1 SATIP-W-011-01 Welding of On-Plot Piping--Rev1

WELDING OF ON-PLOT PIPING

Receiving Inspection and Verification of Welding Consumables-(Properties, Type, approve source, storage, etc.) Welder & Welding Operator

Certifications (and Issuance of JCC)SAIC-W-2035CHECKLIST and/or

TEST RECORD

1.0

Welding Procedure

Specifications/Welding Procedure Qualification Record (WPS/WPQR)SAIC-W-2001Non-Destructive Testing Procedures Post Weld Heat Treatment (PWHT) Procedure

SAIC-W-2003Procedure for Weld Identification and Weld Traceability (Original Welds and modified/repaired welds)

PROJECT TITLE:

2.0

MATERIAL RECEIVING

1.21.1DOCUMENT REVIEW

SATIP-W-011-0125-May-05

RH1R1

RH1

RH1REMARKS

INSPECTION RESPONSIBILITY

ASSIGNMENTS

SAUDI ARAMCO

PROJECT PHASE TASK / ACTIVITY

CNTRCTR

ITEM NO.RH1

QUALITY RECORD

MECHANICAL

S. Aramco shall verify and inspect the first batch of delivered consumables, then random inspection thereafter.

CONTRACTOR/SUBCONTRACTOR

RH1RH1Random witnessing by S. Aramco at each calibration cycle.

H1W2

Refer to the respective SATIP for NDE (SATIP-NDE-UT-01, LPT-01, MPT-01, RT-01)

RH1

1.51.4RH1RH11.7Positive Material Identification Procedure (Alloy Verification)

SAIC-L-2004

SAIC-W-2008W2

H1RH1

RH1

RH1R1

SAIC-W-2010SATR-W-20092.2SAIC-W-2011SATR-W-2011

Welding Equipment Calibration Verification

SAIC-W-20111.6Production Weld Hardness Testing Procedure

SAIC-W-20121.81.92.1SAIC-W-2010Procedure for Control of Welding Consumables

SAIC-W-2009

1.3Method Statement & WPS for Weld Repair, ie:

a) Crack and other weld defects b) Weld mis-alignments

SAIC-W-2002RH1RH1

WELDING OF ON-PLOT PIPING

CHECKLIST and/or

TEST RECORD

PROJECT TITLE:

SATIP-W-011-0125-May-05

REMARKS

INSPECTION RESPONSIBILITY

ASSIGNMENTS

SAUDI ARAMCO

PROJECT PHASE TASK / ACTIVITY

CNTRCTR

ITEM NO.

QUALITY RECORD MECHANICAL

CONTRACTOR/SUBCONTRACTOR

Saudi Aramco inspection responsibility varies from H1 to W1:

a) "W1" -for build-up thickness not exceeding 1/3 of the metal thickness or 10mm whicever is less.b) "H1" - for build-up thickness exceeding the above and requiring CSD's approval.

S. Aramco's responsibilities varies as follows:

a) "W2" - for Welding on normal services at normal conditions, refer to Note 1 of the General Notes.b) "H1" - for critical welds, ie.; Tie-Ins, buttering, Hot Taps, NDE-In-Lieu of Hydro & others as determined by project requirements.

Pre-Welding & Weld Joint Fit-Up Inspection

SAIC-W-2033SATR-W-2006

H1W1/H1

3.5Buttering or Weld Build-Up of Joints SAIC-W-2033

H1

S

3.2

Welding of Strip Linings (If Required)

3.3

Welding of Special Corrosion-Resistant Materials (If Required)

3.6

SAIC-W-2006

3.7SAIC-W-2006SATR-W-2007

In-Process Weld Inspection SAIC-W-2032SATR-W-2010

H13.4Control of Welding Consumables- Storage, Handling, Issuance & Conditioning

SAIC-W-2032

See SATIP No: W-016-01

W2/H1(See remarks)

SAIC-W-2005

SAIC-W-2005SATR-W-2006

3.0INSTALLATION

See SATIP N0: W-016-01 and other applicable SATIP-W series (if required)See SATIP No: W-014-01

Refer to Note 1 of the General Notes for S.Aramco Inspection responsibility, afterwhich pre-arranged witnessing shall be agreed upon.

W1

2.3

H1S. Aramco's responsibilities varies as follows:

a) "S " - Generally is a surveillance activity for Saudi Aramco, except in welding of stainless steel piping and piping in low temp service.

b) "W2" - S. Aramco inspects and verifies Heat Input at random or on routine basis for low temp service and for stainless steel welding.

