箱梁张拉油表读数计算

箱梁张拉油表读数计算
箱梁张拉油表读数计算

箱梁张拉油表读数计算

一、1#千斤顶1500KN 表1088

①X =1000140

1395?×4=781.2KN

Y =0.034X+0.5035=0.034×781.2+0.5035=27.064Mpa 20%时,X =781.2×0.2=156.24KN

Y =5.816Mpa

②X =1000140

1395?×3=585.9KN

Y =0.34X +0.5035=0.034×585.9+0.5305=20.424Mpa 20%时,X =85.9×0.2=117.18KN

Y =4.49Mpa

二、2#千斤顶1500KN 表1082

①X =781.2KN (4孔)

Y =0.0341X +1.0713=27.71Mpa

20%时,X =156.24KN

Y =6.4Mpa

②X =585.9KN (3孔)

Y =0.0341X +1.0713=21.05Mpa

20%时,X =117.18KN

Y =5.067Mpa

三、3#千斤顶1500KN 表1086

①X =781.2KN (4孔)

Y=0.0332X+0.2874=26.223Mpa 20%时,X=156.24KN

Y=5.475Mpa

②X=585.9KN(3孔)

Y=19.74Mpa

20%时,X=117.18KN

Y=4.18Mpa

四、4#千斤顶1500KN 表1057 ①X=781.2KN(4孔)

Y=0.0327X+0.702=26.247 Mpa 20%时,X=156.24KN

Y=5.81Mpa

②X=585.9KN(3孔)

Y=19.86Mpa

20%时,X=117.18KN

Y=4.53Mpa

20米箱梁负弯矩

20米箱梁负弯矩张拉计算书

20米箱梁负弯矩张拉计算书 一、工程概况 1、概况 (1) 低松驰高强度预应力钢绞线应符合GB/T5224-2003的规定。单根钢绞线直径φ,钢绞线面积A=139mm2,钢绞线标准抗拉强度f PK=1860Mpa,弹性模量E P=×105Mpa。钢绞线为天津冶金集团中兴盛达钢业有限公司生产,计算伸长值时取E P=×105 Mpa。 (2))张拉锚具采用开封市齐力预应力有限公司生产的BM15-5、BM15-4锚具。 (3)张拉机具采用开封市大方预应力有限公司生产的YDC270型千斤顶2台,所用设备均已进行标定,每台千斤顶对应压力表编号分别为: (4)压浆机具采用开封大方预应力有限责任公司生产的HB-3型灰浆泵(工作压力:Mpa)。3、主要技术参数 (1)箱梁湿接头采用C50砼浇筑,砼强度达到设计强度的85%后,且混凝土龄期不小于7天时,方可进行负弯矩张拉。 (2)钢绞线张拉锚下控制应力为即δK==1860×=1395 Mpa。 (3)预应力管道成型采用铁波纹管,孔道每米局部偏差对摩擦的影响系数K=,预应力筋与孔道壁之间的摩擦系数μ=,(参数为设计中给出)。 (4)张拉采用应力值和伸长值双控,以钢绞线伸长量进行校核。钢绞线实际伸长值与理论伸长值的偏差控制在±6%以内。 (5)钢绞线下料时,两端均考虑15cm的工作长度。 (6)压浆前将锚具用水泥膏密封,水泥凝固后方可进行压浆作业。 二、箱梁负弯矩张拉计算 钢绞线采用两端张拉,且应在横桥向对称均匀张拉。张拉顺序为台T3;T1、T2号钢束,张拉过程中控制10%、20%、100%的应力。由于钢绞线为低松驰高强度钢绞线,故不进行超张拉。 锚下控制应为δK==1860×=1302 Mpa

