(一)工程概况·················································· - 2 - (二)施工指导思想及组织原则·································· - 4 - (三)施工组织机构框图········································ - 5 - (四)施工准备·················································· - 7 - (五)施工机械设备配备······································· - 11 - (六)劳动力组织·············································· - 12 - (七)施工进度计划安排及进度网络图······················· - 15 - (八)施工总平面布置图······································· - 36 - (九)施工安排及方法·········································· - 36 - (十)质量目标和保证措施····································· - 36 - (十一)确保安全生产的技术组织措施·························· - 37 - (十二)确保文明施工的技术组织措施·························· - 38 - (十三)特殊季节施工及防护措施······························ - 38 - (十四)管线保护施工技术措施································· - 38 - (十五)施工管理·············································· - 40 - (十六)施工环境保护及社会综合治理措施····················· - 42 - (十七)廉政建设·············································· - 42 - (十八)其它需要说明的事项··································· - 42 -

施工组织设计

(一)工程概况

工程位于贵州省都匀市境内,起点为都匀市规划的173转盘,途经都匀市全民、洛邦、牛场、大坪,终点为厦蓉高速公路都匀东互通匝道,全长15.72km。道路全线采用城市I级主干道标准,设计时速60km/小时,K0+000~K0+500、K5+300~K15+720路基宽度为40米,K0+500~K5+300路基宽度31.5米。第十工区路面工程,图纸第9、10合同段,起讫桩号K0+000-K15+720。

本工程路面设计以双轮组单轴载100kN为标准轴载(BBZ-100)。设计年限为15年。

路面结构:

①机动车道路面结构

机动车道路面各结构层及路基顶面验收弯沉值如表1-1

机动车道路面各结构层及验收弯沉值表1-1

土基顶面竣工验收弯沉值LS= 258.8 (0.01mm) (根据“测试规程”)

②匝道路面结构

匝道路面各结构层及路基顶面验收弯沉值如表1-2

匝道路面各结构层及验收弯沉值表1-2

公路工程总体工程施工组织设计方案

公路工程总体施工组织 设计方案 一、工程概况 1.1概述 1.1.1 工程概况 G105、G206、S319段大中修工程03标是合安路的重要组成部分,起讫桩号为K1095+389~K1132+889,全长37.5km。主要工程量为凿除原水泥混凝土路面15332.74m3,凿除水泥稳定碎石基层6850 m3,浇筑C15砼基层1501.9 m3,C35砼面板15332.74 m3,级配碎石基层1280 m2,水泥稳定碎石基层25406.25 m3,合同总产值为13742305元。 1.1.2自然地理概况 本项目东部位于江淮丘陵西段,路线西部为大别山余脉,整个地势为岗地,冲畈交错,起伏不断,但高差不大。路线经过地区属亚热带湿润季风气候区,四季分明,气候温和,雨量适中,春温多变,秋高气爽,梅雨显著,夏雨集中。公路自然区划为Ⅳ2区。沿线水系发达,地表水和浅地下水系对公路路基有一定的影响。根据《中国地震动峰值加速度区划图》该区动峰值加速度0.05g,对应地震基本烈度Ⅵ度。 1.1.3设计标准 公路等级为一级公路,设计车速为80km/h,路面断面形式采用水泥混凝土路面,路基宽26米,路面宽15米,维修后设计载荷为公路-Ⅰ级。 1.2交通 本工程所在位置沿线交通便利,工程材料运输有国省道和县乡道路利用。 1.3供电 沿线村镇密集,电力线、网分布齐全,工程、生活用电方便,施工时与有关部门协商后可就地利用。 1.4筑路材料

本项目各结构层所用工程材料料源稳定,料质良好,运输道路交通便利。 1.5施工组织设计编制依据和原则 1.5.1编制依据 a.本项目招标文件 b.现场考察情况 c.我公司历年从事类似项目的管理方法和经验 d.我公司现有可投入本工程的施工技术力量和机械设备 e.现行的部颁标准和技术规 1.5.2编制原则 施工组织设计按照业主提出的要求,以及招标文件的规定,将G105、G206、S319段大中修工程03标修建成优良工程的原则进行编制。具体表现在以下几方面: a.采用我单位近年来在公路建设中使用的先进施工方法、工艺设备,提高机械化、标准化施工作业水平。 b.调集我单位精锐的管理人员和最雄厚的技术力量,组成一个强有力的项目经理部。 c.树立视优良工程为合格工程的标准,一定要在G105、G206、S319段大中修工程03标施工中确保优良工程。 d.分别考虑各种不利施工进度和质量的因素,在工期安排、人员设备配置、施工方法等方面综合考虑时留有余地。 e.针对本合同段的施工重点、难点,着重考虑相应的施工方案和措施。 二、施工组织设计总体目标和施工部署 2.1 施工组织设计总目标 精心组织,确保工期;规施工,强化过程;以人为本,力创精品;预防为主,杜绝事故;健全机构,绿色环保;快速、有序、优质、高效地完成本标段全部工程和实施缺陷修复。 2.1.1质量目标 确保标段全部工程达到招标文件规定的工程质量验收标准,争创优良工程。具体目

(完整版)护栏工程施工组织设计(修)

施工组织设计

目录 第一章综合说明,质量、工期、安全文明施工目标…………………………… 第二章主要施工方法……………………………………………………………… 第三章降低工程造价的主要措施………………………………………………… 第四章新技术、新材料、新工艺、新设备的应用……………………………… 第五章工程投入的主要物资和施工机械设备情况及主要施工机械进场计划… 第六章劳动力安排计划…………………………………………………………… 第七章确保工程质量的技术组织措施…………………………………………… 第八章确保安全生产的技术组织措施…………………………………………… 第九章确保文明施工的技术组织措施…………………………………………… 第十章雨期施工措施……………………………………………………………… 第十一章总进度工期安排及进度网络图、进度节点控制阶段划分及节点完成时间…………………………………………………………………………… 第十二章水电用量计划………………………………………………………………

