AC-DT-6发电机试验作业指导书-中英文

AC-DT-6发电机试验作业指导书-中英文
AC-DT-6发电机试验作业指导书-中英文

类别电气调试本期规模2×600MW

印度安巴拉

C厂2×600MW机组

机组编号#1机组编号AC-DT-6

发电机作业指导书

Generator instruction

批准:

审核:

编制:

2009年11月

目录

Contents

1、编制目的 (03)

Compilation purpose

2、编制依据 (03)

Compilation gist

3、设备概况 (03)

General instruction of the equipment

4、试验准备 (03)

Preparation for the test

5、试验内容、方法及注意事项 (03)

Testing content, method and precaution

6、危害辩识及技术安全措施 (09)

Dangerous identification and technical safety measures

1、编制目的

Compilation purpose

本作业指导书适用于额定功率为50MW及以上、环氧粉云母绝缘的三相同步发电机和同步调相机,规定了发电机交接验收、预防性试验、检修过程中的常规电气试验的引用标准、仪器设备要求、作业程序、试验结果判断方法和试验注意事项等。制定本作业指导书的目的是规范操作、保证试验结果的准确性,为设备运行、监督、检修提供依据。

This instruction is suitable for the epoxy mica insulating three-phase synchronous generator and synchronous condenser whose rating power is over 50MW, stipulates the quotation standard, operation procedure, apparatus and equipment requirement, the method of judging the test result and test notices of the generator acceptance test, preventive test and conventional electrical test under the overhaul process. The purpose of this instruction is to standardize operation, guarantee the accuracy of the test result and provide the basis for the equipment operation, supervision and maintenance.

2、编制依据

Compilation gist

2.1设计院关于印度安巴拉C厂2×600MW工程#1机组的有关设计图纸及厂家的技术资料

The related design drawing and technical documents of the manufactory for the India, Anpara-C 2X600MW power plant project.

2.2合同中相关规定。

The related regulation in the contract.

3、设备概况

General instruction of the equipment

印度安巴拉C厂2×600MW机组项目工程汽轮发电机组参数如下:

The parameter of the turbine-generator unit in India, Anpara-C 2X600MW project is as follow: 型号QFSN-600-2-22D

Type:

额定功率600MW

Rating power:

额定电压22KV

Rating voltage:

额定电流18525A

Rating current:

额定功率因数0.85

Rating power factor:

额定频率50Hz

Rating frequency:

额定转速3000r/min

Rating rotate speed:

相数 3

Phase:

接法2-Y

Connection:

额定励磁电流4727A

Rating excitation current:

额定励磁电压431V

Rating excitation voltage:

4、试验准备

Preparation for the test

4.1应在试验开始之前详细记录试品的铭牌参数,检查、了解试品的状态及其历史运行有无异常情况,并进行记录。

It should make a detailed record of the nameplate parameter of the test pieces before the test, check and know the test piece’s state and whether there are abnormal conditions in its history operation and make a record.

4.2应根据交接或预试等不同的情况依据相关规程规定,从下面项目中确定本次试验所需进行的试验项目和程序。

It should confirm the items and procedure of this test from the below items according to the different conditions of the acceptance test and preventive test and related regulation of the rule.

5、试验内容、试验方法及注意事项

Testing content, method and precaution

5.1发电机常规试验包括以下试验项目:

The normal test items of the generator are as follow:

定子绕组的绝缘电阻、吸收比

The insulated resistance and absorptance of the stator winding

定子绕组的直流电阻

DC resistance of the stator winding

转子绕组的绝缘电阻

The insulated resistance of the rotor winding

转子绕组的直流电阻

DC resistance of the rotor winding

转子绕组的交流阻抗和功率损耗

The AC impedance and power loss of the rotor winding

轴电压

Shaft voltage

5.2定子绕组的绝缘电阻、吸收比

The insulated resistance and absorptance of the stator winding

5.2.1设备清单和要求

The equipment list and requirement

a)温度计(误差±1℃)、湿度计;

Thermometer (error±1℃), hygrometer;

b)对空冷、氢冷及水冷绕组水回路干燥或吹干测量,应采用量程不低于10000MΩ的

2500V兆欧表;对水冷绕组通水测量应采用水内冷电机绝缘测试仪(简称专用兆欧表)。It should dry the water loop or blow drying measurement to the air cooling, hydrogen cooling and water-cooling windings, adopt the 2500V megar whose range should be not less than 10000MΩ; it should adopt internal water cooling insulated test meter (for short, special ohmmeter) to measure the water cooling winding water-through.

5.2.2测试方法

Measuring method

如果各绕组的首末端单独引出,则应分别测量各绕组对机壳及绕组相互间的绝缘电阻,这时所有其他绕组应同机壳做电气连接。当中性点不易分开时,则测量所有连在一起的绕组对机壳的绝缘电阻。

If each winding head end and terminal end was led out separately, it should measure the insulated resistance between each winding and the casing and between the windings separately, at this time, electrically connect all the other windings with the casing. When the neutral point is not easy to be

separated, it should measure the insulated resistance between all the joined winding and the casing.

a)测量前要把所有发电机出口电压互感器拉出或拆掉电压互感器的一次保险。

It should pull out all generators outlet voltage transformers or dismantle primary insurance of the voltage transformer before the measurement.

b)测量并记录环境温度和湿度,如果绕组温度与环境温度相差较大应测量定子膛内平均

温度作为绕组温度。

Measure and record the surrounding temperature and humidity, if the difference between the winding temperature and surrounding temperature is too big, it should measure the average temperature inside the stator bore as the winding temperature.

c)将所有绕组充分放电。

Discharge all the windings completely.

d)被测如果是水内冷发电机,将汇水管用导线引至试验场地。把汇水管所有引下线拧在

一起,用万用表测量汇水管对地电阻,通常应达到30kΩ以上方可进行步骤e)。将汇水管引线接至专用兆欧表的屏蔽端子上。

If the internal water cooling generator is measured, lead the confluent water pipe to the test field by the conductor. Wring all the down lead of the confluent water pipe together, use the multimeter to measure the confluent water pipe resistance to ground, usually when the resistance reach over 30kΩ, it can carry out the step (5.2.2.5). Connect the lead wire of the confluent water pipe with the shielded terminal of the special megohm-meter.

e)分相或分支测量时,每相或每个分支的绕组必须头尾短接,并将非被试绕组、转子绕

组连接至机壳。而测量绕组整体的绝缘电阻(如起机时不能分相测量)一般在发电机中性点接地变压器或电抗器隔离刀闸上口进行。

When measuring the split phase or branches, the head and the end of the windings of each phase or each branch must be shorted, and connect the non-tested winding and rotor winding with the casing (see graph 1). The insulated resistance used for measuring the winding entirety could be carried out on the generator neutral point grounding transformer or reactor isolated switch.

f)将地线端子用接地线和发电机的外壳连接好,用绝缘把手将火线接触被测量绕组的引

出端头上,开始测量。记录15秒、60秒、600秒的绝缘电阻值。

Connect the earth terminal with the casing of the generator by ground connection; contact the testing end with the exit end of the tested winding by the insulated handle, then start measuring. Set down the insulated resistance value at 15secs, 60secs and 600secs.

g)将被测绕组回路对接地的机壳作电气连接5分钟以上使其充分放电。

Connect grounding casing of the tested winding loop with the electric for more than 5mins to discharge it fully.

h)测量其他绕组。

Measuring other windings.

5.2.3试验结果判断依据

Judgment gist for test result

a)绝缘电阻值自行规定。若在相近试验条件下,绝缘电阻值低到历年正常值1/3以下时,

应查明原因。

The insulated resistance value meets the regulation. Under the similar test condition, if the insulated resistance value is under 1/3 of the annual normal value, find out the reason.

b)各相或分支绝缘电阻的差值不应大于最小值的100%。

The differential value between each phase or branch insulated resistance should be not more than 100% of the minimum value.

c)吸收比不小于1.6或极化指数不小于2.0;水内冷绕组自行规定。200MW以上机组推

荐极化指数。

Absorptance is not less than 1.6 or polarized index is not less than 2.0; internal water cooling winding is stipulated automatically, the unit which is over 200MW is recommended by polarized index.

5.2.4 注意事项

Precaution

a)对水内冷绕组,绝缘电阻测量值受内冷水水质的影响,因此试验时应水质良好,电导

率小于2μS/cm。

To the internal cooling water winding, the insulated resistance measurement value is affected by the water quality of the internal cooling water, therefore, the water quality should be in good conditions during test and electrical conductivity is less than 2μS/cm.

+1)MΩ机组即可启动(其中

b)如果测量带着封闭母线,有时绝缘电阻会较低,但达到(U

N

U

为发电机额定电压,单位:kV)。

N

If measure it with enclosed bus bar, sometimes, the insulated resistance could be lower, it could startup the unit if the insulated resistance reaches (U N+1)MΩ(U N stand for rating voltage of the generator, unit: kV ).

c)应考虑环境温度和湿度对测量结果的影响。

It should be considered that the effect of the environmental temperature and humidity on the result.

