I.J. Information Technology and Computer Science, 2017, 12, 1-10

Published Online December 2017 in MECS (https://www.360docs.net/doc/6916933215.html,/)

DOI: 10.5815/ijitcs.2017.12.01

Use of Project Management Information System to Initiate the Quality Gate Process for ERP

Implementation

Atsushi Taniguchi

Graduate School of Information Science and Technology, Hokkaido University, Sapporo 060-0814, Japan

E-mail: atsushi.taniguchi.2006@https://www.360docs.net/doc/6916933215.html,

Masahiko Onosato

Graduate School of Information Science and Technology, Hokkaido University, Sapporo 060-0814, Japan

E-mail: onosato@ssi.ist.hokudai.ac.jp

Received: 23 August 2017; Accepted: 22 September 2017; Published: 08 December 2017

Abstract—Non-conformance to quality in a project often can lead to a major reason for project failure resulted in not meeting the triple constraints of project management, scope, time and cost. To prevent it from happening, a quality check against the standard for quality needs to be conducted at the critical stages of ERP implementation project. Proactive quality management by the quality gate process is embedded in the implementation methodology to help secure quality outcomes for the customers. However, getting the schedule of each quality gate timely fixed by the independent quality reviewer with the project manager of a newly started project can often be problematic without having a systematic approach implemented. Recent research has provided an application with the use of project management information systems (PMIS) for such implementations in improvement of quality management systems requirements [1].This article describes how PMIS was used to implement the project quality gate process for ERP implementation projects conducted by the solution provider for their customers in the various industries in Japan. PMIS was found to be effective in identifying, notifying and influencing the project managers to timely initiate the quality gate process based on the schedule fixed for each quality gate review.

Index Terms—Project Management Information Systems, PMIS, Project Quality Gates, Q-Gate, ERP, Independent Quality Reviewer, Solution Provider.

I.I NTRODUCTION

Project quality gates are described as part of the internal quality assurance activities in the quality management plan which is included in the project management plan as a subsidiary plan [2] for the ERP implementation projects conducted by the solution provider. However, there have been some projects which happened to end up with the schedule delays and cost overruns where the project quality gates did not get properly conducted at the right timing of the project phase. Therefore, the project outcome could not be clearly predicted to implement the corrective actions. This non-conformity could be very often identified when the procedure for initiation of the project quality gate process is not defined in the quality management plan to get the quality gate review schedule properly fixed. There is a quality gate reference process [3] defined in terms of how the quality gate review is conducted. However, the mandatory project quality gate review activities were flexibly left to be merely conducted and concluded by the resources assigned to and/or directly concerned with the projects, and thus non-conformance governance was virtually nonexistent. Recent research has provided an application with the use of PMIS, which is part of information systems (IS), for such implementations in improvement of quality management systems (QMS) requirements [1].Synergies between the PMIS (or IS) and the QMS according to ISO 9001 standard [4], [5], allows the association between these two systems, so that the PMIS can support and influence the processes related to the QMS, not only limited to the collection and documentation management [6]. On the one hand, the PMIS (or IS) represents a critical component of the backbone of organizations and on the other hand the quality management of products, services and business processes is a key issue for the success of most organizations when they operate in global contexts [7].

This article describes the case study on how PMIS was applied to implement the process of project quality gate reviews for the ERP implementation projects conducted by the solution provider for their customers in the various industries in Japan. PMIS was found to be effective in searching for the newly registered projects classified for the project quality gate requirements by the independent quality reviewer who does not belong to the organization unit responsible for the project delivery. It was effective in identifying the project managers in charge of the

classified projects to conduct the previews of the project quality gate reviews and setting the soft-booked dates for the project quality gate reviews prior to the previews. It was also effective in notifying and influencing the project managers to timely initiate the quality gate process based on the schedule fixed for each project quality gate review. This article is structured as follows: Section II is related to the literature review of quality gates and its adoption. Section III is related to the literature review of PMIS and its current configuration implemented. Use of PMIS to initiate the process of project quality gate reviews for the solution provider led ERP implementation projects by the independent quality reviewer is presented in Section IV. Finally, Section V is composed by the conclusion.

II.R ELATED W ORKS

The concept of quality gates is based on the stage-gate system initially presented in 1986 and later refined by other researchers (e.g., [8]), [9]. It consists on breaking down a project (or process) into several distinct phases. Then, quality checkpoints (or gates) are placed between phases to check the degree of fulfillment of a project or the quality of ―in-progress‖ artifact that is being manufactured (product) [10]. In general, a quality gate marks the formal end to a particular process within a project, a ―gate‖ through which the project proceeds from one phase to another [9].

Project quality gates described in this article are the quality management gates [11], [12] where targets, timeframes and deadlines are fixed for the project at the management level. A quality management gate is positioned at each major deadline or target. Specific products or results are generated within each defined timeframe. Requirements are defined for these specified outputs but not defined for the specific products as in the case of quality control gates. Quality management gates are established for the decision-making process which will predict and control the outcome of the project with the desired quality [12]. Project quality gates are used for the strategy [3] as a quality guideline where the same set of quality gates (and criteria) is applied to all projects resulting in a comparable and at least an equal minimum quality level in all these projects. Although requirements for additional outputs specific to each project can be includ ed to meet the project’s needs in the criteria, project quality gates are not used as a flexible quality strategy where a suitable quality gate process is applied to each project to exactly meet the project’s needs.

Generally, a quality gate is a checkpoint consisting of a set of predefined quality criteria that a project must meet to proceed from stage of its lifecycle to the next [13]. The ERP implementation methodology used by the solution provider has a total of 4 project quality gates embedded based on the traditional waterfall model [3] to assure project quality by formally conducting a quality check against the quality gate checklist [14], [9] before the end of each phase [15] throughout the project life cycle. Furthermore, there is also the mandatory preview of the project quality gate review positioned at an early stage of Phase 1 of the project as shown in Fig. 1.

Fig.1. Project Quality Gate Reviews in a Project Lifecycle

The major objectives of the project quality gate reviews are:

?To assure that all key deliverables and actions of the gate have been completed in compliance with

recommended practices and to the customer’s

satisfactions

?To reduce the risks of the project by making sure that standard methods and tools are used to the

best effect

?To enable the project manager to continuously communicate the process and build quality directly

into the project [14]

Table 1 shows the description of the generic project quality gate checklist, which covers the checklist items (use cases and elements) for all phases of the project. The checklist consists of three major methodologies, internal governance, project management knowledge areas [2] and ERP (i.e. processes, products and services [5]) implementation methodology since ERP implementation faces many difficulties that cause its failure [26], [27]. III.L ITERATURE R EVIEW OF PMIS AND ITS P RODUCTION

C ONFIGURATION

PMIS, which is part of enterprise environmental factors, provides access to automated tools, such as scheduling, cost, and resourcing tools, performance indicators, databases, project records, and financials used during the Monitor and Control Project Work process. Automated gathering and reporting on key performance indicators (KPI) can be part of this system [2]. PMIS provides a wide range of functions directly supporting a complex of process involving various project related activities: planning, monitoring, control and others [16]. In the information technology (IT) industry, Gartner Research estimates that 75% of large IT projects managed with the support of a PMIS will succeed, while 75% of projects without such support will fail [17]. Using PMIS to manage projects, while not sufficient to insure project success, has thus become a necessity [18]. The most appropriate PMIS configuration defined depends on project situation [19]. Project situation requirements for PMIS have been identified accordingly to project classification [20] based on the project type, product, size, organization, management, planning approaches and related guidance, as well as project environments and specific requirements, enterprise environment factors and organizational process assets [2]. Definition of the PMIS

configuration requirements must include the following information [19] such as data entities or work items used in project, attributes or data fields of each data entity and processes or workflows related to the data.

The configuration use case elements supported by the PMIS implemented for the use by the solution provider are shown in Table 2. It aims to provide the KPIs, risk registers and reports such as project financials in terms of the earned value management (EVM) [2].

Table 1. Generic Project Quality Gate Checklist

Table 2. PMIS Production Configuration Use Case Elements

It covers four types of delivery services provided by

the solution provider based on the two contract types, time and material contracts (T&M) and firm fixed price contracts (FFP) [2], related to the ERP implementation projects and operations support for their customer in four major industry sectors in Japan. It also captures 100% of the contracts closed for the four delivery services so that the performance of each project can be closely monitored for early detection of issues and risks and the project outcomes can be controlled in an early stage based on the appropriate corrective actions [2], [5] to be implemented ahead of time.

IV. U SE OF PMIS TO INITIATE Q UALITY G ATE P ROCESS Project Q-Gate Review process consists of the two major processes. One is Project Q-Gate Preview process that is conducted at the beginning of each project. The other is an iterative process of Project Q-Gate Review that is conducted at each phase in the project lifecycle. PMIS applied to trigger the initiation of the project quality gate preview as well as the succeeding iterative project quality gate reviews systematically throughout the project phases is discussed in detail below.

