PMBOK指南(第5版)第五章习题

PMBOK指南(第5版)第五章习题
PMBOK指南(第5版)第五章习题

1.A new project manager is planning a complex hardware installation project. The team consists of 13 people who are experts in their fields. The project manager does not want to micromanage the project. How far should he decompose the work?

A. As small as possible because the work is complex

B. As large as possible because he is dealing with experts

C. To 1000-hour tasks because he is dealing with experts

D. To about 80-hour tasks because it will make the work less complex

1. 一个新项目经理正在规划一个复杂的硬件安装项目。这个团队由13名成员组成,他们都是各自领域的专家。这个项目经理不想管理此项目所有细节。他需要将工作分解到何种程度?

A.因为项目很复杂所以要尽可能细

B.尽可能分解的要大,因为他在与专家们合作

C.分解到1000小时的任务,因为他在与专家们合作

D.分解到80小时左右,因为这样可以减少工作复杂程度

2.The customer wants to make a major change to the scope of work when the project is mostly complete. The project manager should?

A. Make the change

B. Inform the customer of the impact of the change

C. Refuse the change

D. Complain to management

2. 项目快要完成时客户想对工作范围作一大的变更。项目经理应该:

A.进行变更

B.将变更造成的影响通知客户

C.拒绝变更

D.向管理当局抱怨

3. A client has asked you to add scope of work to the project. The project is under budget and a little ahead of schedule. What should you do?

A. Approve the change

B. Let the client know the effects of the change on the project

C. Ask approval from the sponsor for making the change

D. Get approval from the configuration change board

3. 客户要求你增加项目的工作范围,此项目在预算之内进度稍微提前。你应该做什么?A.批准这个变更

B.让客户知道变更对项目的影响

C.请求项目投资人批准此变更

D.从配置管理委员会获得批准

4.The project is mostly complete. However, the customer wants to make a major change to the scope of work. The project manager should:

A. meet with the project team to determine if this change can be made.

B. ask the customer for a description of the change.

C. explain that the change cannot be made at this point in the process.

D. inform management.

4. 项目大部分已完成,然而客户希望进行一个范围工作的大的变更,项目经理应该:A.会见项目团队确定是否进行此变更

B.请客户描述变更内容

C.说明在项目的这一点不能进行变更

D.告知管理层

5.A key attribute of validating scope is:

A. Improved cost estimates

B. Customer acceptance of project efforts

C. Improved schedule estimates

D. An improved project management information system

5. 确认范围的一项重要特点是:

A.改进的成本估算

B.客户对项目所做工作的接受

C.改进的进度估算

D.完善的项目管理信息系统

6.Validate Scope

A. Improves cost and schedule accuracy, particularly on projects using innovative techniques or technology

B. Is the last activity performed on a project before handoff to the customer?

C. Documents the characteristics of the product or service that the project was undertaken to create

D. Differs from quality control in that validate scope is concerned with the acceptance not the correctness-of the work results

6. 确认范围

A.提高了成本与进度计划的准确性,尤其是在项目中利用创新技术或方法

B.项目在转交给客户之前所做的最后--项活动

C.对项目所承担创造的产品或服务的特性进行归档

D.与质量控制的不同之外在于确认范围关心工作结果的验收而非纠正

7.Project scope:

A. is of concern only at the start of the project

B. is usually not a problem after the contract or other document authorizing the project has been approved

C. should be managed and controlled from project concept through close-out

D. is mainly a problem to be handled by change control procedures during the project execution phase.

7. 项目范围:

A.只是在项目开始时才加以考虑

B.在合同或其他项目授权文件被批准后通常就不成为问题了

C.应该从项目概念形成阶段到收尾阶段一直加以管理与控制

D.主要是项目执行期间变更控制程序处理的一个问题

8.At the end of a project, a project manager determines that the project has added four areas of functionality and three areas of performance. The customer has expressed satisfaction with the project. What dose this mean in terms of success of the project?