5.3 定子绕组的直流电阻

The DC resistance of the stator winding

5.3.1设备清单和要求

Equipment list and requirement

a)3~5支温度计(误差±1℃)

3~5 pieces thermometer(error±1℃)

b)有效位数不低于4位、0.5级以上10-5~10-1Ω双臂电桥或0.5级以上直流电阻测试

仪。

Effective digit should be not less than 4, 10-5~10-1Ωdouble bridge over 0.5 grade or d.c resistance test meter over 0.5 grade.

5.3.2测试方法

Measuring method

a)冷态测量,绕组表面温度与周围空气温度之差不应大于±2℃。

Cold measurement, the difference between the surface temperature of the winding and surrounding air temperature should not be over ±2℃.

b)如果各分支的首末端单独引出,则应分别测量各分支的直流电阻。

If the head end and terminal end of each branch has been led out separately, it should measure the direct current resistance of each branch separately.

5.3.3试验步骤

Testing programs

a)在定子膛内放置3~5支温度计15min以上,记录并计算平均值作为绕组平均温度。

如果温差大于2℃,应找出原因并排除。

It should place 3~5 pieces thermometers in the stator bore for over 15min, record and calculate the average value as the winding average temperature. If the temperature difference is over 2℃, find out the reason and resolve it.

b)其他非被测的绕组短路接地,测量各相或各分支的直流电阻值。每一电阻应测3次,

每次应在电桥平衡破坏后重新进行测量,每次读数与3次读数平均值之差在0.5%以内时,取平均值作为测量值。

Ground other non-tested winding short circuit, measure the DC resistance value of the each phase and each branch. Measure 3 times on each resistance, re-measure it after the bridge balance is broken every time, when the difference between every indication and the average value of 3 times

indication is within 0.5%, take the average value as the measurement value.

5.3.4试验结果判断依据

Judgment gist for the test result

a) 各相或各分支直流电阻值互差以及与初次测量值比较,相差值不大于最小值的1.5%

(水轮机为1%)。

Compare the DC resistance value difference between each phase and each branch with the initial measurement value, the differential value should not exceed 1.5% of the minimum value(hydraulic turbine should be 1%)

相间或分支间互差= 最小值

最大值-最小值 ×100% Inter-phase difference or inter-branch difference =

min min max - ×100% 与初次测量值互差=

初次值初次值测量值-×100% The difference compared with

the initial measurement value = value initial value

initial t value measuremen -×100%

其中测量值为换算到同一温度t 0(初次值的绕组测量温度)后的值R 0,

R 0 = ta +235t +2350 R a

The measurement value represents R 0 value after conversion from the same temperature t 0(the winding measurement temperature of the initial value )

式中t a 为测量时绕组平均温度,R a 为测量值。

In the formula, t a represent the winding average temperature, R a represent measurement value.

b) 汽轮发电机相间差或分支间差与历年的相对变化大于1%时应引起注意。

Compare the turbine generator inter-phase difference or inter-branch difference with the history relative changes, if over 1%, pay attention to it.

5.4转子绕组的绝缘电阻

the insulated resistance of the rotor winding

5.4.1设备清单和要求

Equipment list and requirement

1) 温度计(误差±1℃)、湿度计;

Thermometer (error±1℃), hygrometer.

2)500V(或制造厂要求电压等级的)兆欧表;

500V or the voltage grade required by manufacturer megohm-meter

3)有300mm以上绝缘手柄的电刷(发电机动态空转测量时)。

Brush with over 300mm insulated handle which is used for measuring the generator dynamic free running.

5.4.2测试方法

Measuring method

分静态和动态空转两种情况。将兆欧表的测试线接于转子滑环上、地线接于转子轴上。It has two kinds, static and dynamic free running. Connect the test line of the megohm-meter with the rotor slip ring, connect the earth wire with the rotor axis.

5.4.3试验步骤

Test programs

a)静态测量前将滑环短路接地放电,提起碳刷测量。

Ground the slip ring to discharge before static measurement, then take up the carbon brush measurement.

b)动态空转测量时,断开灭磁开关到碳刷架的励磁母线或电缆,将碳刷提起,测量不同

转速下的绝缘电阻。该项目试验结束后发电机加励磁前恢复接线。

During dynamic free running measurement, switch off the excitation bus bar or cable from the de-excitation switch to the carbon brush holder, then take up the carbon brush, measure the insulating resistance under different rotating speed. Reconnect the wire before the generator adding excitation after the item test.

5.4.4安全措施

Safety measures

动态测量时特别注意,不得同时接触两极或一极与接地部分,谨防衣物或其他物品被旋转物挂住。

During the dynamic measurement, pay much attention to following things, forbid contacting two poles or contact one pole and grounding part at the same time, beware of the cloth or other objects not being stuck by the rotating objects.

5.4.5试验结果判断依据(或方法)

Judgment gist (or method) of test result

a)室温下,绝缘电阻一般不应小于0.5MΩ。

Under the room temperature, commonly the insulated resistance should be not less than 0.5MΩ.

b)室温下,水内冷转子绕组绝缘电阻值一般不小于5kΩ。

Under the room temperature, commonly the insulated resistance value of the internal water cooling rotor winding should be not less than 5kΩ.

5.4.6 注意事项

Precaution

a)不宜将兆欧表的地线接在机座或外壳上。

It is inadvisable to connect the earth wire of the mega-meter with the casing or frame.

b)动态空转高转速测量时绝缘电阻值可能会降低较多,应进行综合分析,一般不小于判

断依据中规定的数值,就认为试验通过。

During the dynamic free running high rotating speed measurement, the insulated resistance value might reduce a lot, it should carry out comprehensive analysis, and the test is passed if the insulated resistance value is not less than the stated value of the judgment gist.

5.5 转子绕组的直流电阻

DC resistance of the rotor winding

5.5.1设备清单和要求

Equipment list and requirement

a)温度计1支(误差±1℃);

Thermometer 1 piece (error±1℃);

b)有效位数不低于4位、0.5级以上10-5~10-1Ω双臂电桥或0.5级以上直流电阻测试

仪。

Effective digit should be not less than 4, 10-5~10-1Ωdouble bridge over 0.5 grade or DC resistance test meter over 0.5 grade.

5.5.2测试方法

Measuring method

冷态测量,绕组表面温度与周围空气温度之差不应大于±2℃。

Cold measurement, the difference between the surface temperature of the winding and surrounding air temperature should be not more than ±2℃.

5.5.3试验步骤

Testing program

a)测量绕组表面温度(困难时可用转子表面温度代替),测点不少于3点,取平均值作

为绕组的冷态温度。对水内冷绕组在通水情况下,可在绕组进出口水温差不超过1K,铁心温度与环境温度不超过2K时,取进出口水温的平均值作为绕组的冷态温度。Measure the winding surface temperature (if it is difficult, it could be replaced by the rotor surface temperature), the measurement point should be not less than 3 point. Take the average value as the winding cold temperature. When the internal water cooling winding is under water-through condition, if the temperature difference between the inlet and outlet is not over 1K and the difference between the core temperature and environment temperature is not over 2K, take the average value of the inlet/outlet temperature as the winding cold temperature..

b)将测量设备或仪表接到滑环上进行测量。转子滑环光滑不易接线,应注意把测量线接

牢,否则读数不稳定。

Connect the measuring equipment or instrument with the slip ring to measure. It is not easy to connect with the slip ring because of its smoothness, connect the measuring line firmly, otherwise, the indication would be not steady.

c)当采用电桥测量时,每一电阻应测3次,每次应在电桥平衡破坏后重新进行测量,每

次读数与3次读数平均值之差在0.5%以内时,取平均值作为测量值。

When use the bridge to measure, it should measure 3 times on each resistance, re-measure it after the bridge balance is breaking every time, when the difference between every indication and the average value of 3 times indication is within 0.5%, take the average value as the measurement value.

5.5.4试验结果判断依据

Judgment gist of the test result

a)按5.2.3第a)条中公式将测量值为换算到同一温度(初次值的绕组温度)。Recalculate the measurement value to the same temperature (winding temperature of the initial value) according to the formula in the 5.2.3 a).

b)与初次值(交接或大修)所测结果比较,其差别一般不超过2%。

Compare with the measurement result of the initial value (handover or overhaul), commonly the difference should not exceed 2%.

5.6 转子绕组的交流阻抗和功率损耗

The AC impedance and power loss of the rotor windings.

5.6.1设备清单和要求

Equipment list and requirement

a)温度计(误差±1℃)

Thermometer (error±1℃)

b)220V调压器,容量可根据厂家提供的本项试验数据中电流值定;

220V pressure regulator, the capacity could be fixed according to the current value of this test date provided by the manufacturers.

c)0.5级交流电压表,量程通常选150V;

0.5 grade AC voltmeter with 150V range commonly.

d)0.5级交流电流表,量程5A;

0.5 grade AC ammeter with 5A range.

e)0.5级单相低功率因数功率表,量程通常选150V/5A/cosφ=0.1;

0.5 grade single-phase low power factor wattmeter with 150V/5A/cosφ=0.1 range commonly.

f)0.5级电流互感器,变比通常选50A/5A。

0.5 grade current transformer, no-load voltage ratio always choose 50A/5A.

