should the project manager address this issue?

A.Appoint a senior employee to act as an architect between the architect and the client representative.

B.Request the chief architect’s the sponsor to discuss the with the architect.

C.How a discussion with the sponsor to replace the key client representative.

D.Address the chief architect and client representative in common to identity possible solutions 项目的总建筑师和关键业主代表不能在项目中合作:这对项目进度带来不利影响。

项目经理应该如何解决这个问题?

A.一名高级员工作为建筑师和业主代表之间的仲裁人

B.要求总建筑师的一线经理与该建筑师讨论这个问题

C.与项目发起人协商更换关键业主代表

D.找出总建筑师和业主代表的共同利益,确定可能的解决方案

2、一家公司决定开发一个软件解决方案,后来却发现不是所有的需求都就绪,且不同相关方对解决方案的看法不同。

应实施哪一个执行过程来改善这种情况?

A.管理相关方参与

B.收集要求

C.定义范围

D.识别相关方

3、The project manager experiences difficulties working with the customer.After the project is finished,the customer states that the project was nor completed to their satisfaction.What should the project manager have done throughout the project to avoid this outcome?

A.Advise the customer that their request are being implemented at each project phase

B.Understand,evaluate,define,and manage customer expectations

C.Send the customer the technical specifications for review and approval

D.Identify and replace responsible parties from the project team

项目经理在与客户合作过程中出现了困难,项目完成后,客户称项目没有达到他们的满意水平。若要避免这种结果,项目经理应该在整个项目过程中怎么做?

A.在项目的每一阶段告知客户他们的请求都已在执行

B.了解、评估、定义和管理客户期望

C.向客户发送技术规范,供客户审查和批准

D.识别并更换项目团队中的责任方

4、Your boss,the vice president of research at your electronic system development firm,defines success on the project as providing state-of-the-art development.The vice president of marketing defines it as world-class primarily.The vice president of engineering,who is the customer for this project,is primarily concerned with new features.

Which of the following BEST describes what should you do?

A.Make sure the requirements are defined in measurable terms.

B.Concentrate on new features

C.Identify additional stakeholders that want new features to shift the balance in that direction

D.Concentrate on making the project state-of-the-art

你的上司(你所在的电子系统开发公司的研发副总裁)把项目的成功定义为提供开发的最佳艺术。市场营销副总裁主要关注的是全球领先的产品。技术副总裁(他是这个项目的客户)主要关注的是新特性。下列哪项最恰当地描述了你所应做的?

A.确保要求被定义为可测量的条款

B.集中精力于新特性

C.确定需要新特性地额外项目相关方,以便朝那个方向平衡

D.集中精力把项目做成最新技术

5、一个复杂项目将在六个不同城市的15个商店中部署,项目发起人希望项目立即开始,项目经理接下来应该怎么做?

A.确定客户期望并排列有限顺序

B.访问所有城市,识别初步项目风险

C.确定团队运作原则

D.选择核心项目团队成员

6、Stakeholders can be identified in which project management process groups?

A.Initiating,planning,executing,monitoring and controlling,and closing

B.Initiating and planning

C.Planning and monitoring and controlling

D.Monitoring and controlling and closing

在哪个项目管理过程组中识别相关方?

A.启动、规划、执行、监控和收尾过程组

B.启动和规划过程组

C.规划和监控过程组

D.监控和收尾过程组

7、A project manager is initiating a new project.What is the main reason for identifying all stakeholders?

A.Identify costs and plan a budget

B.Understand expectations and maximize positive influence.

C.Plan communications and collect requirements

D.Plan quality and identify risks

项目经理正在启动一个新项目,识别所有相关方的主要原因是什么?

A.识别成本并计划预算

B.了解预期期望,并将正面影响最大化

C.计划沟通和收集需求

D.计划质量和识别风险

8、The senior management identifies the initial scope and high-level requirements of new warehouse management system.Which of the following must be ordered in initial process?

A.External and internal stakeholders need to be defined.

B.Project manager needs to approve the scope statement.

C.Project plan needs to be approved.

D.Financial budget needs final approval.

高级管理层识别了执行一个新仓库管理系统的初步范围和高层次需求。启动阶段需要下列哪一项?

A.需要定义外部和内部相关方。

B.项目经理需要批准项目范围说明书。

C.需要批准项目计划。

D.需要最终批准财务预算。

9、During a team meeting,the project’s chief architect opposes setting up the plant near agricultural land.Which of the following activities could have prevented this situation?

A.Stakeholder analysis

B Stakeholder manager

C.One-on-one meeting

https://www.360docs.net/doc/b016458932.html,rmation distribution

在团队会议中,项目的总设计师反对在农业用地附近建造工厂。下列哪一项活动可以避免这种情况发生?

A.项目相关方分析

B.项目相关方管理战略

C.与总设计师召开一对一会议

D.信息发布

10、In the initiation phase of your project,it is apparent that factions within the client's company have significantly different views on how the project should be structured and how the deliverables should be defined.Which of the following is the BEST thing to do?

A.Ask the client when they will be iii agreement on the project requirements.

B.Work with leadership from each area to collaboratively engineer a mutually acceptable solution.

C.Make sure the terms and conditions of the contract are clear.

D.List the consequences of changes in the contract's requirement section.

在项目的启动阶段,客户公司内部明显存在对项目应如何构建和如何定义可交付成果的不同观点。做下列哪项是最佳的?

A.问客户他们什么时候能对项目要求达成一致意见。

B.与各领域的领导合作,策划一个相互都可以接受的解决方案。

C.确保合同条款清楚。

D.在合同的要求部分列出变更的后果。

11、During the project’s initiation phase,the project manager meets with multiple resource manager and staff to review the project and obtain feedback。This is an example of which project management activity?

A.Project communication

B.Stakeholder analysis

C.Expectation management

D.Requirements gathering

在项目启动阶段,项目经理与多名资源经理和员工开会,一起审查项目并收集反馈。这属于哪一个项目管理的实例

A.项目沟通

B.相关方分析

C.期望管理

D.需求收集

12、Before seeking endorsement of the project plant,the project manager prepares a stakeholder analysis.Which of the following should the project manager identify?

A.Methods or technologies to be used convey the project plan

B.Level of participation for each identified stakeholder

C.Stakeholders according to their judgment and expertise

D.Roles,interests,expectations,and influence of the stakeholders

寻求项目计划获得批准之前,项目经理准备了一份相关方分析,项目经理应该识别下列那一项?

A.传达项目计划的方法或技术

B.每位识别的相关方参与度

C.根据判断和专业知识识别相关方

D.相关方的角色,兴趣,期望和影响

13、Company A completed a project to a client.However,it was not on the shortlist for a next https://www.360docs.net/doc/b016458932.html,pany A was sure that the relationship with the client was damaged during the previous project’s cooperation.What tools or techniques should the project manager of Company A use to maintain the relationship with client?

A.To collect feedbacks from the client to measure it’s satisfaction at the end of each phase

B.To contact the client to make sure why was it not on the shortlist

C.To create a quality management plan at the start of the project

D.To performed a risk assessment at the end of each phase

公司A向客户交付了一个项目。但是,在下一个项目中,客户没有将公司A列入合作名单中,公司A确定与客户的关系在上一个项目的执行过程中被破坏了。

公司A的项目经理应使用什么工具或技术来确保与客户保持良好的关系。

A.在每个阶段结束时通过收集客户的反馈测量客户的满意度

B.联系客户确定不在名单中的原因

C.在项目开始时创建质量管理计划

D.在每个阶段结束时执行风险评估

14、A task of a project that includes the customer staff resources will occur during a weekend. And the project manager realized that the resource manager rejected to pay the overtime three days before the weekend.So he must reschedule the tasks.Which of the following should the project manager do to avoid this issue?

A.put the payment for overtime in the project’s budget

B.Advise the customer about the importance to finish the task

C.Ask the customer’s staff to inform their human resources manager about the issue

D.identity all of the project stakeholders

一个项目将在周末进行,并包含客户的员工资源,在周末的前三天,项目经理得知资源经理拒绝为其员工支付加班费。因此,必须重新安排该任务的进度。为避免这个问题,项目经理应该事先完成下列哪一项?

A.将加班费包含在项目预算中

B.告知客户周末完成这项任务的重要性

C.让客户的员工将加班情况通知他们的人力资源经理

D.识别所有项目相关方

15、Initial acceptance testing begins on a system upgrade project that is on time and budget. Unexpectedly,the system receives low satisfaction ratings from the staff due terminology used in the system.What should do before test to avoid this happen?

A.Identify the most commonly used terminology by using Delphi research

B.Understand the organizational culture of the staff stakeholder communication Stakeholders process.

C.Submit a FAQ list to senior information technology managers

D.Create a process to familiarize the staff with industry standard terminology.

一个满足时间和预算要求的系统升级项目开始进行初步验收测试。出乎意料的是由于大量术语的运用,导致系统收到来自员工的低满意度评价。

为避免这种情况,应该事先执行什么工作?

A.通过使用德尔菲研究识别最常用的术语。

B.在识别相关方的过程中,了解员工相关方群体的组织文化。

C.向公司的高级信息技术管理层提交一份重要问题清单。

D.创建一个流程,让员工熟悉行业标准术语。

16、During the project initiation phase,the project manager becomes aware that the stakeholders may be influencing the project in multiple positive and negative ways.What should the project manager do in this situation?

A.Assign a task to top management and the project sponsor to reduce the number of stakeholders

B.Perform a stakeholder analysis and group the stakeholders by using a power/interest grid

C.Concentrate management actions on key stakeholders

D.Update the risk register

在项目启动阶段,项目经理得知相关方可能以多种积极和消极的方式影响项目。在这种情况下,项目经理应该怎么做?

A.给高级管理层和项目发起人分配任务,让其减少相关方的人数

B.执行一项相关方分析,并按照权利、利益方格给相关方分组

C.将管理行动集中在关键相关方上

D.更新风险登记册

17、In a project to upgrade a company’s accounting application,the project manager emails regarding the project’s status and the next activities.A key user of the application complains that application outages are affecting their work performance.What should the project manager do

next?

A.Continue working according to planned activities.

B.Report the key user to their supervisor.

C.Review the stakeholder analysis and update to include

D.Review the stakeholder analysis and inform all stakeholders to include the key users’emails.

在升级公司的会计应用程序项目中,项目经理每周发送一次有关项目状态以及后续活动的电子邮件。该应用程序的一位关键用户抱怨应用程序停用影响他们的工作绩效。项目经理接下来应该如何做?

A.按照计划活动继续工作。

B.向主管报告关键用户的情况。

C.审查相关方分析并更新包含该关键用户。

D.审查相关方分析并通知所有相关方将该关键用户包含在所有电子邮件中。

18、A human resources(HR)information system is completed according to the project’s specifications.After using the HR system for the first time the human resources manager states that old system project provided more information than new system,what should the project manager have done to prevent this situation?