第一章综合说明,质量、工期、安全文明施工 目标 质量目标:严格按施工图纸、国家标准和验收规范及业主的要求组织施工,确保分项工程一次合格率100%,单位工程一次交验合格率100%,确保合格、争创优良,实现质量一流,建成优质工程。 质量承诺:我们将通过高标准、严要求,争取实现工程“零缺陷”。 工期目标:严格履行本投标书中我公司对工期的承诺及招标文件中有关施工工期的规定,因我公司原因延误工期,我方承担相应责任。 文明施工目标:执行OHSMS18001标准,确保工程安全环保、文明施工达标,并自愿承担相应的费用。 安全施工目标:实现“双零”目标。即零安全事故,零伤亡率。 文明施工目标:精心组织,科学管理,规范作业,文明言行;处理好与沿线单位、居民的关系,尽量给当地居民提供方便,不扰民;保证并维护施工区域的安全与交通秩序,争创“文明工地”。 第二章主要施工方法 护栏工程分成二大部分那部分出现问题,都将直接影响到工期和质量,为此我们根据工程设计和工期要求,专门制订了详细的施工计划,以保证

房建工程施工组织设计方案

房建工程施工组织设计方案

房建工程施工组织设计目录

第一章编制说明 (1) 第二章工程概况 (3) 第三章施工组织 (5) 第一节施工组织机构 (5) 第二节管理体系及框图 (7) 第三节方针目标管理 (8) 第四节施工安排及流水段的划分 (9) 第五节推广应用新技术、新工艺及降低成本措施 (9) 第六节工程总进度计划 (9) 第七节主要技术经济指标 (10) 第四章施工准备及施工总平面布置 (12) 第一节技术准备 (12) 第二节施工组织准备 (12) 第三节直运输机械及主要机具的选择 (12) 第四节施工平面规划布置 (14) 第五节施工现场临时用电 (14) 第六节施工现场临时用水 (15) 第七节劳动力配备 (15) 第五章主要施工方案方法 (17) 第一节测量放线、轴线及标高控制 (17) 第二节基础工程 (17)

第三节主体工程 (20) 第六章屋面工程 (25) 第七章装饰装修工程 (27) 第一节天棚抹灰 (27) 第二节内墙面抹灰 (27) 第三节楼地面工程 (28) 第四节内墙面涂料及瓷砖 (29) 第五节外墙饰面 (30) 第六节门窗及油漆、玻璃 (32) 第八章重点部位施工方法及技术措施 (33) 第一节桩基础 (33) 第二节三间一台的施工 (34) 第三节屋面工程 (35) 第四节现浇混凝土 (36) 第九章土建与安装的施工配合 (37) 第十章成品保护措施 (40) 第十一章质量保证措施 (41) 第十二章保证工期的措施 (44) 第十三章保证安全、文明施工的措施 (45) 第十四章售前售后服务及工程技术档案资料管理 (47) 第十五章应用新技术、新材料、新工艺及合理化建议 (49)

施工组织设计方案模板

XX片区市政配套道路二期工程 施 工 组 织 设 计 编制: 审核: 审批: XXXXX股份有限公司 年月日

施工组织设计目录 目录 第一章工程总说明 ----------------------------------------------------------- 1第一节编制总则 ------------------------------------------------------------------------------------- 1第二节工程概况 ------------------------------------------------------------------------------------ 2第二章施工总部署 ----------------------------------------------------------- 4第一节施工总计划安排--------------------------------------------------------------------------- 4第二节总体施工顺序和施工流程 ---------------------------------------------------------------- 6第三节管道工程 ---------------------------------------------------------------------------------- 8第四节施工重点、难点和相应对策----------------------------------------------------------- 19 一、沥青路面施工方案----------------------------------------------------------------------------- 19 二、软基换填施工方案----------------------------------------------------------------------------- 22 三、管道拉森钢板支护----------------------------------------------------------------------------- 24第五节劳动力管理 --------------------------------------------------------------------------------- 29第六节材料管理 ------------------------------------------------------------------------------------ 29第七节设备管理 ------------------------------------------------------------------------------------ 30第八节施工组织架构与岗位人员职责 --------------------------------------------------------- 32第四章施工总平面布置和施工准备 ------------------------------------ 34

施工组织设计总体方案

春晓东八路、洋沙山东八路工程 施工组织设计方案 第一章编制说明第一节编制依据 一) 由宁波市城建设计研究院有限公司提供的施工图 二) 《室外排水规范》(GB50014-2006) 三) 《城市道路设计规范》(CJJ 37-90) 四) 《公路路基施工技术规范》(JTG F10-2006) 五) 《公路路基设计规范》(JTG D30-2004) 六) 《公路水泥混凝土路面设计规范》(JTG D40-2002) 七) 《公路水泥混凝土路面施工技术规范》(JTG F30-2003) 八) 《公路沥青路面设计规范》(JTG D50-2006) 九) 《公路沥青路面施工技术规范》(JTG F40-2004) 十)《给水排水管道工程施工及验收 规范》(GB50268-2008) 十一)《公路桥涵设计通用规范》(JTG D60-2004) 十二)《公路钢筋混凝土及预应力混凝土桥涵设计规范》(JTG D62-2004) 十三)《公路土工合成材料应用技术规范》(JTJ/T019-98) 十四)《公路桥涵地基与基础设计规范》(JTG D63-2007) 十 五)《公路桥梁抗震设计细则》(JTG/T B02-01-2008) 十六)《宁波市建筑桩基设计与施工细 则》(2001 甬DBJ02-12) 十七)其他相关标准及规范 第二节编制原则 一) 遵照招标文件中的各项条款要求进行编制。 二) 按“项目法”的施工原则进行管理和施工,严格执行有关的施工规范和验收标准,按图施工。 三) 制定创优目标,严格执行各项施工保证措施,确保工程质量达到预定目标。 四) 保证重点、兼顾一般、统筹安排,科学合理地安排进度计划。 五) 采用先进的施工方案和技术管理措施,确保施工实施方案的可行性和合理性。 六) 制定施工所需的劳动力、材料及施工机具的投入计划,确保工程施工最合理的平面布置方案。 七)实行经济核算,推广增产节约,努力降低生产成本,提高经济效益。 八)编制详细的实施性施工实施方案,突出各重点部位的施工节点,工期网络和质量控制措施,经业主、监理和有关部门批准后严格执行施工。