5.6.2测试方法

Measuring method

a)隐极式转子在膛外或膛内以及不同转速下测量,显极式转子对每个磁极转子绕组测

量。

To the Cathodical rotor, measure the inside or outside of the bore and different rotating speed, to the explicit rotor, measure every magnetic pole rotor winding.

b)每次试验应在相同条件相同电压下进行,试验电压峰值不超过额定励磁电压(显极式

转子自行规定)。

Every test should be done under the same condition and same voltage, the test voltage crest value should not exceed rating excitation voltage (explicit rotor stipulated automatically).

c)交接时超速试验前后进行测量。

When handover, measurement should be carried out before or after the over speed test.

d)对于转子绕组有一点接地,或对水内冷转子绕组测量时,必须用隔离变压器加压,并

在转子轴上加装接地线。

It should ground one point to the rotor winding, or when measuring the internal water cooling rotor windings, it should raise the voltage by insulating transformer and install earth wire on the rotor axis.

5.6.3试验步骤

Testing program

a) 励侧回路断开,电压表要用最短的粗导线直接接于滑环1、2上。

disconnect the excitation side circuit, voltmeter should be connected with the slip ring 1,2 by the shortest thick conductor.

b) 用调压器TR 分级升压,测量并记录电压U 、电流I 和功率P 。

Use regulator TR to raise voltage by grade, measure and record voltage U, current I and power P.

5.6.4安全措施

Safety measures

膛内测量时定子绕组上有感应电压,应将定子绕组与外电路断开。

When measuring inside the bore, the stator winding has induced voltage, so it should cut off the connection between the stator winding and outer electric circuit.

旋转测量时注意谨防衣物或其他物品被旋转物挂住。

When rotating measurement, beware of the clothing and other objects not being stuck by the rotating objects.

5.6.5试验结果判断依据

Judgment gist for test result

交流阻抗Z 计算公式为:Z=I U 。

The calculating formula of the AC impedance is: Z=

I U

.

在相同的试验条件下,将测量的Z 与P 和原始(或历次)数值比较,相差10%应引起注意。相同的试验条件指转子同在膛内或膛外、相同的发电机转速和相同的试验电压。

Under the same test conditions, compare the measured Z and P value with the original (history) date, pay attention to it if the different is 10%. The same test condition means that the rotor is inside or outside the bore at the same time, the same generator rotating speed and same test voltage.

5.6.6注意事项

Precaution

影响交流阻抗和功率损耗的因素除了转子在膛内或膛外、发电机转速、试验电压有关外,还与槽楔、护环、转子本体剩磁等有关,分析时应综合考虑。

The factors which affect alternating current impedance and power loss, except for the rotor inside or outside the bore, generator rotating speed and test voltage, it also has relations with slot wedge, retaining ring and rotor body residual magnetism. It should consider comprehensively while analysis.

5.7轴电压

Shaft voltage

5.7.1设备清单和要求

Equipment list and requirement

万用表,交流电压档精度1.5级。

The accuracy of the multimeter and DC voltage is 1.5 grade.

5.7.2测试方法

Measuring method

被试发电机在额定电压、额定转速下空载和带不同负荷运行时,测量发电机大轴间的交流电压;对于端盖式轴承可仅测汽侧轴对地电压。对静态励磁的发电机,建议同时用示波器或录波仪测量轴电压波形。

When the tested generator operates with on-load or different load under the rating voltage and rating rotating speed, measure the direct current voltage between the generator large axis; to the head cover style bearing, it could only measure the earth voltage of the axis on the turbine side. To the generator of static excitation, it is suggested to use oscilloscope and oscillograph to measure the axis voltage wave shape at the same time.

5.7.3试验步骤

Testing program

a)检查轴承座的绝缘电阻。

Check the insulated resistance of the bearing block.

b)将轴上原有的接地保护电刷抬起。

Take up the original ground brush of the shaft.

c)对座式轴承按图5将两侧轴与轴承用铜刷短路,测量轴电压U

1和轴承座对地电压U

2

对于端盖式轴承按图6将汽侧轴用铜刷接地,测量轴电压。

To the counter housing bearing, short out the shaft and bearing of both sides by copper brush according to the chart 5, measure the shaft voltage U1 and earth voltage U2 of the bearing block. To the head cover style bearing, ground the shaft on the side of turbine by copper brush, measure the shaft voltage.

5.7.4安全措施

Safety measures

注意不使衣物或其他物品被旋转物挂住。

Beware of the cloth and other objects not being stuck by the rotating objects.

5.7.5试验结果判断依据

The judgment gist of the test result

a)轴对地电压一般小于10V。

Earth voltage of the shaft should be not less than 10V

b)对座式轴承U

1与U

2

应基本相等。

Counter housing bearing U1 and U2 should be equal basically.

5.7.6注意事项

Precaution

测点表面与电压表引线应接触良好。

The measuring point surface should have a good contact with the lead wire of voltmeter.

6、危害辩识及技术安全措施

Dangerous identification and technical safety measure

6.1原始记录的填写要字迹清晰、完整、准确,不得随意涂改,不得留有空白,并在原始记录上注明使用的仪器设备名称及编号。

The filling of the original record should be clear, complete and accurate without any modification casually, no blank is left, and mark out the name and number of the equipments on the original record.

6.2当记录表格出现某些“表格”确无数据记录时,可用“/”表示此格无数据。

When there appears no date in certain tables of the record table. It could use “/” to stand for no date. 6.3试验报告应由试验人员、审核人员签字。

The test report should be signed by the test personnel and auditing personnel.

6.4正式报告的试验人与审核人不得是同一人。

The test personnel and auditing personnel of the formal report should be different.

6.5为保证人身和设备安全,要求必须在试验设备周围设围栏并有专人监护,负责升压的人要随时注意周围的情况,一旦发现异常应立刻断开电源停止试验,查明原因并排除后方可继续试验。

In order to guarantee the personnel and equipment safety, it should set rail around the test equipment and assign a special person to guard it. The person who is in charge of increasing the pressure should be careful about the surrounding conditions all the times, switch off the power source to stop the test if finding something abnormal, find out the reason and remove it, then

continue the test.

钣金件检验作业指导书

钣金件检验作业指导书 文件编号 编制:刘桂强 审核: 批准: Xxxxxxxxxxxxxxx有限公司 发放范围:车间、生产部、技术部、档案室各一份

一、目的 规范钣金结构件的检验标准,以使各过程的产品质量得以控制,保证本公司的产品质量,从而使我公司的产品让顾客满意。。 二、适用范围 本标准适用于各种钣金结构件的检验,图纸和技术文件并同使用。当有冲突时,以技术规范和客户要求为准。 三、引用标准 本标准的尺寸未注单位皆为mm,未注公差按以下国标IT13级执行 GB/T1800.3-1998 极限与配合标准公差和基本偏差数值表 GB/T1800.4 -1998 极限与配合标准公差等级和孔、轴的极限偏差表 GB/1804-2000 一般公差未注公差的线性和角度尺寸的公差 未注形位公差按GB/T1184 –1996 形状和位置公差未注公差值执行。 四、原材料检验标准 1.金属材料 1.1钣材厚度及质量应符合国标,采用的钣材需出示性能测试报告及厂商明。 1.2材料外观:平整无锈迹,无开裂与变形。 1.3 尺寸:按图纸或技术要求执行,本司未有的按现行国标执行。 2.塑粉

2.1塑粉整批来料一致性良好,有出厂证明与检验报告,包含粉号、色号以及各项检验参数。 2.2试用后符合产品要求(包括颜色、光泽、流平性、附着力等)。3通用五金件、紧固件 3.1外观:表面无绣迹、无毛刺批锋,整批来料外观一致性良好。3.2尺寸:按图纸与国标要求,重要尺寸零缺陷。 3.3性能:试装配与使用性能符合产品要求。 五、工序质量检验标准 1.冲裁检验标准 1.1对有可能造成伤害的尖角、棱边、粗糙要做去除毛刺处理。 1.2图纸中未明确标明之尖角(除特别注明外)均为R1.5。 1.3冲压加工所产生的毛刺,对于门板、面板等外露可见面应无明显凸起、凹陷、粗糙不平、划伤、锈蚀等缺陷。 1.4毛刺:冲裁后毛刺高L≤5%t(t为板厚)。 1.5划伤、刀痕:以用手触摸不刮手为合格,应≤0.1。 1.6平面公差度要求见表一。 附表一、平面度公差要求 表面尺寸(mm) 变形尺寸(mm) 3以下±0.2以下 大于3小于30 ±0.3以下 大于30小于315 ±0.5以下