A.defined a contingency plan

B.conducted an appropriate stakeholder analysis

C.create the work breakdown structure

D.initiated a change request

按照项目技术规范,人力资源(HR)信息系统已完成。在一次使用新HR系统后人力资源经理表示旧系统比新系统提供更多的信息。若要防止这种情况,项目经理应该做什么?

A.制定应急计划

B.运行适当的相关方分析

C.创建工作分析结构

D.提出一项变更请求

19、A new project manager compiles the stakeholder register for the process management and to review previous projects.Which of the following is a reference for the stakeholder.

A.Cross-functional flowchart that shows all steps in the process management

https://www.360docs.net/doc/b016458932.html,munications management plans within previous project record

C.Detailed charter of the new project

D.Customer survey data for the audit management process

为自动化审计管理流程以及审查之间项目的记录,新项目经理编制相关方登记册。项目经理应该使用下列哪一项作为相关方登记册的参考?

A.显示审计管理流程所有步骤的多职能流程图

B.之前项目记录中的沟通管理计划

C.新项目的详细章程

D.审计管理流程的客户调查数据

20、A project manager is working on a project to launch a new internet service.The project manager plan that this work is to be done by the support team.The support team does not want to be the work because they do not have the necessary expertise and claim that they have never

heard of the project.

What is the root cause of this problem?

https://www.360docs.net/doc/b016458932.html,munication plan was not used

B.Project manager did not involve all the stakeholders

C.Support team is not prepared to do task

D.Project manager did not identify lack-of-expertise risks.

某项目经理目前负责一个项目,旨在推出一项新的网络服务。项目经理计划让支持团队执行此项目工作。支持团队由于不具备必要的专业知识而不愿承担工作,并声称他们从未听说过该项目。

该问题的根本原因是什么?

A.未实施沟通计划

B.项目经理未能让所有相关方参与进来

C.支持团队不愿承担此项工作

D.项目经理未对缺乏专业知识的风险加以识别。

21、Individuals outside of the project are undermining major deliverables.What could the project manager have better developed to prevent this issue?

A.Scope statement

B.Work breakdown structure

C.Stakeholder management strategy

D.Project management plan

项目以外的个人破坏主要的可交付成果.若要预防这个问题,项目经理可以更好地制定下列哪一份文件?

A.范围说明书

B.工作分解结构

C.相关方管理策略

D.项目管理计划

22、One of your team members informs you that he does not know which of the many projects he is working on is the most important.Who should determine the priorities among projects in a company?

A.The project manager

B.The project management team

C.The project management office

D.The team

1、一团队成员告诉你,他不知道自己负责的项目中哪个最重要。公司中谁确定项目的优先级?

A、项目经理

B、项目管理团队

C、项目管理办公室

D、项目团队

23、A project is plagued by changes to the project charter.Who has the primary responsibility to decide if these changes are necessary?

A.The project manager

B.The project team

C.The sponsor

D.The stakeholders

9、一个项目因为项目章程的修改而难以进行下去。谁有权决定对项目章程的修改?

A、项目经理

B、项目团队

C、发起人

D、相关方

24、During project executing,a project manager from the information systems department is trying to complete the project,yet is constantly faced with interference from the manager of the engineering department.The engineering department keeps changing the resources assigned to the project team and their availability.What type of matrix does this represent?

A.Strong matrix

B.Weak matrix

C.Functional matrix

D.Tight matrix

10、在项目执行期间,来自于信息部门的项目经理负责完成项目,但工程部门的经理经常干涉到项目。工程部门经理经常改变放在项目上的资源。此项目处于哪种矩阵组织中?

A、强矩阵

B、弱矩阵

C、职能矩阵

D、紧密矩阵

25、Under a certain contract,a list of allowable costs is established for supplier reimbursement. The supplier is paid$102,000,of which$80,000is actual cost.The original cost estimate of the contract is$90,000and$20,000is incentive fee.The supplier gets a20%share of cost savings achieved.This is which of the following types of contracts?

A.Fixed-price incentive-fee

B.Cost-plus-fixed-fee

C.Fixed-price with economic price adjustment

D.Cost-plus-incentive-fee

5、在某种特定合同下,确定有可列支成本作为供应商的补偿。供应商已获得$102,000的支付款项。其中$80,000为实际成本。合同原始成本估算为$90,000,$20,000作为奖励酬金。对于实现成本节约,供应商获得其中的20%。

这属于下列哪一个合同类型?

A、固定总价加奖励费用合同

B、成本加固定费用合同

C、可按经济指数价格调整的固定总价合同

D、成本加激励费用合同

26、1.Which of the following is a tool of the Manage Stakeholder Engagement?

A.Expert judgment.

B.Interpersonal skills.

C.Meetings.

D.Information management systems.

1、下列哪一项是管理相关方期望的工具?

A.专家判断

B.人际关系技能

C.会议

D.信息管理系统

27、Which of the following is an output of the Plan Stakeholder Management? A.Stakeholder register.

B.Issue log.

C.Work performance information.

D.Stakeholder management plan.

2、下列哪一项是规划相关方管理的输出?

A.相关方登记册

B.问题日志

C.工作绩效信息

D.相关方管理计划

28、A major construction project has been having a lot of schedule changes due to unanticipated weather problems.Who is it BEST to notify of these changes?

A.Stakeholders.

B.Sponsor.

C.Project team.

D.Functional managers.

3、由于不可预料的天气原因,一个主要建设项目遇到了很多进度方面的变更。谁最应该知道这些变更信息?

A.相关方。

B.发起人。

C.项目团队。

D.职能经理。

29、A project manager is initiating a new project.What is the main reason for identifying all stakeholders?

A.Identify costs and plan a budget

B.Understand expectations and maximize positive influence.

C.Plan communications and collect requirements

D.Plan quality and identify risks

4、项目经理正在启动一个新项目,识别所有相关方的主要原因是什么?

A.识别成本并计划预算

B.了解预期期望,并将正面影响最大化

C.计划沟通和收集需求

D.计划质量和识别风险

30、Who determines the project scope requirements of a new project?

A.The customer.

B.The stakeholders.

C.The project manager.

D.Senior manager

谁确定新项目的项目范围需求?

A.客户。

B.项目相关方。

C.项目经理。

D.高层管理层。

31、A discretionary dependency is one that is based on:

A.Experience.

B.The needs of someone outside the project.

C.The nature of the work being done.

D.The needs of the project sponsor.

选择性依赖关系是基于以下哪项决定的?

A.经验。

B.项目外人员的需求。

C.工作的性质。

D.项目发起人的需求。

32、The communications management plan is developed to meet the needs of the:

A.Project sponsor.

B.Team.

C.Project manager.

D.Stakeholders.

沟通管理计划要满足谁的需求?

A.项目发起人。

B.团队。

C.项目经理。

D.相关方。

33、A new project manager is having difficulty creating a WBS with the team.To alleviate this situation,the project manager should ask for help from:

A.The sponsor.

B.Other project managers.

C.The project management office.

D.The team.

项目经理和团队在制定工作分解结构时遇到了困难,为了解决此问题,项目经理应该寻求谁的帮助?

A.发起人。

B.其他项目经理。

C.项目管理办公室。

D.团队。

34、Which of the following would be the MOST appropriate thing to do during the planning process group?

A.Determine high-level stakeholders.

B.Hold a meeting with all stakeholders to make sure everyone is on the same page. C.Implement approved process improvements.

D.Focus on preventing problems rather than dealing with them as they arise.

以下哪项在规划过程组完成?

A.确定高层级的相关方。

B.和所有相关方召开会议,以确保他们的意见一致。

C.实施批准的过程改进流程。

D.尽量避免问题的发生,而不是发生后再去解决。

35、A project is plagued by changes to the project charter.Who has the primary responsibility to decide of these changes are necessary?

A.Project manager.

B.Project team.

C.Project sponsor.

D.Stakeholder.

项目被项目章程的变更所困扰。确定这些变更是否必要是下述哪位主要负责?

A.项目经理。

B.项目团队。

C.项目发起人。

D.项目相关方。

36、Which of the following statements BEST describes how stakeholders are involved on a project?

A.They determine the project schedule,deliverables,and requirements.

B.They help to determine the project constraints and product deliverables.

C.They determine the resource needs and resource constraints on the project.

D.They help provide assumptions,the WBS,and the management plans.

相关方对项目的影响以下描述正确的是?

A.他们决定项目的进度、可交付成果及需求。

B.他们有助于确定项目的约束条件和产品可交付物。

C.他们决定项目的资源需求和资源制约因素。

D.他们有助于提供假设条件、工作分解结构和管理计划。

37、Who should be responsible for defining project objectives?

A.Project manager.

B.Sponsor.

C.Project management team.

D.Stakeholders.

由谁负责定义项目的目标?

A.项目经理。

B.发起人。

C.项目管理团队。

D.相关方。

38、The project has been going well,except for the number of changes being made.The project is being installed into seven different departments within the company and will greatly improve departmental performance when operational.There are14project management processes selected for use on this project.The project manager is a technical expert as well as having been trained in communications and managing people.Which of the following is the MOST likely cause of the project problems?

A.The project manager was not trained in understanding the company environment.

B.The project should have more management oversight since it will result in such great benefits to the company.

C.The project should have used more of the project management processes.

D.Some stakeholders were not identified.

除了几个变更之外,项目一切进展的很好。项目的成果将来要安装在公司内不同的七个部门,而且将会大大提高它们的运营绩效。项目使用14个管理过程。项目经理是一位技术专家,同时在沟通和管理人员方面也得到过很好的培训。以下哪项最有可能导致项目出现问题?

A.项目经理在理解公司环境方面没有得到培训。

B.由于项目将对公司带来极大益处,所以项目应该得到更多的监管。

C.项目应该采用更多的项目管理过程。

D.有些相关方没有识别出来。

39、The requirements of many stakeholders were not approved for inclusion in your project. Therefore,you had a difficult time receiving formal approval of the project management plan for this project.The stakeholders argued and held up the project while they held meeting after meeting about their requirements.The project was finally approved and work was began six months ago.All of the following would be good preventive actions to implement EXCEPT:

A.Keep a file of what requirements were not included in the project.

B.Make sure the change control process is not used as a vehicle to add back the requirements into the project.

C.Maintain an issue log.

