电热水龙头安装步骤.
德龙2180406M电热水龙头安装及使用说明书

Installation andoperatinginstructions2180406M - January 2016CONTENTS PagePlumbing and electrical notes (1)Introduction (2)Safety warnings (2)Main components (3)Specifications (3)Site requirements (4)General installation notes (5)Siting of the shower (6)Removing the cover (7)Plumbing connections (7)Fitting the shower to the wall (10)Electrical connections (11)Commissioning (12)Operating the shower (15)Adjusting the maximum temperature stop (16)Instructions for installers and service engineers only (17)Spare parts (18)Fault finding ...............................................................................19 - 20Water/Cable entry points diagram (21)Service policy, guarantee, etc. ..................................................rear coverTo check the product suitability for commercial and multiple installations, please contact Triton’s speci cation advisory service before installation.Telephone: Facsimile:E mail:************************************************.uk1 PLUMBING NOTES1.1All installations must comply with WaterRegulations or Water Bylaws.1.2Supply pipes must be flushed to cleardebris before connecting the shower unit.1.3DO NOT connect the shower unit tothe mains cold water supply as it woulddamage the unit and also, the installationwould be in breach of Water Regulations.1.4DO NOT use excessive force when makingconnections to the flexible hose orshowerhead – finger tight is sufficient.1.5ALL plumbing connections are to becompleted and water supplies turned onBEFORE switching on the electricity supply.The shower must not be operated drywithout water.1.6DO NOT solder pipes or fittings within300 mm of the shower appliance, as heattransfer can damage components.1.7When installed, the top of the shower unitmust be at least 75 mm lower than thebase of the cold water storage cistern toprevent the pump being run dry withoutwater.1.8 A dedicated cold water supply must betaken directly from the cold water cisternto the shower. This draw-off must be onthe opposite side of the cistern to the floatoperated valve to reduce the risk of airentering the unit.1.9The action of the pump is to increase theflow rate. If the supply pipework cannothandle the resulting flow rate then:1.9.1The anticipated flow rate may notbe achieved.1.9.2 Air may be drawn into the hotsupply from the vent pipe causingspluttering and temperature fluctuations atthe showerhead.1.10 Fullway isolating valves MUST be fittedon the hot and cold water supplies tothe shower as an independent meansof isolating the water supplies shouldmaintenance or servicing be necessary. DONOT use stop taps or ball-o-fix type valveswhich restrict flow.2 ELECTRICAL NOTES2.1The installation must comply with BS 7671‘Requirements for electrical installations’(IEE wiring regulations). Make sure theincoming hot and cold water supplies tothe shower are adequately earth bonded. 