环路电阻测试仪作业指导书

环路电阻测试仪作业指导书 1.目的 规范MEHL-2A环路电阻测试仪的操作程序,保证正确使用仪器,保证检测工作的顺利进行和设备安全。 2.适用范围 MEHL-2A环路电阻测试仪是取代直流单、双臂电桥的高精度换代产品。仪器采用了先进的开关电源技术,由四位半LCD液晶显示测量结果,三位半LCD 液晶显示环境温度或测试电流值,克服了其它同类产品由LED显示值在阳光下不便读数的缺点,同时具备了自动消弧功能。本仪器具有测速快、精度高、显示直观、抗干扰能力强、体积小、耗电省、测试数据稳定可靠、不受人为因素影响等优点。是测量电力变压器等各种感性负载电阻及低压开关接触电阻、电线电缆或焊缝接口电阻的理想仪器,其测量速度比电桥快一百多倍。仪器内装可充电电池组(12V),交、直流两用,便于现场及野外测试。本表适用于电力、邮电、铁路、通信、矿山等部门测量各种装置的接地电阻以及测量低电阻的导体电阻值;本表还可测量土壤电阻率及地电压。 3.主要技术指标

4.操作规程 4.1. 电源的选择 本仪器为测试提供的电源的两种:AC220V/DC12V。在强电磁场干扰的情况下,建议最好使用直流电源测试,此状态下测试的数值稳定,抗工频干扰能力强。 4.1.1. 直流电源测试: 开启电源开关,LCD点亮,相应2kΩ档位指示灯亮,按下“启停”键,即可进行测试。测试完毕,关闭总电源开关,相应的指示灯熄灭,再转换测试夹,进行再次测试。(在按下“启停”键后测试时,将禁止换其他档位,需在停止测试后换其他挡位) 4.1.2. 交流电源测试: 接上交流AC220V电源,相应的指示灯亮,闭合总电源开关,相应的指示灯亮,按下“启停”键,即可进行测试。测试完毕,关闭总电源开关(AC220V),相应的指示灯灭,放电后,再转换测试夹,进行再次测试。 4.1.3. 充电: 接上交流AC220V电源,“充电“指示灯闪动,表示正在对机内的可充电池进行充电工作,电池充满后指示灯长亮。仪器在使用直流时也可根据“电量指示”了解电量的多少随时充电,仪器使用交流电源测试,同时也在对机内电池进行充电。(仪器设计了充电保护电路,不会有过充现象产生) 4.2. 测试线的联接方法: 将仪器的I+、V+、V-、I-端子与被试品按图1的方法联接好。这种联接法,可消除A、B、C、D处的接触电阻,以及联线电阻对测量的影响。测量的值即为B、C、之间的电阻Rx (注意:B、C之间不要反向)。 A

发电机安全操作规程完整

发电机安全操作规程 一、发电机启动前必须认真检查各部分接线是否正确,各连结部分是否牢靠,电刷是否正常、压力是否符合要求,接地线是否良好。 二、启动前将励磁变阻器的阻值放在最大位置上,断开输出开关,有离合器的发电机组应脱开离合器。先将柴油机空载启动,运转平稳后再启动发电机。 三、发电机开始运转后,应随时注意有无机械杂音,异常振动等情况。确认情况正常后,调整发电机至额定转速,电压调到额定值,然后合上输出开关,向外供电。负荷应逐步增大,力求三相平衡。 四、发电机并联运行必须满足频率相同,电压相同,相位相同,相序相同的条件才能进行。 五、准备并联运行的发电机必须都已进入正常稳定运转。 六、接到“准备并联”的信号后,以整部装置为准,调整转速,在同步瞬间合闸。 七、并联运行的发电机应合理调整负荷,均衡分配各发电机的有功功率及无功功率。有功功率通过油门来调节,无功功率通过励磁来调节。 八、运行中的发电机应密切注意发动机声音,观察各种仪表指示是否在正常范围之内。检查运转部分是否正常,发电机温升是否过高。并做好运行记录。

九、停机时,先减负荷,将励磁变阻器回复,使电压降到最小值,然后按顺序切断开关,最后停止运转。 十、移动式发电机,使用前必须将底架停放在平稳的基础上,运转时不准移动。 十一、发电机在运转时,即使未加励磁,亦应认为带有电压。禁止在旋转着的发电机引出线上工作及用手触及转子或进行清扫。运转中的发电机不得使用帆布等物遮盖。 十二、发电机经检修后必须仔细检查转子及定子槽间有无工具、材料及其它杂物,以免运转时损坏发电机。 十三、机房内一切电器设备必须可靠接地。 十四、机房内禁止堆放杂物和易燃、易爆物品,除值班人员外,未经许可禁止其它人员进入。 十五、房内应设有必要的消防器材,发生火灾事故时应立即停止送电,关闭发电机,并用二氧化碳或四氯化碳灭火器扑救。 配电室安全操作规程 1、电工必须具备必要的电工知识,熟悉安全操作规程,必须具有劳动局和安检办颁发的电工操作证及技术等记证熟悉供电系统和配电室各种设备的性能和操作方法,并具备在异常情况下采取措施的能力;必须熟悉车间的电气线路和电气设备的种类及性能,对电气设备性能未充分了解,禁止违规作业。 2、电工要有高度的工作责任心,严格执行值班巡视制度,

标志(丝印)、标签的耐磨试验作业指导书

丝印附着力试验作业指导书 文件编号:WD/JS-JY-01-22 版本:A版 编制/日期: 审核/日期: 批准/日期: 受控状态: 修订页

1. 适用范围 家用和类似用途的电器。 2. 参考标准 IEC/EN60335-1、的第7章 3. 试验的主要设备 4. 试验的说明 标志应清晰易读并持久。经过试验后,标志仍应清晰易读,标志牌应不易揭下并且不应卷边。 5. 试验前的准备 检查设备和仪器是否符合本项目试验要求; 接到样机后,准备样机资料和检测记录; 将样机状况、样机标识内容及有关技术参数填写在检测记录上。 6. 试验方法及判定 拇指测试 条件:实验样品5PCS以上 实验程序:取样品,用拇指放在印刷的图片上,以3+-0KGF的力来回檫试15次。 实验判定:制品印刷图案不可缺口/断线/油墨粘附不良等,否则为不合格。 75%酒精测试 条件: 1、实验样品5PCS以上 2、白棉纱布 3、75%的酒精 4、+-0KGF的制具 实验程序:将的制具的底部绑上白棉纱布,蘸上75%的确酒精,然后再用白棉纱布在印刷的图案上往返30个来回(约15SEC) 实验判定:制品印刷图案不可有脱落/缺口断线/油墨粘附不良等,可允许颜。 +-0KGF的制具,色淡,但印刷图案应清晰不模糊,否则为不合格。 95%酒精测试 条件:1、实验样品5PCS以上 2、白棉纱布 3、95%的酒精

4、+-0KGF的制具 实验程序:将的制具的底部绑上白棉纱布,蘸上95%的确酒精,然后再用白棉纱布在印刷的图案上往返30个来回(约15SEC) 实验判定:制品印刷图案不可有脱落/缺口断线/油墨粘附不良等,可允许颜。 +-0KGF的制具,色淡,但印刷图案应清晰不模糊,否则为不合格。 810胶带测试 条件:1、试验样品5PCS以上 2、810胶带 实验程序:将810胶带完全的黏贴在丝网印刷上,然后以45度角的方向迅速拉起胶带,连续测三次。 实验判定:制品印刷图案不可缺口/断线。 3M600胶带测试 条件:1、实验样品5PCS以上 2、2、250胶带 实验程序:将3M600胶带完全的黏贴在丝网印刷,以45度角的方向迅速拉起胶带。只需测试一次。 实验判定:制品印刷图案不可缺口/断线。 250胶带测试 条件:1、实验样品5PCS以上 2、250胶带 实验程序:将250胶带完全的黏贴在丝网印刷,以45度角的方向迅速拉起胶带,连续进行三次。 实验判定:制品印刷图案不可缺口/断线。 汽油擦拭测试 条件:1、实验样品5PCS以上 2、白棉纱布 3、汽油混合液(汽油:75%酒精=1:1) 4、+-0KGF的制具 实验程序:将的制具的底部绑上白棉纱布,蘸上汽油混合液,在印刷的图案上往返30个来回(约15 SE 实验判定:制品印刷图案不可有脱落/缺口/断线/油墨粘附不良等,可允许颜色偏淡,但印刷图案应清晰不模糊,否则为不合格。 正己烷擦试测试 条件:1、实验样品5PCS以上 2、白棉纱布 3、正己烷 4、+-0KGF的制具 实验程序:将的制具的底部绑上白棉纱布,蘸上正己烷溶液,在印刷的图案上往返30个来回(约15 SEC