D.Hold meetings with the stakeholders to go over the work that will not be added to the project.项目上很多相关方的需求没有得到批准,所以项目管理计划在得到正式批准上遇到了很大的困难。在他们的需求没有满足之前,他们开会争论并阻止项目开始。最终在六个月前,项目得到了正式批准并开始实施。在执行过程中以下均是有效的预防措施,除了:

A.将没有包含在项目中的需求记录在案。

B.确保变更控制流程没有阻碍相关方的需求被增加到项目上。

C.保留问题日志。

D.和相关方开会讨论将不会增加到项目上的工作。

40、Project manager issue reports on the amount of testing done throughout the life of the

project.However,Testing is only a minor aspect of the quality control plan.It would be BEST for the project manager to:

A.Issue the report,as this is a major stakeholder,her needs would have been included in the staffing management plan.

B.Not issue the report,project resources should be expended on communicating information that contributes to success.

C.Request details of the information the stakeholder needs in the report.Provide that information to those handling the quality control function on the project.

D.Have the stakeholder meet with the project sponsor to get the sponsor’s agreement that project funds should be expended on this effort.

项目的沟通管理计划已经完成,并得到了客户的批准。此时,一位主要相关方要求项目经理报告整个项目生命周期中的测试数量。然而,测试只是质量控制计划中不太重要的内容。项目经理的最佳做法是什么:

A.发布报告,因为她是一位主要的相关方,人员配备管理计划中要包括她的需求。

B.拒绝发布报告,项目资源应该使用在有助于项目成功的沟通信息上。

C.收集这位相关方所需的信息细节,然后将这些信息提供给项目上负责质量控制的人员。

D.让相关方和发起人见面,以征得发起人同意将项目费用使用在这项内容上。

41、A particular stakeholder has a reputation for making many changes on projects.What is the BEST approach a project manager can take at the beginning of the project to manage this situation:

A.Say No to the stakeholder a few times to dissuade him from submitting more changes.

B.Get the stakeholder involved in the project as early as possible.

C.Talk to the stakeholder's boss to find ways to direct the stakeholder's activities to another project.

D.Ask that the stakeholder not be included in the stakeholder listing.

一位相关方以变更闻名。在项目初始阶段,项目经理应该怎样做才能更好的管理此相关方:

A.当他提及变更时,拒绝他。

B.让他尽早参与项目。

C.与他的老板谈谈,让他接触另外一个项目。

D.将他从相关方登记册中删除。

42、The project has been challenging to manage.Everyone has been on edge due to pressure to complete the project on time.Unfortunately the tension has grown to the point where team meetings have become shouting matches and little work is accomplished during the meetings. One team member asks to be excused from future team meetings,as all the shouting upsets him. Meanwhile,the sponsor has expressed interest in attending future team meeting in order to better understand how the project is going and the issues involved in completing the project,and the customer has started discussions about adding scope to the project.In this situation,it would be BEST for the project manager to:

A.Ask the sponsor if the information needed could be sent in a report rather than have her attend the meetings.

https://www.360docs.net/doc/b016458932.html,rm the team member who asked to be excused from the meetings of value of communication in such meetings.

C.Create new ground rules for the meetings and introduce them to the team.

D.Hold a team-building exercise that involves all the team members.

项目对管理来说十分具有挑战性。由于要按时完成项目的压力,每个人都很紧张。不幸的是,紧张已经提升到了一定的点,团队会议变成了大吼大叫的比赛,会议中几乎没有完成什么工作。一名团队成员希望退出以后的团队会议,因为那些争吵令他很困扰。同时,发起人对参加以后的团队会议表示很感兴趣,以便更好的了解项目的执行情况和以往工作中碰到的问题。并且,客户已经开始讨论增加项目的范围。在这种情况下,项目经理最好应该:

A.询问发起人是否可以把必要的信息写到报告中,而非让她参加会议。

B.告知那位要求不参加会议的成员,这种会议沟通的价值。

C.制定一些新的会议规则,并且将他们引入到团队之中。

D.进行一次全员参加的团队建设活动。

43、Effective managing stakeholder expectations include the following except

A.timely status information

B.frequent cost reports

C.scope change control

D.clearly requirement control

有效的项目相关方管理包括下列内容,除了

A.定期的状态信息

B.频繁的费用报告

C.范围变更控制

D.清晰的需求控制

44、In dealing with the customer,the project manager should_______.

A.be honest to the extent that the project organization is prompted from litigation

B.strive to develop a friendly9honest and open relationship

C.try to maximize profits by encouraging scope creep

D.do whatever it takes to satisfy the customer and win additional business

在处理有关客户的问题上,项目经理应该______。

A.对公众诚实,以面对来自诉讼的质询

B.努力建立一种友好的、诚实的和开放的关系

C.通过扩展范围使收益最大化

D.为满足客户可以做任何事,并以此赢得更多的生意

45、The project status meeting is not going well.Many attendees are talking at the same time,there are people who are not participating,and many topics are being discussed at random. Which of the following rulers for effective meetings is NOT being adhered to?

A.Demonstrate courtesy and consideration of each other,and control who is allowed to speak.

B.Schedule meetings in advance.

C.Have a purpose for the meeting,with the right people in attendance.

D.Create and publish an agenda and a set of rules for controlling the meeting.

项目状态会议进展的并不是很好。很多与会者都同时在讨论,也有人没有参加会议,很多话题的讨论都很随意。下面哪项有效会议的准则没有被遵守?

A.表明对彼此的礼节和尊重,控制谁可以发言。

B.把会议提前。

C.为会议设定一个主题,和适当的出席人员。

D.创建和公布一个议程,以及一套规则,来控制会议。

46、One of the engineers in your team performs a presentation to a perspective client about a proposed design.In answering questions,the engineer reveals that she does not agree with the way in which this system is engineered during the presentation.What are your opinions as project manager of the engineer listening to the presentation?

A.Immediately stop the engineer and do damage control.

B.Ask the engineer to explain the discrepancy and what recommendation she can offer.

https://www.360docs.net/doc/b016458932.html,municate an openness to the problem and lead a discussion to resolve the issues.

D.Rephrase the problem to ensure that everyone understands the various major points,and solicit input form everyone.

你的项目团队中的一位工程师为一个潜在客户介绍设计建议书。在回答问题时,工程师表示她不同意建议书中的系统构建方式。你作为这个工程师的项目经理,在听了这个介绍后如何反应?

A.立刻打断这位工程师,并对损失进行控制。

B.让这位工程师解释其中的区别,并提出她的意见。

C.公开这个问题,并组织一个讨论来解决这个问题。

D.重新描述一下问题以保证每个人都理解了各个重点,并请每个人提出意见。

47、The project manager is working to clearly describe the level of involvement expected from everyone involved in the project in order to prevent rework,conflict and coordination problems. Which of the following best describes the project manager’s efforts?

A.Integration management,control,communications planning.

B.Smoothing,control,goodwill,gold plating.

C.Validate,Scope,quality,control,execution.

D.Risk assessment,scheduling,lessons learned,stakeholder management.

项目经理正在致力于明确描述参与项目的每个人的预期参与程度,以便防止返工、冲突和协调问题。下列哪项可以最恰当地描述项目经理的工作?

A.综合管理、控制、沟通。

B.缓和、控制、商誉、镀金。

C.确认范围、质量控制、执行。

D.风险评估、进度制定、经验教训、项目相关方的管理。

48、Which of the following statements BEST describes how stakeholders are involved on a project?

A.They determine the project schedule,deliverables,and requirements.

B.hey help to determine the project constraints and product deliverables.

C.They determine the resource needs and resource constraints on the project.

D.They help provide assumptions,the WBS,and the management plans.

下列哪个陈述最恰当地描述了相关方如何参与一个项目?

A.他们确定项目进度可交付成果和要求。

B.他们帮助确定项目制约因素和产品可交付成果。

C.他们决定项目中的资源需求和资源制约因素。

D.他们帮助提出假设WBS和管理计划。

49、All of the following are parts of the team’s stakeholder management effort

以下不属于团队的相关方管理工作部分的是

A.给相关方额外费用。

B.识别相关方。

C.确定相关方的需求。

D.管理相关方的期望。

50、A project manager wants to more extensively involve the stakeholders on the project.Which of the following would be the BEST way to accomplish this?

A.Have the stakeholders periodically review the list of project requirements.

B.Invite the stakeholders to attend project status meetings.

C.Send status report to the stakeholders.

D.Update the stakeholders on the status of all project changes.

一名项目经理想要相关方更加广泛地参加到这个项目当中。下列哪一种方法可以最好地完成这项任务?

A.让相关方定期回顾项目需求列表。

B.邀请相关方参加项目状态会议。

C.向相关方发送状态报告。

D.更新所有项目变更状况中的相关方。

51、The requirements of many stakeholders were not approved for inclusion in your project. Therefore,you had a difficult time receiving formal approval of the project management plan. The stakeholders argued and held up the project while they held meeting after meeting about their requirements.The project was finally approved and work began six months ago.All of the following would be good preventive actions to implement except_.

A.Keep a file of what requirements were not included in the project.

B.Make sure the change control process is not used as a vehicle to add the requirements back into the project.

C.Maintain an issue log.

D.Hold meetings with the stakeholders to go over the work that will not be added to the project.很多相关方要求在你的项目中没有被通过。因此,你很难获得项目管理计划的正式批准。在开了一个又一个关于他们要求的会议之后,相关方争论并且发起一个项目。项目最终被批准了,并且在六个月之前已经开始了。以下除了_____都是可以实行的好的预防措施。

A.记录一份文档,哪些要求不包含在项目中。

B.确保变更控制流程不被用作给项目添加要求的工具。

C.维护问题日志。

D.与相关方举办会议来重温一下不会被添加到项目中的工作。

52、When do stakeholders have the MOST influence on a project?

A.At the beginning of the project.

B.In the middle of the project.

C.At the end of the project.

D.Throughout the project.

什么时候相关方对项目最有影响?

A.在项目的初期。

B.在项目的中期。

C.在项目的末尾。

D.在整个项目过程中。

53、The project has been going well,except for the number of changes being made.The project is being installed into seven different departments within the company and will greatly improve departmental performance when operational.The team has selected the appropriate processes for use on the project.The project manager is a technical expert as well as having been trained in communications and managing people.Which of the following is the MOST likely cause of the project problems?

A.The project manager was not trained in understanding the company environment.

B.The project should have more management oversight since it will result in such great benefits to the company.

C.The project should have used more of the project management processes.

D.some stakeholders were not identified.

项目进展的很顺利,除了做了一些变更。项目被应用到公司内部不同的七个部门中,并且将会大大提升营运中部门的表现。团队已经选择了合适的过程在项目中使用。项目经理是一名技术专家,并且在沟通和管理人员方面接受过培训。下面哪一个最有可能是造成项目问题的原因?