A. The project was an unqualified success

B. The project was unsuccessful because it was gold plated

C. The project was unsuccessful because the customer being happy means they would have paid more for the work

D. The project was successful because the team had a chance to learn new areas of functionality and the customer was satisfied

8. 某项目即将结束。项目经理确定该项目在产品功能方面增加了四项,在产品性能方面增加3项。顾客对此感到非常满意。从项目是否成功来看意味着什么?

A. 该项目非常成功

B. 因为该项目“镀金”,所以是个失败的项目

C. 由于顾客将为产品功能的增加而付出更多的资金,所以项目不成功

D. 项目团队有机会学习一些新的产品功能,并且顾客对产品表示满意,所以该项目是个成功的项目

9.A project manager is in the process of validating scope of a deliverable with the customer. What is the MOST important thing the project manager should ensure?

A. Accuracy

B. Timeliness

C. Acceptance

D. Completeness

9. 项目经理在与客户进行某可交付成果的确认范围过程。下面哪项是项目经理应该确定的最重要的事情?

A.正确程度

B.时间符合要求

C.接受

D.完全

10.The process of creating a work breakdown structure results in?

A. A project schedule

B. Team buy-in

C. A project completion date

D. A list of risks

10.创建工作分解结构过程的结果是:

A.项目进度计划

B.团队意见统一

C.项目完成日期

D.风险清单

11.Your customer asked you to perform some additional tasks that are not included in the formal contract.You should:

A. acknowledge the request and advise the customer to submit a formal change request

B. accept the request as sign of future business chance

C. rufuse the request and report to the project sponsor

D. convenne a meeting of the project team and rewrite the project scope statemen

11. 客户要求你实施一个正式合同不包括的任务,你应该:

A. 了解这个请求,并建议客户提交一个正式的变更请求

B. 作为将来业务机会的迹象,接受客户请求

C. 否决请求并向项目发起人汇报

D. 召集项目团队会议并重写项目范围说明书

12. You are assigned as a project manager to lead a new quality improvement project. Management is asking for a plan. Which of the following should you create FIRST?

A. Scope statement

B. Quality plan

C. Schedule

D. Project plan

12.你被分配为一个新的质量改进项目的项目经理。管理层要求创建一个计划。下面哪项你必须首先创建?

A.范围说明书

B.质量计划

C.进度表

D.项目计划

13.Scope decomposition involves subdividing the major project deliverables into smaller pieces to:

A. improve accuracy of estimates, define a baseline for performance, and to assist responsibilityassignments.

B. provide more tasks to assign resources.

C. provide the project duration, provide project control, and assign control charts.

D. assist in stakeholder assignment to project tasks.

13. 范围分解通过将大的项目可交付成果分解为较小的组织部分以:

A.改进估算的准确程度,定义项目绩效的基线,而且有助于职责分配

B.准备更多的任务去分配资源

C.提供项目历时,提供项目控制,分配控制图

D.帮助向项目干系人分配项目任务

14.A key reason to use a work breakdown structure is to

A. Organize the work

B. Prevent work from slipping through the cracks

C. Provide a basis for estimating the project

D. All of the above

14. 使用工作分解结构的主要原因是:

A.组织工作

B.避免工作因失去控制而拖延

C.为项目估计提供基础

D.所有上述选项

15. A project manager is concerned abort the amount of gold plating that has been occurring on past project. All the following would not be of use in controlling gold plating EXCEPT:

A.A staffing management plan.

B.A project charter.

C.A work breakdown structure dictionary.

D.A risk management plan.

15. 一个项目经理正在关心发生在过去项目的镀金量。除以下()都不用于控制镀金。A.人员管理计划

B.项目章程

C.工作分解结构词典

D.风险管理计划

16. The construction phase of a new software product is near completion. The next phase is testing and implementation. The project is two weeks ahead of schedule. What should the project manager be MOST concerned with before moving onto the final phase?

A. Validate scope

B. Quality control

C. Report performance

D. Control cost

16.一个新软件产品的构建阶段即将完工。下一个阶段是测试和执行。这个项目比进度计划提前了两周。在进入最后阶段之前,项目经理最应该关注什么?

