轻型井点降水方案设计
完整版 轻型井点降水方案

轻型井点降水施工方案XX工程公司年月日目录一、工程概况···································································2二、编制依据····································································2三、降水方案选择·······························································2四、井点降水相关计算·························································3五、主要降水设备·······························································6六、施工工期·····································································7七、井点施工方法·······························································7八、质量标准及质量保证措施················································8九、危险点分析································································10十、安全生产及文明施工措施···············································10 十一、环保措施································································11一、工程概况本期设计为2×600MW亚临界汽轮发电机组。
轻型井点降水施工方案设计

一.工程概况:陈家镇石竹路二期〔江韵路-银鸥路〕新建工程2标工程位于某某市崇明县,西起0+758.741,北至银鸥路〔1+000.265〕.主要工程内容包括新建道路199.524米、敷设DN600污水管线248米、DN1200雨水管线173米以与42米铁塔河桥一座.本工程沟槽开挖在3~6米左右,根据本工程的勘测报告显示,地下水静止水位埋深在0.80~1.10m之间,相应标高为2.46~2.33m.为确保施工安全,达到经济、安全的目的,本工程采用轻型井点降水施工.二.施工准备1.施工机具〔1〕滤管:φ45mm,壁厚为4.0mm的无缝钢管或镀锌管,长5.0m左右,一端用厚为4.0mm的钢板焊死,在此端1m长X围内,在管壁上钻φ15mm的小圆孔,孔距为25mm,外包两层滤网,滤网采用编织布,外部再包一层网眼较大的尼龙丝网,每隔50~60mm用10号铅丝绑扎一道,滤管另一端与井点管进展连接.〔2〕井点管:φ45,壁厚为3.0mm的无缝钢管或镀锌管.〔3〕连接收:透明管或胶皮管,与井点管和总管连接,采用8号铅丝绑扎,应扎紧以防漏气.〔5〕总管:φ160mm钢管,壁厚为4mm,用法兰加橡胶垫圈连接,防止漏气、漏水.〔6〕抽水设备:根据设计配备离心泵、真空泵或射流泵,以与机组配件和水箱.〔7〕移动机具:移动式井架、牵引力为6t的绞车.〔8〕水枪:φ50×5无缝钢管,下端焊接一个φ16的枪头喷嘴,上端弯成大约直角,且伸出冲击管外,与高压胶管连接.〔9〕蛇形高压胶管:压力应达到1.50MPa以上.〔10〕高压水泵:100TSW-7高压离心泵,配备一个压力表,作下井管之用.2.井点管的计算井点平面采用双排线型布置,井管间距1m.井管长度按以下公式计算: H≥H1+h1+i×L+0.5H—井点管埋设深度<不包括滤管长度><m>;H1—井管顶至槽底距离<m>;h1—地下水位至槽地面以下距离<m> <取0.5m>;i—地下水位降落坡度<单排取1:3>;L—井点管至要降低水位点的水平距离<m>;3.