1. Unit costs provide essential information needed for inventory valuation and preparation of

income statements. Knowing unit costs is also critical for many decisions such as bidding decisions and accept-or-reject special order decisions.

2. Cost measurement is determining the dollar amounts associated with resources used in

production. Cost assignment is associating the dollar amounts, once measured, with units produced.

3. An actual overhead rate is rarely used because of problems with accuracy and timeliness.

Waiting until the end of the year to ensure accuracy is rejected because of the need to have timely information. Timeliness of information based on actual overhead costs runs into diffi-culty (accuracy problems) because overhead is incurred nonuniformly and because produc-tion also may be nonuniform.

4. For plantwide rates, overhead is first collected in a plantwide pool, using direct tracing. Next,

an overhead rate is computed and used to assign overhead to products.

5. First stage: Overhead is assigned to production department pools using direct tracing, driver

tracing, and allocation. Second stage: Individual departmental rates are used to assign overhead to products as they pass through the departments.

6. Departmental rates would be chosen over plantwide rates whenever some departments are

more overhead intensive than others and if certain products spend more time in some de-partments than they do in others.

7. Plantwide overhead rates assign overhead to products in proportion to the amount of the

unit-level cost driver used. If the products consume some overhead activities in different proportions than those assigned by the unit-level cost driver, then cost distortions can oc-cur (the product diversity factor). These distortions can be significant if the nonunit-level overhead costs represent a significant proportion of total overhead costs.

8. Low-volume products may consume nonunit-level overhead activities in much greater pro-

portions than indicated by a unit-level cost driver and vice versa for high-volume products. If so, then the low-volume products will receive too little overhead and the high-volume prod-ucts too much.

9. If some products are undercosted and others are overcosted, a firm can make a number of

competitively bad decisions. For example, the firm might select the wrong product mix or submit distorted bids.

10. Nonunit-level overhead activities are those overhead activities that are not highly correlated

with production volume measures. Examples include setups, material handling, and inspec-tion. Nonunit-level cost drivers are causal factors—factors that explain the consumption of nonunit-level overhead. Examples include setup hours, number of moves, and hours of in-spection.

11. Product diversity is present whenever products have different consumption ratios for differ-

ent overhead activities.

12. An overhead consumption ratio measures the proportion of an overhead activity consumed

by a product.

13. Departmental rates typically use unit-level cost drivers. If products consume nonunit-level

overhead activities in different proportions than those of unit-level measures, then it is poss-ible for departmental rates to move even further away from the true consumption ratios, since the departmental unit-level ratios usually differ from the one used at the plant level. 14. Agree. Prime costs can be assigned using direct tracing and so do not cause cost distor-

tions. Overhead costs, however, are not directly attributable and can cause distortions. For example, using unit-level activity drivers to trace nonunit-level overhead costs would cause distortions.

15. Activity-based product costing is an overhead costing approach that first assigns costs to

activities and then to products. The assignment is made possible through the identification of activities, their costs, and the use of cost drivers.

16. An activity dictionary is a list of activities accompanied by information that describes each

activity (called attributes)

17. A primary activity is consumed by the final cost objects such as products and customers,

whereas secondary activities are consumed by other activities (ultimately consumed by pri-mary activities).

18. Costs are assigned using direct tracing and resource drivers.

19. Homogeneous sets of activities are produced by associating activities that have the same

level and that can use the same driver to assign costs to products. Homogeneous sets of activities reduce the number of overhead rates to a reasonable level.

20. A homogeneous cost pool is a collection of overhead costs that are logically related to the

tasks being performed and for which cost variations can be explained by a single activity driver. Thus, a homogeneous pool is made up of activities with the same process, the same activity level, and the same driver.

21. Unit-level activities are those that occur each time a product is produced. Batch-level activities

are those that are performed each time a batch of products is produced. Product-level or sus-taining activities are those that are performed as needed to support the various products produced by a company. Facility-level activities are those that sustain a factory’s general manufacturing process.

22. ABC improves costing accuracy whenever there is diversity of cost objects. There are vari-

ous kinds of cost objects, with products being only one type. Thus, ABC can be useful for improving cost assignments to cost objects like customers and suppliers. Customer and supplier diversity can occur for a single product firm or for a JIT manufacturing firm.

23. Activity-based customer costing can identify what it is costing to service different customers.

Once known, a firm can then devise a strategy to increase its profitability by focusing more on profitable customers, converting unprofitable customers to profitable ones where possi-ble, and ―firing‖ customers that cannot be made profitable.

24. Activity-based supplier costing traces all supplier-caused activity costs to suppliers. This

new total cost may prove to be lower than what is signaled simply by purchase price.

EXERCISES

4–1

1.

Quarter 1 Quarter 2 Quarter 3 Quarter 4 Total Units produced 400,000 160,000 80,000 560,000 1,200,000 Prime costs $8,000,000 $3,200,000 $1,600,000 $11,200,000 $24,000,000 Overhead costs $3,200,000 $2,400,000 $3,600,000 $2,800,000 $12,000,000 Unit cost:

Prime $20 $20 $20 $20 $20

Overhead 8 15 45 5 10

Total $28 $35 $65 $25 $30 2. Actual costing can produce wide swings in the overhead cost per unit. The cause

appears to be nonuniform incurrence of overhead and nonuniform production (sea-sonal production is a possibility).

3. First, calculate a predetermined rate:

OH rate = $11,640,000/1,200,000

= $9.70 per unit

This rate is used to assign overhead to the product throughout the year. Since the driver is units produced, $9.70 would be assigned to each unit. Adding this to the actual prime costs produces a unit cost under normal costing:

Unit cost = $9.70 + $20.00 = $29.70

This cost is close to the actual annual cost of $30.00.

4–2

1. Predetermined rates:

Drilling Department: Rate = $600,000/280,000 = $2.14* per MHr

Assembly Department: Rate = $392,000/200,000

= $1.96 per DLH

*Rounded

2. Applied overhead:

Drilling Department: $2.14 ? 288,000 = $616,320

Assembly Department: $1.96 ? 196,000 = $384,160

Overhead variances:

Drilling Assembly Total Actual overhead $602,000 $ 412,000 $ 1,014,000

Applied overhead 616,320 384,160 1,000,480

Overhead variance $ (14,320) over $ 27,840 under $ 13,520

3. Unit overhead cost = [($2.14 ? 4,000) + ($1.96 ? 1,600)]/8,000

= $11,696/8,000

= $1.46*

*Rounded

4–3

1. Yes. Since direct materials and direct labor are directly traceable to each product,

their cost assignment should be accurate.

2. Elegant: (1.75 ? $9,000)/3,000 = $5.25 per briefcase

Fina: (1.75 ? $3,000)/3,000 = $1.75 per briefcase

Note: Overhead rate = $21,000/$12,000 = $1.75 per direct labor dollar (or 175 per-cent of direct labor cost).

There are more machine and setup costs assigned to Elegant than Fina. This is clearly a distortion because the production of Fina is automated and uses the ma-chine resources much more than the handcrafted Elegant. In fact, the consumption ratio for machining is 0.10 and 0.90 (using machine hours as the measure of usage). Thus, Fina uses nine times the machining resources as Elegant. Setup costs are similarly distorted. The products use an equal number of setups hours.

Yet, if direct labor dollars are used, then the Elegant briefcase receives three times more machining costs than the Fina briefcase.

3. Overhead rate = $21,000/5,000

= $4.20 per MHr

Elegant: ($4.20 ? 500)/3,000 = $0.70 per briefcase

Fina: ($4.20 ? 4,500)/3,000 = $6.30 per briefcase

This cost assignment appears more reasonable given the relative demands each product places on machine resources. However, once a firm moves to a multipro-duct setting, using only one activity driver to assign costs will likely produce product cost distortions. Products tend to make different demands on overhead activities, and this should be reflected in overhead cost assignments. Usually, this means the use of both unit- and nonunit-level activity drivers. In this example, there is a unit-level activity (machining) and a nonunit-level activity (setting up equipment). The consumption ratios for each (using machine hours and setup hours as the activity drivers) are as follows:

Elegant Fina

Machining 0.10 0.90 (500/5,000 and 4,500/5,000)

Setups 0.50 0.50 (100/200 and 100/200)

Setup costs are not assigned accurately. Two activity rates are needed—one based on machine hours and the other on setup hours:

Machine rate: $18,000/5,000 = $3.60 per MHr

Setup rate: $3,000/200 = $15 per setup hour

Costs assigned to each product:

Machining: Elegant Fina

$3.60 ? 500 $ 1,800

$3.60 ? 4,500 $ 16,200

Setups:

$15 ? 100 1,500 1,500

Total $ 3,300 $ 17,700

Units ÷3,000 ÷3,000

Unit overhead cost $ 1.10 $ 5.90

4–4

Activity dictionary:

Activity Activity Primary/ Activity

Name Description Secondary Driver Providing nursing Satisfying patient Primary Nursing hours care needs

Supervising Coordinating Secondary Number of nurses nurses nursing activities

Feeding patients Providing meals Primary Number of meals

to patients

Laundering Cleaning and Primary Pounds of laundry bedding and delivering clothes

clothes and bedding

Providing Therapy treatments Primary Hours of therapy physical directed by

therapy physician

Monitoring Using equipment to Primary Monitoring hours patients monitor patient

conditions

4–5

1. Deluxe Percent Regular Percent

Price $900 100% $750 100% Cost 576 64 600 80

Unit gross profit $324 36% $150 20% Total gross profit:

($324 ? 100,000) $32,400,000

($150 ? 800,000) $120,000,000

2. Calculation of unit overhead costs:

Deluxe Regular Unit-level:

Machining:

$200 ? 100,000 $20,000,000

$200 ? 300,000 $60,000,000 Batch-level:

Setups:

$3,000 ? 300 900,000

$3,000 ? 200 600,000 Packing:

$20 ? 100,000 2,000,000

$20 ? 400,000 8,000,000 Product-level:

Engineering:

$40 ? 50,000 2,000,000

$40 ? 100,000 4,000,000 Facility-level:

Providing space:

$1 ? 200,000 200,000

$1 ? 800,000 800,000 Total overhead $ 25,100,000 $ 73,400,000 Units ÷100,000 ÷800,000 Overhead per unit $ 251 $ 91.75

Deluxe Percent Regular Percent Price $900 100% $750.00 100% Cost 780* 87*** 574.50** 77*** Unit gross profit $120 13%*** $175.50 23%*** Total gross profit:

($120 ? 100,000) $12,000,000

($175.50 ? 800,000) $140,400,000

*$529 + $251 **$482.75 + $91.75 ***Rounded

3. Using activity-based costing, a much different picture of the deluxe and regular

products emerges. The regular model appears to be more profitable. Perhaps it should be emphasized.

4–6

1. JIT Non-JIT

Sales a$12,500,000 $12,500,000

Allocation b750,000 750,000

a$125 ? 100,000, where $125 = $100 + ($100 ? 0.25), and 100,000 is the average order size times the number of orders

b0.50 ? $1,500,000

2. Activity rates:

Ordering rate = $880,000/220 = $4,000 per sales order

Selling rate = $320,000/40 = $8,000 per sales call

Service rate = $300,000/150 = $2,000 per service call

JIT Non-JIT

Ordering costs:

$4,000 ? 200 $ 800,000

$4,000 ? 20 $ 80,000

Selling costs:

$8,000 ? 20 160,000

$8,000 ? 20 160,000

Service costs:

$2,000 ? 100 200,000

$2,000 ? 50 100,000

T otal $ 1,160,000 $ 340,000

For the non-JIT customers, the customer costs amount to $750,000/20 = $37,500 per order under the original allocation. Using activity assignments, this drops to $340,000/20 = $17,000 per order, a difference of $20,500 per order. For an order of 5,000 units, the order price can be decreased by $4.10 per unit without affecting customer profitability. Overall profitability will decrease, however, unless the price for orders is increased to JIT customers.

3. It sounds like the JIT buyers are switching their inventory carrying costs to Emery

without any significant benefit to Emery. Emery needs to increase prices to reflect the additional demands on customer-support activities. Furthermore, additional

price increases may be needed to reflect the increased number of setups, pur-chases, and so on, that are likely occurring inside the plant. Emery should also im-mediately initiate discussions with its JIT customers to begin negotiations for achieving some of the benefits that a JIT supplier should have, such as long-term contracts. The benefits of long-term contracting may offset most or all of the in-creased costs from the additional demands made on other activities.

4–7

1. Supplier cost:

First, calculate the activity rates for assigning costs to suppliers:

Inspecting components: $240,000/2,000 = $120 per sampling hour

Reworking products: $760,500/1,500 = $507 per rework hour

Warranty work: $4,800/8,000 = $600 per warranty hour

Next, calculate the cost per component by supplier:

Supplier cost:

Vance Foy Purchase cost:

$23.50 ? 400,000 $ 9,400,000

$21.50 ? 1,600,000 $ 34,400,000 Inspecting components:

$120 ? 40 4,800

$120 ? 1,960 235,200 Reworking products:

$507 ? 90 45,630

$507 ? 1,410 714,870 Warranty work:

$600 ? 400 240,000

$600 ? 7,600 4,560,000 Total supplier cost $ 9,690,430 $ 39,910,070

Units supplied ÷400,000 ÷1,600,000

Unit cost $ 24.23* $ 24.94*

*Rounded

The difference is in favor of Vance; however, when the price concession is consi-dered, the cost of Vance is $23.23, which is less than Foy’s componen t. Lumus should accept the contractual offer made by Vance.

2. Warranty hours would act as the best driver of the three choices. Using this driver,

the rate is $1,000,000/8,000 = $125 per warranty hour. The cost assigned to each component would be:

Vance Foy Lost sales:

$125 ? 400 $ 50,000

$125 ? 7,600 $ 950,000

$ 50,000 $ 950,000 U nits supplied ÷ 400,000 ÷1,600,000

I ncrease in unit cost $ 0.13* $ 0.59*

*Rounded

PROBLEMS

4–8

1. Product cost assignment:

Overhead rates:

Patterns: $30,000/15,000 = $2.00 per DLH

Finishing: $90,000/30,000 = $3.00 per DLH

Unit cost computation:

Backpacks Duffel Bags Patterns:

$2.00 ? 0.1 $0.20

$2.00 ? 0.2 $0.40

Finishing:

$3.00 ? 0.2 0.60

$3.00 ? 0.4 1.20

Total per unit $0.80 $1.60

2. Cost before addition of duffel bags:

$60,000/100,000 = $0.60 per unit

The assignment is accurate because all costs belong to the one product.

3. Activity-based cost assignment:

Stage 1: Pool rate = $120,000/80,000 = $1.50 per transaction

Stage 2:

Overhead applied:

Backpacks: $1.50 ? 40,000* = $60,000

Duffel bags: $1.50 ? 40,000 = $60,000

*80,000 transactions/2 = 40,000 (number of transactions had doubled)

Unit cost:

Backpacks: $60,000/100,000 = $0.60 per unit

Duffel bags: $60,000/25,000 = $2.40 per unit

4. This problem allows the student to see what the accounting cost per unit should be

by providing the ability to calculate the cost with and without the duffel bags. With this perspective, it becomes easy to see the benefits of the activity-based approach over those of the functional-based approach. The activity-based approach provides the same cost per unit as the single-product set-ting. The functional-based approach used transactions to allocate accounting costs to each producing department, and this allocation probably reflects quite well the consumption of accounting costs by each producing department. The problem is the second-stage allocation. Direct labor hours do not capture the consumption pat-tern of the individual products as they pass through the departments. The distortion occurs, not in using transactions to assign accounting costs to departments, but in using direct labor hours to assign these costs to the two products.

In a single-product environment, ABC offers no improvement in product costing ac-curacy. However, even in a single-product environment, it may be possible to in-crease the accuracy of cost assignments to other cost objects such as customers.

4–9

1. Unit-level costs ($120 ? 20,000) $ 2,400,000

Batch-level costs ($80,000 ? 20) 1,600,000

Product-level costs ($80,000 ? 10) 800,000

Facility-level ($20 ? 20,000) 400,000

Total cost $ 5,200,000

2. Unit-level costs ($120 ? 30,000) $ 3,600,000

Batch-level costs ($80,000 ? 20) 1,600,000

Product-level costs ($80,000 ? 10) 800,000

Facility-level costs 400,000

Total cost $ 6,400,000

The unit-based costs increase because these costs vary with the number of units produced. Because the batches and engineering orders did not change, the batch-level costs and product-level costs remain the same, behaving as fixed costs with respect to the unit-based driver. The facility-level costs are fixed costs and do not vary with any driver.

3. Unit-level costs ($120 ? 30,000) $ 3,600,000

Batch-level costs ($80,000 ? 30) 2,400,000

Product-level costs ($80,000 ? 12) 960,000

Facility-level costs 400,000

Total cost $ 7,360,000

Batch-level costs increase as the number of batches changes, and the costs of en-gineering support change as the number of orders change. Thus, batches and or-ders increased, increasing the total cost of the model.

4. Classifying costs by category allows their behavior to be better understood. This, in

turn, creates the ability to better manage costs and make decisions.