25m箱梁预应力张拉计算书

25m箱梁预应力张拉计算书 1、工程概况 杏树凹大桥左线桥中心桩号为ZK9+875,上部构造采用16×25m预制预应力混凝土小箱梁,先简支后连续.全桥分4联,桥长406m,,右线中心桩号为YK9+782、5,上部构造采用15×25m预制预应力混凝土小箱梁,先简支后连续。全桥分4联,桥长381m.本桥左线位于R-3600左偏圆曲线上,右线位于R—3400左偏圆曲线上。每跨横桥面由4片预制安装小箱梁构成。25m预制箱梁为单箱单室构造,箱梁高度为140厘米, 跨中断面腹板、底板厚度为18厘米,支点断面腹板、底板厚度为25厘米,顶板一般厚度为18厘米,箱梁底宽为100厘米,中梁翼缘顶宽为240厘米,边梁翼缘顶宽为284、5厘米。 本桥共有C50预应力混凝土箱梁124片. 各梁得预应力筋分布情况如下表所示: 预应力筋均为纵向,分布在底板、腹板及顶板,其中底板4束,腹板4束,顶板5束,对称于梁横断方向中线布置。预应力钢绞线采用抗拉强度标准值f pk=1860 MP、公称直径d=15、2mm得低松驰高强度,其力学性能符合《预应力混凝土用钢绞线》(GB/T5224-2003)得规定,公称截面积Ap=139mm2,弹性模量E

p=1、95*105MPa,松驰系数:0、3。试验检测得钢绞线弹性模量Ep=1、95*105MPa。 预应力管道采用金属波纹管,腹板及底板为圆孔,所配锚具为M15-3及M15-4,顶板为长圆孔,所配锚具为BM15—4及BM15-5. 2、后张法钢绞线理论伸长值计算公式及参数 后张法预应力钢绞线在张拉过程中,主要受到两方面得因素影响:一就是管道弯曲影响引起得摩擦力,二就是管道偏差影响引起得摩擦力。导致钢绞线张拉时,锚下控制应力沿着管壁向梁跨中逐渐减小,因而每一段得钢绞线得伸长值也就是不相同得。 2、1、力学指标及计算参数 预应力筋力学性能指标及相关计算参数如下: ※弹性模量:Ep=1、91*105 MPa ※标准强度:f =1860MPa pk =1395MPa ※张拉控制应力:σcon=0、75f pk ※钢绞线松驰系数:0、3 ※孔道偏差系数:κ=0、0015 ※孔道摩阻系数:μ=0、15 ※锚具变形及钢束回缩每端按6mm计 2、2、理论伸长值得计算 根据《公路桥梁施工技术规范》(JTJ 041-2000),关于预应筋伸长值得计算按如下公式进行: (公式1) 式中:ΔL——各分段预应力筋得理论伸长值(mm); Pp——预应力筋得平均张拉力(N); L—-预应力筋得长度(mm); Ap——预应力筋得截面面积(mm2); Ep——预应力筋得弹性模量(Mpa). 预应力筋得平均张拉力Pp按如下公式计算:

30米箱梁张拉计算

天大二标25米预制箱梁预应力计算书 一、工程概况 我单位承建天大高速公路第二合同段,起点里程K8+660,终点里程K13+000,线路全长4.340km。我标段主要工程为大桥3座,中桥1座,天桥2座,拱型小桥4座,拱涵2个,盖板涵2个,圆管涵1个,箱型通道2个。共有桩基132根,墩台柱88个,系梁54个,盖梁36个,预制箱梁175片,路基挖方216.014万方,路基填方89.651万方,小型构造物779.043m。 我标段共有25m预制箱梁148片,其中边跨边梁28片,边跨中梁28片,中跨边梁46片,中跨中梁46片。 二、编制依据 1、《公路桥涵施工技术规范》JTJ 041-2000 2、《两阶段施工图设计》山西省交通规划勘察设计院 2009年10月 3、委托试验检测报告 三、预应力张拉 依据图纸要求:混凝土达到设计强度的85%后张拉正弯矩区钢束,压注水泥浆并及时清理箱梁底板通气孔,在主梁正弯矩索张拉完毕,孔道压浆强度达40MPa以上才允许移梁或吊装,吊装过程中要保持主梁轴线垂直,防止倾斜,注意横向稳定。 张拉正弯矩钢束时,若主梁连接端的预留钢筋影响张拉操作,可先将其折弯,待张拉完毕后再将其恢复,张拉时采用两端张拉,且应在横桥向对称均匀张拉,顶板负弯矩钢束也可采用两端张拉,并采用逐根对称张拉。 箱梁腹板张拉时钢束均采用两端对称均匀张拉,在张拉过程中应保证两端同步张拉,左右腹板钢束对称均匀张拉,张拉顺序为: N1→N3→N2→N4。 四、实际伸长量的量取 最终伸长量的计算:由15%至30%的伸长量(L2-L1)加上由30%至100%的伸长量(L3-L1),即:△L=(L2-L1)+(L3-L1)。 注意:在量取伸长值的过程中,前后应以同一个位置为基点进行量取,并且使用钢板尺进行量测。