Fig.2. Provide Project Q-Gate Reviews in a Project Lifecycle

A. Provide Project Quality Gate (Q-Gate) Reviews in a Project Lifecycle

Systematic overview of the project quality gate review process that is triggered by the appropriate project initiation information from PMIS can be expressed in IDEF0 (Integration DEFinition level 0) [21], [22] as shown in Fig. 2. This is the top-level context diagram A-0. It is decomposed to the next level diagram with a systematic framework that consists of two nodes, A1 and A2 as shown in Fig. 3. Node A1 is project quality gate preview process that is triggered by the relevant project

initiation information from PMIS to be conducted at the beginning of each project. It is specifically positioned to influence the phase and project results positive, as well as coach and advise project manager on upcoming project phase with the methodology, tools, project documents, quality and standards, deliverables, customer duties and so on. Node A2 is an iterative process of project quality gate review to be conducted at each phase in the project lifecycle. It is positioned to check that necessary standards and project approach have been established along with response plans for the identified risks.

Fig.3. Conduct Project Q-Gate Preview and Project Q-Gate Reviews

Fig.4. Conduct Project Q-Gate Preview and Get Agreement on Project Q-Gate Review Schedule

B. Conduct Project Q-Gate Preview and Get Agreement on Project Q-Gate Review Schedule

The decomposition of node A1 to 5 activities is shown

in Fig. 4. This process for conducting Quality Gate 1 Preview by the internal quality reviewer plays the most important role to properly kick off the project quality gate review process that is to be carried out at each phase in

the project management lifecycle.

Below are the major activities required to plan and conduct Quality Gate 1 Preview.

? Node A11; Classify Project requiring Q-Gates in

PMIS: The independent quality reviewer is to check (during the 1st two weeks of the month) if there is any newly started project in PMIS relevant for triggering the initiation of the project quality gate process based on the following criteria that the Solution Provider is:

o To provide project manager and project team o To be responsible for providing particular results based on contractual agreements

o To provide advisory services that are mainly relevant to meet customers ’ project goals

o To provide project work with the budget of the contract that is greater than the threshold value

? Node A12; Request Q-Gate 1 Preview Meeting:

Once a relevant project is found:

o The independent quality reviewer is to send an email to the project manager responsible for the execution of the project, which is also copied to the delivery manager in charge of the portfolio category, based on the explanation for the need

of getting Q-Gate 1 Preview conducted before a proposed due date for completion stated on the email.

o The independent quality reviewer is also to have the generic project quality gate checklist template and the internal KPI document template attached to the email.

o The project manager is to send back an hour meeting request with a date proposed for having Q-Gate 1 Preview conducted.

o The independent quality reviewer is to respond to the meeting invite to have the preview date finally fixed.

? Node A13; Maintain Q-Gate Schedule in Control

List: Once the scope document attached to the contract of the classified project is made available, the independent quality reviewer is to maintain the soft-booked dates of the project quality gates for the project in the Q-Gate Control List in PMIS prior to conducting Q-Gate 1 Preview based on the process that is expressed in UML (Unified Modelling Language) class diagram [23], [24], [25] shown in Fig. 5. Table 3 shows a snapshot of Q-Gate Control List maintained in PMIS prior to conducting the Project Q-Gate 1 Preview based on the soft-booked quality gate schedule.

Fig.5. Maintain Q-Gate Schedule in Q-Gate Control List

Table 3. Q-Gate Control List Maintained prior to Conducting Project Q-Gate 1 Preview

Industry Sector Name

Project Name Q-Gate Name

Q-Gate Severity Status (Q-Gate)Compliance StaReview Date

Forecast Finish date Late Gates

Consumer / Trading Project K Quality Gate 1In Progress 2017/4/32017/4/3Consumer / Trading Project K Quality Gate 2In Progress 2017/11/272017/11/27Consumer / Trading Project K Quality Gate 3In Progress 2018/11/262018/11/26Consumer / Trading Project K Quality Gate 4In Progress 2019/11/252019/11/25

?

Node A14; Agree on Q-Gate Schedule and Deliverables: In Quality Gate 1 Preview, there are two major tasks to be conducted as follows:

o Agree on Quality Gate Schedule: Scheduling of the date for each project quality gate to be

conducted needs to be fixed based on the proposed soft-booked dates maintained in PMIS. The tool used to capture the dates fixed for the project quality gates is the internal KPI document shown in Table 4 that is a mandatory item in the generic project Q-Gate 1 checklist.

Table 4. Get Internal KPI Document Filled Out and Signed Off

It is developed to contain the objectives for the project manager that are aligned with company business objectives and customer project goals. KPIs listed are to be agreed upon by the project manager responsible for execution of the project and the delivery manager in charge of the portfolio category where the project relevant for

project quality gates belongs to.

o Agree on Deliverables: Walk-through of the project quality gate checklist is to be conducted. All key deliverables listed in the project quality gate checklist for each phase are to be looked at and agreed with the project manager, to build quality into the project to comply with recommended practices.

Node A15; Update Q-Gate Schedule in Control

List if Needed: If there were some adjustments in the soft-booked dates for quality gate reviews required as the results of the meeting with the project manager, update them if needed in the Q-Gate Control List in PMIS. C. Conduct Project Q-Gate Review in Iterative Process The decomposition of node A2 to 6 activities is shown in Fig. 6. Once the dates fixed for the planned project quality gates are maintained in the Q-Gate Control List in PMIS, the iterative process for conducting a quality check at each phase is to be started accordingly to the schedule.

Fig.6. Conduct Project Q-Gate Review in Iterative Process

Table 5. Q-Gate Control List with Project Q-Gate Reviews Due Next Month

Industry Sector Name

Project Name Q-Gate Name

Q-Gate Severity Status (Q-Gate)Compliance StaReview Date

Forecast Finish date Late Gates

Consumer / Trading Project K Quality Gate 1In Progress 2017/4/32017/4/3High Tech Project T Quality Gate 3In Progress 2017/4/32017/4/3High Tech

Project M Quality Gate 4In Progress 2017/4/102017/4/10Consumer / Trading Project J Quality Gate 3In Progress 2017/4/142017/4/14

Below are the steps of major activities required for conducting Quality Gate Review.

?Node A21; Identify Q-Gate Review due in Control List: By leveraging the Q-Gate Control List that is

maintained in PMIS, the independent quality

reviewer is to check in PMIS the projects having

respective project quality gate reviews due in the

coming month on the 25th of every month. Table 5

shows a sample output of all the project quality

gates due in April 2017.

?Node A22; Request Relevant Q-Gate Review Meeting:For each project with relevant project

quality gate review due in the coming month, the

independent quality reviewer is:

o To send an email to the project manager responsible for the execution of the project,

which is also copied to the delivery manager in

charge of the portfolio category, for preparation

of getting the relevant quality gate review

conducted on the planned date captured in the

internal KPI document.

o To request the project manager to submit all the key deliverables mandatory in the generic quality

gate checklist at least one week in advance of the

date of the quality gate review.

o To request the project manager to respond by sending back an hour meeting request on the date

fixed for having the quality gate review

conducted.

?Node A23; Execute Relevant Q-Gate Review: The following major activities are conducted:

o The project manager is to send all key deliverables available for review by mail to the

independent quality reviewer at the earliest

timing possible prior to the relevant quality gate review meeting.

o The independent quality reviewer is to review the deliverables submitted by the project manager prior to the meeting for the quality gate review.

o At the meeting for the relevant quality gate review, the project manager is to facilitate the review by presenting the overall project status with the major issues logged and response plans for the risks identified, and briefing the contents of key deliverables mandatory in the relevant quality gate checklist.

o The independent quality reviewer is to determine the overall status as the results of the Q-Gate Review based on the following criteria:

?Accepted: Indicates that there were no non-conformances identified and thus the project

quality gate is passed.

?Conditionally Accepted: Indicates that action items need to be completed or certain

deliverables need to be fixed for

improvement, as well as the corrective

actions need to be implemented [4], [5] to get

―Accepted‖. No direct risk for project success

is given.

?Not Accepted: Indicates that the project quality gate is not passed as there are serious

action items. Direct risk for project success is

given.

o Once the review is over, the independent quality reviewer is to update the Q-Gate Control List in PMIS. Table 6 shows a snapshot of Q-Gate Control List updated in PMIS as the results of the Project Q-Gate 1 Review.