A.确认范围

B.质量控制

C.绩效报告

D.成本控制

17. You recently finished working on a project team that required extensive overtime to meet a demanding schedule. Although the initial tasks involving

computer design were a good fit for you, you also were required to produce numerous technical documents and to perform several programming tasks. The tasks involving technical documents and programming were not a part of your original assignment and were not in your area of expertise. You had to work many weekends and nights to get everything done. You wondered why you had to do the work and why it was not assigned at the beginning of the project. You are managing the company’s next project and want to avoid a similar situation. Therefore, you should:

A. Ensure that the WBS is detailed enough and that all the activities are defined in sufficient detail.

B. Use project management software that includes resource histograms and resource leveling.

C. Ensure that all work efforts are traced back to the scope statement for scope verification.

D. Use critical chain scheduling to account for possible unplanned events with its emphasis on buffers.

17. 你最近刚刚结束了一个项目的工作,这个工作要求你做大量的额外工作以按时完成任务。虽然起初的电脑设计工作很适合你,但是你同时要处理大量技术文档和复杂的编程工作。最初你进入到这个项目以后给你分配的工作并不包括准备技术资料和编程,而且这些工作也不是你的专长,你不得不在周末和夜晚加班工作。

你在疑问为什么自己要做这些工作,以及为什么一开始的时候没有分配好工作。你马上要开始管理公司的下一个项目,非常希望避免出现类似的情况,你应该:

A. 确保工作分解结构足够详细,所有的活动都有详细地阐述

B. 使用包含资源柱状图和资源平衡图的项目管理软件

C. 确保所有的工作都与项目范围说明一致,以核实项目范围

D. 利用关键链进度法来设置缓冲以包含那些未计划到的工作

18.Sponsor decreased the Project funding significantly. What is the alternative?

A. Request to the sponsor for additional fund

B. Reduce the scope to fit the budget.

C. Due to the decreased fund, it is not possible to continue the project.

D. Complete scope for available budget.

18. 在项目发起人大量减少项目资金的情况下,下面哪种做法是正确的?

A.要求发起人额外增加资金

B.按照预算缩小范围

C.由于减少了资金,项目已经不可能继续执行

D.完成可用预算的范围

19.A WBS is BEST described as a tool for tracking:

A. the schedule.

B. resources.

C. cost.

D. scope.

19. WBS被认为是跟踪__的最好的工具

A. 进度

B. 资源

C. 成本

D. 范围

20.Your customer signed off on the requirements definition document and scope statement of your video game project last month. Today she requested a project scope change. She would like to make it an interactive game that can be played on a person's television and on a computer. This represents a scope change that, at a minimum

A.Modifies the project's agreed-upon scope as defined by the WBS B.Results in a change to all project baselines

C.Requires adjustments to cost, time, quality, and other objectives D.Results in a lesson learned

20. 你在负责管理一个视频游戏的项目。上个月客户已经签署项目需求说明和范围说明。但是现在她提出了一项范围变更要求。她希望把这个游戏做成一种在电视和电脑上都能玩的互动式游戏。这种范围变更至少会表现在哪一个方面?

A.修改工作分解结构己经确定的项目范围

B.导致所有项目基线的变更

C.需要对成本、时间、质量以及其他目标进行调整

D.得到一个经验教训

21.A work package is a

A. Deliverable at the lowest level of the WBS

B. Task with a unique identifier

C. Required level of reporting

D. T ask that can be assigned to more than one organizational unit

21. 工作包是:

A.最低层次工作分解结构的可交付成果

B.具有惟一标识的任务

C.报告的要求水平

D.可以被分配到一个以上组织单位的任务

22. When training new project team members, you were asked what should be done during validating scope, your answer should be:

A. Verify product correctness

B. Create WBS

C. Inspection

D. Performance measurement

22. 在培训新的项目团队成员时,项目团队成员问你确定范围应该怎么做,你的回答是:

A. 核实产品的正确性

B. 建立WBS

C. 检查

D. 绩效测量

23. System analysis/engineering, value engineering and value analysis are all examples of?

A. Alternatives identification

B. Expert judgment

C. Product analysis

D. Validate Scope

23. 系统分析/系统工程、价值工程和价值分析属于什么的例子?