4–10

1. Overhead rate = $6,990,000/272,500 = $25.65 per DLH*

Overhead assignment:

X-12: $25.65 ? 250,000/1,000,000 = $6.41*

S-15: $25.65 ? 22,500/200,000 = $2.89*

*Rounded numbers used throughout

Unit gross margin:

X-12 S-15

Price $ 15.93 $ 12.00

Cost 10.68* 6.02**

Gross margin $ 5.25 $ 5.98

*Prime costs + Overhead = ($4.27 + $6.41)

**Prime costs + Overhead = ($3.13 + $2.89)

2. Pools Driver Pool Rate

Setup Runs $240,000/300 = $800 per run

Machine Machine hrs. $1,750,000/185,000 = $9.46/per MHr

Receiving Orders $2,100,000/1,400 = $1,500/per order

Engineering Engineering hrs. $2,000,000/10,000 = $200/per eng. hour Material handling Moves $900,000/900 = $1,000/per move

Overhead assignment:

X-12 S-15 Setup costs:

$800 ? 100 $ 80,000

$800 ? 200 $ 160,000 Machine costs:

$9.46 ? 125,000 1,182,500

$9.46 ? 60,000 567,600

Receiving costs:

$1,500 ? 400 600,000

$1,500 ? 1,000 1,500,000 Engineering costs:

$200 ? 5,000 1,000,000

$200 ? 5,000 1,000,000 Material-handling costs:

$1,000 ? 500 500,000

$1,000 ? 400 400,000 Total overhead costs $ 3,362,500 $ 3,627,600

Units produced ÷ 1,000,000 ÷200,000

Overhead cost per kg $ 3.36 $ 18.14

Prime cost per kg 4.27 3.13

Unit cost $ 7.63 $ 21.27

Selling price $ 15.93 $ 12.00

Less unit cost 7.63 21.27

Unit gross margin $ 8.30 $ (9.27)

3. No. The cost of making X-12 is $7.63, much less than the amount indicated by

functional-based costing. The company can compete by lowering its price on the high-volume product. The $10 price offered by competitors is not out of line. The concern about selling below cost is unfounded.

4. The $12 price of compound S-15 is well below its cost of production. This explains

why Pearson has no competition and why customers are willing to pay $15, a price that is probably still way below competitors’ quotes.

5. The price of X-12 should be lowered to a competitive level and the price of

S-15 increased so that a reasonable return is being earned.

4–11

1. GAAP mandate that all nonmanufacturing costs be expensed during the period in

which they are incurred. GAAP are the most likely cause of the practice. The limita-tions of GAAP-produced information for cost management should be emphasized.

2. The total product consists of all benefits, both tangible and intangible, that a cus-

tomer receives. One of the benefits is the order-filling service provided by Soren-sen. Thus, it can be argued that these costs should be product costs and not as-signing them to products undercosts all products. From the information given, there are more small orders than large (50,000 orders averaging 600 units per order);

thus, these small orders consume more of the order-filling resources. They should, therefore, receive more of the order-filling costs.

The average order-filling cost per unit produced is computed as follows: $4,500,000/90,000,000 units = $0.05 per unit

Thus, order-filling costs are about 6 to 10 percent of the selling price, clearly not a trivial amount.

Furthermore, the per-unit cost for individual product families can be computed us-ing the number of orders as the activity driver:

Activity rate = $4,500,000/100,000 orders

= $45 per order

The per-unit ordering cost for each product family can now be calculated: Category I: $45/600 = $0.075 per unit

Category II: $45/1,000 = $0.045 per unit

Category III: $45/1,500 = $0.03 per unit

Category I, which has the smallest batches, is the most undercosted of the three categories. Furthermore, the unit ordering cost is quite high relative to Category I’s selling price (9 to 15 percent of the selling price). This suggests that something should be done to reduce the order-filling costs.

3. With the pricing incentive feature, the average order size has been increased to

2,000 units for all three product families. The number of orders now processed can be calculated as follows:

Orders = [(600 ? 50,000) + (1,000 ? 30,000) + (1,500 ? 20,000)]/2,000

= 45,000

Reduction in orders = 100,000 – 45,000 = 55,000

Steps that can be reduced = 55,000/2,000 = 27 (rounding down to nearest whole number)

There were initially 50 steps: 100,000/2,000

Reduction in resource spending:

Step-fixed costs: $50,000 ? 27 = $1,350,000

Variable activity costs: $20 ? 55,000 = 1,100,000

$2,450,000

Customers were placing smaller and more frequent orders than necessary. They were receiving a benefit without being charged for it. By charging for the benefit and allowing customers to decide whether the benefit is worth the cost of providing it, Sorensen was able to reduce its costs (potentially by shifting the cost of the service to the customers). The customers, however, apparently did not feel that the benefit

was worth paying for and so increased order size. By increasing order size, the number of orders decreased, decreasing the demand for the order-filling activity, al-lowing Sorensen to reduce its order-filling costs. Other benefits may also be rea-lized. The order size affects activities such as scheduling, setups, and material handling. Larger orders should also decrease the demand for these activities, and costs can be reduced even more.

Competitive advantage is created by providing the same customer value for less cost or better value for the same or less cost. By reducing the cost, Sorensen can increase customer value by providing a lower price (decreasing customer sacrifice) or by providing some extra product features without increasing the price (increasing customer realization, holding customer sacrifice constant). This is made possible by the decreased cost of producing and selling the bolts.

4–12

1. Supplier cost:

First, calculate the activity rates for assigning costs to suppliers:

Replacing engines: $3,200,000/4,000 = $800 per engine

Expediting orders: $4,000,000/400 = $10,000 per late shipment

Repairing engines: $7,200,000/5,000 = $1,440 per engine

Next, calculate the cost per engine by supplier:

Supplier cost:

Watson Johnson Purchase cost:

$900 ? 72,000 $64,800,000

$1,000 ? 16,000 $16,000,000

Replacing engines:

$800 ? 3,960 3,168,000

$800 ? 40 32,000

E xpediting orders:

$10,000 ? 396 3,960,000

$10,000 ? 4 40,000

Repairing engines:

$1,440 ? 4,880 7,027,200

$1,440 ? 120 172,800

Total supplier cost $ 78,955,200 $16,244,800

Units supplied ÷72,000 ÷ 16,000

Unit cost $ 1,096.60 $ 1,015.30

The Johnson engine costs less when the full supplier effects are considered. This is

a better assessment of cost because it considers the costs that are caused by the

supplier due to poor quality, poor reliability, and poor delivery performance.

2. In the short run, buy 40,000 from Johnson and 48,000 from Watson. In the long

run, one possibility is to encourage Johnson to expand its capacity; another possi-bility is to encourage Watson to increase its quality and maintain purchases from both sources.

Managerial Decision Cases

4–13

1. Disagree. Chuck is expressing an uninformed opinion. He has not spent the effort

to find out exactly what activity-based management and costing are attempting to do; therefore, he has no real ability to offer any constructive criticism of the possible benefits of these two approaches.

2. and

3.

A t first glance, it may seem strange to even ask if Chuck’s behavior is unethical.

After all, what is unethical about expressing an opinion, albeit uninformed? While offering uninformed opinions or recommendations may be of little consequence in many settings, a serious issue arises when a person’s expertise is relied upon by others to make decisions or take actions that could be wrong or harmful to them-selves or their organizations. This very well may be the case for Chuck’s setting, and his behavior may be labeled professionally unethical.

Chuck’s lack of knowledge about activity-based systems is a signal of his failure to maintain his professional competence. Standard I-1 of the IMA ethical standards indicates that management accountants have a responsibility to continually develop their knowledge and skills. Failure to do so is unethical.

企业成本管理会计试卷

企业成本管理会计试卷 The final edition was revised on December 14th, 2020.

全国2015年5月 企业成本管理会计试题 (课程代码:11751) 第一部分必答题 (本部分包括一、二、三题,共60分) 一、单项选择题(每小题1分,共5分) 在每小题列出的四个备选项中只有一个是符合题目要求的,请将其代码填写在题后的括号内。错选、多选或未选均不得分。 1.不考虑过去业务信息而进行的预算属于(D) A.固定预算 B.弹性预算 C.增量预算 D.零基预算 2.某企业的部分财务信息包括:本期销售收入460 000美元,期初存货48 000美元,本期购货280 000美元,期末存货60 000美元。该企业的存货周转天数为(B) 天天 天天 3.下列关于投资评价内部报酬率法的描述正确的是(C)。 A.不考虑货币时间价值 B.根据会计净收益计算 C.忽略投资规模 D.不以比率形式表示 4.某企业生产储藏盒,单位成本美元,完工产品40 000个,期末存货8 000个完工程度为40%,该企业的期末存货为(A) 680美元 B. 11 520美元 200美元 D. 38 400美元 5.下列反映直接材料价格差异的描述正确的是(A)

