中英文对照工程施工方案

  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

第八章各分部分项工程的施工方案Chapter 8 Construction Scheme of Subprojects

8.1 土建施工方案

8.1 Civil Engineering Construction Scheme

8.1.1 工程测量

8.1.1 Engineering Surveying

1)测量概述

1) Measurement Overview

为满足工程施工特点,该工程的测量控制网按照“从整体到局部,高精度控制低精度”的原则,由高到低设置三级控制网,各级控制网相互衔接,统一为整体系统。

In order to meet the characteristics of construction, the survey control networks of the project have three levels from high to low in accordance with the principle “From the whole to the part; High precision controls low precision”. Control networks at all levels should be connected, thus forming the overall system.

1、测量注意事项

1. Measurement Considerations

建筑物占地面积超大,这对轴线控制网的布设和投测带来难度,需要充分利用高精度电子全站仪进行轴线控制网的布设及细部测量放线,钢尺作为辅助;轴线投测时,仪器要架设在建筑物两端,以减少投测误差。

As the buildings occupy a large area, which brings difficulty to the layout design and measurement of the axis control network, the electronic total station with high precision should be used to lay the network and do detailed survey with steel rulers as assistive devices. When transfer of building lines is conducted, instruments should be erected on both ends of the buildings to minimize measuring errors.

2、测量前准备工作

2. Preparations before measurement

(1)、测量仪器检定:本工程使用的所用测量仪器及工具(包括专业分包的测量仪器)均应经国家计

量单位检校合格并在有效时间之内。

(1) Measuring instrument calibration: All measuring instruments and tools (including those used in professional subcontracts) should be examined and calibrated by the national units of measurement and meet the standards within the effective time.

(2)、校核图纸:总图校核,包括建筑物定位依据及条件;校核建筑图、结构图、机电图纸是否对应。

(2) Checking drawings: Check the general drawing, including the position basis and conditions of buildings; Check whether architectural drawings, structural drawings and electrical mechanical drawings correspond to one another.

(3)、根据建筑总平面要求,对规划勘测部门提供的坐标点和水准点进行复核,确保工程测量的准确性。

(3) Check the coordinate points and benchmarks given by Planning Survey department in accordance with the requirements of the building general layout and ensure the accuracy of engineering surveying.

(4)、施测用辅助材料如标高控制桩油漆、麻线等提前准备到位。

(4) Auxiliary measuring materials should be prepared in advance in place, such as elevation control pile paint, twine, etc.

(5)、测量仪器及人员准备:成立测量组组长,负责整个工程的测量与验线工作。人员、仪器配置如下:

(5) Preparation of measuring instruments and personnel: Appoint a team leader in charge of the measurement and checking of building lines of the whole project. Personnel and instrument configurations are as follows:

测量组:

Measurement group:

技术组3人,负责编制测量方案/作业指导书,内业管理,收集检查施工测量数据,控制网及高程网的测设与校核。

Technology group: 3 persons, responsible for preparing the measurement program / work instructions, doing interior management, collecting and checking the construction survey data,

相关文档
最新文档