目录

一、编制依据 ·······························································································- 1 -

二、工程概况 ·······························································································- 1 -

三、施工进度计划及保证措施··········································································- 2 -

1、工期目标 (2)

四、施工人员、机械设备配置··········································································- 2 -

4.1.人员配置 (2)

3.2机械设备配置 (3)

五、施工工艺与流程······················································································- 4 -

5.1钢支撑支护施工工艺 (4)

5.2钢支撑支护施工流程 (4)

六、质量控制 ·······························································································- 6 -

6.1钢支撑支护质量控制基本要求 (6)

6.2钢支撑具体质量控制措施 (7)

七、安全保证措施 ·························································································- 8 -

7.1建立安全保证体系 (8)

7.2安全教育和培训 (8)

7.3落实安全责任制,制定安全管理的各项规章制度 (8)

7.4钢支撑针对性安全技术措施 (8)

八、环境保护措施 ······················································································· - 10 -

8.1组织措施 (10)

8.2防止大气污染措施 (10)

8.3防止水污染措施 (11)

8.4防止施工噪声污染措施 (11)

一、编制依据

1.1、海西高速公路网厦沙线三明段A8合同段两阶段施工图设计图纸。

1.2、《公路隧道施工技术规范》(JTG F60-2009)

1.3、《公路工程施工安全技术规范》(JTJ076-95)

1.4、《公路工程质量检验评定标准》(JTG F80/1-2004)

1.5、《公路工程国内招标文件范本》(2003年版)。

1.6、现场踏勘及调查了解的施工环境、条件等。

1.7、福建省高速公路《隧道施工标准化指南》。

二、工程概况

本合同段秀村隧道左线起点桩号YK163+500,终点桩号YK167+322,长3822米,本合同段的地势为南北高中间低,沿线多有河流阶地、山间河谷、谷地及小盆地等,地形较复杂,坡地天然坡度10-45°,天然边坡稳定,沿线最高海拔位于秀村隧道主峰五马落槽,标高约为1021米,河谷阶地多分布于沙溪两岸,标高50-150米,地形起伏较大,在凸岸多以堆积作用为主、在凹岸多以侵蚀作用为主。

施工里程: ZK163+500~ZK167+322,设计支护类型表1:

五道岭隧道衬砌施工方案

五道岭衬砌施工方案 一、工程概况 五道岭隧道右幅起讫里程桩号为:YK9+780~YK12+865,隧道全长3085米;左幅起讫里程桩号为:ZK9+655~ZK12+815,隧道全长3160米;洞内设有5处人行横洞,3处车行横洞。设计行车速度80Km/h,隧道净宽14.0米,净高5.0米。隧道净空断面采用三心圆曲墙式衬砌,隧道洞身所穿越围岩为Ⅴ~Ⅲ级以及断层带,衬砌类型为复合式衬砌。除Ⅲ级围岩段外,其余Ⅳ、Ⅴ、Sm、断层带围岩段均有仰拱,衬砌砼厚度为45~70cm,二次衬砌采用C30泵送自防水砼结构,抗渗标号达S8。 二、衬砌施工的总体安排 衬砌采取先仰拱、后拱墙的施工顺序,衬砌施工时先安装防、排水设施及预留洞室然后安装二衬钢筋进行衬砌。为了掌子面出碴不受衬砌施工的影响,仰拱及填充砼采用半幅施工,拱墙衬砌采用一次成型方式,衬砌台车由项目部统一定制,衬砌台车长度12m ,进出口各两台,隧道仰拱距离掘进工作面不得大于50m,衬砌距离掘进工作面最大不得大于200m。计划开工时间:2008年10月10日,计划完工日期:2009年10月5日,具体安排见“施工进度计划横道图”。

三、劳动力安排 为确保隧道按期、优质、安全的完成施工,五道岭隧道左右幅进出口各安排一个衬砌施工队。衬砌施工队包括台车定位、混凝土浇筑、钢筋、防水板帮扎及杂工班,台车定位工班负责衬砌台车的脱模、运行、定位、挡头板安装等工序,混凝土浇筑工班主要负责衬砌砼的灌注,钢筋、防水板帮扎工班主要负责衬砌预埋钢筋、防水板、止水带、及预埋件的安装工作。劳动力安排见下表: 隧道衬砌队劳动力工种安排表(人) 四、施工方法及要求 Ⅰ、衬砌防排水施工 本隧道防排水遵循“防、排、截、堵结合,因地制宜,综合治理”的原则,保证结构和设备的正常使用和行车安全。 1、防水工程 (1)衬砌柔性防水:在衬砌背面设置隧道专用防水卷材,无纺土工布设置在防水卷材与喷射砼层之间,兼作衬背排水层及缓冲层,无纺布规格为400g/m2,采用射钉加钢垫圈固定在基面上。 (2)衬砌漏防水:衬砌防水采用在初期支护与二次衬砌之间敷设一层PVC+土工布的复合防水卷材,做为第一道防水措施,防水卷材敷设

钢支撑架设及拆除专项施工方案

目录 一、编制说明 (1) 1.1.编制依据 (1) 1.2.编制原则 (2) 1.3.编制范围 (3) 二、工程概况 (3) 2.1.工程地点及内容 (3) 2.2.支撑形式 (3) 三、钢支撑架设施工 (3) 3.1.施工工艺流程 (4) 3.2.钢支撑安装 (4) 3.3.支撑安装技术措施 (8) 四、钢支撑拆除 (9) 4.1.施工工艺流程 (9) 4.2.脚手架支撑 (9) 4.3.分级卸力 (9) 4.4.吊运 (10) 五、质量保证措施 (10) 六、安全保证措施 (11) 七、文明施工措施 (12) 一、编制说明 1.1.编制依据 (1)长沙市轨道交通2号线一期工程SG—1标段施工合同。 (2)长沙市轨道交通2号线一期工程土建项目招投标文件:招标编号CSGD Ⅱ—1—TJ; (3)长沙市轨道交通2号线一期工程土建项目设计图纸和设计交底; (4)长沙市轨道交通2号线一期工程土建施工项目招标答疑文件;

