大工19秋《水利工程施工》在线作业1(参考答案)大工19秋《水利工程施工》在线作业1-0001试卷总分:100得分:100一、单选题(共5道试题,共30分)1.立堵法截流的截流工作面一般比较(),合龙时间较()。
A.狭窄,长B.狭窄,短C.宽,长D.宽,短答案:A2.当炸药的含氧量大于可燃物完全氧化所需的氧量,则称之为()。
A.零氧平衡B.负氧平衡C.正氧平衡答案:C3.在水工建筑物岩石基础的开挖中,基础保护层以上的岩体开挖主要采用()爆破方法。
A.以秒爆破技术为主的深孔台阶B.以秒爆破技术为主的浅孔C.以毫秒爆破技术为主的深孔台阶D.以毫秒爆破技术为主的浅孔答案:C4.纵向围堰的堰顶高程,根据()确定。
A.调洪计算B.设计洪水过程线C.束窄河段水面曲线D.实验总结答案:C5.对于混凝土导流建筑物,导流建筑物级别为Ⅴ级时,洪水重现期为()年。
A.5-3B.50-30C.30-20D.15-5答案:A2、多选题(共5道试题,共30分)6.截流后的进度应尽量提前,为()留够时间。
A.排水清基B.导流设计C.基础处理D.围堰加高答案:ACD7.非电起爆网路首要包括()。
A.混合起爆网路B.提早起爆网路C.导爆索起爆网路D.导爆管起爆网路答案:ACD8.非电起爆的方法主要包括()。
A.火雷管起爆B.火花起爆C.导爆索起爆D.导爆管起爆谜底:BCD9.底孔导流时导流底孔的布置主要是()的布置。
A.数目B.底坎高程C.底坎宽度D.尺寸谜底:ABD10.光面爆破的装药结构首要可分为哪些段()。
A.隙缝调药段B.孔底加强段C.堵塞段D.均匀装药段谜底:BCD三、判断题(共10道试题,共40分)11.深孔爆破一般XXX 超过5m,适用于大规模、高强度开挖。
谜底:精确12.选择纵向围堰位置考虑应尽量与导墙、隔墙等类似的临时性建筑物相结合。
谜底:错误13.分段围堰法导流是指用围堰把水工建筑物分段,分期围护起来进行施工的方法。
大工16春《水利水能规划》在线作业3 参考答案

大工16春《水利水能规划》在线作业3一、判断题(共 10 道试题,共 40 分。
)V1. 若水库不需要承担下游防洪任务,则洪水期下泄流量可不受限制。
A. 错误B. 正确满分:4 分2. 无论建设项目开工时间是否相同,但应取同一基准年进行资金时间价值折算。
A. 错误B. 正确满分:4 分3. 水库调洪计算的基础原理为明渠非恒定流基本方程。
A. 错误B. 正确满分:4 分4. 当正常高水位一定时,兴利和防洪结合库容的大小取决于死水位。
A. 错误B. 正确满分:4 分5. 水库调洪的列表试算法原理:依据时段内的水量平衡原理逐时段计算下泄洪水过程和相应的水位、库容变化。
A. 错误B. 正确满分:4 分6. 水库校核洪水位的高低与下游防洪区的安全流量有关。
A. 错误B. 正确满分:4 分7. 水利工程中经济计算的基准年只能选择在施工期的第一年。
A. 错误B. 正确满分:4 分8. 火电站的机组开停灵便、迅速,从停机到满负荷只需1-2分钟。
A. 错误B. 正确满分:4 分9. 大中型水、火电站等都参加电力系统运行。
A. 错误B. 正确满分:4 分10. 最大下泄流量是为确保大坝安全溢洪道敞开泄流的最大泄量。
A. 错误B. 正确满分:4 分二、单选题(共 5 道试题,共 30 分。
)V1. 某年调节水库运行中,某时刻水库水位落在保证供水区,这说明该时刻以后到供水期未水库正常供水()。
A. 能保证B. 不能保证C. 不一定能保证D. 不确定满分:6 分2. 某水库所属流域洪水发生的时间缺乏规律性,则水库的防洪限制水位宜定为()。
A. 高于正常水位B. 低于正常水位C. 等于正常水位D. 以上都可以满分:6 分3. 尤其适合于有复杂综合利用任务的水库水能计算方法是()。
A. 电算法B. 图解法C. 列表法D. 以上都可以满分:6 分4. 从基准年起折算资金至第n年年末的数值,称为()。
A. 现值B. 终值C. 年值D. 期望值满分:6 分5. 一般是,随着洪水波沿河向下游推进,洪峰流量逐渐减小,洪水历时逐渐()。
大工13春《水利水能规划》在线作业3

大工13春《水利水能规划》在线作业31、判断题(共10 道试题,共40 分。
)V 1. 社会折现率是衡量经济内部收益率的基准值,是项目经济可行性和方案比选的主要判据。
(B)A. 错误B. 正确2. 入库洪水的大小要根据防洪标准或水工建筑物的设计标准来选定。
(B)A. 错误B. 正确3. 若水库不需要承担下游防洪任务,则洪水期下泄流量可不受限制。
(B)A. 错误B. 正确4. 计算水电站出力和发电量是水能计算的主要内容。
(B)A. 错误B. 正确5. 无调节水电站无论在何种情况下都只能承担基荷。
(A)A. 错误B. 正确6. 无论建设项目开工时间是否相同,但应取同一基准年进行资金时间价值折算。
(B)B. 正确7. 影子价格是真实价值的一种度量,在资源或产品数量有限的情况下,影子价格是这种资源或产品增加或减少一个单位引起边际效益改变的量值。
(B)A. 错误B. 正确8. 求解明渠非恒定流基本方程,很容易就能得出精确的解析解。
(A)A. 错误B. 正确9. 国民经济评价与财务评价两大部分,是建设项目优选与科学决策的重要依据。
(B)A. 错误B. 正确10. 当水库有下游防洪任务时,它的主要作用是消减下泄洪水流量,使其不超过下游河床的安全泄量。
(B)A. 错误B. 正确二、单选题(共5 道试题,共30 分。
)1. 已知本金现值P=1万元,年利率i=12%,五年后的本利和为(A)元。
B. 18170C. 16000D. 560002. 已知某水电站25年后更换机组设备需重新投资,F=100万元,设i=10%,问从现在起每年年末须提存的基本设备更新基金A 为(A)元。
A. 10170B. 18170C. 40000D. 360003. 用电特点为季节性变化,年内不均匀,但在一定时期内相对均匀的用户为(C)。
A. 工业用电B. 市政用电C. 农业用电D. 交通用电4. 一般是,随着洪水波沿河向下游推进,洪峰流量逐渐减小,洪水历时逐渐(A)。
大工20春《水利水能规划》在线作业36A3BE

大工20春《水利水能规划》在线作业3
推求某一流域的设计洪水,就是推求该流域的设计洪峰和各历时设计洪量。
A:错误
B:正确
答案:A
正态频率曲线在普通格纸上是一条直线。
A:错误
B:正确
答案:A
水电站保证出力就是水电站在长期工作中,符合水电站设计保证率要求的枯水期(供水期)内的平均出力。