25米预应力混凝土箱梁张拉计算

四、拉设备及检验 1、拉设备的选用 设备能力计算: 3束:P=1860*0.75*140*3/1000=585.9KN 4束:P=1860*0.75*140*4/1000=781.2KN 5束:P=1860*0.75*140*5/1000=976.5KN 拉采用两端对称拉,选用两个YDC1500型穿心液压千斤顶,其拉力150T。 压力表的选用:压力表选用最大读数为60MPa,千斤顶同油压表的关系必须经省级计量单位标定。 2、在下述情况下,应对油表、千斤顶进行配套校验。 油泵、千斤顶、油表之中有一件是进场后修复过,第一次使用的;使用超过六个月或连续拉200次以上的;在运输和拉操作中出现异常时。 五、拉有关数量值计算 拉时应两端同时对称拉,拉控制以拉力为主,伸长值为校核控制,实际伸长值与理论伸长值控制在±6%以。 锚下控制应力计算:σcon=1860mpa*0.75=1395mpa。 预应力钢绞线拉理论伸长量计算公式: ΔL=(P p L)/(A p E p) (1) 式中:P p――预应力筋的平均拉力(N); 当预应力筋为直线时P p=P;

L――预应力筋的长度(mm); A p――预应力筋的截面面积(mm2); 本工程采用每根A p=140mm2; E p――预应力筋的弹性模量(N/mm2); 本工程采用E p=197444mpa。 预应力筋平均拉应力按下式计算: P p=P(1-e-(kx+μθ))/(kx+μθ) (2) 式中:P p――预应力筋平均拉力(N); P――预应力筋拉端的拉力(N); x――从拉端至计算截面的孔道长度(m); θ――从拉端至计算截面曲线孔道部分切线的夹角之和(rad); k――孔道每米局部偏差对摩擦的影响系数;由于本工程采 用的是预埋金属螺旋管道,故采用0.0015; μ――预应力筋与孔道壁的摩擦系数;本工程采用0.25。 六、拉伸长量计算: (一)中跨半跨计算方法如下: 1、N1#束:分为工作段长65cm+直线长789.2cm+曲线长349.1cm(5o)+直线90.7cm; 2、N2#束:分为工作段长65cm+直线长628.5cm+曲线长349.1cm(5o)+直线252.9cm; 3、N3#束:分为工作段长65cm+直线长467.8cm+曲线长349.1cm(5o)+直线415.1cm; 4、N4#束:分为工作段长65cm+直线长106.6cm+曲线长

30米箱梁张拉计算书

G3012喀什至疏勒段公路工程项目KS-1标段 (K0+000~K22+000) 30m预制箱梁张拉计算方案 编制: 审核: 审批: 中铁二十三局集团有限公司 G3012喀什至疏勒段公路项目KS-1标 项目经理部 二0一六年五月

目录 一、基础数据.............................................................................................................................. - 2 - 二、预应力钢束张拉力计算...................................................................................................... - 2 - 三、压力表读数计算.................................................................................................................. - 3 - 四、理论伸长量的复核计算...................................................................................................... - 6 - 五、张拉施工要点及注意事项.................................................................................................. - 8 -