油田保障点 施工组织设计

油田生产保障点工程施工组织设计 编制人: 审核人: 审批人: 工程有限公司 2018年3月

目录 1. 编制依据 2.施工组织部署 3.施工总体部署 4.施工进度计划 5.施工准备及资源配置计划 6、主要施工方法 7.施工现场平面布置及主要施工管理计划(保证措施)

123井区前线生产保障点工程 施工组织设计 一、编制依据 1、施工合同及施工许可证 (1)长庆油田分公司456产能建设123井区前线生产保障点工程施工许可证 (2)长庆油田分公司456产能建设123井区前线生产保障点工程施工合同 2、编制依据 (1)施工设计图纸及建设单位、监理单位现场施工技术交底。 (2)有关建筑工程的法令、法规。 (3)《建筑工程施工质量验收统一标准》(GB50300-2013) (4)《建筑地基基础工程施工质量验收规范》(GB50202-2012); (5)《砌体结构工程施工质量验收规范》(GB50203-2011); (6)《混凝土结构工程施工质量验收规范》(GB50204-2015); (7)《屋面工程质量验收规范》(GB50207-2012); (8)《钢结构工程施工质量验收规范》(GB50205-2002); (9)《建筑地面工程施工质量验收规范》(GB50209-2002); (10)《建筑装饰工程质量及验收规范》(GB50210-2002); (11)《石油天然气建设工程质量验收规范电气工程》(SY4206-2007) 二、工程概况 123井区前线生产保障点工程位于庆阳市环县境内,由陕西万豪建筑工程有限公司承担施工,由西安长庆工程建设监理有限公司456项目监理部监理。 主要工作量为:(1)宿舍及食堂905.5m21栋砖混结构 (2)煤棚13.7m2 1座砖混结构,轻钢屋面 (3)篮球场15mx14m 210m2 (4)道路及停车场宽4米 ,210m2 (5)铁艺大门宽4米1座 (6)人行才彩转铺地366M2 (7)铁艺围墙高2.2米230 (8)站内绿化1078m 绿化率30%

钢结构房施工组织设计方案

工程名称: 江苏康力源健身器材有限公司 钢结构1#、2#厂房工程 (技术标) 投 标 文 件 投标单位:江苏恒信钢结构有限公司 2016年9月12日 目录 一、各分部分项工程的主要施工方法和加工工艺 二、拟投入本工程的主要施工机械设备情况

三、劳动力安排计划 四、确保工程质量的技术组织措施 五、确保安全文明生产的技术组织措施 六、施工工艺流程图 七、施工总平面图 八、项目管理机构框架示意图 九、保修措施 十、有必要说明的其他内容 目录 第一章总则.................................................... 错误!未指定书签。第二章工程概况及质量目标...................................... 错误!未指定书签。 第1节工程概况............................................ 错误!未指定书签。 第2节质量目标............................................ 错误!未指定书签。

第三章施工准备................................................ 错误!未指定书签。 第1节材料、半成品........................................ 错误!未指定书签。 第2节作业条件............................................ 错误!未指定书签。第四章钢柱基础................................................ 错误!未指定书签。 第1节钢柱基础支承面形式.................................. 错误!未指定书签。 第2节钢柱基础调整方法.................................... 错误!未指定书签。 第3节钢柱基础质量标准.................................... 错误!未指定书签。第五章操作工艺................................................ 错误!未指定书签。 第1节工艺流程............................................ 错误!未指定书签。 第2节安装准备............................................ 错误!未指定书签。 第3节钢柱安装............................................ 错误!未指定书签。 第4节柱间刚性系杆安装.................................... 错误!未指定书签。 第5节钢梁拼装............................................ 错误!未指定书签。 第6节钢梁安装............................................ 错误!未指定书签。 第7节钢联系构件的安装.................................... 错误!未指定书签。 第8节屋面檩条系统安装.................................... 错误!未指定书签。

总施工组织设计方案模板

总施工组织设计方 案

第一章: 总体概述 第一节、工程简介: 1、工程名称: 广东第二师范学院番禺附属中学教学楼卫生间改建工程; 2、工程地点: 广东第二师范学院番禺附属中学内 3、建设单位: 广东第二师范学院番禺附属中学; 4、设计单位: 广州番禺区市桥建筑设计院有限公司 5. 监理单位: 广州城工建设监理有限公司; 6、工程规模及设计要求: 总建筑面积: 480.5㎡建筑层数: 地上 五层 ; 建筑工程等级: 三级 ; 结构形式:钢筋混凝土 框架结; 抗震设防烈度: 七度 ; 防火设计的的建筑 分类: 二类 该工程基础采用天然独立地基, 工程主体结构砼采用C25的商品砼, 结构墙体采用Mb7.5砂浆砌筑MU10蒸压加气砼砌块, 外窗户采用玻璃铝合金, 外墙饰面砖为条形砖。 第二节、项目管理目标 质量目标 本工程质量目标: 经过国家及行业质量验收达到合格标准。 工期目标 本工程暂定开工日期为12月13日。施工总工期60日历天,其中主体工程计划40个工作日内完成, 余下时间穿插着水电和装饰装修工程的施工。根据本工程的施工条件、施工地点、施工内