A:错误
B:正确
答案:B
方案比较需满足需要的可比性和费用的可比性两个原则。
A:错误
B:正确
答案:A
入库洪水无实测资料,只能用间接方法推求。
A:错误
B:正确
答案:B
对于一个灌溉水库来讲,当兴利库容一定时,灌区灌溉面积越大,其灌溉设
计保证率越小。
A:错误
B:正确
答案:B
设计代表年的年径流整编应由丰水期水库开始蓄水统计到次年再度蓄水为止。
A:错误
B:正确
答案:B
随机试验的可能结果称为概率。
A:错误
B:正确
答案:A
水电站保证出力是指水电站在长期工作中符合水电站设计保证率要求的枯水
期内的平均出力。
A:错误
B:正确
答案:B
同倍比放大法不能同时满足设计洪峰、设计峰量具有相同频率。
A:错误
B:正确
答案:B
灌溉水库属变动供水调节,主要原因是()各年不同。
大工15春《水利水能规划》在线作业3满分答案

大工15春《水利水能规划》在线作业3判断题单选题多选题一、判断题(共 10 道试题,共 40 分。
)1. 水库进行调洪时水库的最高洪水位与入库洪水的洪峰同时发生。
A. 错误B. 正确-----------------选择:A2. 暴雨强度公式实质上是暴雨时深关系的一种表示方法。
A. 错误B. 正确-----------------选择:B3. 水库在汛期允许兴利蓄水的上限上位,称为防洪限制水位。
A. 错误B. 正确-----------------选择:B4. 灌溉水库属变动供水量调节,主要原因是水库入库径流各年不同。
A. 错误B. 正确-----------------选择:A5. 电力系统中的备用容量,可以设置在水电站,也可以设置在火电站。
A. 错误B. 正确-----------------选择:B6. 兴利调节计算是根据水量平衡原理进行的。
A. 错误B. 正确-----------------选择:B7. 最大下泄流量是为确保大坝安全溢洪道敞开泄流的最大泄量。
A. 错误B. 正确-----------------选择:B8. 当正常高水位一定时,兴利和防洪结合库容的大小取决于死水位。
A. 错误B. 正确-----------------选择:A9. 大中型水、火电站等都参加电力系统运行。
A. 错误B. 正确-----------------选择:B10. 洪峰径流系数与次降雨径流系数的含义相同。
A. 错误。
大工秋《水利水能规划》大作业及要求答案

大工16秋《水利水能规划》大作业及要求答案Big work 16 autumn "water conservancy and hydropower planning" major operations and requirements answerJob contentTitle: time series method for calculating favorable reservoir capacityLearning center:Major:Year: Spring / autumnStudent number:Student:Tutor:1 basic knowledge1.1 regulation of reservoir profitExcept for non regulated water conservancy and hydropower projects that can only supply natural runoff water, all of them can adjust the storage capacity to a certain extent.The relation between regulation performance and reservoir capacity: the longer the cycle, the better the regulationperformance and the larger the storage capacity.1, according to the adjustment cycle points:(1) daily regulation: the regulation period of daily regulation is one day and four days. That is to say, the daily water demand of reservoir will be adjusted by the daily water demand of the water sector. Daily variation of power load.(2) weekly adjustment: the regulation cycle of the week adjustment is one week, and the inflow runoff which is not changed within a week is adjusted according to the water demand process of the water sector. The weekly variation of power consumption in a period of time.(3) annual adjustment: the annual runoff of inland rivers has changed greatly, and the water supply during the rainy season and the dry season is very different. The task of regulating the annual runoff is to store and increase the surplus water during the flood season in accordance with the annual domestic water demand process in the water sector, so as to increase the water supply during the water shortage period, and the regulation cycle is less than one year. According to the variation of the abundance and drought in the runoff, the regulation of the abundance and deficiency of the seedlings was carried out.