预制箱梁张拉计算书

预制箱梁张拉计算书 预应力钢绞线施工时,采用张拉应力和伸长值双控,实际伸长值与理论伸长值误差不得超过6%,后张预应力技术一般用于预制大跨径简支连续梁、简支板结构,各种现浇预应力结构或块体拼装结构。预应力施工是一项技术性很强的工作,预应力筋张拉是预应力砼结构的关键工序,施工质量关系到桥梁的安全和人身安全,因此必须慎重对待。一般现行常接触到的预应力钢材主要:有预应力混凝土用钢绞线、PC光面钢丝、刻痕钢丝、冷拔低碳钢丝、精轧螺纹钢等材料。对于后张法预应力施工时孔道成型方法主要有:金属螺旋管、胶管抽芯、钢管抽芯、充气充水胶管抽芯等方法。本人接触多的是混凝土预应力钢绞线(PCstrand、1×7公称直径15,24mm,f pk=1860Mpa,270级高强底松弛),成孔方法多采用金属螺旋管成孔,本文就以此两项先决条件进行论述。 1 施工准备: 1.1 熟悉图纸:拿到施工图纸应先查阅施工说明中关于预应力钢绞线的规格,一般预应力钢束采用ASTMA416-270级低松弛钢绞线,其标准强度为f pk=1860Mpa,1×7公称直径15,24mm,锚下控制力为Δk=0.75 f pk Mpa。 1.2 根据施工方法确定计算参数: 注:摘自《公路桥涵施工技术规范》(JTJ 041-2000)附录G-8 根据钢绞线试验结果取得钢绞线实际弹性模量Ep(一般为1.9~2.04×105Mpa) 1.3 材料检测: 金属螺旋管根据《公路桥涵施工技术规范》(JTJ 041-2000)附录G-7之要求检测; 锚具根据《公路桥梁预应力钢绞线用YM锚具、连接器规格系列》(JT/T 329.1-1997)及《公路桥梁预应力钢绞线用锚具、连接器试验方法及检验规则》(JT/T 329.2-1997)之要求检测; 钢绞线根据《预应力混凝土用钢绞线》GB/T5224-2003之要求检测 2 理论伸长量计算: 后张法预应力钢绞线在张拉过程中,主要受到以下两方面的因素影响:一是管道弯曲影响引起的摩擦力,二是管道偏差影响引起的摩擦力;两项因素导致钢绞线张拉时,锚下控制应力沿着管壁向跨中逐渐减小,因而每一段的钢绞线的伸长值也是不相同的。 2.1 计算公式: 《公路桥梁施工技术规范》(JTJ 041-2000)中关于预应筋伸长值ΔL的计算按照以下公式(1): ΔL=Pp×L Ap×Ep ΔL—各分段预应力筋的理论伸长值(mm); Pp—各分段预应力筋的平均张拉力(N); L—预应力筋的分段长度(mm);

钢绞线张拉计算书

洞路35m预制梁钢绞线拉计算交底书 一、材料规格 预应力钢绞线直径Φ15.2mm,公称面积为140mm2,钢绞线标准强度为f PK =1860Mpa,弹性模量E=195GPa。钢绞线由钢绳股份提供、夹片式锚具由川锚路桥机械有限责任公司提供、塑料波纹管由市路宇建筑材料有限责任公司提供,以上材料均在监理的见证下取样送检并已出具合格报告。根据《市洞路道路改造工程跨铁路桥工程35m预制梁施工图中35m简支T梁预应力钢束布置图》中说明要求预应力钢绞线锚下控制力(不包括钢束与锚圈口之间的摩擦及钢束在锚下垫板喇叭口处因弯折产生摩擦而引起的预应力损失),35m预制简支T梁需拉钢束为N1、N2、N3、N4(均为腹板束),采用钢绞线规格有以下两种情况:当预制梁为中梁时,N1、N2、N3、N4钢束规格均为10-15.2mm;当预制梁为边梁时,N1、N2的钢束规格为10-15.2mm ,N3、N4的钢束规格为11-15.2mm。锚下控制应力均为σcon=0.75*f PK=1395MPa。 二、拉要求 预制梁混凝土立方体强度达到混凝土强度设计等级的90%且龄期不少于7d,方可拉预应力。混凝土强度设计等级为C50,根据混凝土抗压强度检测报告可知已满足设计及规要求。 三、拉顺序 拉采用2台250t千斤顶两端对称、匀称拉,采用拉力和伸长量双控,根据省建筑科学研究检测中心校准证书可知:千斤顶编号及油表编号分别为910#(压力表编号:HT35310397#)、0122#(压力表编号:912940#)。