A. 替代方案识别

B. 专家判断

C. 产品分析

D. 确认范围

24. These two processes in the Controlling process group are performed in parallel to assure correctness and acceptance of the work. Which are they?

A. Quality Assurance and Validate Scope

B. Quality Assurance and Control Scope

C. Quality Control and Validate Scope

D. Quality Control and Control Scope

24. 在控制过程中有两个过程同步进行以保证工作的正确性和验收,这两个过程分别是:

A. 质量保证和确认范围

B. 质量保证和控制范围

C. 质量控制和确认范围

D. 质量控制和控制范围

25. Which of the following is an important input to validate scope?

A. Verified deliverables

B. Historical information

C. Formal acceptance

D. Change request

25. 以下哪项是确认范围的重要依据?

A. 核实的可交付成果

B. 历史信息

C. 正式验收

D. 变更请求

26.Who rarely request changes to the project scope?

A. Project manager

B. Functional managers

C. Customer

D. Sponor

26. 谁对项目范围很少提出变更请求?

A. 项目经理

B. 职能经理

C. 客户

D. 发起人

27. A deliverable fails to give expected results, but was formally accepted by the customer. Which of the following best describes the activity involved?

A. Inspection

B. Rework

C. Quality audit

D. Validate scope

27. 一个可交付成果未能达到预期的结果,但是客户依然正式验收了。下述哪项最好地描述了这项活动?

A. 检验

B. 返工

C. 质量审计

D. 确认范围

28. Just assigned as a Project Manager to a new petrochemical facility construction project and have been given the completed project scope, you will first:

A. Create a project plan using the WBS.

B. Confirm that all the stakeholders have had input to scope of work.

C. Form a team to create the procurement plan.

D. Create a network diagram.

28. 你刚刚被公司安排为一个新石油化工装置建设项目的项目经理。你拿到了完整的项目范围,首先你要:

A. 用工作分解结构生成项目计划

B. 确认是否所有的项目利害关系者都对项目工作范围提供了依据

C. 组成团队创建采购计划

D. 制定网络图

29. The project is completed and the final deliverable has been sent to the customer, but the customer refuses to give final acceptance on the project. It is most important for the manager to:

https://www.360docs.net/doc/6c1892632.html,rm management of the situation

B.Ask the team for assistance

C.Document the situation

D.Initiate legal proceedings

29. 项目完成且日以继夜成果已交付客户,但客户拒绝签发最终验收报告。此时项目经理要做的最重要做的事是:

A. 通知管理层

B. 寻求团队的帮助

C. 做好记录

D. 采取法律行动

30. You are working on a project that is similar in scope to a project performed last year by your company. You might consider which of the following?

A. Using the previous project’s alternatives identification as a template

B. Reusing the pre vious project’s benefit/cost analysis as justification for this project

C. Using the previous project’s WBS as a template

D. Reusing the previous project’s product description when writing the scope statement

30. 你正在进行的一个项目和你公司去年进行的一个项目的范围是类似的。你可以考虑下列哪一项?

A. 利用从前项目的方案识别作为模板

B. 重复利用从前项目的效益/成本分析作为验证该项目的依据

C. 利用从前项目的WBS作为模板

D. 撰写范围说明书时重复利用从前项目的产品描述

31.Validate scope should be done?

A. At the end of the project

B. At the beginning of the project

C. During each phase of the project

D. Once during planning

31.确认范围应该在( )

A.项目结束时

B.项目开始时

C.项目每个阶段期间

D.计划编制期间进行一次

32.Which of the following is correct in regard to scope change control?

A. Scope change control is never integrated with other control processes.

B. Controlling cost is the most effective way of controlling scope.

C. Scope change control must be integrated with other control processes.

D. Controlling schedule is the most effective way of controlling scope.

32. 下面哪个关于范围变更控制的说法是正确的?