A.项目经理没有接受过理解公司环境的训练。

B.项目经理在管理方面应该更有远见,能够为公司创造更大的利益。

C.项目应该运用更多的项目管理过程。

D.—些相关方没有识别出来。

54、A particular stakeholder has a reputation for making many changes on projects.What is the BEST approach a project manager can take at the beginning of the project to manage this situation?

A.Say No to the stakeholder a few times to dissuade him from submitting more changes.

B.Get the stakeholder involved in the project as early as possible.

C.Talk to the stakeholder’s boss to find ways of directing the stakeholder’s activities to another project.

D.Ask that the stakeholder not be included in the stakeholder list.

一位相关方因喜欢变更而出名。哪一个方法是项目经理在项目开头处理这个情况的最好方法?

A.多次对那位相关方说不来防止他提出更多的变更。

B.让那位相关方尽早地参与到项目之中。

C.和那位相关方的老板谈话,寻找方法使相关方的活动转向另一个项目。

D.让那位相关方不要包括在相关方的名单之内。

55、Effective stakeholder management includes all of the following project elements except_.

A.clear requirements definition.

B.scope change control.

C.timely status information.

D.frequent cost reports.

有效的相关方管理包括以下的全部内容,除了_______。

A.明确的需求定义

B.范围变更控制

C.及时的进度报告信息

D.经常的成本支出报告

56、Stakeholders can be identified in which project management process groups?

A.Initiating,planning,executing,monitoring and controlling,and closing.

B.Initiating and planning.

C.Planning and monitoring and controlling.

D.Monitoring and controlling and closing.

在项目的哪个过程组识别相关方?

A.启动/规划/执行/监控和收尾。

B.启动和规划。

C.规划和监控。

D.监控和收尾。

57、Which of the following BEST describes stakeholders?

A.People who may have a positive or negative influence on project.

B.End users.

C.Sponsor and the team.

D.The public.

以下对相关方的描述,哪项最准确?

A.对项目会有积极或消极影响的人。

B.终端用户。

C.发起人和团队成员。

D.公众。

58、You have been assigned to manage the development of an organization,s first Web site.The site will be highly complex and interactive,and neither your project team nor the client has much experience with Web site development.The timeline is extremely aggressive.Any delay will be costly for both your firm and the client.You have a project sponsor and have achieved agreement and sign-off on both the project charter and the project management plan.Client personnel have been kept fully informed of the project’s progress through status reports and regular meetings. The project is on schedule and within budget,and a final perfunctory review has been scheduled. Suddenly you hear that the entire effort may be cancelled because the product developed is totally unacceptable.What is the MOST likely cause of this situation?

A.A key stakeholder was not adequately involved in the project.

B.The project charter and project management plan were not thoroughly explained or adequately reviewed by the client.

https://www.360docs.net/doc/b016458932.html,munications arrangements were inadequate and did not provide required information to interested parties.

D.The project sponsor failed to provide adequate support for the project.

你被委派去管理一个组织的第一个网站的开发。这个网站非常复杂并且是交互性的,你的项目组和客户都没有什么关于网站开发的经验。时间表是极其紧张的,任何延迟对于你的公司和客户都是代价高昂的。你有一个项目发起人,而且项目章程和项目管理计划都已经达成协议并得到了签署。通过状态报告和定期会议,客户的人员保持着对项目进展的完全了解。项目在预算内按原进度进行,已经安排了最终的例行评审。突然你得知所有努力都可能白费了,因为开发的产品完全不能被接受。什么是这一处境出现的最可能原因?

A.—个关键的项目相关方没有充分的参与这个项目。

B.项目章程和项目管理计划没有被客户彻底解释或充分评审。

C.沟通协议是不充分的而且没有提供必要的信息给感兴趣的各方。

D.项目出资人没有给项目提供足够的支持。

59、The primary communication skills you will use in working with externalstakeholders will be_.

A.problem solving

B.negotiating

C.team building

D.public relations

你在与外部项目利害关系者一起工作时将使用的主要的沟通技能是

A.问题解决

B.谈判

C.团队建设

D.公关

60、You are the project manager for a new system project.Management wants your project to yield high-value results at a low cost.Although,you would like to take the time and money to incorporate features that would increase long-term project value,one of your major programming sellers employs senior-lever staff that typically cost more than other vendors. When working with stakeholders,you should______.

A.group stakeholders into categories for easy identification

B.proactively curtail stakeholders activities that might affect the project adversely

C.the interests of the stakeholder are often interwoven and the stakeholder management are often in great difficulties

D.recognize that the roles and responsibilities may overlap

你是一个项目经理,负责完成一个新的计算机系统。管理层希望项目能在低成本的情况下实现高收益。你希望能够将时间成本和产品的功能很好地结合起来,这样从长远角度来看是增加了项目的价值。但是,项目的一个承包商雇佣了高级的编程员,这使得该承包商比其他几个承包商的成本高。当与相关方一起工作时,你应该______。

A.把相关方分成容易识别的几类

B.对于那些会给项目带来反面影响的相关方,提早对其行为进行干预

C.要认识到不同的相关方往往持有不同的目标,而这也使得相关方的管理工作非常闲难

D.认识到角色和责任可能会出现重叠

61、You are eating lunch with a group of business professionals from New England.Everyone has ordered soup as an appetizer.As you begin to eat,you hear a sound that you find quite irritating:10people are slurping soup at the same time.People in your country simply do not eat this way. You are taught eat silently.Yet as you sit,you realize that your business partners have been taught in a much different manner than you were.You say to yourself,here is my first confrontation with cultural differences.Then you begin slurping as well.You have put aside your personal prejudices and have moved on to the next step which is to_.

A.integrate others’worlds into your own

B.look globally for new ideas

C.be open to change

D.understand and value others

你和一群来自英格兰的商业伙伴共进午餐。所有人都点了汤作为开胃菜。在你开始喝汤时,你听见10个人同时大声地喝汤,感到很不舒服。因为你们国家的人从来不这样喝汤,你们习惯于安静地进食。然而当你坐下,你发现你的生意伙伴的吃饭习惯和你的完全不同。你对自己说:这是我第一次面对文化差异的问题。接着你也开始大声地喝汤。你已经放下个人的偏见并向前走了一步,这步是____

A.把别人的世界统一到你的世界中

B.以宏观的角度寻找新的观点

C.以开发的态度对待变更

D.理解并尊重别人

62、While staffing a project in another country,the project leader from that country comes to you with a suggested team consisting of members of the project leader’s family.Your FIRST course of action should be to_.

A.inquire if hiring only through family lines is common practice in the project leader’s country

B.review the resumes of the individuals to see if they are qualified

C.ask the project leader to provide additional names of people unrelated to him/her

https://www.360docs.net/doc/b016458932.html,e a different project leader to prevent problems later in the project

在其他国家配备一个项目时,你发现那个国家的项目由项目领导和他的很多家庭成员组成,你第一个要采取的行动应该是________。

A.询问一下在这个项目领导人的国家,通过家庭关系进行雇佣是否是一个常见的行为

B.回顾一下每个人的简历,看他们是否合格

C.要求项目经理提供额外的和他/她不相干的人名

D.使用一名别的项目领导人,以防今后在项目中出现问题

63、After the kickoff meeting,two team members engage in a casual conversation about the project objectives and deliverables.It is clear they heard different messages during the meeting. One member is so adamant that the other member gives up arguing the point.After talking to the project manager,the second member confirms that the first member is mistaken.At this point,what is the best course of action?

A.The second team member should send the other team member an E-mail describing what he discovered.

B.At the next project meeting,the team member should ask the mistaken team member to describe his interpretation so the project manager can get everyone on the same page.

项目管理九大知识体系和五大阶段

驱动21世纪新型商务企业发展的原动力是什么?有人答曰:项目管理。的确,项目管理作为一门新兴的学科,发展之快已超过了我们的想象。美国Fortune杂志甚至预言,项目经理将是21世纪的首选职业。让我们共同走近项目管理。 “金字塔工程”到“北极星导弹计划” 论起项目管理的起源,其实很早。古代诸如金字塔、长城等著名的伟大工程项目的成功,都得助于当时对工程项目进行的严密和科学的管理。20世纪60年代初,在著名数学家华罗庚教授的倡导下,将项目管理的概念引入了我国,并在当时的国民经济各个部门进行试点应用,将这种方法命名为“统筹法”。之后,中国科学院管理科学与科技政策研究所,还牵头成立了“中国统筹法、优选法与经济数学研究会”。改革开放后,项目管理在水利、建筑、化工等领域开始被大量地应用起来。2000年底,联想在“天麒”、“天麟”两款计算机产品的开发过程中,结合业务对项目管理的需求,配合项目管理相关理论、方法编制软件方案,使该项目在8个月的时间内便全部完成,并达到了国际上PC生产技术的最高水平。 现代项目管理的概念起源于美国。上个世纪五十年代后期,美国的Booz-Allen Lockheed 公司首次在北极星导弹计划中运用了PERT技术。同一时期,美国的Dupont and RamintonnRand公司创造了CPM方法,用于研究和开发、生产控制和计划编排,结果大大缩短了完成预定任务的时间,之后它们分别被称为“计划评审技术”和“关键路径法”。现代项目管理科学便是从这两项技术的基础上迅速发展起来的,融合了后来发展起来的WBS工作分解技术、蒙特卡罗(Monte Carlo)模拟技术和EV挣值分析技术,形成了一门关于项目资金、时间、人力等资源控制的管理科学。著名的阿波罗登月计划、曼哈顿计划等都是采用项目管理的理论和方法而取得成功的经典案例。 9大知识体系与5个具体阶段 早期的项目管理主要关注的是成本、进度(时间),后来又扩展到质量。最近十几年间,项目管理逐渐发展成为一个涵盖9大知识体系、5个具体阶段的单独的学科分支。9大知识体系包括: ·集成管理在项目分析中,项目管理人员必须把各种能力综合起来并加以协调利用。 ·范围管理定义项目的边界,着眼于“大画面”的事物。例如项目的生命周期、工作分工结构的开发、管理流程变动的实施等。 ·时间管理要求培养规划技巧。有经验的项目管理人员应该知道,当项目出现偏离规划时,如何让它重回规划。 ·成本管理要求项目管理人员培养经营技巧,处理诸如成本估计、计划预算、成本控制、资本预算以及基本财务结算等事务。 ·人力资源管理着重于人员的管理能力,包括冲突的处理、对职员工作动力的促进、高效率的组织结构规划、团队工作和团队形成以及人际关系技巧。 ·风险管理需要管理人员在信息不完备的情况下作决定。风险管理模式通常由三个步

软件项目管理大作业

软件项目管理大作业 软件项目购销合同 本合同由下述双方签署: 甲方: 联系电话: 乙方: 联系电话: 根据《中华人民共和国合同法》及其他有关规定,甲乙双方在平等、自愿、公开、

