矿副井施工组织设计

矿副井施工组织设计

摘要

在全球范围对煤碳需求上升的情形下,煤炭产销两旺,煤炭价格基本稳定,煤炭企业经济效益明显好转。

本文就某矿副井施工组织设计方面做了具体的介绍。根据当地的地质和地层情况做出了具体的分析,确定采用冻结法施工。结合冻结法施工原理,对冻结施工中的相关参数进行计算和设计。根据立井井筒施工机械化配套方面要求和实际施工情况,对立井施工机械化设备进行最优选型。根据井筒施工的相关规范和计算公式,对基岩段爆破、矿井通风、井壁支护、井壁注浆等方面相关参数进行详细、严谨的演算,分析和研究了一系列工序的施工组织设计。对冻结孔和炮眼的布置做出了具体的设计。最后一部分对矿井水处理方面做了具体的介绍,特别是酸性矿井水处理,分析了其危害性、成因、预防和治理。最后介绍了某矿区矿井水治理方案。设计过程中至始至终本着最优经济效益、施工质量和进度来进行的。

关键字:冻结法、井筒施工、爆破、通风、矿井水

Xuehu Vice-well Construction and Organization

plan

Abstract

Under the global scope to coal demand rise situation , The coal production and marketing are prosperous, The coal price basic is stable, Coal enterprise economic efficiency obvious change for the better.

This article concrete introduction the vice-well construction and organization plan aspect has made the on Shenhuo group's XueHu well. Have made the concrete analysis according to the local geology and Stratum situation, So the determination uses the freezing process construction. Has calculated and designed in the freeze construction related parameter that union the freezing process construction principle. Carries on optimal to the vertical shaft construction mechanization equipment, Requests according to the vertical shaft well chamber construction mechanization necessary aspect with the actual construction situation。Carrying on the rigorous calculation to the bedrock section demolition、Well ventilated、Wall of a well support、Wall of a well note thick liquid aspect correlation parameter and so on in detail。Analyzed and has studied a series of working procedures construction organization plan。To froze hole and artillery eye the arrangement to make the arrangement。Last the part has made the concrete introduction to the pit water processing aspect,Specially acidic pit water processing, Has analyzed its hazardous nature、the origin、the prevention and the government。Finally introduced the Xuehu mining area pit water government plan。In the design process to the beginning to the end in line with the most superior economic efficiency, the construction quality and the progress carries on。

Keywords:Freezing process、Well chamber construction、Demolition、Well ventilated、Pit water

目录

摘要 (1)

英文摘要 (2)

1 绪论 (10)

1.1 位置与交通 (10)

1.2 地形地貌及水系 (10)

1.2.1 地势 (10)

1.2.2 地表水系 (10)

1.2.3 气象 (10)

1.2.4 地震 (11)

1.3 煤炭销售及预测 (11)

2 井筒设计概况 (12)

2.1 井筒地质及测量工作 (12)

2.1.1 地层 (12)

2.1.2 煤层及瓦斯 (12)

2.1.3 水文地质 (13)

2.2 全矿井涌水量 (15)

2.3 副井筒特征表 (15)

2.4 矿井主要生产及辅助系统 (18)

2.4.1 副井提升系统 (18)

2.4.2 矿井通风系统 (18)

2.4.3 矿井排水系统 (18)

2.4.4 压缩空气供应系统 (18)

2.4.5 矿井供电系统 (19)

2.4.6 井下运输系统 (19)

2.4.7 排矸系统 (19)

3 冻结施工 (20)

3.1 施工方案 (20)

3.2 冻结法施工 (20)

3.2.1 冻结法的凿井原理 (20)

3.2.2 冻结壁厚度设计 (21)

3.2.3 冻结孔的布置 (23)

3.2.4 冻结壁平均温度的计算 (25)

3.2.5 测温孔、水文孔的布置 (29)

3.3 井筒冻结制冷设计 (29)

3.3.1 冷冻站设计 (29)

3.3.2 盐水系统设计 (30)

4 井筒施工 (31)

4.1 锁口施工 (31)

4.2 井筒表土段施工 (31)

4.2.1掘进 (31)

4.2.2装岩 (32)

4.2.3 提升、排矸 (32)

4.2.4 通风 (32)

4.3 风硐施工 (32)

4.4 防排水 (33)

4.5 砌壁施工 (33)

4.6 冻结与掘砌的配合 (34)

4.7 夹层注浆 (34)

4.8 基岩段井筒施工 (35)

4.8.1掘进 (37)

4.8.2装岩 (40)

4.8.3 提升、排矸 (40)

4.8.4支护 (40)

5 通风 (44)

5.1 通风方式 (44)

5.2 通风计算 (45)

5.2.1 初期风量 (45)

5.2.2 后期风量 (47)

5.3 矿井通风负压 (48)

5.4 矿井通风等积孔 (48)

6 井壁注浆 (50)

6.1 施工方案 (50)

6.2 施工方法 (50)

6.2.1 注浆设备及布置 (50)

6.2.2 注浆孔布置及要求 (50)

6.2.3 钻孔设备的规格 (51)

6.2.4 注浆孔口管选择及规格 (51)

6.2.5 注浆材料选择 (51)

6.2.6 注浆参数选择 (51)

6.2.7 注浆压力 (51)

6.2.8 注浆量 (52)

6.3 扩散半径 (53)

6.4 注浆前的准备工作 (53)

6.5 注浆施工顺序 (53)

7 矿井水处理 (54)

7.1 我国矿井水现状 (54)

7.2 矿井水处理技术现状 (55)

7.2.1 混凝剂和混合形式 (55)

7.2.2 沉淀和澄清 (55)

7.2.3 过滤 (56)

7.2.4 消毒 (58)

7.3 酸性矿井水的处理 (58)

7.3.1 酸性矿井水的危害 (58)

7.3.2 酸性矿井水形成的原因 (60)

7.3.3 酸性矿井水预防 (61)

7.3.4 酸性矿井水的治理 (61)

7.4 薛湖矿矿井水处理方法 (64)

7.4.1薛湖矿区矿井水概况 (64)

7.4.2 混凝试验研究 (64)

7.4.3 单一混凝剂混凝效果 (64)

7.4.4复合混凝剂混凝效果的研究 (65)

7.4.5矿井水处理回用的手段、途径以及节水情况 (67)

7.4.6 结论 (67)