(5)遵照的部分技术标准和规范如下: 国标GB/T19001标准;安全、环境和职业健康GB/T24001/28001 《地下铁道设计规范》(GB50157-2003) 《地下铁道工程施工及验收规范》(GB50299-1999) 《地下铁道、轨道交通工程测量规范》(GB50308-2008) 《建筑基坑支护工程技术规程》(JGJ/120-99) 《建筑地基基础工程施工质量验收规范》(GB50202-2002) 《建筑基坑工程技术规范》(YBJ9258-97) 《建筑安装工程质量验收统一标准》(GBJ300-88) 《工程测量规范》(GB50026-2007) 《城市测量规范》(CJJ8-99) 《建设工程施工现场管理规定》(建设部) 《建筑钢结构荷载规范》(GB50009-2001) 建筑钢结构焊接技术规程(JGJ81-2002) (6)我公司现有的施工技术、管理水平及机械配套能力。 (7)我公司地铁施工及其他类似工程的成功经验和科研成果。 (8)施工现场详细调查和踏勘资料。 1.2.编制原则 (1)全面响应施工合同,严格遵守施工合同所有条款; (2)满足业主对质量、安全、工期、文明施工等方面的规定和要求,确保高效优质完成本标段内所有工程; (3)综合考虑本工程特点、重点、难点采用先进、科学、成熟、有效的施工方案,并结合本投标人历年轨道交通施工经验,使施工组织设计具有合理性、全面性、实用性; (4)本工程地长沙市主要街道,减少对周边环境的影响; (5)采用科学合理的监控措施和信息反馈系统指导施工;

隧道初期支护施工方案

南龙铁路扩能工程NLZQ-3标 城关隧道初期支护施工方案 一、编制依据 1、NLZQ-3标段城关隧道设计图(南龙施(隧)17)。 2、铁路隧道工程施工质量验收标准TB10417-2003 3、新建时速200公里客货共线铁路工程施工质量验收暂行标准 4、高速铁路隧道工程施工技术指南(铁建设[2010]241号)。 5、铁路隧道工程施工安全技术规程TB10304-2009 二、工程概况 起讫里程为DK62+905~DK70+211,隧道全长7306m。 隧道设置单车道斜井一座,斜井位于线路前进方向左侧,与左线线路中线相交于DK65+904处,与线路小里程方向夹角为45°,综合坡度7.85%,长度395m。 隧道DK64+913.87~DK68+631.90段3718.03m位于右偏曲线上,纵坡为单面上坡,进口段坡度3.0%,出口段坡度9.408%,变坡里程DK65+900。 隧道围岩分级,Ⅱ级围岩5865延米,占整个隧道80.28%,Ⅲ级围岩895延米,占整个隧道12.25%,Ⅳ级围岩385延米,占整个隧道5.27%,Ⅴ级围岩161延米,占整个隧道2.20% 。 隧址区地层主要为,白垩系沙县组(K2S)粉砂岩、侏罗系兜岭群(J3dl)凝灰熔岩、喜马拉雅期侵入(γ∏)花岗岩,此外零星分布有第四系坡积层及杂填土。粉砂岩、凝灰熔岩主要分布在隧道进口段,花岗岩主要分布在出口段。 隧道区埋深≥350m的地段DK69+619~DK69+654段地温温度≥28°,属存在地温危害的区域。 隧道埋深≥340m的深埋段凝灰岩、花岗岩地段,构造简单,较不利于围岩应力释放,为高应力-极高应力区。 隧址区发育有2条断层,F1断层,位于DK63+484附近,断层破

预应力钢支撑施工方案

预应力装配式钢支撑 施 工 方 案 编制: 审核: 2018年1月

预应力钢支撑施工方案 根据基坑支护工程设计图要求,本工程采取一道支撑围檩,平面布置图如下: 1、安装前准备工作 1、现场准备 ⑴现场了解工程面貌、环境情况及供电位置。 ⑵确定现场钢构件堆放位置和施工机械进出场线路。 ⑶清理施工道路和出行路线。 2、施工现场布置 本工程中装配式组合内支撑施工阶段,主要的材料及设施有:型钢围檩、支撑构配件、堆放场地;施工机具如挖机、吊机、电焊机等。

3、安装前期准备 根据土建施工的施工计划要求,在装配式支撑构件安装前,必须对安装现场进行调查。针对本工程,主要掌握以下情况: ⑴道路是否具备车辆进出条件。 ⑵现场环境是否具备构件堆放要求。 ⑶复核安装定位使用的轴线控制点和测量标高的基准点。 ⑷配套构件及预埋件是否满足图纸要求。 ⑸与其他协作单位配合中是否存在障碍。 ⑹施工人员的现场辅助设施是否符合标准。 4、装配式组合内支撑构件配套供应 现场钢构件吊装是根据预先制定的安装流水顺序进行的,运输到现场指定位置的编号构件至少提前一天进场,以满足吊装进度要求,进场构件要参照设计方案及吊装区域合理分布。 根据现场吊装进度计划,提前一周通知加工厂,使加工厂随时掌握现场安装届时所需构件的进场时间。 5、钢构件堆场安排、清理 按照安装流水顺序将配套好运入现场的钢构件,利用挖机、吊车、塔吊尽量将其就位到吊车的回转半径内。钢构件堆放应安全、整齐、防止构件受压变形损坏。构件吊装前必须清理干净,特别在接触面、摩擦面上,必须用钢丝刷清除铁锈、污物等。 6、现场立柱检查 立柱为管桩立柱,施工过程严格控制立柱的插入深度及角度、垂直度等,之后再进行装配式组合内支撑的托座及横梁施工。要求立柱的施工必须对定位轴线的间距进行测量,复核检查。 7、吊装区域划分及施工工艺流程 根据总包单位土方开挖进度,全力配合施工。遵循“竖向分层,纵向分段”“开槽支撑、先撑后挖、分层开挖、严禁超挖”的总体原则。土方开挖到标高后立即做好第一道装配式钢支撑,并施加预应力。 ⑴施工顺序如下: 施工准备→立柱施工→钢围檩施工→土方开挖→开槽施工牛腿、钢横梁施工→支撑安装施工→预应力施加→土方工程和支撑工程循环施工,直至基坑底→做地下室结构、

