Wind Turbine Operation & Maintenance Based on Condition Monitoring WT-O

Wind Turbine Operation & Maintenance Based on Condition Monitoring WT-O
Wind Turbine Operation & Maintenance Based on Condition Monitoring WT-O

April 2003ECN-C--03-047

Wind Turbine Operation & Maintenance

based on Condition Monitoring

WT-?

Final report

T.W. Verbruggen

Acknowledgement

This report is part of the project entitled WT_? (WT_OMEGA = Wind Turbine Operation and Maintenance based on Condition Monitoring) which has been carried out in co-operation with Lagerwey the WindMaster, Siemens Nederland, and SKF.

The work was partly financed by NOVEM, and partly by ECN Wind Energy.

ECN project number: 7.4028

Novem contract number: 224.321-9960

CONTENTS

SUMMARY5 1.INTRODUCTION7 1.1Background7

1.2Objectives7

2.LITERATURE STUDY (SUMMARY)11 2.1Condition Monitoring Techniques11 2.1.1Vibration Analysis11 2.1.2Oil analysis12 2.1.3Thermography12 2.1.4Physical condition of materials12 2.1.5Strain measurement13 2.1.6Acoustic monitoring13 2.1.7Electrical effects13 2.1.8Process parameters13 2.1.9Performance monitoring13 2.2Possibilities of application in wind turbines14 2.2.1Rotor14

2.2.1.1BLADES14

2.2.1.2PITCH MECHANISM14 2.2.2Nacelle14 2.2.2.1GEARBOX AND MAIN BEARING14 2.2.2.2GENERATOR15 2.2.2.3HYDRAULIC SYSTEM15 2.2.2.4YAW SYSTEM15 2.3Economical Aspects15

2.4Conclusions16

3.SELECTED SUB-SYSTEMS, COMPONENTS AND CM-TECHNIQUES19 3.1Global condition monitoring techniques19 3.2Pitch mechanism19 3.3Gear box21 3.4Main bearing21 3.5Sound registration22

3.6Blade monitoring22

4.INSTRUMENTATION OF THE LAGERWEY 50/75023

5.INSTRUMENTATION OF THE ENRON 1,5 S25

6.CONCLUSIONS29

7.REFERENCES31 APPENDIX A: MEASUREMENT AND INSTRUMENTATION PLAN OF THE LAGERWEY 50/75033 APPENDIX B: MEASUREMENT AND INSTRUMENTATION PLAN OF THE ENRON

1,5S TURBINE37

SUMMARY

In 1999, ECN has taken the initiative to investigate the further application of condition monitoring for wind turbines. With financial support from NOVEM, ECN has carried out the project WT-?.

The project included three parts, being:

1. A literature study on available condition monitoring techniques, also including a selection

of techniques which has added value for wind turbines.

2.Instrumentation of a turbine and demonstration of some of the selected condition

monitoring techniques.

3.Identification of new areas for further development such as new sensors, algorithms and

system integration.

This document contains a summary of the literature survey and an overview of the work that has been carried out to instrument the Lagerwey LW50/750 and the Enron 1.5S turbines.

The literature study has been carried out and gives insight in the application of condition monitoring techniques and the possibilities, economically as well as technically. The most interesting areas have been identified, taking into account the state of the art of the monitoring techniques.

For the second part of the project, a prototype of the Lagerwey the Windmaster LW 50/750 was selected. Great advantage of this turbine was that instrumentation for load measurements was already available for certification. So for the condition monitoring project only additional measurements with respect to process parameters had to be added. Critical subsystems, where added value of condition monitoring can be expected are the pitch system and the main bearing. Important disadvantage of this type of turbine is the absence of a gearbox, which is normally considered as a critical component where important costs reduction can be achieved when faults are detected in an early stage. Also the main bearing is not representative for common wind turbine designs.

For a development project on condition monitoring, steady state operation for a long period is necessary in order to be able to recognise trend in characteristic signals. The prototype of the Lagerwey was prone to frequent replacement of components and control software. Because steady state operation could not be assured, the measurement program has been cancelled.

In order to carry out the second phase of the project, another turbine was selected to perform measurements. The ENRON 1,5s turbine, owned by Siemens and located in Zoetermeer, appeared to be suitable for the project because the main objective is electricity production and the design can be considered as representative. The drive train is conventional, including a gearbox, it operates with variable speed and it has three independent electrical pitch systems. Besides that, Siemens was also very interested in the project from the point of view of maintenance for off shore wind application.

Unfortunately, the time delay in the project caused by the non-availability of the Lagerwey turbine, the time needed for instrumentation and consultation for the Lagerwey turbine as well as for the Enron turbine appeared to be so time consuming that the third part could not be carried out. The measurement system for the Enron turbine has been implemented and will be used in a successive project.

Important spin-off of the project is the development of fibre optic measurement technology. This techniques offers large potential with respect to blade condition monitoring and load reduction. A first measurement system has been installed in the DOWEC turbine for load

measurements. Further development should result in off-the-shelf sensors and instrumentation, which can easily be integrated in the wind turbine control system.

From the experience gained during the project it can be concluded that:

?There is a rapid growing interest for condition monitoring for wind turbines.?Systems, based on vibration analysis, developed for other branches of industry, are available.?The effectiveness of standard condition monitoring systems for wind turbines is not yet demonstrated and not yet evident.

?Besides the standard condition monitoring techniques, there are also opportunities for more specialised provisions which can be implemented in the wind turbine control system.

?The activities for adaptation and verification of standard monitoring techniques for wind turbines as well as development of specialised functions require will require a long term.? A measurement facility, which is available for a long period and which is provided with flexible communication provisions is essential for development and improvement of condition monitoring systems.

1.INTRODUCTION

1.1Background

The operational costs of offshore wind turbines that are presently commercially available, seem too high to make offshore wind projects economically viable. For offshore wind, the costs for O&M (Operation and Maintenance) are estimated in the order of 30 to 35 % of the Costs of Electricity. Rough 25 to 35% is related to preventive maintenance and 65 to 75% to corrective maintenance (note that onshore this ratio is approximately 1:1). The revenue losses for offshore wind turbines are estimated in the same order as the direct costs for repair whereas for onshore projects the revenue losses are negligible [7], [8], [9].

One of the approaches to reduce the cost for corrective maintenance is the application of condition monitoring for early failure detection. If failures can be detected at an early stage, the consequence damage can be less so the repair will be less expensive. Offshore wind turbines however, will benefit the most from the fact that with early failure detection, repairs can be better planned. This will lead to shorter downtimes and less revenue losses.

The application of condition monitoring has grown considerably in the last decade in several branches of industry. The interest from the wind turbine industry and operators is also increasing for the reasons mentioned above. Because of small financial margins in the wind turbine branch, the relatively small production losses, the minor effects on the electricity network (a wind turbine is operating stand-alone), and the easy access, the application remained limited to some experimental projects. Additionally, most components have been designed for the lifetime of the turbine, which implies that degradation leading to replacement, is expected not to occur.

At present, with the increasing installed power of the wind turbines, the application of off shore wind turbines and major problems with gearboxes, the necessity of condition monitoring cannot be neglected any longer. Some components, although designed for the turbine lifetime, fail earlier than expected. This is emphasised by the approach of insurance companies in Germany, which simply require application of monitoring provisions. Otherwise, expensive preventive replacements or inspections should be carried out periodically. Also the development of special purpose instrumentation for wind turbines result in more or less off the shelf systems for a reasonable price.

1.2Objectives

In 1999, ECN has taken initiatives to further investigate the applicability of condition monitoring for wind turbines. With financial support from NOVEM, ECN has carried out the project WT_? (WT_OMEGA = Wind Turbine Operation and Maintenance based on Condition Monitoring) from 2000 to 2003. The objectives of the project were threefold:

1.making an inventory of the available condition monitoring techniques and selecting a set

which has added value for wind turbines;

2.to instrument a wind turbine and demonstrate some of the selected condition monitoring

techniques;

3.identifying areas for further development, e.g. new sensors, algorithms for data analysis ,or

integration of the systems in the turbine and wind farm controller.