诚实信用的基础上就XXXXXX储蓄软件项目事宜,经甲乙双方友好协商如下: 第一条储蓄软件项目实施所需的条件(人工及人工费由甲方负责,但技术和质量全部由乙方负责),所进行项目开发所需的事宜明细见附件,附件与本合同不可分割,具有同等法律效力。 第二条产品交付甲方验收前所有质量问题由乙方负责,当交付甲方验收合格后,所有利害由甲方负责。 第三条交货方式双方见面交易。合同为证。 第四条交货时间为2014年9月17日,交货地点xxx。对于产品的数量、质 量等问题,全部由乙方负责。 第五条合约执行内容 经甲乙双方协商约定,整个软件项目设计由乙方提供专业人员和技术进行开发,甲方不用参与,按照乙方技术进行开发且监工由乙方负责,开发完成后,应达到国家验收标准,当与国家标准发生冲突时,按国家标准执行,测试达到标准后,视为乙方工程全部验收合格。如未达到验收标准时,所人工费由乙方负责承担,如能补救,由乙方尽快全部负责,直至达到验收标准。 第六条补充说明 乙方计算的全部材料已全部包含软件项目的全部,甲方不再支付任何费用,经乙方设计与预算得出以上内容与附件包含的内容外,不再有任何增项费用,如有乙方全部承担。 第七条双方职责 1、甲方职责 甲方负责协调乙方与同期作业的其他工程之间的关系(作业时间、作业面等)。 2、乙方职责 (1)乙方负责交付工程的可靠性、安全性,如因未按规定施工造成甲方工期延误、财产损害等严重问题,一切责任由乙方承担。

西南大学-工程项目管理-2015作业答案

1:[多选题]建设项目进度控制的目标是实现建设项目按计划的时间投入使用,因此,对建设项目的进度必 A:设计、招标、施工和竣工验收及保修各阶段的进度 B:项目组成所有部分的进度 C:与项目建设有关的所有工作的进度 D:影响进度的所有因素 E:投资、进度、质量三大目标 参考答案:ABCD 2:[单选题]确定项目经理和进度控制、质量控制等主管工作部门或主管人员的工作任务分工应采用( )。 A:组织结构模式 B:任务分工表 C:职能分工表 D:工作流程图 参考答案:B 3:[论述题] 1.背景: 某建筑公司承接了该市一娱乐城工程,该工程地处闹市区,紧临城市主要干道,施工场地狭窄,该工程建筑面积47800平方米,主体地上22层,地下3层,基础开挖深度11.5米,位于地下水位以下,地下防水混凝土等级为C40P8。 2问题 (1)建筑施工质量检查中"三检制”是什么? (2)防水混泥土配合比应符合什么规定? (3)地下防水混泥土工程施工质量检查重点是什么? 2.建设监理的概念是什么? 3.有两种混凝土泵均可满足施工需要,有关经济资料见表10―3,当每月需输送5040m3 混凝土时,问选哪一种好? 表10―3两种混凝土泵的有关经济资料 参考答案:

1答:1)建筑施工质量检查中"三检制”是什么? 建筑工程的施工,应建立各道工序的自检、交接检和专职人员检查的"三检”制度,并有完整的检查记录,未经建设(监理)单位的对上道工序的检查确认,不得进行下道工序的施工; (2)防水混泥土配合比应符合什么规定? 防水混泥土配合比应符合下列规定: 1.试配要求的抗渗水压值应比设计值提高0.2Mpa; 2.水泥用量不得少于300kg每立方米,掺有活性掺合料时,水泥用量不得少于280kg每立方米; 3.砂率宜为35%-45%,灰砂比宜为1:2-1:2.5。 4.水灰比不得大于0.55;5普通防水混凝土塌落度不宜大于50mm,泵送时入泵塌落度宜为100-140mm。 (3)地下防水混泥土工程施工质量检查重点是什么?检查重点:应建立各道工序的自检、交接检和专职人员检查的"三检”制度。 2.答:工程监理是对工程建设有关活动的"监理”,这是一项目标性很明确的具体行为,它包括视察、检查、评价、控制等从旁纠偏,督促目标实现等一系列活动,是一个以严密的制度构成为显著特征的综合管理行为。工程监理通过对工程建设参与者的行为及其他投入物和产出物进行监控、督导和评价,并采取相应的管理措施,保证工程建设行为符合国家法律、法规和有关政策,制止建设行为的随意性和盲目性,促使工程建设费用、进度、质量按计划实现,确保工程建设行为合法性、科学性、合理性和经济性。 3.答:因选择机种A月总费用=5040/42*35+5000=9200元 选择机种B月总费用=5040/35*40+4000=9760元 所以选择机种A 4:[单选题] 1、( )不能认定为工伤。 A: A、自杀 B: B、患职业病 C:C、因工作受到伤害 D:D、在上下班途中,受到机动车事故 参考答案:A 1:[多选题]建设项目进度控制的目标是实现建设项目按计划的时间投入使用,因此,对建设项目的进度必 A:设计、招标、施工和竣工验收及保修各阶段的进度 B:项目组成所有部分的进度

业主方的项目管理包括了哪些内容

业主方的项目管理包括了哪些内容业主方的项目管理包括了哪些内容, 由于这一行业在我国刚开展,如果只是借国外的内容可能不太适应。至少目前大多数项目管理公司的管理内容与书本要求还不尽相同。 个人的一点心得: 依据项目管理合同所确定的有关内容,代表或协助业主对项目前期管理(包括立项、规划、设计、开工审批等各项管理)、工程施工阶段的管理(包括工程质量、进度、投资、安全控制及承包商、供应商、设计及其他单位的管理等)、竣工移交、项目后评估等阶段进行全过程的工程项目总控制。 项目管理的内容按时间顺序可分为三个阶段的内容: 1、项目前期的管理(开工前的项目管理): 这一阶段项目管理的核心任务是项目立项的分析与决策、项目目标的确立、施工图的优化以及承包商的选择。具体内容包括了以下几方面: (1)项目策划:进行项目可行性研究报告,对项目方案进行初步确定,确定项目的质量、进度、投资等目标。 (2)设计管理:编制设计任务书,提供各项设计参数,审核工程初步设计,对项目设计进度管理,对设计施工图组织各类技术、经济专家进行审核,确定图纸的功能合理、造价经济、技术先进。 (3)手续办理:办理或协助业主办理工程手续,包括规划用地许可证、计划委员会批文、规划手续、协助业主签订设计合同、供水手续、供电手续、消防手续、规划许可证、工程招标手续、协助业主签订施工合同、监督手续、施工许可证等。 (4)确定项目实际计划:编制项目管理规划、项目总进度计划、项目实施用款计划,并对施工组织设计、监理规划、材料设备供应计划进行审批。

(5)外部关系协调:包括与相关政府部门以及周边环境等进行关系协调。 (6)审核施工图预算、进行现场管理等工作。 在项目前期的管理中,手续办理与价值分析为主要工作,在我国建设行业目前存在较大的问题就是资金的浪费,工程项目投资可节省额的70%发生在项目决策和设计阶段,通过项目管理方的工作,能较好的达到节省投资的目的。 2、项目中期的管理(施工阶段的项目管理) 这一阶段项目管理的核心任务是现场施工产品的保证、资金使用的计划与审核、以及竣工验收。 (1)现场目标控制 质量目标控制:对承包商、材料供应商的工作进行管理,对工程的质量情况进行检查,对工程的验收进行监督,组织工程竣工验收,对不符合合同质量标准的行为进行纠正,确保质量目标的实现。 进度目标控制:审批承包商的总进度及分段进度计划,对形象进度与实际进度进行对比,要求承包商做好进度分析与纠偏,对影响进度的原因进行记录与分析。 投资目标控制:进行成本核算,准确反映工程的实际造价,充分利用价值原理,提出可合理降低工程造价的建议。按照合同约定,对承包商提出的工程款支付申请进行审查,确保工程款按合同拨付,避免拨付不合理费用或超拨工程款。 安全目标控制:监督承包商的安全管理体系正常运行。 (2)承包商的管理:审查承包商组织机构的人员相关资格,检查其管理体系的健全性。审查分包单位的资质和业绩,并审查总包单位与分包单位的分包合同。 (3)设备、材料供应商的管理:项目管理方首先编制初步的设备采购进度计划,确定主要 设备的采购周期,安排落实进度里程碑。然后将采购进度计划与施工进度计划衔接起来,协调设计、采购、施工进度计划之间发生的矛盾。以“同类产品比质

东财《项目管理》在线作业三(随机)1答案

东财《项目管理》在线作业三(随机)-0018 试卷总分:100 得分:0 一、单选题(共25 道试题,共100 分) 1.进度控制与下列哪种因素无关()。 A.确定项目进度发生变化 B.对促进项目进度产生变化的影响因素进行管理,保证这些变化是有益的 C.当变化出现时,对实际发生的变化进行管理 D.根据客户要求改变项目进度 正确答案:D 2.一个人估计在最常见的情况下往返家里需要1小时。在被进一步询问后,他估计最少的时候需要45分钟,最多的时候需要1小时45分钟,该估计的标准差是()。 A.15分钟 B.60分钟 C.10分钟 D.50分钟 正确答案:C 3.在项目生命周期阶段的()会发生最严重的不确定性。 A.构思阶段 B.规划阶段 C.收尾阶段 D.执行阶段 正确答案:A 4.项目办公室人员通常是(),而职能团队的人员常常是()。 A.兼职的,兼职的 B.全职的,兼职的 C.全职的,全职的 D.兼职的,全职的 正确答案:B 5.项目风险管理的第一步是( ) 。 A.风险评估 B.风险分析 C.风险控制 D.风险识别 正确答案:D

6.计划系统,如PERT、ADM和PDM,是由()使用的项目管理工具。 A.项目负责人 B.以上皆是 C.项目组织 D.项目负责人和项目管理团队人员 正确答案:D 7.一个汽车设计团队应该熟悉最新的汽车装配技术。团队可以通过许多方法来获得这方面的知识:可以雇用一位全职的课题专家,可以雇用一位顾问,可以派一位现有的设计工程师参加有关机器人技术的研讨会,还可以把制造部门的某些人员引进团队。每一种方法的相关成本必须包括在项目计划之中。这个例子表明了()的重要性。 A.在项目规定时间范围内平衡资源的使用 B.在定义活动之前,先要完成资源计划编制 C.确保制定一个资源分配矩阵,并将其当做一个控制工具来使用 D.使资源计划编制与成本估算紧密协调起来 正确答案:D 8.一个2000000的项目有一个不利的事件,发生概率为50%,潜在的损失为20 000元。这表示期望负值为:()元。 A.100 000 B.10 000 C.100 D.1 000 正确答案:B 9.资源约束项目是指()。 A.在一定时间之内完成并尽量少使用资源的项目 B.资源配置有限,不足以完成项目 C.职能经理不是在项目经理要求的时间内分配所需的资源数量 D.该项目必须尽快完成,但所用资源不能超过某一具体范围 正确答案:D 10.有效的团队建设导致的主要结果是()。 A.项目干系人作为个人和项目组成员发生的作用得以加强 B.团队成员充分理解项目经理对项目的执行负最终责任 C.项目情况得到改善 D.一个高效率、运作正常的团队 正确答案:C