T梁的拉顺序:钢束拉顺序为N1(控制应力的100%) N2(控 制应力的100%) N3 (控制应力的50%) N4 (控制应力的100%) N3 (控制应力的100%) 即:100%N1 100%N2 50%N3 100%N4 100%N3。 初始拉力P1=0.10P 持荷3分钟测引申量δ1 继 续加载拉力至P2=0.20P 持荷3分钟测引申量δ2 拉 至总吨位P3=P 持荷3分钟测引申量δ3 回油。 千斤顶、油泵、锚具安装好,检查正常后,每一钢束按以下程序 拉: 四、控制力下油表读数计算 HT35310397#油表的回规方程: Y=0.0216X+0.0286 912940#油表的回规方程: Y=0.0219X-0.0857 当预制梁为中梁时: N1第一行程(初拉力为控制力的10%) 10根钢束P初=σcon×10%=(1395×140×10)×10%=195.3KN HT35310397#油表读数:Y=195.3×0.0216+0.0286=4.25MPa 912940#油表读数:Y=195.3×0.0219-0.0857=4.19MPa N1第二行程(初拉力为控制力的20%) 10根钢束P初=σcon×20%=(1395×140×10)×20%=390.6KN HT35310397#油表读数:Y=390.6×0.0216+0.0286=8.47MPa 912940#油表读数:Y=390.6×0.0219-0.0857=8.47MPa N1第三行程(初拉力为控制力的100%) 10根钢束P初=σcon×100%=(1395×140×10)×100%=1953KN

20米、40米箱梁预应力筋伸长量计算

箱梁预应力筋伸长量计算书 一、工程简况 我分部桥梁上部结构采用20m、40m箱梁,结构体系为先简支后连续。箱梁预应力束采用公称直径φs15.2预应力钢绞线,其公称面积Ap=140mm2,抗拉标准强度f pk=1860Mpa,弹性模量Ep=2.01×105Mpa,技术标准符合GB/T5224-2014,配M15-3、M15-4和M15-5系列锚具,预应力管道采用波纹管。 二、计算说明 钢绞线理论伸长值(mm)可按式(1-1)计算: (1-1)式中:—预应力筋的平均张拉力(N),直线筋取张拉端的拉力;两端张拉的曲线筋,计算方法见式(1-2); L—预应力筋的长度(mm); —预应力筋的截面面积(mm2); —预应力筋的弹性模量(N/mm2)。 预应力筋平均张拉力应按式(1-2)计算: (1-2)式中:—预应力筋的平均张拉力(N); P—预应力筋张拉端的张拉力(N); —从张拉端至计算截面的孔道长度(m); —从张拉端至计算截面曲线孔道部分切线的夹角之和(rad); —孔道每米局部偏差对摩擦的影响系数0.0015; —预应力筋与孔道壁的摩擦系数0.25。 注:当预应力筋为直线时。 1.锚下控制力:σk=0.75×1860Mpa=1395Mpa; 2.张拉控制力:P=σk×Ap=1395×140=195.3kN; 3.弹性模量:Ep=2.01×105Mpa;

4.公称面积:Ap=140mm2。 三、计算过程 3.1 20米箱梁边跨(半跨)伸长值计算: N1筋: AB=20.927/2-0.65-BC-CD=20.927/2-0.65-2.128-2.8798=4.8057; BC=R*θ/180*π=30*5.5/180*π=2.8798; CD=2.128; θ=5.5/180*π=0.09599rad。 名称L(m)(rad)P(KN)(cm) AB 4.805700.007208550.007183976.5 3.3 BC 2.87980.095990.02831720.027920969.5 2.0 CD 2.12800.0031920.003187942.4 1.4 9.8135 6.7 N2筋: AB=20.938/2-0.65-BC-CD=20.938/2-0.65-3.582-2.8798=3.3572; BC=R*θ/180*π=30*5.5/180*π=2.8798; CD=3.582; θ=5.5/180*π=0.09599rad。 名称L(m)(rad)P(KN)(cm) AB 3.357200.00503580.005023781.2 2.3 BC 2.87980.095990.02831720.027920777.3 2.0 CD 3.58200.0053730.005359755.6 2.4 9.819 6.7 N3筋: AB=20.801/2-0.65-BC-CD=20.801/2-0.65-0.7330-8.001=1.0165; BC=R*θ/180*π=30*1.4/180*π=0.7330; CD=8.001; θ=1.4/180*π=0.0244rad。