For objective 1, a literature survey has been carried out and reported in [1]. A summary of this study can be found in Chapter 2. It gives insight in the application of condition monitoring techniques and the possibilities, economically as well as technically. A trade off has been performed to identify the most interesting application areas, taking into account the state of the art of the monitoring techniques. Some techniques seem very promising on a long term, which requires a separate development with related risks. Fibre optics measurement technology is such a technique. (Note that the development of fibre optic measurement techniques is outside the scope of this project and will not be discussed further on. Details can be read in [2].) The condition monitoring systems and techniques that seem promising for optimising the maintenance procedures of wind farms have been summarised in Chapter 3.

For objective 2, a prototype of the Lagerwey the WindMaster LW 50/750 turbine was selected. The LW 50/750 is a direct drive turbine with a rated power of 750 kW, independent electro-mechanical blade pitch mechanisms, and variable speed. Based on the literature study, a measurement and instrumentation plan were made, with the aim to obtain measurement data for further signal analysis. This turbine was selected because Lagerwey the Windmaster was already a partner in the project, and this turbine was already instrumented for load measurements. Only additional instrumentation had to be added at relatively low costs.

After the turbine was fully instrumented, it appeared that the consequences of applying condition monitoring systems to a prototype were underestimated. The blades were replaced several times during the project, the parameter settings changed regularly and the back-to-back converter was subject of continuous development. For condition monitoring experiments, a stable configuration for a longer period is very important. The start of the measurement campaign was postponed several times, waiting for a configuration that remained unchanged for a period of at least 3 months. Unfortunately, the required stable configuration could not be assured by Lagerwey the Windmaster. After waiting for almost 1 year, but without obtaining valuable measured data, the project team decided to cancel the measurements. The measurement and instrumentation plan and the experiences with the LW 50/750 turbine are described in Chapter 4 and Annex A.

After consultation with Novem, the project team decided to continue with the condition monitoring experiments, however it was realised that within the constraints of the project (mainly limited time and budget) the initial project objectives could not be fully met. First of all, another project partner and another turbine had to be found. Secondly, the new turbine had to be instrumented again, and finally a measurement period of at least 3 to 6 months was necessary. Within the constraints of the project, only the instrumentation of a new turbine was feasible. Finalising the measurements and collecting relevant data was not possible. To make sure that the condition monitoring experiments could be finished satisfactorily, a new project was defined. It was decided to initiate a new European project on condition monitoring for offshore wind farms (CONMOW) [6]. This new project should be regarded as the “successor” of WT_?.

The new project partner was Siemens Nederland N.V.. Siemens has shown their interest in the project for some time, and offered the possibility to use the Enron 1.5S turbine in Zoetermeer for condition monitoring measurements. The Enron 1.5 S turbine is more suited for condition monitoring experiments since it is equipped with a gearbox, and a high speed generator. The Enron turbine is more representative for the first generation offshore turbines than the LW 50/750 turbine. Due to technical and contractual matters among the partners and General Electric (formerly Enron Wind), it took about a year before the instrumentation of this turbine started. By the end of the project, the Enron 1.5 S turbine was instrumented to a large extent and ready for executing the CONMOW project. The instrumentation is very flexible, and incorporates the possibility to install different condition monitoring techniques for development and evaluation. This is described in Chapter 5.

Unfortunately, the objective 3 could not be met, mainly due to the problems with the LW 15/750 turbine. The remaining time and budget appeared to be too limited to collect and analyse measured data and to draw robust conclusions on how to incorporate condition monitoring in the O&M procedures of an offshore wind farm. However, the positive result is that the project ended with an instrumented turbine with which it is possible to continue the condition monitoring experiments over a longer period of time. This is necessary because trends in characteristic signals will manifest very slowly and that it might take years in stead of months to detect significant changes. So, the CONMOW project, which is the successor of WT_ ?, has better prospects to meet the original WT_ ? objectives, The WT_ ? plan was clearly too ambitious.

2.LITERATURE STUDY (SUMMARY)

A literature study [1] has been carried out which includes a broad overview of available condition monitoring techniques. Next to this inventory of condition monitoring systems, techniques and methods for data processing, the literature study also contains possible application areas within wind energy. This was done for typical sub systems in wind turbines. The literature study also includes a chapter covering the economical aspects of condition monitoring systems. However data are very limited, depending on the design and also changing rapidly due to development of specific systems.

2.1Condition Monitoring Techniques

The following techniques, available from different applications, which are possibly applicable for wind turbines, have been identified:

1.Vibration analysis

2.Oil analysis

3.Thermography

4.Physical condition of materials

5.Strain measurement

6.Acoustic measurements

7.Electrical effects

8.Process parameters

9.Visual inspection

10.Performance monitoring

11.Self diagnostic sensors

2.1.1Vibration Analysis

Vibration analysis is the most known technology applied for condition monitoring, especially for rotating equipment. The type of sensors used depend more or less on the frequency range, relevant for the monitoring:

-Position transducers for the low frequency range

-Velocity sensors in the middle frequency area

-Accelerometers in the high frequency range

-And SEE sensors (Spectral Emitted Energy) for very high frequencies (acoustic vibrations) Examples can be found for safeguarding of:

1.Shafts

2.Bearings

3.Gearboxes

https://www.360docs.net/doc/d46927582.html,pressors

5.Motors

6.Turbines (gas and steam)

7.Pumps

For wind turbines this type of monitoring is applicable for monitoring the wheels and bearings of the gearbox, bearings of the generator and the main bearing.

Signal analysis requires specialised knowledge. Suppliers of the system offer mostly complete systems which includes signal analysis and diagnostics. The monitoring itself is also often executed by specialised suppliers who also perform the maintenance of the components. The costs are compensated by reduction of production losses.

Application of vibration monitoring techniques and working methods for wind turbines differ from other applications with respect to:

-The dynamic load characteristics and low rotational speeds

In other applications, loads and speed are often constant during longer periods, which simplifies the signal analysis. For more dynamic applications, like wind turbines, the experience is very limited.

-The high investment costs in relation to costs of production losses.

The investments in conditions monitoring equipment is normally covered by reduced production losses. For wind turbines, especially for land applications, the production losses are relatively low. So the investment costs should for a important part be paid back by reduction of maintenance cost and reduced costs of increased damage.

2.1.2Oil analysis

Oil analysis may have two purposes:

-Safeguarding the oil quality (contamination by parts, moist)

-Safeguarding the components involved (characterisation of parts)

Oil analysis is mostly executed off line, by taking samples. However for safeguarding the oil quality, application of on-line sensors is increasing. Sensors are nowadays available, at an acceptable price level for part counting and moist. Besides this, safeguarding the state of the oil filter (pressure loss over the filter) is mostly applied nowadays for hydraulic as well as for lubrication oil.

Characterisation of parts is often only performed in case of abnormalities. In case of excessive filter pollution, oil contamination or change in component characteristic, characterisation of parts can give an indication of components with excessive wear.

2.1.3Thermography

Thermograhy is often applied for monitoring and failure identification of electronic and electric components. Hot spots, due to degeneration of components or bad contact can be identified in a simple and fast manner. The technique is only applied for of line usage and interpretation of the results is always visual. At this moment the technique is not interesting for on line condition monitoring. However cameras and diagnostic software are entering the market which are suitable for on-line process monitoring. On the longer term, this might be interesting for the generator and power electronics.

2.1.4Physical condition of materials

This type of monitoring is mainly focussed on crack detection and growth. Methods are normally off line and not suitable for on line condition monitoring of wind turbines. Exception might be the usage of optical fuses in the blades and acoustic monitoring of structures.

2.1.5Strain measurement

Strain measurement by strain gauges is a common technique, however not often applied for condition monitoring. Strain gauges are not robust on a long term. Especially for wind turbines, strain measurement can be very useful for life time prediction and safeguarding of the stress level, especially for the blades. More robust sensors might open an interesting application area. Optical fibre sensors are promising, however still too expensive and not yet state-of-the-art. Availability of cost effective systems, based on fibre optics can be expected within some years. Strain measurement as condition monitoring input will than be of growing importance.

2.1.6Acoustic monitoring

Acoustic monitoring has a strong relationship with vibration monitoring. However there is also a principle difference. While vibration sensors are rigid mounted on the component involved, and register the local motion, the acoustic sensors "listen" to the component. They are attached to the component by flexible glue with low attenuation. These sensors are successfully applied for monitoring bearing and gearboxes.

There are two types of acoustic monitoring. One method is the passive type, where the excitation is performed by the component itself. In the second type, the excitation is externally applied.