A. 实际成本-实际耗用量×标准价格 B. 实际成本-标准耗用量×标准价格 C. 实际产量×(实际单位成本-标准单位成本) D. 预算产量×(实际单位成本-标准单位成本) 二、简答题(每小题5分,共15分) 6.说明安全边际的含义及其对管理决策的意义。 含义: 安全边际是指预计销售收入与损益平衡点销售额之差; 可以表示为销售量、预计销售量的百分比或预计销售收入的 百分比。 意义: 安全边际意味着企业在发生亏损之前,销售收入可以下降 的程度。 7.解释缺货成本的含义以及包括的内容。 含义: 缺货成本是指企业存货耗尽而发生的成本。 内容: 企业销售量受到损失而发生的成本; 不得不紧急订货以补充存货而发生的成本; 生产停工损失,例如机器不得不进行额外维护的成本; 工人停工带来的成本; 企业声誉和形象受损所带来的成本。 8.解释战略信息和战术信息的含义并举例说明。

成本管理会计三

成本管理会计三 一、判断题( 每小题1分, 共8分) 1、定额比例法适用于定额管理基础较好, 各项消耗( 费用) 定额比较稳定、准确, 各月在产品数量变动比较大的产品。( √ ) 2、直接人工预算是以销售预算为基础编制的。( ×) 3、成本分配基础的选择, 一般以因果关系为标准。( √ ) 4、在不存在专属成本的情况下, 经过比较不同备选方案的贡献毛益总额, 能够正确地进行择优决策。( √ ) 5、利润实现最大化时边际收入大于边际成本。( × ) 6、产品标准成本=产品计划产量×单位产品标准成本。( × ) 7、能增加股东回报的作业称为增值作业。( × ) 8、如当前的物价上涨幅度为30%, 物价上涨意味着同等数量货币所能购买的商品减少, 减少的幅度为( 1-100/130) =23%。( √ ) 二、单选题( 每小题1分, 共10分) 1、几种产品共同耗用的原材料费用, 属于间接计入费用, 应采用的分配方法是( B ) A. 计划成本分配法 B. 按材料定额费用比例分配 C. 按工时比例分配

D. 回归分析法 2、下列费用中属于酌量性固定成本的是( B ) A. 房屋及设备租金 B. 技术开发费 C. 行政管理人员的薪金 D. 不动产税 3、在计算完工产品成本时, 如果不计算在产品成本, 必须具备下列条件( B ) 。 A. 各月末在产品数量比较稳定 B. 各月末在产品数量很少 C. 各月末在产品数量较大 D. 定额管理基础较好 4、下列不属于产品成本表补充资料内容的是( D ) A. 可比产品成本降低额 B. 可比产品成本降低率 C. 产值成本率 D. 可比产品和不可比产品本月及本年累计实际产量, 实际单位成本 5、某企业3年前用6万元购买了一台专用机床, 由于6万元的买价早已支付, 因此它是( B ) A. 相关成本

成本管理会计》期末试题

成本管理会计期末试题 一、单选题(每题2分,共10分) 1、成本还原的对象是( B )。 A.产成品成本B.各步骤所耗上一步骤半产品的综合成本 C.最后步骤的产成品成本D.各步骤半成品成本 2、不在“废品损失”科目核算的内容是( C ) A.修复废品人员的工资 B.修复废品耗用的材料 C.实行“三包”损失 D.不可修复废品的净损失 3、假设每个质检员最多检验500件产品,也就是说产量每增加500件就必须增加一名质检员,而且是在产量一旦突破500件的倍数时就必须增加。那么,该质检员的工资成本就属于( B ) A.半变动成本B.半固定成本 C.延伸变动成本D.变动成本 4、作业消耗一定的( D )。 A.成本B.时间C.费用D.资源 5、某企业只生产一种产品,单位变动成本为36元,固定成本总额为4000元,产品售价为56元,要使安全边际率达到50%,该企业的销售总量应达到( B )件 A.400 B.222 C.143 D.500 二、多选题(每题4分,共20分) 1.在制定标准成本时,根据所要求达到的效率的不同,所采取的标准有(BDE )A.理想标准成本B.正常标准成本C.现实标准成本 D.定额成本E.历史成本 2、构成直接材料成本差异的基本因数有(AB ) A.效率差异B.时间差异 C.用量差异D.价格差异 3、企业拥有若干辅助生产车间时,企业辅助生产费用的分配方法主要有以下几种:(AB ) A.间接分配法B.直接分配法 C.交互分配法D.代数分配法 4、完工产品与在产品之间分配费用的方法有(AB ) A.约当产量比例法B.交互分配法 C.按年初数固定成本计价法D.定额比例法 5、为实现目标利润可以采取如下措施(ABCDE ) A.提高单价B.降低单位变动成本C.增加销售量

企业成本管理会计

《企业成本管理会计》【目录】第1章成本管理会计概述第2章成本分类第3章成本性态第4章成本要素第5章成本核算系统第6章决策第7章预算与业绩评价【第1章成本管理会计概述】 1.1战略、战术与运营信息【选择】战略信息是指企业的高层管理者用来制定公司目标并评价这些目标是否已经达到的信息。典型的战略信息包括企业整体以及各部门获利能力的详细情况,未来的资金需求等。【筒答】战略信息的特征: (1)可以通过外部或内部渠道获得。(2)对信息使用者的知识水平要求较高。 (3)与进行长期决策相关。 (4)所涉及的问题与企业整体相关。 (5)通常基于特定情况。 (6)既有定量信息,也有定性信息。【选择】战术信息是指与中层管理者做出可用资源应该如何进行分配,以及如何有效使用这些资源等决策相关的信息。如劳动力与设备生产率、预算控制、差异分析以及现金流预测等信息都是战术信息。【筒答】战术信息的特征:(1)信息大多来源于企业内部。(2)对信息使用者的知识水平要求较低。 (3)与中短期决策相关。 (4)通常描述和分析个别部门或区域的活动。 (5)通常基于常规情况。 (6)只有定量信息. 1.2决策过程【选择】决策过程开始于对活动的计划,结束于对这些活动的控制。计划可能由高层或中层管理人员实施,而控制职能则更可能由基层或监管人员实施。 1.3成本管理会计的性质【各词解释】成本会计:收集组织内部关于成本活动的信息,根据预算、产品成本等信息编制报表,将相关成

本归集到产品、服务和存货中去。【选择】管理会计是利用各种财务数据为使用者提供相关信息的会计。使用者可以利用这些信息做出决策、制订计划,并控制企业的活动。【筒答】成本会计最常见的要素包括以下内容: (1)生产、销售产品和服务的成本。(2)与某个特定部门或地区的活动有关的成本。(3)企业整体、某个部门或地区获得的收入。(4)企业整体、某个部门或地区取得的利润。(5)企业提供的每一产品或服务的销售收入与销售成本之间的关系。(6)企业在会计期末持有的存货的价值,包括全部原材料、在产品(即部分完工的产品)以及产成品。每→项目应单独计价以便准确反映企业资产的构成情况。(7)对企业未来成本的预测(8) 实际生产成本与计划生产成本之间的关系。【第2章成本分类】【2. 1直接成本与间接成本】【简答】产品或服务的总成本主要由三个要素构成: 原材料成本,指生产过程中使用的原材料。人工成本,指与生产过程中雇用的劳动力相关的费用。(3)其他费用,指与生产相关的其他费用。例如电费、设备的折旧费、厂房的租金与税费等。【筒答】简述直接成本与间接成本。(1)直接成本是指能够采取追溯方式整体计入相关产品、服务或部门的成本。 直接成本包括: ①直接材料,指那些已经确知在生产过程中使用的材料。②直接人工,指为生产产品或提供劳务必须支付报酬的劳动力成本。③直接费用,指那些制造产品必须整体满足的费用。(2)间接成本或间接费用是指与生产过程相关,但是不

高级成本管理会计复习题 (2)

高级成本管理会计复习题 单选题知识点: 1、根据经济学的一般原理,商品价值等于C+V+M,成本是产品价值 中的C+V部分。2、成本会计的首要职能是反映的职能。4、成本会计的各项职能中,成本决策的前提是成本预测。9、成本是一种资金耗费,是相对于一定对象而言的耗费。产品成本与一定种类和数量的产品相联系,生产费用不一定都能计入产品成本,产品成本是对象化的生产费用。10、需要在各个成本对象之间分配的生产费用数额指的是本期发生的生产费用。11、生产费用要素是指生产费用按其经济内容的项目分类. 2、不能继续使用需要报废的出借包装物的残料,应增减营业费用。3、企业发出随同产品出售单独计价的包装物时,应借记其他业务支出科目。5、预提利息费用时应计入“财务费用”科目借方。6、按照福利人员的工资总额提取的福利费应借记管理费用科目。7、直接用于产品生产,并构成产品实体的原材料费用,应记入的会计科目是基本生产。8、材料按计划成本计价时,期末应将发出材料的计划成本调整为实际成本。9、“应付工资”科目月末借方余额表示应付工资数额大于实际支付工资数额。10、鸿博公司制造A产品,工时定额为15分钟,工人的小时工资率20,则A产品的计件单价为5.0 元11、在采用计划成本分配法分配辅助生产费用时,为简化工作,将辅助生产成本差异全部计入管理费用科目。1、按完工产品和月末在产品数量比例,分配计算完工产品与月末在产品的原材料费用,必须具备原材料在生产开始时一次投入的条件。2、基本生产车间应付的管理人员工资,记