预应力张拉油表读数及伸长值

预应力张拉油表读数及伸长值计算 一、油表读数计算 油表1(13.11.428)线性回归方程:Y=0.02050X+0.79500 油表2(13.11.421)线性回归方程:Y=0.02073X+0.24500 单根张拉控制力:1860×0.75×140=195300N 10根张拉控制力195300×10÷1000=1953KN 11根张拉控制力195300×11÷1000=2148.3KN 1、10根时油表读数 (1)油表1(13.11.428) 100%应力:Y=0.02050×1953+0.79500=40.83MPa 20%应力:Y=0.02050×(1953×20%)+0.79500=8.8MPa 10%应力:Y=0.02050×(1953×10%)+0.79500=4.8MPa (2)油表2(13.11.421) 100%应力:Y=0.02073×1953+0.24500=40.73MPa 20%应力:Y=0.02073×(1953×20%)+0.24500=8.3MPa 10%应力:Y=0.02073×(1953×10%)+0.24500=4.3MPa 2、11根时油表读数 (1)油表1(13.11.428) 100%应力:Y=0.02050×2148.4+0.79500=44.84MPa 20%应力:Y=0.02050×(2148.4×20%)+0.79500=9.6MPa 10%应力:Y=0.02050×(2148.4×10%)+0.79500=5.2MPa (2)油表2(13.11.421) 100%应力:Y=0.02073×2148.4+0.24500=44.78MPa 20%应力:Y=0.02073×(2148.4×20%)+0.24500=9.2MPa 10%应力:Y=0.02073×(2148.4×10%)+0.24500=4.7MPa 二、伸长值计算△L=P P×L/A P E P 1、N1伸长值=195300×(29516+1.44)/140×1.95×105=221㎜ 2、N2伸长值=195300×(29499+1)/140×1.95×105=218㎜ 3、N3伸长值=195300×(29440+1)/140×1.95×105=218㎜

20米预应力空心小箱梁张拉伸长量计算

20米预应力空心小箱梁张拉伸长量计算 一、钢绞线张拉控制力计算 边跨:N1=N2=N3=5×(1860×0.75×140)=976.5KN 中跨:N1=N3=4×(1860×0.75×140)=781.2 KN N2=5×(1860×0.75×140)=976.5 KN 二、钢绞线伸长量计算 已知θ1=(2×3.14)÷180=0.035 θ2=θ3=(6×3.14)÷180=0.1047 E=2.0×105Mpa A=140mm2 U=0.17 K=0.0015 边跨: N1 L ab=2.198+(0.05+0.35+0.025)=2.198+0.425=2.623m L bc=1.047mm L CD=5.256+1.237=6.493m §=0.75×1860×140=195.3KN AB段:Pq=195.3×5=976.5KN Pz=976.5×e-(0.0015×2.623+0.17×0)=974.35KN Pp=Pq×(1-e-(KX+UQ))/(KX+UQ)=(Pq+ Pz)/2=(976.5+974.35)/2=975.42KN △L1=Pp*L/(A×E)=975.42×2.623/(5×140×200)×1000=18.34mm BC段:Pq=974.35KN Pz=974.35×e-(0.0015×1.047+0.17×0.035)=967.05KN Pp=(974.35+967.05)÷2=970.7KN △L2=Pp*L/(A×E)=970.7×1.047÷(5×140×200)×1000=7.26mm CD段:Pq=967.05KN Pz=967.05×e-(0.0015×6.493+0.17×0)=957.68KN Pp=(967.05+957.68)÷2=962.37KN △L3= 962.37×6.493÷(5×140×200)×1000=44.63mm 则总伸长值为:L=(△L1+△L2+△L3)×2=(18.34+7.26+44.63)×2=140.46mm N2 L ab=2.637+0.425=3.062m L bc=3.142m L cd=2.716+1.237=3.953m