(完整版)大工19秋《管理学》大作业

网络教育学院 《管理学》课程大作业 学习中心:奥鹏远程教育济南学习中心(直属)[25]层次:专升本 专业:电气工程及其自动化 年级: 学号: 姓名: 完成日期:

题目五:你认为什么情况下采用矩阵型组织结构比较好? 答: 矩阵型组织是一种混合体,是职能型组织结构和项目型组织结构的混合。它既有项目型组织结构注重项目和客户(业主)的特点,也保留了职能型组织结构的职能特点。这种结构将职能与任务很好地结合在一起,既可满足对专业技术的要求,又可满足对每一项目任务快速反应的要求矩阵制是将按职能划分的部门与按产品或按项目划分的小组(项目组)结合成矩阵型的一种组织结果形式。 矩阵制是将按职能划分的部门与按产品或按项目划分的小组(项目组)结合成矩阵型的一种组织结果形式。这种组织结构形式多用于项目管理。 例如研发型企业、软件公司、工程企业。矩阵型就是一方面服从项目的管理,一方面服从公司各个职能部门的管理,形成一种矩阵。 特点:加强了横向联系,组织的机动性加强,集权和分权相结合,专业人员潜能得到发挥,能培养各种人才。 距阵型组织是一种很有效的组织结构,在西方国家被普遍采用。引进这种组织结构,对处在快速发展中的我国企业来说,具有非常现实的意义。然而一物有一利必有一弊,矩阵结构的缺点是:项目负责人的责任大于权力,因为参加项目的人员都来自不同部门,隶属关系仍在原单位,只是为"会战"而来,所以项目负责人对他们管理困难,没有足够的激励手段与惩治手段,这种人员上的双重管理是矩阵结构的先天缺陷;。 学习心得 答: 。 管理作为一种实践活动,可以说和人类的历史一样悠久。没有学习管理学之前,一直以为管理就是小到对自身日常生活的计划,大到国家对各个事物的领导与规划。学习了管理学后才开始明白,管理学上所研究的管理是指发生在组织中的管理活动,是组织中的管理者为了实现组织的目标对组织成员施加的影响的行为。 管理活动贯穿与生活的方方面面,管理已经成为现代社会最重要的一项活动。而且随着社会的发展,管理活动变得越来越重要,离开了管理,国家将无法

设计阶段业主方的项目管理浅析

设计阶段业主方的项目管理浅析 【摘要】本文主要通过设计阶段业主方的项目管理对项目的投资、质量、进度三大目标的影响,对设计阶段业主方的管理工作进行了探讨,并结合设计变更分析业主方设计阶段项目管理的重要措施。 【关键词】设计阶段;业主方;项目管理;设计变更 引言: 设计阶段是项目管理中的重要环节,它在项目建设过程中具有承上启下的作用,其好坏与否直接影响到项目的后续阶段以及相关项目的经济效益。而业主作为建设工程项目生产过程中的总集成者和总组织者,如何对项目进行高效率的计划、组织、控制和指导以实现项目全过程的动态管理和项目目标的综合协调与优化,设计阶段的业主方项目管理成为一个不容忽视的问题。 为此,本文主要以项目管理三大控制目标为重点分析业主方设计阶段的主要工作,并结合设计变更探讨设计阶段的业主方项目管理工作。 设计阶段业主方项目管理的概念 设计阶段的业主方项目管理的本质,应是从建设项目业主方的项目管理角度,通过确立组织结构模式、明确组织分工、设计工作流程等建立起一整套沟通、交流与协作的系统化管理制度,协调工程项目各阶段中业主与设计单位、承包商、政府部门及其他相关单位之间的技术、经济及管理的关系,最终达到建设项目社会、环境、效益的最佳平衡点。 从项目管理三大目标的角度分析设计阶段业主方的主要控制工作 工程项目管理的核心内容是质量、进度和投资三大目标的控制。 1)从设计对工程造价的影响角度 设计阶段可以说是影响投资程度最大的阶段。依据德国专家墨尔的相关研究结果以及许多建筑工程案例分析,在方案设计阶段初期对投资的影响程度可以说是高达95%,而在施工阶段至多占10%左右。在设计阶段初期节约投资的可能性大约占了88%,相反在施工中节约投资的可能性则仅仅占了12%。 因此,该阶段业主方需要加强设计与经济相结合的重点上,防止超额设计。业主不仅要根据项目计划的实际需求明确设计要求,而且还要用技术经济方法组织评选设计方案,并审查设计概预算,根据实际情况和专业设计特色,要求按照批准的投资估算控制初步设计,并按批准的初步设计总概算控制施工图设计,同时严格控制技术设计和施工土设计的不合理变更,以保证总投资限额不被突破。

项目管理作业答案1

1.1 简述项目与项目管理概念,及其相关内涵。 A.项目 项目,是一种临时性的、一次性的活动,它是一个特殊的将被完成的有限任务,它是在一定时间内,满足一系列特定目标的多项光管工作的总称。 项目的定义包含三层含义:项目是一项有待完成的任务,并且有特定的环境与要求;在一定的组织机构中,项目是利用有限资源(人力、物力、财力等)在规定的时间内完成的任务;这些任务要满足一定的性能、质量、数量、技术指标等要求。 项目的主要属性有: 一次性/独特性 目标确定性/过程的不确定性 活动的整体性/过程的渐进性 团队的临时性与开发性 对资源的依赖性 项目的组成要素主要包括: 基本要素——项目的界定范围和项目的组织结构; 依附于界定和组织的要素——项目的质量、项目的费用和项目的时间进度等。 项目的范畴是指项目本身活动相关的各方面的总和,主要有项目的阶段和生命期、项目当事人和利益相关者、组织结构的影响以及外部环境的影响等。 项目的生命周期包括:启动阶段、计划阶段、实施阶段和收尾阶段四个阶段的内容。在启动阶段,主要进行项目论证,明确项目需求和项目选择;在计划阶段,主要制定进度安排、成本预算、验收标准等内容;在实施阶段,重点是进行项目的实施和项目的控制;在收尾阶段,主要完成项目评估和项目总结工作。 项目的特征是: 项目有开始、结束,分为不同的生命周期,有一个预算,有独特的、非重复的、相互联系的活动。项目是一个团队合作的工作,但责任由一个人(项目经理)承担,老板可能有几个。项目的成本具有不确定性。在项目中,冲突无处不在。 B.项目管理 项目管理是以项目为对象的系统管理方法,它是项目的管理者在有限的资源约束下,通过一个临时性的、专门的柔性组织,运用相关的知识、技术、工具和手段,对项目进行高效率的计划、组织、知道和控制,以实现项目全过程的动态管理和项目目标的综合协调与优化。 项目管理的基本要素包括:项目、干系人、资源、目标和需求。 项目管理的特点: 项目管理的对象是项目或被当作项目来处理的运作。 项目管理的思想是系统管理的系统方法论。 项目管理的组织通常是临时性、柔性、扁平化的组织。 项目管理的机制是项目经理负责制,强调责权利的对等。 项目管理的方式是目标管理,包括进度、费用、技术与质量。 项目管理的要点是创造和保持一种使项目顺利进行的环境。 项目管理的方法、工具和手段具有先进性和开放性。 项目管理的主要内容: 1、项目范围管理 是为了实现项目的目标,对项目的工作内容进行控制的管理过程。它包括范围的界定,范围的规划,范围的调整等。

网上购物系统软件项目管理大作业

《网上购物系统》项目管理目录 1.合同 (1) 1.1合同双方 (1) 1.2供应的商品和服务 (1) 1.3时间地点 (1) 1.4专利成果分配 (1) 1.5验收标准 (1) 1.6报酬计算 (1) 1.7违约处理 (1) 2. 生存期 (2) 3.需求管理 (3) 3.1 功能需求 (4) 3.2确定用例 (4) 3.3用例文档 (5) 3.4非功能需求 (6) 3.4.1 性能需求 (6) 3.4.2安全性需求 (7) 3.4.3故障处理 (7) 4.任务分解 (7) 5.项目估算 (9) 5.1直接成本 (9) 5.2间接成本 (9) 5.3网上购物系统总成本 (10) 6. 进度计划 (10) 7.质量计划 (12) 7.1组织机构 (12) 7.2职责 (14) 7.2.1项目负责人的职责 (14) 7.2.1质量保证人员的职责 (14) 7.3质量目标 (14) 7.4质量策略 (15) 7.5软件质量保证活动 (15) 7.5.1审计 (15) 8.风险计划 (15) 8.1风险种类 (16) 8.1.1资金风险 (16) 8.1.2人员风险 (16) 8.1.3时间风险 (16) 8.1.4技术风险 (17) 8.1.5进度风险 (17) 8.2风险控制 (18)

8.2.1风险的化解 (18) 8.3风险监控 (18) 9.团队管理 (18) 9.1项目组织结构 (19) 9.2团队沟通管理 (19) 10.项目结束 (20) 14.1项目终止 (20) 14.2结束计划 (20) 14.3项目收尾 (20)

1.合同 1.1合同双方 甲方:胡某某 乙方:盛某某 1.2供应的商品和服务 供应的软件:乙方为甲方提供所需的网上购物系统 提供的服务:乙方为甲方提供所需的日常维护和服务器管理。 提供的文档:乙方在交付软件时提供详细的软件规格说明书和使用文档。 安装服务:乙方为甲方提供软件的安装。 公文处理:乙方负责将甲方提供的公文资料加载入系统并进行分类。 维护协议:当甲方在使用该产品时,在正常操作的情况下出现BUG或系统错误,乙方免费为甲方提供修复服务以保障软件的正常使用。当由于甲方的错误使用等非软件原因导致出现故障,乙方同样提供修复服务。由于甲方拥有该软件的源代码所有权,因此甲方需要承担部分维修和进一步开发的责任。当软件需要新的功能拓展或改版升级时,由双方共同协商决定。 1.3时间地点 6月10日上午9:00在河北省沧州市黄骅市 1.4专利成果分配 该软件是由甲方向乙方定制,甲方拥有该软件的版权,乙方不能将该软件的任何版本卖个其他客户。软件提交时,项目源代码的所有权自动移交到甲方,乙方不得擅自对源代码进行修改。 1.5验收标准 乙方在开发过程中必须遵守ISO 12207关于软件生命周期和文档的标准。 1.6报酬计算 软件总价为2万元。合同签订后,甲方向乙方支付1万元定金。项目的第二个月,乙方按计划时间表完成需求分析、系统分析、设计和完成系统的基本框架后,甲方向乙方支付0.5万元。该系统完成后,甲方进行验收测试,在签字验收后完成后,甲方向乙方支付全款。 1.7违约处理 任何一方违反本协议导致本协议无法继续履行的,违约方需赔偿守约方违约金人民币2万元,该违约金不足以弥补守约方实际损失的,违约方应赔偿守约方所有实际损失。 甲方法人代表:胡某某