2.2DO NOT turn on the electrical supplyuntil the plumbing connections have beencompleted. Only then can the electricity beswitched on in order to power the solenoidto turn water on to the shower whencommissioning. The shower must not beoperated dry without water.2.3The mains supply must be 230/240V, at50Hz, connected to the unit via a doublepole switched 3 Amp fused connectionunit (not supplied) with a minimum 3 mmcontact separation gap in each pole.2.4In accordance with ‘The Plugs and Socketsetc. (Safety) Regulations 1994’, this unitis intended to be permanently connectedto the fixed electrical wiring of the mainssystem.2.5Fuses do not give personal protectionagainst electric shock.2.6 A 30mA residual current device (RCD)MUST be installed. This may be part of theconsumer unit or a separate unit.INTRODUCTIONThis book contains all the necessary fitting and operating instructions for your Triton Power Shower. Please read them carefully.The shower installation must be carried out by suitably competent person and in sequence of this instruction book.Care taken during the installation will ensure a long and trouble free life from your shower IMPORTANT: All plumbing connections must be completed BEFORE making the electrical connections.Please read through the whole of this book before beginning your installation. IMPORTANT: The fittings on the pipe inlet elbows are of the push-in type. The pipework must be cut with a pipe cutter and all burrs and rough edges removed from the endof the tube. The fittings can be used with copper and plastic pipe.Where chrome plated pipe is used, remove the first 25 mm of plating.Note: The pump inside this product is rated15 minutes on / 45 minutes off duty cycle.SAFETY WARNINGSa.DO NOT insert fingers into the push-in inletfittings. Doing so could cause injury.b.Under no circumstances must this productbe connected to mains cold or hot watersupplies.Failure to comply will invalidatethe guarantee.c.The shower MUST NOT be used ifsuspected of being frozen.d.The outlet of this appliance MUST NOT beconnected to any form of tap or fitting notrecommended by the manufacturer.e.The showerhead cartridge MUST be cleanedregularly to remove scale and debris.f.This appliance MUST be earthed.g.Switch off immediately at the isolatingswitch if water ceases to flow during use. h.DO NOT operate the shower outside theguidelines laid out in ‘site requirements’.i.DO NOT operate the shower if theshowerhead or spray hose becomesdamaged.j.DO NOT restrict flow out of the shower by placing the showerhead in direct contactwith your body.Replacement parts can be ordered from Triton Customer Service. See ‘spare parts’ for details and part numbers.will minimise the effects of scale in hard waterareas.Maximum supply head 10m.Fig.3 illustrates all the incorrect connections that must be avoided.All pipework to the shower unit must be routed where it remains below the level of water in the cistern. In the case of horizontal sections of pipework in lofts, it may be necessary to fit automatic air vents at high points on the supplies to remove the possibility of air locks.For the operation of the shower only, it is recommended that the cold water storagecistern is capable of holding at least 114 litres(25 gallons). Where other hot and cold outlets are likely to be in use simultaneously, the storagecapacity should be increased to 228 litres (50 gallons) in accordance with BS 6700.Do ensure compliance with the Water Regulations/Bylaws.DO NOT connect to a combination cylinder unless there is a guaranteed 114 litre cold supply to the cylinder as the shower can deliver up to 14 litres per minute. It is advisable to