预应力空心板梁桥施工组织设计

预应力空心板梁桥施工组织设计
预应力空心板梁桥施工组织设计

XX桥梁工程

建设单位:

监理单位:

施工单位:

编制人:审核人:编制时间:年月

目录

第一章编制说明--------------------------------------------1 第二章工程概况--------------------------------------------1 第三章施工准备--------------------------------------------2

1. 技术准备--------------------------------------------2

2. 施工前的准备工作------------------------------------2 第四章施工部署和主要施工方法------------------------------2

4.1. 施工部署--------------------------------------------2

4.2. 各分部分项工程的主要施工方法------------------------3 4.2.1. 桥梁钻孔桩基础--------------------------------------3 4.2.2 墩台及盖梁施工--------------------------------------5 4.2.3 桥面板梁施工----------------------------------------6 4.2.4 桥面铺装及附属设施----------------------------------9 4.2.5 测量控制-------------------------------------------11 4.2.6. 土方开挖-------------------------------------------12 4.2.7. 沥青砼路面施工-------------------------------------12 4.2.8. 路边石安装-----------------------------------------16 4.2.9. 人行道施工-----------------------------------------17 4.2.10. 钢筋工程-------------------------------------------18 4.2.11 模板工程-------------------------------------------18 4.2.12 混凝土工程-----------------------------------------19 第五章施工进度计划及各阶段的保证措施---------------------19

5.1. 施工进度计划安排-----------------------------------19 5.2. 保证施工进度计划措施-------------------------------20 5.3. 总施工进度计划网络图、横道图-----------------------20 第六章施工机械配置计划-----------------------------------20 第七章劳动力安排计划-------------------------------------22 第八章施工现场组织机构-----------------------------------23 第九章施工现场布置及临时设施布置-------------------------26 第十章确保工程质量的技术组织措施--------------------------28

第一章编制依据

一、市府工程施工图及其招标文件(项目编号:ZZJC-09-027),及其他技术经济资料。

二、招标文件规定的施工工期。

三、编制依据和主要工程施工方案和施工方法。

A、《道路施工工程师手册》、《公路项目施工管理》、《山东省市政工程预算定额》、《山东建筑安装工程费用定额》、《山东省市政工程施工定额》。

B、材料、劳动力和机械设备供应情况。

C、《公路桥涵施工技术规范》和施工要求。

第二章工程概况

1、工程概况

XX桥梁工程位于兖州市九州路东延,府河下游与抢险大道对接处。横断面布置为人行道3米+非机动车道5米+分隔带2米+机动车道22米+分隔带2米+非机动车道5米+人行道3米=全宽42米。本工程上部结构均采用20米预应力砼空心板梁,下部结构采用桩顶盖梁式桥台,基桩采用钢筋混凝土灌注桩,桩径1.0米,人行道采用彩色道板和花岗岩路沿铺设,桥栏杆和抱鼓石均采用麻灰色花岗岩整体雕刻,桥立面采用喷真石漆处理。

合同工期:90天

第三章施工准备

1、技术准备

组织技术人员认真审核施工图纸,熟悉规范和操作规程,结合现场情况制定分部分项工程施工组织设计;组织测量人员对现场坐标点、水准点进行复核、测试,增设控制点,对施工段原地貌进行定位、放线、复测,对主要控制点做永久性桩,并加以保护。

2、施工前的准备工作

考察当地材料行情,原则上质量上乘、价格合理;组织施工机具、劳动力进场;落实土源,修整临时灰土拌合场地;施工用水、电引到现场;

16米空心板梁汽车吊吊装建筑施工组织设计

目录 1.编制说明 (1) 2. 编制依据 (1) 3.工程概况 (1) 4.人员及机械配置 (2) 5.施工准备 (2) 5.1技术准备 (2) 5.2施工现场准备 (3) 5.3施工机械准备 (3) 6.机具选择 (4) 7.施工方法 (8) 7.1工艺流程 (8) 7.2预制梁的运输 (10) 7.3板梁定位 (10) 7.4板梁安装方法 (10) 7.5双机抬吊施工注意事项 (12) 7.6.板梁安装实测项目表 (12) 8.质量保证措施 (12) 9.安全保证措施 (16) 10.吊装过程中突发事件紧急预案 (21) 11.文明施工措施 (23) word 专业资料

1.编制说明 本施工方案的编写充分考虑在及地方相关法律法规,以及市质监站,项目公司、二监理办的相关要求,认真分析两阶段施工设计图纸的基础上,考虑本项目的现场实际情况,阐述了16米空心板梁的架设方法和工艺流程,以及施工的安全、质量、环保注意事项,该方案适用于K41+678.8-K49+800段16米空心板梁架设施工。 2.编制依据 1、根据总体施工组织设计文件。 2、、交通部、建设部和现行工程施工规、验收标准及安全准则; 3、我单位可投入本工程的资源和类似工程施工中积累的施工、管理经验。 4、对施工现场实地考察情况。 5、《公路桥涵施工技术规》(JTJ/T F50-2011) 6、《公路工程施工安全技术规程》JTJ076-95 7、《路桥施工计算手册》 8、《起重机设计规》GB3811-2008-T 9、《起重机械安全规程》GB6067-85 10、《起重吊运指挥信号》GB5082-85 3.工程概况 本合同段桥梁工程共有桥梁5座,主线桥梁3座,互通匝道桥梁2座。上部构造主要为T梁、空心板及连续箱梁,其中16m空心板梁片,采用集中预制,然后分跨安装的方法作业。预制采用龙门吊施工,吊车安装就位。梁板具体工程数量见下表: 表-1梁体数量及结构表