发电机操作 作业指导书 - 制度大全

发电机操作作业指导书-制度大全 发电机操作作业指导书之相关制度和职责,物业管理有限公司作业指导书建筑研究中心发电机操作作业指导书1.目的确保发电机处于良好状态,保障后备电源。2.适用范围适用于XX总部物业服务处。3.方法和过程控制3.1开机前... 物业管理有限公司作业指导书 建筑研究中心发电机操作作业指导书 1.目的 确保发电机处于良好状态,保障后备电源。 2.适用范围 适用于XX总部物业服务处。 3.方法和过程控制 3.1开机前应检查以下内容:检查供油阀门应处于"全开"位,机油位、冷却液位应在规定高度。 3.2 手动起动 3.2.1将三位开关旋转到"手动起动"位置,"手动"按钮上方的LED灯亮,并且LED显示。 3.2.2然后按起动按钮,"起动"按钮上方的LED灯亮, LED显示,发动机起动。 3.2.3若第一次起动失败,应暂停10秒钟后,才能再起动第二次,通常设定为三次。 3.2.4若三次起动失败,面板上的"起动失败"灯亮。 3.2.5发动机起动后,当机组转速和电压达到额定值时,发动机运行灯亮。 3.2.6当发电机组频率和电压稳定在额定值后,才能闭合断路器,向负载供电。 3.2.7机组在运行中,应随时检查机组运行情况,如噪音、电压、油、水、电流、频率,当发生停机故障时,故障指示灯亮。 3.3手动停机 3.3.1断开断路器。 3.3.2发动机需在空载状态下,继续运行一段时间(通常5分钟)后再停机。 3.3.3将三位开关旋转到停机"OFF"位置。 3.4自动起动 3.4.1将三位开关旋转到"自动"位置。 3.4.2当机组接收到异地信号后,机组经一定时间延迟后(通常设定为5秒钟)自动起动。 3.4.3发动机第一次起动失败,暂停数秒后,再起动第二次,通常设定为三次。 3.4.4若第三次起动失败,在面板上"起动失败"灯亮。 3.4.5发动机起动后,当机组转速和电压达到额定值时,发电机运行灯亮。 3.4.6当机组频率和电压稳定在额定值后,才能闭合断路器,向负载供电。 3.4.7机组在运行中,应随时检查机组运行情况,如噪音、电压、油、水、电流、频率,当发生停机故障时,故障指示灯亮。 3.5自动停机 3.5.1当异地信号解除后,发动机将在空载状态下,继续运行一段时间(通常为5分钟)后自动停机。 4.质量记录表格 **WY7.5.1-S01-02-F1 《柴油发电机运行记录表》

接地电阻测试仪作业指导书

4105A接地电阻测试仪 作业指导书文件编号:___________________________ 版本::____________________________ 受控状态:___________________________ 编写人:_____________________________ 审检人:_____________________________ 批准人:_____________________________ 2014年03月28日批准2014年03月28日生效 深圳市正方检测有限公司发布 第02章目录 第1章封面、批准页 (1) 第2章目录 (2) 第3章修改页 (3) 第4章接地电阻检测 (4) 第03章文件修改页

第04章接地电阻检测 一、目的: 检测电气设备接地装置的接地电阻大小,判别接地电阻是否符合相应的规范。 二、相关参数和注意事项 2.1测量范围为0--1999 Q; 2.2测量对地电压0-199.9V范围内; 2.3注意事项:移动电话等高频率器请勿在仪器旁使用。 三、按钮和配件说明 1、电阻档位选择开关:20 Q /200 Q /2000 Q /EARTH VOLTAGE 2、量程选择开关:RANGE

3、电源开关:POWER 4、锁定读数按钮:HOLD 5、测试按钮: 圆形黄色按钮( PRESS TO TES)T 6、P/C:探测线插口; 7、E:接地端口 &红色/绿色探测线:接P/C插孔 9、绿色探测线:接E端口 10、接地金属棒2 根 四、检测仪器使用方法: 4.1? 天气及检测现场要求 检测接地电阻避免在雷雨天、潮湿、雨后和温度过低的环境下进行,宜在每年的 4 月份前或10 月后进行 4.2 现场接地装置的测量准备 ( 1)接地测试点的确定(变配电室或大楼接地测试点有相应的接地装置标识) ,接地装置上无带电设备, 接地装置上测试点应作预先除去接地装置上防腐层、锈蚀层、绝缘层,裸露出导体,接地装置测试仪上夹钳与其接触良好。 (2)检测时红色探测线插入P,黄色线插入C,绿色线插入E; 红钱和黄线的夹具端夹住金属棒,两线沿相反方向拉伸至最长,将金属棒打入地下,尽可能将接地棒插入潮湿泥土中,若不得不插入干燥泥土,石子地或沙地中时,请将辅助接地棒插入部分用水淋湿, 使泥土保持湿润。若在混凝土上进行测量时,请将辅助接地棒放平淋水或将湿毛巾等放在接地棒上。 ( 3)打开电源按钮,将绿色探测线夹住测试点,先将选择开关调节至接地电压(EARTH VOLTAGE当,若显示屏显示电压值则表示系统中有接地电压存在,如果此数值超过10V, 需将接地设备断电,使接地电压下降后再测量。 (4)先从2000Q档开始,按下测试键,如果数值过小,再依200Q、20Q的顺序切换量程直至读数合适为止。 五、相关文件:(无) 六、执行日期

2021发电机作业指导书

Safety is the goal, prevention is the means, and achieving or realizing the goal of safety is the basic connotation of safety prevention. (安全管理) 单位:___________________ 姓名:___________________ 日期:___________________ 2021发电机作业指导书

2021发电机作业指导书 导语:做好准备和保护,以应付攻击或者避免受害,从而使被保护对象处于没有危险、不受侵害、不出现事故的安全状态。显而易见,安全是目的,防范是手段,通过防范的手段达到或实现安全的目的,就是安全防范的基本内涵。 编制人员:编号: 序号 作业步骤名称 步骤详细说明 潜在危害 预防控制措施 备注 1 作业前安全教育 1、加强作业前的安全教育,杜绝违章操作,确保安全 2、作业现场安全巡检 1、作业前未进行安全教育违章操作,引起火灾爆炸,人员伤亡,经济损失 1、落实操作规程,加强监督检查,提高认识加强防范,杜绝违章,

确保安全 2、搞好作业现场的监护工作,防止发生事故 2 发电机组的检查 1、检查机组的紧固螺栓 2、检查机组的传动部分 3、检查仪器仪表的控制系统 4、检查燃油的数质量情况 5、检查机组的润滑系统 6、检查机组的冷却系统 7、检查启动充气瓶情况 8、检测发电机输出线路 1、螺栓松动、脱落,造成机体震动,增加机件磨损,发生事故 2、传动部分卡死,造成机组不能正常使用。 3、控制仪器仪表不准确,造成判断失误,设备损坏 4、燃油质量不合格,增加机件的磨损、降低内燃机工作寿命,经济损失;增加废气排放量,环境污染 5、机组的润滑系统不畅,发生抱轴烧瓦,设备损坏,经济损失 6、机组的冷却系统,不畅阻塞,机体产生的热量不能及时散发,功率降低,影响输出电值,耽误工作,经济损失

Removed_涂层附着力检测作业指导书

工艺文件 涂层附着力检测作业指导书WT00000000-54640 XX公司 2010-09-01

共 4 页第1页 工艺文件编号WT00000000-54640 XX公司 涂层附着力检测作业指导书代替WPT00-54020 1 适用范围 本作业指导书适用于钢铁表面涂层、不锈钢表面涂层和铝合金表面涂层附着力检测。 本作业指导书采用划格试验法,对漆膜附着力进行检测。可用于现场定性评判单层涂膜或多层涂膜与基底面附着力的大小;也可评定多涂层体系中各道涂层从其它底层涂层脱离的抗性。 本试验方法不适用于涂膜厚度大于250μm的涂层,也不适用于有纹理的涂层。 本试验可以在专门制作的试板上进行,也可以在待测产品的内表面进行。 2 引用标准 GB-T 4957-2003 非磁性基体金属上非导电覆盖层覆盖层厚度测量涡流法 GB-T 4956-2003 磁性基体上非磁性覆盖层覆盖层厚度测量磁性法 GB/T9286—1998 色漆和清漆漆膜的划格试验 GB/T 9271—2008 色漆和清漆标准试板 3 仪器材料 3.1 BYK划格试验器、 配备符合DIN/ISO标准、A-5126型划格试验器刀头(刀齿间距为2mm)和A-5128型划格试验器刀头(刀齿间距为3mm)。 3.2 清洁用刷子和钢直尺 3.3特氟龙粘胶带 宽25mm,粘着力(10±1)N/25mm。 3.4 目视放大镜 手持式、放大倍数为2倍或3倍。 4检测前准备 编制会签 校核标准化