check thatSITE REQUIREMENTSWaterThe installation must be in accordance with Water Regulations/Bylaws and BS 6700.For correct operation of this shower unit, both hot and cold water supplies to the appliance must be gravity fed, at nominally equalpressures, from a cold water storage cistern and a hot water storage cylinder.The water circuit should be installed so that the flow is not significantly affected by other tapsand appliances being operated elsewhere on the premises.Fig.2 shows a recommended installation wherethe hot water supply for the shower is madevia a tee connection on the underside of thehorizontal section of pipework from the cylinder. Alternatively, the connection can be taken from the hot supply pipe to other outlets as long as it is the first draw-off below the ventilation pipe tee.the infill rate from the float operated valve meets the output requirements..It is recommended that there is a minimum of approximately 114 litres (25 gallons) of hot water storage per appliance.The shower MUST NOT be connected to the mains cold water supply.DO NOT use jointing compounds.GENERAL INSTALLATION NOTES1. DO NOT take risks with plumbing orelectrical equipment.2. DO NOT install this unit in a position whereit could become frozen.3. Isolate electrical and water supplies BEFOREproceeding with installation work.4. Shower control MUST be fed from a coldwater storage cistern and hot water cylinderthat provides nominally equal pressures.5. The unit must be mounted onto the finished wall surface (on top of tiles).DO NOT tile up to the unit after fixing to the wall.6. If installing with rear inlet supplies, it isrecommended the supply pipework is sealed to the wall so as to prevent water from leaking back into the wall.7. In solid wall installations, the supplypipework should be housed withinducting in order to allow some free lateral movement when making connections and to ensure compliance with requirements of accessibility of pipes and pipe fittings.Fig.4 shows a schematic wiring diagram of the unit.SITING OF THE SHOWERIMPORTANT: If fitting to a tiled wall, always mount the unit on the surface of the tiles. NEVER tile up to the unit.Refer to fig.5 for correct siting of the shower. Position the unit vertically where it will NOT be in direct contact with water from the showerhead.Note: Allow sufficient room between the ceiling and the shower unit to access the top cover screw.Position the shower and showerhead on the wall so that all controls can be comfortably reached when using the shower.The showerhead and riser rail can be positioned either side of the shower unit.Note: Water Regulations require the showerhead be ‘constrained by a fixed or sliding attachment so that it can only discharge water at a point not less than 25 mm above the spill-over level of the relevant bath, shower tray or other fixed appliance’. The use of the supplied soap dish will in most cases meet this requirement, but if the showerhead can be placed within a bath, basin or shower tray, then a device must be fitted toprevent back-flow.fig.9 and fig.10., but right-hand side for(fig.12).backplate as template (fig.17). Note that four fixing holes are provided but using only two should be adequate for most site ing the pipe removal tool supplied, push back and hold the collets from the pipework (fig.18) to disengage the pipework from the inlet elbows.Remove unit from the wall.Drill and plug the wall.