(毕业论文)跨径16m预应力混凝土简支空心板桥设计

跨径16m 预应力混凝土简支空心板桥设计 一 设计资料 1.道路等级 三级公路(远离城镇) 2.设计荷载 本桥设计荷载等级确定为汽车荷载(道路Ⅱ级) 3.桥面跨径及桥宽 标准跨径:m l k 16= 计算跨径:m l 50.15= 桥面宽度:m 5.0(栏杆)+m 7(行车道))+m 5.0(栏杆) 主梁全长:m 96.15 桥面坡度:不设纵坡,车行道双向横坡为2% 桥轴平面线形:直线 4.主要材料 1)混凝土 采用C50混凝土浇注预制主梁,栏杆和人行道板采用C30混凝土,C30防水混凝土和沥青混凝土磨耗层;铰缝采用C40混凝土浇注,封锚混凝土也采用C40;桥面连续采用C30混凝土。 2)钢筋 主要采用HRB335钢筋。预应力筋为71?股钢绞线,直径mm 2.15,截面面

积13902mm ,抗拉标准强度MPa f pk 1860=,弹性模量MPa E p 51095.1?=。采用先张法施工工艺,预应力钢绞线沿板跨长直线布置。 3)板式橡胶支座 采用三元乙丙橡胶,耐寒型,尺寸根据计算确定。 5.施工工艺 采用先张法施工,预应力钢绞线两端同时对称张拉。 6.计算方法及理论 极限状态法设计。 7.设计依据 《通用规范》《公预规》。 二 构造类型及尺寸 全桥宽采用7块C50预应力混凝土空心板,每块m 1.1,板厚m 85.0。采用后张法施工,预应力混凝土钢筋采用71?股钢绞线,直径15.2mm ,截面面积 2139mm ,抗拉强度标准值MPa f pk 1860=,抗拉设计值MPa f pd 1260=,弹性模 量MPa E p 51095.1?=。C50混凝土空心板的抗压强度设计值MPa f cd 4.22=,抗拉强度的标准值MPa f td 56.2= 抗拉强度设计值MPa f td 83.1=。全桥空心板横断面图如图所示,每块空心板截面以及构造尺寸如图所示。

预应力空心板梁桥施工组织设计

XX桥梁工程 施 工 组 织 设 计 建设单位: 监理单位: 施工单位: 编制人:审核人:编制时间:年月

目录 第一章编制说明--------------------------------------------1 第二章工程概况--------------------------------------------1 第三章施工准备--------------------------------------------2 1. 技术准备--------------------------------------------2 2. 施工前的准备工作------------------------------------2 第四章施工部署和主要施工方法------------------------------2 4.1. 施工部署--------------------------------------------2 4.2. 各分部分项工程的主要施工方法------------------------3 4.2.1. 桥梁钻孔桩基础--------------------------------------3 4.2.2 墩台及盖梁施工--------------------------------------5 4.2.3 桥面板梁施工----------------------------------------6 4.2.4 桥面铺装及附属设施----------------------------------9 4.2.5 测量控制-------------------------------------------11 4.2.6. 土方开挖-------------------------------------------12 4.2.7. 沥青砼路面施工-------------------------------------12 4.2.8. 路边石安装-----------------------------------------16 4.2.9. 人行道施工-----------------------------------------17 4.2.10. 钢筋工程-------------------------------------------18 4.2.11 模板工程-------------------------------------------18 4.2.12 混凝土工程-----------------------------------------19 第五章施工进度计划及各阶段的保证措施---------------------19 5.1. 施工进度计划安排-----------------------------------19 5.2. 保证施工进度计划措施-------------------------------20 5.3. 总施工进度计划网络图、横道图-----------------------20 第六章施工机械配置计划-----------------------------------20 第七章劳动力安排计划-------------------------------------22 第八章施工现场组织机构-----------------------------------23 第九章施工现场布置及临时设施布置-------------------------26 第十章确保工程质量的技术组织措施--------------------------28

连续梁桥设计毕业设计

连续梁桥设计毕业设计公司内部档案编码:[OPPTR-OPPT28-OPPTL98-OPPNN08]

目录 第一章绪论................................................................ 第一节桥梁概述.................................................... 第二节方案比选 (3) 一、比选方案的主要标准.......................................... 二、方案编制.................................................... 第二章结构尺寸拟定............................................... 第一节结构尺寸拟定 (7) 一、桥梁横向布置................................................ 二、细部尺寸.................................................... 第二节截面几何特性................................................ 一、毛截面面积 ................................................. 二、惯性矩及刚度参数 ........................................... 第三章主梁内力计算............................................... 第一节横向分布系数的计算.......................................... 第二节恒载内力计算................................................ 一、单元化分.................................................... 第三节活载内力计算................................................ 一、冲击系数()u+1的计算......................................... 二、活载布载 (20) 第四章次内力计算 ................................................. 第一节基础位移引起的次内力计算.................................... 第二节温度应力引起的次内力计算. (24) 第三节混凝土收缩徐变引起的次内力计算.............................. 第五章作用效应组合Ⅰ............................................. 第一节承载力极限状态作用效应组合 (28) 第二节正常使用状态作用效应组合.................................... 第六章预应力筋的估算............................................. 第一节计算原理....................................................