(建筑工程管理)风井施工组织设计

(建筑工程管理)风井施工 组织设计

神华亿利黄玉川煤矿 回风立井装备安装 施 工 组 织 设 计 中煤三建(集团)公司 机电安装有限责任公司 二0壹0年二月 目录 壹、工程简介 二、主要工作量 三、施工前的准备工作 四、施工程序 五、施工方法 六、临时挂装 七、有关强度校核 八、安装质量标准 九、质量保证体系及措施 十、安全保证体系及措施十壹、安全保证体系及措施十二、文明施工措施 十三、文明施工措施 十四、“四新”采用措施 十五、劳动力安排 十六、施工机具壹览表

壹、工程简介 黄玉川回风立井井筒装备工程由华宇工程XX公司设计。回风立井井筒直径φ6m,第壹层梯子间主梁标高为1152.7m,最后壹层梯子间主梁绝对标高833.5m,回风立井井筒装备为6m 层间距标准玻璃钢复合材料梯子间52层,非标准玻璃钢复合材料梯子间4层。 为使该工程施工顺利进行,做到“快速、优质、安全、低耗”,确保工程按期交付使用特编写本措施,以利于指导施工。 二、主要工作量 1、梯子主梁托架110只 2、梯子小梁托架165只 3、梯子主梁55根 4、梯子次梁165根 5、玻璃钢梯子间54套

三、施工前的准备工作 1、组织施工人员熟悉有关图纸,进行技术交底,学习有关安全规程、质量标准及本施工措施。 2、按照图纸查对加工件数量、规格、型号、质量情况,于开工前配齐所有需用材料。 3、井筒施工前平整施工场地,按使用要求把各类加工件运至井口附近,各类材料堆摆放有序且挂牌标明。 4、要求提供井筒竖直情况测量资料及井筒矿建设计预留情况资料,超标处井筒施工前修改或提出整修方案。 5、根据井筒施工设定大线点位置,于梁上做出安装用关联基准线且打样冲眼标记,且于托架上用白漆标出安装方位编号,以利施工。 6、按照施工需要备齐施工机具、专用工具。 7、编制施工用各种图表、记录表及现场标牌。 8、施工现场应备有黄沙、水源、灭火器等消防器材。 9、风水管接至井口附近,且装阀门控制。 10、由测量人员给出施工用基准点线。 11、对临时挂装的施工机具做壹次全面认真的安全检查,消除安全隐患。 12、对施工人员作壹次全面的身体检查。 四、施工程序 1、临时挂装(暂时先不封口) 2、利用吊盘安装上井口第壹层及第二层梯子梁(+1152.7米),且以此作为基准稳线梁,继续安装第二层及第三层梯子间。 3、于第三层梯子间(+1143.5米)利用吊盘进行封口盘的组装。 4、稳线,卡上井口大线。 5、由上向下利用活大线进行井筒装备施工。 6、安装至最后壹层梯子间后,割吊盘,起吊盘于起吊盘的过程中检查梯子间安装质量 7、将吊盘提至井口,拆除封口盘及吊盘。 五、施工方法 1、各稳车天轮布置好后,将于井口旁组装好的方吊盘提起放至井筒内,按挂装图将盘子组装为圆盘。且安装盘内的电源开关、电焊机、通讯工具及照明等。 2、利用吊盘封井口,且根据测量所给十字线,把基准点线翻到封口盘上。 3、根据井口放线位置先进行安装第壹层梯子间平台板,以及安装第壹层梯子间网门和梯子。 4、利用井筒标高和十字线安装第壹层托架、梁,且以此作为基准稳线梁。 5、井筒内基准大线稳卡完毕后,请甲方组织验收,全部符合要求后,方可向下进行下壹步井筒其他构件的安装工序。 6、锚杆螺栓的安装 根据大线位置及自制的号眼工具进行定位号眼,锚杆孔用风锤打出,打孔时钻杆应水平且和井壁垂直。钻头直径选用φ42mm,锚杆孔深以锚杆长度为准,为控制孔深,应于钻杆上做出明显标记。打眼过程中,眼孔要用水冲洗,使其孔内不得留有杂物。如遇有钢筋,可用电焊氧气配合吹除。孔眼打好后用锚杆检查深度后将药包送到孔底,且用煤电钻或风动扳手将锚杆迅速送入孔内,推绞至规定深度。锚杆拉力试验应于栽入壹小时后按设计要求进行,其值不应小于规定值(壹般为50KN)。 7、托架安装 先将托架和井壁贴合面的杂物用钢丝刷清除干净。层间距用钢卷尺控制,中心线用线坠控制。安装找正托架,托架面必须保持水平,安装好的托架和井壁之间应按设计要求填入充填物。

灵北主副井设计(两双钩)

前言 山西汾西矿业公司曙光煤业灵北煤矿位于山西省灵石县两渡镇境内,距灵石县城约20公里。该区交通较为便利,108国道从矿区旁穿越,北可达太原,南可至运城到陕西,往南可达大运高速公路。 我们认真地研究了灵北矿井主、副斜井工程图纸内容,仔细分析了灵北矿井主、副斜井井筒地质条件,同时结合大断面斜井施工的先进经验及先进的斜井施工装备和技术力量,本着实事求是的原则编制灵北矿井主、副斜井施工组织设计。本施工组织设计采用首创的“大断面斜井机械化作业线快速施工工法”(国家级工法),运用喷射砼远距离输料技术,采用专业工种,固定工序交叉作业,使掘进支护平行作业,减少辅助时间,缩短循环时间,实现快速施工。 本施工组织设计编制依据: 1、山西汾西曙光煤业有限责任公司灵北矿井主斜井井筒平、剖断面图S1764-111-01、副斜井井筒平、剖断面图S1764-116-01; 2、崔家沟专用回风井预想地层柱状图(邻近矿井); 3、《煤矿安全规程》2006版; 4、《煤矿井巷工程质量检验评定标准》(MT5009-94); 5、《矿山井巷工程施工及验收规范》(GBJ213-90)。