钢支撑施工方案

南京新港研发中心大楼工程基坑支护基坑支护 钢支撑工程 施 工 方 案 编制人: 审核人: 批准: 南京海通建设工程有限公司 2012-05-21

南京新港研发中心大楼工程基坑支护 钢支撑工程施工方案 一.编制依据: 建筑结构荷载规范(GB50009-2001) 建筑基坑支护技术规程(JGJ120-99) 建筑地基基础设计规范(GB50007-2002) 建筑地基基础工程施工质量验收规范(GB50202-2002) 钢结构设计规范(GB50017-2002) 二、工程概况: 、基本概况: 1、工程名称:南京新港研发中心大楼建设项目; 2、基坑规模:基坑面积约18000平方米,周长约560米。 3、基坑开挖深度:本工程±相当于绝对标高,图中所示标高均为相对标高。地面标高为:,基坑开挖深度为。 、基坑支护结构: 1、AB、BC、DE、FG段采用φ900@1100钻孔灌注桩+一层支撑进行支护(局部二层); 2、CD、DE段采用φ1000@1200钻孔灌注桩+一层钢支撑进行支护; 3、其他段采用φ800@1000钻孔灌注桩+一层钢支撑进行支护(局部二层). 、钢支撑概况:

本工程为了确保地下室结构施工安全施工,基坑支护二层部位按设计要求为钢支撑。主撑采用Φ609×12钢管,钢围檩采用H400×400×13×21型钢双拼。基坑开挖必须先撑后挖,支撑的拆除必须满足砼结构设计后方可拆除。 、专业工程特点: 钢结构支撑拼装和拆除方便、迅速,为工具式支撑,可多次重复且可施加预应力,有一定的优点。但与钢筋砼支撑相比,变形较大,比较敏感,且由于圆钢管和型钢的承载力不如钢筋砼支撑。因而支撑水平间距不能很大。钢支撑可通过多次连续施加预应力来控制变形。 三、钢围檩及钢管撑施工方案 钢支撑的架设是保证基坑开挖和主体结构施工安全、控制基坑收敛和位移的有效措施。明挖基坑水平支撑共设2层,第二层纵向设钢围檩。钢支撑采用钢管Φ609×12加工制作,钢围檩采用H400×400×13×21型钢双拼组成,两片之间采用钢板连接成整体,长度可以根据实际情况加工。钢支撑与钢围檩之间采用千斤顶施加预应力,顶紧后焊接固定。钢围檩与桩体连接采用钢楔顶紧,基坑四个角为角撑,基坑中部为水平撑。 (1)钢支撑的组成 第一道钢支撑由钢管、钢筋砼圈梁及其附属构建组成。钢支撑钢管型号为φ609mm,t=12mm。 第二道设钢围檩,由H400×400×13×21型钢双拼、外肋板、内肋板、钢缀板、连续肋板焊接而成。附属构件有活络头、钢楔、钢板及与

隧道二次衬砌工程专项施工方案

武汉市花山大道新建工程光谷五路至武九铁路段施工总承包项目经理部 隧道二次衬砌工程 专项施工方案 中国核工业中原建设有限公司 批准: 审核: 校核: 编制:姚冰 二〇一〇年十月

目录 1.编制依据 (4) 2.编制原则 (4) 3.工程概况 (4) 3.1工程简介 (4) 3.2主要设计技术指标 (5) 4.材料与试验 (5) 4.1材料检测 (5) 4.2施工现场砼检测 (5) 5.施工计划 (6) 6.机械设备与人员配备 (6) 6.1劳动力安排 (6) 6.2机械设备配置 (7) 7.施工工艺 (8) 7.1衬砌施工工艺 (8) 7.2衬砌施工方法 (9) 7.3拱顶衬砌混凝土施工 (9) 7.4衬砌背后压浆 (10) 8.质量检验 (10) 8.1主控项目 (10)

8.2一般项目 (13) 9.质量保证措施 (13) 10.保证安全的主要措施 (15) 11.文明施工 (15) 12.环境保护 (16)

1.编制依据 武汉市花山大道新建工程光谷五路至武九铁路隧道施工设计图纸; 《地下工程防水技术规范》(GB50108-2008) 《地下防水工程质量验收规范》(GB50208-2002) 《公路隧道设计规范》(JTG D70-2004); 《公路隧道施工技术细则》(JTG/T F60-2009); 《公路工程质量检验评定标准》(JTG/T F80/1-2004) 2.编制原则 公路隧道二衬施工方案根据各隧道的设计图纸、洞内围岩级别,选择适宜的方法进行施工;采用新技术、新设备、新方案,做到适用性和先进性相结合,进行技术经济方案的比选,选择最优方案施工;提高施工机械化水平,提高劳动生产率,加快施工进度,确保工程质量。总结经验教训,不断的提高隧道工程二衬施工质量,为隧道工程施工安全保驾护航。 隧道二衬施工方案除应符合《公路隧道施工技术细则》外,尚应符合环境保护和劳动卫生有关法律、法规的要求。 3.工程概况 3.1工程简介 工程花山大道东湖高新段自光谷五路至武九铁路(K-1+720~K3+920),长约

钢支撑安拆专项施工方案

钢支撑安拆专项施工方 案 -CAL-FENGHAI-(2020YEAR-YICAI)_JINGBIAN

钢支撑安拆专项施工方案 一、工程概况 本工程标段隧道基坑西起古墩路以西K1+538,东至丰潭路以东K2+848,全长1310m,其中隧道U型槽范围为K1+538~K1+735、K2+585~K2+848,总长460m;隧道暗埋段范围为K1+735~K2+585,总长850m。 本次隧道工程采用明挖顺做法施工,隧道基坑围护设计中,U型槽段基坑挖深较浅,采用放坡开挖或1~2道钢管支撑条件下开挖;暗埋段基坑挖深10~16m,采用3~4道支撑条件下开挖,暗埋段除第1道支撑采用钢筋砼支撑外,其余2~3道支撑均为钢管支撑。本工程设计钢管支撑直径609mm,壁厚16mm。 基坑开挖运用时空效应原理指导基坑施工,土方开挖遵循“分层、分段开挖,严禁超挖”及“先支护,后开挖”等原则。在各道支撑的土层开挖过程中,要求每段开挖长度控制在6m内,并及时安装好该段钢支撑或钢斜撑,并施加预应力,待结构底板强度达到100%后方可拆除最下道钢支撑,拆除自下而上第二道钢支撑前应进行换撑,即在结构侧墙处架设钢支撑,并施加预应力。 二、编制依据 1、《标段基坑围护工程调整施工图设计》; 2、《标段隧道结构工程施工图设计》; 3、《标段隧道深基坑施工方案》; 4、《标段隧道深基坑监测方案》; 5、《标段岩土工程勘察报告》; 6、《建筑基坑支护技术规程》(JGJ120-99); 7、《建筑钢结构焊接技术规程》(JGJ81-2002); 8、《建筑工程施工现场供用电安全规范》(JG50194-93); 9、《建筑地基基础工程施工质量验收规范》(GB50202-2002) 10、《建筑安装工程质量验收统一标准》(GBJ300-88) 11、我单位在以往类似工程施工中所积累的成熟施工技术和施工管理经验。 三、施工步骤及流程 本工程隧道结构采用明挖顺做法施工,施工中Φ609钢管支撑安装与土方开挖两工序密切结合,施工步骤如下(按标准暗埋段):