大跨度预应力混凝土梁桥施工技术

大跨度预应力混凝土梁桥施工技术 一、我国预应力混凝土梁桥的现状与发展 1、预应力混凝土梁式桥的结构特点 各种形式的预应力混凝土梁式桥在桥梁建设中占有主导地位,而且有着广阔的发展前景。 按结构体系划分一般有:简支梁、连续梁、T形刚构、连续刚构、刚构连续组合梁以及V型墩刚构等。按截面形式划分有:I形梁、T形梁、 形梁、槽形梁、箱形梁等,大跨度超静定梁桥绝大多数采用箱形截面。 预应力混凝土简支梁桥由于结构简单、受力明确、施工方便,仍将是我国量大面广的中小跨径桥梁的首选结构。一般认为,简支梁桥的合理跨径在50m以下,超出这一范围,梁高会急剧加大,失去其经济合理性。 与简支梁相比,其它超静定梁则具有较大的跨越能力,那就是预应力混凝土连续梁与连续刚构。预应力混凝土连续刚构桥对地形、地质和通航要求适应性强、施工方便、较经济,已成为国内大跨径桥梁的首选桥型。 预应力混凝土连续梁与连续刚构同为大跨度梁式桥,但受力上存在着一定的差异。与连续梁相比,连续刚构由于在墩顶处的墩梁固结,对梁跨形成附加约束,因而能够增加顺桥向的抗弯刚度和横桥向的抗扭刚度,从而提高桥梁的跨越能力;同时由于墩柱的约束,温度变化、收缩徐变等对连续刚构造成的内力影响,也比连续梁大得多;尽管在高墩桥

位,经常采用柔性墩结构,但桥墩的材料用量、设计难度要比连续梁大得多。 与连续刚构相比,连续梁桥在支座处仅提供竖向约束。所以,在正常“恒载+活载”作用下的跨中截面弯矩要比连续刚构大,但由温度变化所产生的各种内力要比连续刚构小很多;大跨度连续梁对支座的承载能力要求很高,甚至需要特别设计(如南京长江大桥二桥北汊桥连续梁的支座吨位达到65000KN)。但它要求桥墩只承受竖向反力,在深水基础的情况下允许采用高桩承台,能够大大简化基础及桥墩的设计与施工。 刚构、连续组合梁桥的受力特点则介于连续梁桥和连续刚构之间;V 型墩刚构则具有增加桥梁刚度的特点。总之,在大跨度桥梁的桥式方案中,应当结合具体的技术经济条件,权衡选择。 2、我国预应力混凝土桥梁的现状与发展 桥梁跨越能力,也就是常说的跨径大小,是桥梁建设水平的一个重要指标,在一定程度上反映一个国家的工业、交通、桥梁设计和施工各方面的成就。 近二十年来,随着我国交通运输业的蓬勃发展,预应力混凝土桥梁的建设取得了很大的成就,其技术进步主要表现在: 在结构材料方面,高强、早强混凝土,又发展到高性能混凝土,以及在特殊使用要求下的特种混凝土正在得到推广应用,商品混凝土和泵送混凝土正在取代传统的施工方法;在预应力技术上,高强钢绞线、大吨位群锚技术日益普及,目前1860MPa级的高强低松驰钢绞线,几乎包揽了新建大跨度预应力混凝土桥梁天下(已研制出2000MPa的钢绞

空心板桥梁施工组织设计

空心板桥梁施工组织设 计 Company Document number:WUUT-WUUY-WBBGB-BWYTT-1982GT

施工组织设计 表1 施工组织设计文字说明 序言 我单位是家富有公路施工经验、实力较为雄厚的施工企业,为公路交通事业的发展和省内路网的改造做出了较为突出的贡献。经过多年的锻炼和发展,企业的管理水平、技术水平、施工经验、机械设备等都有了大幅度的提高,已成为拥有高素质的职工队伍和高新装备的现代化公路施工企业,取得了良好的社会信誉。 我单位本着“积极参与、努力竞争、把握机遇、共同发展”的原则,积极参与竞标。在此,我单位郑重承诺:如果中标,我们将坚决履行诺言,以“一流的队伍、一流的管理、一流的施工”建设“一流的工程”,以“最短的工期,最佳的质量”,完成本合同段施工任务,回报业主的厚爱与信任,为公路改造和发展再立新功。 一、工程概况 柴源桥:桥长米,桥面宽米(米行车道+2*米防撞栏)。设计荷载公路-II级,上部结构采用1*10米钢混凝土简支空心板,下部结构采用U型桥台,扩大基础。 官陂桥:桥长米,桥面宽米(米行车道+2*米防撞栏)。设计荷载公路-II级,上部结构采用1*13米预应力钢混凝土简支空心板,下部结构采用桩接盖梁桥台,桩基础。 二、质量目标 我方完全接受招标文件中对投标人施工质量的要求,同时承诺: 1、分项工程一次检验合格率达到100%,优良率达到85%以上; 2、单位工程一次检验合格率达到100%,优良率达到85%以上; 三、施工总体安排 为确保本工程质量达到向业主承诺的质量标准,我单位成立由工程师饶茸同志任项目经理、工程师郭志忠同志任项目技术负责人、李军东同志任项目质量检验负责人组成的项目经理部,上述主要管理人员资质合格,施工技术和管理经验丰富,专职专用能胜任工作。