最新现浇箱梁预应力张拉计算过程说课讲解

预应力张拉 一、张拉控制 (一)、理论伸长量 1、基本参数 1)钢绞线:规格φs15.2,公称直径15.2mm ,公称截面积140mm 2 ,张拉控制应力con pk 0.75f 0.75*18601395MPa σ===。钢绞线弹性模量按5Ep 1.95*10MPa =。 2)精轧螺纹钢:规格φ32mm ,截面积 804.2mm 2 con pk 0.9f 0.9*930837MPa σ===。 3)波纹管管道摩擦系数0.17μ=,管道偏系差数k 0.0015=。X 从张拉端至计算截面的孔道长度,X 2为孔道长度与工作长度之和(工作长度:锚具长度+限位器长度+千斤顶长度)。X 3为孔道长度与工作长度之和(工作长度:底座高度+千斤顶长度)。两端对称张拉的钢束以平直段中点断面为计算截面,单端张拉的钢束以固定端为计算截面(锚固长度不计)。 2、计算过程 1)纵向、横向张拉 将总和切角α换算为弧度θ:*180 πθ= α,钢束的总和切角为计算长度范围之内的角度之和。 计算单束钢绞线最大张拉力:P 1395*140*n =(根数), 平均张拉力:(kx )p P 1e P kx μθμθ-+-=+(), 则有理论伸长量:p 2 p p P L A E X ?=。

2)竖向张拉 竖向预应力筋为32mm 精轧螺纹钢,计算精轧螺纹钢最大张拉力:2con *804.367.3P mm t σ==, 则有理论伸长量:3P L A E X ?=。 由于精轧螺纹钢伸长量较小,张拉施工时误差影响较大,因此按照设计以张拉吨位为主,伸长量为辅。 (二)、实际伸长量 预应力施加顺序为:con con con 015%30%σσσ---,持荷两分钟后锚固。 为保证实际伸长量数据准确性,减少计算预应力损失的误差,采用30%张拉力的伸长量减去15%张拉力的伸长量,代替0-15%张拉力的伸长量。 实际伸长量测量程序为:施加预应力15%时记录伸长量1L ,施加预应 力30%时记录伸长量2L ,施加预应力100%时记录伸长量3L ,则有: 实际伸长量3121L L L L L =-+-()。 由于预应力张拉采用伸长量与张拉力双控,因此在控制张拉力的同时,需计算实际伸长量与理论伸长量的差值是否满足规范及设计要求。 合格标准为L-L 6%6%L ?≤≤?-+。 为保证竖向预应力筋张拉质量,采取复拉以减少预应力损失,即跳块张拉,如施工4#块时可对已经张拉完成的2#块竖向预应力筋再次进行张拉,补偿应力损失。 二、注意事项 1、预应力筋、锚具、夹具和连接器使用前应进行外观质量检查,不得有弯曲,表面不得有裂纹、毛刺、机械损伤、铁锈、油污等。

现浇连续箱梁预应力张拉计算演示教学

现浇连续箱梁预应力 张拉计算

重庆沙滨路连续箱梁张拉计算预应力施工作业指导书 编制: 审核: 审批: 重庆拓达建设集团有限公司 2011年5月21日

目录 一、张拉前的准备工作 (2) 二、张拉程序 (2) 三、张拉控制数据计算 (2) 四、张拉力与油表读数对应关系 (12) 五、伸长值的控制 (14) 六、质量保证措施 (14) 七、安全保证措施 (15)

预应力施工作业指导书 后张法预施应力是待混凝土构件达到一定的强度后,在构件预留孔道中穿入预应力筋,使预应力筋对混凝土构件施加应力。这是一项十分重要的工作,施加预应力过多或不足都会影响预制构件质量,必须按设计要求,准确地施加预应力。 一、张拉前的准备工作 1、张拉前需完成梁内预留孔道、制束、制锚、穿束和张拉机具设备的准备工作。 2、张拉作业上岗作业人员必须经过特种作业培训,并取得特种作业合格证书。施工前,还必须对所有作业人员进行严格的施工技术交底。 3、钢绞线、锚具、张拉千斤顶、压力表等设备必须经专业检测单位检测,并取得检验合格报告。 4、张拉安全防护设备已安装完毕并在作业区周边布设警示标志,由专人负责看护、挪动。 二、张拉程序 预应力张拉要求混凝土强度达到90%且龄期不少于7天方可张拉,张拉时需纵横向钢束交替进行,纵向钢束张拉按先长后短的原则进行作业。 张拉工序为:0→初应力→控制应力(持荷2分种锚固)。 三、张拉控制数据计算 本作业指导书以标准段3×30m箱梁纵向和横向预应力筋伸长量计算为例进行编制。 ㈠、计算依据