2.1.7Electrical effects

For monitoring electrical machines MCSA (Machine Current Analysis) is used to detect unusual phenomena. For accumulators the impedance can be measured to establish the condition and capacity.

For medium and high voltage grids, a number of techniques are available:

-Discharge measurements

-Velocity measurements for switches

-Contact force measurements for switches

-Oil analysis for transformers

For cabling isolation faults can be detected. These types of inspection measurements do not directly influence the operation of the wind turbines.

2.1.8Process parameters

For wind turbines, safeguarding based on process parameters is of course common practice. The control systems become more sophisticated and the diagnostic capabilities improve. However safeguarding is still largely based on level detection or comparison of signals, which directly result in an alarm when the signals become beyond predefined limit values. At present, more intelligent usage of the signals based on parameter estimation and trending is not common practice in wind turbines.

2.1.9Performance monitoring

The performance of the wind turbine is often used implicitly in a primitive form. For safeguarding purposes, the relationship between power, wind velocity, rotor speed and blade angle can be used and in case of large deviations, an alarm is generated. The detection margins

are large in order to prevent for false alarms. Similar to estimation of process parameter, more sophisticated methods, including trending, are not often used.

2.2Possibilities of application in wind turbines

In the previous chapter, the available techniques have been identified. The next step is to establish the applicability and desirability for wind turbines. The decision w.r.t. investments for condition monitoring provisions is based on the economical factors. The rate of return of the provisions is determined by the investment costs, the relevant failure characteristics, the cost savings of maintenance and damage and the reduction of production loss. For off shore wind application, the cost savings due to reduction of corrective maintenance will be the most important factor. When extra visit can be avoided or postponed to a regular visit, or when more damage can be prevented, considerable amounts of money can be saved.

2.2.1Rotor

Blades

Strain monitoring can be used for life time prediction. Methods are not yet "well developed" but there certainly is interest and potential for condition monitoring based on strain measurement. The measurement techniques and the necessary rotating interfaces, which push up the investments, are reasons that this type of monitoring is not often used. Techniques based on optical fibres are in development and will be suitable for commercial application within some years. Several parties work on this subject (Smart Fibres, FOS, Risoe, ECN, and some manufacturers.).

Vibration monitoring and acoustic emission are also interesting for condition monitoring of the blades. Acoustic emission can be used to detect failures in the blade.

2.2.1.2Pitch mechanism

Large turbines often have independent pitch control. Safeguarding is often realised by current measurement / time measurement and pitch angle differences. Trend analysis based on parameter estimation is not applied up to now, but might be an interesting possibility for condition monitoring.

2.2.2Nacelle

Gearbox and main bearing

Gearboxes are widely applied components in many branches of industry. Condition monitoring is more or less common practice. Despite all design effort, wind turbines often had en still have problems with gearboxes. So condition monitoring is of growing interest, because the costs of replacement are very high.

Condition monitoring techniques for gearboxes are:

1.Vibration analysis based on different sensors

2.Acoustic emission

3.Oil analysis

For vibration analysis, different types of sensors can be used. Most commonly used are acceleration sensors. Also displacement sensors can be used, which might be of interest for bearing operating at a low speed (main bearing).

Acoustic emission is another technique, based on higher frequencies. For vibration analysis the frequencies related to the rotational speeds of the components are of interest. For acoustic emission higher frequencies are considered, which give an indication of starting defects. The effects normally attenuate after short period.

Oil analysis is especially of interest when defects are identified, based on one of the previous techniques and is of use for further diagnostics. Based on characterisation of parts and component data, diagnosis can be approved. This simplifies the repair action.

Lubrication of oil itself can also be a source for increasing wear. There exist a strong relationship between the size and amount of parts and the component life time. Also moist has a strong reducing effect on the lubrication properties. Safeguarding of the filters and on line part counting and moist detection can help to keep the oil in an optimal condition. Costs resulting from oil replacement as well as from wear of the components can be reduced by an optimal oil management.

2.2.2.2Generator

The generator bearing can also be monitored by vibration analysis techniques, similar to the gearbox. Apart from this, the condition of the rotor and stator windings can also be monitored by the temperatures. Due to the changing loads, trend analysis based on parameter estimation techniques will be necessary for early detection of failures.

2.2.2.3Hydraulic system

The hydraulic system for pitch adjustment is the most critical. However this is not relevant for the GE-turbines (electrical pitch adjustment). Condition monitoring of hydraulic systems is very similar to other applications because intermittent usage is common practice.

2.2.2.4Yaw system

Although the yaw system is rather failure prone, condition monitoring is difficult because of the intermittent usage. The system is only operating during a longer period during start-up and re-twisting. However the operational conditions during these actions are certainly not representative. The loads are relatively low, because the turbine is not in operation in this situation. Apart from this, the lubrication conditions are not constant.

2.3Economical Aspects

Because financial margins are very small for wind turbines, economic aspects play a very important role. The installed power per wind turbine is relatively small. Wind turbines are available in the order of 1 MW, while other power generation units are in the range of 10 up to several hundreds of MW's. So the production loss due to failures are very small for wind turbines, compared with other units. On the other side, due to the low installed power per wind turbine, the investment level for condition monitoring system is relatively high. So from economical point of view, the margins for investments are very small for on shore application. For offshore application, the situation is quite different. Due to the restricted accessibility of wind turbines for maintenance, the waiting and repair periods, following a failure will be

considerably longer, which implies increasing production losses and repair costs. Together with decreasing prices of condition monitoring systems, the economical break even will decrease significantly.

A condition monitoring systems, based on vibration analysis is in the range of €10000 to €15000. Although the robustness with respect to failure detection/forecasting is certainly not yet demonstrated, the level of investment makes application feasible.

On line oil analysis is still very expensive. However these kind of sensors are relatively new, which implies that reduction of prices is likely over the coming years. Similar to vibration monitoring oil analysis is also focussed on one of the most critical wind turbine components, being the gearbox.

Apart from the condition monitoring systems, based on vibration analysis and existing applications, there are also techniques which can specially developed for wind turbines. One of the techniques, based on general (available) measurement signal, require specific algorithm development and verification. However, it is expected that these kind of algorithms can be implemented in the control system of the turbine, which implies that no extra hardware investment is involved.

Condition monitoring of the blades is rather new, and very expensive at this moment. The measurement techniques are based on optical fibres. The sensors are very expensive, however large series and automation of the production process can cause a dramatic decrease of production costs. Also at the side of the instrumentation, developments are necessary with respect to cost reduction and improvement of robustness. Developments are still necessary for algorithms as well as for the instrumentation and sensors.

2.4Conclusions

Before condition monitoring can be applied successfully for wind energy, at least the following items should be solved

Improvement of safeguarding functions

Wind turbine control systems incorporate an increasing functionality. Some of the functions come very close to Condition monitoring. With relatively low costs, some more intelligence can be added, which makes early fault detection based on trend analysis possible. (Pitch mechanism, brake, yaw system, generator).

Development of global techniques

Apart from safeguarding, trending of wind turbine main parameters (power, pitch angle, rotational speed, wind velocity, yaw angle) can give global insight in the operation in the turbine. It may be possible to detect that "something might be wrong". Dirt on the blades has a strong reducing effect on the power production, which can also be detected by trend analysis. Adaptation of existing systems

In other industries, condition monitoring provisions are normally separate systems, apart from the machine control and safe guarding functions. The monitoring is often focussed on a very limited number of aspects. For wind turbines however, the system to be monitored is rather complex and the margins for investments are small. The number of systems is very high. So when existing systems are used, the adaptation should not only be focussed on the dynamic load behaviour, but also on streamlining the system and integration.

Information mapping

Offshore wind turbines normally operate in a park, which is remote controlled from a central control room. Because a great number of turbines is controlled from the central facility,

information should be processed and filtered before being reported to the operator and maintenance planning.

When applying condition monitoring techniques in wind turbines, the following two pitfalls should be considered.

Application of existing techniques

Only adaptation of existing systems is often not sufficient to make them suitable for wind turbines. Although the systems will "function" of course, the effectiveness can only be determined on the long term.

Robustness of secondary systems

Manufacturers often have an aversion to a large amount of sensors. Failure of condition monitoring functions may never result in turbine stop. Operational decisions are made by the control system or by the operator.

From the literature study, the following overall developments in condition monitoring have been recognised.