《工程项目管理》 0755作业答案

1:[单选题]确定项目经理和进度控制、质量控制等主管工作部门或主管人员的工作任务分工应采用( )。A:组织结构模式B:任务分工表C:职能分工表D:工作流程图参考答案:B 2:[多选题]建设项目进度控制的目标是实现建设项目按计划的时间投入使用,因此,对建设项目的进度必 A:设计、招标、施工和竣工验收及保修各阶段的进度B:项目组成所有部分的进度 C:与项目建设有关的所有工作的进度D:影响进度的所有因素E:投资、进度、质量三大目标参考答案:ABCD 3:[论述题] 1.背景: 某建筑公司承接了该市一娱乐城工程,该工程地处闹市区,紧临城市主要干道,施工场地狭窄,该工程建筑面积47800平方米,主体地上22层,地下3层,基础开挖深度11.5米,位于地下水位以下,地下防水混凝土等级为C40P8。 2问题 (1)建筑施工质量检查中"三检制”是什么? (2)防水混泥土配合比应符合什么规定? (3)地下防水混泥土工程施工质量检查重点是什么? 2.建设监理的概念是什么? 3.有两种混凝土泵均可满足施工需要,有关经济资料见表10―3,当每月需输送5040m3混凝土时,问选 哪一种好? 表10―3 两种混凝土泵的有关经济资料 机种月固定费 用(元) 每小时操作 费(元/h) 每小时产量(m3/h) A5000 35.00 42 B4000 40.00 35 参考答案: 1答:1)建筑施工质量检查中"三检制”是什么? 建筑工程的施工,应建立各道工序的自检、交接检和专职人员检查的"三检”制度,并有完整的检查记录,未经建设(监理)单位的对上道工序的检查确认,不得进行下道工序的施工; (2)防水混泥土配合比应符合什么规定? 防水混泥土配合比应符合下列规定: 1.试配要求的抗渗水压值应比设计值提高0.2Mpa; 2.水泥用量不得少于300kg每立方米,掺有活性掺合料时,水泥用量不得少于280kg每立方米; 3.砂率宜为35%-45%,灰砂比宜为1:2-1:2.5。 4.水灰比不得大于0.55;5普通防水混凝土塌落度不宜大于50mm,泵送时入泵塌落度宜为100-140mm。 (3)(3)地下防水混泥土工程施工质量检查重点是什么?检查重点:应建立各道工序的自检、交接检和专职人员检查的"三检”制度。 2.答:工程监理是对工程建设有关活动的"监理”,这是一项目标性很明确的具体行为,它包括视察、检查、评价、控制等从旁纠偏,督促目标实现等一系列活动,是一个以严密的制度构成为显著特征的综合管理行为。工程监理通过对工程建设参与者的行为及其他投入物和产出物进行监控、督导和评价,并采取相应的管理措施,保证工程建设行为符合国家法律、法规和有关政策,制止建设行为的随意性和盲目性,促使工程建设费用、进度、质量按计划实现,确保工程建设行为合法性、科学性、合理性和经济性。 3.答:因选择机种A月总费用=5040/42*35+5000=9200元 选择机种B月总费用=5040/35*40+4000=9760元 所以选择机种A 1:[单选题]涉及项目整个实施阶段的是()的项目管理规划。

业主方项目管理内容和职责

业主方的项目管理内容及相应职责 业主方的项目管理工作涉及项目实施阶段的全过程,即在设计前的准备阶段、设计阶段、施工阶段、动用前准备阶段和保修期分别进行安全管理、投资控制、进度控制、质量控制、合同管理、信息管理及组织和协调主要7项工作,即三控三管一协调。 对项目前期管理(包括立项、规划、设计、开工审批等各项管理)、工程施工阶段的管理(包括工程质量、进度、投资、安全控制及承包商、供应商、设计及其他单位的管理等)、竣工移交、项目后评估等阶段进行全过程的工程项目总控制。 项目管理的内容按时间顺序可分为三个阶段的内容: 1、项目前期的管理(开工前的项目管理): 这一阶段项目管理的核心任务是项目立项的分析与决策、项目目标的确立、施工图的优化以及承包商的选择。具体内容包括了以下几方面: (1)项目策划:进行项目可行性研究报告,对项目方案进行初步确定,确定项目的质量、进度、投资等目标。 (2)设计管理:编制设计任务书,提供各项设计参数,审核工程初步设计,对项目设计进度管理,对设计施工图组织各类技术、经济专家进行审核,确定图纸的功能合理、造价经济、技术先进。 (3)手续办理:办理工程手续,包括签订设计合同、供水手续、供电手续、消防手续、规划许可证、工程招标手续、签订施工合同、监督手续、施工许可证等。

(4)确定项目实际计划:编制项目管理规划、项目总进度计划、项目实施用款计划,并对施工组织设计、监理规划、材料设备供应计划进行审批。 (5)外部关系协调:包括与相关政府部门、开放商、物业公司以及周边环境等进行关系协调。 (6)审核施工图预算、进行现场管理等工作。 在项目前期的管理中,手续办理与价值分析为主要工作,在我国建设行业目前存在较大的问题就是资金的浪费,工程项目投资可节省额的70%发生在项目决策和设计阶段,通过项目管理方的工作,能较好的达到节省投资的目的。 2、项目中期的管理(施工阶段的项目管理) 这一阶段项目管理的核心任务是现场施工产品的保证、资金使用的计划与审核、以及竣工验收。 (1)现场目标控制 质量目标控制:对承包商、材料供应商的工作进行管理,对工程的质量情况进行检查,对工程的验收进行监督,组织工程竣工验收,对不符合合同质量标准的行为进行纠正,确保质量目标的实现。 进度目标控制:审批承包商的总进度及分段进度计划,对形象进度与实际进度进行对比,要求承包商做好进度分析与纠偏,对影响进度的原因进行记录与分析。投资目标控制:进行成本核算,准确反映工程的实际造价,充分利用价值原理,提出可合理降低工程造价的建议。按照合同约定,对承包商提出的工程款支付申请进行审查,确保工程款按合同拨付,避免拨付不合理费用或超拨工程款。 安全目标控制:监督承包商的安全管理体系正常运行。 (2)承包商的管理:审查承包商组织机构的人员相关资格,检查其管理体系的

华南理工网络教育项目管理大作业

如何选聘优秀的项目经理和合格的项目团队成员? 答:项目经理是整个项目组的灵魂,是项目组中很重要的一个角色,是项目完成与否的核心人物。项目经理的任职资格 一、人格魅力 1、忠诚,首先要带有对项目负责的态度,对项目忠诚。 2、公正无私,项目经理要整合项目组的所有资源为实现预期的目标服务,那么项目经理就要站在公正无私的立场合理地分配项目组的资源,如人力、物力、财力等,不能因为个人的原因而刻意增减各类资源, 3、良好的职业道德,由于项目的特殊性,任一个细微的变化都有可能导致项目的终止。因而,要求项目经理要具有良好的职业道德,时时跟踪和关注项目的进展情况,遇到项目运作过程中所发生的问题和困难要及时地与公司、用户进行充分沟通和协调,共同探讨解决之道方为上策。蓄意隐瞒困难的真相是一种不负责任的态度。 4、善于学习,没有人什么都懂,只有虚心的人才会真的懂。虽然项目经理是一个项目的核心人物,但他所具备的知识不一定比项目组的每个人都强,因此,项目经理应该要放下架子,善于向别人学习,虚心学习大家的优点,积极收集大家的意见,并集体探讨,不搞一言堂,更不能不懂装懂。 二、知识素养 1、独到见解,项目经理对所接受的项目要有深刻的认识和理解,能够提出独到的见解,并针对项目实施,提出总体框架和解决方案。这样可以让项目在开始时,可以让整个项目组对项目的总体目标和方向有个理性认识,增强项目组对项目成功的信心。 2、知识渊博,这是的知识渊博是要求项目经理对项目所涉及的方方面面的知识,都要有所涉猎,特别是懂得技术层面上的知识,不要求精通,但是要全面认识和理解。一般情况下,对于一个中小型的项目,不大会在设置了一个项目经理之后,还要安排一个技术负责人的职务。这样做的话很容易造成资源的浪费和项目经理的工作量不饱满。 3、善于分析和解决问题,项目经理要具有敏锐的眼光和善于分析问题的能力,能够通过项目进展过程中的种种不寻常细节发现大问题,在发现问题后又能要果断地采取措施给予解决,而不是延误时机。 三、管理能力 1、具备管理的基本技能与知识, 在岗位设计上,项目经理也属于一个管理岗位,因此,要做一个好的项目经理,他要熟悉项目管理的基础知识和分析方法,并进行必要项目管理的技能训练,既要有管理意识,还要有管理的基本技能,在处理各种突发事件中,作到“心有余且力也有余”。2、很好的沟通与表达能力,一个项目经理在某种程度上担当着一个协调员的角色,因为,项目经理要和方方面面的人员沟通,这个不仅局限在项目组内的人员之间的沟通,还要涉及到与其他部门或人员之间的沟通与协调。 当然,项目经理的选拔还要考虑许多的因素,如项目的规模、项目的紧迫性、项目的难易程度、公司的具体要求等等诸多方面。 项目团队成员可以参照 不确定性分析有哪几种主要方法? 他们各自有什么优点和局限性? 答:不确定性分析析的方法主要有:盈亏平衡分析法、敏感性分析法、概率分析法和决策分析法。盈亏平衡分析法只适用于财务分析,其他方法可同时适用于财务分析和经济分析盈亏平衡分析——优点 计算简单 盈亏平衡分析的思路除了应用在产量——成本——利润分析之外,还可以对项目的投资、收入、费用、残值、折现率、寿命周期等进行盈亏平衡分析。例如财务内部收益率(FIRR)就是项目盈亏平衡点的折现率。 盈亏平衡分析——局限