预应力混凝土空心板

预应力混凝土空心板 本合同段共有空心板梁桥2座,共计有空心板梁216片,梁板采取集中预制,梁板安装计划采用汽车吊吊装,模板采用整体大块钢侧模,充气胶囊芯模,龙门吊起板的方法施工。 A、预制空心板台座 先张法预应力台座,张拉台座为C25钢筋砼墩式结构,台面即底层为C25砼,表面为水磨石面层做成底模。张拉横梁用30mm钢板焊成,一端为固定端,设置拉杆长由端头到台面,以减少钢绞线的浪费,另一端为活动端。横梁设计验算最大张拉力时,挠度变形不超过2mm。为使台座具有足够的强度、刚度和稳定性,不致使台座承受全部预应力筋的拉力时,台座变形、失稳,在设计张拉台座结构时进行台座的稳定性和强度验算,使其抗倾覆安全系数大于1.5,抗滑移系数大于1.3。 B、钢绞线和钢筋制作安装 钢绞线和钢筋统一在钢筋棚内制作、编号和堆放,钢筋和钢绞线在施工前分批抽样进行物理性试验,其性能强度满足设计要求,经监理工程师认可才能使用。安装工作:先将U型钢筋分布倒放于台面作垫衬,再布钢绞线,然后预拉钢绞线,预拉前按设计将预应力失效胶管穿入两端钢绞线,扶正U型筋,开始绑扎安装。钢筋绑扎注意将扎丝头转向上、下两侧的四周,以防气囊取出挂破,同时特别注意内模定位筋制作和绑扎的准确性。 C、张拉与锚固 预应力钢绞线采用千斤顶进行单根单向张拉,并分两次进行,第一次为预拉,即提供绑扎钢筋,待钢筋绑扎完毕在浇筑砼前最后张拉到设计值。张拉预应力采取张拉力伸长值双控制施工。张拉程序为0→初应力→100%δcon(持荷2min,锚固)(δcon为张拉时的控制应力)。张拉中,实际伸长量在计算伸长量±6%范围内为正常,否则应查明原因,在锚固后,预应力筋对设计位置的偏差不得大于5mm。 锚固:张拉时锚固固定端和张拉端用锚环楔片锚固,卸张后梁体靠混凝土的握裹力锚固,锚固后的变形控制在6mm以内。 D、模板

预应力混凝土连续梁桥毕业设计

摘要 本设计所设计的是预应力混凝土连续梁桥的设计,该桥位于王洼到原州区段,为单线铁路桥梁,主要设计桥梁的上部结构,设计荷载采用中—活载。 本设计采用预应力混凝土连续梁桥,其孔径布置为48+80×2+48m,全长为256m,主梁采用变高度变截面的单箱单室箱型截面,施工方法采用对称悬臂施工法。本设计使用midas 软件分析,考虑施工过程体系转换和混凝土收缩徐变因素进行恒载力计算。计算各控制截面力影响线,并按最不利情况进行加载,求得活载力包络图。定义基础沉降组,按最不利组合求得基础沉降引起的最不利力。依据规选取截面梯度温差模式,并计算温差引起的结构力。分别按主力组合和主力附加力进行荷载组合,并得到结构组合力包络图。根据各控制截面力进行了估束和配筋计算,并绘制了梁体钢束布置图。最后,对各控制截面进行了强度、抗裂性、应力和变形验算,各项检算均满足规对全预应力结构的要求。 关键词:连续梁;力计算;预应力混凝土;检算;

Abstract What I designed at the undergraduate design is a prestressed concrete continuous beam bridge .It lies in Wangwa to Yuanzhou,Ningxia province .It is a single line railway .I mainly designed the superstructure of the bridge. The load for design is the “zhonghuo”load. I adopt a prestressed concrete continuous beam bridge with four spans of 48+80×2+48m ,Its total span is 256m . First the size of girder is determined;highly variable for the variable beam cross-section single-Box Single girder and balanced cantilever construction is used . Then the Midas program is used to calculate the internal force caused by dead load of the first stage ,considering the construction stage ,after imposing the second stage dead load on the complete system . The internal force of the stage is calculated . The internal force influence lines of the control section is calculated ,then the live load is imposed according to the most adverse circumstances to get the Force Envelope .The program is used to determine the most adverse circumstances and calculate the internal force after defining the settlement groups of the basis.The temperature load is imposed consider the shrinkage and creep of the concrete . Then combination of load effects is made acoording to the Main force combination and the Main force plus additional force combination .According to the internal force of control sections ,the number of per-stressing steel stands is estimated and the per-stressing steel stands are arranged in the bridge . Finally a check is made of the bearing capacity ,the ability to resist crack and the sterss of the control section ,all the requirements can be met . Keywords: Continuous beam;Internal force calculation;Prestressed concrete ;Checking computation;