1地质、工程概况 1.1气象及地震: 本井田属暖温带大陆性气候,四季分明,昼夜温差悬殊。冬季少雪,春季风大雨少,夏季雨量高度集中,秋季阴雨天较多。风向以西北风为主,平均风速1.6m/s,最大冻土深度77cm。 1.2水文地质条件: 井田内地形不利于大气降水入渗。对矿床充水的含水层富水性弱,且井田内断层及陷落柱稀少,对岩层破坏程度小,含水层之间联系微弱或无联系。综上所述,井田内水文地质条件简单。井田02、2、4、5号煤层开采以基上覆砂岩裂隙含水层为主要充水含水层。井田水文地质勘探类型确定为二类一型,建设方提供井筒涌水量小于5m3/h。 附崔家沟专用回风井(建设方提供邻近矿井)的预想地层柱状图。 1.3瓦斯: 本矿井属低瓦斯矿井。 1.4工程范围及工程量 本次施工工程范围为汾西矿业集团公司曙光煤业灵北矿井主、副斜井井筒。 主斜井井筒全长779m,倾角-19°,副斜井井筒全长548.72m,倾角-22°。 附主、副斜井井筒剖面图1-1, 1-2; 主、副斜井井筒断面图1-3, 1-4; 具体工程量及特征见表1-1。

井筒施工组织设计 课程设计

第一章 矿井概况 一 设计编制依据 1 井筒地质柱状图 2 《煤矿安全规程》 3 《煤矿井巷工程质量检验评定标准》 二 矿井条件 本矿井为城郊矿井,设计服务年限为30年。城郊矿井的设计生产能力位240万吨。 本次设计的井筒为副井井筒。井筒净直径8.5m ,井筒的深度为680m,副井井筒的开拓方式为立井开拓,通风方式为中央分列式通风系统。煤层含沼气的等级及突出危险程度:低沼气,无突出。 副井井筒的表土段深230m ,表土段井壁结构为双层钢筋混凝土井壁,内壁的厚度为450mm ,外壁的厚度为500mm 。基岩段厚430m,为普通混凝土井壁,厚650mm ,混凝土标号为C30。 井筒内提升容器采用单层双车罐笼,提升容器导向装置的结构类型采用组合罐笼。井筒的提升方位角为15o 。 三 矿井水文地质情况 (一) 表土厚度及类型:表土土层为第四纪冲击层,厚度为230m (二) 含水情况:表土含水情况为3200m ,表土下方的风化基岩带厚度为 20m ,基岩为泥岩和粉砂岩,厚度为430m ,基岩岩倾角为08,含水情况为400~430m ,h m 330。 四 井筒特征 (一)副井井筒特征表

(二)井筒断面布置形式 井筒断面布置形式如图1-1所示: 图1-1 井筒断面布置图 第二章井筒基岩段施工方案

一、选择施工方案时应考虑的因素: (一)井筒穿过岩层的性质,涌水量的大小。 (二)井筒直径和深度(主要指基岩部分的深度)。 (三)可能采用的施工工艺及技术装备条件。 (四)施工队伍的操作技术水平和施工管理水平。 选择施工方式,首先要求技术先进,安全可行,有利于采用新型凿井装备,不仅能获得单月最高纪录,更重要的是能取得较高的平均成井速度,并应有明显的经济效益。 二、现有立井井筒基岩段施工方案分析 (一)掘、砌单行作业 凿井时将井筒划分为若干段高,自上而下分段施工,在同一段高内,按照掘砌先后交替顺序作业称为单行作业且由于掘进的段高不同,单行作业又分为长段单行作业和短段平行作业。 掘、砌单行作业的最大优点是工序单一,设备简单,管理方便,当井筒涌水量小于3 30m/h时,任何工程地质条件均可使用。特别是当井筒深度小于400m 时,施工管理技术水平薄弱,凿井设备不足,无论井筒直径大小,应首先考虑采用掘砌单行作业。其中,短段掘、砌单行作业更具优势。 (二)掘、砌平行作业 掘砌平行作业仍有长段平行作业和短段平行作业之分。长段平行施工,是在工作面进行掘进作业和临时支护,而上段,则由吊盘自下而上进行砌壁工作。短段掘、砌平行作业,掘、砌工作也是自上而下,并同时进行施工。掘进工作在掩护筒保护下进行;砌壁是在多层吊盘上,自上而下逐段浇灌混凝土,每浇灌完一段井壁,即可进行下一段的混凝土浇灌工作。掘砌、掘安平行作业一次成井,是在两个段高内、下端掘进与上段砌壁,安装相平行,而砌壁和安装工序则按先后循序进行,砌壁自上而下,安装自上而下。 长段平行作业施工装备复杂,设备用量多,围岩暴露时间长,对井筒围岩稳定产生不利影响,施工组织和安全作业复杂;短段平行作业不受井筒深度和截面大小的制约,在严格信号系统的管理和施工工序组织恰当的情况下,可以掘、砌共用提升系统。平行作业方式主要用于井筒直径大的深井工程。 (三)掘、砌混合作业 井筒掘、砌工序在时间上有部分平行时称混合作业。它既不同于单行作业也

浅谈施工组织设计在矿建工程中的作用

浅谈施工组织设计在矿建工程中的作用 矿建工程的施工不同一般的建筑施工,需要进行详细的细化分析,施工组织设计对矿建工程的施工有着十分重要的影响,施工组织能够为矿建施工提供指导,是工程施工的指导性文件,能够为工程建设提供措施保障,对矿建工程的施工具有重要的作用。 标签:施工组织;矿建工程;目标控制 施工组织设计是矿建工程施工的系统的指导性文件,是工程施工的建设计划和具体设计的要求;施工组织是矿建工程施工的重要环节,是实现矿建工程通过竣工验收的重要保证和基础;施工组织设计为具体的实施过程提出计划和方案,提出工程施工的工艺流程、质量目标、节点工期控制、安全措施的控制以及执行的相关标准等,能够有效的组织和协调施工中各职能部门的作用,对各环节存在的问题进行合理的安排,能够有效的保证矿建工程按期、保质、保量施工。 1 矿建工程施工中常见的问题 就目前的矿建工程的具体施工而言,大多数矿山企业对项目施工的重要程度和作用认识不够,认为矿建工程的建设都是粗放型的,不需要美观、精准等要求,导致矿建施工出现质量缺陷问题,导致矿建工期的拖延、建设的施工成本上升。在分析工程施工的具体原因时,将出现的工程问题归结为工程的地质情况出现的问题,而很少分析施工中的自身问题,很少分析施工组织措施上的内在原因,缺乏对矿建施工组织设计的正确认识,并没有按照施工组织编制施工计划,忽视矿建施工组织设计的编制,即使有的单位编制了施工计划,也没有按照详细的施工作业规程执行,有的工程单位技术力量薄弱、施工工艺落后、管理水平不到位,编制的施工计划内容缺乏新技术、新理念、新设备、新工艺、新方法等创新内容运用到施工的建设过程中,施工过程中生产效率低下、施工材料消耗大、施工的工期无法掌控;有的单位更是根本就没有详细的施工组织设计,按照自己的想法进行施工,施工中各种资源的需求无计划,任意更改施工计划,调整施工的工期,施工只有口号没有具体施工管理措施,致使矿建施工过程的管理混乱无序,偶遇特殊工程地质施工时,则惊慌失措,没有具体的应对措施,无所适从,影响矿建工程的施工,直接导致工程项目进度控制、质量控制、成本控制的失控,给企业造成重大的经济损失。 2 矿建施工组织设计的主要构成 2.1 矿建工程的施工方案 矿建工程的施工方案是依据项目设计的文件进行设计的施工计划,是施工企业的设计核心,矿建工程的设计方案是否合理,直接影响到企业施工的工程进度、质量、生产的安全,需要施工企业、施工单位认真的分析、思考和重视。在进行矿建施工方案比选时,要结合采场的实际情况,对矿建的施工方案中施工工艺、