容及建设单位对工期的要求, 结合本公司的施工力量穿插着安排施工, 我司确保在60日历天内完成本工程施工。 安全生产文明施工目标 1、在施工期间严格遵守国家、省、市有关防火、防爆和施工安全的规定, 建立规章制度和防护措施。贯彻”安全第一, 预防为主”的方针, 有效地控制和防止事故的发生。实现: ①无工伤死亡事故; ②无交通死亡事故; ③无等级火警事故; ④无重伤事故, 轻伤事故率控制在3‰范围内; ⑤无倒塌、无中毒事故。 2、文明施工目标: 做好规划管理, 场容场貌创一流水平, 使本工程施工工地达到市级安全文明工地, 争创省级”双优”工地。 3、环境保护: 在施工过程严格遵守相关法规, 减少水污染、大气污染和噪声污染。 第三节、施工管理及计划 一、项目管理模式 我公司将委派具有同类工程承包经验和能力的项目经理和具有同类型工程施工管理经验的高素质的管理人员组成项目经理部, 对工程施工实施项目管理。项目经理部在总部和区域公司领导下充分发挥企业集团的整体优势, 标准模式建立管理体系, 形成以全面质量管理为中心环节, 以专业管理和计算机管理相结合的科学化管理为体制, 以便出众地实现对建设单位的承诺以及我公司的质量方针。 二、施工进度控制

石油化工工程施工组织设计

中化1200万吨/年炼油项目绿化工程标段Ⅲ 施 工 组 织 设 计 编制人: 复核人: 审批人: 禾鑫园林工程 项目部 二0一五年五月二十五日

目录 第一节工程概况及主要工程量 (1) 1编制依据 (1) 2工程概况 (1) 3 主要工程量 (2) 4 建设条件 (2) 第二节工程重点及施工难点分析 (4) 1场地施工重点及难点分析 (4) 2乔灌木种植重点及难点分析 (5) 3大树的栽植施工方案 (5) 4保护地下管线和周围构筑物的措施 (6) 第三节现场组织管理机构 (6) 1 施工组织机构设置和组织机构图 (6) 2 项目部管理职责 (7) 3 施工主要管理岗位职责 (8) 4 项目管理人员计划 (11) 第四节施工布署及工程进度 (12) 1 施工组织 (12) 2 施工总平面布置 (12) 3 工程进度 (13) 4 工程施工进度计划表 (14) 第五节人员、施工机具进场计划及进度的保证措施 (14)

2 施工机具计划 (15) 3 工程进度的保证措施 (15) 第六节主要施工技术方案 (19) 1施工测量技术方案 (19) 2绿化土方工程施工方案 (19) 3 绿化种植施工方案 (20) 4苗木反季节施工方案 (29) 5绿化养护施工方案 (31) 第七节质量保证措施 (34) 1质量方针和目标 (34) 2质量组织机构 (34) 3质量职责 (34) 4栽植基础工作 (36) 5栽植工作 (36) 6确定质量控制点 (38) 第八节HSE保证措施 (38) 1 HSE组织机构和职责 (38) 2施工机具 (40) 3开挖安全 (42)

房建施工组织设计方案

录目 4 ............................................................................... 1 综合说明 5 ........................................................................ 2 项目控制目标 6 ............................................................................... 3 编制依据 7 ............................................................. 4 工程概况与特点分析 7工程概况 ..................................................................... 4.1 9工程特点: ................................................................. 4.2 10.......................................................................... 施工部署5 .......................................................... 105.1 项目控制目标 ................................................. 10/项目管理组织 .5.2 施工 .......................................................... 125.3 项目

模板工程施工组织设计方案

宁晋名门世家 1# 楼 模 板 工 程 方 案 编制人: 审核人: 审批人: 编制日期:二零一二年二月三日 编制单位:建设集团

目录 第一节编制依据 第二节工程概况 第三节模板方案选择 第四节材料选择 第五节模板安装 第六节模板拆除 第七节模板技术措施 第八节安全、环保文明施工措施 第九节模板计算

第一节编制依据 《建筑结构荷载规》GB50009-2001中国建筑工业; 《混凝土结构设计规》GB50010-2002中国建筑工业; 《建筑施工计算手册》江正荣著中国建筑工业; 《建筑施工手册》第四版中国建筑工业; 《钢结构设计规》GB 50017-2003中国建筑工业; 第二节工程概况 一、工程建设概况 1、本工程为宝盈房地产开发建设开发的宁晋名门世家1#楼。本工程采用剪力墙结构体系,建筑抗震设防类别为标准设防类,结构安全等级为二级。剪力墙的抗震等级为三级。主楼基础采用钢筋混凝土筏板基础. 2、建设单位:宝盈房地产开发 监理单位:安泰建设监理 设计单位:威斯顿建筑设计分公司 施工单位:建设集团 二、建筑设计概况 地下建筑面积() 地上建筑面 积() 总建筑面积 ()