预应力混凝土桥梁工程施工方案

预应力混凝土桥梁工程 本标段内桥梁为石院子中桥长67米,上部为预应力混凝土T梁,下部采用柱式墩,U 型桥台,钻孔灌注桩基础。 1、基础施工 1、1桩基施工方法 钻机施工工艺见钻孔灌注桩施工工艺框图。 1.1.1施工准备: 开钻前根据地层岩性等地质条件、技术要求确定钻进方法和选用合适的钻具;规划施工场地,合理布置临时设施;开孔前,测量班放出桩位中心后将钢护筒埋入土中正确对位。开孔时,采用短钻具、低钻速、轻压慢进。 1.1.2钢护筒的制作: 桩基护筒用δ=10mm的A3钢板卷制,护筒焊接采用开坡口双面焊,要求焊逢连续,保证不漏水。护筒埋置深度须符合下列规定:黏性土不小于1m,砂类土不小于2m,当表层土松软时将护筒埋置到较坚硬密实的土层中至少0.5m;岸滩上埋设护筒,在护筒四周回填黏土并分层夯实;护筒顶面中心与设计桩位偏差不大于5cm,倾斜度不大于1%。 1.1.3钻进施工:

钻孔灌注桩施工工艺框图 钻进施工时,再次将钻头、钻杆、钢丝绳等进行全面检查;钻进时,钻头对准设计桩位中心,匀速下放至作业面,液压装置加压,旋转钻进,钻进过程中,应根据地质资料掌握土层变化,及时捞取钻碴取样,判断土层,记入钻孔记录表,并与地质资料进行核对。根据核对判定的土层调整钻机的转速和钻孔进尺。 1.1.4护壁: 钻孔护壁采用泥浆护壁的形式。选用成品膨润土配制优质泥浆,其具有相对密度低、粘度低、含砂量少、失水量少、泥皮薄、稳定性强、固壁能力高等优点。根据不同的地质情况选择不同的泥浆比重。根据地层情况及时调整泥浆性能,参照<公路桥梁施工规范>(JTG/T F50-2011)泥浆性能指标。 1.1.5第一次清孔: 钻孔至设计高程,经过检查,孔深符合要求后,开始进行清空。清孔采用换浆法,在钻进至设计深度后,稍稍提起钻头,同时保持原有的泥浆比重进行循环浮碴,随着 终 孔 清 孔 测 孔 安放钢筋笼 安放导管 测孔深、孔径、倾斜度 测泥浆性能指标 监理工程师签字认可 监理工程师签字认可 水密性试验 测孔深、孔径 钢筋笼及检测管制作 凿桩头 二次清孔 灌注混凝土 检查泥浆指标及沉渣厚度 制作混凝土试件

空心板梁预制工程施工组织设计方案

空心板梁预制首件工程施工方案 一、工程概况 S253、S262保靖夯沙至公路改建工程项目起点段位于保靖县,K0+000位于保靖县夯沙乡乡政府处,与省规划的新增省道S253线对接;本项目终点接于在建永顺至北互通连接线K3+700处,终点桩号为K13+653.117。此连接线为路基宽度8.5米的二级公路,全线共设置2处断链,累计断链长32.461,(1)K0+622.967=原K0+540,断链长82.697m;(2)K5+203.604=原K5+253.84,断链短50.256m,路线总长度为13.685km,其中保靖段4.082m(K0+000~K4+000),段9.603km(K4+000~K13+653.117)。段路基土石方49.737万m3,路面67.478k m2,隧道810m/1座,桥梁236m/5座:均为中桥,涵洞36道,其中盖板涵12道,圆管涵23道,金属波纹管涵1道,均为新建。 本次桥梁空心板梁预制首件工程拟选位置为:夯坨一桥第一跨第一片空心板梁;主要工程量为预应力钢绞线259Kg,C50混凝土8.4m3,C40混凝土0.33m 3,HPB300钢筋407Kg,HRB400钢筋1102Kg。 二、施工方法及主要工艺 2.1 施工工艺图

后法预应力空心板梁预制施工工艺流程图 2.2、工艺要求 2.2.1、浇筑空心板混凝土前应严格检查伸缩缝、泄水管、护栏、支座等附属设施预埋件是否齐全,确定无误后方可浇筑。施工时,应保证预应力孔道及钢筋位置准确,控制混凝土骨料最大粒径不得大于20mm。浇筑混凝土时应充分振捣密

实,严格控制其质量。 2.2.2、为了防止预制板上拱过大,及预制板与桥面现浇层由于龄期差别而产生过大收缩差,存梁期不超过90d,若累计上拱值超过计算值8mm, 应采取控制措施。 2.2.3、空心板预制时,按1m一道在铰缝的侧模嵌上500mm长的φ6钢筋,形成6mm凹凸不平的粗糙面。 2.2.4、空心板预制时,除注意按设计图纸预埋钢筋和预埋件外,桥面系、伸缩缝、护栏及其它相关附属构造,均应参照有关图纸施工,护栏预埋钢筋必须预埋在预制空心板。 2.3、空心板梁施工工艺 2.3.1、钢筋制作安装 钢筋的制作在钢筋加工场地进行。底模清理好后即可进行底板钢筋的绑扎。应符合设计与规要求。 波纹管与钢筋一起安装,波纹管的定位筋位置一定要安装正确,并且应绑扎牢固,防止混凝土浇筑时波纹管移位。 2.3.2、模板安装 模和侧模用钢板制作成定型模板,以丝杆连接对拉支护。模及侧模在模板精加工后运至施工现场经拼装合格后才能够使用,每一次使用前需要进行打磨和除锈。拼装完毕后,进行支护与调整。 2.3.3、混凝土的浇筑和养护 C50混凝土拟采用商品混凝土,在施工中采用斜分层浇筑的方式进行,即由梁的一端向另一端进行。混凝土振捣采用插入式振捣器与附着式振捣器配合进行。浇筑混凝土时,应经常检查模板、锚固端及预埋件,保证其位置及尺寸符合设计要求。在梁体混凝土浇筑完成并初凝后,应铺盖草袋或土工布防护,采用洒水自然养护,经常洒水以保持混凝土表面充分潮湿状态。 2.3.4、模板的拆除 梁体混凝土强度大于80%设计强度;梁体表面温度与环境之差≯15℃;风雪天气,气温将发生急剧下降时,不得拆模。