隧道施工方案45919

隧道工程施工工艺 一、总体方案 (一)施工原则 采用大型施工机械配套施工,开挖出渣机械配套作业线、初期支护砼机械配套作业线与二次衬砌砼施工作业线相配合一条龙作业。软弱围岩坚持“短进尺、弱(不)爆破、快封闭、强支护、紧衬砌”的原则,开挖后仰拱及时跟上封闭成环。施工中进行超前地质预报,采用先进的量测探测技术对围岩提前做出判断,拟定相应的施工方案。 (二)施工布置 隧道根据施工现场场面状况,采用单向掘进,隧道进口布置一个隧道专业机械化施工队。洞内施工开挖、出渣初期支护与二次衬砌模筑砼平行作业。隧道路面待贯通后从洞口反向施工。根据地形地貌及工期要求,本隧道不设施工支洞。 (三)总体方案 根据磐南隧道围岩情况、及断面设计,结合本承包人现有技术装备力量和多年的隧道施工经验,确定Ⅲ类围岩采用正台阶开挖法施工,Ⅳ类采用全断面开挖法施工。隧道出渣采用侧翻装载机装车,自卸汽车运输。初期支护施作及时可靠,衬砌砼采用机械化作业,二次衬砌采用砼输送车、输送泵和全断面液压衬砌台车相配合的方案。施工过程中加强监测,及时处理分析数据,高速支护参数。开挖前做好超前地质预报、探测工作,根据围岩情况采取相应的施工方案。 二、隧道施工测量控制 为保证隧道贯通精度,拟定如下测量控制方案: 1、地表平面控制 (1)为保证洞口投点的相对精度,平面控制网根据设计提供的控制点和实地地形情况布设精密控制网,并保证洞口附近有二个或二个以上的精密控制网点。 (2)地表控制网经过多次复测,复测无误后方可引线进洞的测量工作。 2、洞口联系测量 为保证地面控制测量精度很好地传递到洞内,采用如下洞口控制测量方案: (1)在洞口仰坡完成及洞口施工至设计标高后,在洞口埋设二个稳固的导线控制点。 (2)洞口附近在基础稳定处埋设2~4个水准点,与地表水准控制网级网观测及平差计算,以便于隧道进洞水准测量。 3、测量方法及措施 (1)地表平面控制测量选用全站仪施测,建立四等导线控制网,并把隧道中线和横向轴线纳入控制网内以保证放样精度。 (2)高程控制按四等网施测,用自动按平水准仪施测,精度至毫米。 (3)洞内控制测量与地表控制测量按同等精度建网,施工中线测量使用全站仪。 (4)具体要点:

市政明挖隧道支撑施工方案

明挖隧道围护结构支撑 施工方案 工程名称:_呈贡外环中路下穿隧道________ 工程地点:昆明呈贡____________ 施工单位:_中铁建安公司_____________ 编制单位:项目部 技术负责人: 编制人: 编制日期:年月日审批单位:中铁建安公司 审批负责人: 审核人: 审批日期:年月日

目录 一、编制依据 (3) 二、工程概况 (3) 三、施工进度计划 (3) 四、施工管理组织及人员架构 (3) 五、施工工艺 (5) 六、质量保证措施 (14) 七、安全保证措施 (16) 八、文明环保保证措施 (22)

一、编制依据 1、外环隧道土建二标设计图纸 2、建筑基坑支护技术规程(GJG120-99) 3、建筑地基基础工程施工质量验收规范(GB50202-2002) 4、地下隧道施工及验收规范(GB20299-2003) 5、施工招标文件及施工合同 6、国家、云南省相关法规及规定 7、我公司已掌握的现场资料 二、工程概况 本工程地下连续墙厚度为800mm,墙顶设置钢筋混凝土冠梁,兼作抗浮压顶梁,截面尺寸1500×1000mm(宽×高),基坑南北两端截面为1000×1000mm (宽×高)。内支撑沿基坑竖向共设置3道,第一道采用混凝土支撑,支撑断面为800×800mm,纵向间距 6.0~7.2m;第二道和第三道支撑为?600mm(t=14mm)钢管支撑,纵向间距一般为3.0~3.5m;角撑采用钢筋混凝土支撑,断面尺寸根据支撑长度不同分为700×1000mm和500×700mm(宽×高)2种,在南北端的转角处设置三角形板撑,板撑的尺寸为1500×1500mm。 三、施工进度计划 本分项工程计划开工日期为2010年5月17日,完工日期为2010年8月20日。 详细施工进度计划见附件施工进度横道图。 四、施工管理组织及人员架构

隧道初期支护侵限换拱施工方案

一编制依据、编制范围及设计概况 (一)编制依据 1.国家法律、法规和河南省交通厅规章制度; 2.河南省高速公路采用的标准、规范、规程等; 3.2011年06月01日玉皇庙隧道初期支护异常变形施工方案评审会议纪要; 4.2011年07月01日玉皇庙隧道出口端浅埋段施工专家意见。 (二)编制范围 玉皇庙隧道左线初期支护变形侵限段F2K60+742~F2K60+695,右线初支变形段F2K60+738~K60+716,左线F2K60+683、右线F2K60+713开挖掘进。 (三)设计概况 玉皇庙隧道出口端范围地质情况为:山体顶部被第四系地层覆盖,表层为褐红色粉质粘土,山体为红褐色夹灰褐色强风化安山岩,节理裂隙非常发育,同时还存在浅埋、偏压,该段隧道埋深在11m~15m。 该范围设计采用Ⅴ级围岩加强复合式衬砌结构(洛阳至嵩县高速公路施工图设计No.9)。设计开挖建议采用三台阶+预留核心土法,Φ42超前小导管 2.4m/环,I20a 工字钢架,间距0.6m。该范围设计值支护参数见下表。该段侵限加固建议方案已于2011年06月01日下发。 玉皇庙隧道出口端设计支护参数表