材料粗砂与豆石,不得采用中砂,严禁使用细砂,以防堵塞滤管网眼.4.技术准备详细查阅工程地质勘察报告,了解工程地质情况,分析降水过程中可能出现的技术问题与采取的措施.三.施工工艺:由于本工程地质条件较差,在沟槽开挖前3~4天开始进展井点降水,降低基槽地面土壤的含水量,防止滑坡和塌方,可以稳定基地,不破坏地基承载力,不发生隆起、管涌和泉眼,为施工得到干面坚实的工作面.同时要做好地表水和天然降水的疏导和排除,防止地表水流入和渗入,防止加大井点负荷.同时为了防止塌方对施工人员造成伤害,在可能发生坍塌的部位要安好支撑.1.安装程序井点放线定位→挖井点沟槽→安装高压水泵→凿孔安装埋设井点管→布置安装总管→井点管与总管连接→安装抽水设备→试抽与检查→正式投入降水程序.2.井点管埋设〔1〕测量放线确定井点位置,然后在井位先挖一个小土坑,深大约500mm,以便于冲击孔时集水、埋管时灌砂,并用水沟将小坑与集水坑连接,以便排泄多余水.〔2〕用绞车将简易井架移到井点位置,将套管水枪对准井点位置,启动高压水泵,水压控制在0.4~0.8MPa,在水枪高压水射流冲击下套管开始下沉,并不断地升降套管与水枪.一般含砂的粘土,按经验,套管落距在1000mm之内,在射水与套管冲切作用下,大约在10~15min时间之内,井点管可下沉10m左右,假如遇到较厚的纯粘土时,沉管时间要延长,此时可增加高压水泵的压力,以达到加速沉管的速度.冲击孔的成孔直径应达到300~350mm,保证管壁与井点管之间有一定间隙,以便于填充砂石,冲孔深度应比滤管设计安置深度低500mm以上,以防止冲击套管提升拔出时局部土塌落,并使滤管底部存有足够的砂石.凿孔冲击管上下移动时应保持垂直,这样才能使井点降水井壁保持垂直,假如在凿孔时遇到较大的石块和砖块,会出现倾斜现象,此时成孔的直径也应尽量保持上下一致.井孔冲击成型后,应拔出冲击管,通过单滑轮,用绳索提起井点管插人井孔,井点管的上端应用木塞塞住,以防砂石或其他杂物进入,井在井点管与孔壁之间填灌砂石滤层.该砂石滤层的填充质量直接影响轻型井点降水的效果,应注意以下几点:1〕砂石必须采用粗砂,以防止堵塞滤管的网眼.2〕滤管应放置在井孔的中间,砂石滤层的厚度应在60~100mm之间,以提高透水性,并防止土粒渗入滤管堵塞滤管的网眼.填砂厚度要均匀,速度要快,填砂中途不得中断,以防孔壁塌土.〔3〕砂石滤层的填充高度,至少要超过滤管顶以上1000~1800mm-般应填至原地下水位线以上,以保证土层水流上下畅通.〔4〕井点填砂后,井口以下1.0~1.5m用粘土封口压实,防止漏气而降低降水效果.3.冲洗井管将φ30mm的胶管插入井点管底部进展注水清洗,直到流出清水为止.应逐根进展清洗,防止出现"死井〞.4.管路安装首先沿井点管线外侧,铺设集水毛管,并用胶垫螺栓把干管连接起来,主干管连接水箱水泵,然后拔掉井点管上端的木塞,用胶管与主管连接好,再用10#铅丝绑好,防止管路不严漏气而降低整个管路的真空度.主管路的流水坡度按坡向泵房5‰的坡度并用砖将主干管垫好.5.检查管路检查集水-下管与井点管连接的胶管的各个接头在试抽水时是否有漏气现象,发现这种情况应重新连接或用油腻子堵塞,重新拧紧法兰盘螺栓和胶管的铅丝,直至不漏气为止.在正式运转抽水之前必须进展试抽,以检查抽水设备运转是否正常,管路是否存在漏气现象.在水泵进水管上安装一个真空表,在水泵的出水管上安装一个压力表.为了观测降水深度,是否达到施工组织设计所要求的降水深度,在基坑中心设置一个观测井点,以便于通过观测井点测量水位,并描绘出降水曲线.在试抽时,应检查整个管网的真空度,应达到550mmHg<73.33kPa>,方可正式投入抽水.6.抽水轻型井点管网全部安装完毕后进展试抽.当抽水设备运转一切正常后,整个抽水管路无漏气现象,可以投入正常抽水作业.井点降水示意图四.