地铁施工风井改造施工方案

无锡地铁1号线谈渡桥站商业配套工程 清明桥站W-3风井改造施工组织设计 中铁十九局集团有限公司 无锡地铁1号线谈渡桥站商业配套工程项目经理部 2014年9月

无锡地铁1号线土建工程清明桥站 W-3风井改造施工组织设计 一、工程概况 无锡地铁1号线土建工程清明桥站位于无锡市南长区清扬路上,W-3风井位于清扬路茂业商场一侧人行路上,现将W-3风井口向南侧移动11.5m,施工风道及井口,该风道高2.2m,长11.5m,采用明挖法施工。 二、技术要求 1、混凝土采用C35P8混凝土,保护层厚度迎土面为50mm,背土面为40mm。 2、结构植筋用胶粘剂为A级胶,A级胶应满足《混凝土结构加固设计规范》(GB50367-2006)的要求,其耐久性能满足地铁使用年限。植筋施工前须进行约束条件下胶粘剂粘结钢筋与基材混凝土的粘结强度测定,其测定方法应按照《混凝土结构加固设计规范》 (GB50367-2006)附录K进行。植筋边距(即植筋中心距离混凝土构件外边缘)需≥2.5d。 3、应将出入口顶板以上的原风井墙全部凿除后再进行植筋,施工过程中应注意对结构防水层的保护与修补。 4、后建结构与原有结构接缝处理: 水平接缝:水平施工缝浇筑混凝土前,应将混凝土凿毛,清楚表面浮浆和杂物,然后涂刷混凝土界面处理剂、水泥基渗透结晶型防水涂料,再铺30-50mm厚的1:1水泥砂浆,并应及时浇筑混凝土;

垂直接缝:垂直施工缝浇筑混凝土前,应将混凝土凿毛,清理干净其表面,再涂刷混凝土界面处理剂、水泥基渗透结晶型防水涂料,并应及时浇筑混凝土; 接缝处均设置遇水膨胀止水条两道及预埋式注浆管一到进行止水。 风道底板与已施工出入口顶板之间的混凝土应保证其密实。 应严格施工,保证混凝土振捣密实,新旧混凝土界面结合牢靠,防水处理可靠。 三、施工组织 1、人员组织 施工过程中,项目部加强各队的管理和协调,保证劳动力资源的充分利用,并根据现场进度情况,及时调配相关人员,确保工序按期有序进行。 管理人员由谈渡桥站商业配套项目人员担任,配备6人(项目经理1名、生产经理1名、技术负责人1名、安全负责人1名、其他技术人员2人); 施工人员配备20人(凿除工人4人、钢筋工人4人、模板工人4人、植筋工人3人、防水工人3人,杂工2人)。 2、材料组织 根据工程计划安排,制订详细的材料计划,确保工程按期完成。由于施工场地较小,施工所用钢筋、方木、模板、防水材料等提前进入谈渡桥站商业配套工程场地内加工好后倒运至现场直接安装,混凝

主副井冻结施组讲解

山东黄金集团昌邑矿业有限公司 东辛庄矿区100万吨/年采矿工程井巷掘砌主、副井标段井筒冻结工程 施工组织设计 编制:年月日 审核:年月日 批准:年月日 中冶集团华冶资源开发有限公司 邯郸马万水分公司

目录 1 编制依据 2 工程概况 2.1 矿井概况 2.2 建筑地点特征 3 施工准备 3.1 资源准备 3.2 施工现场准备 4 施工方法 4.1 冻结方法 4.2 冷冻站制冷设计 4.3 供配电设计 4.4 钻孔施工技术 4.5 冻结施工技术 5 劳动组织 6 施工工期 7 施工技术要求 8 工程质量保证措施 9 施工安全保证措施

1 编制依据 编制本设计的主要依据是: ⑴昌邑市东辛庄—莲花山矿区主井工程地质孔抽水试验综合成果图; ⑵昌邑市东辛庄—莲花山矿区副井工程地质孔柱状图; ⑶山东省昌邑市东辛庄—莲花山矿区主井、副井、莲花山风井工程地质勘查工程位臵图; ⑷《矿山井巷工程施工及验收规范》(GB213-90); ⑸《冶金矿山井巷工程质量检验评定标准》(YBJ218-89); 2 工程概况 2.1 矿井概况 山东黄金集团昌邑矿业有限公司东辛庄矿区位于昌邑市东南13km,矿井采用立井开拓方式,由于地质及水文地质条件较复杂,采用普通法施工难度大、效率低。为加快矿井建设速度,决定主、副井井筒采用冻结法施工。 表1 井筒技术参数 2.2 建筑地点特征 2.2.1 位臵、交通

项目工作区位于昌邑市东南13km,隶属昌邑市围子镇管辖。极值坐标:东经119°30′45″~119°33′30″,北纬36°48′30″~36°52′30″,矿区距烟(台)—潍(坊)公路4km。昌(邑) —平(度)公路从矿区通过,南距潍(坊) —莱(阳)高速公路石埠出口约8.5km。市、乡(镇)级公路与之相通,交通方便。 2.2.2 自然地理 本区位于潍东北滨海冲洪积平原区,地势平坦,第四系大面积覆盖,仅在