Oil filtering and monitoring

There is an increasing interest for oil filtering and diagnosis. There is no doubt about the importance of adequate filtering and the price of sensors is decreasing. Troubles with gearboxes and pressure from the side of insurance companies have enlarging effects.

Blade monitoring

There is an increasing interest in blade monitoring. However, blade instrumentation is still very expensive. However there are several developments going on at this moment, in which developers in instrumentation as well as wind turbine manufacturers and blade manufacturers are involved.

Standardisation of interfaces / control system versus CM-instrumentation

Condition monitoring is a specialism, which requires knowledge and experience. Signal processing and interpretation are often outsourced by firms, who are also involved in the maintenance. These firms need access to the systems involved. Standardisation in the field of communication and interfacing is of increasing importance in order to accommodate these systems.

3.SELECTED SUB-SYSTEMS, COMPONENTS AND CM-TECHNIQUES

3.1Global condition monitoring techniques

Apart from the applied condition monitoring techniques on sub system level (gearbox, pitch mechanism, e.s.o.) there is already a lot of information available in the wind turbine. Normally this information is only used at the level of safeguarding. Exceeding of the alarm levels often simply results in a wind turbine shut down and waiting for remote restart or repair. By application of more advanced methods of signal analysis, focussed on trends of representative signals or combination of signals, significant changes in turbine behaviour can be detected at an early stage. Because the approach is based on general turbine parameters, the information will also be of a global nature, so specific diagnostics cannot be expected.

Application of this approach does not require additional investments in hardware. Only development costs are involved. Although it cannot be expected, that the results will be very specific, information which give an indication that something might be wrong can already be very valuable. In literature, some references have been found however, concrete results are not available. This means that long term development will be necessary.

In this chapter, also the application of “model based condition monitoring” will be discussed. Model based condition monitoring is suitable for non-stationary operation. It will be explained later on.

3.2Pitch mechanism

The pitch mechanism is one of the most vulnerable systems in a wind turbine. Following the development of larger wind turbines, the importance of the pitch mechanism will increase because:

1.The pitch mechanism is part of the safety system for large wind turbines

2.Pitch adjustment is of increasing importance for power control and load reduction

provisions

Nowadays condition monitoring of this system is restricted to the individual performance of the servo motors themselves at the level of detection of maximum current. However model based condition monitoring of all three servo-systems is a promising possibility in this situation. Model based condition monitoring is suitable for non-stationary operation. The process I/O signals are used for diagnosis of the system, see Fig. 3.1.

Fig 3.1:Principle of model based fault detection

The diagnosis can be based on the residual of the process and estimator output signals (see Fig.

3.2). In this situation, a constant model is used. The difference between the output of the system and the output of the model can be monitoring. Trend analysis of this residu can be used to detect changing characteristics of the system.

Fig. 3.2:Fault estimation based in residual

Another possibility of model based fault detection is continuous estimation of the model parameters, based on the measured I/O values and to monitor the trends in the paramaters (see figure 3.3). The performance strongly depends on the accuracy of the estimation procedure. The number of I/O signals and the measurement accuracy of these signals are of importance to be able to detect changes in trends in an early stage.

Fig. 3.3:Fault estimation based on model parameters

Because the application of this technique is very specific for this application, the algorithms should be developed. This requires specific knowledge of the system, the control and model development. On the other side the application of the technique in a real wind turbine does not or hardly require addition hardware and sensors.

3.3Gear box

The importance of monitoring the condition of the gearbox is obvious by now. Because there already exists a lot of experience in this field. Also for wind energy, specialised companies supply special systems adapted for wind turbines (SKF, Pruftechnik, Gramm&Juhl, Schenck).

Fig. 3.4:Example of fault detection based on FFT (source: Prueftechnik)

The fault detection is often based on frequency analysis and level detection for certain frequency bands. Based on the level of amplitudes, status signals can often be defined and generated. Diagnosis is often done by the supplier of the system or of the gearbox, because specialised knowledge is required for signal interpretation.

The effectiveness of these systems is yet not evident. Due to the non-stationary operation, it appears to be difficult to develop effective algorithms for early fault detection, especially for variable speed operation. Practical experience builds up very slowly, because component degeneration is fortunately a slow process, and additional information about turbine loads and operational conditions are only fragmentarily available.

3.4Main bearing

The situation with the main bearing is identical to the gearbox. Along with condition monitoring of the gearbox, most of the systems also monitor the main bearing and the generator bearings.

3.5Sound registration

During the project, it was decided to cancel the condition monitoring based of sound/noise. From the manufacturer point of view it appeared difficult to define a development target for this item. In practical situation, maintenance personnel can often well observe what is wrong. This is based on long experience, and it will be very difficult to extract this information from noise signals. Furthermore, the sound is heavily disturbed by the background and also strongly dependent on the operational conditions of the turbine.

3.6Blade monitoring

There are already some practical examples of blade monitoring. LM for instance has a system available, which operates completely, stand-alone and which is focussed on detectiing excessive vibration levels and sending messages to the company. The system uses acceleration sensors. The system has mainly been used for prototyping but was intended to be widely applied for stall regulated turbines in the 600 kW range.

NGUp has a sensor available, which was developed by blade manufacturer Aerpac. This sensor

Fig. 3.5:Principle of fibre optic blade monitoring

Although the LM system as well as the Aerpac sensor already have a track record, application of fibre optic measurement techniques are foreseen as the most promising.

4.INSTRUMENTATION OF THE LAGERWEY 50/750 Initially, the prototype of the Lagerwey 50/750 (see Fig. 4.1)was chosen for the execution of the measurement programme. Important advantage of this turbine at that time was the fact that this turbine was already instrumented to carry out load measurements.. At the beginning of the project, the turbine was a prototype and it was expected that after one year of operation, the configuration should remain stable, and that the turbine should stay in operation as a production turbine. Initially, the fact that the turbine was a prototype, only seemed to have advantages. There was a close collaboration with the manufacturer, which makes the instrumentation easier, the design data was accessible, and the turbine could be adjusted very easily without too many consequences for the revenue losses.

Fig. 4.1:Lagerwey LW 50/750 turbine

An important disadvantage of the choice of this turbine design with respect to a general condition monitoring project was the specific design. For condition monitoring the gearbox is probably the most vulnerable component, while the Lagerwey turbine is a direct drive machine. Also the main bearing is specific for this design. So for this turbine the condition monitoring aspect were mainly focussed on the pitch mechanism, the main bearing and general detection mechanisms. The disadvantages were recognised in the beginning of the project but they seemed minor as compared to the advantages mentioned above.

The main bearing is a critical component for this design. This bearing is not a normal roller bearing, but a 4 point ring bearing with a large diameter. Rothe Erde, the supplier of the bearing has also delivered a vibration sensor which was also incorporated in the measurement system. Besides the vibration, also the bearing temperature was monitored.

Wind资讯金融终端板块分析使用说明

Wind 资讯金融终端 板块分析使用说明 上海万得信息技术有限公司 Shanghai Wind Information Co., Ltd. 地 址: 上海市浦东新区福山路33号建工大厦9楼 邮编Zip: 200120 电话T el: (8621) 6888 2280 传真Fax: (8621) 6888 2281 Email: sales@https://www.360docs.net/doc/d46927582.html, https://www.360docs.net/doc/d46927582.html, ——中国金融数据及解决方案首席服务商

目录 1板块分析概述 (1) 1.1板块数据浏览器 (1) 1.2板块行情序列 (2) 1.3板块财务纵比 (3) 2板块分析使用操作 (4) 2.1板块数据浏览器使用操作 (4) 2.1.1模块入口 (4) 2.1.2指标选择 (5) 2.1.3板块选择 (5) 2.1.4输出结果操作 (6) 2.1.5功能键说明 (6) 2.2板块行情序列使用操作 (7) 2.2.1模块入口 (7) 2.2.2指标选择 (7) 2.2.3板块选择 (7) 2.2.4输出结果操作 (7) 2.2.5功能键说明 (8) 2.3板块财务纵比使用操作 (8) 2.3.1模块入口 (8) 2.3.2指标选择 (8) 2.3.3板块选择 (8) 2.3.4输出结果操作 (8) 2.3.5功能键说明 (8) 3公司介绍 (9)