第三节模板方案选择 本工程考虑到施工工期、质量和安全要求,故在选择方案时,应充分考虑以下几点: 1、模板及其支架的结构设计,力求做到结构要安全可靠,造价经济合理。 2、在规定的条件下和规定的使用期限,能够充分满足预期的安全性和耐久性。 3、选用材料时,力求做到常见通用、可周转利用,便于保养维修。 4、结构选型时,力求做到受力明确,构造措施到位,升降搭拆方便,便于检查验收; 5、综合以上几点,模板及模板支架的搭设,还必须符合规检查标准要求,要符合省文明标化工地的有关标准。 6、结合模板及模板支架设计原则,同时结合本工程的实际情况,综合考虑了以往的施工经验选择合理的模板方案。 第四节材料选择 在模板满足强度、刚度和稳定性要求的前提下,尽可能提高表面光洁度,阴阳角模板统一整齐。 采用15mm厚清水墙板,木方作楞,配套穿墙螺栓M14使用。竖向楞采用40×80 木方,水平外楞采用48×3.5钢管。 第五节模板安装 1、一般要求 竖向结构钢筋等隐蔽工程验收完毕、施工缝处理完毕后准备模板安装。安装模板前,要清除杂物,焊接或修整模板的定位预埋件,预埋套管等,并经验收合格,做好测量放线工作。 2、±0.000以下模板安装要求 (1)底板模板安装顺序及技术要点 垫层施工完毕后进行底板模板安装,底板侧模全部采用砖模,沿底板边线外延20mm砌筑120mm厚砖墙,高度=底板厚+50mm,在底板厚度围砌筑永久性保护墙,砂浆采用1:3水泥砂浆,上面砌筑临时性保护墙,用混合砂浆砌筑,砖墙侧抹20mm厚1:3水泥砂浆。地下室墙体第一道水平施工缝留置在基础底板上

公路工程总体施工组织设计(doc 61页)

公路工程总体施工组织设计(doc 61页)

国道307平定城段改线工程(庙沟至西关段) 总 体 施 工 组 织

设 计 国道307平定城段改线工程项目部 2008年1月15日 施工组织设计目录 第一章:施工组织设计编制说明 第二章:工程概况 第三章:施工组织设计目标 第四章:施工总体部署及进场安排 第五章:各分项工程的施工顺序及时间安排 第六章:主要工程项目的施工方案 第七章:冬季雨季施工措施

第八章:确保工程质量和工期的措施 第九章:施工安全和环境保护的措施 第十章:附表 第一章施工组织设计编制说明 一、编制范围: 国道307平定城段改线工程(庙沟至西关段)范围内的路基、涵洞、排水及防护等有关项目。 二、编制原则: 1、质量目标:确保本工程达到优良。 2、工期目标:确保本工程在业主要求的时间内完成。 3、遵循有关文件中通用、专用条款原则。在编制施工组织设计文件时,做到统一标准,规范编制。 4、遵循设计文件、施工规范和有关质量验收评定标准的原则。在编写主要工程项目施工方法和技术措施时,严格按设计要求,并按

现行施工技术规范质量评定验收标准,科学组织施工,确保工程质量优良。 5、坚持实事求是的原则。在制定施工方案时,坚持科学组织,统筹安排,保证重点,均衡生产,确保高速度、高质量、高效益地完成本工程的施工。 6、坚持施工中严格管理的原则。在施工过程中,从加强基础管理入手,实现质量管理、进度控制、成本管理、安全生产及环境保护。 7、坚持在施工中推广和采用新技术、新工艺、新设备,不断优化、改进施工方案和技术措施。 8、加强精神文明建设和廉政建设。 三、编制依据: 本施工组织设计是在现场实地考察的基础上,根据设计文件及施工图纸等相关要求,结合我单位实际情况,经项目部相关职能部门研究讨论后制定的。 本施工组织设计的编制是以公司的施工技术力量和历年来省内外公路路基、路面、桥梁施工的经验作为基点,以“保部优,争国优”和提前竣工为目标,统筹考虑了全合同段的施工工艺,现场布置及施工进度计划。 本施工组织设计主要以下列文件和资料为依据: 1、业主汇编的“国道307平定城段改线工程(庙沟至西关段)”的设计文件及施工图纸。 2、《公路路基施工技术规范》(JTG F10-2006)

油田施工组织设计

1.1《施工组织设计》 1.1.1编制目的 为长庆油田公司第四采油厂云盘山作业区罗八增压站、罗一拉油转接站数字化建设工程提供指导性的施工方案与设计,用于工程的施工组织与管理,保证优质、高速、安全、文明地完成该工程的施工任务。施工组织设计是技术、经济和组织等方面的综合文件,是对施工全过程实行科学管理的重要手段。 1.1.2编制依据 1)根据长庆油田公司“标准化设计、模块化建设、数字化管理、市场化运作”的指导方针,编制数字化管理建设施工方案。 2)以产建工程方案或老油田调整改造方案的实施内容为编制依据。 国家现行的质量评定标准及有关施工标准、验收规范、规程和环境保护等地方性法规及规定。 ISO9000系列标准及西安冠林智能科技有限公司《质量手册》、《程序文件》。 1.1.3编制原则 认真执行工程建设程序。 搞好项目排队,保证重点,统筹安排。 遵循施工工艺及其技术规律,合理地安排施工程序和施工顺序 采用先进的施工方法和网络计划技术,组织有节奏、均衡、连续的施工 采用国内外先进的是技术和科学管理方法 科学布置施工平面,尽量减少暂设工程,合理地储备物资 1.1.4采用的标准 《数字化设计图纸》 CTEC161 GB50319-2000《建设工程监理规范》 GB 50168-2006《电气装置安装工程电缆线路施工及验收规范》 GB 50169-2006《电气装置安装工程接地装置施工及验收规范》 1