入制造费用科目的借方。3.完工产品与在产品之间分配费用的在产品固定成本计价法,适用于各月末在产品数量虽大,但各月之间变化不大的产品。4.适合于季节性生产的企业分配制造费用的方法是年度计划分配率法。5.按完工产品和月末在产品数量比例,分配计算完工产品和月末在产品成本,必须具备在产品已接近完工条件。3.计算出来的废品损失应分配记入当月同种合格品的成本中。6.定额管理基础较好,各项耗费定额或费用定额比例准确、稳定,但各月末在产品数量变化较大的企业,在产品成本的计算通常采用定额比例法。7.完工产品与在产品之间分配费用的在产品忽略不计法,适用于各月在产品数量很小的产品。8.企业在核算废品损失时,一般是指基本生产车间的废品损失。9.在计算完工产品成本时,如果不计算在产品成本,必须具备各月末在产品数量很小条件。10.适用于各种产品机械化程度相近的车间或部门的制造费用分配方法是机器工时比例分配法。11.某企业生产产品经过两道工序,各工序的工时定额分别为30小时和20小时,则第二道工序在产品的完工率约为80%。12.对于因季节性生产或因固定资产大修理而停工所发生停工期间的一切费用,应列入制造费用科目。12.在产品从上一道工序转入下一道工序时,前面各工序完工程度均按100%计算。11.企业产生不可修复废品时,应将其生产成本从产品成本计算单中转出,会计分录为借:废品损失贷:基本生产。1.按产品材料定额成本比例分配法分配材料费用时,其适用的条件是各项材料消耗定额比较准确稳定。2.某企业的A产品经三道工序加工完成,各道工序单位产品工时定额分别为30小时、40小时和30小时,则第

成本管理会计案例一

案例一用完全成本法和变动成本法分别计算利润 某电视机厂连续两年亏损,厂长召集销售和生产部门的负责人开会,研究扭亏为盈的办法,会议要点如下: 厂长:我厂去年亏损500万元,比前年还糟,金融机构对于连续三年亏损的企业将停止贷款,如果今年不扭亏为盈,企业将被迫停产。 销售经理:问题的关键是我们以每台电视机1600元的价格出售,而每台电视机的成本是1700元。如果提高售价,面临竞争,电视机就卖不出去,只有降低成本这条路,否则,销售越多,亏损越大。 生产经理:我不同意。每台电视机的制造成本只有1450元,我厂的设备和工艺是国内最先进的,技术力量强,熟练工人多,控制物耗成本的经验得到同行业人士的肯定。问题在于生产线的设计能力是年产10万台,而销路打不开,去年只生产4 万台,所销售的5万台中,还有一万台是前年生产的。由于开工不足,内部矛盾增加,人心涣散。 厂长:成本到底是怎么回事? 对于销售经理和生产经理的分歧,厂长请财务经理做出具体意见,财务经理对厂长解释到:每台电视机的变动成本是1050元,全厂固定制造费用总额是1600万元,销售和管理费用总额是1250万元。并建议生产部门满负荷生产,通过扩大产量来降低单位产品所负担的固定制造费用。这样,即使不提价和扩大销售也能使企业扭亏为盈、度过危机。为了减少将来的风险,今年应追加50万元来改进产品质量,这笔费用计入固定制造费用;再追加50万元做广告宣传,追加100万元作职工销售奖励。厂长会采纳财务经理的建议吗? 1)请说明去年亏损的500万元是怎样计算出来的。 2)用完全成本法计算的利润。 3)用变动成本法计算的利润。 4)请你分析厂长若采纳财务经理的意见,今年能够盈利多少?

成本管理会计三

成本管理会计三 一、判断题(每小题1分,共8分) 1、定额比例法适用于定额管理基础较好,各项消耗(费用)定额比较稳定、准确,各月在产品数量变动比较大的产品。(√) 2、直接人工预算是以销售预算为基础编制的。(×) 3、成本分配基础的选择,一般以因果关系为标准。(√) 4、在不存在专属成本的情况下,通过比较不同备选方案的贡献毛益总额,能够正确地进行择优决策。(√) 5、利润实现最大化时边际收入大于边际成本。(×) 6、产品标准成本=产品计划产量×单位产品标准成本。(×) 7、能增加股东回报的作业称为增值作业。(×) 8、如当前的物价上涨幅度为30%,物价上涨意味着同等数量货币所能购买的商品减少,减少的幅度为(1-100/130)=23%。(√) 二、单选题(每小题1分,共10分) 1、几种产品共同耗用的原材料费用,属于间接计入费用,应采用的分配方法是(B ) A.计划成本分配法 B.按材料定额费用比例分配 C.按工时比例分配 D.回归分析法 2、下列费用中属于酌量性固定成本的是(B ) A.房屋及设备租金 B.技术开发费 C.行政管理人员的薪金 D.不动产税 3、在计算完工产品成本时,如果不计算在产品成本,必须具备下列条件(B )。 A.各月末在产品数量比较稳定 B.各月末在产品数量很少 C.各月末在产品数量较大 D.定额管理基础较好 4、下列不属于产品成本表补充资料内容的是(D ) A.可比产品成本降低额 B.可比产品成本降低率 C.产值成本率 D.可比产品和不可比产品本月及本年累计实际产量,实际单位成本 5、某企业3年前用6万元购买了一台专用机床,由于6万元的买价早已支付,因此它是(B ) A.相关成本 B.沉没成本 C.差量成本 D.机会成本 6、有一批可修复废品,存在两种处置方案,一个是降价后直接出售,一个是修复后按正常价格出售,修复成本为3000元,降价后出售收入为7 000元,修复后出售收入为11

成本管理会计材料

第一章总论 一、名解 成本管理会计: 成本管理会计是会计与管理的直接融合, 向企业管理当局提供信息( 如预测、决策、预算、控制等) 以帮助其进行经营管理的会计分支。 二、简答: 1.成本管理会计的职能是什么? 预测职能、决策职能、规划职能、控制职能、评价职能 2.成本管理会计和财务会计的联系和主要区别是什么? 联系: 1成本管理会计与财务会计同属于现代会计 2成本管理会计与财务会计的最终目标相同 3成本管理会计与财务会计相互分享部分信息 4财务会计的改革有助于成本管理会计的发展 区别: 1.服务对象不同——( 成) 服务于企业内部各管理层次, 内部会计( 财) 服务于企业外部各利益关系人, 外部会计 2.会计主体不同( 成) 企业整体及企业内部各管理部门、单位、班组等( 财) 企业整体 3.工作侧重点不同( 成) 规划未来, 属于经营管理会计侧重于对未来的预测、决策和规划( 财) 反映过去, 属于报账型会计侧重于核算和监督 三、选择题( 见课后练习) 第二章成本信息的生成与运用 一、名词解释

1.生产费用: 企业一定时期内( 会计期间: 月) 在生产产品和提供劳务过程中发生的各种耗费。 2.成本: 企业在生产经营中为特定对象( 甲产品成本、 103批别成本等) 而发生的耗费或支出。 3.期间费用: 企业在生产经营过程中发生的, 与产品生产活动没有直接联系, 接计入产品成本, 而直接计入当期损益的费用。不宜直 二、熟悉费用、成本的各种分类 三、理解制造费用、销售费用、管理费用、财务费用 制造费用: 车间管理中发生的费用 销售费用: 销售部门发生的费用 管理费用: 企业行政管理部门发生的费用 财务费用: 筹集生产经营资金而发生的费用。包括利息、汇兑损益、手续费等。 第三章生产经营费用的归集和分配 一、名词 约当产量法: 约当产量法: 指先将月末在产品的数量, 按照其完工程度折算为相当于完工产品的产量, 即约当产量。然后将生产费用合计按照完工产品产量和在产品的约当产量的比例进行分配的方法。具体: 在产品约当产量=在产品数量×完工百分比( 完工率或完工程度)