1板块分析概述 板块分析是用于行业、指数、自定义板块等总体指标的计算,如计算全部A股的市盈率等,还可以实现总体指标的时间序列分析、横向对比等功能。 1.1板块数据浏览器 板块数据浏览器主要用于市场板块(全部A股、上证180、上证50、沪深300等)、行业板块(GICS行业、申万行业、证监会行业等)等相应板块的截面数据的提取,如板块的行情指标、财务指标、估值指标等。

Wind资讯金融终端行情序列使用说明

Wind 资讯金融终端 行情序列使用说明 上海万得资讯科技有限公司 Shanghai Wind Information Co., Ltd. 地 址: 上海市浦东新区福山路33号建工大厦9楼 邮编Zip: 200120 电话Tel: (8621) 6888 2280 传真Fax: (8621) 6888 2281 Email: sales@https://www.360docs.net/doc/d46927582.html, https://www.360docs.net/doc/d46927582.html, ——中国金融数据及工具首席服务商

目录 1行情序列简介 (1) 2进入“行情序列”模块 (1) 3行情序列使用说明 (2) 3.1选择证券 (3) 3.2选择指标 (6) 3.3选择时间 (7) 3.4选择格式 (8) 3.5选择输出方式 (9) 3.6导出数据 (11)

1行情序列简介 行情序列是专用的行情数据导出工具。用户可以定义各种要素进行数据导出,包括证券类型、行情指标、时间范围、时间单位、数据组织方式、数据文件格式等。 股票行情指标包括:开盘价、收盘价、最高价、最低价、涨跌、涨跌幅、成交量、PE 市盈率、PB市净率、总股本、流通股本、总市值等。 基金行情指标包括:开盘价、收盘价、最高价、最低价、涨跌、涨跌幅、成交量、单位净值、累计净值等。 指数行情指标包括:开盘价、收盘价、最高价、最低价、涨跌、涨跌幅、成交金额等。2进入“行情序列”模块 可以通过首页“股票>>多维数据>>行情序列”或者菜单“股票>>多维数据>>行情序列”进入该模块。

3行情序列使用说明 行情序列的使用可以分为六个步骤:选择证券、选择指标、选择时间、选择格式、选择输出方式、导出数据。

Wind资讯金融终端快讯(2011年6月)

Wind资讯金融终端2011 (2011年6月升级快讯) 、

目录 1本期总结 (2) 1.1改进功能列表 (3) 2WIND资讯互动金融社区 (4) 3股票改进 (5) 3.1股票资金流向 (5) 3.2股票技术指标增强 (6) 4债券改进 (7) 4.1C HINA MONEY 实时收益率曲线 (7) 4.2风险缓释工具(CRM) (8) 4.3香港人民币债券(CNHB) (9) 5★期货活跃合约 (10) 5.1期货活跃合约 (10) 5.2全球商品概览(8)改进 (11) 6基金FACTSHEET (12) 7指数改进 (13) 7.1增加上证\深圳指数综合屏 (13) 7.2增加中证\巨潮指数综合屏 (14) 7.3增加恒生指数综合屏 (15) 8实时滚动新闻 (16) 9★EDB改进--云数据管理 (17) 9.1EDB改进—模板功能加强 (18) 9.2EDB改进—计算功能加强 (18) 9.3EDB改进—图形功能加强 (19) 9.4EDB改进—快捷键功能增强 (19) 10EXCEL插件:交易函数+更多模板 (20) 11多屏功能 (21) 【公司介绍】 (22)

1本期总结 春夏之交的6月,Wind资讯金融终端迎来了2011年的第一次升级,暨2011版发布,我们期待全新的金融终端能给您带来愉悦的使用体验。通过本次升级,我们在股票模块、债券模块、期货模块、基金模块、新闻情报、宏观行业、EXCEL插件、等方面都有着力提升。

1.1 改进功能列表

2Wind资讯互动金融社区 【Wind资讯金融风,风从东方来】 【新锐,新知,新体验】 金融之风正从东方吹来,Wind资讯乘上移动互联新媒体,推出全新体验的Wind金融风,实现我们对金融资讯的新锐、新知的理解; ●实时更新内容,首页NEW导航,点击可直接跳转 ●左键点击自助翻页 ●左键拖放,想看哪,翻哪 ●键盘“←→”,便捷翻页 ●点击标题,新闻、培训报名、研究报告全搞定

Wind资讯产品简介(WFT、WAT、WET)

Wind 资讯产品简介 (WFT 、WAT 、WET ) 上海万得信息技术股份有限公司 Shanghai Wind Information Co., Ltd. 地 址: 上海市浦东新区福山路33号建工大厦9楼 邮编Zip: 200120 电话T el: (8621) 6888 2280 传真Fax: (8621) 6888 2281 Email: sales@https://www.360docs.net/doc/d46927582.html, https://www.360docs.net/doc/d46927582.html, ——中国金融数据及解决方案首席服务商

目录 1公司简介 (1) 2产品报价 (1) 3产品介绍 (2) 3.1Wind资讯金融终端(WFT) (2) 产品简介 (2) 产品截图 (3) 功能介绍 (3) 3.2Wind资讯理财终端(WAT) (6) 产品简介 (6) 产品截图 (6) 功能介绍 (7) 3.3Wind资讯经济数据库(WET) (8) 产品简介 (8) 产品截图 (9) 功能介绍 (9) 4服务、增值 (9)

1 公司简介 上海万得信息技术股份有限公司()是中国大陆领先的金融数据、信息和软件服务企业,总部位于上海陆家嘴金融中心。 在国内市场,Wind资讯的客户包括超过85%的中国证券公司、基金管理公司、保险公司、银行和投资公司等金融企业;在国际市场,已经被中国证监会批准的合格境外机构投资者(QFII)中75%的机构是Wind资讯的客户。同时国内多数知名的金融学术研究机构和权威的监管机构也是我们的客户,大量中英文媒体、研究报告、学术论文等经常引用Wind资讯提供的数据。 在金融财经数据领域,Wind资讯已建成中国最完整、最准确的以金融证券数据为核心一流的大型金融工程和财经数据仓库,数据内容涵盖股票、基金、债券、外汇、保险、期货、金融衍生品、现货交易、宏观经济、财经新闻等领域,新的信息内容在第一时间进行更新以满足机构投资者的需求。 针对金融业的投资机构、研究机构、学术机构、监管部门机构等不同类型客户的需求,Wind资讯开发了一系列围绕信息检索、数据提取与分析、投资组合管理应用等领域的专业分析软件与应用工具。通过这些终端工具,用户可以7x24x365从Wind资讯获取到及时、准确、完整的财经数据、信息和各种分析结果。 精于数据,以数据为起点,Wind资讯紧密跟随金融市场日新月异的发展,不断向新的领域发展,新的产品和服务战略不断在延伸。 2 产品报价

Wind金融数据库介绍

W i n d金融数据库介绍标准化管理处编码[BBX968T-XBB8968-NNJ668-MM9N]

——中国金融数据及解决方案首席服 Wind中国金融数据库介绍上海万得信息技术有限公司 Shanghai Wind Information Co., Ltd. 地址: 上海市浦东新区福山路33号建工大厦9楼 邮编Zip: 200120 电话Tel: (8621) 6888 2280 传真Fax: (8621) 6888 2281 Email 目录

1为什么选择Wind中国金融数据库 数据全面:Wind资讯作为中国最领先的金融数据服务商,经过十年的 积累,已建成国内最完整、最准确的以金融证券数据为核心的一流大 型金融工程和财经数据仓库,数据内容涵盖股票、基金、债券、外 汇、保险、期货、金融衍生品、现货交易、宏观经济、财经新闻等领 域。收集了所有金融品种完整的(包括上市前和上市后)数据,尤其 是推出了很多独具特色的深度加工数据,为其他公司所不具备。万得 数据库的全面完整已经得到了中国证券行业高端专业人士的公认。 数据准确:Wind资讯视数据的准确为生命,%的准确率倚靠科学的核查 方法和先进的管理手段得以保证。从核查方法来看,除了传统的人工 校对外和数据库约束条件外,更多地利用各种平衡公式和经验公式对 数据进行合法性校验、一致性校验和统计校验。第一层是合法性校 验,即表内校验,不符合公式的不得入库,起到事前控制的作用;第 二层是一致性校验,即表间校验,每日所有数据处理完毕后,找出不 同表中相互矛盾的数据,并制作出报告,提交相关人员解决,起事后 稽核的作用;第三层是统计校验,即从数据库中提取大量数据制作专 题报表,与权威机构的公布报表核对,从中发现问题,如每年年报结 束后的综合统计。从管理手段来看,Wind资讯成立质量检验部门,选 派专人负责数据核查工作,通过一系列的激励措施,使数据质量始终 保持在很高的水准之上。更重要的是,目前有1500家机构每天实时对 Wind中国金融数据库进行使用和校验。 更新及时:为满足机构投资者投资决策和学术机构实证研究的需要, Wind资讯一直视及时性为公司发展的基石,所有数据在第一时间进行