A.范围变更控制从来都不需要和其它控制过程综合在一起

B.控制成本是控制范围的一种有效的方式

C.范围变更控制必须和其它控制过程综合在一起

D.控制进度是控制范围的一种有效的方式

33.The tool that provides a basis to identify the work that must be scheduled is the

A. Master schedule

B. Budget

C. WBS

D. Gantt chart

33. 可以帮助我们明确有哪些工作必须计划的工具是:

A.项目主进度表

B.预算

C.工作分解结构

D.甘特表

34.The product scope is measured against the ( ),

A. contract

B. measure of success

C. product requirements

D. scope baseline

34. 产品范围以( )为标准进行测量。

A.合同

B.对成功的度量

C.产品需求

D.范围基线

35.Each item of the Work Breakdown Structure is assigned a unique identifier. What is the name of this identifier?

A. quality inspection identifier.

B. Chart of accounts

C. Project activity code

D. Code of accounts

35. 工作分解结构的每一项都被分配了惟一的一个标识符。该标识符的名称是什么? A.质量检查标识

B.会计科目表

C.项目活动编码

D.账户编码

36.( ) contains detailed descriptions of work packages.

A. WBS Dictionaries

B. Scope of work

C. Budget estimates

D. Cost estimates

36. ( )包含了工作包的详细说明。

A.工作分解结构词典

B.工作范围

C.预算估计

D.成本估算

37. All of the following are inputs into Create WBS EXCEPT:

A. Work Breakdown Structure.

B. Project scope statement.

C. Requirements documentation

D. Organizational process assets.

37. 下面都是创建WBS这一过程的输入,除了:

A. 工作分解结构

B. 项目范围说明书

C. 需求文件

D. 组织过程资产

38.You are asking R&D staffs to lower you sots but with the same exact scope of work. Your staff will firstly-

A. offer to reduce the quality of the end product.

B. Do a value engineering.

C. Look at procuring less expensive resources.

D. Do a cost/benefit analysis.

38. 你要求你的研发人员在不改变工作范围的前提下降低你的成本。你的研发人员将首先:

A. 提议降低最终产品的质量

B. 做一次价值工程

C. 着眼于采购便宜些的资源

D. 做一次成本/收益分析

39.The preparation of the scope baseline involves the:

A. functional managers.

B. project manager

C. Project manager,PMO,functional team and project sponsor.

D. project expediter.

39. 准备范围基线需要下列哪些人员参与?

A.职能经理

B.项目经理

C.项目经理、PMO、职能团队和项目发起人

D.项目促进者

40. During the execution phase of the project, you realized the subcontractors are working with incomplete and different scope statements. As the project manager, what should you do FIRST:

A. Check the work completed against the correct scope statements.

B. Review the scope of work with the stakeholders.

C. Document the inconsistencies to management, calculating the cost of non-conformance.

D. Stop all activities until the scope of work is complete.

40. 在项目的实施阶段期间,你发现分包商在按照不完整并且不同的范围说明进行工作。作为项目经理,你应该首先做什么?

A.检查按照正确对待的范围说明完成工作

B.与项目干系人一起审核工作范围

C.用文件记录与管理不一致之处,计算不一致性的成本

D.在工作范围完整之前停止工作

41. 下述关于WBS的说法,正确的是?

A. 所有可交付成果有相同的分解层次

B. 所有可交付成果应该分解到最大层次

C. 不同的可交付成果可以有不同的分解层次

D. 所有可交付成果可以有不同的分解层次

42. 当一名团队成员为工作包定义活动时,找到你说目前信息不足,不能分解成具体的活动。你指示该成员,把工作包分解到里程碑的水平。这体现了?

A. 50-50规则

B. 100%规则

C. 滚动式规划

D. 你关心团队成员

43.在以下情形需要修订WBS:

A. 定义了新的项目的可交付成果

B. 分配了额外资源

C. 项目限制因素被改变

D. 定义了的依赖关系

44. 在什么阶段会参考需求跟踪矩阵?

A.启动

B.执行

C.收尾

D.整个项目生命周期

45.You are having difficulty estimating the cost of a project. Which of the following BEST describes the most probable cause of your difficulty?

A. Inadequate scope definition

B. Unavailability of desired resources

C. Difficulty in scheduling

D. Lack of adequate budget

45. 在估算某个项目成本时遇到些困难。下面哪项最好的描述了出现这些困难的大多数原因?