(4) adjustment over many years: the task of regulating runoff for many years is to utilize the storage capacity of the reservoir to save the surplus water in the year of the flood so as to increase the water supply in the dry season. For manyyears, the drought and flood change year by year.2, according to reservoir task points(1) single task streamflow regulation;(2) comprehensive utilization of runoff regulation;3, according to the reservoir water supply mode(1) fixed water supply;(2) variable water supply;4. Other classifications(1) reverse regulation reservoir: the downstream reservoir is adjusted again according to the demand of water.(2) compensation adjustment of a single reservoir: mutual compensation between reservoir and downstream water supply.(3) adjustment of reservoir group compensation: hydrology, storage capacity and power compensation.1.2, the concept of regulatory cycleConstruction of the so-called regulatory cycle, refers to the reservoir capacity of the reservoir, from storage to full storage and then emptying of the complete storage process. The longer regulation period, the better regulation performance ofreservoir and the corresponding storage capacity.1.3 hour calendar method1, according to the water use process to determine reservoir benefit storage capacityKnown: natural runoff, dead storage capacity, according to the requirements of water to facilitate the storage capacity and facilitate the settlement of water storage.(1) annual adjustment calculation process without water loss:Determine the regulatory cycle: usually in October of that year, second years, June;The difference between water demand and natural runoff was calculated monthly from 10 to June;The accumulated difference is the favorable reservoir capacity and the advantageous reservoir position;Returning to the beginning of the flood season, the reservoir will be stored, discharged and abandoned.Determine the water level of the downstream section according to the discharge.(2) annual adjustment calculation process of water loss (considering water evaporation loss):Use of water loss calculation results;Determine the water area of each period;Calculate the evaporation loss at each period;The difference between the amount of water supply + evaporation loss and natural runoff is calculated monthly;The difference between the accumulated traffic;Determine the reservoir capacity and profit and fill water level, and determine the reservoir operation process.Summary and induction:The greater the difference between runoff and water use, the greater the storage capacity;Under the condition of one charge and