关于采购wind资讯金融终端的申请

关于购买Wind资讯金融终端的请示 尊敬的领导: 您好! 针对Wind资讯金融终端,我部及进行了为期近2个星期的试用,并进行了深入调查、分析比较。我们认为Wind资讯金融终端从内容的及时、准确、完整;使用的便利性和数据跟踪服务等方面存在比较明显的优势;为我们查找数据、债券交易、信息统计、分析研究、风险控制提供了极大便利,它集国内证券市场股票、基金、债券、指数、期货、贵金属数据、宏观和区域经济数据、行业数据、全球金融市场重要数据、新闻情报于一个平台,极大的提高了我们的工作效率,对在投资、发展等领域有非常大的帮助。经过我部充分讨论,一致认为有必要采购Wind资讯金融终端。 一、Wind资讯简介 万得资讯(Wind资讯)是中国大陆领先的金融数据、信息和软件服务企业,总部位于上海陆家嘴金融中心。Wind资讯始终专注于整合与资本市场密切相关的信息资源,为政府部门(中国人民银行、财政部、中国证监会、中国银监会、中国保监会、上海证券交易所、深圳证券交易所、国资委、发改委等各大部委)、上市公司、拟上市公司及大型企业集团了解资本市场而提供的辅助决策工具。目前,在企业市场,中国前500强的企业中有将近2/3的大型企业是万得的正式客户。 万得资讯同时是上海市政府重点扶持的软件和信息服务业龙头企业,在上海构建国际金融中心的进程中,肩负着维护国家金融信息安全的重要责任。 万得资讯以自己多年来积累的经济金融信息数据库优势,在我行信息化建设中,也能起到不可或缺的重要作用。 二、Wind资讯金融终端产品特点 1、债券模块特色: A、拥有最齐全的中国银行间债券市场的报价数据,从当日报价与到历史报价查询与统计,同时还提供债券交易员信息查询功能。

Wind金融数据库介绍

W i n d金融数据库介绍 This model paper was revised by the Standardization Office on December 10, 2020

——中国金融数据及解决方案首席服 Wind中国金融数据库介绍上海万得信息技术有限公司 Shanghai Wind Information Co., Ltd. 地址: 上海市浦东新区福山路33号建工大厦9楼 邮编Zip: 200120 电话Tel: (8621) 6888 2280 传真Fax: (8621) 6888 2281 Email 目录

1为什么选择Wind中国金融数据库 数据全面:Wind资讯作为中国最领先的金融数据服务商,经过十年的 积累,已建成国内最完整、最准确的以金融证券数据为核心的一流大 型金融工程和财经数据仓库,数据内容涵盖股票、基金、债券、外 汇、保险、期货、金融衍生品、现货交易、宏观经济、财经新闻等领 域。收集了所有金融品种完整的(包括上市前和上市后)数据,尤其 是推出了很多独具特色的深度加工数据,为其他公司所不具备。万得 数据库的全面完整已经得到了中国证券行业高端专业人士的公认。 数据准确:Wind资讯视数据的准确为生命,%的准确率倚靠科学的核查 方法和先进的管理手段得以保证。从核查方法来看,除了传统的人工 校对外和数据库约束条件外,更多地利用各种平衡公式和经验公式对 数据进行合法性校验、一致性校验和统计校验。第一层是合法性校 验,即表内校验,不符合公式的不得入库,起到事前控制的作用;第 二层是一致性校验,即表间校验,每日所有数据处理完毕后,找出不 同表中相互矛盾的数据,并制作出报告,提交相关人员解决,起事后 稽核的作用;第三层是统计校验,即从数据库中提取大量数据制作专 题报表,与权威机构的公布报表核对,从中发现问题,如每年年报结 束后的综合统计。从管理手段来看,Wind资讯成立质量检验部门,选 派专人负责数据核查工作,通过一系列的激励措施,使数据质量始终 保持在很高的水准之上。更重要的是,目前有1500家机构每天实时对 Wind中国金融数据库进行使用和校验。 更新及时:为满足机构投资者投资决策和学术机构实证研究的需要, Wind资讯一直视及时性为公司发展的基石,所有数据在第一时间进行

Wind资讯金融终端条件选股使用说明

Wind 资讯金融终端 条件选股使用说明 上海万得资讯科技有限公司 Shanghai Wind Information Co., Ltd. 地 址: 上海市浦东新区福山路33号建工大厦9楼 邮编Zip: 200120 电话Tel: (8621) 6888 2280 传真Fax: (8621) 6888 2281 Email: sales@https://www.360docs.net/doc/d46927582.html, https://www.360docs.net/doc/d46927582.html, ——中国金融数据及工具首席服务商

目录 1条件选股概述 (1) 1.1什么是条件选股 (1) 1.2条件选股界面 (1) 1.3快捷操作 (1) 2如何使用条件选股 (2) 2.1基本步骤 (2) 2.2可选操作 (4) 2.3指标管理 (5) 2.3.1如何创建自定义指标 (6) 2.3.2如何使用自定义指标 (14)

1条件选股概述 1.1什么是条件选股 条件选股是最强大的智能选股引擎。 用户可在系统板块或用户自定义板块的范围内,针对3000余项系统提供的指标或自定义指标进行参数设置,筛选出符合条件的证券品种。 相应的筛选结果可以保存为自定义板块;筛选条件可保存到“我的方案”中,便于重复调用。 针对基金,相应的筛选模块称为“基金筛选”,操作方法与“条件选股”相似。 1.2条件选股界面 可以概括为四个区域,两排功能按钮。 1.3快捷操作 通过功能按钮可实现快捷操作。

2如何使用条件选股 2.1基本步骤 进行条件选股可概括为五个基本步骤:具体操作详见下图。 第一步:设置待选范围 第二步:选择指标 第三步:设置指标参数 第四步:设置条件表达式 第五步:执行选股 第一步:设置待选范围——通过选择板块的方式设置待选范围 可以勾选多个板块。 第二步:选择指标——(选择进行筛选的指标 指标支持拼音查找指标的功能;还可通过鼠标右键 点击指标树,查看相应指标的详细帮助,

WIND咨询金融终端产品分析报告

WIND咨询金融终端产品分析报告 一、WIND公司与产品介绍 1、公司简介 Wind资讯是中国大陆领先的金融数据、信息和软件服务企业,总部位于上海陆家嘴金融中心。在国内市场,Wind资讯的客户包括超过90%的中国证券公司、基金管理公司、保险公司、银行和投资公司等金融企业;在国际市场,已经被中国证监会批准的合格境外机构投资者(QFII)中75%的机构是Wind资讯的客户。 在金融财经数据领域,Wind资讯已建成国内最完整、最准确的以金融证券数据为核心一流的大型金融工程和财经数据仓库,数据内容涵盖股票、基金、债券、外汇、保险、期货、金融衍生品、现货交易、宏观经济、财经新闻等领域。Wind资讯开发了一系列围绕信息检索、数据提取与分析、投资组合管理应用等领域的专业分析软件与应用工具。通过这些终端工具,用户可以从Wind资讯获取到及时、准确、完整的财经数据、信息和各种分析结果。 2、公司主要产品和项目介绍 2.1公司开发的主要产品 2.1.1 Wind信息导航系统 1996年证券行业内最早采用HTML技术,独立开发的中文浏览器。首开信息服务领域先河。 2.1.2 WFA财务分析系统 2000年发布。直接浏览上市公司年报、中报、首季报、三季报中的原始财务数据,并提供财务数据进行定基比分析、环比分析、结构比分析和杜邦分析,提供对财务数据的预警和调整功能。 2.1.3 https://www.360docs.net/doc/d46927582.html,信息终端 2003年发布。https://www.360docs.net/doc/d46927582.html,利用微软最新.NET技术借鉴国外布隆博格、路透优点,推出的一个在线实时金融信息终端,为用户提供无缝集成的行情报价、金融数据、财经信息、分析工具、组合管理等功能的综合性金融服务平台。 2.1.4 Wind.EDB金融数据库 Wind金融数据库是本公司自主研发设计、自主采集加工的大型专业数据库,是目前国内最大最完整,应用最广泛的以证券为核心的金融数据库,收录了中国证券市场十年来的所有上市公司公告、上市公司数据、股票基金债券数据和财经法规,建国以来的所有国内宏观经济数据,以及一部分海外经济数据。 2.2公司承建过的主要相关项目 Wind资讯具有丰富的客户定制项目实施经验,先后为行业内多家客户提供不同种类系统的开发。 2001年为银河证券研究中心开发完成内部网系统,主要用于进行研究成果的管理、研究人员绩效考核、网站信息的自动发布等。 2002年为平安保险投资管理中心开发完成投资决策辅助支持系统,主要用于对基金和