Table 6. Q-Gate Control List Updated as the Results of Project Q-Gate 1 Review

Industry Sector Name Project Name Q-Gate Name Q-Gate Severity Status (Q-Gate)Compliance StaReview Date Forecast Finish date Late Gates Consumer / Trading Project K Quality Gate 1Accepted2017/4/32017/4/3 Consumer / Trading Project K Quality Gate 2In Progress2017/11/272017/11/27 Consumer / Trading Project K Quality Gate 3In Progress2018/11/262018/11/26 Consumer / Trading Project K Quality Gate 4In Progress2019/11/252019/11/25

?Node A24; Determine Action Items, Sign-off Review:The independent quality reviewer is to communicate by email to the project manager and the delivery manager:

o The evaluation on each deliverable against the project quality gate checklist items and provide

the management summary as the overall status of

the project quality gate review

o The corrective actions with a deadline if it requires the re-evaluation

o The reminder of the next project quality gate review date unless it is the final project quality

gate planned for the project ?Node A26; Archive Results in PMIS:The independent quality reviewer is to upload to PMIS the review results based on the management summary input in the header of the relevant project quality gate checklist along with the actual deliverables reviewed

?Node A25; Monitor Action Items: If there are any corrective actions outstanding from the project quality gate review:

o The independent quality reviewer is to send an email to request them with a deadline set for the

re-evaluation of the project quality gate review. o The project manager is to send back the updated

deliverables due by the deadline.

o The independent quality reviewer is to provide the results of re-evaluation by email to the

project manager and the delivery manager, along

with the reminder of the next quality gate review

date unless it is the final quality gate.

?Node A26; Archive Results in PMIS:The independent quality reviewer is:

o To upload to PMIS the updated relevant project quality gate checklist as the results of re-

evaluation of the deliverables or the corrective

actions implemented

o To update the Q-Gate Control List if needed.

V.C ONCLUSION

As described in Section 4, use of PMIS was found to be effective in:

?Searching for the newly registered projects relevant for the project quality gate requirements

by the independent quality reviewer who does not

belong to the organization unit responsible for the

project delivery.

?Identifying the project managers in charge of the classified projects to conduct the previews of the

project quality gate reviews and setting the soft-

booked dates for the project quality gate reviews

prior to the previews.

?Notifying and influencing the project managers to timely initiate the iterative process of quality gate

review based on the schedule fixed for each

project quality gate review.

PMIS that captures 100% of the closed contracts used for reporting the monthly project financials can surely influence the project managers on their KPIs for project success.

R EFERENCES

[1]S. Berzisa, ―Application of Project Management

Information Systems in Efficiency Improvement of Quality Management System,‖ in Proceedings of the 10th

International Scientific and Practical Conference on Environment. Technology. Resources, (2015), Volume III, 17-21. DOI: https://www.360docs.net/doc/6916933215.html,/10.17770/etr2015vol3.173 [2]Project Management Institute, A Guide to the Project

Management Body of Knowledge (PMBOK? Guide)-Fifth Edition. PMI, 2013.

[3]T. Flohr, Z. Huzar, R. Koci, J. Zendulka, B. Meyer, B.

Walter (Eds.), ―Assessing the Quality of Quality Gate Reference Processes,‖ in Proceedings of the Third IFIP TC 2 Central and East European conference on Software engineering techniques (CEE-SET 2008). Springer-Verlag, Berlin, Heidelberg, 207-217, 2008.

[4]ISO,ISO 9001:2008 –Quality management systems –

Requirements. Forth edition, 2008-11-15.

[5]ISO,ISO 9001:2015 –Quality management systems –

Requirements. Fifth edition, 2015-09-15. [6]S. G. G. Ferreira, J. A. Carvalho, P. Sampaio,

―Articulation between Information Systems and Quality Management Systems –Literature Review,‖ Conference on Industrial Engineering and Operations Management (ICIEOM). Guimaraes, Portugal, July 9-11, 2012.

[7]S. Figueiredo, P. R. Cunha, ―Joint Design of the

Information System and Quality Management System in an Organization: Theory and Illustration with a Field Case,‖ Proceedings of ISO ne World Conference, 2008. [8] C. Hammers, R. Schmitt, ―Governing the Process Chain

of Product Development with an Enhanced Quality Gate Approach,‖ CIRP Journal of Manufacturing Science and Technology, 1 (2009) 206-211.

[9]V. Ambartsoumian, J. Dhaliwal, E. Lee, T. Meservy, C.

Zhang, ―Implementing Quality Gates throughout the Enterprise IT Production Process,‖ Journal of Information Technology Management Volume XXII, November 1, 2011.

[10]J. P. Dourado, R. Silva, A. Silva, ―Development of New

Products usi ng APQP and Quality Gates,‖ International Journal of Engineering and Industrial Management, N. 5 (2013), 79-91.

[11]Prosys, Introducing the PROsys Quality Gate

Methodology – A Requirements-based Technique for Managing Quality, PROsys, 1998. Retrieved May 18, 2017, from http://www.prosys-

https://www.360docs.net/doc/6916933215.html,/Web_Files/qgintro1.pdf

[12]S. Koul, J. J. Alexander, ―Enhancing Project Management

– A Quality Gate Usage,‖ Proceedings of 2013 International Conference on Technology Innovation and Industrial Management,May 29-31, 2013, Phuket, Thailand.

[13]R. Schneider, ―Quality Gates: A New Device for

Evaluation in Cross-Lingual Information Retrieval,‖ in Proceedings of the LREC-2004 Workshop of Transparency and Integration in Cross-Lingual Information Retrieval, Lissabon, Portugal, May 30, 2004.

[14]J. Charvat, How to use quality gates to guide IT projects,

TechRepublic, January 31, 2003. Retrieved May 22, 2017, from https://www.360docs.net/doc/6916933215.html,/article/how-to-use-

quality-gates-to-guide-it-projects/

[15]H. R. Kerzner, Ph.D., Project Management - Best

Practices: Achieving Global Excellence, Third Edition, John Wiley & Sons, Inc., 207-211, 2014.

[16]S. Berzisa, ―The Baseline Configuration of Project

Management Information System,‖ Scientific Journal of Riga Technical University, Computer Science, vol. 5, no.

40, 59-65, 2009.

[17]M. Light, B. Rosser, S. Hayward, Realizing the benefits of

projects and portfolio management, Gartner, Research ID: G0*******, January 4, 2005, 1-31.

[18]L. Raymond, F. Bergeron, ―Project Management

Information Systems: An Empirical Study of Their Impact on Project Managers and Project Success,‖ International Journal of Project Management, 26 (2008), 213-220. [19]S. Berzisa, ―Application of Knowledge and Best Practices

in Configuration of Project Management Information Systems,‖ Ph.D. Thesis, Riga Technical University, Latvia, 2012.

[20]S. Berzisa, ―Project Man agement Knowledge Retrieval:

Project Classification,‖ in Environment. Technology.

Resources: Proceedings of 8th International Scientific and Practical Conference, June 20-22, 2011. Volume II, vol. I, 33-39.

[21] B. El-Sharef, K. S. El-Kilany, ―Process Modeling and

Analysis of a Quality Management System for Higher Education,‖ in Proceedings of the World Congress on

Engineering 2011, Vol I, WCE 2011, July 6-8, 2011, London, U. K.

[22]

L. Tsironis, A. Gent sos, V. Moustakis, ―Empowerment the IDEF0 Modeling Language,‖ International Journal of Business and Management, Vol. 3, No. 5, May 2008, 109-118.

[23] R. Singh, V. Arora, ―Literature Analysis on Model based Slicing,‖ International Journal of Computer Applications (0975-8887), Volume 70- No. 16, May 2013, 45-51.

[24]

B. Mathur, M. Kaushik, ―Empirical Analysis of Metrics Using UML Class Diagram,‖ International Journal of Advanced Computer Science and Applications (IJACSA), Vol. 7, No. 5, 2016, 32-37.

[25]

V. Vyas, R. G. Vi shwakarma, C. K. Jha, ―Modeling Aspects with AODML: Extended UML Approach for AOD‖, I.J. Engineering and Manufacturing (IJEM), 2017, 2, 11-22. DOI: 10.5815/ijem.2017.02.02

[26]

M. R. J. Qureshi, A. M. Abudulkhalaq, ―Increasing ERP Implementation Success Ratio by Focusing on Data Quality & User Participation‖, Inte rnational Journal of Information Engineering and Electronic Business (IJIEEB), 2015, 3, 20-25. DOI: 10.5815/ijieeb.2015.03.03 [27]

A. M. Qazi, S. Shahzadi, M. Humayun, ―A Comparative Study of Software Inspection Techniques for Quality Perspective‖, International Journal of Modern Education and Computer Science (IJMECS), 2016, 10, 9-16. DOI: 10.5815/ijmecs.2016.10.02

Authors ’ Profiles

Atsushi Taniguchi is a certified PMP and holds Master of Science degree in information and computer science from Georgia Institute of Technology, Atlanta, USA.

He has over 25 years of extensive experience in designing, developing and managing software development and implementation projects including ERP

implementation projects for 15 years. He is currently pursuing Ph.D. degree in information science at the Graduate School of Information Science and Technology, Hokkaido University, Sapporo, Japan.