项目管理大作业及答案

网络学院《项目管理》大作业 2012-2013第一学期 1.什么是项目财务评价?它与企业日常财务分析有何区别?与社会经济评价有何异同点? 答:项目财务评价是从项目的微观角度出发,根据国家现行财税制度和现行市场价格,预测项目周期全过程中可能发生的费用和效益,运用货币时间价值的理论,对项目的获利能力、偿还能力、创汇能力等财务状况进行动态分析,为投资决策者取舍项目提供依据。 项目财务评价与正常进行生产经营的企业财务分析有着明显的区别: 1 .评价的目的不同。项目财务评价为项目取舍提供决策依据,是在项目决策实施前的事先性分析;企业日常财务分析属于生产经营过程中的阶段性的事后性分析,是为判别企业经营优劣、改善经营效益寻找原因和薄弱环节。 2 评价的时间跨度不同。日常的企业财务分析只对近期的(少则一月,多则一年)生产经营活动中的财务状况,进行短期分析;项目的财务评价必须对项目寿命周期的全过程进行分析,评价涉及的时间跨度较长。 3 .评价时依据的数据不同。日常的财务分析是根据实际价格所记录的数据加以整理、对比分析;项目财务评价是根据现行市场价格对未来可能发生的数据加以预测,然后再进行分析论证。 4.运用的评价方法不同。日常的财务分析只对当期的财务状况做静态分析,不考虑货币时间价值的因素;而项目的财务评价除静态分析外,还要考虑时间因素,对不同时点的资金进行贴现作动态分析。 社会经济评价是在财务评价所预测的基本数据基础上,经过调整,以社会成本代替财务成本,以社会效益代替项目本身的效益,再进行计算和分析。 2.投资机会研究、初步可行性研究和可行性研究三者有什么区别? 答:机会研究是指寻求投资的机会与鉴别投资的方向,其主要任务是对投资项目进行初步鉴定。这种研究一般是靠经验数据估计,是匡算的,时间较短,费用也较少。 初步可行性研究对投资项目的关键性问题需要做专门的调查研究,例如:市场情况、资源条件、产品方案、工艺路线、技术设备、及经济效益的评价等,需要取得较精确的数据。初步可行性研究要用半年左右的时间,估算误差一般为±20% ,所需费用约占投资总额的1% 。

设计阶段的项目管理

第8章设计阶段的项目管理 学习目标: 1.掌握设计前的准备工作、项目管理规划的类型、组织和项目实施的合同结构。 2.掌握设计过程特点、设计阶段的项目管理类型、设计项目管理工作内容。 3.了解设计竞赛、设计协调的内涵、设计文件的分类与编码和设计文件管理。 4.掌握设计任务的委托方式及合同结构、设计合同的签订、设计阶段合同管理任务、设计合同索赔管理、设计阶段投资控制、进度控制、质量控 制、设计协调的方法和设计阶段信息管理任务, 重点难点: 1、设计阶段的项目管理类型 2、设计委托的合同结构 3、设计阶段的目标控制 4、设计文件的分类与编码 课程内容: 设计过程是项目实施阶段的重要环节,项目管理的“三控三管一协调”六大基本职能也贯穿于整个设计过程的始终,成为设计阶段的项目管理的核心任务。此外,设计过程自身的独特性,则决定了设计阶段的六大基本项目管理职能的特殊性。与实现其它阶段的项目管理职能不同,它们具有一套特殊的管理措施和方法。本章内容包括设计阶段的项目管理概述、设计任务的委托及设计合同的管理、设计阶段的目标控制、设计协调、设计阶段信息管理。 8.1设计阶段的项目管理概述 建设项目设计是集社会、经济、技术和管理为一体的复杂的特殊的系统性生产过程,它不单是设计单位的个体创造,而是业主、设计单位、政府主管部门和其它项目参与方共同参与和协作的成果。而设计阶段项目管理的核心并不是对设计单位工作进行监督,而是通过建立一套沟通、交流与协作的系统化管理制度,帮助业主和设计方去解决设计阶段中,设计单位与业主(建设单位)、政府有关建设主管部门、承包商以及其它项目参与方的组织、沟通和协作问题,实现建设项目建设的艺术、经济、技术和社会效益的平衡。 8.1.1 设计过程特点 要进行设计阶段的项目管理工作,先必须对设计过程的特点有所了解。与施工过程相比,设计过程具有三个方面的特点: 1)创造性 设计过程是一个创造过程,它是一个“无中生有”、从粗到细、从轮廓到清晰的过程。应当注意的是,在工程设计中,设计的原始构思就是一种创造,应最大限度地发挥建筑师的创造性思维。但是在整个设计过程中又并非所有的设计工作都是无中生有的,每个阶段的设计都应当是在上一阶段的设计成果及相关文件依据下而进行的,后阶段设计的重点应该是把设计的原始构思在优化的基础上进

项目管理作业答案

1、(A)不能认定为工伤。 A、自杀 B、患职业病 C、因工作受到伤害 D、在上下班途中,受到机动车事故[单选题]由于建设工程项目大量数据处理的需要,应重视利用信息技术的手段进行信息管理,当今时代其核心手段是(C) A:数据库技术B:数据仓库技术C:基于网络的信息处理平台 2:[单选题]确定项目经理和进度控制、质量控制等主管工作部门或主管人员的工作任务分工应采用(B)。 A:组织结构模式B:任务分工表C:职能分工表D:工作流程图 1:[单选题]涉及项目整个实施阶段的是(A)的项目管理规划。 A:业主方B:设计方C:施工方D:供货方 2:[多选题]施工方项目管理规划的内容一般包括(ABDE) A:质量控制的方法和手段B:进度控制的方法和手段C:投资控制的方法和手段D:安全管理的策略E:风险管理的策略 2:[多选题]招标人应对投标人的资格进行预审,资格预审应主要审查潜在投标人或者投标人是否符合(ABE) A:具有独立订立合同的权利B:具有履行合同的能力 C:没有处于被责令停业,投标资格被取消的状态D:5年内没有重大工程质量问题E:法律法规规定的其他资格条件 :[多选题]建设项目进度控制的目标是实现建设项目按计划的时间投入使用,因此,对建设项目的进度必ABCD A:设计、招标、施工和竣工验收及保修各阶段的进度 B:项目组成所有部分的进度C:与项目建设有关的所有工作的进度D:影响进度的所有因素E:投资、进度、质量三大目标 4:[多选题]8、风险管理的工作包括(ABDE)几方面。 A:风险识别B:风险回避C:风险评估D:风险应对E:风险控制 某建筑公司承接了该市一娱乐城工程,该工程地处闹市区,紧临城市主要干道,施工场地狭窄,该工程建筑面积47800平方米,主体地上22层,地下3层,基础开挖深度11.5米,位于地下水位以下,地下防水混凝土等级为C40P8。 2问题 (1)建筑施工质量检查中"三检制”是什么? (2)防水混泥土配合比应符合什么规定? (3)地下防水混泥土工程施工质量检查重点是什么? 参考答案:1答:1)建筑施工质量检查中"三检制”是什么? 建筑工程的施工,应建立各道工序的自检、交接检和专职人员检查的"三检”制度,并有完整的检查记录,未经建设(监理)单位的对上道工序的检查确认,不得进行下道工序的施工; (2)防水混泥土配合比应符合什么规定? 防水混泥土配合比应符合下列规定: 1.试配要求的抗渗水压值应比设计值提高0.2Mpa; 2.水泥用量不得少于300kg每立方米,掺有活性掺合料时,水泥用量不得少于280kg每立方米; 3.砂率宜为35%-45%,灰砂比宜为1:2-1:2.5。 4.水灰比不得大于0.55;5普通防水混凝土塌落度不宜大于50mm,泵送时入泵塌落度宜为100-140mm。 (3)地下防水混泥土工程施工质量检查重点是什么?检查重点:应建立各道工序的自检、交接检和专职人员检查的"三检”制度。 2.建设监理的概念是什么?

设计项目管理的方案与步骤

设计项目管理的方案与步骤 项目管理指在项目活动中运用专门的知识、技能、工具和方法,使项目能够在有限资源限定条件下,实现或超过设定的需求和期望的过程。以下是收集的设计项目管理的方案与步骤,欢迎查看! 设计项目管理最核心的部分是设计项目规划阶段制定的有关项目。设计项目实施的好坏,在很大程度上在于对实施过程控制的好坏,而实施过程的控制又依赖于评估和沟通实行的情况,总体来看,设计项目管理的实施让整个设计过程环环相扣,形成严密的整体。虽然,设计项目管理在国内患处于起步阶段,但全球化的经济已使设计与管理相结合成为必然。 一、设计项目管理综述 1、定义 设计项目管理是定义于设计问题,以设计项目为对象的系统管理方法,通过计划、组织、指导和控制等管理手段对设计资源进行合理配置,对设计项目全过程进行高效整合,综合协调及优化。作为对具体设计项目的管理,它具有务实性、可操作性,是较低级的可操作的管理。它与一般的管理不同之处是将管理的对象具体到具体的设计项目,但它仍是管理的一部分,所以管理的理论也对之适用。 2、基本任务 设计项目管理在设计项目过程中有四个基本任务:计划、组织、监督、控制。设计项目管理计划是在设计项目建立之后,设计项目展开之前,对设计前期准备工作的规划。它包括设计项目的目标设定、

设计项目流程图、设计项目时间总体规划、设计项目考核等。设计项目管理计划中的各项都极为重要,它们是以后设计项目管理工作展开,评估的参考依据和衡量标准。它的“质量”的好坏,直接影响着最终产品的成败。所以应进行各方面的综合思考,做出完美计划,为以后的成功打下坚实的根基。设计项目管理组织除包括团队成员的确定外,还包括组织结构的选择。组织结构直接影响团队内部信息传递和反馈的快慢,即沟通问题。设计项目管理监督包括在一定阶段进行总结、评价,且按照进程督促员工保证设计进度。设计项目管理控制是实施阶段很重要的一点,管理者依据设计计划,对目标,进程等进行把握,控制在正常范围内。 3、设计项目的建立 一个设计项目的展开,是以设计项目的建立为前提。设计项目 地建立与否直接与产品的可行性研究结果决定。产品可行性研究要涉及面广,要评估准确。产品可行性研究主要包括以下要点:市场前景评估;技术的可行性;加工工艺可行性;成本问题;综合评估。设计项目建立后,设计项目建立后从开始实施到项目工作结束称作设计项目生命周期:即设计项目规划阶段,设计项目实施阶段,设计项目评估阶段。依据生命周期的三阶段展开文章的三大部分。 二、设计设计项目规划阶段 设计项目建立后,就进入了规划阶段。首先应组建团队。设计 管理者。设计管理者要具备设计和管理两方面的知识。他要从战略,从企业角度去全盘考虑问题,这是设计管理者必备的素质。同时要考

相关文档
最新文档