须知事项1.土方挖掘运输车道不设置井点,这不影响整体降水效果.2.在正式开工前,由电工与时办理用电手续,保证在抽水期间不停电.抽水应连续进展特别是开始抽水阶段,时停时抽,会导致井点管的滤网阻塞.同时由于中途长时间停止抽水,造成地下水位上升,会引起土方边坡塌方等事故.3.轻型井点降水应经常进展检查,其出水规律应"先大后小,先浑后清〞.假如出现异常情况,应与时进展检查.4.在抽水过程中,应经常检查和调节离心泵的出水阀门以控制流水量,当地下水位降到所要求的水位后,要减少出水阀门的出水量,尽量使抽吸与排水保持均匀,达到细水长流.5.真空度是轻型井点降水能否顺利进展降水的主要技术指数,现场设专人经常观测假如抽水过程中发现真空度不足,应立即检查整个抽水系统有无漏气环节,并应与时排除.6.在抽水过程中,特别是开始抽水时,应检查有无井点管淤塞的死井,可通过管内水流声、管子外表是否潮湿等方法进展检查.如"死井〞数量超过10%,如此严重影响降水效果,应与时采取措施,采用高压水反复冲洗处理.7.在打井点之前应勘测现场,采用某某铲凿孔,假如发现场内有旧根底、隐性墓地等应与早上报.8.如粘土层较厚,沉管速度会较慢,如超过常规沉管时间时,可增大水泵压力,但不要超过1.5MPa.9.主干管流水坡度流向水泵方向.10.如在冬季施工,应做好主干管保温,防止受冻.11.基坑周围上部应挖好水沟,防止雨水流入基坑.12.井点位置应距坑边2~2.5m,以防止井点设置影响坑边土坡的稳定性.水泵抽出的水排到离基坑越远越好,以防止渗下回流,影响降水效果.13.如场地粘土层较厚,这将影响降水效果,因为粘土的透水性能差,上层水不易渗透下去采取套管和水枪在井点轴线X围之外打孔,用埋设井点管一样成孔作业方法,井内填满粗砂,形成二至三排砂桩,使地层中上下水贯穿.在抽水过程中,由于下部抽水,上层水由于重力作用和抽水产生的负压,上层水系很容易漏下去,将水抽走.14.井点降水施工队应派员24小时值班,定时观测流量与水位降低情况并做好《轻型井点降水记录》,同时施工人员在井点施工时,亦应做好《井点施工记录》.15.质量通病的防治:通病与现象原因分析预防措施井点抽水时在周围地面出现沉降开裂与位移含水层疏干后,土体产生密实效应,土层压缩,地面下沉.限制基坑周围堆放材料,机械设备量,且不宜集中.降水速度过慢或无效,坑内水位无明显下降或不下降.表层土渗水性较强,抽出的水又迅速返回井内.做好地表排水系统,防止雨水倒灌,井点抽水就近排入下水道中.五.轻型井点降水系统拆除1.根据工程结构特点和土方回填进度要求,陆续关闭与逐步拔除井点降水管.所留孔洞立即用砂土填实.2.拔除井点管拆除集水总管等配件,应分门别类堆放,与时余运出施工现场.轻型井点降水系统的设备和附件应与时清洗和保养.六.质量验收标准七.环境安全措施1.机电设备操作人员应具备相应的资质,电的有关各项规定,并要严格检查,发现问题与时纠正.2.机电设备应有漏电保护装置.符合施工用电的有关各项规定,并要严格检查,发现问题与时纠正.3.废水排放应符合环境保护的有关各项规定,并要严格检查,发现问题与时纠正.。
轻型井点降水的施工方案

轻型井点降水的施工方案一、轻型井点降水介绍沿基坑四周每隔肯定间距布设井点管,井点管底部设置滤水管插入透水层,上部接软管与集水总管进行连接,集水总管为Φ150钢管,周身设置与井点管间距相同的Φ40吸水管口,然后通过真空吸水泵将集水管内水抽出,从而达到降低基坑四周地下水位的效果,保证了基底的干燥无水。
水井大致分为四大类,无压完整井、无压非完整井、承压完整井、承压非完整井。
二、适用范围适用于渗透系数为0.1~50m/d的土层中。
降水深度为:单级井点3~6m,多级井点6~12m三、基坑涌水量计算计算公式:式中:Q基:基坑基本排水量K:粘土层渗透系数,K=0.10m/d。