A.不充分的范围定义

B.想要得到的资源不可用

C.进度规划中的困难

D.缺乏足够的预算

46. What is the WBS typically used for?

A. To identify the logical person to be project sponsor.

B. To organize and define the total scope of the project.

C. To define the level of reporting the seller provides the buyer.

D. As a record of when work elements are assigned to individuals.

46. WBS典型的用途是?

A. 去识别合适的项目出资人

B. 组织和定义项目的所有范围

C. 定义提供商提供给买主的包括的层次

D. 在工作元素分配给个人的时间记录

47.Starting from formal scope change request by an internal stakeholder,a project manager has taken scope change control process.What is the next step?

A. Ensure the stakeholder understood the impact of the change

B. Before you move into next step.make sure that there will not be any more changes

C. Submit the change for the approval by change control board(CCB)

D. Complete integrated change control

47. 从内部干系人的正式范围变更请求开始,项目经理采取了范围变更控制过程。下一步做什么?

A. 确保干系人理解变更的影响

B. 在你开始下一步之前,确保再没有任何变更

C. 通过变更控制委员会提交批准的变更

D. 完成整体变更控制

48. During planning, a project manager discovers that part of the scope of work is undefined. What should the project manager do?

A. Remove the scope of work from the project and include it in the upgrade to the project

B. Continue to plan for the project until the scope of work is defined

C. Issue a change to the project when the scope is defined

D. Ask management to help get the work defined

48. 在规划时,项目经理发现部分工作范围没有定义。项目经理应该怎么作?

A. 将这部分工作范围从项目中去掉,并把它放到项目升级里

B. 继续规划项目,直到工作范围完成定义

C. 当范围定义后,对项目进行一次变更

D. 求助于管理层完成工作定义

49.Two people on the same project team have just found out they are working on the same scope of work. This is an example of a lack of:

A. good work breakdown structure.

B. a matrix organization.

C. sponsor direction.

D. status meetings.

49. 同一项目团队中的两个人发现他们工作范围一样。这是一个缺乏什么的例子?

A.非常好的WBS

B.矩阵型组织

C.项目投资人指导

D.状态会

50. 在以下哪一个项目管理过程组用到需求跟踪矩阵?

A.执行过程组Executing Processes

B.规划过程组Planning Processes

C. 监控过程组Monitoring & Controlling Processes

D.启动过程组Initiating Processes

答案:

1.

参考答案:D。工作包的详细程度因项目规模与复杂程度而异,一般不要超过80小时。

参见培训讲义第98页,或《PMBOK指南》第五版第128页

2.

参考答案:B。变更需要遵循变更管理流程。参见培训讲义第68页,或《PMBOK指南》第五版第94-100页

3.

参考答案:B。变更需要遵循变更管理流程。参见培训讲义第68页,或《PMBOK指南》第五版第94-100页

4.

参考答案:B。变更需要遵循变更管理流程。参见培训讲义第68页,或《PMBOK指南》第五版第94-100页

5.

参考答案:B。确认范围就是验收可交付成果。参见培训讲义第102页,或《PMBOK

指南》第五版第133页

6.

参考答案:D。确认范围在于验收可交付成果,控制质量在于确定可交付成果的正确性。参见培训讲义第103页,或《PMBOK指南》第五版第134页

7.

参考答案:C。范围是基础,需要从头至尾加强管理

8.

参考答案:B。PMI的理念:拒绝镀金。镀金的项目是失败的项目。参见培训讲义第105页

9.

参考答案:C。确认范围就是验收可交付成果。参见培训讲义第102页,或《PMBOK 指南》第五版第133页

10.

参考答案:B。根据PMI的理念,项目团队成员一起共事可以达到团队建设的效果。比如创建工作分解结构,能形成团队一致。参见培训讲义第98页

11.

参考答案:A。变更需要遵循变更管理流程。参见培训讲义第68页,或《PMBOK指南》第五版第94-100页

12.

参考答案:A。范围是基础,首先确定范围,才能确定进度和质量,最后综合协调为项目计划

13.

参考答案:A。参见《PMBOK指南》第五版第131页

14.