(An appropriate drill bit should be used. If the wall is brick, plasterboard or a soft building block, appropriate wall plugs and screws should be fitted).Note: If fitting rising supplies to the unit, ensure debris does not enter the pipes when drilling the wall.Offer the backplate unit up to the completed pipework and manoeuvre so that the end of the pipes enter fully into the inlet fittings.Check the backplate is square and the fixing holes are aligned (fig.17).Secure to the wall with fixing screws supplied.OPERATING THE SHOWERCheck all plumbing and electrical supplies are connected and switched on.To start the shower, rotate the flow controlanti-clockwise from the ‘stop’ position (fig.29). Adjust the control until the flow rate is satisfactory.For maximum flow, turn the flow control fully anti-clockwise to the ‘max’ position.To adjust the temperature, rotate the control (fig.30). The temperature is numbered for ease of use. The temperature ranges from-‘1’ – fully cold to ‘9’ – fully hot.Once the preferred temperature is reached, no further adjustment is required, providing the hot and cold water supplies remain constant.To stop the shower, return the flow controlto the ‘stop’ position by rotating clockwise (fig.31). This stops the pump and water flow. Unless the shower is to be used again immediately, the shower should also be switched off at the electricity isolating switch.As a safety feature, the temperature controlhas a built-in stop to prevent you accidentally exceeding your highest desired temperature. If adjustment is required see section ‘Adjusting the maximum temperature stop’.To override this stop, depress the button (fig.32) while the control is up against the stop and turn the control anti-clockwise to the higher settings (pressing the button before the stop will not operate the override mechanism even if the control is turned with the button depressed).To return to the normal temperature range just turn the temperature control clockwise until itis past the maximum temperature stop. Make sure the temperature control is in the normal temperature range when the shower is switched off. The stop comes in a factory set position based on 65°C stored hot water temperature. Note: As the flow control is adjusted it is normal for the sound of the pump to alter in pitch.fitted and the wires are clear of obstructions. Secure with the top and bottom fixing screws (fig.8). Replace the flow control so that it aligns with the ‘min’ position.Fit the temperature disc (it will only fit one way) and maximum temperature stop (fig.27). Replace the temperature control onto the valve spindle. Make sure the pointer aligns with setting ‘9’ on the temperature disc (fig.28). Secure with the retaining screw and fit the cover trim.Switch on the electricity supply to the unit and then turn on both water supplies.SPARE PARTSIMPORTANT: Switch OFF the electricity at the mains supply and remove the correct circuit fuse before attempting any fault finding inside the unit.Symptom Cause Action/Cure1.1.1 Turn the temperature control clockwise. 1.2.1 Turn the temperature control clockwise. 