storage, the sum of the water shortage and the loss amount accumulated during the whole water supply period, that is, the favorable storage capacity is independent of the amount of water allocated within each month;The total adjustment water quantity in water supply period is converted into flow, and then is adjusted by the average runoff for many years, and the adjustment coefficient is obtained to reflect the regulating performance.2, according to the favorable reservoir capacity to determinethe flow adjustmentAccording to the two calculation methods: the annual adjustment process of water loss and the annual adjustment process of water loss loss can be seen:(1) if the water loss is not considered, adjust the flow rate = (W for +V Xing), /T supply(2) if water loss is consideredAdjust flow = = W (W, +V, /T)(3) the storage capacity factor B=V is /W and the average annual rate is 830%;Over more than 30% years to adjust.3, according to the reservoir capacity and reservoir operation plan, the reservoir operation process is deduced:Constant flow operation: irrigation, water supply, shipping, etc., actual demand.Constant power operation: in order to meet the requirement of power consumption, the water quantity of hydropower station should be adjusted to the change of load.Because the output is related to the flow rate and the head, and the flow is related to the head, the calculation of the output is calculated by trial calculation.2 calculate content2.1 calculation dataAccording to the basic data given, the calculation process is described in detail.The average annual discharge of the dam site of a proposed reservoir is annual average water inflow. According to the design guarantee rate = 90%, the selected design low flow year hydrograph is shown in table 1. The initial storage capacity. Try to calculate the regulated flow rate (excluding water loss) and the adjustment factor.Table 1 monthly flow data sheet for designing low flow yearAverage of 789101112123456 years in MarchMonthly average flow ()294824167644875413.52.2 determine reservoir regulation performanceAccording to the basic data, the reservoir regulation performance is determined, and the calculation process and final results are described in detail.2.3 determine the regulated flowAccording to the basic data for flow adjustment calculation, detailed description of the calculation process and final results.2.4 adjustment factorAccording to the basic data given adjustment coefficient calculation, detailed description of the calculation process and final results."Water conservancy and hydropower planning offline operation" course learning requirementsI. the form of curriculum assessmentThe assessment of this course is offline, with online homework. The