二工程概况 (一)工程概述 玉皇庙隧道为山岭区高速公路上下行分离四车道双洞小净距隧道+独立双洞隧道;设计行车速度为100km/h;隧道限界净宽:10.75m,限界净高:5.0m;隧道最小间距为15.2m,左线长815m,右线长809m。左右线位于直线、缓和曲线和R=1000m 的圆曲线上。路线纵坡采用单向坡,右线设计纵坡为-2.5%、-2.99%,左线设计纵坡为-2.7%、-3.0%。 目前玉皇庙隧道左线出口已开挖至F2K60+683,仰拱施工里程到F2K60+703,二衬施工里程到F2K60+742。初期支护侵限段临时护拱里程F2K60+726~F2K60+714,临时仰拱里程F2K60+700~ F2K60+693。已完成开挖及初期支护100m,仰拱及填充80m,二次衬砌41m,已施工段均处于Ⅴ级围岩段。 玉皇庙隧道右线进口已开挖至K60+713,仰拱施工里程到K60+724,二衬施工里程到K60+743。已完成开挖及初期支护66m,仰拱及填充55m,二次衬砌36m,已施工段均处于Ⅴ级围岩段。 (二)病害情况 2010年11月2日至2011年05月28日,玉皇庙隧道出口F2K60+742~F2K60+695段初期支护出现变形超限,局部侵入二次衬砌结构,且隧道上方山体出现裂缝,裂缝宽度最大8cm,深度约2m。 2011年06月01日,嵩阳公司组织设计、监理、监控量测、施工单位四方共同查勘了现场,并查阅了有关施工和技术资料,召开四方会议,决定对该段变形超限段采取加固处理措施;2010年07月01日,嵩阳公司组织召开玉皇庙隧道出口端浅埋段专家会议。 玉皇庙隧道出口端按照设计Ⅴ级围岩加强复合式衬砌结构进行了开挖和初期支护施工,但由于围岩变形较大,经现场测量因变形侵限的左线里程段为F2K60+742~F2K60+695,局部最大侵限42.8cm,因变形侵限的右线里程段为K60+738~K60+716 ,局部最大侵限32.9cm。

钢支撑、围檩专项施工方案

亳州市建安隧道工程 钢围檩、支撑及系梁专项施工方案 工程名称:亳州市建安隧道工程 .编写单位:中铁十局集团有限公司亳州市建安隧道工程项目经理部编写人:日期:年月日审核人:日期:年月日

目录 1.编制依据、原则 (1) 编制依据 (1) 编制原则 (1) 适用范围 (1) 2.工程概况 (1) 设计概况 (1) 主要工程量 (1) 3.施工计划 (2) 施工进度计划 (2) 资源配置计划 (2) 4.施工方案与工艺 (3) 施工工艺流程 (3) 支撑轴力设计值 (3) 材料加工 (4) 钢围檩安装 (5) 钢管支撑安装 (5) 钢围檩、钢支撑防脱落措施 (10) 5.保证措施 (11) 安全保证措施 (12)

质量保证措施 (12) 文明施工保证措施 (14) 环境保护措施 (14)

钢围檩、支撑及系梁专项施工方案 1.编制依据、原则 编制依据 (1)《建筑基坑工程技术规程》JGJ120-2012; (2)《工程测量规范》(GB50026-2007); (3)亳州市建安隧道工程施工图; (4)《亳州市建安隧道工程实施性施工组织设计》; (5)《亳州市建安隧道工程深基坑安全专项施工方案》; (6)本单位类似工程施工经验。 编制原则 (1)严格执行施工过程中涉及的相关规范、规程和设计标准; (2)确保实现业主要求的工期、质量、安全、环境保护、文明施工等各方面的目标; (3)结合工程情况,使施工方案具有技术先进、方案可靠、经济合理的特点; (4)充分研究现场施工环境,妥善处理现场施工和周边环境协调问题,使施工对周边环境的影响最小化。 适用范围 本方案适用于亳州市建安隧道工程的钢围檩、支撑及系梁。 2.工程概况 设计概况 本工程除第一道支撑为砼支撑外,余下道支撑为钢支撑,包括围檩、支撑、系梁。 钢围檩采用两根H型(HM500*300*11*18)加缀板焊接而成(落深区为三拼钢围檩),钢肋板采用464*130*20,间距为800mm,支撑节点处钢肋板加密设置,间距为250mm。 钢支撑采用φ609(φ800)mm两种规格,壁厚16mm的钢管。一般部位采用φ609钢管,A8、A9、A18、A19段落深区(加强部位)采用φ800钢管。钢管支撑分节制作,每节标准长度采用4m和6m两种规格,管节间采用法兰盘螺栓连接,其端部(仅一端)设预加轴力装置。 钢系梁采用两根H型(HM400*300*10*16),安装于钢立柱两侧的牛腿上,与钢支撑连接在一起。 主要工程量

地铁深基坑钢支撑施工方案..

目录 一、编制依据 (2) 二、工程概况 (2) 三、施工部署 (2) 3.1项目管理组织机构 (3) 3.2主要机械设备 (3) 3.3 劳动力计划 (4) 3.4主要工程材料 (4) 四、支撑施工工艺 (4) 4.1 土方开挖 (4) 4.2钢支撑施工 (5) 五、钢支撑监控量测 (10) 5.1支撑轴力监测布置 (10) 5.2轴力应变计埋设与安装 (10) 六、质量保证措施 (10) 6.1钢支撑稳定的保证措施 (10) 6.2 钢支撑的检验标准 (11) 七、安全和环保措施 (13)