最新副井井筒掘砌施工组织设计终版

副井井筒掘砌施工组织设计终版

编号:001 华兴能源有限责任公司 唐家会煤矿副井井筒及相关硐室掘砌工程 施工组织设计 编制人:王成军 审核人:倪四清 华煤集团有限公司 2011年4月20日

目录 前言 ............................................................................................................................................................... - 1 -第一章工程概况.............................................................................................................................................. - 3 -1.1 矿井概况 ..................................................................................................................................................... - 3 -1.2 井筒技术特征 ............................................................................................................................................. - 3 -1.3地质构造 ..................................................................................................................................................... - 4 -1.4 水文地质情况 ............................................................................................................................................. - 4 -第二章施工准备.............................................................................................................................................. - 5 -2.1 技术工作准备 ............................................................................................................................................. - 5 -2.2 施工力量配备 ............................................................................................................................................. - 5 - 2.3 施工现场准备 ............................................................................................................................................. - 5 - 3.1 施工方案确定原则 ..................................................................................................................................... - 8 -3.2 总体施工方案 ............................................................................................................................................. - 8 -3.3 施工方案的确定 ......................................................................................................................................... - 8 -由于井筒和井塔同时进行立体交叉作业,井筒施工前需要在井塔门洞口搭设8M长安全防护通道。顶部采用双层50MM厚竹跳板、内附一层6MM厚钢板进行防护,两侧挂密布网。 ................................. - 8 -3.4施工主要机械设备 ..................................................................................................................................... - 9 -3.5 凿井设施布置 ............................................................................................................................................. - 9 -

框剪结构施工组织设计完整版

二、主要施工方法 1.测量 1.1 施工测量的准备工作: (1).了解工程的总体布局、定位及标高情况。 (2).对图纸进行校核。 (3).确定放线精度。 (4).测量设备、仪器确保在有效期内。 1.2 建筑定位放线: (1).建筑物平面控制网的测设:建筑物平面控制网的定位依据建筑为原有建筑物,其中新建教学楼南墙外皮距物理楼北墙外皮16.95m,新建教学楼西墙及物理楼西墙平齐。 1).平面控制网的精度要求:根据建筑的结构和使用特点,布网精度为二级,测角中误差为±12",边长相对误差为 1/15000。 2).距离丈量方法:距离丈量采用I级钢尺,进行往返测量。并考虑尺长、温度、倾斜、拉力等各项改正数。具体公式为:

(考虑采用标准拉力,则拉力改正数不计) 式中:L---丈量时钢尺读数 t0---鉴定时标准温度 L0---实际距离 a---钢尺线膨胀系数 L实---钢尺实际长度 t---测量时实际温度 L明--钢尺名义长度 h---两端高差 3).角度测设:采用合格的经纬仪根据已知的起始方向,测设角度。用正倒镜法测出角后,量取距离。 (2).建筑物高程控制网测设:高程引入采用原场区内已知水准点进行测设,本工程布设6个临时水准点,组成建筑物的高程控制网,控制网的测量由专人负责,技术负责人复测。 (3).测设轴线控制桩:根据已布好的建筑物平面控制网,测设轴线控制桩,测设时以两端控制桩为准,测定该边的控制桩,并校核各桩间距,精度同平面控制网。 1.3 基础开挖和基础施工放线: (1).基础开挖放线 1).根据轴线控制点,按图纸尺寸撒出基槽开挖上下口控制线,基槽上口控制线允许偏差为+50mm、-20mm,基

XX煤矿主副风井矿建施工组织设计

XX煤业有限公司 XX矿主、副、风井井筒及相关硐室掘砌 施工组织设计 XXXX 二〇一六年十二月三十日

XX煤业有限公司XX煤矿位于XX煤田东部,太行山南麓,行政隶属XX市所辖的XX县。井田中心西距XX12km,东南距XX县城3km,交通十分便利。矿井设计生产能力为60万t/a,服务年限为37.5a。采用立井开拓方式,工业广场内设计三个立井,分别为主井、副井和回风井。主、副、风井井筒表土段及风化基岩采用冻结法施工,基岩段采用普通钻爆法施工。 经公开招投标,由XXXX中标,承建主、副、风井井筒及相关硐室的掘砌工程,为了有计划的组织劳动力、资金、设备及材料,努力把该工程建设成为优质、安全、快速、高效的工程,特编制本施工组织设计。 本施工组织设计编制依据: 1、XX煤矿主、副、风井井筒掘砌工程招标文件 2、XX煤矿主、副、风井井筒掘砌工程投标书 3、XX煤矿主、副、风井井筒工程施工合同 4、XX煤矿主、副、风井井筒施工图 5、《矿山井巷工程施工及验收规范》(GBJ213-90) 6、《煤矿井巷工程质量检验评定标准》(MT5009-94) 7、《普通混凝土拌合物性能试验方法》(GBJ80-85) 8、《混凝土强度检验评定标准》(GBJ107-87) 9、《普通混凝土配合比设计规程》(JGJ55-2000) 10、《混凝土外加剂应用规范》(GB50119-2003) 11、《混凝土拌合用水标准》(JGJ68-89) 12、《建筑钢结构焊接技术规程》(JGJ81-2002) 13、《钢结构施工质量验收规范》(GB50205-2001) 14、《建筑工程施工质量验收统一标准》(GB50300-2001) 15、《煤矿安装工程质量检验评定标准》(MT5010-95) 16、《煤矿安全规程》(2006年版) 17、《煤矿建设安全规定》(1997年版) 18、《简明建井工程手册》 19、《公司及XX安全质量标准化标准》 20、《XX立井提升、吊挂手册》 21、《煤炭工业建设工程质量技术资料管理规定》 22、《煤炭工业煤矿井巷工程、建筑安装工程单位工程质量保证资料评级办法》 23、GB/T19001-2000 idtISO9001:2000标准 本设计分文字说明书和主要施工图两部分。