1.3.1 Remove filter and clean. If problem is with check valve, contact Customer Service.1.4.1 Isolate shower and consult a competent plumber or contact Customer Service.2.1.1 Turn temperature control anti-clockwise. 2.2.1 Turn temperature control anti-clockwise. 2.3.1 Turn off the shower and wait for hot water cylinder to reheat.2.4.1 Remove filter and clean. If problem is with check valve, contact Customer Service.2.5.1 Turn off the shower. Consult a competent plumber or contact Customer Service.3.1.1 Blown fuse. Check supply. Renew fuse. If it fails again consult a competent electrician.3.1.2 Power cut. Check other appliances and if necessary, contact local Electricity Supply Co.3.2.1 Consult a competent electrician or contact Customer Service.3.3.1 Thermal protection on motor has operated. Allow appliance to cool and reset itself. If it persists, contact Customer Service.1 Water too hot.2 Water too cold.3 Pump does not operate.1.1 Not enough cold water flowing through shower.1.2 Increase in the ambient cold water temperature.1.3 Cold inlet filter blocked or check valve sticking.1.4 Cold water supply blocked or cut off.2.1 Not enough hot waterflowing through shower.2.2 Decrease in ambient cold water temperature.2.3 No hot water in the storage cylinder.2.4 Hot inlet filter blocked or check valve sticking.2.5 Hot water supply blocked or otherwise cut off.3.1 Interrupted powersupply.3.2 Electrical malfunction. 3.3 Motor overheated.Symptom CauseAction/Cure4.1.1 Check water elsewhere in house and if necessary contact the local Water Company.4.2.1 Switch off shower and contact Customer Service.4.3.1 Clean showerhead.4.4.1 Clean filters.5.1.1 Isolate water to unit. Remove check valves. Clean and replace.6.1.1 Call Customer Service. 6.2.1 Call Customer Service.7.1.1 Call Customer Service.7.2.1 Replace pump.8.1.1 Fit blanking plugs into unused inlets.4 Water does not flow or is reduced.5 Cross flow of hot and cold water into system.6 Water dripping from showerhead when turned off.7 Pump is noisy or air lock in pump.8 Unit running erratically.4.1 Water supplies cut off. 4.2 Shower blocked or air in the system.4.3 Showerhead blocked.4.4 Blocked filters.5.1 Dirt/debris in check valves.6.1 Debris in solenoid valve.6.2 Potentiometer faulty.7.1 Air lock in pump.7.2 Worn pump bearings.8.1 Blanking plugs not fitted into unused inlets.Entry PointsDiagram Key:Water Entry PointsCable Entry PointsWEEE Directive – Policy StatementAs a producer and a supplier of electric showers, Triton Showers is committed to the protection of the environment via our own environmental policy and the compliance with the WEEE directive.Triton Showers is fully registered with the Environment Agency under the following schemes: Repic: Producers take-back scheme (PTS), registration number WEE/EJ3466QVV alpak: Distributor take-back scheme (DTS), registration number 9659All our electric products are labelled accordingly with the crossed out wheeled bin symbol. This indicates, for disposal purposes at end of life, that these products must be taken to a recognised collection points, such aslocal authority sites/local recycling centres; this will be free of any charges. Do not return to Triton Showers.Triton Showers Triton Road NuneatonWarwickshire CV11 4NRTriton is a division of Norcros Group (Holdings) LimitedTRITON reserve the right to change product specification without prior notice. © TRITON SHOWERS 2015Customer Service: ***********Fax:***********E-mail:*********************************.uk26-02-2015 - 1 yr elec UK SERVICE POLICYIn the event of a product fault or complaint occurring, the following procedure should be followed:1. Telephone Customer Service on *********** having available,your details including post code, the model number and power rating of the product, together with the date of purchase and, where applicable, details of the particular fault.2. If required, the Customer Service Advisor will arrangefor a qualified engineer to call.3. All products attended to by a Triton service engineer must be installedin full accordance with the Triton installation guide applicable to the product. (Every product pack contains an installation guide, however, they can also be bought via our Customer Service Spares Department).4. Our engineer will require local parking and if a permit is required thismust be available to the engineer on arrival at the call.5. It is essential that you or an appointed representative (who mustbe over 18 years of age) is present for the duration of the serviceengineer's visit. If the product is in guarantee you must produce proof of purchase.6. Where a call under the terms of guarantee has been booked andthe failure is not product related (i.e. scaling and furring, incorrect water pressure, pressure relief device operation or electrical/plumbing installation fault) a charge will be made. A charge will also be issued if nobody is at home when the service engineer calls or adequate parking/permit is not available.7. If the product is no longer covered by the guarantee an up front fixedfee will be charged before the site visit.8. Should proof of purchase not be available on an “in-guarantee” call,or should the service engineer find that the product is no longer under guarantee, the engineer will charge the same fixed price and the customer will be expected to pay the engineer before he leaves. If payment is not made on the day an administration charge will be added to the fixed charge.9. If a debt is outstanding from a previous visit, or from any other Tritonpurchase, Triton reserves the right to withhold service until the debt has been settled.10. Triton takes the health, safety and wellbeing of its employees veryseriously and expects customers to treat all staff members with respect. Should any employee feel threatened or receive abuse, either verbally or physically, Triton reserves the right to withhold service and will support the employee with a legal prosecution.Replacement Parts PolicyAvailability: It is the policy of the manufacturer to maintain parts availability for the duration of production and a period of five years thereafter, in accordance with industry standards.Spare parts are available via our website, , or by telephoning Triton Customer Service Spares Department. Payment should be made by credit/debit card (excluding American Express or Diners Card). Payment can also be made by pre-payment of a pro forma invoice by cheque or money order.Telephone orders are based on information given during of the call. Before contacting Triton, please verify your requirements using the information contained in the supplied user guide. Triton cannot accept liability for incorrect part identification.。