基坑支撑施工方案 一、编制依据 1、昆明市轨道交通3号线西昌路站车站附属结构设计图纸、总体施工组织设计、围护结构施工方案 2、《岩土工程勘察报告》(020626-kj) 3、《建筑基坑工程技术规范》(YB9258-97) 4、《地下铁道工程施工及验收规范》(GB50299-1999) 5、《钢结构焊接规范》(GB50661-2011) 6、《建筑机械使用安全技术规程》(JGJ33-2012) 7、《建筑地基基础工程施工质量验收规范》(GB50202-2002) 8、《建设工程施工现场供用电安全规范》(JG50194-93) 9、《建设工程施工现场安全、防护、场容卫生、环境保护及保卫消防标准》(DBG01-83-2003) 10、国家和郑州市有关施工的法律法规 二、工程概况 郑州市轨道交通2号线一期工程土建施工01工区新龙路站位于郑花路与三全路路口,沿郑花路呈南北走向布置。车站有效站台中心里程为YDK11+418.00,车站全长186.5m,车站标准段宽度18.7m,最大宽22.4m(端头井处),站台宽10m,底板埋深17.0m(中心里程处),顶板覆土3.0m。车站主体为地下二层双跨闭合箱形框架结构,采用明挖顺筑法施工。 车站主体围护结构采用钻孔灌注桩的围护形式,采取坑内降水、坑外止水的措施,钻孔灌注桩桩间采用三轴搅拌桩止水帷幕。围护结构采用Ф1000mm@1200mm的钻孔灌注桩和Ф850mm@600mm的三轴搅拌桩;支撑系统采用Ф609,壁厚16mm的钢管作为内支撑;钢支撑共设3道支撑、1道换撑。支撑间距第一道为5.4m,二、三道为2.7m,换撑间距为2.7m。 三、施工部署

隧道二次衬砌专项施工方案

XXX省XXXX(XXX界)至XXXX公路XX隧道二次衬砌专项施工方案 编制: 复核: 批准:

XX隧道二次衬砌专项施工方案 一、编制依据及原则 1、编制依据: xxxxxxxxxxxxxxxxxxxxxxxxxxx合同《两阶段施工图设计》施工设计图纸; 《公路工程质量检验评定标准》JTG F80/1-2004; 《公路隧道施工技术规范》JTG F60-2009; 《河北省茅荆坝(蒙冀界)至承德公路施工标准化实施细则》;本公司历年来积累的施工经验,施工管理、技术与质量管理水平,技术装备实力和各专业人才技术条件。 2、编制原则: 科学组织施工,满足建设单位对本工程工期、质量、安全等方面要求,合理进行施工组织安排,充分利用各种条件,确保工程顺利施工和保证施工安全。根据本工程施工特点建立适合本工程的管理机构和质量体系,满足于本项目质量、安全目标顺利实现。 二、工程概况 1、本合同系XXXXXXXXXXXXXXXXXXXXXX合同段,全长7.113Km。XX隧道为分离式隧道,右线起讫桩号K64+252~K67+162,总长2910m,其中Ⅲ级围岩1670m,Ⅳ级围岩930m,Ⅴ级围岩310m;左线起讫桩号ZK64+248.9~ZK67+194,总长2945.1m,其中Ⅲ级围岩1670m,Ⅳ级围岩950m,Ⅴ级围岩325.1m。洞门形式为端墙式。项目区属亚湿润中温带大陆性季风气候,四季分明,雨热同季,季风显著,水流受季节影响较大。该区域年蒸发量1838.7mm,年平均日照2800-2900h,无霜期150d,气象条件造成每年有效施工期较短。 2、隧道结构设计 隧道按新奥法原理设计,结构采用锚、网、喷、钢拱架组成初期支护与二次模筑砼相结合的复合式衬砌型式;二衬采用C30防水砼,抗渗等级不小于S8。仰拱采用普通C25砼。隧道主洞、紧急停车带内轮廓一般采用三心圆、曲边墙形式;拱墙采用1.5mm厚复合式防水卷材 2.3人员组织概况 管理人员10人、开挖班40人、支护班60人、模板班40人、二次衬砌班40人。 三、总体施工方案 3.1 总体施工安排

隧道初期支护专项施工方案

XX省XXX (XXX界)至XX公路XX隧道初期支护专项施工方案 中国中铁 编制:__________________ 复核:__________________ 批准:__________________

XX隧道初期支护专项施工方案 一、编制依据及原则 1、编制依据: xxx合同《两阶段施工图设计》施工设计图纸; 《公路工程质量检验评定标准》JTG F80/1-2004 ; 《公路隧道施工技术规范》JTG F60-2009; 本公司历年来积累的施工经验,施工管理、技术与质量管理水平,技术装备实力和各专业人才技术条件。 2、编制原则: 科学组织施工,满足建设单位对本工程工期、质量、安全等方面要求,合理进行施工组织安排,充分利用各种条件,确保工程顺利施工和保证施工安全。根据本工程施工特点建立适合本工程的管理机构和质量体系,满足于本项目质量、安全目标顺利实现。 二、工程概况 1、本合同系XXXXXXXXXXXXXXXXXXX合同段,全长7.113Km。XX隧道为分离式隧道,右线起讫桩号K64+252?K67+162总长2910m,其中川级围岩1670m, W级围岩930m, V级围岩310m;左线起讫桩号ZK64+248.9?ZK67+194总长2945.1m ,其中川级围岩1670m W级围岩950m V级围岩325.1m。洞门形式为端墙式。项目区属亚湿润中温带大陆性季风气候四季分明雨热同季季风显著水流受季节影响较大。该区域年蒸发量1838.7mm年平均日照2800-2900h,无霜期150d 气象条件造成每年有效施工期较短。 2、设计技术参数: IV-V 级围岩的初期支护由工字钢拱架、系统锚杆、钢筋网及喷射混凝土组成 III 级围岩的初期支护由系统锚杆、钢筋网及喷射混凝土组成。钢拱架之间采用纵向钢筋连接并与系统锚杆及钢筋网焊为一体与围岩密贴形成承载结构。XX 隧道初期支护采用C25混凝土湿喷技术施工。 (一)锚杆支护 1、中空注浆锚杆 ①W、V级围岩段初期支护系统锚杆采用? 25X 5mn中空注浆锚杆,长3m 3.5m,按规

隧道钢支撑作业指导书

隧道钢支撑施工指导书 一.编制目的 为防止隧道钢拱架间距,钢板连接等问题,保证施工安全和正常进行,编制钢支撑施工作业指导书指导施工。 二.工程地质及水文概述 隧址区中风化岩体较完整,裂隙不发育。进口端掩体发育有两种裂隙:①51°∠77°,裂隙面较平直,多呈闭合状,局部张开0.5~3mm,泥质填充,延伸约0.5~1.5m,发育间距2~3条/m,结合程度一般;②148°∠81°,裂面较平直,张开1~4mm,无充填或部分泥质充填,延伸约1~2m,发育间距2~3条/m,结合程度一般。出口端岩体中发育有两种裂隙:①210°∠75,裂面较平直,多呈闭合状,局部张开0.5~2mm,泥质填充,延伸约1~2m,发育间距2~3条/m,结合程度一般;②294°∠80°,裂面较平直,张开0.5~3mm,局部泥质充填,延伸约0.5~1.5m,发育间距2~3条/m,结合程度一般。 三.钢支撑施工 (一)、加工准备:钢支撑制作之前检查工字钢的尺寸是否符合图纸和规范要求,检查合格后进行钢支撑的制作;制作时检查工字钢的弯曲半径,以保证钢支撑尺寸符合要求,同时检查连接板的尺寸和厚度,螺栓孔的位置必须准确,以保证连接板的连接平顺。 (二)、测量定位:钢筋网片施工完成后,测量放出每榀工字钢的位置,作出明显标识。