《成本管理会计》期末试题

成本管理会计期末试题 一、单选题 (每题 2分,共 10 分) 1、成本还原的对象是 ( B )。 A.产成品成本 B ?各步骤所耗上一步骤半产品的综合成本 C.最后步骤的产成品成本 D .各步骤半成品成本 5、某企业只生产一种产品,单位变动成本为 36 元,固定成本总额为 4000元, 产品售价 为 56 元,要使安全边际率达到 50%,该企业的销售总量应达到 ( B ) 件 A.400 B.222 C.143 D.500 二、多选题 (每题 4分,共 20 分) 1、 在制定标准成本时,根据所要求达到的效率的不同, 所采取的标准有( BDE ) A.理想标准成本 B .正常标准成本 C .现实标准成本 D.定额成本 E .历史成本 2、 构成直接材料成本差异的基本因数有( AB ) A.效率差异 B .时间差异 C.用量差异 D .价格差异 3、 企业拥有若干辅助生产车间时,企业辅助生产费用的分配方法主要有以 下几种:( AB ) A.间接分配法 B .直接分配法 C ?交互分配法 D .代数分配法 4、 完工产品与在产品之间分配费用的方法有( AB ) A.约当产量比例法 B .交互分配法 C ?按年初数固定成本计价法 D .定额比例法 5、 为实现目标利润可以采取如下措施( ABCDE ) A.提高单价 B .降低单位变动成本 C .增加销售量 2、 不在“废品损失”科目核算的内容是 A.修复废品人员的工资 C .实行“三包”损失 3、 假设每个质检员最多检验 加一名质检 员, 而且是在产量 检员的工资成本就属 于( A.半变动成本 C.延伸变动成本 4、 作业消耗一定的 A.成本 B D .时间 B. C ) 修复废品耗用的材料 不可修复废品的净损失 D. 500 件产品,也就是说产量每增加 500件就必须增 旦突破 500件的倍数时就必须增加。 那么,该质 ) .半固定成本 .变动成本 ) C .费用 D .资源

2013年05月企业成本管理会计试题及答案

全国2013年5月企业成本管理会计试题(课程代码:11751) 第一部分必答题 (本部分包括一、二、三题,共60分) 一、单项选择题(每小题1分,共5分) 1.劳动力和设备生产率报告属于( B ) A.战略信息 B.战术信息 C.公司目标 D.运营计划 2.采用完全成本法对产品进行计价时,成本是指(A) A.生产成本 B.生产成本、管理费用 C.生产成本、销售及配送费用 D.生产成本、销售费用、管理费用和配送费用 3.下图描述了某种产品的损益平衡,XY表示(D)。 A.变动成本 B.净损失 C.毛利 D.固定成本 4.下列最有可能使用工序成本法的单位是(C) A.造船厂 B.电影制片厂 C.炼油厂 D.医院 5.在相关范围内,下列关于变动成本的描述正确的是( A ) A.变动成本总额随着业务量的变化而成正比例变化 B.当业务量变化时,变动成本将保持不变 C.单位变动成本将随着业务量的增加而增加 D.单位变动成本将随着业务量的减少而增加 二、简答题(每小题5分,共15分) 6.举例解释在产品的含义。 答:在产品是指已经开始生产但没有完工的产品,发生在营运资金循环中的原材料与产成品之间的环节。例如已经完成部件加工但尚未完成组装汽车。 7.解释存货控制的帕累托(80/20)分类法。 答:基于存货价值与存货数量之间的统计关系发现,多数情况下,80%的存货价值其数量只占存货数量的20%。(3分);因此,企业应该将精力集中于高价值存货的有效控制。(2分) 8.解释零基预算的含义。 答:零基预算是一种与每一个业务活动的必要性都有关系的预算;

◆它不是基于前期的、甚至是考虑了通货膨胀情况而作出了调整的预算; ◆对每个业务活动都评价其与企业的相关性,以及预计取得的资金价值; ◆如果一种产品过去创造了价值,我们不应该假设下一个时期它会自动创造价值; ◆预算应该从零业务量开始,然后,加上增加的业务量所创造的额外价值。 三、案例分析题(仔细阅读下面案例,回答9-12小题,共40分) 长城家居公司 作为一名管理会计师,王勇在过去两年里向长城家居公司的老板提出了很多建议,并取得了明显的效果。公司由两兄弟建立,按合伙制进行管理,对经营结果不做系统性分析。兄弟俩最初对王勇的建议不感兴趣。但是当王勇向他们演示了分析法的运用之后,他们改变了想法,认为会计分析有助于经营控制。 最初,王勇向两兄弟介绍了本量利以及差异分析法。这些方法的应用为企业带来很大的成功,利润和营业额飞速增长。企业业绩已跃居该市场前五名。 两兄弟打算进一步扩张企业。他们已向银行经理申请增加公司借款额度。银行经理对此表示支持的同时,也略有担心,因为两兄弟似乎没有长期的投资计划,又没有制定经营投资评价战略。 两兄弟为此咨询了王勇。王勇建议他们采用正规的投资评价方法,例如回收期法和平均报酬率法(ARR)。两兄弟对这些方法毫无所知,因此,王勇选取一些会计信息向他们演示了如何使用这些方法。王勇使用的会计信息如下: ●企业正进行项目A和项目B的投资决策。项目A需要投资一台成本为475000元的新设备。该设备预计 每年会带来120000元的收入,每年的运营成本为70000元。该设备预计使用年限12年,到期无残值。 ●项目B需要投资一台成本为120000元的设备,预计使用年限5年。扣除运营成本后,该项目预计每年 净收益为30000元。 一段时间后,两兄弟已经能够熟练使用回收期法和平均报酬率(ARR)法。他们进一步向往勇咨询如何改进公司的经营。他们迫切希望扩大企业规模,以便能够成立有限责任公司。王勇提醒他们谨慎行事,因为他们仍然面临很多问题。 目前,企业的预算控制过于简化,王勇认为在一个多变的环境中,企业应采用零基预算法。王勇同意为企业建立该预算制度提供帮助。 王勇还对企业急于扩张表示担心。他认为企业应采用标杆法来进行业绩评价。银行经理对该建议表示完全赞同,他提出只要使用该方法得到的结果是有利的,他就准备增加企业的借款额度。 9.说明长城家居这类企业需要进行投资及认真对每一个项目进行评价的原因。(10分) 答:进行投资的原因: ★1.)当现有资产陈旧、不再可靠或过时的时候,对其进行更换; ★2.)为增加产量或降低生产成本而引入新资产; 3.)为保持竞争力而购买最新技术; ★ 4.)通过购置能够推动研发并改进产品的新生产设备而进行内部扩张; ★ 5.)通过企业并购或企业联合进行外部扩张…

新编《成本管理会计》作业考核试题【优质精彩实用】

《成本管理会计》作业考核试题 一、单选题(每题2分,共10分) 1、成本还原的对象是( a.产成品成本 b.各步骤所耗上一步骤半产品的综合成本 c.最后步骤的产成品成本 d.各步骤半成品成本 2、不在”废品损失”科目核算的内容是( a.修复废品人员的工资 b.修复废品耗用的材料 c.实行”三包”损失 d.不可修复废品的净损失 3、假设每个质检员最多检验500件产品,也就是说产量每增加500件就必须增加一名质检员,而且是在产量一旦突破500件的倍数时就必须增加。那么,该质检员的工资成本就属于(a.半变动成本 b.半固定成本 c.延伸变动成本 d.变动成本 4、作业消耗一定的( a.成本 b.时间 c.费用 d.资源

5、某企业只生产一种产品,单位变动成本为36元,固定成本总额为4000元,产品售价为56元,要使安全边际率达到50%,该企业的销售总量应达到( )件 二、多选题(每题4分,共XX年初数固定成本计价法 d.定额比例法 5、为实现目标利润可以采取如下措施( a.提高单价 b.降低单位变动成本 c.增加销售量 d.降低固定成本 e.调整产品品种结构 三、判断题(每题2分,共10分) 1、保本点、保利点和保本作业率都是反指标。( 2、”制造费用”帐户的发生额最终用转入”基本生产成本”帐户,故月末必然没有余额。( 3、分类法是以产品类别为成本计算对象的一种产品成本计算的基本方法。() 4、由于实际工时和预算工时之间的差异造成的固定制造费用差异,称为固定制造费用开支差异。( 5、销售预算是编制全面预算的基础和起点。() 四、计算题(每题XX年最大生产能力为1XX年初已按100元/件的价格接受正常任务1000 件。该产品的单位完全生产成本为80元(其中,单位固定

成本管理会计作业3

成本管理会计作业3 单项选择题 第1题主要产品单位成本的一般分析,通常首先采用()进行分析。 A、对比分析法 B、趋势分析法 C、比率分析法 D、连环替代法 答案:A 第2题原材料脱离定额差异是()。 A、数量差异 B、一种定额变动差异 C、价格差异 D、原材料成本差异 答案:A 第3题食品厂在生产一些时令、节令食品时,既可将品种法与分类法结合,又可以将()与分类法结合。 A、分批法 B、分步法 C、系数法 D、定额法 答案:A 第4题采用分类法的目的是:()。 A、分类计算产品成本 B、分品种计算产品成本 C、简化各类产品成本的计算工作 D、简化各种产品成本的计算工作 答案:D 第5题成本还原是指从()生产步骤起,将其耗用上一步骤的自制半成品的综合成本,按照上一步骤完工半成品的成本项目的比例分解还原为原来的成本项目。 A、最前一个 B、中间一个 C、最后一个 D、随意任选一个 答案:C 第6题产品成本计算的分批法,应以()。 A、每种产品设置成本计算单 B、每批产品设置成本计算单 C、产品类别设置成本计算单