主副井空气加热室联合建筑施工组织设计

主副井空气加热室联合建筑施工组织设计 编制: 审核: 批准: 编制单位:中铁三局集团隆安项目部编制时间:2017年9月17日

1编制说明 1.1 编制依据 1.1.1根据施工图纸及答疑文件。 1.1.2施工现场调查、采集、咨询所获得的资料及现场施工条件。 1.1.3现行国家、山西省有关的建筑施工技术规范和行业法规及验收标准。 1.1.4依照ISO9001:2000版标准编制的《管理手册》和《程序文件》。 1.1.5中铁三局集团有限公司工程部颁发的《施工技术管理办法》。 1.1.6本工程采用的技术规范标准: 1.1.6.1施工及验收规范、规程及标准 (1)《工程测量规范》GB50026-93 (2)《工程做法》05J1 (3)《钢筋混凝土过梁》03G322-1 (4)《钢筋混凝土雨篷》03G501-2 (5)《建筑物抗震构造详图》03G363 (6)《建筑物抗震构造详图》97G329-2 (7)标准图集01J925-1、06J925-2 (8)《混凝土结构工程施工质量验收规范》GB50204-2002 (9)《钢筋焊接及验收规程》JGJ18-96 (10)《砌体工程施工质量验收规范》GB50203-2002 (11)《建筑地基基础工程施工及验收规范》GB50202-2002 (12)《建筑地面工程施工及验收规范》GB50209-2002 (13)《建筑装饰装修工程质量验收规范》GB50327-2001 (14)《建筑给水排水采暖工程施工质量验收规范》GB50242-2002 (15)《钢结构工程施工质量验收规范》GB50205-2001

1.1.6.2施工安全管理规范、规程及规定 (1)《建筑施工高处作业安全技术规范》JGJ80-91 (2)《建筑机械使用安全技术规程》JGJ33-2001 (3)《施工现场临时用电安全技术规范》JGJ46-2001 (4)《建设工程施工现场供用电安全规范》GB50194-93 (5)《建筑施工安全检查标准》JGJ59-99 (6)《建筑施工门式钢管脚手架安全技术规范》JGJ128-2000 (7) 山西省建委关于建筑施工现场安全管理的文件及规定。 1.1.7设计单位设计的施工图中涉及到的规范、规程和标准图集及相关技术要求。 1.2 编制原则 1.2.1在坚持实事求是的基础上,力求施工技术先进、科学合理、经济环保、安全文明的原则。 1.2.2结合本工程特点、难点、重点,吸取以往工程的施工经验,运用先进的建筑施工技术、建筑材料和现代化管理手段,实行动态管理,责任落实到人。 1.3 编制范围 隆安煤矿主副井空气加热室联合建筑施工图纸的土建工程。 2工程概况 2.1工程名称及单位 本工程名称:隆安煤矿主副井空气加热室联合建筑。 地理位置:山西省保德县隆安煤矿。 建设单位:山西煤炭运销集团泰山隆安煤业有限公司。 设计单位:太原市明仕达煤炭设计有限公司。 勘察单位:太原市长瑞达岩土工程有限公司。

立井井筒施工组织设计

第三章立井井筒施工组织设计 1.井筒概况 1.1.水文地质 根据根据永夏安全改建工程井筒检查孔地质报告成果资料,井位处地层自上而下为:第四系、第三系、二叠系(上石盒子组、下石盒子组)。副井井位处新生界松散层厚为:340.45m,基岩风化带厚分别为12.87m。北回风井井位处新生界松散层厚为294.03m,基岩风化带厚为29.97m左右。箕斗井、副井和回风井井筒基岩段有两个主要含水层,煤间砂岩裂隙第一含水层(段),其垂深在1147.50米~1154.00米,厚度为60~100米;第二含水层(段),其垂深在1267.50米~1329.00米,厚度30~40m。副井井筒基岩段全井筒混合含水层涌水量171.55m3/h。二叠系煤系各砂岩裂隙含水层(段)由于砂岩裂隙不发育,富性弱,渗透性差,在自然状态下,地下水运动缓慢,处于半封闭状态,地下水补给、排泄条件差,以储存量为主。主要为区域层间补给、迳流、排泄。垂向上各含水层(段)之间都有相应的隔水层,正常情况下无直接水力联系。 副井基岩段两个含水层均在设计水平以下,其风化带以下至井底水平之间没有较大的含水层。 二叠系地层岩性主要由砂岩、粉砂岩、泥岩及煤层组成,以泥岩、粉砂岩为主,砂岩次之。不同岩石的抗压强度大小不同,一般是砂岩>粉砂岩>泥岩。而风氧化带岩石由于风化裂隙发育,受地下水作用影响,岩石的抗压强度明显降低。总体上二叠系基岩段岩体工程质量较差,岩性软弱。 预计井筒涌水量见副井井筒单层涌水量计算结果表3—1 表3—1副井井筒单层涌水量计算结果表 含水层名称井筒深度(m)涌水量(m3/h) 基岩风化带322.33~333.10 110 K5砂层326.97~372.18 400 三煤下砂层443.85~447.13 150 二煤顶砂层483.4~489 75 K3灰岩547.92~549.73 15

钢结构施工组织设计 完整版

一综合说明 1. 1工程简介 本施工组织设计是根据施工工程图纸和招标文件,针对工程特点, 结合可操作性编制的,仅对于该工程的钢结构施工 ,内容包括:①施工部署②加工制作及生产工艺,③施工组织设计等 工程名称: 建设地址: 建设单位: 1. 2 编制依据: 1.2.1 工程招标文件 1.2.2 《建筑结构设计规范》 1.2.3 《钢结构设计规范》 1.2.4 《冷弯薄壁型钢结构设计规范》 1.2.5 《建筑抗震设计规范》 1.2.6 《钢结构工程施工及验收规范》 1.2.7 《钢结构高强螺栓连接的设计、施工及验收规范》 1.2.8 《门式钢架轻型房屋钢结构技术规程》 1. 3 指导思想 确保工程质量,达到设计意图,达到预定的工期目标。选配高素质的项目班子及工程技术管理人员,遵照 ISO9002《质量管理和质量保证》的标准,建立工程质量保

证体系,积极推广应用新技术新工艺、新材料、新设备,以强有力的管理和技术手段措施,确保施工的顺利进行。 1. 4 实施目标 1.4.1工期目标:我方保证按时完工。合理安排施工工工序,制作和安装的交叉施工,力争提前完工。 1.4.2质量目标:确保工程达到“合格”等级标准。 1.4.3 安全文明施工目标:杜绝重大人身伤亡和机械事故,确保安全文明施工。 1.4.4 服务目标:信守合约,密切配合,做好施工图纸深化工作, 配合解决有关的设计问题,自觉接受业主和监理的检查监督。 二施工组织设计第一章:施工部署 1. 1 施工准备 1. 2 施工组织机构 1. 3 施工顺序 1. 4 主要劳力装配计划 1. 5 主要设备、机具、仪器计划表 1. 6 现场施工平面布置图及现场供水、供电和临时设施第二章:加工制作组织与生产工艺 钢构部分 2. 1 钢板 2. 2 焊材