四、井点计算式中:q——单井出水本领(m3/d)r0——过滤管半径=0.025ml——滤管进水部分长度=2m井点数及井距采纳公式:井数:n=1.1Q/q根平均井间距b=L*m/n式中:L——基坑周长n——井点根数五、井点降水工艺及技术措施降水井成孔采纳冲孔机械成孔,但由于冲击成孔效率较低,先由人工先清理块石层障碍,再布置冲击钻机进场。
1、管井成孔工艺场地平整→井位放线→人工清理块石障碍→复核桩位→开挖浆池、浆沟→护筒埋设→桩机就位、孔位校正→冲击造孔、泥浆循环、清除废浆、泥渣→终孔验收→下滤水井管和填充砂砾。
2、降水运行(1)可采纳分次降水,即边抽水边进行土方开挖,以使水位缓缓平稳下降,因猛烈水位下降会加添沉降量,避开导致相邻建筑物及道路损坏。
(2)严禁挖土机、吊车等设备撞击降水管、排水管线、电缆等。
(3)降水要保证昼夜连续运转,防止因停泵使水位上升,造成“涌槽”事故,现场要配备备用电源(现场配备2台300KW发电机组)。
(4)设多个闸箱,单闸单箱单机。
(5)专人巡查,发觉停泵,立刻处理。
(6)降水结束需缓慢稳定抬升水位必具备两个条件:一是建筑物基础工程必需施工完毕,二是建筑物荷载大于地下水上顶托力,充足抗浮设计要求。
3、降水动态观测(l)降水开始后即对地下水位进行全面的观测记录,以便随时获得水位降落信息。
轻型井点降水方案(全文完整版)

轻型井点降水方案(全文完整版)范本一:轻型井点降水方案(全文完整版)一:方案目的本方案旨在通过轻型井点降水技术,解决城市中心区域的降水不足问题,提高城市生态环境。
二:方案背景城市中心区域由于高楼大厦的密集,导致空气不流通,水蒸气无法自然凝结形成雨水,造成城市中心区域降水量明显不足的现象。
为了改善这一情况,提高城市中心区域的生态环境,我们提出了轻型井点降水方案。
三:方案内容1. 安装人工井点: 在城市中心区域的指定位置,安装一定数量的人工井点,每个井点覆盖范围为1000平方米。
2. 井点设备: 每个井点设备包括水泵、喷头和控制系统,水泵用于提取地下水,喷头用于将水喷洒到空中形成雾气,控制系统用于控制水泵的开关和喷头的喷水量。
3. 雾气: 通过控制系统,每个井点按照设定的时间和喷水量释放水雾,使雾气形成云团,进而产生降水。
4. 监测系统: 在城市中心区域设置监测系统,对降水量和雾气浓度进行实时监测,以便及时调整井点设备的工作状态。
5. 运行管理: 设立专门的运行管理团队,负责井点设备的维护和运行管理,定期检查设备的工作状态,保证方案的有效进行。
四:方案效果本方案实施后,可有效增加城市中心区域的降水量,改善空气质量,提高生态环境。
五:风险评估1. 设备故障: 井点设备可能会出现故障,导致降水效果减弱或停止。
需要进行定期检查和维护,及时修复故障。
2. 水资源限制: 如果地下水资源有限,可能会限制井点设备的使用。
需与相关部门进行协调,确保水资源的充足供应。
六:附件本文档涉及附件如下:1. 井点设备安装图纸2. 监测系统示意图3. 运行管理团队成员名单七:法律名词及注释本文涉及的法律名词及注释如下:1. 城市生态环境保护法:指对城市生态环境实施保护,促进城市可持续发展的法律法规。
2. 水资源管理条例:指对水资源的开发、利用和保护实施管理的法律法规。
范本二:轻型井点降水方案(全文完整版)一:方案目的本方案旨在通过轻型井点降水技术,解决城市广场降水不足的问题,改善城市生态环境。
轻型井点降水施工方案

轻型井点降水施工方案1、工程简介着中重说明基础工程中的地质概况、地下水概况以及与降水有关的情况,即为什么要降水?2、降水方式方法及采取的措施现场井点布置,采用的设备型号,技术参数等。