D、产品生产步骤设置成本计算单 答案:B 第7题产品成本计算的最基本的方法是:()。 A、分类法 B、分步法 C、分批法 D、品种法 答案:D 第8题决定成本计算对象的因素是生产特点和()。 A、成本计算实体 B、成本计算时期 C、成本管理要求 D、成本计算方法 答案:C 第9题以每批商品的实际进价作为该批商品的销售成本的方法称之为()。 A、分批实际进价法 B、先进先出法 C、后进先出法 D、毛利率计算法 答案:A 第10题在汽车营运过程中发生的不能直接计入成本核算对象的各种费用称之为()。 A、车辆费用 B、营运间接费用 C、营运费用 D、间接费用 答案:B 多项选择题 第11题按成本的归宿方式,可划分为:()。 A、直接成本 B、变动成本 C、间接成本 D、固定成本 E、责任成本 答案:A|C 第12题下列哪些项目是将费用按经济用途划分?() A、制造费用 B、固定费用 C、直接材料 D、间接费用

《成本管理会计》期末试卷A

▆■■■■■■■■■■■■ 福建师范大学网络与继续教育学院 《成本管理会计》期末考试 A 卷 姓名: 专业: 学号: 学习中心: 一、单项选择题(每题 3 分,共 15 分) 1在成本管理工作中能充分发挥其应有的积极作用,因而在实际 工作中得到最广泛应用的标准成本是()。 A .基准的标准成本B.理想的标准成本 C.正常的标准成本D.历史的标准成本 2. 下列方法中,属于辅助生产费用分配方法的是() A 、定额成本法B、计划成本分配法 C、生产工时比例分配法 D、机器工时比例分配法 3.固定制造费用的实际金额与固定制造费用的预算金额之间的差 额称为() A.耗费差异 B.效率差异 C.闲置能量差异 D.能量差异 4、某企业只生产一种产品,单价 6 元,单位变动生产成本 4 元, 单位销售和管理变动成本0.5 元,销售量为500 件,则其产品边 际贡献为()元 A.650 B.750 C.850 D.950 5.完全成本法和变动成本法分期营业净利润出现差异的根本原 因在于()。 A.两种成本法计入当期损益表的制造费用的水平出现了差异 B.两种成本法计入当期损益表的变动性制造费用的水平出现了 差异C.两种成本法计入当期损益表的固定性制造费用的水平 出现了差异 D.两种成本法计入当期损益表的变动性管理费用的水平出现了 差异 ▆《成本管理会计》试卷共2页(第1页)二、判断题(每题 3 分,共 15 分) 1.定性分析法与定量分析法在实际应用中是相互排斥的。() 2.影响目标利润的因素主要有销售量、销售单价、单位变动成本、 固定成本和品种结构等因素。() 3.沉没成本是无关成本,在决策时可以不予考虑。() 4.销售预算、生产预算等其他预算的编制,要以现金预算为基础。 () 5.采用平行结转分步法,各步骤不计算半成品成本() 三、多项选择题(每题 3 分,共 15 分) 1、下列方法中,属于产品成本计算的辅助方法有()。 A 、品种法B、分批法C、分步法 D、定额法 E、分类法 2.在传统式盈亏临界图中,下列描述正确的是() A、在总成本既定的情况下,销售单价越高,盈亏临界点越低 B、 在总成本既定的情况下,销售单价越高,盈亏临界点越高C、 在销售单价、单位变动成本既定的情况下,固定成本越大,盈 亏临界点越高 D、在销售单价、固定成本总额既定的情况下,单位变动成本越 高,盈亏临界点越高 E、在销售单价、固定成本总额既定的情况下,单位变动成本越高, 盈亏临界点越低 3、下列直接材料用量差异中应该由生产部门负责的有() A. 材料浪费 B.不能合理下料 C.不能做到综合利用 D. 不能修旧利废 4.评价和考核投资中心工作成果的指标是()。 A 经营净利润 B 投资利润率 C 经营资产 D 剩余利润 5.下列方法中,属于制造费用分配方法的有() A 、生产工人工时比例分配法B、生产工人工资比例分配法 C、机器工时比例分配法 D、按年度计划分配率分配法 E、交互比例分配法 四、简答题 (10 分) 1.简述变动成本、固定成本定义特征。 五、计算分析题(每题15 分,共 45 分) 1..某产品经两道工序完工,其月初在产品与本月发生的直接人工 之和为 300 000 元,该月完工产品 500 件。该产品的工时定额为: 第一工序 60 小时,第二工序 40 小时。月末在产品数量为:第一工 序 600 件,第二工序 400 件。各工序在产品在本工序的完工程度均 按 50%计算。 答案务必写在答题纸上,否则不得分,超出黑色边框区域的答案无效! 要求:(1)计算该产品月末在产品的约 (2)按约当产量比例分配计算完工产品和 人工。 2.设某企业仅产销一种产品,年产销量为 价 50 元,单位变动成本 30 元,年固定成 拟购置一台专用设备,价值 1200000 元。 值 200000 元,按直线法计提折旧。该设 产品生产的变动成本下降 40%。 要求:分析该企业是否应购置该项设备。 3.某企业生产甲产品,第一车间完工甲 完工甲产成品成本有关资料如下: 项目半成品原材料工资及福利 费 产成品成216004400 本 半成品成80003400 本 要求:进行成本还原,编制产品成本还原 产品成本还原计算表 项目还原半成品原材料 分配率 还原前产成品 成本 本月所产半成 品成本 成本还原 还原后产成品 成本

年月中英合作金融管理企业成本管理会计试题及答案

2013年5月中英合作商务管理专业与金融管理专业管理段等数课程考试 企业成本管理会计试卷及答案 第一部分必答题 一、单选题 本题包括第1—5小题,每小题1分,共5分。在每小题给出的四个选项中,只有一项符合题目的要求。 1、劳动力和设备生产率报告属于() A、战略信息 B、战术信息 C、公司目标 D、运营计划 2、采用完全成本法对产成品进行计价时,成本是指() A、生产成本 B、生产成本、管理费用 C、生产成本、销售与配送费用 D、生产成本、销售费用、管理费用和配送费用 3、下图描述了某种产品的损益平衡,XY表示() 、净损失A、变动成本 B 、固定成本C、毛利 D )、下列最有可能使用工序成本法的单位是( 4 、电影制片厂、造船厂 BA 、医院、炼油厂 DC )5、在相关范围内,下列关于变动成本的描述正确的是( A、变动成本总额随着业务量的变化而成正比例变化 B、当业务量变化时,变动成本将保持不变 C、单位变动成本将随着业务量的增加而增加、单位变动成本将随着业务量的减少而增加D 简答题二、 分。小题,共15本题包括第6—8 6、举例解释在产品的含义。答案可能包括:●在产品是指已经开始生产但没有完工的产品,发生在营运资金循环中的原材料与产成品之间的环节。例如:按尺码裁剪并送交缝纫工加工的衣服布料;已经完成部件加工但尚未完成组装的汽车,等等。)分类法。7、解释存货控制帕累托(80/20答案可能包括:分)因此,企(380%●基于存货价值与存货数量之间的统计关系发现,多数情况下,的存货价值其数量只占20% 分)业应该将精力集中于高价值存货的有效控制。(2、解释零基预算的含义8答案可能包括:1 / 7 ●零基预算是一种与每个业务活动的必要性有关系的预算。 ●它不是基于前期的、甚至是考虑了通货膨胀情况而做出了调整的预算。

《企业成本管理会计复习资料(1)

《企业成本管理会计》考点串讲 第1章成本管理会计概述 1. 1 战略、战术与运营信息 [选择]战略信息是指企业的高层管理者用来制定公司目标并评价这些目标是否已经达到的信息。典型的战略信息包括企业整体以及各部门获利能力的详细情况,未来的资金需求等。 [简答]战略信息的特征: (1)可以通过外部或内部渠道获得。 (2)对信息使用者的知识水平要求较高。 (3)与进行长期决策相关。 (4)所涉及的问题与企业整体相关。 (5)通常基于特定情况。 (6)既有定量信息,也有定性信息。 [选择]战术信息是指与中层管理者做出可用资源应该如何进行分配,以及如何有效使用这些资源等决策相关的信息。如劳动力与设备生产率、预算控制、差异分析以及现金流预测等信息都是战术信息。 [简答]战术信息的特征: (1)信息大多来源于企业内部。 (2)对信息使用者的知识水平要求较低。 (3)与中短期决策相关。 (4)通常描述和分析个别部门或区域的活动。 (5)通常基于常规情况。 (6)只有定量信息。 [选择]运营信息是指基层管理者或监管人员完成其工作所必需的信息。这些信息使他们能够监督企业各个部门的运营效率。运营信息包括生产工人与设备的产量报告、每个工人的人工工时、每个工人完成任务所花费的时间等信息。 [简答]运营信息的特征: (1)信息完全来自于企业内部。 (2)非常详细,通常是没有经过加工汇总的原始数据。 (3)与中期目标相关。 (4)与具体任务相关。 (5)应连续编制和提供。 (6)本质上属于定量信息。 1. 2 决策过程 [选择]决策过程开始于对活动的计划,结束于对这些活动的控制。计划可能由高层或中层管理人员实施,而控制职能则更可能由基层或监管人员实施。 1. 3 财务会计与成本管理会计的区别 [简答]财务会计与成本管理会计的区别:

成本管理会计复习题及答案

成本管理会计复习题及 答案 Pleasure Group Office【T985AB-B866SYT-B182C-BS682T-STT18】

成本管理会计复习题 一、判断题 1. 直接成本是为某一特定产品所消耗,可以直接计入该产品的成本(√) 2. 制造费用是企业在生产过程中发生的各项可以直接计入产品成本的费用。(Χ) 3. 变动成本是指在一定期间和一定业务量范围内,其总额不随着业务量变动而变动的 成本。(Χ) 4. 混合成本兼有固定成本和变动成本两种性质。(√) 5. 生产车间发生的制造费用应由本车间生产的产品负担,因此,期末时“制造费用”科目 期末一定没有余额。(Χ) 6. 企业在进行费用分配时,应先分配基本生产车间的制造费用,然后才能分配辅助生 产车间的制造费用。(Χ) 7. 企业按月计提的固定资产折旧费用,应该全部计入产品成本。(Χ) 8. 在一般情况下企业在本期投产的产品往往能在本期完工,本期完工的产品一定全部 都是由本期投产的。(Χ) 9. 材料费用的分配一般是通过编制材料费用分配表进行的。(√) 10. 在几种产品共同耗用几种材料的情况下,材料费用的分配应采用产品材料定额成本 比例法进行分配。(√) 11. 在所有的辅助生产费用分配法中,最准确的方法是一次交互分配法。(Χ) 12. 采用直接分配法分配辅助生产费用时,一般不需要考虑各辅助生产车间之间相互提 供产品或劳务的情况。(√) 13. 采用辅助生产费用的代数分配法时,其计算过程中是不考虑辅助生产车间之间相互 提供产品或劳务情况的。(Χ)

14. 采用一次交互分配法分配辅助生产费用时,第一阶段是对内分配,第二阶段是对外 分配。(√) 15. 当企业完工产品入库时,所作的会计分录是借记“库存商品”科目,贷记“生产成本” 科目。(√) 16. 采用约当产量法计算在产品成本时,如果原材料不是在开始时一次投入,而是随着 加工进度陆续投入的,其投料程度与其加工进度完全一致,则计算材料费用的约当产量与计算加工费用的约当产量应是一致的。(√) 17. 完工产品与在产品之间分配费用的约当产量法只适用于工资和其他加工费用的分 配,不适用于原材料费用的分配。(Χ) 18. 当企业的各项消耗定额或费用定额比较准确、稳定,而且各月末在产品数量变化不 大时,可采用定额比例法计算在产品的成本。(Χ) 19. 不论什么组织方式的制造企业、不论什么生产类型的产品,也不论成本管理要求如 何,最终都必须按产品品种计算出产品成本。(√) 20. 品种法一般适用于大量大批单步骤生的企业。(√) 21. 分批法是以产品批别为成本计算对象,归集费用,计算产品成本的一种方法。 (√) 22. 分批法的成本计算应定期进行,成本计算期与某批次或订单产品的生产周期也应保 持一致。(Χ) 23. 分批法下如果产品批量较大,出现批内跨月陆续完工和分次交货情况下,应该采取 适当的方法计算完工产品成本和月末在产品成本。(√) 24. 分批零件法下零件、部件、成品明细账中的在产品指的是广义在产品。(Χ)

成本管理会计模拟试卷-(2)

成本管理会计模拟试卷十四 1、下列属于直接生产费用的是() A、车间生产工人的工资 B、车间辅助人员的工资 C、车间管理人员的工资 D、生产车间的办公费 2、如果某种产品所耗原材料费用在产品成本中所占比重很大,在产品成本的确定可使用的 方法是( ) A、约当产量法 B、在产品按所耗原材料费用计算法 C、在产品按固定成本法 D、在产品按完工产品成本法 3、下列各项中,不计人产品成本费用的是( )。 A.直接材料费用B.辅助车间管理人员工资 C.车间厂房折旧费D.厂部办公楼折旧费 4、某产品4月份在生产过程中发现的不可修复废品的生产成本为800元,入库后发现的不可修复废品的生产成本为400元,可修复废品的修复费用为300元,回收废品残料的价值为100元。据此计算的该产品4月份废品净损失是( )元。 A.1000 B.1100 C.1400 D.1500 5、几种产品共同耗用的原材料费用,属于间接计入费用,应采取的分配方法是( )。 A.按材料定额费用比例分配法 B.计划成本分配法 C.按工时比例分配法 D.代数分配法 6、下列情况中,不宜采用简化的分批法的是()。 A.月末未完工产品批数较多 B.各月间接计入费用水平相差较多 C.同一月份投产的批数很多 D.各月间接计入费用水平相差不多 7、某种产品经两道工序加工完成。第一工序的月末在产品数量为100件,完工程度为20%;第二工序的月末在产品数量为200件,完工程度为70%。据此计算的月末在产品约当产量为()。 A.20件 B.135件 C.140件 D.160件 8、辅助生产交互分配后的实际费用,应再在( )进行分配。 A.各基本生产车间 B.各受益单位之间 C.辅助生产以外的受益单位之间 D.各辅助生产车间 9、某企业定额管理基础较好,能够制定比较准确、稳定的消耗定额,各月末在产品数量变化不大的产品,应采用( )。

《成本管理会计》(1-3)练习答案

《成本会计》第1~3章练习 一、填空题 1、产品的制造成本是指为制造产品而发生的各种生产费用的总和,包括直接材料、直接人工和 制造费用。在制造成本法下,期间费用不计入产品成本,而是直接计入当期损益。 2、在成本会计的各项内容中,成本核算是成本会计的核心。 3、企业根据需要可将“生产成本”账户分设_基本生产成本_和_辅助生产成本_两个明细账户。 4、“制造费用”账户是核算企业为组织和管理生产而发生的,应该计入产品成本,但不能专设成本项目的各项生产费用。 5、各种要素费用发生后,对于直接用于产品生产、专设成本项目的费用,应单独记入生产成本总账账户。 6、直接生产产品的生产工人工资和根据生产工人工资按规定比例提取的职工福利费,应记入直接人工成本项目。 7、专设的销售部门人员工资应记入_销售费用(营业费用)_总账账户和所属明细账。 8、辅助生产费用的分配方法主要有直接分配法、顺序分配法、交互分配法、代数分配法 和计划成本分配法。 9、废品按能否修复分为可修复废品和不可修复废品。 10、如果辅助生产的制造费用,不是通过“制造费用”账户核算,则应全部借记“生产成本—辅助生产成本”账户。 11、按计划分配率方法,“制造费用”账户期末有余额,就是实际发生额与计划分配额的差额,一般应在年末调整计入12月份的产品成本。 二、单项选择题 1、下列应计入产品生产成本的费用是(C) A、广告费 B、租入办公设备的租赁费 C、生产工人工资 D、利息支出 2、制造业产品成本是指(B) A、生产费用、销售费用、管理费用、财务费用之和 B、生产一定种类和数量的产品所支出的各种生产费用之和 C、生产费用与管理费用之和 D、生产费用与管理费用、财务费用之和 3、下列应计入产品成本的费用是(B) A、职工教育经费 B、生产车间机器设备的修理费 C、技术服务部门设备的修理费 D、仓库设备的修理费 4、成本理论构成的内容是(B) A、C+V+M B、C+V C、V+M D、C+M 5、按照医务及生活福利部门人员的工资额提取的职工福利费,实际工作中应计入(C) A、应付福利费 B、制造费用 C、管理费用 D、辅助生产成本 6、基本生产车间计提的固定资产折旧费,应借记(C)账户。 A、“基本生产成本” B、“管理费用” C、“制造费用” D、“待摊费用” 7、辅助生产费用的交互分配法,一次交互分配时应在(B)之间进行分配。 A、各受益单位 B、相互受益的辅助生产车间 C、辅助生产以外受益单位 D、各受益的基本生产车间 8、基本生产车间应付车间管理人员工资,记入(B)账户的借方。 A、“基本生产成本” B、“制造费用” C、“应付工资” D、“管理费用” 9、各辅助生产费用分配法中,以(D)的结果最精确。 A、直接分配法 B、计划成本分配法 C、交互分配法 D、代数分配法

相关文档
最新文档