共 4 页第2页 工艺文件编号WT00000000-54640 XX公司 涂层附着力检测作业指导书代替WPT00-54020 编制会签 校核标准化

接地电阻测试仪操作规程

接地电阻测试仪操作规程 1 范围 适用于LK2678型接地电阻测试仪的操作和保养. 2 职责 各相关使用部门负责仪器的保养,点检,使用,保管. 3 日常点检和运行检查 3.1 日常点检 3.1.1 检查频率:每天一次. 3.1.2 检查内容:打开仪器开关,观察各指示仪显示是否正常,运行是否有杂音. 3.2 运行检查 3.2.1 检查频率:每天一次. 3.2.2 检查内容:按操作规程操作,将仪器两极夹住600mΩ电阻两端,按下启动钮,仪器报警表明仪器正常,不报警则仪器不正常. 3.3 记录:将点检和检查结果记录在《设备点检表中》. 4 操作步骤 4.1 将一起配备的一付(两组)测量线,红线组粗测量线,接入测试仪红色电流接线柱,红线组细测量线,接入测试仪红色电阻接线柱;黑线组粗测量线,接入测试仪黑色电流接线柱,黑线组细测量线,接入测试仪黑色电阻接线柱. 4.2 接通电源,打开电源开关,显示屏点亮. 4.3 将两组测量线的夹子夹在一起互相短路,将电流调节旋钮逆时钟旋至零位. 4.4 按下预置按钮,量程开关档选择在600mΩ档,再按下启动按钮,将电流值调节为25A. 4.5 调节报警预置调节器,将报警预置调节值设定为500mΩ. 4.6 按下复位按钮,将电流调节旋钮旋到零位,按下测试按钮,拿开两测试线夹. 4.7 将测试线夹一端夹在测试灯具的接地线上,另一端夹在灯具上的可触及金属部分. 4.8 按下定时开关,将定时设定为60s,按下开路报警按钮. 4.9 打开启动按钮,调节电流旋钮,将电流调节到25A,这时接地电阻值显示屏显示的数字为该灯具的接地电阻值. 4.10 观测时间60s,读取最小的值为该灯具的接地电阻值,单位mΩ. 5 注意事项 5.1 操作人员必须经过培训方可使用本设备 5.2 在测试过程中,不能随意调节其他按钮. 5.3 测试电流大于5A才能报警. 5.4 为保证测试稳定,建议使用交流稳压电源. 5.5 测试完毕后,须处于“复位”状态,方可取下接线. 5.6 测试过程中,操作人员禁止接触被测物.

(完整版)检验作业指导书

检验作业指导书 1.进料检验 1.1 定义 进料检验又称来料检验,是制止不良物料进入生产环节的首要控制点。进料检验由IQC执行。 1.2 检测要项 IQC在对来货检验前,首先应清楚该批货物的品质检测要项,不明之处要向本部门主管问询,直到 清楚明了为止。在必要时,IQC验货员可从来货中随机抽取两件来货样,交IQC主管签发来货检验临时样品,并附相应的品质检测说明,不得在不明来货检验与验证项目、方法和品质允收标准的情况下进行验收。 1.3 检验项目与方法 1.3.1 外观检测 一般用目视、手感、限度样品进行验证。 1.3.2 尺寸检测 一般用卡尺、千分尺、塞规等量具验证。 1.3.3 结构检测 一般用拉力器、扭力器、压力器验证。 1.3.4 特性检测 如电气的、物理的、化学的、机械的特性一般采用检测仪器和特定方法来验证。 1.4 检验方式的选择 1.4.1 全检方式 适用于来货数量少、价值高、不允许有不合格品物料或公司指定进行全检的物料。 1.4.2 免检方式 适用于低值、辅助性材料或经认定的免检厂来料以及生产急用而特批免检的,对于后者IQC应跟进生产时的品质状况。 1.4.3 抽样检验方式 适用于平均数量较多、经常性使用的物料。 样本大小:批量的10%(不少于20件),允收数AC=0,拒收数RE=1。 1.5 检验结果的处理方式 1.5.1 允收 经IQC验证,不合格品数低于限定的不合格品个数时,则判为该批来货允收。IQC应在验收单上签名,盖检验合格印章,通知货仓收货。

若不合格品数大于限定的不良品个数,则判定该送检批为拒收。IQC应及时填制《IQC退货报告》,经相关部门会签后,交仓库、采购办理退货事宜。同时在该送检批货品外箱标签上盖“退货”字样,并挂“退货”标牌。 1.5.3 特采 特采,即进料经IQC检验,品质低于允许水准。IQC虽提出“退货”的要求,但由于生产的原因,而 做出的“特别采用”的要求。 若非迫不得已,公司应尽可能不启用“特采”。“特采”必须由总经理批准,可行时还必须征得客户的 书面许可。 1.5.3.1 偏差 送检批物料全部不良,但只影响工厂生产速度,不会造成产品最终品质不合格。在此情况下,经特批,予 以接收。此类货品由生产、质检单位按实际生产情况,估算出耗费工时数,对供应商做扣款处理。 1.5.3.2 全检 送检批不合格品数超过规定的允收水准,经特批后,进行全数检验。选出其中的不合格品,退回供 应商,合格品办理入库或投入生产。 1.5.3.3 重工 送检批几乎全部不合格,但经过加工处理后,货品即可接受。在此情况下,由公司抽调人力进行来 货再处理。IQC对加工后的货品进行重检,对合格品接受,对不合格品开出《IQC退货报告》交相关部门办理退货。此类货品由IQC统计加工工时,对供应商做扣款处理。 1.6 紧急放行控制 1.6.1 紧急放行内涵 a. 紧急放行的定义 紧急放行是指生产急需来不及验证就放行产品的做法,称为“紧急放行” b. 紧急放行条件 产品发现的不合格能在技术上给以纠正,并且在经济上不会发生较大损失,也不会影响相关、连接、相配 的零部件质量,可紧急放行。 1.6.2 紧急放行的具体操作步骤 1.6. 2.1 应设置适当的紧急放行的停止点,对于流转到停止点上的紧急放行产品,在接到证明该批产品合 格的检验报告后,才能将产品放行。 1.6. 2.2 若发现紧急放行的产品经检验不合格,要立即根据可追溯性标识及识别记录将不合格品追回。 2.过程检验: 过程检验(IPQC)指来料入仓后,至成品组装(或包装)完成之前所进行的质量检验活动。

发电机操作作业指导书-

北京站至北京西站 地下直径线工程ZJX-2标 发电机操作作业指导书 文件编号: 拟制:王亚丽 审核: 批准: 生效日期:2008年3月1日 中国中铁隧道集团有限公司北京铁路地下直径线一工区

一、编制目的 为规范发电机的安全作业,避免由于误操作或盲目作业造成机械事故或工程事故,保障设备的正常使用和操作人员的人身安全,降低施工成本,特指定本安全作业指导书。 二、一般规定 1、操作人员应体检合格,无妨碍作业的疾病和生理缺陷,并应经过专业培训、考核合格取得有关主管部门颁发的操作证或公安部门颁发的机动车驾驶执照后,方可持证上岗。学员应在专人指导下进行工作。 2、按章操作,严禁无证驾驶机、酒后开车。 3、严禁将机械交给其他无证人员操作。 4、操作人员必须严格遵守机械设备的有关保养规定,认真及时地做好各级保养。正确操作,合理使用,严禁违章作业。经常保持机械处于完好状态。 5、实行多班作业的机械,应严格执行交接班制度,认真填写交接班记录;接班的人员经检查确认无误后,方可进行工作。 6、设备应保持干净,防止驾驶员上下时滑倒。机身保持清洁美观。 三、安全操作 1、运行前的检查 1.1机组表面及周围是否有杂物阻碍; 1.2机房进、排风通道是否畅通;

1.3水箱冷却液面是否正常; 1.4空气滤清器是否指示正常; 1.5润滑油油位是否在正常范围内; 1.6燃油阀是否打开,燃油是否已正常地供给发动机; 1.7电瓶电缆是否已连接正确; 1.8发电负载设备是否准备好,当发电机直接带负载时,启动前,必须分断空气开关。 2、机组运行 2.1预热:启动前,人员可根据环境温度决定是否对机组进行预热操作,带预热按钮的控制屏可控制发动机启动加热器进行工作,以达到预热目的。 2.2上电:将控制屏钥匙开关从“OFF”打向“ON”位置,观察到面板上仪表背景灯亮,表示控制屏已上电,同时机组燃油处于打开状态,带电子调速控制器或电喷型机组的控制器也处于工作状态。 2.3启动 a.部分机组控制屏具有怠速/全速转换开关,可根据实际的需要,选择是否怠速启动或者全速一次性启动。通常怠速运行时间不宜超过5分钟;机组切勿长时间在怠速状态下运行。 b.按下启动按钮,持续时间最大不要超过30秒,发动机在启动马达的带动下开始启动,一旦启动成功,即可释放启动按钮,机组进入运行状态。 c.带自启动(或通讯)仪表的控制屏,机组预热、启动周期及

钢筋锈蚀性状检测作业指导书

钢筋锈蚀性状检测作业指导书文件编号: 版本号: 分发号: 编制: 批准: 生效日期:

钢筋锈蚀性状检测作业指导书 一、目的 为使测试人员在做钢筋锈蚀情况检测时有章可循,并使其操作合乎规范。 二、适用范围 适用以PS-6型钢筋锈蚀测定仪采用半电池电位法来定性评估混凝土结构及构件中钢筋的锈蚀性状,适用于带涂层的钢筋以及混凝土已饱水和接近饱水的构件检测。 三、检测依据 3.1《建筑结构检测技术标准》(GB/T 50344-2004); 3.2《混凝土结构工程施工质量验收规范》(GB 50204-2015); 3.3《混凝土中钢筋检测技术规程》(JGJ/T 152-2008); 四、主要仪器设备 4.1 PS-6型钢筋锈蚀测定仪 4.2 HC-GY61型一体式钢筋扫描仪 4.3 温度计 五、检测前的准备 5.1 PS-6型钢筋锈蚀测定仪和HC-GY61型一体式钢筋扫描仪应通过技术鉴定,并必须具有产品合格证。 5.2 PS-6型钢筋锈蚀测定仪由铜-硫酸铜半电池(以下简称半电池)、电压仪和导线构成。 5.2.1 铜-硫酸铜半电池 铜-硫酸铜半电池,它由一根不与铜或硫酸铜发生化学反应的刚性有机玻璃管、一只通过毛细作用保持湿润的多孔塞、一个浸泡在刚性管里饱和硫酸铜溶液中的紫铜棒构成,如下图5.2.1所示,饱和硫酸铜溶液应用分析纯硫酸铜试剂晶体溶解于蒸馏水中制备,溶液应清澈且饱和,应使刚性管的底部积有少量未溶解的硫酸铜结晶体,此时可以认为该溶液是饱和的。 铜-硫酸铜半电池在温度为25℃时,与氢电极参照的标准电极电势为0.337V,其温度数为0.9mV/℃。

图5.2.1 铜-硫酸铜半电池剖面图 5.2.2 电压仪 电压仪应具有采集、显示和存储数据的功能.满量程不宜小于1000mV,在满量程范围内的测试允许误差为士3%。 5.2.3 导线 用于连接电压仪与棍凝土中钢筋的导线宜为铜导线.其总长度不宜超过150m、戴面面积宜大于0.75mm2,在使用长度内因电阻干扰所产生的测试回路电压降不应大于0.1mV。 5.2.4 导电溶液 为使铜/硫酸铜电极与混凝土表面有较好的电接触,在水中加适量的家用液态洗涤剂(约2%),可提高与混凝土表面附着力,湿润效果更好。 5.3 半电池的电连接垫应预先浸湿,多空塞和混凝土构件表面应形成电通路。 5.4 硫酸铜溶液应根据使用时间给予更换,更换后宜采用甘汞电极进行校准。在室温(22±1)℃时,铜-硫酸铜电极与甘汞电极之间的电位差应为(68±10)mV。 5.5 HC-GY61型一体式钢筋扫描仪检测前应采用校准试件进行校准,当混凝土保护层厚度为10-50mm时.混凝土保护层厚度检测的允许误差为±1mm,钢筋间距检测的允许误差为±3mm。 六、测区的布置 在混凝土结构及构件上可布置若干测区,一般选择能代表不同环境条件和不同的锈蚀外观表征的结构及构件部位作为测区,每种条件的测区数量不宜少于3个,测区面积不宜大于5m ×5m,并按正确的位置编号。每个测区应采用矩阵式(行、列)布置测点,依据被测结构及构件的尺寸,宜用100mm×100mm-500mm×500mm划分网格,网格的节点为电位测点,测区中的测点数不宜少于20个。 在测区上一般布置200mm×200mm的测试网格,矩阵形成一般为7(行)×7、6×7、5×7

柴油发电机作业指导书

柴油发电机组作业指导书 1范围 本作业指导适用于丰润电厂柴油发电机组的检修、试验工作。 2 本作业指导书涉及的资料和图纸 柴油发电机组技术说明书 柴油发电机组使用说明书 柴油发电机组电气图纸 3 安全措施 严格执行《电业安全工作规程》。 4 备品备件清单 5 修前准备 5.3 工作准备 5.3.1工器具已准备完毕,材料、备品已落实。 5.3.2作业文件已组织学习,工作组成员熟悉本作业指导书内容。5.3.3工作票已履行开工手续。 5.3.4其他检修该设备需要做的其他准备。 6 检修工序 6.1 柜体内检查及清扫 6.1.1控制柜内应清洁无尘,接线应无机械损伤,端子压接应紧固。 6.1.2检查前应先断开直流电源,后断开交流电压。 6.2一般性外观检查 6.2.1 控制柜内外部清洁积尘。

6.2.2检查小开关及按钮、指示灯是否良好。 6.2.3检查各控制部件连线是否连接好。各插接线是否插接紧固。 6.2.4 控制柜内端子排螺丝是否拧紧,配线连接良好。 6.3 绝缘检查 用1000V兆欧表摇测,要求大于1MΩ 测试后,应将各回路对地放电。 6.3.1测交流电压回路对地绝缘 6.3.2测交流电流回路对地绝缘 6.3.3测控制电源回路对地绝缘 6.4 IG-CU控制器开入信号检查 检查前应先合上交流电压,后合上直流电源。 6.4.1 DCS启动信号BI1 6.4.2 DCS停机信号BI1 6.4.3 GCB开关合闸位置信号BI2 6.4.4 MCB开关合闸位置信号BI3 6.4.5远程紧急停机BI4 6.4.6远程故障复位BI5 6.4.7保安段故障不启动BI6 6.4.8远程手动BI7 6.4.9远程启动测试BI8 6.4.10远程带载测试BI9 6.5 IG-CU控制器开出测试 6.5.1启动控制信号BO1 驱动继电器K1 6.5.2燃油供油信号BO2 驱动继电器K2 6.5.3润滑油压力低BO3 驱动继电器K3 6.5.4机组超速BO4 驱动继电器K4 6.5.5三次启动失败BO5 驱动继电器K5 6.5.6冷却液高温BO6 驱动继电器K6 6.5.7发电电压异常BO7 驱动继电器K7 6.5.8故障跳闸BO8 驱动继电器K8 6.5.9润滑油压力低预警BO9 驱动继电器K9 6.6 IG-I/O M控制器开出测试 6.6.1冷却液高温预警BO1 驱动继电器K10 6.6.2非自动状态BO2 驱动继电器K11 6.6.3冷却液低液位BO3 驱动继电器K12 6.6.4发电合、分闸命令BO4 驱动继电器K13 6.6.5保安段合、分闸命令BO5 驱动继电器K14 6.6.6逆功故障BO6 驱动继电器K15 6.6.7机组运行正常BO7 驱动继电器K16 6.6.8机组公共警告BO8 驱动继电器K17 6.7IG-I/O M控制器开入信号检查 6.7.1应急!!(紧急停机)BI1 6.7.2保安段故障(闭合正常)BI4 6.7.3GCB开关按钮BI5

目视检验作业指导书

目视检验作业指导书 1 适用范围 本文件规定了道路运输液体危险货物罐式车辆金属常压罐体目视检验的方法及人员等技术管理要求。 2 编制依据 2.1 GB18564.1-2019 道路运输液体危险货物罐式车辆第1部分:金属常压罐体技术要求 2.2 NB/T4701 3.7-2012承压设备无损检测第7部分:目视检测 2.3 ISO6520.1-2007焊接和相关工艺金属材料中几何缺陷的分类第1部分熔焊 2.4GB150.4-2011压力容器第4部分:制造、检验和验收 3人员要求 3.1从事目视检验人员必须经过VT的培训,有半年以上工作经验方可独立上岗操作。 3.2检测人员必须熟悉和掌握相关标准要求(如:GB/T1856 4.1、GB150、GB25198、JB/T4734、JB/T47003.1等)。 3.3检测人员必须熟悉和掌握相应的焊接工艺。 3.4检测人员必须满足NB/T47013.7要求(如每12个月检查一次视力),且应当有足够的视力和颜色分辨力。 4 检测条件 4.1被检工件表面的光照度至少达到500Lx,对于必须仔细观察或发现异常情况并需要作出进一步观察和检测的区域则至少要达到1000Lx的照度。 4.2眼睛距离被检区域的距离应不超过600mm。

