现代企业管理——管理科学基础网络图
现代企业管理管理科学基础
班级:
组员:
指导教师:
日期:
一、网络草图的绘制
二、网络图的时间计算
1、最早开始时间ET(j)
ET (1) = 0
ET (j) = max{ET(i) + t(i, j)}
式中
ET(j):箭头节点 j 的最早开始时间
ET(i):箭头节点 i 的最早开始时间
t(i, j):箭线(i, j)所代表活动的作业时间
计算过程:
ET (1) = 0
= 0 + 4 = 4
ET (2) = ET (1) + t
1,2
ET (3) = ET (2) + t
= 4 + 6 = 10
2,3
}= max{10,4 + 5 = 9}= 10 ET (4) = max{ET (3),ET (2) + t
2,3
ET (5) = ET (2) + t
= 4 + 9 = 13
2,5
ET (6) = ET (3) + t
= 10 + 8 = 18
3,6
ET (7) = max{ET (4) + t
4,7 ,ET (5) + t
5,7
}= max{10 + 2 = 2,
13 + 4 }= 17
ET (8) = max{ET (6) + t
6,8 ,ET (7) + t
7,8
}= max{18 + 5 = 23,
17 + 6 = 23 }= 23
ET (9) = ET (8) + t
8,9
= 23 + 5 = 28 2、最迟结束时间LF(i)
LT (i) = min{LT (j) - t(i, j)}
计算过程:
LT (9) = 28
LT (8) = LT (9) - t
8,9
= 28 - 5 = 23
LT (7) = LT (8) - t
7,8
= 23 - 6 = 17
LT (6) = LT (8) - t
6,8
= 23 - 5 = 18
LT (5) = LT (7) - t
5,7
= 17 - 4 = 13
LT (4) = LT (7) - t
4,7
= 17 - 2 = 15
LT (3) = LT (6) - t
3,6
= 18 - 8 = 10
LT (2) = min{LT (3) - t
2,3 ,LT (4) - t
2,4
,LT (5) - t
2,5
}=
min{10 - 6,15 - 5,13 - 9}= 4 LT (1) = LT (2) - t
1,2
= 4 - 4 = 0
3、活动时间参数计算
1)活动最早开始时间
ES( i,j ) = ET( i )
计算过程:
ES (1,2) = ET (1) = 0
ES (2,3) = ET (2) = 4
ES (2,4) = ET (2) = 4
ES (2,5) = ET (2) = 4
ES (3,4) = ET (3) = 10
ES (3,6) = ET (4) = 10
ES (4,7) = ET (4) = 10
ES (6,8) = ET (6) = 18
ES (7,8) = ET (7) = 17
ES (5,7) = ET (5) = 13
ES (8,9) = ET (8) = 23
2)活动最早完工时间
EF( i,j ) = ES( i,j ) + t(i,j)
计算过程:
= 0 + 4 = 4 EF (1,2) = ES (1,2) + t
1,2
EF (2,3) = ES (2,3) + t
= 4 + 6 = 10
2,3
= 4 + 5 = 9 EF (2,4) = ES (2,4) + t
2,4
= 4 + 9 = 13 EF (2,5) = ES (2,5) + t
2,5
= 10 + 0 = 10 EF (3,4) = ES (3,4) + t
3,4
EF (3,6) = ES (3,6) + t
= 10 + 8 = 18
3,6
= 10 + 2 = 12 EF (4,7) = ES (4,7) + t
4,7
EF (6,8) = ES (6,8) + t
= 18 + 5 = 23
6,8
= 17 + 6 = 23 EF (7,8) = ES (7,8) + t
7,8
= 13 + 4 = 17 EF (5,7) = ES (5,7) + t
5,7
EF (8,9) = ES (8,9) + t
= 23 + 5 = 28
8,9
3)活动最迟完工时间
LF( i,j ) = LT( j )
计算过程:
LF (1,2) = LT (2) = 4
LF (2,3) = LT (3) = 10
LF (2,4) = LT (4) = 15
LF (2,5) = LT (5) = 13
LF (3,4) = LT (4) = 15
LF (3,6) = LT (6) = 18
LF (4,7) = LT (7) = 17
LF (6,8) = LT (8) = 23
LF (7,8) = LT (8) = 23
LF (5,7) = LT (7) = 17
LF (8,9) = LT (9) = 28
4)活动最迟开始时间
LS( i,j ) = LF( i,j ) - t(i,j)
计算过程:
= 4 - 4 = 0 LS( 1,2 ) = LF (1,2) - t
1,2
= 10 - 6 = 4 LS( 2,3 ) = LF (2,3) - t
2,3
= 15 - 5 = 10 LS( 2,4 ) = LF (2,4) - t
2,4
= 13 - 9 = 4 LS( 2,5 ) = LF (2,5) - t
2,5
= 15 - 0 = 15 LS( 3,4 ) = LF (3,4) - t
3,4
LS( 3,6 ) = LF (3,6) - t
3,6
= 18 - 8 = 10
LS( 4,7 ) = LF (4,7) - t
4,7
= 17 - 2 = 15
LS( 6,8 ) = LF (6,8) - t
6,8
= 23 - 5 = 18
LS( 7,8 ) = LF (7,8) - t
7,8
= 23 - 6 = 17
LS( 5,7 ) = LF (5,7) - t
5,7
= 17 - 4 = 13
LS( 8,9 ) = LF (8,9) - t
8,9
= 28 - 5 = 23
5)活动总工期
总工期=28 - 0 =28
6)活动关键工序
A/B/D/E/G/H/I/J
7)活动关键路线
①→②、②→③、②→⑤、③→⑥、⑥→⑧、⑦→⑧、⑤→⑦、⑧→⑨三、网络图活动时间表
工序i→j 工序时
间ES EF LF LS R(i,j)关键路线
A ①→② 4 0 4 4 0 0
B ②→③ 6 4 10 10 4 0
C ②→④ 5 4 9 15 10 6
D ②→⑤9 4 13 13 4 0 虚③→④0 10 10 15 15 5
E ③→⑥8 10 18 18 10 0
F ④→⑦ 2 10 12 17 15 5
G ⑥→⑧ 5 18 23 23 18 0
H ⑦→⑧ 6 17 23 23 17 0
I ⑤→⑦ 4 13 17 17 13 0 J ⑧→⑨ 5 23 28 28 23 0
四、网络正图的绘制
五、小组成员及分工
姓名分工
六、小组互评
姓名
成绩