参考答案:D

15.

参考答案:C。镀金是指做了额外工作,范围基准可用于控制镀金,选项C属于范围基准的一部分。

16.

参考答案:A。重点关注可交付成果的验收,即确认范围

17.

参考答案:A。把范围分解细致,分配责任到人,就可以避免类似情况发生

18.

参考答案:B。发起人减少资金,应该是缩小范围

19.

参考答案:D。WBS组织并定义项目的总范围。参见培训讲义第95页,或《PMBOK 指南》第126页

20.

参考答案:A。范围变更会修改已确定的范围

答案:

21.

参考答案:A。工作包是WBS是最底层,是具体的可交付成果,须由一个人或一个部门负责。参见培训讲义98页,或《PMBOK指南》第五版第128页

22.

参考答案:C。确认范围的工具。参见培训讲义第103页,或《PMBOK指南》第五版第133页

23.

参考答案:C。产品分析包括的具体方法。参见培训讲义第93页,或《PMBOK指南》第五版第122页

24.

参考答案:C。质量控制和确认范围的区别。参见培训讲义第103页,或《PMBOK指南》第五版第134页

25.

参考答案:A。确认范围的输入。参见培训讲义第103页,或《PMBOK指南》第五版第133页

26.

参考答案:A。尽量少变更

27.

参考答案:D。确认范围就是让客户验收可交付成果。参见培训讲义第102页,或《PMBOK 指南》第五版第133页

28.

参考答案:B。你没有参与范围定义,先要确认范围是否定义清晰,干系人是否提供了完整的需求

29.

参考答案:C。及时做好文字记录

30.

参考答案:C。参考组织过程资产的历史信息,即从前项目的WBS模版。参见《PMBOK 指南》第五版第128页

31.

参考答案:C。确认范围属于监控过程组,需要在贯穿整个项目生命周期

32.

参考答案:C。范围变更控制过程需要与实施整体变更控制过程结合处理。参见培训讲义第105页,或《PMBOK指南》第五版第137页

33.

参考答案:C。明确工作就是指确定范围,由WBS来定义范围。参见培训讲义第95页,或《PMBOK指南》第五版第126页

34.

参考答案:C。参见培训讲义第75页,或《PMBOK指南》第五版第106页

35.

参考答案:D。参见培训讲义第98页,或《PMBOK指南》第五版第128页

36.

参考答案:A。参见培训讲义第102页,或《PMBOK指南》第五版第132页

37.

参考答案:A。参见培训讲义第96页,或《PMBOK指南》第五版第125页

38.

参考答案:B。价值工程的定义。参见培训讲义第93页,或《PMBOK指南》第五版第561页

39.

参考答案:C。准备范围基准,应该鼓励所有相关的干系人参与

40.

参考答案:A。题干中“分包商在按照不完整并且不同的范围说明进行工作”--说明范围未定义好,需要重新定义范围

答案:

41.

参考答案:C。参见培训讲义第98页,或《PMBOK指南》第5版第131页

42.

参考答案:C。参见培训讲义第113页,或《PMBOK指南》第5版第152页

43.

参考答案:A。WBS以可交付成果为分解对象,当有新的可交付成果,WBS需要更新。参见培训讲义第95页,或《PMBOK指南》第5版第128页

44.

参考答案:D。参见培训讲义第90页,或《PMBOK指南》第5版第118页

45.

参考答案:A。范围是基础,当范围不确定时,估算时间或成本就会遇到困难

46.

参考答案:B。参见培训讲义第95页,或《PMBOK指南》第5版第126页

47.

参考答案:D。范围变更控制须与实施整体变更控制结合处理。参见培训讲义第105页,或《PMBOK指南》第5版第137页

48.

参考答案:B。发现范围没有定义清晰,就继续定义清晰

49.

参考答案:A。WBS最底层是工作包,确保只有一个人负责。如果有二个人工作范围一样的,说明WBS没有制定好

50.

参考答案:C。确认范围过程和控制范围过程需要参考需求跟踪矩阵,这二个过程属于监控过程组

相关主题
相关文档
最新文档