水龙头开关:安装与施工方法

水龙头开关:安装与施工方法
水龙头开关是一个重要的设备,它能够控制水龙头的开关状态,并提供方便的使用体验。
本文将介绍水龙头开关的安装与施工方法。
安装准备
在进行水龙头开关的安装前,需要做一些准备工作。
首先,确
定安装的位置,确保水龙头开关与水龙头之间的距离适中。
其次,
检查水龙头开关的配件是否齐全,并确保其质量良好。
最后,准备
好所需的工具,如螺丝刀、扳手等。
安装步骤
以下是水龙头开关的安装步骤:
1. 关闭主水源:在安装水龙头开关之前,确保主水源已关闭,
以避免水流造成不必要的困扰。
2. 拆卸水龙头:使用扳手将原有的水龙头拆卸下来,注意保护周围的管道和墙面,以免损坏。
3. 安装水龙头开关:将水龙头开关按照说明书上的步骤进行安装,确保紧固螺丝牢固可靠。
4. 连接水管:将水龙头开关与水管进行连接,确保连接处无漏水现象。
5. 安装水龙头:将新的水龙头安装在水龙头开关上,注意与开关的对应位置,确保安装牢固。
6. 测试使用:打开主水源,测试水龙头开关的使用效果,检查是否正常开关,水流是否畅通。
施工注意事项
在进行水龙头开关的安装与施工时,需要注意以下事项:
- 定期检查水龙头开关的连接处,确保没有漏水现象。
- 注意使用合适的工具和力度,避免损坏水龙头开关或周围设施。
- 如果对安装不熟悉,建议请专业人士进行安装,以确保安全和可靠性。
以上是水龙头开关的安装与施工方法的简要介绍。
根据上述步骤进行安装,可以方便地控制水龙头的开关状态,提升使用体验。
如有其他问题,请随时咨询专业人士。
水龙头开关的安装施工详解

水龙头开关的安装施工详解1. 施工准备1.1 材料准备- 水龙头开关:根据需求选择适合的水龙头开关,确保质量合格。
- 管道:根据水龙头开关的尺寸和接口,准备相应的管道。
- 密封材料:如橡胶垫、密封胶等。
- 螺丝、螺母等紧固件。
- 工具:扳手、螺丝刀、切削工具等。
1.2 工作环境准备- 确保工作场地干净、整洁,无杂物。
- 确保水管系统已关闭,避免施工过程中发生漏水。
2. 安装步骤2.1 管道预埋1. 根据设计图纸,确定水龙头开关的位置,并在管道上做好标记。
2. 使用切削工具,将管道切割成合适的长度。
3. 将切割好的管道进行打磨,去除毛刺。
4. 将管道与水龙头开关的接口对齐,确保连接紧密。
2.2 安装水龙头开关1. 将水龙头开关的底座与管道接口紧密贴合,确保无间隙。
2. 使用扳手或螺丝刀,将水龙头开关底座的螺丝拧紧,确保连接牢固。
3. 安装水龙头开关的手柄,调整到合适的位置,并使用螺丝将其固定。
2.3 密封处理1. 在水龙头开关的接口处涂抹适量的密封胶。
2. 安装橡胶垫或密封垫,确保完全覆盖接口。
3. 使用螺丝将橡胶垫或密封垫固定在水龙头开关和管道之间。
2.4 检查与调试1. 打开水管系统,检查是否有漏水现象。
2. 检查水龙头开关的手柄是否灵活,是否能正常开启和关闭。
3. 如有需要,调整水龙头开关的位置,确保使用方便。
3. 施工注意事项- 确保在安装过程中,避免对水管系统造成损坏。
- 在密封处理过程中,确保密封材料涂抹均匀,无空隙。
- 在调试过程中,确保水龙头开关能正常使用,无异常声音或抖动。
4. 施工验收1. 检查水龙头开关的安装位置是否正确,是否符合设计要求。
2. 检查水龙头开关的连接是否牢固,是否有漏水现象。
3. 检查水龙头开关的手柄是否灵活,是否能正常开启和关闭。
5. 施工总结本施工详解详细介绍了水龙头开关的安装步骤和注意事项,通过正确按照施工步骤进行操作,可以确保水龙头开关的正常使用和安全性。
水龙头、电源插座安装

水龙头、电源插座安装1. 背景本文档旨在提供水龙头和电源插座的安装指南,以确保正确安装并提供使用者的便利。
2. 水龙头安装1. 准备工作:- 确保有足够的工具和材料,如螺丝刀、扳手、密封胶、管道等。
- 查阅水龙头的安装说明书,了解需要的安装步骤和特殊要求。
2. 安装过程:- 关闭水源,并用毛巾或布将水管拧紧,确保不漏水。
- 用螺丝刀拆下原有的水龙头,并将其底座清理干净。
- 根据安装说明书,安装新水龙头并确保底座与水槽紧密连接。
- 使用扳手适当拧紧螺丝,并使用密封胶固定水龙头。
3. 完成步骤:- 打开水源,并检查新安装的水龙头是否有漏水情况。
- 测试水龙头的热水和冷水功能,确保正常运转。
- 清理工作场地,并将旧水龙头适当处理或回收。
3. 电源插座安装1. 准备工作:- 确保有足够的工具和材料,如螺丝刀、电线、插座等。
- 查阅电源插座的安装说明书,了解需要的安装步骤和特殊要求。
- 关闭电源,确保操作安全。
2. 安装过程:- 根据安装说明书,选择合适的插座位置,并用螺丝刀固定插座底座。
- 连接电线到插座的对应插槽,并确保插线端与插座相匹配。
- 使用螺丝刀拧紧插座,并确保插座稳固。
3. 完成步骤:- 打开电源,并使用测试仪器检查插座的正常工作。
- 确保插座周围没有其他杂物或危险物品。
- 清理工作场地,并将旧插座适当处理或回收。
4. 注意事项- 在进行水龙头和电源插座安装前,确保已关闭相关的水源和电源,以避免意外伤害。
- 仔细阅读并遵循安装说明书,以确保正确安装并避免损坏产品。
- 如需专业帮助或安装困难,请咨询合格的专业人士。
以上是水龙头和电源插座安装的简要指南,希望对您有所帮助。
如需进一步信息或有其他问题,请随时与我们联系。
谢谢!---。
深入解析水龙头开关的安装施工

深入解析水龙头开关的安装施工
一、水龙头开关安装前的准备工作
在进行水龙头开关的安装施工之前,需要准备以下材料和工具:
1. 水龙头开关;
2. 专用扳手;
3. 测量尺;
4. 密封胶带或生料带;
5. 管道清洁剂。
二、水龙头开关的安装步骤
1. 测量和标记
首先,使用测量尺测量并确定水龙头开关的安装位置。
这个位
置需要根据个人使用惯、洗手盆或水槽的大小以及水管的位置来确定。
2. 清洁管道
使用管道清洁剂清洁水管的连接部位,以保证连接部位的密封性。
3. 安装水龙头开关
使用专用扳手将水龙头开关固定在预定位置,注意不要过于用
力以免损坏水龙头开关。
确定水龙头开关已经牢固固定后,使用密
封胶带或生料带将连接部位包裹,防止漏水。
4. 检查安装效果
打开水源,检查水龙头开关是否工作正常,是否存在漏水现象。
如果存在问题,需要重新安装或调整。
三、水龙头开关安装施工的注意事项
1. 安装水龙头开关时,要确保水源已经关闭,否则可能会导致
安装过程中的水溅出或漏水。
2. 水龙头开关的安装位置应尽量避免在阳光直射或温度过高的地方,以防止水龙头开关因长时间暴露在高温下而损坏。
3. 在安装水龙头开关时,应尽量选择质量好的产品,并按照产品说明书进行安装,以保证产品的使用寿命和使用效果。
以上就是关于水龙头开关的安装施工的详细步骤和注意事项。
希望这些信息能对您有所帮助,如果在安装过程中遇到问题,建议寻求专业人员的帮助。
电热水龙头的安装步骤

电热水龙头的安装步骤在寒冷的冬季家里的热水一定要足够,不过如果是想要开开水龙头都流出来热水的话,这恐怕就要使用电热水龙头了。
电热水龙头有着热水器和太阳能所不能比的优势,虽然它们也可以产生热水,但是水管中的水却依然还是凉的,因此需要您把水管中的水流完之后才可以有热水使用。
电热水龙头可以让您打开水龙头就有热水使用。
所谓电热水龙头就是我们通常说的快加热水龙头,它就是通过瞬间冲电加热,使得水龙头流出来的水是热的。