16m公路预应力简支空心板梁桥中板设计

16m 公路预应力简支空心板梁桥中板设计 一、 设计资料 1.设计荷载 本桥设计荷载等级确定为汽车荷载:公路Ⅱ级;人群荷载:3.02N/m k 。 2.桥面跨径及净宽 标准跨径:k l =16m 。 计算跨径: l =15.6m 。 板 长:1l =15.96m 。 桥梁宽度:7m+2×0.5m 。 板 宽:2l =0.99m 。 3.主要材料 混凝土:主梁板采用C50混凝土,桥面铺装采用10cm 混凝土+柔性防水涂层+10cm 沥青混凝土。预应力筋:采用?s 15.20高强度低松弛钢绞线,抗拉强度标准值pk f =1860MPa ,弹性模量 p E =1.95510MPa ?,普通钢筋:直径大于和等于12mm 的用HRB335级 热轧螺纹钢筋,直径小于12mm 的均用R235级热轧光圆钢筋。锚具、套管、连接件和伸缩缝等根据相关规范选取。 4.施工工艺 先张法施工,预应力钢绞线采用两端同时对称张拉。 5.计算方法及理论 极限状态设计法

6.设计依据及参考资料 (1) 交通部颁《公路工程技术标准》(JTG B01-2003)。 (2) 交通部颁《公路桥涵设计通用规范》(JTG D60-2004)。 (3) 交通部颁《公路钢筋混凝土及预应力混凝土桥涵设计规范》 (JTG D62-2004)。 (4) 交通部颁《公路桥涵施工技术规范》(JTJ041-2000)。 (5) 《预应力筋用锚具、夹具和连接》(GBT14370-93)。 (6) 《公路桥梁板式橡胶支座规格条例》(JTT663-2006)。 (7) 《桥梁工程》、《结构设计原理》等教材。 (8) 计算示例集《混凝土简支梁(板)桥》(第三版),易建国 主编,人民交通出版社。 (9) 《公路桥涵设计手册梁桥(上)》,徐光辉,胡明义主编, 人民交通出版社。 二、 构造布置及尺寸 桥面宽度为:净—7m+2?0.5m (防撞护栏),全桥宽采用8块 C50的预制预应力混凝土空心板,每块空心板宽99cm (中板),边板99.5cm ,宽62cm ,空心板全长15.96m 。采用先张法施工工艺,预应力筋采用?s 15.20高强度低松弛钢绞线,pk f =1860MPa , p E =1.95510MPa ?。pd f =1260MPa ,预应力钢绞线沿板跨长直线布置。 C50混凝土空心板的ck f =32.4MPa ,tk f =2.65MPa ,td f =1.83MPa 。全桥空心板横断面布置如图所示,每块空心板截面及构造尺寸见图2。

预应力混凝土连续梁桥设计 (毕业设计)

第一章绪论 第一节桥梁设计的基本原则和要求 一、使用上的要求 桥梁必须适用。要有足够的承载和泄洪能力,能保证车辆和行人的安全畅通;既满足当前的要求,又照顾今后的发展,既满足交通运输本身的需要,也要兼顾其它方面的要求;在通航河道上,应满足航运的要求;靠近城市、村镇、铁路及水利设施的桥梁还应结合有关方面的要求,考虑综合利用。建成的桥梁要保证使用年限,并便于检查和维护。 二、经济上的要求 桥梁设计应体现经济上的合理性。一切设计必须经过详细周密的技术经济比较,使桥梁的总造价和材料等的消耗为最小,在使用期间养护维修费用最省,并且经久耐用;另外桥梁设计还应满足快速施工的要求,缩短工期不仅能降低施工费用,面且尽早通车在运输上将带来很大的经济效益。 三、设计上的要求 桥梁设计必须积极采用新结构、新设备、新材料、新工艺利新的设计思想,认真研究国外的先进技术,充分利用国际最新科学技术成果,把国外的先进技术与我们自己的独创结合起来,保证整个桥梁结构及其各部分构件在制造、运输、安装和使用过程中具有足够的强度、刚度、稳定性和耐久性。 四、施工上的要求 桥梁结构应便于制造和安装,尽量采用先进的工艺技术和施工机械,以利于加快施工速度,保证工程质量和施工安全。