3、降水工作中应注意的事项在降水施工过程中,技术、质量、安全、环保应注意的事项4、计算书(附后)本节主要讨论轻型井点降水有关计算轻型井点降水计算一、总涌水量计算1.基坑总涌水量Q(m3/d),即环形井点系统用水量,常按无压完整井井群,用下式计算公式:Q=1.366K (2H―s)s/ lgR―lgx02.单井井点涌水量q(m3/d)常按无压完整井,按下计算公式:q=1.366K(2H―s)s/lgR―lgr式中:K—土的渗透系数(m/d);H—含水层厚度(m);s—水的降低值(m);R—抽水影响半径(m),由现场抽水试验确定,也可用下式计算:R=1.95 s√H Kr—井点的半径(m);x0—基坑的假想半径(m,当矩形基坑长宽比小于5时,可化成假想半径x0的圆形井,按下式计算:x0=√F/πF—基坑井点管所包围的平面面积(m2);π—圆周率,取3.1416;二、井点管需要根数井点管需要根数n可按下式计算:n=m Q/ q式中q=65πdl 3√ K式中:n—井点管根数;m—考虑堵塞等因素的井点备用系数,一般取m=1.1;q—单根井点管的出水量(m3/d);d—滤管直径(m);l—滤管长度(m);三、井点管平均间距井点管平均间距D(m),可按下式计算:D=2(L+B)/n-1求出的D应大于15d,并应符合总管接头的间距(一般为80、120、160mm)要求。
式中:L—矩形井点系统的长度(m);B—矩形井点系统的宽度(m);四、例题某工程基坑平面尺寸见图,基坑宽10m,长19m,深4.1m,挖土边坡1:0.5。
地下水位-0.6m。
根据地质勘察资料,该处地面下0.7m,为杂填土,此层下面有6.6m的细砂层,土的渗透系数K=5m/d,再往下为不透水的粘土层。
轻型井点降水施工方案

轻型井点降水施工方案一、施工前准备。
1. 地质勘察,在施工前,需要对井点周边地质情况进行勘察,了解地下水位、土层情况等,为施工方案的制定提供依据。
2. 设备准备,准备好所需的轻型降水设备,包括水泵、管道、阀门等,并进行设备检查和维护,确保施工过程中设备的正常运转。
3. 安全防护,施工现场需要进行安全防护措施,包括设置警示标志、搭建安全围栏、配备安全帽、手套等防护用具,确保施工人员的安全。
二、施工流程。
1. 井点布置,根据地质勘察结果,确定井点的布置位置,采用轻型设备进行井点的布置和固定。
2. 设备连接,将水泵与管道连接,确保管道畅通无阻,阀门处于关闭状态,待施工准备就绪。
3. 开启水泵,启动水泵,将地下水抽出到地面,控制水泵的流量和压力,确保井点降水的效果。
4. 监测井点,在降水过程中,需要对井点进行实时监测,包括水位、水质等指标,确保降水效果符合要求。
5. 施工结束,当达到降水要求后,关闭水泵,拆除井点设备,并对施工现场进行清理,确保施工结束后环境整洁。
三、施工注意事项。
1. 环境保护,在施工过程中,要注意保护周边环境,避免污染地下水和土壤,合理处理井点降水产生的废水。
2. 安全管理,严格执行施工安全规范,保障施工人员的人身安全,避免发生意外事故。
3. 设备维护,定期对降水设备进行维护保养,确保设备的正常运转,提高施工效率和降水效果。
四、施工效果评估。
1. 水位监测,在施工结束后,对地下水位进行监测,评估降水效果是否符合预期要求。
2. 数据分析,对降水过程中的监测数据进行分析,总结施工中存在的问题和改进措施,为今后的施工提供参考。
3. 效果评价,根据实际降水效果,对本次施工进行评价,总结经验,提高施工质量和效率。
结语。
轻型井点降水施工方案的制定和实施,对于地下水位调控和施工安全具有重要意义。
在施工过程中,要严格执行施工方案,确保施工质量和效果,同时注重环境保护和安全管理,为工程建设提供良好的保障。
轻型井点降水工程设计方案

轻型井点降水工程设计方案一、工程概况本工程位于XX市XX区,为一栋高层建筑,占地面积约为XX平方米,建筑高度约为XX米。
建筑地下室三层,基坑深度约为XX米。
场地周围环境复杂,附近有居民区、道路和地下管线等。
根据地质勘察报告,场地内土层主要由粉土、砂土和粘土组成,地下水位较高,对基坑稳定性有较大影响。
因此,本工程采用轻型井点降水方法进行基坑降水。
二、设计依据1. 地质勘察报告:提供场地的地质条件、土层分布、地下水位等信息。