Mr. Taniguchi is a member of PMI, PMI Japan Chapter, the Society of Project Management, and Information Processing Society of Japan.

Masahiko Onosato received his Ph.D. in engineering from the University of Tokyo, Japan in 1993.

He is Professor in the Graduate School of Information Science and Technology at Hokkaido University, Sapporo, Japan. His main research fields are virtual manufacturing systems, computer-aided systems, and disaster

information systems.

Prof. Onosato is a member of IEEE, ACM, JSME, JSPE, and SICE.

How to cite this paper: Atsushi Taniguchi, Masahiko Onosato, "Use of Project Management Information System to Initiate the

Quality Gate Process for ERP Implementation", International Journal of Information Technology and Computer Science(IJITCS), Vol.9, No.12, pp.1-10, 2017. DOI: 10.5815/ijitcs.2017.12.01

工程建设项目综合管理信息系统设计方案

工程建设项目综合管理信息 系统设计方案 概述 1.1项目背景 工程项目建设历来是一项复杂的课题,做为政府主导投资的大型工程,项目普遍具有投资大、建设周期长、参建单位多、地域分散,交通不便、并且受地域与气候因素影响较大等显著特征。这些项目特征及其包含的复杂业务流程、繁琐的工程数据给政府主管部门、项目业主、监理和承包商等项目参与方之间的信息传递、管理行为的落实和及时正确的决策指令的发布造成客观制约。随着我国对国家大型工程的精细化管理的要求,对工程建设的参与方的管理水平提出了更高的要求,做为建设项目的政府主管部门、业主或承包商来说如何有效的管理项目让工程效益最大化已经是摆在管理人员面前的一个重要问题。 1.2工程项目管理的基本原理 根据PMI项目管理知识体系(PMBOK)的规划,项目管理可划分成围管理、时间管理、成本管理、质量管理、采购管理、人员管理、沟通管理、风险管理、综合管理等九个领域;项目管理工作可归纳为5大过程组(启动、规划、执行、监控和收尾)及44个管理子过程,成功的项目管理就是科学的将这些管理过程和管理领域交互、重叠地应用于项目全生命周期。 从普遍意义上我们可以将以上管理容概括为四流、四控制、两管理、一协调;四流指资金流、信息流、物资流、资料流;四控制指成本控制、进度控制、质量控制、围控制;两管理指合同管理、信息管理;一协调指项目管理组织协调。 工程项目管理是在工程项目建设过程中,按照工程项目自身的运行规律和管理程序,对项目建设进行全过程、全方位的计划、组织、指挥、控制与协调,在有限的资源条件下,按照预期的预算目标、工期目标和质量目标,高效率地实现项目的预期目标,最大程度实现项目的实际效益。它涉及以下几个特征: 1)项目管理是项目建设过程和项目管理过程相结合的产物,具体组织的 项目管理要结合其所从事项目的过程特点及组织管理结构来进行; 2)从项目的角度看项目管理和从组织的高度看项目管理的结果是不同 的。从项目的角度看是如何管理好项目。从组织的角度看是如何管理 好一批项目,即是应该如何建立一个项目管理体系;

ERP项目管理实施经验总结1.0

ERP项目管理实施经验总结1.0 ERP项目管理实施经验总结1.0 ERP项目管理实施经验总结 1、 售前:加强与销售和售前人员的沟通了解客户情况、需求情况,如果有售前需求分析文档一定要仔细分析,以便提前了解规避风险;借鉴售前方案进行实施,减少调研时间和实施成本投入。 2、 启动:重视项目启动会的沟通,启动会建议沟通内容与注意事项:用友实施方法及实施过程的沟通;项目组成员的确定及角色划分; 项目组成员各自职责的明确(参照方法论中文档;)明确项目目标与范围;项目实施主计划的确定(综合所有关键用户的意见); 明确“关键用户培训”、“方案讲解与测试”两个阶段的重要性,进而 要求客户提前准备所需环境、设备及项目组成员工作时间的安排;明确并宣读项目考核内容(项目考核制度提前制定);明确实施人天投入与阶段性确认的必要性;明确项目阶段例会制度;明确项目验收标准的; 启动会后留出十分钟左右做答疑; 3、4、5、 安装与备份:产品安装、系统备份等操作尽量指导IT部门人员操作。项目组人员确定:了解客户情况后再确定项目组成员。 主计划编制:编制实施主计划一定要与双方沟通、确认,让对方提前对计划有所准备。

6、 知识转移:充分利用对方项目组成员、关键用户,调动项目组成员、关键用户的积极性和主观能动性,积极沟通,充分完成知识转移的过程。 7、 方案编写:按照业务流程而非产品模块的形式来编写方案,实施方案中要可用特殊颜色重点描述需求解决。 8、 调研:采取让客户上台讲流程的方式进行项目调研,同时进行业务流程分析和流程梳理。 9、 流程分析;认真进行流程分析,建议将系统不能实现的企业流程放在系统外实现,按以前的手工方式进行。 10、需求分析报告编写:培训、调研后再出具需求分析报告,因为培训中可以进行补充调研,可以将调研了解不到的情况挖掘出来。 11、培训与考核:注重培训质量,完成知识转移的重要手段和过程,不要顾虑在培训中投入时间,培训后一定要考核,培训质量不能保证对后期实施影响很大,培训过程中注意对客户的需求加以记录。 12、需求分析确认:需求分析报告一定要签字确认后再开展后面的工作,否则客户需求膨胀时不易控制。 13、基于方案的培训和方案讲解:如果对行业应用熟悉可不进行标准产品培训直接按思路中形成的方案培训,若对行业应用不熟悉可在标准培训和方案出具后再安排一次基于方案的培训。

软件系统项目建设项目管理文档

目录 1.项目管理 (1) 1.1项目范围管理 (1) 1.2项目时间管理 ......................................................................... 错误!未定义书签。 1.3项目里程碑 (6) 1.4培训方案 (6) 1.5技术支持与售后服务 (7) 1.6项目进度管理 (8) 信息系统项目建设项目管理文档 1.项目管理 1.1项目范围管理 (1)概述 项目范围管理就是要明确项目目标是什么,界定哪些工作必须做,并将项目目标分解到可以独立分包的程度,形成工作分解结构(WBS),并以此作为控制项目范围变更的基准。即项目范围管理是确保项目包含且只包含项目所必须完成的工作。 很多项目经常由于有做不完的报表、解决不完的问题而导致项目无法验收,很大一部分原因就是因为项目的范围没有定义清楚或者项目范围经常发生无可控制的变更所致。事实证明,缺少正确的项目范围定义和范围的核实是导致项目失败的主要因素。 因此,项目管理最重要的也是最难做的一项工作就是确定项目范围,并使项目范围在控制中,这就是项目范围管理的范畴,即项目范围管理就是项目该做什么,不该做什么,以及确保该做的事情必须做到,不该做的事情不能做。 在项目的规划阶段和蓝图设计阶段的前期,我们通过售前阶段的资料和项目

现场的需求调研,确定项目该做什么,这就是经常说的定义项目范围。 (2)管理内容 1、定义项目范围 1)定义项目范围重要的参考资料和依据一般如下: ●项目售前实施方案; ●项目主合同; ●许可软件通用条款及清单; ●咨询实施服务和工作任务书; ●支持服务条款; ●战略合作承诺书; ●建设单位内部正式发问的项目实施意见书。 2)口头承诺 定义范围除了依据上述可见的项目资料外,售前阶段的一些口头承诺也是定义项目范围的重要信息来源,因此在项目准备阶段与售前进行内部交接时,一定不能忘记交接口头承诺的内容,实践证明,口头承诺的往往是在项目实施过程中难以交付的或者需求范围不好清晰界定的,正是范围管理的难点。 通过范围定义,可形成详细的范围说明书,以及对项目管理计划进行更新。 2、项目范围 范围是指项目所提供的产品或服务的总和,它包括以下两种含义: ●产品范围:产品或者服务的特性与功能,其衡量标准为产品要求,即产 品需求说明书。 ●项目范围:为交付所需产品(具有特定属性和功能)和服务而必须完成 的工作,其衡量标准为项目管理计划、项目范围说明书、WBS及WBS词汇 表。 项目实施的产品范围的描述一般应该通过两个维度,即产品功能模块和公司范围两个维度,清晰的描述出哪些公司具体实施、哪些产品的功能模块,对于集团型企业一定要以企业法人作为实施的公司范围。借用EXCEL建立功能模块与法人