GB50093-2002《自动化仪表工程施工及验收规范》 GB-50303-2002《建筑电气工程施工质量验收规范》 SY4205-2007《石油天然气建设工程施工质量验收规范自动化仪表工程》 1.1.5工程实施目标 工期目标 工程建设总工期40日历天,计划开工时间为2010年9月15日,保证满足工程竣工日期2010年10月30日完成安装、测试并通过验收。加强协调管理,使得各施工顺序,衔接关系适当,施工科学、合理。保证计划总工期实现,力争提前完成合同工期。 质量目标 加强质量检查管理,建立质量管理体系,狠抓施工过程控制,使项目各子系统均达到或超过各行业的质量标准和质量等级,保证工程质量满足国家《工程施工质量验收规范》的合格及长庆油田数字化管理项目竣工验收规定(暂行) 环境保护目标 采取有效措施,避免施工扰民,最大限度地减少对环境的污染。 安全生产目标 建立完整的安全管理体系,整个工程期间杜绝人员伤亡事故,轻伤事故不超过0.1%,年工伤频次在1‰以下。 1.1.6项目工程量 项目包括罗八增压站、罗一拉油转接站2座,15个井场,共61口油井。 单井场工程量: ●每台抽油机电机加装井口采集器并将信号送入主RTU; ●每台抽油机安装无线载荷和位移传感器,并将控制电缆接入井口采集器; ●井口压力数据接入主RTU,并敷设电缆; ●注水井压力接入阀组RTU,并敷设电缆; 2

房屋工程施工组织设计方案

房屋施工组织设计方案 第一卷编制依据 (一)施工图 (二)主要图集、标准、法规、规程、规

(三)建设单位提供施工用地、水、电等条件 建设单位提供施工用地600m2,建筑面积为95.85m2,施工现场场地基本能满足施工要求。 水、电按建设单位指定地点引入,提供150KW电源。

第二卷工程概况 (一)工程简介 (二)建筑设计特点

(三)结构设计特点

第三卷施工部署 (一)工程目标 1、质量目标:满足施工验收规要求,质量合格。 2、安全目标:确保无重伤、无死亡事故。 3、工期目标:科学组织施工,合理安排工序穿插,确保合同工期实现。 4、现场管理目标:市文明安全工地。 5、管理体系:管理机制采用项目法施工管理。质量体系经认证并符合GB/T19002—1994idt ISO9002:1994标准的质量体系。

(二)管理组织机构 1、组织机构:本工程按项目法组织施工,所派项目经理承担过鲁班奖工程项目管理,并积累了丰富的施工管理经验的一级项目经理担任;项目总工选派有较高技术管理水平、并有创优管理经验、参加过获优质工程项目管理的工程技术人员任本项目总工程师。根据工程特点,组建精干项目经理部,对本项目的人、财、物按照项目法施工管理的要行统一组织,统一布置,统一计划,统一协调,统一管理,并认真执行ISO9002质量标准,充分发挥各职能部门、各岗位人员的职能作用,认真履行管理职责,确保本项目质量体系持续、有效的运行。通过我们科学、严谨的工作质量和项目管理经验,确保实现合同规定的工期、结构工程创结构长城杯、单位工程创市优质工程、现场达省江市文明安全工地的预定目标。 项目部班子主要成员及各主要组室的职责执行我单位的《质量手册》和《程序文件》。 (1)领导班子:由项目经理、项目副经理、项目总工程师组成,负责对工程的领导、指挥、协调、决策等重大事宜,对工程进度、成本、质量、安全和创优及现场文明施工等负全部责任。 (2)技术部:负责编制工程施工组织设计,并在施工过程中进行动态管理,完善施工方案,对施工工序进行技术交底,组织技术培训,办理工程变更,及时收集整理工程技术档案,组织材料检验、试验、施工试验和施工测量,检查监督工序质量,调整工序设计,并及时解决施工中出现的一切技术问题。

模板施工组织设计方案

xx花园三期C区工程 模板施工组织设计方案 编制:xxx 审核:xxx 审批:xxx 编制单位:xxxx建筑安装工程有限公司编制时间:二0一0年七月二十五日 xx花园三期C区工程

1.工程概况: 1.1工程总体概况 工程名称:xx花园三期C区工程 工程地点:xx经济开发区 建设单位:xxx经济开发区投资发展有限公司 设计单位:xxxx工程设计有限公司 工期:210天 1.2工程建筑概况 建筑总面积:6882.4m2 建筑层次:五层 2.模板设计思想: 2.1根据工程特点及合同计划要求,本工程工期为7月,由于前期拆迁工作拖延比较长,导致工期非常紧张,主要影响工程进度因数集中地主体施工上,其中模板安装进度直接影响工程进程,因此如何抓好工程进度确保质量,特别是模板工程的安装质量,成为项目经理部质量工作的重中之重。 2.2工程中的拟采用清水模板,根据施工图施工组织设计及我司实际情况,参照有关施工规范进行模板设计,确定木模板制作几何形状、尺寸要求,龙骨的规格,间距、选用支架系统,支撑间距,绘制各部砼模板设计图,编制工艺要求及说明。 3.施工准备: 3.1主要材料及机具: 3.1.1胶合板(1830×915×18、2440×1220×18双面刷脱模剂),松方木(50×105mm统一压刨50×100mm),木档(50×50mm) 3.1.2钢管支架,对拉螺柱、托具、卡具,压刨机、木工电锯等 3.2作业条件 3.2.1模板数量已按模板设计方案结合施工流水段的划分以及工期要求,确定模板套数。