矿建工程施工组织设计编制

矿建工程施工组织设计编制 施工组织设计是矿建工程项目实施科学管理的重要依据,必须引起项目管理者的高度重视,从而保障矿建工程进度、质量、安全管理目标的实现。本文对矿建工程如何编制施工组织设计进行分析,并就如何充分发挥施工组织设计的作用进行探讨。 标签:施工组织设计;矿建工程;编制 1、施工组织设计的作用 施工组织设计是指拟定工程项目施工过程的组织、技术和经济等实施方案的综合性设计文件。它是工程开工后施工活动能有序、高效、科学合理地进行的保证,是确保实现工期、质量目标和施工安全、创建文明工地、节约成本等施工目标的保证。工程施工组织设计,即针对目标工程所在地所具备的自然、社会、人文等资源现状,综合考虑工程设计的目标任务,采用科学的方式方法来实现各种施工方案的具体实施。 2、矿建工程施工组织设计的任务与分类 2.1矿建工程施工组织设计的任务 矿建工程施工组织设计的任务主要是把工程项目在整个施工过程所需用的人力、材料、机械、资金和时间等因素,按照客观的经济技术规律,科学地做出合理安排。使之达到耗工少、速度快、质量高、成本低、安全好、利润高的要求。 2.2矿建工程施工组织设计的分类 (1)建设项目(矿区)施工组织总设计以整个建设项目为对象。它是在建设项目总体规划批准后,依据相应的规划文件和现场条件编制。矿区建设组织设计由建设单位或委托有资质的设计单位或由项目总承包单位进行编制。矿区建设组织设计,要求在国家正式立项后和施工准备大规模开展之前进行编制并预审查完毕。 (2)单项工程施工组织设计以单项工程为对象,根据施工组织总设计和对单项工程的总体部署要求完成的,可直接用于指导施工。适用于新(改扩)建矿井、选矿(煤)厂或构成单项工程的输变电工程、矿区机修厂、办公大楼、职工宿舍、总仓库等。单项工程(矿井)施工组织设计的编制与审批主要分两个阶段进行。开工前的准备阶段,为满足招标工作的需要,由建设单位单项工程(矿井)施工组织设计,其主要内容是着重于大的施工方案、总工期及总投资概算的安排,对建设单位编制的施工组织设计由上级部门进行审批,一般在建设工程大规模开工前6个月完成。经过招投标后的施工阶段,由已确定的施工单位或总承包单位再编制详尽的施工组织设计,作为指导施工的依据。施工单位编制的施工组织设

林华副井井架施工组织设计文档

编制依据: 1、施工图 2、施工及验收规范: 《施工现场临时用电安全技术规范》(JGJ46-2005) 《建筑施工高处作业安全技术规范》(GBJ80-91) 《建筑机械安全技术规范》(GBJ33-86) 《钢结构工程施工及验收规范》(GB50205-95) 3、主要质量检验评定标准 《煤矿安装工程质量检验评定标准》MT5010-95 《建筑施工安全检查评定标准》(GBJGJ59-99) 《钢结构工程质量检验评定标准》(GB50211-95) 4、《煤矿安全规程》2006年版 5、中煤五公司《一体化管理体系文件》

1、工程概况 贵州林华矿业有限公司林华矿井副井井架安装工程由贵州煤矿设计研究院设计。本井架为四斜柱式钢井架,主要构件采用箱形截面。斜撑为箱形梁柱组成的框架结构,斜撑下端与混凝土基础铰接,立架部分为桁架式钢结构,该井架设三层平台,第一层下天轮平台标高20.850m, 第二层上天轮平台标高 26.350m,第三层为起重设备平台标高33.400m,井架结构及技术特征如下: ⑴总高度:高33.400m (主斜架长:34.55m 副架高:20.350m) ⑵天轮中心高度:上天轮:+27.000m 下天轮:21.500m ⑶天轮直径:Ф3.5m ⑷主斜架与地面夹角:70. 747° ⑸井架基础上平面标高:+0.800m ⑹井架总重量:210吨(主斜架重140T)(不带梯子栏杆) 2、施工部署 2.1施工项目管理组织 (见项目组织机构框图) 2.2总施工方案 土建基础施工时,按设计位置把铰链预埋件预埋设好。井架采用现场组装,井架主斜架采用单抱杆承力翻转倒杆提升法施工,立架采用滑移提升法施工。 井架加工防腐完毕运到安装地点后即可进行井架的组装、安装。 2.3质量目标工程质量优良。 2.4劳动力组织

矿井施工组织设计完整版

(此文档为word格式,下载后您可任意编辑修改!) 第一章概述 第一节矿井施工组织设计编制依据与原则 一、编制原则 1.执行国家及煤炭建设的方针和经济政策; 2.统筹安排内部与外部;生产与生产服务、生活服务之间的协调建设,通过综合平衡,确定合理建设工期。 3.以矿建为主,全面安排井下与地面、生产与生活的建设顺序,做到“五通一平”先行,环保绿化同步。 4.充分利用时间和空间,在确保安全、质量和经济效益的前提下,合理组织矿井建设全过程的各个环节、各项工作及各个工程项目之间的平行交叉作业和协调建设。 5.以经济效益为中心,突出市场经济和竞争意识,增加时间观念、利息观念和资金周转观念,尽快形成综合生产能力,缩短建设工期。 6.结合矿井建设实际,扬长避短,大胆探索。 7、依靠科技进步,积极采用新技术、新装备、新材料、新工艺。 8、因地制宜、就地取材、降低工程成本。 9、合理利用永久设施建井,减少大临工程‘ 10、积极进行施工准备,缩短施工准备工期。

11、在工作安排上,做到“四个优先安排”即被利用永久工程优先安排,工期长的工程优先安排,安装任务重的工程优先安排,大型工程优先安排;“四个不停”即矿井主要矛盾线上的工程不停,井筒装备时提升不停,井巷交叉施工时运输不停,单位工程开工后不停;“三个缓干”即需要长期维护的煤巷缓干,用作平衡劳动力的工程缓干,建设期间不使用的井下电器设备缓购,力争做到劳动力、施工设备的基本平衡。 二、编制依据 1.批准的地质报告、矿井初步设计及概算。 2.建设单位与有关单位签订的协议。 3.矿井建设的客观条件及现场条件。 4.国家及煤炭工业有关经济技术方面的政策、法令、规程、规范、标准等。 第二节矿井设计概论 根据山西省煤矿企业兼并重组整合工作领导组办公室文件(晋煤重组办发[2009]110号文),批准以山西煤销集团为主体对古交市屯川矿、马兰镇营立矿、古交后沟煤矿、白道煤矿有限公司进行兼并重组整合,整合后企业名称为山西煤销集团古交铂龙煤业有限公司,井田面积5.995km2。开采煤层为02、2、4、8、9号煤层。 矿井保有储量51.61mt,可采储量29.14 mt。矿井设计生产能力为120万吨,矿井服务年限为17.3a。 一、矿井设计方案