项目管理系统设计方案和对策

项目管理系统 页面设计方案 第V1.0版 文件编号 拟制单位 拟制设计人员年月日校对项目经理年月日审核技术助理年月日 标准化检查年月日批准产品经理年月日

1、项目管理系统页面设计说明 项目管理系统主要对项目立项、执行等流程进行信息化管理,主要功能是将项目各个节点流程状态进行存档备案,以反映出项目的进程,同时也反映出项目中存在的问题: 1.1组织角色 (1)生产科所 (2)所长 (3)经营计划部 (4)经营计划部负责人 (5)财务部 (6)安质部 (7)法律事务部 (8)设备物质部 (9)总工 (10)分管院长 1.2系统菜单 (1)项目前期 ●项目申报 ●项目审核 ●项目查询 (2)财务账目 ●收款 ●借款 ●报销及还款 ●账目查询 (3)合同管理 ●合同起草 ●合同审批 ●经营计划部审核 ●分管院长审核 ●法律事务部审核

●合同查询 (4)项目管理 ●项目立项 ●立项查询 ●进度计划 ●周报填写 ●周报查询 ●月报填写 ●月报查询 ●结项填写 ●结项审核 ●结项查询 ●项目进度查询 (5)采购管理 ●申请 ●审核 ●入库 ●领用 ●归还 (6)项目查询 ●项目信息查询 (7)统计报表 ●项目费用统计 ●项目完成率统计 ●项目工作量统计 ●项目进度统计 ●科所成本明细 ●项目到款情况统计 ●项目合同管理收款情况 (8)系统管理 1.3首页展示 首页用于展示项目管理的重要信息,包括通知公告、待办事务、任务提醒、投标信息、所动态四个板块 (1)通知公告:显示项目的进度情况和重要信息。

(2)待办事务:提醒用户需要办理项目事务,并提供快捷入口。 (3)任务提醒:提示用户项目进度情况,完成节点剩余时间。

建设项目管理信息系统的组成和功能

建设项目管理信息系统的组成和功能 建设项目管理信息系统的组成 建设项目管理信息系统是处理项目信息的人―机系统。它通过收集、存储及分析项目实施过程中的有关数据,辅助工程项目的管理人员和决策者规划、决策和检查,其核心是辅助对项目目标的控制。它与一般管理信息系统的差别在于一般管理信息系统是针对企业中的人、财、物、产、供、销的管理,是以企业管理系统为辅助工作的对象。而建设项目管理信息系统是针对建设项目中的投资、进度、质量目标的规划与控制,是以建设工程系统为辅助工作对象。项目管理信息系统与管理信息系统服务的对象和功能是不同的。 应用建设项目管理信息系统的主要意义是: ①实现项目管理数据的集中存储; ②有利于项目管理数据的检索和查询; ③提高项目管理数据处理的效率; ④确保项目管理数据处理的准确性; ⑤可方便地形成各种项目管理需要的报表。 建设项目管理信息系统的功能

建设项目管理信息系统的基本功能构成应包括投资控制、进度控制和合同管理三个子系统。有些项目管理信息系统还包括质量控制和一些办公自动化的功能。 各个子系统应实现的基本功能包括。 (1)进度控制子系统把投资建设项目管理师站点加入收藏夹 ①编制双代号网络计划(CPM)和单代号搭接网络计划(MPM); ②编制多阶网络(多平面群体网络)计划(MSM); ③工程实际进度的统计分析; ④实际进度与计划进度的动态比较; ⑤工程进度变化趋势预测; ⑥计划进度的定期调整; ⑦工程进度各类数据的查询; ⑧提供多种(不同管理平面)工程进度报表; ⑨绘制网络图; ⑩绘制横道图等。 (2)投资控制子系统

①编制投资估算; ②编制建设项目概算和预算; ③投资估算与项目概算的对比分析; ④建设项目概算与预算的对比分析; ⑤合同价与投资估算、概算、预算的对比分析; ⑥实际投资与概算、预算、合同价的对比分析; ⑦建设项目投资变化趋势预测; ⑧建设项目结算与预算、合同价的对比分析; ⑨建设项目投资的各类数据查询; ⑩提供多种(不同管理平面)建设项目投资报表等。 (3)合同管理子系统。 ①提供和选择标准的合同文本; ②合同文件、资料的管理; ③合同执行情况的跟踪和处理过程的管理; ④涉外合同的外汇折算;

项目管理系统信息系统方案设计书

无锡东方环境管理信息系统建设实施建议 O方正集团

世界在变创新不变

方正国际软件有限公司二0一一年四月

目录 第1章前言 (5) 1.1 信息化现状分析 (5) 1.2项目建设内容和目标 (6) 1.3建设原则 (6) 第2章系统实施要求 (8) 2.1总体技术要求 (8) 2.2系统总体框架 (9) 2.2.1底层支撑平台 (9) 2.2.2数据管理平台 (9) 2.2.3应用支撑平台 (9) 2.2.4数据应用平台............................................ 1.0. 2.2.5应用门户................................................ 10.. 第3章系统功能分析 (11) 3.1数据中心功能 .................................................. 1..1.. 3.1.1数据标准规范设计 ........................................... 1.1.. 3.2无锡东方环境管理信息系统要求 (12) 3.2.1企业管理 .................................................... 1.3.. 3.2.2人事管理 ................................... 错误!未定义书签。 3.2.3客户管理 ................................... 错误!未定义书签。

3.2.4项目管理 ................................... 错误!未定义书签。 3.2.5采购管理 ................................... 错误!未定义书签。

公司项目管理信息系统简介

公司项目管理信息系统简介 (作者:王建华、胡蓉) 《中国水利水电第三工程局有限公司项目管理信息系统》全面覆盖并整合公司办公自动化(包括档案系统)、项目综合管控、市场经营管理、综合项目管理、决策驾驶舱等方面的信息,解决项目部、分局、公司间各为一体的信息孤岛,建成公司集中的信息数据库,最终形成数据仓库,实现公司在项目综合管理方面的全面信息化、高度集中和系统化,对项目管理向精细化、精益化迈进将起到极大的促进作用。 一、项目管理系统的基本情况 1、项目建设背景、建设目标及意义 建设背景:根据建市[2007]72号及建市[2007]241号文件要求,为加快信息化建设步伐,大幅提升企业信息化水平和市场竞争能力,在新修订的建筑业企业资质管理规定中,特级资质标准增加了企业信息化建设考核内容,而综合项目管理系统的应用是信息化建设系统的核心内容,其所占考核权重达50%。为此,为顺利完成企业资质的重新核定工作,根据资质核定信息化建设的考评要求,公司于2009年5月引进了易建科技有限公司研发的《项目管理软件》,并结合公司自身管理需求进行了系统改进和完善,最终形成了《中国水利水电第三工程局有限公司项目管理信息系统》,并于2009年8月正式投入使用。 建设目标:项目管理系统是以项目为管理对象,覆盖项目从招投标-开工-竣工生命周期各个阶段和各个业务环节的管控。通过系统的实施,可建立公司、区域分局(专业分局)、项目部三级项目综合管理信息平台,满足各管理

层级管理需要,实现项目管理的标准化、规范化,以提高项目管理工作的效率和效益。 建设意义和实施必要性:从企业层面讲,综合项目管理系统实施是企业信息化建设的重要组成部分,既是建设部特级资质考评的硬性要求(在建项目使用综合项目管理系统需达项目总数的50%以上,近两年项目竣工管理、档案管理使用率为50%以上),更是提升公司管理水平和竞争力,实现管理现代化与信息化的根本需要,它的实施是现代企业发展的必然趋势。从项目层面讲,系统通过不同的业务模块划分和流程设计,促进项目管理行为规范化、标准化,实现了以数据为依据的科学决策方法,规范了施工管理中的经济活动,由被动管理向主动管理转型,是项目管理模式的重大变革,系统的实施对项目管理向精细化、精益化管理迈进起到极大的促进作用。 2、系统架构 从管理架构划分,系统分为业务执行层、管理控制层和决策规划层,即各项目-区域分局(专业分局)-公司三层结构。通过信息管理平台可实现不同管理层的审批流程、数据汇总、信息传递。其管理层级体系如下:

学生管理信息系统项目管理

一,项目概述 1.1、项目建设的目的 本项目主要目的是为了将所有学生的信息集中管理,实现对于信息化学生信息管理。 1.2、开发团队 1.3、组分工 二、围管理 2.1、WBS表

1420 网络系统实施接入局域网或广域网2.2、WBS 三、时间管理 3.1、程序作业时间图 学生管理信息系统建设的作业程序及作业时间: 任务名称紧前工序任务时间(天)项目规划(A)— 4 需求获取(B)— 2 需求确认(C) A 1 项目计划评审(D)B、C 1 概要设计(E) D 3 详细设计(F) E 5 学生基本信息数据库(G) F 10 课程管理数据库(H) F 10 成绩管理数据库(I) F 10 用户管理(J) F 3 系统集成测试(K)J、H、I、J 5 系统测试(L)K 6 提交(M)L 2

3.2、学生管理信息系统建设的网络图: 3.3、学生管理信息系统建设的时差计算:

四、成本管理 4.1、成本估算 成本估算法有两种基本的成本估算法:自上而下和自下而上。自上而下法是对整个工程项目的总开发时间和总工作量做出估算,然后将它们按阶段、步骤和任务进行分配。自下而上法则正好相反,先分别估算各个任务所需要的工作量和开发时间,再相加,从而得到总的工作量和总的开发时间。学生信息管理系统成本估算(自下而上):

4.2、成本预算(基准成本) 成本预算是把估算的总成本分配到各个工作项目,建立基准成本以衡量项目执行情况。基准成本,是以时间为自变量的预算,被用于度量和监督项目执行成本。把预计成本按时间累加便为基

准成本,可用S曲线表示。 4.3、成本控制(挣值分析法) 成本控制包括寻找产生正负偏差的原因,必须和其他控制过程结合(围控制、进度控制、质量控制及其他)。挣值分析法主要衡量目标实施与目标期望之间的差异,又叫成本偏差分析法。这种法通过测量和计算已完成工作预算成本、已完成工作实际成本以及计划工作预算成本,从而得到相关计划实施的进度和成本偏差,以此达到判断项目预算和进度执行情况的目的。 五、质量管理 5.1、项目围说明:开发适合学校需求的学生管理信息系统5.2、产品说明:通过这个系统,可以做到信息的规管理、

信息系统建设项目管理办法

项目建设管理办法 第一章总则 第一条为规范公司信息化建设项目实施过程管理,明确项目组织与职责分工,规范项目活动和交付质量控制,特制定本管理办法。 第二条本管理办法管理信息化建设项目项目合同生效后到项目验收前的整个实施过程,主要内容包括项目分类与组织、项目里程碑管理及项目管理规范。其中项目里程碑管理包括项目的里程碑划分、关键任务规范、主要的交付件模板和评审点,项目管理规范主要包括计划与会议管理、问题与风险管理、变更管理。 第三条本管理办法适用于公司所有与信息技术应用相关的项目和参与信息化建设项目项目实施过程中的信息化建设项目、业务部门和供应商人员。 第二章组织机构与职责 第四条项目分类:根据项目的实施性质分为应用实施、定制开发、硬件集成类项目。根据实施方式分为外包、自主实施、自主实施部分外包类项目。 第五条项目小组由供应商、业务部门、信息化建设项目部门共同组成,项目组根据专业分工分为项目管理组、业务组、开发组和系统支持组。 第六条不同项目分类,参与项目的角色有所不同,项目启动前,双方项目经理需根据项目要求和资源状况重新确定项目组织和项目组人员,明确项目职责分工后予以正式发布。 第七条项目经理:负责项目过程的计划与会议管理、问题与风险管理、变更管理,为项目执行过程管理的责任人。应用类项目可分别设立业务项目经理和信息化建设项目项目经理,业务项目经理由项目主办单位项目负责人担任,信息化建设项目项目经理由信息化建设项目部门项目管理人员担任。 第八条项目业务组:由业务分析、实施顾问、关键用户组成,业务分析由主办单

位的业务负责人或业务骨干担任,负责项目需求和业务管理方案的确认;实施顾问由供应商或信息化建设项目部门具备业务咨询和分析能力的业务顾问担任,参与或负责项目需求的分析、设计与变更管理。关键用户参与需求调研、测试。 第九条 项目开发组:由供应商或信息化建设项目部门系统架构师、技术支持、开发顾问、软件测试、软件配置等角色,负责信息化建设项目项目软件或定制开发需求的设计、开发、测试与质量控制,其中大型应用或基础类项目,必须设立系统架构师,负责总体方案的设计或评审。 第十条 系统支持组:由信息化建设项目部门的运维中心系统管理人员担任,负责系统正式环境管理、系统环境规划、搭建及系统管理规范的建立,参与技术方案评审和协助系统环境优化,负责系统移交的正式接收人。 第三章 项目里程碑管理 第十一条 项目组与供应商签订正式合同后,标志着项目正式进入项目实施阶段。项目实施过程包括项目准备、需求分析、方案设计、系统实现、上线运行、项目移交等六大里程碑,里程碑的关键工作任务如(图一)所示。 第十二条 项目经理根据项目特点制定项目计划及项目的交付要求,所有项目实施交付文档按里程碑每月定期在公司信息化建设项目管理部备案。 第四章 项目准备阶段 成立项目组 建立项目章程 制定项目计划 业务调研 需求分析 需求评审 需求确认 总体设计 详细设计 实施方案编制 软件编码 硬件安装 验收方案编制 功能测试 性能测试 安全性测试 验收报告评审 上线方案编制 上线评审 最终用户培训 正式环境部署 项目初验 试运行跟踪 项目初验 系统移交 制定系统规范 制定业务规范 项目终验

综合项目管理信息系统说明

综合项目管理信息系统说明 一、概念 项目管理信息系统是以工程项目为目标,利用计算机辅助工程项目管理的信息系统。它是基于项目运行信息的管理分析,为项目管理提供信息服务与决策支持的工具。项目管理信息系统,涉及项目总体的计划、组织、领导、控制和评价等各个方面,具体包括质量控制、进度控制、费用估算与费用控制、材料控制和文件控制等多方面的控制和管理,并对项目的全过程实施动态管理和控制。项目管理信息系统不像以往那样只具有人事档案、工资、财务等常规的静态管理信息,而加入了生产建设过程中的许多生产实时动态的控制,有大量的实时数据和信息需要处理,需要各种图表、项目执行过程的真实记录、不断调整的计划。对这些功能的实现过程,关键在于把较成熟和先进的项目管理软件与工程企业自己的信息综合集成、实现信息实时共享与互操作性。 二、重要性 随着建设项目大型化、综合化与复杂化趋势的不断加剧,以及建设项目面临的投入、进度、质量、安全、环境等约束的进一步严格,提高项目管理的效率,在有限的时问与投入下高质量地完成合约并满足安全、环境等要求已成为当前建设项目管理面临的重大挑战。准确的、及时的、相关的信息是项目决策进程的实质,信息对

项目管理者来说是一个非常重要的资源。但是,项目管理者们却总是无法提交确保项目成功的那些种类的信息,所以构建项目管理信息系统是满足重要的项目信息需求的一种方法,也是大型工程项目管理的重要基础设施和手段。 2007年 l0月 18日,建设部建筑市场管理司发布了《建筑业企业资质管理规定实施意见》(建市[2007]241号)附件2“施工总承包企业特级资质标准信息化考评表”,对申报特级资质的施工企业的信息化建设提出了具体的要求。在市场经济竞争日益激烈的环境里,很多大型施工企业面临着许多管理困境,需要借助信息化手段提高管理水平。在现有环境和条件下,如何建设实施一个安全、有效、可靠、可随企业发展而变化的综合项目管理信息系统来支撑项目管理,从而提高项目管理能力,进而提升市场环境下的竞争能力,对企业而言具有非常重大的实际应用意义。 三、现状 在如今建筑企业中计算机已经相当普及,在10多年前就有许多施工企业已筹建了独立的机房、计算机中心,设有专门的人员从事这方面的工作。从硬件来说,我们所使用的计算机基本上紧跟国际先进水平。在项目管理实践中,综合项目管理信息系统在近1O余年间经历了从无到有的发展过程,目前一些大型的施工企业已经具备了专用的综合项目管理信息系统,并用于实践。但是,由于缺乏高层的统筹规划和统一的信息标准,致使设计、生产和经营管理信息不能快捷流通,信息不能共享,形成了许多“信息孤岛”,远没有

项目管理系统毕业设计任务书

毕业设计(论文)任务书 题目:基于.NET的项目管理系统的设计与实现 专业:计算机科学与技术指导教师: 学院:信息学号: 2008080305325 班级: 200808030501A 姓名: 一、主要内容和基本要求 该毕业设计题为《基于.NET的项目管理系统的设计与实现》,主要运用C#语言进行开发,数据库采用MSSQL Server 05,将运行于安装有.NET Framewrok3.5以上的Windows系统平台上。该设计的主要内容包括: ①资源管理:主要为人员管理,包括人员基本的增删改查,角色分配等。 ②交付管理:项目经理录入、维护项目基本信息(包括一般信息、客户信息、分包商信息、财政信息、申请人员信息、项目经理等)、费用预算,建立项目里程碑,制定项目计划,管理项目风险;系统每周一凌晨计算分析上周人员、项目的收支情况以及费用管理员导入的其他ERP系统导出的报销费用明细;相关人员可以查询上述基本信息和统计分析图表(下钻)展示。 ③TIMESHEET管理:项目经理填写和提交项目组成员工时,以记录、查询出勤情况,同时也为项目实际开支计算提供基础数据。 ④系统管理:主要为用户管理。给用户分配角色和机构权限。 二、主要参考资料 [1]刘智勇,王文强.JavaScript从入门到精通[M].北京:化学工业出版社,2009:261-269. [2]奚江华https://www.360docs.net/doc/6916933215.html,3.5开发详解Ⅱ——新功能篇[M].北京:电子工业出版社,2008:174-176. [3]w3school. 领先的Web技术教程.[EB/OL].[2011]. https://www.360docs.net/doc/6916933215.html,/. [4]李力.企业项目管理系统的设计与实现[D].南开大学,2009. [5]应尚军,王炎.项目管理的研究现状与研究前景[J].科技进步与对策,2005,22(11):131-133. [6]袁经勇.国内外项目管理现状及发展趋势[J].化工建设工程,2001,23(3):8-9,12. [7]北京维普时代软件有限公司.成功案例.[OL] https://www.360docs.net/doc/6916933215.html,/index.asp [8]金平.企业项目管理系统的分析与设计[J].中国制造业信息化,2009,38(9):10-12.