4.3眼睛与被检工件的夹角应大于30o。 4.4为达到最佳检测效果,照明条件应满足以下要求: ●使照明光线方向相对于观察点达到最佳效果; ●避免表面眩光; ●优化光源的色温度; ●使用与表面反射光相适应的照度级。 5环境要求 5.1作业场所应避免潮湿,场所应整洁宽敞。 5.2检验环境光照度应至少达到500Lx,对于必须仔细观察或发现异常情况并需要作出进一步观察和检测的区域则至少要达到1000Lx的照度。 6检测设备 6.1检测量具:钢直尺、游标卡尺、塞尺、焊接检验尺。 6.2放大镜的放大倍数为2~5倍,应尽量有刻度,放大镜的选用按GB/T20968执行。 6.3其他检测仪器:成型样板、镜子、照相机等。 7检测程序 检查范围应按GB18564.1及文件资料中的规定进行,检测前应将罐体及附件清理干净以符合检测要求。 7.1罐体及附件外观检测 按GB18564.1及文件资料中的规定进行检查罐体及附件,可以借助铜锤等辅助工具进行检查,当发现变形、开焊等重点部位,应在予以记录。7.2焊缝的外观检测 7.2.1焊缝的外观特征(形状和几何偏差)必须满足GB150.4的要求。焊缝表

发电机作业指导书

编号:AQ-JS-08654 ( 安全技术) 单位:_____________________ 审批:_____________________ 日期:_____________________ WORD文档/ A4打印/ 可编辑 发电机作业指导书 Generator operation instruction

发电机作业指导书 使用备注:技术安全主要是通过对技术和安全本质性的再认识以提高对技术和安全的理解,进而形成更加科 学的技术安全观,并在新技术安全观指引下改进安全技术和安全措施,最终达到提高安全性的目的。 编制人员:编号: 序号 作业步骤名称 步骤详细说明 潜在危害 预防控制措施 备注 1 作业前安全教育 1、加强作业前的安全教育,杜绝违章操作,确保安全 2、作业现场安全巡检 1、作业前未进行安全教育违章操作,引起火灾爆炸,人员伤亡,经济损失

1、落实操作规程,加强监督检查,提高认识加强防范,杜绝违章,确保安全 2、搞好作业现场的监护工作,防止发生事故 2 发电机组的检查 1、检查机组的紧固螺栓 2、检查机组的传动部分 3、检查仪器仪表的控制系统 4、检查燃油的数质量情况 5、检查机组的润滑系统 6、检查机组的冷却系统 7、检查启动充气瓶情况 8、检测发电机输出线路 1、螺栓松动、脱落,造成机体震动,增加机件磨损,发生事故 2、传动部分卡死,造成机组不能正常使用。 3、控制仪器仪表不准确,造成判断失误,设备损坏 4、燃油质量不合格,增加机件的磨损、降低内燃机工作寿命,经济损失;增加废气排放量,环境污染

5、机组的润滑系统不畅,发生抱轴烧瓦,设备损坏,经济损失 6、机组的冷却系统,不畅阻塞,机体产生的热量不能及时散发,功率降低,影响输出电值,耽误工作,经济损失 7、充气瓶体锈蚀、变形、未鉴定,气瓶发生爆炸,人员伤亡;瓶嘴阀门漏气,压力值不够,机组启动困难,影响供电 8、发电机输出线路存在问题,造成供电不畅,耽误生产,经济损失 1、做好机组的日常检查工作发现问题及时处理。 2、落实机组各部件三级保养制度,确保机组良好状态 3、做好机组的运行记录及维修保养记录 4、发电机输出线路定期检测,存在问题的线路,及时更换,保证安全供电 3 发电机组的起动、操作、使用 1、启动前先盘动机组的飞轮,使机组转动轴良好转动 2、搬动油泵手柄数次,增加机油压力(压力达不到规定值,缺

涂层附着力检测(划格法)实施细则

钢构作业指导书涂层附着力检测(划格法) 文件编号: 版本号: 编制: 批准: 生效日期:

涂层附着力检测(划格法)实施细则 1. 目的 为使测试人员在进行钢结构涂层附着力检测时有章可循,并使其操作合乎规范。 2. 适用范围 适用于建筑物及构筑物钢结构涂层附着力的检测。 3. 检测依据 GB50205-2001钢结构工程施工质量验收规范 TB/T1527-2011铁路钢桥保护涂装及涂料供货技术条件 GB/T10610-2009色漆和清漆漆膜的划格试验 4.检验器材 4.1切割刀具 单刃切割刀具适用于硬质或软质底材上的各种涂层; 多刃切割刀具不适用于涂层厚度(>120μm)或坚硬涂层,或施涂在软底材质上的涂层。 4.2导向和刀刃间隔装置 4.3软毛刷 4.4胶粘带:透明,宽25,粘着力(10±1)N/25mm。 4.5手把式放大镜:2倍或3倍。 5. 工作程序 5.1检测准备 5.1.1测试前可由项目负责人或有关人员前往现场踏勘,了解现场基本情况以及检测数量等。 5.1.2现场测量前防腐涂层应已涂装完毕且干透。 5.1.3测量前应确认构件的底材材质、涂层类型、涂层设计厚度等参数。

5.1.4检测人员应能熟练操作仪器。 5.2现场检测 5.2.1切割:切割数量为每个方向6条; 切割间距,每个方向切割间距应相等,其间距取决于涂层厚度和底材的类别 5.2.2刷扫:用软毛刷沿网格图形第一条对角线,轻轻地向后扫几次,再向前扫几次。 5.2.2粘贴胶粘带:匀速拉出胶带,去除最前面一段,剪下约75mm长,粘贴在网格上方,方向与一组切割线平行,用手指把网格上方的胶带压平,保证胶带与涂层紧密接触,且胶带长度至少超过网格20mm,如图1所示。 5.2.3撕离胶粘带:在贴上胶粘带5min以内,拿住胶带悬空的一端,并在尽可能接近60°的角度,在0.5~1.0s内平稳撕离胶粘带,如下图2所示。 图 1 图 2

TS16949来料检验作业指导书(中英文)

TS16949来料检验作业指导书Incoming_Inspection_Work_Instruction 文件更改历史记录 Amendment History

TS16949来料检验作业指导书 Incoming_Inspection_Work_Instruction 1.0Purpose目的 The objective of this procedure is to define a standard inspection method in performing inspection and testing of components or materials. 本程序目的在于定义对元件或材料进行检验/测试的标准操作方法。 Scope适用范围 This procedure is applicable to all components and materials that require the relevant inspection and testing, as specified in the individual Part or Material Specification. 本程序适用于所有按照元件和材料规格进行检验和测试的元件和材料。 2.0Sampling / Equipment Used 取样 / 使用设备 2.1Per sampling plan stated in the Incoming Inspection Procedure: AQL: MA=0.4、MI=1.0 按照来料检验程序所规定的抽样计划;AQL:MA=0.4、MI=1.0级别进行抽样. 2.2Inspection Aids检验工具 4.2.1 LCR Meter / LCR 测量仪 4.2.2 Fluke Multimeter / Fluke 万用表 4.2.3 Caliper / Plug Gauge / Pin Gauge / 游标卡尺/ 塞规/针规 4.2.4 Magnifier / Microscope / 放大镜 / 显微镜 3.0Reference Documents参考文件 3.1 Customer’s AVL / 客户接受的供应商清单 3.2 Manufacturer Part Specification / 供应商的元件规格

发电机操作作业指导书

编号:SM-ZD-70274 发电机操作作业指导书Through the process agreement to achieve a unified action policy for different people, so as to coordinate action, reduce blindness, and make the work orderly. 编制:____________________ 审核:____________________ 批准:____________________ 本文档下载后可任意修改

发电机操作作业指导书 简介:该制度资料适用于公司或组织通过程序化、标准化的流程约定,达成上下级或不同的人员之间形成统一的行动方针,从而协调行动,增强主动性,减少盲目性,使工作有条不紊地进行。文档可直接下载或修改,使用时请详细阅读内容。 1.目的 确保发电机处于良好状态,保障后备电源。 2.适用范围 适用于XX总部物业服务处。 3.方法和过程控制 3.1开机前应检查以下内容:检查供油阀门应处于"全开"位,机油位、冷却液位应在规定高度。 3.2 手动起动 3.2.1将三位开关旋转到"手动起动"位置,"手动"按钮上方的LED灯亮,并且LED显示。 3.2.2然后按起动按钮,"起动"按钮上方的LED灯亮,LED显示,发动机起动。 3.2.3若第一次起动失败,应暂停10秒钟后,才能再起动第二次,通常设定为三次。 3.2.4若三次起动失败,面板上的"起动失败"灯亮。

3.2.5发动机起动后,当机组转速和电压达到额定值时,发动机运行灯亮。 3.2.6当发电机组频率和电压稳定在额定值后,才能闭合断路器,向负载供电。 3.2.7机组在运行中,应随时检查机组运行情况,如噪音、电压、油、水、电流、频率,当发生停机故障时,故障指示灯亮。 3.3手动停机 3.3.1断开断路器。 3.3.2发动机需在空载状态下,继续运行一段时间(通常5分钟)后再停机。 3.3.3将三位开关旋转到停机"OFF"位置。 3.4自动起动 3.4.1将三位开关旋转到"自动"位置。 3.4.2当机组接收到异地信号后,机组经一定时间延迟后(通常设定为5秒钟)自动起动。 3.4.3发动机第一次起动失败,暂停数秒后,再起动第二次,通常设定为三次。