final course results include 80% offline homework scores and +20% online assignments. Offline jobs and requirements are downloaded from the offline homework module of the course.Two, offline job requirementsStudents need to download the "big 16" autumn "planning of water conservancy and hydropower operations and requirements in platform offline operation, watch the course video courseware, courseware based on knowledge and theory, fill in the" big 16 "autumn" planning of water conservancy and hydropower operations and requirements, and submit to the course platform, off-line homework as one of the main basis for the submission of course assessment.Three, offline job submission form and deadlineStudents need to submit an offline job in the form of an attachment (the size of the attachment is limited to 10M), select the completed job, and click "turn in". As shown in the following figure.Deadline: March 7, 2017. Prior to this, students can submit offline work at any time. If you need to modify, you can upload new files directly. The platform will automatically overwrite the original file.Four, offline operation markingThe teacher will be in operation after the closure of centralized marking offline operation, the offline operation is not carried out before the deadline to submit any form of marking.Matters needing attention:Complete the offline operation independently, allowed plagiarism or ask someone to do, any similarity scores to 0!School of network education, Dalian University of TechnologyNovember 2016。
大连理工大学21春《水利水能规划》在线作业2-辅导答案
大工21春《水利水能规划》在线作业2注:本套试卷为学习辅导资料,仅供学生复习使用!!!一、判断题 (共 10 道试题,共 40 分)第1题,随机变量的取值与其概率的对应关系,称为随机变量的概率分布。
提示:按照课程学习要求,完成本学期在线作业【正确答案】:正确第2题,对于一个统计系列,当Cs=0时称为正态分布;当Cs﹥0时称为负偏态分布;当Cs﹤0时称为正偏态分布。
提示:按照课程学习要求,完成本学期在线作业【正确答案】:错误第3题,变差系数CV是衡量系列相对离散度的一个参数。
提示:按照课程学习要求,完成本学期在线作业【正确答案】:正确第4题,利用水库蓄洪或滞洪是防洪工程措施之一。
提示:按照课程学习要求,完成本学期在线作业【正确答案】:正确第5题,在水库规划设计阶段和管理运用阶段,调洪计算任务不同,但调洪计算的方法、原理则相同。
提示:按照课程学习要求,完成本学期在线作业【正确答案】:正确第6题,确定水库的防洪标准只要考虑水库的经济效益即可。
提示:按照课程学习要求,完成本学期在线作业【正确答案】:错误第7题,历史最大洪水加成法比频率计算法的应用范围广泛,适用性更好。
提示:按照课程学习要求,完成本学期在线作业【正确答案】:错误第8题,水文频率计算中配线时,增大Cv可以使频率曲线变陡。
提示:按照课程学习要求,完成本学期在线作业【正确答案】:正确第9题,水文分析计算中, 相关分析的先决条件是两变量在物理成因上不必有联系。
提示:按照课程学习要求,完成本学期在线作业【正确答案】:错误第10题,坝式(抬水式)水能资源开发方式的水能资源利用率低,基建工程大,会形成淹没。
提示:按照课程学习要求,完成本学期在线作业【正确答案】:错误二、单选题 (共 5 道试题,共 30 分)第11题,必然事件的概率等于()。
【A.】1【B.】0.5【C.】0【D.】0到1之间提示:按照课程学习要求,完成本学期在线作业【正确答案】:A第12题,资金折算至基准年的数值,称为()。
大工15春《水利水能规划》在线作业3满分答案
大工15春《水利水能规划》在线作业3一、判断题(共 10 道试题,共 40 分。
)1. 水库进行调洪时水库的最高洪水位与入库洪水的洪峰同时发生。
A. 错误B. 正确-----------------选择:A2. 暴雨强度公式实质上是暴雨时深关系的一种表示方法。
A. 错误B. 正确-----------------选择:B3. 水库在汛期允许兴利蓄水的上限上位,称为防洪限制水位。
A. 错误B. 正确-----------------选择:B4. 灌溉水库属变动供水量调节,主要原因是水库入库径流各年不同。
A. 错误B. 正确-----------------选择:A5. 电力系统中的备用容量,可以设置在水电站,也可以设置在火电站。