关于采购wind资讯金融终端的申请

关于采购wind资讯金融终端的申请

Wind资讯简介关于购买 Wind资讯金融终端的请示 尊敬的领导: 您好! 针对Wind资讯金融终端,我部及进行了为期近2个星期的试用,并进行了深入调查、分析比较。我们认为Wind资讯金融终端从内容的及时、准确、完整;使用的便利性和数据跟踪服务等方面存在比较明显的优势;为我们查找数据、债券交易、信息统计、分析研究、风险控制提供了极大便利,它集国内证券市场股票、基金、债券、指数、期货、贵金属数据、宏观和区域经济数据、行业数据、全球金融市场重要数据、新闻情报于一个平台,极大的提高了我们的工作效率,对在投资、发展等领域有非常大 的帮助。经过我部充分讨论,一致认为有必要采购Wind资讯金融终端。 万得资讯(Wind资讯)是中国大陆领先的金融数据、信息和软件服务企业,总部位于上海陆家嘴金融中心。Wind资讯始终专注于整合与资本市场密切相关的信息资源,为政府部门(中国人民银行、财政部、中国证监会、中国银监会、中国保监会、上海证券交易所、深圳证券交易所、国资委、发改委等各大部委)、上市公司、拟上市公司及大型企业集团了解资本市场而提供的辅助决策工具。目前,在企业市场,中国前500强的企业中有将近2/3的大型 企业是万得的正式客户。 万得资讯同时是上海市政府重点扶持的软件和信息服务业龙头企业,在上海构建国际金融中心的进程中,肩负着维护国家金融信息安全的重要责任。 万得资讯以自己多年来积累的经济金融信息数据库优势,在我行信息化建设中,也能起到不可或缺的重要作用。 二、Wind资讯金融终端产品特点 1、债券模块特色: A、拥有最齐全的中国银行间债券市场的报价数据,从当日报价与到历史报价查询与统计, 同时还提供债券交易员信息查询功能 B、提供中国债券实时行情,包括“上交所、深交所、银行间债券市场”的数据,涵盖“国债、企业债、金融债、可转债、央行票据、短期融资券、资产支持证券、回购”等所有

万得资讯金融终端,卖给最需要的您!

WIND资讯金融终端,您值得拥有! 广告词: 万得WIND资讯金融终端,炒股必备,全国90%的机构专用投资软件,国内最好的炒股软件,你值得拥有。 让个人拥有机构版WIND金融终端,打破信息不平衡。 WIND资讯对股票信息的研究,不是一般软件(如,大智慧)所能比的,详细,准确。 本人拥有WIND官方销售的各种软件,如果有需要,请联系本人,价格远低于其公司销售价格。 WIND金融终端在万得资讯公司是不出售给个人的,本人拥有特殊机构拥有的号,不绑定机器,可以随地登录,如果你确实需要请加我,保证和机构所需要的功能一样,但是保证物超所值,个人QQ:1 7 4 3 7 8 5 7 9。 声明:需要的加我,非常需要的加我,认为我是骗子的不要加我,我没有那么多时间解释,保证物超所值! 万得资讯(Wind资讯)介绍: 万得资讯(Wind资讯)介绍是中国大陆领先的金融数据、信息和软件服务企业,总部位于上海陆家嘴金融中心。 在国内市场,Wind资讯的客户包括超过80%的中国证券公司、基金管理公司、保险公司、银行和投资公司等金融企业;在国际市场,已经被中国证监会批准的合格境外机构投资者(QFII)中60%的机构是Wind资讯的客户。同时国内多数知名的金融学术研究机构和权威

的监管机构也是我们的客户,大量中英文媒体、研究报告、学术论文等经常引用Wind资讯提供的数据。 在金融财经数据领域,Wind资讯已建成国内最完整、最准确的以金融证券数据为核心一流的大型金融工程和财经数据仓库,数据内容涵盖股票、基金、债券、外汇、保险、期货、金融衍生品、现货交易、宏观经济、财经新闻等领域,新的信息内容在第一时间进行更新以满足机构投资者的需求。 针对金融业的投资机构、研究机构、学术机构、监管部门机构等不同类型客户的需求,Wind资讯开发了一系列围绕信息检索、数据提取与分析、投资组合管理应用等领域的专业分析软件与应用工具。通过这些终端工具,用户可以7x24x365从Wind资讯获取到及时、准确、完整的财经数据、信息和各种分析结果。 精于数据,以数据为起点,万得资讯紧密跟随金融市场日新月异的发展,不断向新的领域发展,新的产品和服务战略不断在延伸。 个人联系方式 :QQ:1 7 4 3 7 8 5 7 9 电话:1 5 0 8 6 9 9 6 5 8 7(咨询前,请先短信联系) E-MAIL:174378579@https://www.360docs.net/doc/d46927582.html,

Wind资讯金融终端主要功能模块介绍

Wind资讯金融终端主要功能模块介绍 ?研究报告 Wind资讯目前与150余家国内外的主流研究机构有合作,实时发布这些机构的最新研究成果,支持全文检索,可以快速检索到所需内容。通过行业研报可以快速定位到“医疗”子行业,全面了解行业最新发展概况,同时研报平台中提供了大量海外研究机构撰写的研究报告,内容更丰富。 ?3C会议 Wind资讯目前与多家国内外的主流研究机构有合作,开展3C电话会议,第一时间分析当前宏观、行业等各个主体研究,支持全文检索,可以快速检索到所需内容。客户可以及时在线参会提问,也可以看历史会议记录。

?公司公告

公司公告每30s更新一次,通过侧边栏可以定位到“通信”子栏目,行业内所有上市公司(包括新三板上市)的公告都可以快速找到,所有信息支持下载和导出。 ?深度资料 深度资料目前涵盖了上市公司股票、基金、债券、商品、指数等所有交易品种。针对于上市公司,可以看到“公司资料”、“重要股东”、“交易数据”、“财务数据”、“财务分析”、“同业比较”等多维度数据,方便上市公司进行市值管理,同时和行业内其他公司进行比较。F9深度资料,新增关系网功能,一图理清各类关系。 ?行业中心

行业中心中有关于“通信”行业的详细介绍,包括产业目前概况、行业细分的“通信设备”和“电信业”现状等数据,同时对行业内的上市公司做了整理,可以查看到行业整体财务数据以及各上市公司的分布情况等信息。 ?财务纵比 通过财务纵比,可以导出多只上市公司股票的多报告期财务数据,方便对上市公司的财务数据进行比较和监控。终端同时支持板块之间的财务数据比较,快速生成图形,各股票以及板块的基本面情况一目了然。 ?数据浏览器

Wind资讯金融终端学生版免费通知

Wind资讯金融终端学生版免费通知 大家好: Wind资讯是中国金融信息服务行业的领导者,致力于为金融专业人士提供准确、及时、完整的财经资讯信息和交流平台,客户涵盖全球知名高等学府、政府金融监管机构、银行与金融机构体系、世界顶级咨询公司、审计与评估机构、著名跨国企业、媒体等超过10,000家。 为立体化提升高校财经教学与科研水平,全方位提高学生实战能力,多角度促进产学研对接,Wind资讯特针对高校学生免费推出“财经学子阳光计划”(详情介绍:https://www.360docs.net/doc/d46927582.html,/University/ElitePlan.html),欢迎各位同学前去了解。 一、产品定位: 整合金融机构高端客户资源,帮每位在校学生找到来自机构的职业导师,提高财经专业学子的实战能力,让每位同学获得满意的实习机会和工作岗位。 二、5大功能: ●模拟实战:通过完全仿真的模拟环境,让同学们快速理解金融理论与金融实 务 ●云课堂:金融机构专业人士通过系列讲座、在线课程等形式为在校同学传道、 授业、解惑