2. 基坑支护设计:确定基坑的支护结构形式、深度和施工要求。
3. 基坑降水设计规范:依据《建筑基坑支护技术规范》(GB 50007-2011)等规范进行设计。
三、轻型井点降水设计1. 井点布置:根据基坑形状和大小,布置环状井点,并在基坑周边设置附加井点,以提高降水效果。
井点间距根据土层性质和地下水位情况确定,一般为1.5~2.0米。
2. 井点设备选择:- 井点管:选用直径48mm的钢管,长5.4米,下端装1.2米长的滤管。
- 连接管:选用内径48mm的透明塑料管,与集水总管连接。
- 集水总管:选用直径75mm的钢管,分节连接,每节长4.0米。
每隔0.8~1.2米设一个连接井点管的接头。
- 抽水设备:选用4台真空泵。
3. 施工工艺:- 确定井点的布置形状:根据基坑形状和大小,布置环状井点,并在基坑周边设置附加井点。
- 开挖沟槽:用挖掘机开挖沟槽,埋设井点管,回填粗砂滤层。
- 敷设集水总管:将集水总管连接到井点管上,形成闭合的降水系统。
- 连接抽水设备:将抽水设备与集水总管连接,进行试抽。
- 检查井点系统:检查井点系统是否有死管、漏气等现象,确保系统正常运行。
4. 施工技术措施及质量保证措施:- 施工前,对施工人员进行技术培训,了解轻型井点降水的施工工艺和注意事项。
- 施工过程中,严格把控井点管的埋设深度和滤管的长度,确保井点系统的正常运行。
- 定期检查井点系统,发现问题及时处理,确保降水效果。
轻型井点降水施工方案

轻型井点降水施工方案
一、背景
在建筑施工中,往往需要进行降水措施,以确保施工现场的安全和施工进度的顺利进行。
在一些地下工程中,如地铁、地下室等地方,传统的泵车降水方案无法使用。
因此,轻型井点降水方案应运而生。
二、适用场合
轻型井点降水方案适用于以下工程:
1.地下承台
2.地下车库
3.地下管廊
4.埋地燃气管道
5.地下电站
6.地下洗车房
三、施工流程
1. 施工前准备
进行轻型井点降水前,需要进行以下准备工作:
1.准备井点材料、钻机、降水泵等设备;
2.制定施工计划,并进行现场勘察;
3.设计井点布置方案,并进行标注。
2. 井点钻孔
1.在井点标注处进行钻孔;
2.对钻孔进行检查并进行补强;
3.安装铁管和水泵。
3. 井点施工
1.开始施工,对井点进行降水;
2.根据现场实际情况,对降水量进行调整。
4. 施工结束
1.检查降水效果;
2.拆除井点设备。
四、注意事项
1.施工过程中应注意安全;
2.严格按照施工计划进行施工;
3.对现场进行清理,保持施工环境整洁;
4.在施工过程中,注意保护现场周边环境。
五、总结
轻型井点降水方案在建筑施工中起到了非常重要的作用。
通过合理的设计和完善的施工流程,可以确保施工现场的安全和施工进度的顺利进行。
同时,在施工过程中,应做好安全防护和环境保护,保证施工的质量和效率,为建设一个更加美好的社会做出贡献。
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
石武高铁新郑东220千伏牵引站接入系统工程I标段」般施工技术方案(轻型井点降水)郑州祥和集团电力工程有限公司2011年02月25日批准:年月日审核:年月日编写:年月日一、工程地质概况 (4)二、编制依据 (4)三、降水方案选择 (4)四、井点降水相关计算 (5)五、主要降水设备 (6)六、施工工期 (7)七、井点施工方法 (7)八、质量标准及质量保证措施 (9)九、危险点分析 (10)十、安全生产及文明施工措施 (11)十^一、环保措施 (11)一、工程地质概况线路经过地区为平地,海拔高程为110m左右,最高气温为40C,最低气温为-20 C, 最大风速为28.12m/s。
土质主要为粉质粘土及砂土,陇海铁路以东地下水位较高,G44、G45地下水位在-1.5m~-2.0m 处。