而作为一种比较新型的产品,电热水龙头要如何安装呢?步骤一:先拆除原有的普通水龙头首先得关闭水管阀门,拆掉原有的非电热水龙后,将其用清水把管道接口清洗干净,避免锈过多,形成梗塞。
步骤二:组装部件1.先将电热水龙头弯管与电热水龙头本体连接起来,机器固定就行。
2.如要用洗脸盆的话,那么将其把本体进水口的螺帽拧下,把电热水龙头固定在洗脸盆上;如不用洗脸盆那么可省略这一步。
3.然后再将电热水龙头与自来水管相连接起来。
步骤三:检查1.在安装好电热水龙头后,其先打开水阀开关,检查衔接件处能否漏水。
2.然后打开电热水龙头开关,给机器放水,冷热水开关来回打开调试几次。
3.在彻底排出空机器内气泡后,再*上电源。
4.将其热水调到所需的位置,因热水的温度是经过热水大小控制开关来调理的。
红灯亮了就将表示开端加热。
热水龙头安装注意事项:1、电热水龙头装置完了后,应先通水再通电,将手柄上、下旋转,看到出水口有水流出后,再接通电源即可运用。
(仅限于第一次运用)。
2、电热水龙头具有冷、热两种水流,在热水断水断电时,不需求频繁拔*出电源。
3、电热水龙头采用压力安装,开关打到热水方向即自动启动加热,打到冷水不耗费任何电。
运用简单,省水省电。
上述就是电热水龙头的具体安装步骤,安装成功之后您就可以非常方便的使用到热水了,一般开开水龙头3-5秒的时间就可以让您用到暖暖的热水,再也不用受到寒冷的侵袭,而且它除此之后还非常的小巧方便,是您家里不可缺的好帮手。
如何正确安装一个水龙头?

如何正确安装一个水龙头?一、准备工作1.测量水龙头尺寸:在安装水龙头之前,首先要测量水龙头的尺寸。
这样可以确保所购买的水龙头与已有的水管相匹配。
一般来说,水龙头的尺寸有标准尺寸,测量方法是将尺子放在水龙头的进水口上,然后测量出水龙头的直径。
测量好尺寸后,方便购买相应的水龙头。
2.准备工具:在安装水龙头之前,要确保自己准备了必要的工具。
常见的安装工具有扳手、螺丝刀、螺丝批等。
这些工具能够帮助我们拆卸旧的水龙头,安装新的水龙头。
3.关闭水源:在安装水龙头之前,记得关闭水源。
这样可以避免工作时水源泄漏,保证工作环境的安全性。
关闭水源的方法可以通过关闭水管旁边的阀门来实现。
二、拆卸旧水龙头1.关闭水管阀门:在拆卸旧水龙头之前,应该先关闭水管的阀门。
这样可以避免在拆卸过程中出现水源泄漏的情况。
2.拆卸旧水龙头:使用扳手等工具,解开旧水龙头与管道之间的连接。
需要注意的是,有些水龙头是用螺纹固定的,需要用扳手逆时针旋转才能拆卸。
3.清洁水龙头安装处:拆卸完成后,我们需要清洁水龙头安装处的管道。
可以使用抹布将管道擦拭干净,保持清洁卫生。
三、安装新水龙头1.安装新水龙头:将新水龙头放入安装处,然后用扳手逆时针旋转将其固定。
固定时要掌握力度,不能使水龙头过紧或者松动。
2.连接水管:拧紧水龙头后,需要将水管与水龙头连接起来。
使用螺纹连接件将水管固定到水龙头上,要确保连接处没有漏水的情况。
3.打开水源检测:在安装完成后,记得打开水源检测水龙头是否正常工作。
可以通过打开水管阀门,检测水龙头是否有漏水现象。
四、注意事项1.注意安装方向:在安装水龙头时,要注意水龙头的方向。
通常来说,冷水龙头安装在左边,热水龙头安装在右边。
确保水龙头的安装方向正确,使用时方便。
2.严禁漏电:安装过程中,要注意防止水龙头漏电的情况。
可以在水龙头和管道之间安装绝缘垫,避免因为电流引起的危险。
3.定期检查维护:安装好水龙头后,我们要定期检查维护。
如果发现水龙头有漏水、堵塞等情况,要及时修理或更换。
双孔冷热水龙头怎么安装

双孔冷热水龙头怎么安装在如今的家居生活中,浴室中都会安有面盆双孔冷热水龙头这一卫浴用品。
面盆双孔冷热水龙头在生活中使用的频率与日俱增,基本只要洗漱都会用到。
大家对于面盆双孔冷热水龙头的安装有多少了解呢?不妨通过本文进行一个学习吧。
双孔冷热水龙头怎么安装—安装技巧1、水管的介面水龙头接水管的介面有“公”、“母”之分,说白了就是用螺丝还是螺帽一端连接。
2。
安装的介面:一般厨房水槽都用单孔安装,洗脸盆用双孔安装,有关孔径、孔间距都是标准的,不用自己麻烦。
从你图片上看,你这个柱盆应该是使用双孔安装的水龙头,两头母的软管连接,如果你单独购买水龙头的话,应该连水管都不需要另买。
看上去你这个洗脸盆应该没有联动的下水阀,买普通水龙头就够了。
另外,如果需要自己安装的话,建议买水龙头的时候要些“生料带”(也有叫“生胶带”的),安装的时候缠绕在螺口上,防止漏水。
安装双孔面盆龙头,需再买2根高压管。
双孔面盆龙头的安装步骤与单孔面盆龙头安装步骤相似,橡胶垫圈分别套上两个进水软管,将软管分别从两个孔出,连接面盆龙头的进水埠和出水角阀的介面。
2、双孔水龙头安装1、单把双孔水龙头:是指冷热水分别由两个管孔引入,而出水则由一个水嘴流出。
其水温由一个把手左右调节来实现的。
一般左边为热水,右边则为冷水。
这种阀门,实际就是人们常说、常用的冷热混水阀。
2、双把双孔水龙头:是指冷热水分别由两个管孔引入,而出水则由两个阀门控制、一个水嘴流出。
其水温由由两个阀门控分别左右调节来实现的,其水温较易控制。
实际应用较少。
面盆双孔冷热水龙头怎么安装—安装注意事项1、淋浴、浴缸龙头的安装如果购买淋浴、浴缸、挂墙龙头,那就需要选择合适的高度埋出水管。
冷热水管距离大概在20里面以上。
安装前先冲洗水管,避免因水质硬而损坏水龙头。
2、暗装淋浴、浴缸龙头购买暗装龙头后,一般要把龙头的阀芯预埋在墙内。
预埋前要考虑卫生间墙体的厚度。
墙体太薄的话,阀芯将无法预埋。
预埋时阀芯的塑胶保护罩不要轻易摘除,以免在预埋时水泥和其他杂务损坏阀芯。
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
电热水龙头安装步骤
2018-01-18
在寒冷的冬季家里的热水一定要足够,不过如果是想要开开水龙头都流出来热水的话,这恐怕就要使用电热水龙头了。
电热水龙头有着热水器和太阳能所不能比的优势,虽然它们也可以产生热水,但是水管中的水却依然还是凉的,因此需要您把水管中的水流完之后才可以有热水使用。
电热水龙头可以让您打开水龙头就有热水使用。
所谓电热水龙头就是我们通常说的快加热水龙头,它就是通过瞬间冲电加热,使得水龙头流出来的水是热的。
而作为一种比较新型的产品,电热水龙头要如何安装呢?
步骤一:先拆除原有的普通水龙头
首先得关闭水管阀门,拆掉原有的非电热水龙后,将其用清水把管道接口清洗干净,避免锈过多,形成梗塞。
步骤二:组装部件
1.先将电热水龙头弯管与电热水龙头本体连接起来,机器固定就行。
2.如要用洗脸盆的话,那么将其把本体进水口的螺帽拧下,把电热水龙头固定在洗脸盆上;如不用洗脸盆那么可省略这一步。
3.然后再将电热水龙头与自来水管相连接起来。
步骤三:检查
1.在安装好电热水龙头后,其先打开水阀开关,检查衔接件处能否漏水。
2.然后打开电热水龙头开关,给机器放水,冷热水开关来回打开调试几次。
3.在彻底排出空机器内气泡后,再插上电源。
4.将其热水调到所需的位置,因热水的温度是经过热水大小控制开关来调理的。
红灯亮了就将表示开端加热。
热水龙头安装注意事项:
1、电热水龙头装置完了后,应先通水再通电,将手柄上、下旋转,看到出水口有水流出后,再接通电源即可运用。
(仅限于第一次运用)。
2、电热水龙头具有冷、热两种水流,在热水断水断电时,不需求频繁拔插出电源。
3、电热水龙头采用压力安装,开关打到热水方向即自动启动加热,打到冷水不耗费任何电。
运用简单,省水省电。
上述就是电热水龙头的具体安装步骤,安装成功之后您就可以非常方便的使用到热水了,一般开开水龙头3-5秒的时间就可以让您用到暖暖的热水,再也不用受到寒冷的侵袭,而且它除此之后还非常的小巧方便,是您家里不可缺的好帮手。