(三)、就位:人工配合装载机运输入洞,安装就位。安装误差控制在±50mm。钢支撑应靠紧岩面,其与围岩间隙不得用片石回填,而应用喷射混凝土填实。 (四)、钻孔安装锁脚锚杆,焊接连接筋。钢支撑支护,钢支撑在安装时要严格控制钢支撑的间距不得大于5cm,钢支撑之间必须用连接筋连接,拱脚必须放在牢固的基础上,拱脚标高不足时,不得用块石、碎石垫砌,应用钢板进行调整,或用混凝土浇注,强度不小于C20。 (五)定位工字钢 1、钢支撑安装前先检查工字钢材料、类型、规格、质量以及性能是否与设计相符; 2、检查工字钢放线尺寸,控制在±50mm内。 四施工及安全注意事项 1、安装人员到达工作地点时,首先检查工作面是否处于安全状态,如有松动的石、土块或裂缝应先予以清除或支护。 2、施工时安全人员现场值班,随时发现问题并及时采取相应措施,确保人员安全。 3、凿岩机开挖时,开挖工人须采用必要的防噪音措施和防灰尘措施,戴口罩和耳塞。

钢支撑专项施工方案

一、编制说明.编制依据 (1)南宁东站综合交通枢纽一期工程(地下空间)-轨道交通换乘站工程招标文件。 (2)南宁东站综合交通枢纽一期工程(地下空间)-轨道交通换乘站工程主体工程围护结构施工图设计。 (3)南宁东站综合交通枢纽一期工程(地下空间)-轨道交通换乘站工程勘察报告的水纹地质、环境和管线探查资料。 (4)现行的主要施工规范、规程和标准。 .编制原则 (1)全面响应施工合同,严格遵守施工合同所有条款; (2)满足业主对质量、安全、工期、文明施工等方面的规定和要求,确保高效优质完成本标段内所有工程; (3)综合考虑本工程特点、重点、难点采用先进、科学、成熟、有效的施工方案,并结合本投标人历年轨道交通施工经验,使施工组织设计具有合理性、全面性、实用性; (4)本工程地长沙市主要街道,减少对周边环境的影响; (5)采用科学合理的监控措施和信息反馈系统指导施工; .编制范围 主要工程范围包括主体结构钢支撑架设及拆除。 二、工程概况

. 工程位置 南宁东站综合交通枢纽工程(地下空间)-轨道交通换乘站工程是轨道交通1号线、7号线换乘车站,站址位于国铁南宁东站站房南侧地下,地铁1、7号线东西方向穿过东站南广场,2条轨道交通线平行换乘。 工程地处南宁市青秀区,位于凤岭北路以北、凤凰岭路以东,高坡岭路以西,地势东西高中间低,且起伏很大,最大高差达25m以上。 .工程地质 场区范围属剥蚀丘陵地貌,覆盖层为第四系土层,其下为第三系半成岩,泥岩、粉砂质泥岩、泥质粉砂岩、粉砂岩。地层岩性分述如下: (1)填土(Q4ml) 素填土①2层:灰黄色,以粉土为主,稍密,稍湿~湿,含砖渣、砾石、植物根。 填土层广泛分布于拟建车站的地表,厚度约为~1.50m。 (2)第四系上更新统残、坡积层(Q3el+dl) 残、坡积层粘土、粉质粘土⑥1-1层:黄褐~褐红色,硬塑,粘粒含量高,切面光滑,手可捏断,韧性中等,干强度中等。 (3)第三系岩层(E) 第三系岩层(E)按不同岩性特性、状态分为6个亚层。 1)泥岩、粉砂质泥岩⑦1-1层:灰~青灰色,未成岩,呈硬塑土状,含锰质结核,岩芯呈短~中柱状,泥质结构,层理不明显,切面光滑,有蜡状光泽;干强度较高,遇水易软化,晒干易开裂。属于极软岩。

小断面隧道工程施工方案

小断面隧道工程施工方案 Prepared on 24 November 2020

.隧道工程施工方案 总体施工方案 (1)总体施工思路 坚持采用综合的超前地质预报措施;努力提高隧道施工的机械化程度;坚持围岩监控量测、实施隧道信息化动态设计施工。 (2)总体施工方案 本标段隧道采用小型运输机械无轨运输方案。根据工期安排,隧道全部安排平行施工。 隧道按新奥法组织施工,严格遵循“超前探、管超前、弱(不)爆破、短进尺、强支护、早封闭、勤量测、紧衬砌”的原则。用先进的探测和量测技术取得围岩状态参数,通过对信息、数据的综合分析和处理,判定地质变化,反馈于设计和施工,实行动态管理信息化施工。 施工准备阶段完成临时施工便道,架设供电线路,铺设供水管路;洞口场地开挖完成后,安装和修建隧道供风、供水、供电、混凝土生产、钢构件加工等设备与设施;砌筑洞顶截排水沟,进行洞顶地表加固,开挖洞口土石方;尽早修建洞口段衬砌及洞门,以策安全。 明洞按明挖法施工,暗洞按锚喷构筑法施工,加强超前地质探测与预报,加强围岩量测,实现施工信息化,并实施掘进(钻、爆、装、运)、锚喷(拌、运、锚、喷)、衬砌(拌、运、灌、捣)等三条机械化作业线。 运用开挖掌子面地质素描、TSP203地震波反射法、超前水平钻探等对崩塌、黄土、膨胀土、采空区等进行综合超前地质探测和预报,提前预测地层情况,根据不同的岩层和岩性及地质情况采取相应的措施进行有效处理以改善围岩状况,达到安全、高质量施工的目的。具体做法如下:

(1)针对隧道各种围岩级别选定出合理的钻爆及支护方案。保证隧道每次开挖进尺及超欠挖控制,在保证了隧道施工安全可靠的前提下控制支护循环时间,并做到经济合理。 (2)根据隧道空间断面的特点,隧道单口掘进小于1Km时采用压入式通风。隧道单口掘进长度大于1km,采用混合式通风。两台轴流风机分别供风、抽风的通风方式。尽量减小通风系统所占空间,又能满足通风要求。 (3)由于隧道净空小、宽度窄,不能满足大型施工机械的操作场地要求,考虑了采用小型运输机械无轨出渣方案,避车洞的设置数量和间距可根据现场实际情况进行调整,选择合适的运输方法运输,使之做到车辆转换间不消耗施工时间。 (4)对施工每循环进尺所需用的机械、人员等配备情况进行了详细分析,并在此基础上计算出每月、每年的施工进度,保证工期要求。 (5)以类似隧道施工经验为基础,保证该隧道施工的各种方法、安全管理、文明施工等满足工期、质量、环保要求。 主要工序施工方案 隧道开挖方案 隧道开挖方案详见“表2-2-1隧道总体开挖方案表”。 隧道开挖作业施工工艺流程:开挖爆破→出渣→初支→下一循环。

隧道钢支撑工程技术方案

隧道钢支撑支护施工方案 施工方案 钢拱架施工 隧道钢架支护分为型钢钢架,型钢钢架主要由I20 、I16工字钢弯制而成。Ⅳ级围岩采用I16工字钢,Ⅴ级围岩采用I20工字钢。 隧道各部开挖完成初喷砼后,分单元及时安装钢架,采用系统锚杆以及双侧锁脚锚杆固定,钢架之间铺挂钢筋网,然后复喷混凝土到设计厚度。钢架施工工艺流程图见图。 A、钢架加工 ①型钢钢架加工: 加工场地用砼硬化,精确抹平,按设计放出加工大样。钢架弯制结合隧道开挖方法采用型钢弯制机按照隧道断面曲率分节进行弯制,弯制完成后,先在加工场地上进行试拼。各节钢架拼装,要求尺寸准确,弧形圆顺。要求沿隧道周边轮廓误差不大于3cm;型钢钢架平放时,平面翘曲小于2cm。 B、钢架安装 钢架安装在掌子面开挖初喷完成后立即进行。 根据测设的位置,各节钢架在掌子面以螺栓连接,连接板应密贴。为保证各节钢架在全环封闭之前置于稳固的地基上,安装前应清除各节钢架底脚下的虚碴及杂物。同时每侧安设2根锁脚锚杆将其锁定,底部开挖完成后,底部初期支护及时跟进,将钢架全环封闭。 为保证钢架位置安设准确,隧道开挖时在钢架的各连接处预留连接板凹槽。初喷砼时,在凹槽处打入木楔,为架设钢架留出连接板(和槽钢)位置。钢架按设计位置安设,在安设过程中当钢架和初喷层之间有较大间隙应每隔2m用砼预制块楔紧,钢架背后用喷砼填充密实。钢架纵向连接采用φ22钢筋,环向间距1m。

型钢钢架施工工艺流程图 钢架落底接长在单边交错进行,每次单边接长钢架1~2排。在软弱地层可同时落底接长和仰拱相连并及时喷射砼。接长钢架和上部钢架通过垫板用螺栓牢固准确连接。 架立钢架后应尽快进行喷砼作业,以使钢架与喷砼共同受力。喷射砼分层进行,先从拱脚或墙角处由下向上喷射,防止上层喷射料虚掩拱脚(墙角)不密实,造成强度不够,拱脚(墙角)失稳。 C、土隧道防止钢架下沉的措施 拱部开挖安装型钢拱架后,由于黄土隧道围岩的自稳 性较差以及各部开挖拉开了一定距离,钢架短时间内不能全断面闭合,有可能会出现拱顶钢架下沉,导致围岩失稳或侵入衬砌界限,因此在施工过程中需加强对钢架安装以后的监控量测,必要时采取有效措施进行加固,以防止拱顶钢架下沉。具体措施如下: a、强对钢架的锁脚固定措施

隧道钢支撑施工方案

隧道钢支撑施工方案 一、施工准备 1、熟悉图纸及相关规范要求。。。。。。。 2、根据现场施工组织情况,在施工前将所需材料提前运送至现场,所有进场材料均应经过试验室检验,并满足招投标文件对原材料各项指标的要求。 二、施工方案 1、施工顺序 测量放样→立钢架→钻锁脚锚杆孔→安装锁脚锚杆→焊接纵向连接筋→下一道工序。 2、钢拱架加工制作及架设的施工方法 本隧道Ⅴ级围岩(含Ⅳ 停车带)采用热轧普通HW型钢钢架支护,Ⅳ级围岩采用格栅钢架支护。Ⅴ 偏 土 型、Ⅴ 浅 土型衬砌采用HW175型钢,纵向间距60cm;Ⅴ型衬砌采用HW150型钢,纵向间距70cm;Ⅳ型衬砌采用12×12钢筋格栅钢架,格栅钢架由Φ22主筋、φ10蹬筋和φ8箍筋焊接而成,纵向间距120cm。 2.1钢拱架制作 钢拱架在的加工在工地加工场内利用胎架进行,焊制好的钢架使用前在加工场内进行试拼,将整个隧道轮廓各节钢架进行整体试拼,以检查连接部位是否吻合,加工误差符合规范要求的钢架才运到工地使用。 2.2钢拱架安装 2.2.1每榀钢钢架安装前,用全站仪、水准仪准确测量定出钢架安装的中线、标高及拱脚设计位置。 2.2.2钢架安装由人工借助机具进行架立就位,拱脚必须架立在坚固的基座上。拱脚标高不够时设置钢板进行调整,或用混凝土加固基底。用短钢筋将钢架焊牢在锚杆上。用Φ22螺纹钢筋按设计间距连接成整体。 2.2.3每榀钢架安装好后在其拱脚处设置两根Φ22、L= 3.0m锁脚锚杆来固定,以限制初支下沉,其入土段用锚固剂锚固,与另一端和钢拱架焊接牢固。钢架与围岩间的空隙需用混凝土块塞紧,间距不大于设计要求。 2.2.4钢架安装后根据已施工段量测结果确定限位变形量,现场焊接限位钢板,限位钢板每个接头设一处。 3、施工注意事项: 3.1钢架应及时落底封闭,钢架基础应稳固,避免沉降过大造成侵限。每榀钢架间必须严格按设计用纵向钢筋连接成整体,以增强钢架的整体支承能力。