●Wind认证:通过Wind终端使用、金融基础知识、金融岗位技能训练,让同 学们掌握进入金融机构的基本能力 ●校外导师:200,000+的金融机构从业人员,贴身为你提供实习和工作指导

●实习就业:10,000+金融机构客户,每天发布各类实习机会和工作岗位 三、5大特色: ●数据面广:全球40多个交易所实时行情,中国及全球40多个国家和地区的 宏观数据,超过100,000家中港台及美国主板、NASDAQ上市公司和非上市公司数据,5,000个基金产品的深度数据,日均原创及引用第三方新闻超过10,000篇

Wind金融数据库介绍

W i n d金融数据库介绍Last revision on 21 December 2020

——中国金融数据及解决方案首席服 Wind中国金融数据库介绍上海万得信息技术有限公司 Shanghai Wind Information Co., Ltd. 地址: 上海市浦东新区福山路33号建工大厦9楼 邮编Zip: 200120 电话Tel: (8621) 6888 2280 传真Fax: (8621) 6888 2281 Email: sales

目录 1为什么选择WIND中国金融数据库 (1) 2数据库分类介绍 (4) 宏观经济数据库 (4) 中国宏观经济数据库 (4) 进出口数据库 (5) 世界经济国民经济帐户数据库 (6) 中观经济数据库 (7) 地区经济数据库 (7) 行业经济数据库 (8) 微观经济数据库 (9) 单公司海量数据大全 (9) 多公司指标型、股价行为、事件型数据库 (10) 外汇市场研究数据库 (13) 银行间交易数据库 (14) 基金数据库 (15) 其他数据库 (16) 指数数据库 (16) 新闻情报数据库 (17) 组合数据库及模拟投资 (18) 3公司介绍与资质 (19) 公司介绍 (19) 公司资质 (19) 公司部分客户 (20)

1为什么选择Wind中国金融数据库 数据全面:Wind资讯作为中国最领先的金融数据服务商,经过十年的积累,已建成国内最完整、最准确的以金融证券数据为核心的一流大型 金融工程和财经数据仓库,数据内容涵盖股票、基金、债券、外汇、 保险、期货、金融衍生品、现货交易、宏观经济、财经新闻等领域。 收集了所有金融品种完整的(包括上市前和上市后)数据,尤其是推 出了很多独具特色的深度加工数据,为其他公司所不具备。万得数据 库的全面完整已经得到了中国证券行业高端专业人士的公认。 数据准确:Wind资讯视数据的准确为生命,%的准确率倚靠科学的核查方法和先进的管理手段得以保证。从核查方法来看,除了传统的人工校 对外和数据库约束条件外,更多地利用各种平衡公式和经验公式对数 据进行合法性校验、一致性校验和统计校验。第一层是合法性校验, 即表内校验,不符合公式的不得入库,起到事前控制的作用;第二层 是一致性校验,即表间校验,每日所有数据处理完毕后,找出不同表 中相互矛盾的数据,并制作出报告,提交相关人员解决,起事后稽核 的作用;第三层是统计校验,即从数据库中提取大量数据制作专题报 表,与权威机构的公布报表核对,从中发现问题,如每年年报结束后 的综合统计。从管理手段来看,Wind资讯成立质量检验部门,选派专 人负责数据核查工作,通过一系列的激励措施,使数据质量始终保持 在很高的水准之上。更重要的是,目前有1500家机构每天实时对Wind 中国金融数据库进行使用和校验。

Wind资讯金融终端WFT报价单

Wind资讯金融终端(WFT)报价单 单位:人民币元 品种及模块 每终端数据服务年费 A:组合套餐购买报价:(此优惠报价为全国统一市场底价,无折扣;以下表格中的“年费”中软件升级许可费占56%,其余为数据服务费)B:第三方合作系统:Wind经济数据终端报价(WET) 购买终端 优惠价格套餐年费 新增每终端年费 品种及模块 每终端年费 软件升级许可年费 (安装、调试、增强等) (2011年12月31日前执行) A:基础模块自选零售报价股票:行情报价(含沪深交易所LEVEL1,国内期货行情)、多维数据、板块分析、 专题统计报表、估值定价、专项业务应用 债券:行情报价、债券分析、信息速览、多维数据、专题统计报表、债券进阶分析期货:行情报价、多维数据、专题统计报表 基金:报价及净值排行、基金资料、多维数据、基金分析、基金评级、理财产品指数:行情报价、指数管理、指数分析组合:组合管理、模拟投资 新闻情报:财经新闻、公司公告、法律法规、宏观经济新闻、行业经济新闻、 RSS阅读器、全文检索 18,800 136,800 A1:一次性批量购买 5 个终端,开通上述模块 192,800 16,800A2:一次性批量购买 10 个终端,开通上述模块 262,800 15,800A3:一次性批量购买 20 个终端,开通上述模块 372,800 13,800A4:一次性批量购买 30 个终端,开通上述模块 432,800 12,800A5:一次性批量购买 40 个终端,开通上述模块 492,800 11,800A6:一次性批量购买 50 个终端,开通上述模块 532,800 9,800A7:一次性批量购买 100 个终端,开通上述模块 952,800 8,800A8:一次性批量购买 200 个终端,开通上述模块 1,822,800 8,800A9:一次性批量购买 300 个终端,开通上述模块 2,652,800 8,800A10:一次性批量购买 400 个终端,开通上述模块 3,512,800 8,800A11:一次性批量购买 500 个终端,开通上述模块 4,382,800 8,800 中国宏观数据,中国各行业数据 全球各国宏观数据,全球主要行业数据 38,00036,00018,0006,000 8,0006,0006,00023,800(其中包含软件升级许可费13,328元;数据服务费10,472元)9,600(其中包含软件升级许可费7,680元;数据服务费1,920元) 年费合计

Wind资讯金融终端新闻情报使用说明

Wind 资讯金融终端 新闻情报使用说明 上海万得资讯科技有限公司 Shanghai Wind Information Co., Ltd. 地 址: 上海市浦东新区福山路33号建工大厦9楼 邮编Zip: 200120 电话Tel: (8621) 6888 2280 传真Fax: (8621) 6888 2281 Email: sales@https://www.360docs.net/doc/d46927582.html, https://www.360docs.net/doc/d46927582.html, ——中国金融数据及工具首席服务商

目录 1新闻情报简介 (1) 2新闻情报功能 (2) 2.1功能性需求概述 (2) 2.1.1进入“新闻情报”模块 (2) 2.1.2主要操作区域 (3) 3详细功能 (4) 3.1财经新闻 (4) 3.1.1新闻目录 (4) 3.1.2浏览 (5) 3.1.3收藏 (6) 3.1.4订阅 (7) 3.1.5导出与保存 (8) 3.1.6检索 (9) 3.2公司公告 (12) 3.2.1公告的栏目 (12) 3.2.2公告订阅 (13) 3.3法律法规 (14) 3.4宏观经济新闻 (15) 3.5行业经济新闻 (16) 3.6道琼斯新闻 (17) 3.7经济通新闻 (18) 3.8RSS新闻 (19) 3.8.1开放式的新闻资源 (19) 3.8.2RSS新闻订阅 (20) 3.9全文检索 (23)

1新闻情报简介 Wind资讯金融终端的新闻情报: z覆盖500个信息源的滚动新闻每天超过8000篇 z每日跟踪2000多家上市公司、400个行业信息网站、50个财经媒体的动态情报z拥有中国公司在上海、深圳、香港、纽约、纳斯达克、新加坡等全球各大交易所上市以来所有的公告信息 z完整收集来自国务院、中国人民银行、财政部、证监会、交易所等来源的法律法规大全 z Wind全文检索功能,财经界的Google z道琼斯实时更新的中国货币市场快讯 z经济通香港市场新闻 z RSS阅读器,订阅国内财经媒体大全

相关文档
最新文档