3.2.2根据图纸要求,放好轴线和模板边线,定好水平控制标高。 3.2.3柱钢筋绑扎完后,水电管及预埋件已安装、通过隐蔽验收手续。 3.2.4根据模板方案,图纸要求和工艺标准,以书面形式向班组进行安全,技术交底。 4.模板设计: 4.1柱模板 4.1.1构造 柱柜由四面侧板,柱箍、支撑组成,其中柱侧采用大模裁割,纵向拼接,则模板接缝较少(如图①) 柱顶与梁交接处,留出缺口、缺口尺寸即为梁的高及宽(梁高以扣除平板厚度计算),并在缺口两侧及口底钉上衬口档,衬口档离缺口边的距离即为梁侧板及底板的厚度,衬口档为50×50mm木档,与梁柱接面刨平,拼接密实。 柱侧模外设竖向方木楞,方木楞与柱接面刨平,木楞以刨平面顶边压缝,如图② 柱截面大于500mm的柱模,在其中部设M12穿墙螺栓@800,柱模外设置Φ48@500钢管箍,以防止砼浇筑模板产生膨胀变形,安装。 柱模板安装时、先在基础面(或楼面)上弹柱轴线及边线。同一柱列应先弹两端柱轴线边线,然后拉通线弹出中间部分柱的轴线及边线,按照边线先把底部方盘固定好,再对准边线安装底部侧模,用临时支撑支牢,吊线调整垂直度,上口模外侧设高出板模50mm木档圈边锁口,再支设上部侧模,将中部接口档钉紧,调整柱口尺寸,钉紧侧模后,用线坠校正垂直度,用支撑加以固定,为保证柱模稳定,柱钢管箍与梁板立杆应联系牢固,柱模设剪力撑在梁板杆交接点周围与立杆系拉接固定。 柱拉结筋拟采用预埋后焊,在靠砼柱面相应柱侧模以间距500MM,定出预埋件位置,如图将预埋件钉干柱内侧模。 同一柱列模,采取先校正两端的柱模,在柱模顶中心拉通线,按通线校正中间部分。 4.2梁模板 4.2.1构造要求:

抽油机施工组织设计汇总

施工组织设计(方案) 编制人: 审批人: 批准人: 施工单位:江汉油田瑞腾达工程有限责任公司 工程地点:甘肃省合水县 二00九年八月十日

目录 1、编制依据 (1) 2、工程概况 (2) 3、施工部署 (2) 3.1总体部署 (2) 3.2组织机构 (2) 3.3职责 (3) 3.4施工力量配备 (3) 4、施工准备 (4) 5、施工方案及技术措施 (6) 5.1总体施工方案……………………………………………………

6 6、质量和HSE管理措施 (6) 7、工期保证措施 (19) 1.编制依据 《石油天然气站内工艺管工程道施工及验收规范》SY0402—2000 《油田集输管道施工及验收规范》SY0422—97 《油气田地面管线和设备涂色标准》SY0043—96《工业金属管道工程施工及验收规范》GB50235—97 《现场设备、工业管道焊接工程及验收规范》GB50236—98 《手焊、手工电弧焊及气体保护焊缝破口的基本形式与尺寸》GB985

《双金属复合管道焊接工程施工及验收规范》Q/SY04—2001 《油田油气处理用钢制压力容器施工及验收规范》SY/T0448—97 《涂装前钢材表面预处理规范》SY/T0407—97《钢制容器防腐和保温工程施工及验收规范》SY/T4059—93 《工业设备及管道绝热过程施工及验收规范》GBJ126—89《通风与空调工程施工及验收规范》GB50243—97 《电气装置安装工程电力变压器、油浸电抗器、互感器施工及验收规范》GBJ148—90 《电气装置工程母线装置施工及验收规范》GBJ149—90《电气装置安装工程电气设备交接试验标准》GB50150—91 《电气装置安装工程电缆线路施工及验收规范》GB50168—92 《电气装置安装工程接地装置施工及验收规范》GB50169—92 《电气装置安装工程旋转电机施工及验收规范》GB50170—92 《电气装置安装工程盘、柜及二次回路接线施工及验收规范》GB50171—92《施工现场临时用电安全技术规范》JBJ46—88《电气装置安装工程低压电器施工及验收规范》GB50254—96 《石油建设工程质量检验标准建筑工程》SY4025—93《地基与基础工程施工及验收规范》GBJ202—88《建筑工程施工质量验收统一标准》GB50300—2001

最新版房屋修缮工程施工组织设计方案

房屋修缮工程施工组织设计方案

第一章工程概况 一、工程基本概况 项目名称:**市公安局连山分局案件审核管理改革“一队两中心”建设项目建设地点:项目单位指定地点 计划工期:合同签订后50天内完成 工程质量:合格 二、本工程的施工特点 1、本工程在施工时间内须严格遵守国家、省、市对文明施工管理要求,项目经理要精心组织、科学安排施工流程,并根据现场施工进度的要求,合理计划材料、机具的进场时间、顺序,对施工现场进行合理的安排、使用。 2、本工程的工期要求紧,质量要求较高,因此如何合理安排好施工进度,完善施工措施、确保本工程的质量,按照合同工期完成,就成了本工程的重点和难点问题。 3、由于工期要求紧,各个专业间要相互交叉作业,必须在施工前互相交底配合。 三、本工程主要施工内容