五、美观上的要求 在满足上述要求的前提下,尽可能使桥梁具行优美的建筑外型,并与周围的景物相协 调,在城市和游览地区,应更多地考虑桥梁的建筑艺术,但不可把美观片面地理解为豪华的细部装饰。 第二节计算荷载的确定 桥梁承受着整个结构物的自重及所传递来的各种荷载,作用在桥梁上的计算荷载有各种不同的特性,各种荷载出现的机率也不同,因此需将作用荷载进行分类,并将实际可能同时出现的荷载组合起来,确定设计时的计算荷载。 一、作用分类与计算 为了便于设计时应用,将作用在桥梁及道路构造物上的各种荷载,根据其性质分为:永久作用、可变作用和偶然作用三类。 (一)永久作用 指长期作用着荷载和作用力,包括结构重力(包括结构附加重力)、预加力、土重力及土的侧压力、混凝土收缩徐变作用、水的浮力和基础变位而产生的影响力。 (二)可变作用 指经常作用而作用位置可移动和量值可变化的作用力。包括汽车荷载及其的引起的冲击力、离心力、汽车引起的土侧压力、人群荷载、汽车制动力、风荷载、流水压力、温度作用和支座摩阻力。 (三)偶然作用 偶然作用是指在特定条件下可能出现的较强大的作用,如地震作用或船只或漂浮物的撞击力和汽车的撞击作用(施工荷载也属于此类)。

预应力混凝土桥梁转体施工技术

浅谈预应力混凝土桥梁转体施工技术【摘要】近年来随着我国经济高速发展的需要,国家不断扩大对运输部门的投资,并高度重视桥梁的修建工作,同时预应力技术也得到了突破发展,预应力混凝土桥梁的转体施工技术也得到越来越广泛的应用。本文从桥梁施工的特点、流程、方法等方面对预应力混凝土桥梁施工技术进行介绍和探讨。 【关键词】预应力混凝土桥; 转体施工; 转盘制作 【 abstract 】 in recent years as china’s rapid economic development needs, the state of the transportation sector continues to expand the investment, and pay close attention to the construction of the bridge, while prestressed technique also get the breakthrough, prestressed concrete bridge construction technology also swivel get applied more and more. this article from the characteristics of the bridge construction, process and method of bridge construction of prestressed concrete technology are introduced and discussed. 【 keywords 】 prestressed concrete bridge; swivel construction; turntable production 中图分类号:tu37文献标识码:a 文章编号: 随着我国经济建设的发展,交通事业的建设也取得了重大进展,而在交通线的扩展方面桥梁的修筑有着重要地位和作用,但是在桥

毕业设计开题报告-空心板

1、目的及意义(含国内外的研究现状分析) 设计的目的: 毕业设计是由学生独立、系统完成一项工程设计。因而有利于培养学生的综合素质,增加工程意识,以及创新能力具有其他教学环节无可比拟的重要作用。通过毕业设计教学环节,学生独立运用本科四年所学基础课程,以及查阅相关规范手册,分析、解决设计中出现的问题,培养了学生在以后工作实践中解决处理遇到的问题的能力,提高桥梁结构分析能力和运用电算能力,使用商业软件和计算程序,以及提高计算机辅助设计水平,从而具备初步工程人员素质,为将来工作岗位打下良好的基础。 设计的意义(理论或实际、含国内外研究现状分析): 空心板是由井式板演变而来的,它起源于德国,由前联邦德国工程师MULLER·Leopold首先提出,当时被称为“B-Z体系”,源自德文的蜂巢式混凝土空心楼板。之后,G. Franz教授对这种板进行了试验研究,提出了在静力荷载作用下可采用刚度等效的实心无梁楼盖的计算方法。 20实际50年代,我国在修建大量小跨径钢筋混凝土桥梁的同时,开始对预应力混凝土桥梁进行研究与实验。1956年在公路上建成了一座跨径为20m的预应力混凝土简支梁桥,之后,这种桥梁便得到了广泛使用,并提出了装配式预应力混凝土简支梁桥的系列标准设计。国外自20世纪30年代就已出现混凝土预制空心板,并在实际工程中得到应用。虽然这种楼盖具有节约混凝土、生产化高、质量稳定等优点,但其整体性差、抗震性能不好、建筑布置不灵活、开洞困难、使用功能受限。随着人们物质需求的不断提高和建筑功能要求的复杂化,预制空心板已难以适应抗震设计与建筑市场的需要,在实际工程中也已逐渐退出应用行列。现浇混凝土空心无梁楼盖改善了预制单向空心板的缺点,发展了其优点受到行业的广泛关注,并在实际工程中得到了大量的应用。 进入20世纪90年代,我国的工程师提出了采用轻质高强的空心薄壁内膜作为空心板的成孔内膜,从而降低了现浇空心板的施工难度,为空心板的大范围应用开辟了广阔的空间。国内学者在空心板的研究方面也取得了一些初步成绩。 空心板作为梁桥的一种截面形式,空心板截面梁在目前桥梁中广泛使用,随着桥梁

《空心板梁安装施工组织设计方案》

《空心板梁安装施工组织设计方案》

空心板梁安装施工方案 一、工程概况 本标段起止桩号为K30+260-K39+370,全长9.114公里,全线共有中桥6座、分离式立交3座,预制空心板梁共计579片,其中16米空心板梁220片,20米空心板梁359片。空心板梁重量分别为:20米边板40.79t,20米中板31.51t;16米边板30.11t,16米中板 23.12t。 二、编制依据及原则 1、编制依据 《公路桥涵施工技术规范》JTG/T F50-2011 《公路工程质量评定标准》JTG F80/1-2004 《公路工程施工安全技术规范》JTJ076-95 《工程测量规范》GB50026-2007 商登高速公路商丘段第四标段施工设计图 2、编制原则 充分可虑施工组织的设计的科学性、合理性,与业主招投标文件符合性,体现我公司的施工能力和管理水平。 (1)确保质量:优化施工方案,采用机械化、专业化施工,严格质量控制,使架梁施工对地方道路的影响降到最低。