矿山建设工程施工组织设计范本

矿山建设工程施工组织设计范本

第一章矿井概况 一设计编制依据 1 井筒地质柱状图 2 <煤矿安全规程> 3 <煤矿井巷工程质量检验评定标准> 二矿井条件 本矿井为城郊矿井,设计服务年限为30年。城郊矿井的设计生产能力位240万吨。 本次设计的井筒为副井井筒。井筒净直径8.5m,井筒的深度为680m,副井井筒的开拓方式为立井开拓,通风方式为中央分列式通风系统。煤层含沼气的等级及突出危险程度:低沼气,无突出。 副井井筒的表土段深230m,表土段井壁结构为双层钢筋混凝土井壁,内壁的厚度为450mm,外壁的厚度为500mm。基岩段厚430m,为普通混凝土井壁,厚650mm,混凝土标号为C30。 井筒内提升容器采用单层双车罐笼,提升容器导向装置的结构类型采用组合罐笼。井筒的提升方位角为15o。 三矿井水文地质情况 (一) 表土厚度及类型:表土土层为第四纪冲击层,厚度为230m (二) 含水情况:表土含水情况为3 200m,表土下方的风化基岩带厚度为20m,基岩为泥岩和粉砂岩,厚度为430m,基岩岩倾角为08,含水情况为400~430m,m3 30。 四井筒特征

(一)副井井筒特征表 表1-1 副井井筒特征表 (二)井筒断面布置形式 井筒断面布置形式如图1-1所示: 图1-1 井筒断面布置图

第二章井筒基岩段施工方案 一、选择施工方案时应考虑的因素: (一)井筒穿过岩层的性质,涌水量的大小。 (二)井筒直径和深度(主要指基岩部分的深度)。 (三)可能采用的施工工艺及技术装备条件。 (四)施工队伍的操作技术水平和施工管理水平。 选择施工方式,首先要求技术先进,安全可行,有利于采用新型凿井装备,不但能获得单月最高纪录,更重要的是能取得较高的平均成井速度,并应有明显的经济效益。 二、现有立井井筒基岩段施工方案分析 (一)掘、砌单行作业 凿井时将井筒划分为若干段高,自上而下分段施工,在同一段高内,按照掘砌先后交替顺序作业称为单行作业且由于掘进的段高不同,单行作业又分为长段单行作业和短段平行作业。

最新nl明挖段及中间风井施工组织设计

n l明挖段及中间风井施工组织设计

目录 目录 (1) 第一章编制说明 (5) 1.1编制依据 (5) 1.2编制范围 (5) 1.3编制原则 (6) 第二章工程简介 (7) 2.1工程概况 (7) 2.2工程地质及水文地质 (7) 2.3周围环境、交通及管线情况 (14) 2.4工程特点、重点、难点与对策 (15) 2.5关键部位、关键工序主要对策 (16) 第三章施工部署及施工进度计划 (19) 3.1施工总体部署 (19) 3.1.1施工总体部署原则 (19) 3.1.2总体目标 (19) (1)职业安全健康目标 (19) (2)工程质量目标 (19) (3)安全目标 (19) 3.1.3施工总体部署的主要依据 (20) 3.1.4施工顺序及流程 (20) 3.2施工总体方案 (25) 3.2.1明挖段总体施工方案 (25) 3.2.2中间风井总体施工方案 (25) 3.3进度计划 (25) 3.3.1项目总工期要求 (25) 3.3.2明挖段、中间风井进度计划分析 (26) 3.3.3施工进度计划 (27) 第四章施工组织机构及资源配置 (28) 4.1施工组织机构 (28) 4.1.1项目部组织机构 (28) 4.2机械设备配备 (29) 4.2.1明挖段、中间风井土建施工机械设备 (29) 4.3材料供应计划及材料保证措施 (31) 4.3.1土建工程材料供应计划 (31) 4.3.2材料保证措施 (32) 第五章施工现场平面布置及交通疏解 (34) 5.1施工现场布置 (34)

5.1.1施工场地布置原则 (34) 5.1.2各工区施工场地平面布置图 (34) 5.1.3临时设施 (35) 5.1.4临时供电系统 (35) 5.1.5临时给水系统 (40) 5.1.6弃土、弃渣 (40) 5.1.7现场消防 (41) 5.1.8施工临时通讯设施 (41) 5.1.9预防地表水和地下水污染的设施 (41) 5.1.10施工现场视频监控系统 (41) 5.1.11门禁系统 (42) 5.2施工期间排水和防洪措施 (43) 5.2.1施工期间排水 (43) 5.2.2现场防洪 (43) 第六章盾构始发井明挖段施工 (45) 6.1工程概况 (45) 6.1.1工程简介 (45) 6.1.2工程地质及水文地质情况 (45) 6.1.3设计情况 (46) 6.1.4交通疏解与管线迁改保护 (46) 6.2施工方案 (48) 6.2.1盾构始发井明挖段施工工序 (48) 6.2.2主体主要分项工程施工方案 (48) 6.2.2.1 基坑围护结构施工 (48) 6.2.2.2 基坑开挖与支撑体系施工 (62) 6.2.2.3 结构防水工程施工 (87) 6.2.2.4 主体结构施工 (94) 1、主体施工流程 (94) 2、施工准备 (94) 3、垫层施工 (94) 4、底板施工 (95) 5、侧墙、中隔墙施工 (97) 6、顶板施工 (98) 7、结构施工技术措施 (99) 6.2.2.5 顶板回填及地面恢复 (103) 第七章中间风井施工 (105) 7.1工程概况 (105) 7.1.1工程简介 (105) 7.1.2工程地质及水文地质情况 (105) 7.1.3设计情况 (106) 7.1.4交通疏解与管线迁改保护 (106) 7.2施工方案 (107) 7.2.1中间风井施工工序 (107)