ERP实施的项目管理

E R P实施的项目管理 Standardization of sany group #QS8QHH-HHGX8Q8-GNHHJ8-HHMHGN#

ERP实施的项目管理 对ERP项目所有方面的计划、组织、管理和监控,是为了达到项目实施后的预期成果和目标而采取内部和外部的持续性的工作程序。这是对时间、成本,以及产品、服务细节的需求相互间可能发生矛盾进行平衡的基本原则。 以下是结合实施ERP项目的实际经验,介绍ERP项目管理的主要内容、工具和方法。 一、典型的项目管理循环 一个完整的ERP项目通常包括三大阶段:需求分析、系统选型和系统实施;在系统实施阶段又可细分为实施计划、业务模拟测试、系统开发确认、系统转换运行、运行后评估五个主要步骤。项目管理围绕整个ERP项目的全过程,对项目的立项授权、需求分析、软硬件的评估选择,以及系统的实施进行全面的管理和控制。一个典型的ERP项目管理循环通常包括:项目开始、项目选型、项目计划、项目执行、项目评估及更新和项目完成六项主要内容。图1反映了ERP 项目的实施阶段和项目管理循环之间的关系。 1. 项目开始

项目开始阶段主要针对ERP项目的需求、范围和可行性进行分析,制定项目的总体安排计划,并以"项目合同"的方式由企业与ERP 项目咨询公司确定项目责任和授权。在项目开始阶段进行的项目管 理主要包括以下内容: ·需求评估对企业的整体需求和期望作出分析和评估,并据此 明确ERP项目成果的期望和目标。 ·项目范围定义在明确企业期望和需求的基础上,定义ERP项 目的整体范围。 ·可行性分析根据项目的期望和目标以及预计项目的实施范围,对企业自身的人力资源、技术支持等方面作出评估,明确需要为配合项目而采取的措施和投资的资源。 ·项目总体安排对项目的时间、进度、人员等作出总体安排, 制定ERP项目的总体计划。 ·项目授权由企业与ERP项目咨询公司签订ERP项目合同,明 确双方职责,并由企业根据项目的需要对咨询公司进行项目管理的授权。

信息管理系统实施方案设计

信息管理实施方案 一、信息管理体系 (一)本项目信息体系的主要容 1、项目招投标、勘察设计、施工、交付使用、维修等项目生命期或某个阶段中与项目代建有关的容。 2、法律法规、企业规章制度、财政资金、市场、风险、客户、采购、合同、质量、安全、费用、进度、劳务、物资、机械信息等。 3、信息管理数据库系统、通讯系统、应用软件系统;形成若干相互作用、相互联系的,有机结合起来、有一定系统结构和功能且能表达一种管理行为的整体。 (二)建立项目信息管理体系的步骤 1、规划项目代建信息系统; 2、建立项目信息管理模式和制度; 3、选择适用的辅助管理项目信息的软件系统。 二、信息管理的措施方法 (一)硬件配置完善 1、现场将配备电脑、适当的通讯工具,以便信息传递。通讯工具包括手机、座机、对讲机; 2、现场将配置信息记录设备,如照像机、摄像机等,对重要施工现场的情况进行拍照记录,以便查询。

(二)项目信息分类 本项目的项目信息按信息来源可分为项目公共信息和项目个体信息。公共信息包括各种国家法规和政府部门规章、市场价格信息、自然条件信息、供应商信息、勘察、设计、监理和施工单位信息等。项目个体信息则包括工程概况、施工记录、施工技术资料、工程协调、过程进度计划及资源计划、成本、商务、质量检查、安全文明施工及行政管理、竣工验收等信息。上述所有信息都将纳入本项目的信息管理系统围,实施规管理。 (三)项目信息管理的组织及制度保证 本工程项目代建方将设立专职的项目信息主管,隶属工程统筹工程师,专门负责制定本项目的信息管理办法和建立项目信息管理系统,实施信息管理工作。并在项目代建方其他专业工程师下属人员中指定兼职的项目基层信息员,负责收集各管理职能围的信息。兼职信息员受直属专业工程师及项目信息主管的双重领导,形成上通下达的项目信息资源管理组织体系。 项目代建方制订项目信息管理办法,将对项目信息主管的职责、信息分类方法、信息收集和处理、信息传递要求、传递渠道、传递形式、传递容、传递审核及信息储存要求等作出详细规定。 (四)项目信息管理流程 1、外部流程 除本项目代建方外,本项目的其他参与方都从属于项目外部信息管理围。其他参与方包括招标人、使用方,政府有关主管部门,项目

外文翻译---ERP项目实施成功因素和风险管理

ERP项目实施成功因素和风险管理 参考国外的一些文献资料,一个成功的ERP项目,往往要花费数年时间,数千万美元得以完成。再回头看国内,随着ERP怀疑论的抬头,价格战的兴起,ERP 作为一种软件供应商的产品,却有走下神坛趋势。就连ERP界的首领SAP也推出了Business One产品,价格低于十万。不过,即便ERP软件能做到免费,或如IBM推崇的按需收费的境界,从整个企业实施的角度,考虑到人员、培训、维护、业务重组、二次开发、三次、n次开发,其费用应该也在数百万乃至千万人民币的规模。这对于国内企业而言,已是不小的数目了。 但是,还是有不少企业怀着美丽的梦想,踏上ERP实施的艰辛之旅。其中又有不少项目以失败告终。而对于那些最后的幸存者,是否就可以还戟入仓,饮酒高歌呢? 事实上,企业在成功实施ERP项目后,将面对较实施前更大的风险。在未来的五到十年中,是否有一个扎实的ERP风险管理机制将决定了企业是否能在最初的ERP投资中真正获益。 1998年Thomas H.Davenport在哈佛商务评论发表了名为《将企业放入企业系统》的文章(Putting the entERPrise into the entERPrise system)。该文系统地提出了企业系统,或称ERP系统给企业运作带来积极及消极的引响。同时也直接提出了未来企业必须面对的一个风险:将整个企业放入企业系统中的风险。 按照美国项目管理协会对风险的定义,“风险”是指对项目有利或不利的不确定因素。 项目是“为完成某一独特的产品或服务所做的一次性努力”,项目的“独特性”决定了项目不可能是以与以前完全相同的方式、由与以前完全相同的人来完成的,同时,项目所要创造的产品或服务,以及项目可能涉及的范围、时间及成本都不可能在项目开始时完全确定,因此,在项目进行过程中也相应会出现大量的不确定性,即项目风险。本文以下所提到的“风险”是指对项目“不利”的不确定因素。 对项目不利的风险存在于任何项目中,并往往会给项目的推进和项目的成功带来负面影响。风险一旦发生,它的影响是多方面的,如导致项目产品/服务的

工程项目信息管理系统-概要设计

工程项目信息管理系统 概要设计

目录 第一章................................................................................................................ 项目背景4 第二章................................................................................................................ 建设目标5 第三章................................................................................................................ 设计思路5 第四章................................................................................................................ 总体设计6 4.1 ....................................................................................................................... 整体架构 6 4.2 ....................................................................................................................... 功能结构 10 第五章................................................................................................................ 功能设计16 5.1 ........................................................................................................ 工程项目管理软件 17 5.1.1项目信息 (17) 5.1.2施工计量 (19) 5.1.3合同信息 (20) 5.1.4统计报表 (21) 5.1.5待办事宜 (22) 5.1.6系统管理 (22)

项目管理系统PM设计方案

项目管理系统PM设计方案 1产品名称 2概述 本司希望所有的业务都以项目的形式运作,我们知道管理学中的项目分为三种模式, 1.项目型管理,2,职能型管理,3,矩阵型管理,目前本司未确定使用哪种管理模式, 在此,建议使用矩阵型管理模式。 本系统需要贯穿公司的人力管理,资产管理,考核管理,财务管理,因为一个项目肯定是涉及所有这些业务的,成熟的项目管理系统不可能独立存在的。比如,一个项目立项时,需要进行人力预算,资产预算,以及其他财务预算,项目结束后,需要对项目人员进行业绩考核,这就与人员的绩效和工资联系在一起。 项目管理包括:1、范围(项目范围,任务分解),2、时间(任务执行时间计划与进度),3、成本(项目费用人工成本),4、沟通(沟通规划,问题与沟通),5、风险(风险检查,提醒与处理),6、质量(质量目标,质量检查),7、人力资源(人力资源调配,绩效评估),这7个管理层面都需要在本系统中进行体现。