S/W2(See remarks)

W1

3.1Welding of Overlays & Clad Materials (If Required)

Positive Material Identification of Low Alloy, Stainless Steel, Nickel & Copper Based Materials (If Required)

SAIC-L-2010SAIC-L-2010SATR-A-2012SATR-A-2013

WELDING OF ON-PLOT PIPING

CHECKLIST and/or

TEST RECORD PROJECT TITLE:

SATIP-W-011-0125-May-05

REMARKS

INSPECTION RESPONSIBILITY

ASSIGNMENTS

SAUDI ARAMCO

PROJECT PHASE TASK / ACTIVITY

CNTRCTR

ITEM NO.

QUALITY RECORD

MECHANICAL

CONTRACTOR/SUBCONTRACTOR

For Saudi Aramco Responsibility:

a) "W1" -PID Inspectors shall participate in the seletion of weld to be radiographed. b) "W2" - will be in effect once the level of confidence to the QC is established.SATR-W-2007H1W1/W2

3.11Selection of Weld Joints for NDE SAIC-W-2015SAIC-W-2014

3.15

SAIC-W-2014SATR-W-2012

W1& R1

H1SAIC-W-2004SATR-W-2005

3.12

H1W1/RH1Verification of Hardness Testing Application and Results

SAIC-W-20043.13

3.14 Post Weld Heat Treatment Inspection

3.9Post-Welding Visual Inspection SAIC-W-20073.10

SAIC-W-2013

SAIC-W-2013

H1R1See Remarks Repair of Weld Joints or Base Metal by Welding (Prior to Weld Acceptance)

Verification of Non-Destructive

Examination Method Application and Evaluation of Results

See Remarks W1 & R1

Refer to Note 1 of the General Notes for S.Aramco Inspection responsibility, afterwhich pre-arranged witnessing shall be agreed upon.

* Use the applicable SATIPS: a) SATIP-NDE-LT-01b) SATIP-NDE-LPT-01c) SATIP-NDE-MPT-01d) SATIP-NDE-RT-01e) SATIP-NDE-UT-01

**Refer to Note 1 of the General Notes for S.Aramco Inspection responsibility, afterwhich

pre-arranged or random Witnessing shall be agreed upon.

Refer to Note 1 of the General Notes for S.Aramco Inspection responsibility, afterwhich pre-arranged witnessing shall be agreed upon.

S. Aramco reviews on weekly basis.

W1/R1

W1

S

Weekly reporting of the following: a) Production Weld Status,

b) Welder & Project Repair Rate c) Welder's Repair Assessment & Tracer Welds

SAIC-W-2016

SAIC-W-2016SATR-W-2013SATR-W-2018SATR-W-2019SAIC-W-2037SAIC-W-2007SATR-W-2007H1W1SAIC-W-2037H1W13.8Inspect Welding of Socket Joint and Seal Welding Threaded Jts.

WELDING OF ON-PLOT PIPING

CHECKLIST and/or

TEST RECORD

PROJECT TITLE:

SATIP-W-011-0125-May-05

REMARKS

INSPECTION RESPONSIBILITY

ASSIGNMENTS

SAUDI ARAMCO

PROJECT PHASE TASK / ACTIVITY

CNTRCTR

ITEM NO.

QUALITY RECORD MECHANICAL

CONTRACTOR/SUBCONTRACTOR

SAIC-W-2036

H1H1

3.17Weld Modification or Re-Work After Weld Acceptance

SAIC-W-2036Positive Material Identification (PMI) of Deposited Weld for alloyed materials within the scope of SAES-A-206. SAIC-L-20103.16

SAIC-L-2010SATR-A-2012SATR-A-2013H1W\1 & R1

Refer to Note 1 of the General Notes for S.Aramco Inspection responsibility, afterwhich pre-arranged or random Review shall be agreed upon.

Refer to Note 1 of the General Notes for S.Aramco Inspection responsibility, afterwhich pre-arranged witnessing shall be agreed upon.

R1

H112The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the levels of Saudi Aramco participation based upon the Contractor’s performance.

Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization

4.1Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative is not present.

R1W2Final Welding Inspection &

Documentation (Welding Summary Report / Record & Weld Map)

LEGEND

43SATR-W-2008Surveillance

RH1RH2100% Review and Approval of Documents Sample Review and Approval of Documents W1R2

Sample Hold Point for QC Inspection or Test 100% Review of Documents H1

100% Witness Inspection/Test Sample Witness Inspection/Test

100% Hold Point for QC Inspection or Test

Sample Review of Documents

S

H2PRE-COMMISSIONING

GENERAL NOTES

If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

5

Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance. 4.0