(2)确保安全:实行严密的管理和施工措施,针对工程中可能出现安全隐患的部位和施工过程,实行重点监控,确保万无一失。(3)确保工期:鉴于本项目目前工期情况,我们从各种资源配置着手按照总体工期要求,优化施工工序,确保工期顺利完成。 (4)文明施工、注重环保:在施工过程中,采取环境保护措施,做到文明施工、保护环境。 三、组织机构 空心板梁安装工程施工人员组织一览表

空心板梁安装设备一览表 四、特点、重难点分析及应对措施 通过对业主招标文件、施工图纸和参考资料认真调研的基础上,对工程特点、重点及难点归纳如下表。 工程特点、难点、重点与应对措施 五、施工总体部署及进度计划 1、施工总体部署

必看最经典梁格——midas空心板梁桥梁桥法工程实例

空心板梁桥工程实例 1几何尺寸 空心板梁几何尺寸见图4.1.1至图4.1.3。 图4.1.2 边板截面(cm)图4.1.3 中板截面(cm) 2主要技术指标 (1) 结构形式:装配式先张法预应力混凝土简支空心板梁 (2) 计算跨径:16m (3) 斜交角度:0度 (4) 汽车荷载:公路-Ⅱ级 (5) 结构重要性系数:1.0 3 计算原则 (1) 执行《公路桥涵设计通用规范》(JTG D60-2004)和《公路钢筋混凝土及预应力混凝土桥涵设计规范》(JTG D62-2004)。

(2) 6厘米厚现浇C50混凝土不参与结构受力,仅作为恒载施加。 (3) 温度效应,均匀温升降均按20摄氏度考虑;温度梯度按《公路桥涵设计通用规范》(JTG D60-2004)第4.3.10条的规定取值。 (4) 按A 类部分预应力混凝土构件设计。 (5) 边界条件:圆形板式橡胶支座约束用弹性支承进行模拟,弹簧系数SDx=SDy=1890 KN/m;SDz=9.212E+05KN/m;SRx=078E+09KN.m/rad; 4主要材料及配筋说明 (1) 空心板选用C50混凝土 (2) 预应力钢绞线公称直径mm s 2.15φ,1根钢绞线截面积2 139mm A p =,抗拉强度标准值Mpa f pk 1860=,锚具变形总变形值为12mm。横截面预应力筋和普通钢筋布置见图4.4.1和图4.4.2。预应力筋有效长度见表4.4.1 图4.4.1边板钢筋钢绞线布置图(cm) 图4.4.2 中板钢筋钢绞线布置图(cm) 图中N9筋(实心黑点)为普通钢筋,其余为钢绞线。 表4.4.1 16米空心板预应力筋有效长度表

空心板桥梁施工组织设计

施工组织设计 表1 施工组织设计文字说明 序言 我单位是家富有公路施工经验、实力较为雄厚的施工企业,为公路交通事业的发展和省内路网的改造做出了较为突出的贡献。经过多年的锻炼和发展,企业的管理水平、技术水平、施工经验、机械设备等都有了大幅度的提高,已成为拥有高素质的职工队伍和高新装备的现代化公路施工企业,取得了良好的社会信誉。 我单位本着“积极参与、努力竞争、把握机遇、共同发展”的原则,积极参与竞标。在此,我单位郑重承诺:如果中标,我们将坚决履行诺言,以“一流的队伍、一流的管理、一流的施工”建设“一流的工程”,以“最短的工期,最佳的质量”,完成本合同段施工任务,回报业主的厚爱与信任,为公路改造和发展再立新功。 一、工程概况 柴源桥:桥长21.04米,桥面宽12.5米(11.5米行车道+2*0.5米防撞栏)。设计荷载公路-II级,上部结构采用1*10米钢混凝土简支空心板,下部结构采用U型桥台,扩大基础。 官陂桥:桥长18.04米,桥面宽12.5米(11.5米行车道+2*0.5米防撞栏)。设计荷载公路-II级,上部结构采用1*13米预应力钢混凝土简支空心板,下部结构采用桩接盖梁桥台,桩基础。 二、质量目标 我方完全接受招标文件中对投标人施工质量的要求,同时承诺: 1、分项工程一次检验合格率达到100%,优良率达到85%以上; 2、单位工程一次检验合格率达到100%,优良率达到85%以上; 三、施工总体安排 为确保本工程质量达到向业主承诺的质量标准,我单位成立由工程师饶茸同志任项目经理、工程师郭志忠同志任项目技术负责人、李军东同志任项目质量检验负责人组成的项目经理部,上述主要管理人员资质合格,施工技术和管理经验丰富,专职专用能胜任工作。 项目经理部下设工程部、计财部、安质部、机管和综合办公室、工地试验室,具体负责项目施工组织、管理、质量监控和内外关系协调,管理四个施工队,即:预制构件施工队一个;桥梁维修加固施工队两个;其他工程施工队一个。

相关文档
最新文档