二、编制依据《国家电网公司施工项目部标准化工作手册220kV输电线路工程分册》《电力建设施工及验收技术规范》《建筑施工计算手册》《地基与基础工程施工及验收规范(GB50202-2002》《建筑工程质量检验评定标准(GBJ301-88)》《110kV及以上送变电工程启动及竣工验收规程(DL/T 782-2001 )》《电力建设安全工作规程第2部分:架空电力线路(DL 5009.2-2004 )》《电力建设安全健康与环境管理工作规定》 (国家电网工[2004]488号)《110〜500kV架空输电线路设计技术规程(DL/T5092 - 1999)》《110〜500kV架空电力线路工程施工质量及评定规程(DL/T5168-2002)》《国家电网公司输变电优质工程评选办法(2005版)》《国家电网公司输变电工程达标投产考核办法(2005版)》三、降水方案选择本工程G44基础埋深在-2.85m,G45基础埋深在-3.05m 水位在-1.5m~-2.0m处无法施工,本工程采取的措施是:采用井点降水。
本工程G44基础底标高为-2.85m,G45基础埋深在-3.05m,可采用轻型井点降水。
G44基础平面基底长度、宽度约为12m基础埋深为2.65m,结合本工程基础施工采用轻型井点降水法,沿基础环状布置进行降水。
采用 潜水泵的方法。
四、井点降水相关计算1、井点管的埋设深度H> H1+h + iL + I式中H ---- 井点管的埋设深度(m )H1------ 井点埋设面至基坑底面距离(m )取3.0mh —— 基坑中央最深挖掘面至降水曲线点的安全距离 (m )取1.0mL ----- 井点管中心至基坑中心的短边距离(m )取5.3m i ――降水曲线坡度取1/5 I ----- 滤管长度(m )取1.4H > 3+ 1.0 + 5.3 X 1/5 + 1.4=6.46m 取 6.5m承压水完整井涌水量计算简图-5.8-0.32、需井点管数量基坑四周采用的井点管数量为每 2m 距离设置1一眼井,故布置可行。
3、结论根据现场水位情况目前水位在地坪以下 1.5〜2.1米左右以及现场测量实 际情况为-1.8m ,本工程井点管深度在6.5 m (从室外地坪向下埋管)间完全 能保障降水要求。
降水井点管埋深剖面图见下图,平面布置图见附页。
钢管© 200钢管——出水污水井井点管埋深剖面图五、主要降水设备1、 本工程共设轻型潜水泵4台(2寸泵)。
2、 轻型井点降水井点为22眼井(暂定),总排水管长度为150m 塑料管80m3、 井点管:本工程井点管采用内直径 50mn 钢管管,深度为6.5m ,管下端配 有与井点管同径的滤管和管尖。
滤管长度为1.4m,滤管壁上钻有呈梅花状的 直径为© 4的滤孔。
滤孔面积一般为滤管表面积的 15%-20%滤管壁处包两层 滤网内层采自然地面标咼 粘土封闭500m 咼-66.m m抽水设备中粗砂填充基底标高-2.85m 、-3.0m 基底标高-6.00m'1 __________________________用网眼为30-50孔/cm2的尼龙丝布细滤网,外层采用网眼为3-10 孔/cm的尼龙丝布粗滤网,井点管的上端用弯管与总管相连。
4、本工程总排水管采用© 50钢管(排水管长度按现场到下水管道的实际距离定),配用钢管采用直径为50mm六、施工工期井点降水开工时间为2011年3月7日,达到降水效果进行基础土方开挖施工。
七、井点施工方法1、施工流程布置井点管—k井点管与总管连接—试抽水-------------- 进入工作状态—基础结束及回填完后拔管。
2、井点施工方法(1)、井点管的埋设1)、采用直径30mm的冲水管进行冲孔,采用潜水泵循环抽送。
冲孔进冲管应垂直插入土中,并作上下左右摆动,加剧的砂土的松动,并且在孔旁挖一个排泥浆水沟。
冲管深度应比滤管深度深1m以便流泥,井点管与孔壁间及时用粗砂灌实。
井点管要位于砂滤水层中间,并且井点管在地面-0.5m深度内用粘土填实,以防止漏气。
2)、井点管埋设完毕,应接通总管与抽水设备进行试抽水。