A. 错误B. 正确-----------------选择:B6. 兴利调节计算是根据水量平衡原理进行的。
A. 错误B. 正确-----------------选择:B7. 最大下泄流量是为确保大坝安全溢洪道敞开泄流的最大泄量。
A. 错误B. 正确-----------------选择:B8. 当正常高水位一定时,兴利和防洪结合库容的大小取决于死水位。
A. 错误B. 正确-----------------选择:A9. 大中型水、火电站等都参加电力系统运行。
A. 错误B. 正确-----------------选择:B10. 洪峰径流系数与次降雨径流系数的含义相同。
A. 错误B. 正确-----------------选择:A大工15春《水利水能规划》在线作业3判断题单选题多选题二、单选题(共 5 道试题,共 30 分。
)1. 对同一地区而言,设计标准越高时()。
A. 设计雨力越小B. 不变C. 设计雨力越大D. 不能确定-----------------选择:C2. 当水库下游有防洪要求,遇到下游防护对象的设计标准洪水时,经水库调洪后,在坝前达到的最高水位,称()。
A. 防洪高水位B. 设计洪水位C. 正常高水位D. 防洪限制水位-----------------选择:A3. 某水库所属流域洪水发生的时间缺乏规律性,则水库的防洪限制水位宜定为()。
大工21秋《水利水能规划》在线作业1-【答案】
大工21秋《水利水能规划》在线作业1-辅导资料
试卷总分:100 得分:100
一、判断题 (共 10 道试题,共 40 分)
1.基准年一般可选于施工期的任何时刻,都很便利。
<-A.->正确
<-B.->错误
【本题正确参考选择】:错误
2.水电站保证出力就是水电站在长期工作中,符合水电站设计保证率要求的枯水期(供水期)内的平均出力。
<-A.->正确
<-B.->错误
【本题正确参考选择】:正确
3.水库在汛期允许兴利蓄水的上限上位,称为防洪限制水位。
<-A.->正确
<-B.->错误
【本题正确参考选择】:正确
4.枯水流量亦称最小流量。
<-A.->正确
<-B.->错误
【本题正确参考选择】:正确
5.历史最大洪水加成法比频率计算法的应用范围广泛,适用性更好。
<-A.->正确
<-B.->错误
【本题正确参考选择】:错误
6.在洪峰与各时段洪量的相关分析中,洪量的统计历时越短,则峰量相关程度越高。
<-A.->正确
<-B.->错误
【本题正确参考选择】:正确
7.每一坝前水位所对应的实际库容与静库容相等。
<-A.->正确
<-B.->错误
【本题正确参考选择】:错误
8.随机试验的可能结果称为概率。
<-A.->正确
<-B.->错误
【本题正确参考选择】:错误。
大工14秋《水利水能规划》在线作业3答案
水利水能规划大工14秋《水利水能规划》在线作业3一,判断题1. 利用水库蓄洪或滞洪是防洪工程措施之一。
A. 错误B. 正确?正确答案:B2. 资金具有时间价值。
A. 错误B. 正确?正确答案:B3. 确定水库的防洪标准只要考虑水库的经济效益即可。
A. 错误B. 正确?正确答案:A4. 无调节水电站应该尽可能承担电力系统的峰荷。
A. 错误B. 正确?正确答案:A5. 水库校核洪水位的高低与下游防洪区的安全流量有关。
A. 错误B. 正确?正确答案:B6. 由暴雨资料推求设计洪水的基本假定是:暴雨与洪水同频率。
A. 错误B. 正确?正确答案:B7. 洪水调节的瞬态法比较简便,宜于手算。
A. 错误B. 正确?正确答案:B8. 当水利方案的效益基本相同时,应选择其中费用现值较大的方案。
A. 错误B. 正确?正确答案:A9. 对已建成的水利工程也需要进行经济评价。
A. 错误B. 正确?正确答案:B10. 一年内的电力系统负荷变化过程图称为年负荷图。
A. 错误B. 正确?正确答案:B二,单选题1. 某水利工程25年后须重新投资,更换水电机组费用为100万元,i=10%,则从现在起每年年末须提存的设备更新基金为()元。
A. 40000B. 16105C. 12500D. 10170?正确答案:D2. 当正常高水位一定时,兴利和防洪结合库容的大小取决于()。
A. 死水位B. 防洪限制水位C. 校核洪水位D. 设计洪水位?正确答案:B3. 尤其适合于有复杂综合利用任务的水库水能计算方法是()。
A. 电算法B. 图解法C. 列表法D. 以上都可以?正确答案:C4. 分期确定防洪限制水位时,副汛期的防洪限制水位比主汛期的汛限水位()。
A. 高B. 低C. 相同D. 不能确定?正确答案:A5. 水利发电机组的出线端送出的功率,称为水电站的()。
A. 发电量B. 出力C. 最小负荷D. 最大负荷?正确答案:B三,多选题1. 当经济内部收益率()社会折现率时,该项目在经济上是合理的。
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
【奥鹏】大工19秋《水利水能规划》在线作业3-辅导资料
试卷总分:100 得分:100
一、判断题 (共 10 道试题,共 40 分)
第1题,设计年径流成果合理性分析中,可将设计年径流量直接与多年平均径流深等值线图
比较,借以说明此设计年径流量的合理性。
正确的答案是:错误
第2题,某水文变量频率曲线x~p,当CV、CS不变,增加均值的数值时,则x~p线上抬。
正确的答案是:正确
第3题,影子价格是真实价值的一种度量。
正确的答案是:正确
第4题,正态频率曲线在普通格纸上是一条直线。
正确的答案是:错误
第5题,水库面积特性是指水库水位与水面面积的关系曲线。
正确的答案是:正确
第6题,坝式(抬水式)水能资源开发方式的水能资源利用率低,基建工程大,会形成淹没。
正确的答案是:错误
第7题,湿润地区,降水量较多,年径流系数较高,从而使年径流量与年降水量有较密切的
关系。
正确的答案是:正确
第8题,影子价格是真实价值的一种度量,在资源或产品数量有限的情况下,影子价格是这
种资源或产品增加或减少一个单位引起边际效益改变的量值。
正确的答案是:正确
第9题,水库的蓄洪和滞洪都既能削减下泄洪峰流量,又能减少下游洪量。
正确的答案是:错误
第10题,洪水分期划分原则:尽可能根据不同成因的洪水,把全年划分为若干分期。 分期
不宜过短,一般以不短于1个月为宜。
正确的答案是:正确
二、单选题 (共 5 道试题,共 30 分)
1第1题,中国水资源总量排世界第()位
[A.]7
[B.]6
[C.]5
[D.]4