**市公安局连山分局案件审核管理改革“一队两中心”建设项目施工内容(招标范围):室内装修工程包括拆除工程、楼地面工程、墙面工程、天棚工程、门窗工程、电气及水暖工程等。 四、成立精干高效的管理机构 为确保本项目的顺利实施完成各项预计的目标,现场成立项目部,由项目经理负责本工程总体部署和组织。 五、安全文明施工目标 1、开创良好的文明安全施工环境,达到省、市安全文明施工现场标准,组织好文明施工,安全生产,维护好社会秩序、保证施工正常进行,对本工程的顺利施工,具有举足轻重的作用。 2、本公司有着多年装饰装修、改造、维修施工的丰富经验,在非常困难、复杂的环境下成功地组织多项工程顺利施工及时稳妥地解决扰客、扰民、经营、交通、消防、防卫、治安等各项工作,取得了所承建过的施工项目的建设单位的充分信任和理解,创造了良好的社会信誉。 六、施工准备 1、关联原则:装饰工程准备工作不仅需要详细了解装饰本身的设计要求,而且要了解与之关联的通风、给排水工程的设计要求及其施工情况。

模板工程施工组织设计方案

、编制依据: 1)、主要依据施工图纸。 2)、甘肃XXXX发电有限责任公司16#住宅楼工程施工组织设计。 3)、规程、规范:混凝土结构工程施工质量验收规范(GB50204—2002). 二、工程概况: 1)、建筑面积:8905.5 m2,层数,地上六层。 3)、结构形式: 基础结构形式:井桩基础,基础梁。 主体结构形式:砖混结构。 4)、结构断面尺寸:①外墙厚度370伽厚。 ② 内墙厚度240 mm厚。 @两断面尺寸:见施工图。 三、施工准备; 1)、项目部技术负责人组织生产人员熟悉图纸,认真学习掌握施工图的内容,熟悉截面尺寸,标高,制定模板初步设计方案。 2)、机具准备:O、锤子、单头扳手、手提电锯、手提压刨、打眼电锯、线坠、方尺、铁 撬辊、水准仪等。 ②、支撑体系:柱箍、钢管支柱、钢管脚手架。 ③、材料准备:顶板、梁、柱,竹胶板,支撑采用巾48X 3.5钢 架杆,隔离剂用水性隔离剂。 四、主要施工方法及措施: 1)、模板设计: 1、垫层模板:垫层厚度为100伽,垫层模板采用钢模板。沿垫层边线设置方木,方木支撑在基坑壁上,如果支撑不到基坑壁上,用巾12钢筋棒插入地面固定模板。 2、柱模板:柱模板采用小型钢模板,竖楞采用50X 100方木,方木均经压刨找平,每20 cm—道,柱箍采用钢管,每40 cm—道,最底一层距地面300 mm,其板块与板块竖向接缝处理做成企口式拼接,然后加柱箍,支撑体系将柱固定,支撑采用 巾48X 3.5 m架子管钢支撑。 3、梁板模板:梁的底模与侧模均采用10 m厚竹胶板,柱龙骨采用,50X 100m @600单面

刨光方木,次龙骨采用50X 100伽@200双面刨光方木,梁侧模,梁底模按图纸尺寸进行现场加工,然后加横楞并利用支撑体系将梁两侧夹紧,在梁h/2 处加M4穿墙螺栓@600 板模板采用10伽厚度竹胶板,柱龙骨采用100X 100@120nm单面刨光方木,次龙骨选用 50X 200@200mm双面刨光方木,为保证板的整体混凝土成型效果,将整个顶板的竹胶板按同一顺序,同一方向对缝平铺,必须接缝处,下方有龙骨,且接缝严密,表面无错台现象,若与柱相交,则不可意躲开柱头,只在该处将多层板锯开与柱尺寸相应洞口,下垫方木作为柱头的龙骨。 2)、模板加工: 柱梁的模板加工必须满足截面尺寸,两对角线误差小于1伽尺寸过大的模板需 进行刨边,否则禁止使用,次龙骨必须双面刨光,主龙骨至少要一面刨光,翘曲、变形的方木,不得作为方木使用,模板加工完毕后,必须经过项目技术人员验收合格后方可使用。 3)、模板安装: 1、模板安装的一般要求: 竖向结构钢筋等隐蔽工程验收完毕,施工逢处理完毕后,准备模板安装,安装柱模前, 要清除杂物, 焊接或修整模板的定位预埋件,做好测量放线工作, 抹好模板下的找平砂浆 2、梁模板安装顺序及技术要点: ①、模板安装顺序:搭社和调整模板支架—按标高铺梁底模板—拉线找直—绑扎梁钢筋f安装垫块f梁两侧模板f调整模板 ②、技术要点:按设计要求起拱(跨度大于4m时,起拱2%。)并注意梁的侧模包住底模, 下面龙骨包住侧模. 3、板模板安装顺序及技术要点: ①、模板安装顺序:满堂脚手架—主龙骨—次龙骨—柱头模板龙骨—柱头模板顶板模板—拼装—顶板内、外墙柱头模板龙骨—模板调平验收—进行下道工序. ②、技术要点:楼板模板当采用单块就位时,宜以每个铺设单元从四周先用阳角模板与墙、梁模板连接,然后向中央铺设,按设计要求起拱(跨度大于4m时,起拱2%)起拱部分为中间起拱,四周不起拱。 4、柱模板安装顺序及技术要点: ①、柱模板安装顺序:搭设脚手架—柱模就位安装—安装柱模—安设支撑—固定柱模—浇筑混凝土—拆除脚手架、模板—清理模板。 ②、技术要点:板块竖向接缝处理,做成企口拼接,然后加柱箍,支撑体系将柱固定 4)、模板的拆除: 1、柱模板拆除:在混凝土强度达到1.2MPa能保证其表面棱角不应拆除模板而收损后方可拆除,拆除顺序为先纵墙后横墙,脱模困难时,可用撬棍在模板底部撬 动,晃动或用大垂砸模板,拆下的模板及时清理,刷好隔离剂,做好模板检验批质量验收记录,保证使用质量。