检查有无漏水,漏气现象,出水是否正常,有无淤塞现象,如有异常情况应及时进行修理。
(2)、井点管的使用井点管工作后,应保证连续不断的排水,正常出水规律是“先大后小,先混后清”。
如不上水,或水一直较混或出现清后水混等情况,应立即检查纠正。
(3)、井点管的拆除待地下构筑物竣工并进行回填土后,方可拆除井点系统,所留孔洞用砂或土填塞。
3、施工要点因本工程基坑面积较大,故采用沿建筑物环状布置井点。
井点管布置距坑距离为1.5--2.0m,井点管的间距为2m为了充分利用泵的抽空能力。
集水总管标高尽量接近地下水位线,并沿抽水水流方向有0.5%的上仰坡度,水泵轴心与总管齐平,因渗透系数为150 m/d。
拉土进出口处可不设置井点管。
降水设施完毕后开始降水,降水对在基础底板四角设直径为400mm水位观测孔4个(深2m),观测孔设置于无设备基础的空白位置,降水过程中随时观测水位并进行记录,发现水位异常随时汇报。
降水过程中水泵设备设专职人员昼夜进行值班,观测各井点降水情况和各泵运行情况,如下渗水量不满足水泵运行时,及时更换水泵。
水位降至设计基层下0.5m后,进行土方施工。
八、质量标准及质量保证措施1、质量标准2、质量保证措施(1)、坐标及高程控制点经过厂区内基准点引测,检查验收合格后进行土方开挖、降水施工。
(2)、土方开挖前用石灰划出开挖线,确保土方开挖尺寸正确。
基坑开挖尺寸及标高符合质量标准。
(3)、为了保证达到有效降水,机械型号、功率须达到方案要求。
并现场配有备用泵。
(4)、在施工区域设有降水观察孔,掌握了解降水情况,保证降水效果。
(5)、井点降水设备正常工作后,应设置专人24小时不间隔值班,以防出现异常应及时修复。
(6)、在临近本工程的建筑物上设置沉降观测点;开始降水时,应缓慢进行,防止降水速度过快,影响原主厂房地基发生不均匀沉降;随时观察原主厂房沉降情况,控制降水速度。
(7)、因基坑范围比较及渗透系数大,宜在基坑中部设置临时井点系统进行辅助降水,井点环不能封闭时,在机械挖土有开行路线入口部位向基坑外侧延长20m 作为保护段,以确保降水效果。
九、危险点分析1、电源线老化漏电伤人。
预防措施:根据水泵电机电流量配置相应电源线,做到一闸一机,漏电保护器动作灵活,交接班时对漏电保护器进行试动作,防止因长时间运行而失灵。
2、塌方预防措施:土方施工按要求坡度放坡,设置专人巡视边坡的稳定性,防止土方坍塌事故发生。
3、机械伤害预防措施:由于同挖土工程交叉施工,严禁在机械挖土范围内进行人工降水施工,防止机械伤害。
4、高处坠落预防措施:在基坑四周设置红白相间警示栏杆,栏杆距基坑不小于1m防止车辆、人员坠入坑内。
十、安全生产及文明施工措施1、进入施工现场的作业人员,必须正确佩戴安全帽及穿戴好劳动防护用品。
2、如有交叉作业应设专人监护或有防护措施,否则严禁施工,以免发生物体打击及碰撞事故。
3、如在夜间施工安全照明必须充足。
4、文明施工责任区划分明确,无死角,责任落实,并设有明显标记,便于检查、监督。
5、施工用机械、设备完好、清洁,安全操作规程齐全,操作人员持证上岗,并熟悉机械性能和工作条件。
6、施工现场在施工过程中出现的各种坑、沟、孔洞,施工单位应根据实际情况,设置标准的与地平行的安全沟道盖板或可靠的围栏、档脚板或警告标志。
7、拉电源时,严禁将电线直接勾挂在闸刀上或直接插入插座内使用,必须用插头连接。
8施工单位应经常组织施工人员进行安全文明施工学习,使每位施工人员掌握安全文明施工知识,不断地提高安全文明施工意识,做到安全生产文明施工。
9、由于井点降水处于湿工作状态下,电源安全装置须达到三级保护要求。
十、环保措施1、井点施工产生的泥浆、弃土应及时清运,运输时必须覆盖,避免产生扬尘和遗撒。
2、排出的地下水应经过沉淀处理后方可排入专用管道。
3、施工现场应遵守现行国家标准《建筑施工场界噪声限值》GB12523规定的噪声限值,发现超标应及时采取措施纠正。