3功能架构图 4项目管理 项目管理包括立项启动,立项评审,立项等过程,立项启动时,需要进行立项预算,风险评估,项目权重设置等工作。 下面会在每个章节中对每个项目活动进行详细阐述,下面流程图是基于金融项目的一般项目流程。

5预算管理 预算包括下图中的各项活动: 5.1成本预算 主要是人力成本的预算,不同员工的人力成本是不同的,因此单纯的做人力预算是不够的,人力成本才是项目成本的重要指标。 5.2人力预算 在系统中设置项目需要的人力,包括人员数量,人员级别或者具体要求,然后由行政部门根据成本预算以及人力预算的要求,综合评估后,向项目派发项目参与人员。

5.3资产预算 项目执行时,不但需要人力,还需要其他配套的资产,如服务器,产品,办公用品等,这些都属于项目开销,因此需要在系统中设置资产名称,资产数量,资产价格等属性,系统自动计算最终的资产预算。 5.4时间预算 主要就是项目的开始时间,结束时间,有的项目还会设置各种里程碑时间。 5.5其他预算 其他预算主要是为项目正常运作,所需的出差费用,招待费用等,这些也需要在系统中录入,作为日后项目评估的依据,需要包括费用名称,费用金额。 6核算管理 核算即对预算准确性的评估,可以发生在项目结束时,也可以发生在项目执行过程中,如各个里程碑时间点,实时的核算有利于控制项目风险。 核算包括部门的核算与项目的核算,核算内容为实际的投入或者使用,与项目立项时的预算进行对比分析,以便进行风险控制以及经验总结。 核算的项目就是预算管理中的各个项目,每个项目都需要进行核算。 7任务管理 项目立项后,项目经理向项目组成员下发任务,项目组成员填写任务日志,在进行考核时,需要计算项目工时,根据项目工时以及项目完成情况对项目组成员进行考核。 任务管理属性: 项目名称,任务名称,填报人员,任务时间,填报时间,完成进度,完成描述,工时。 8人力资源 包括人力投入比例的配置,项目组人员工作负荷的统计分析。 每个人员可以参与到多个项目中,行政部门负责人需要对人力负荷合理评估,并设置每个项目的参与比例(参与比例在人事在线系统中设置),参与比例的确定也就决定了参与项目的工时,因此在下发任务时,尽量不要超出工时,如果超出所分配的工时,

管理信息系统的项目流程

一、管理信息系统开发项目管理流程 管理信息系统的开发是一项涉及面广,技术难度大的综合性系统工程,需要投入大量的人力、财力、物力、时间等资源,对整个企业组织的改革与发展会产生很大的影响。只有对企业管理信息系统的整个开发过程按照系统的观点使用现代项目管理的科学理念和方法进行控制,才可能以较小的投入,取得较为理想的效果。 1、项目管理的概念 项目管理是指在一定资源如时间、资金、人力、设备、材料、能源、动力等约束条件下,为了高效率地实现项目的既定目标(即到项目竣工时计划达到的质量、投资、进度),按照项目的内在规律和程序,对项目的全过程进行有效的计划、组织、协调、领导和控制的系统管理活动。项目是具有明确目标的一次性任务,具有明显的生命周期,阶段性强。项目管理是面向所有工程项目的管理,是运用系统科学的原理对工程项目进行计划、组织与控制的系统管理方法。项目管理要解决的基本问题就是如何按所选择的研制方法,对开发项目进行有效的计划、组织、协调、领导、控制。 项目的管理是“一把手”工程,领导参与是关键。项目经理必须合理配置项目参加人员,制定项目建设的有关规范,及时产生详尽的报表,正确评价项目的进展情况。 近年来,世界各国都开始对信息系统的建设实施项目管理,不少软件开发商还提供了项目管理软件,如美国微软公司的Project2000、美国Primavera公司的ProjectPlannerP3和OS/23.0、我国北京梦龙公司的PERT3.0等。这些软件主要用于编排项目的进度计划,通过资源的分析和成本管理,合理配置资源使计划进度更为合理,同时按计划来安排工程进度,并对进度进行动态跟踪与控制等。 2、加强信息系统开发项目管理的重要意义 已经在国民经济诸多领域中成功运用的项目管理方法,也完全可以用于信息系统开发项目的管理。管理信息系统开发是一项长期的任务,必须根据企业组织的改革、发展的需要和可能,分成若干项目,分步进行开发。信息系统的“开发项目”包含信息系统分析、设计和实施的整个过程。它由项目负责人(项目经理)负责,利用可获得的资源为用户组织系统的建设。根据系统科学的观点,小项目可以构成一个大项目,一个大项目可以分解成若干个小项目。项目管理实质上是保证整个系统开发项目顺利、高效地完成的一种过程管理技术,贯穿于系统开发的整个生命周期。信息系统开发也是一项系统工程项目 如同其他工程项目一样,研制开发一个信息系统也需要在给定的时间内计划、协调和合理使用配置各种资源,对信息系统进行项目管理的重要性有以下四点: (1)可以进行系统的思考,进行切合实际的全局性安排;

集团ERP系统项目管理办法

第一章总则 第一条为加强**集团企业资源计划系统项目(下称ERP项目)管理和建设,保证ERP项目实施顺利进行,根据ERP项目实施的总体工作要求,特制定本办法。 第二条本办法适用于ERP项目实施过程中涉及的**集团及所属二级单位、部门及人员、其他经**集团授权参与项目实施的第三方公司人员。 第三条ERP项目实行项目管理制,即以各专业组组长负责制为核心的紧密型项目管理方式,各专业组关键用户根据项目实际进度需求全职投入工作。 第二章组织机构及职责 第四条为加强项目实施的组织领导和工作力度,保证项目目标任务如期实现,成立项目领导小组及其办事机构。各机构名称、职责及组成人员如下(项目办公室、宣传推进组、信息技术组及5个专业管理组下统称各工作组) 项目办公室: 宣传推进组: 信息技术组 专业组: 第五条为加强对项目建设监督考核工作的领导,成立公司ERP 项目考核委员会,全面负责考核工作。考核委员会人员组成如下:主任: 成员: 第六条考核委员会的职责: 1、对项目进展、各工作组及参与实施部门(单位)的工作进度、工作质量进行监督、考核; 2、对各工作组的工作态度、考勤情况进行检查、督促和考核; 3、对各工作组、参与实施部门(单位)在项目管理制度方面的执行情况进行检查、评议与考核; 4、对参与实施部门(单位)工作配合情况进行评议与考核。

第七条各工作组的考核职责: 1、对本组人员工作开展情况进行督促、检查与评议; 2、对本组工作结果、工作质量、工作完成时效进行检查、把关; 3、对本组人员考勤情况进行统计; 4、对本组成员工作态度、工作配合程度进行评议; 5、向考核委员会提交本组工作自评意见,向考核委员会提交试点单位、推广实施单位的工作考评意见。 第三章计划及进度管理 第八条项目实施过程按照日小结、周计划、月考核的方式进行管理,目的是确保项目按照实施进度计划有效推进。 第九条各工作组每日应小结当日完成的工作内容、分析存在问题、提出改进措施。 第十条各工作组应在周五对每周工作做总结回顾,按照周计划文档的模板填写,并于当日提交给项目办公室。每周进度报告应对照周工作计划,逐项说明工作完成情况,对周进度、周工作成果、存在问题进行总结,对顾问服务时间进行汇总。 第十一条各工作组应在每月末对当月工作完成情况进行总结,并将月工作完成总结于月度例会前一天提交项目办公室。 第十二条实施方应严格控制项目实施进度。各工作组应严格控制计划的实施,对严重偏离原计划和进度的,应及时做出调整并在周例会上详细说明情况。 第四章变更管理 第十三条变更管理的目的是规避项目实施风险,控制项目实施内容和范围不偏离整体规划。 第十四条差异性分析后形成的实施蓝图一经确认,原则上不应改变。各专业组组长应负责对实施范围、流程、内容的变更进行控制。 第十五条各专业组应考虑变更对项目实施造成的影响。确需变更的,应由各专业组提出书面申请。变更申请应详细说明变更的内容和理由、变更部分在项目进程中的状态,并评估该变更对项目进程和费用可能产生的影响。 第十六条变更应履行审批程序。变更申请由专业组组长签字后报项目实施工作组审批,涉及重大实施范围变更的,上报项目领导小组批准。

相关文档
最新文档