1、采用YJM15系列自锚性能锚具(即:YJM15-15、YJM15-7),张拉设备采用YCW250型、YCW400型配套千斤顶,已通过质量监督检验所检验合格并标定,检验证书附后。 2、本桥采用低松驰高强度预应力钢绞线,单根钢绞线为15.24mm(钢绞线试验面积A g=140.9mm2),标准强度f pk=1860Mpa,弹性模量E p=1.98×105Mpa。锚下控制应力:σcon=0.75f pk=0.75×1860=1395Mpa。 3、张拉时采用预应力筋的张拉力与预应力筋的伸长量双控,并以预应力筋的张拉力控制为主。 4、瓯海大道西段快速路8标高架桥标准段施工图纸及《公路桥涵施工技术规范》JTJ041-2000。 ㈡、理论张拉伸长值的计算 1、按现行桥涵施工规范,预应力筋的理论伸长值△L(mm)为: △L=Pp×L/Ap×Ep (1) Pp—预应力筋的平均张拉力(N); L —预应力筋的长度(mm); Ap—预应力筋的截面积(mm2); Ep—预应力筋的弹性模量(N/mm2)。 2、预应力筋的平均张拉力为: Pp=P(1-e-(kx+uθ))/(kx+uθ) (2) P —预应力筋张拉端的张拉力(N); x —从张拉端至计算截面的孔道长度(m);

预应力张拉油表读数计算表

油表编号钢束编号 油表读数(MPa ) 1573#N2(7束)29.45059#N2(7束)28.81573#N1(8束)33.65059#N1(8束)32.91573#N3(7束)29.45059#N3(7束)28.81573#N3(8束)33.65059#N3(8束) 32.9 1573#读数 (MPa )N1 10% 3.4N1 20% 6.7 N2 10% 2.9N2 20% 5.9 5059#读数(MPa )N1 10% 3.3N1 20% 6.6N2 10% 2.9N2 20% 5.81573#读数(MPa )N3 10% 2.9N3 20% 5.9 N3 10% 3.4N3 20% 6.7 5059#读数(MPa ) N3 10% 2.9 N3 20% 5.8 N3 10% 3.3 N3 20% 6.6 油表读数=控制张拉力*标定方程式=1860*0.75*140*7/1000*0.0215+0.0048油表读数=控制张拉力*标定方程式=1860*0.75*140*7/1000*0.0211-0.06677束 8束 后附:千斤顶力值与油压表读数关系校正表 油表读数=控制张拉力*标定方程式=1860*0.75*140*8/1000*0.0215+0.0048油表读数=控制张拉力*标定方程式=1860*0.75*140*8/1000*0.0211-0.0667 8束 7束 计算公式 油表读数=控制张拉力*标定方程式=1860*0.75*140*7/1000*0.0211-0.0667油表读数=控制张拉力*标定方程式=1860*0.75*140*7/1000*0.0215+0.0048BD07合同段预应力张拉油表读数计算表 油表读数=控制张拉力*标定方程式=1860*0.75*140*8/1000*0.0215+0.0048油表读数=控制张拉力*标定方程式=1860*0.75*140*8/1000*0.0211-0.0667

30m箱梁张拉计算书

神木市沙峁至贺家川公路改建工程LJ-2标 段窟野河大桥 30m箱梁预应力张拉计算书 编制: 审核: 2019年5月20日

目录 第1章工程概况 (1) 第2章张拉力计算 (2) 第3章张拉工艺流程质量控制 (14) 第4章张拉注意事项及安全技术 (16)

第1章工程概况 本计算书适用于神木市沙峁至贺家川公路改建工程LJ-2标段。30m预应力砼连续箱梁采用先简支后连续结构,主梁由预制C50预应力混凝土浇筑,和现浇砼桥面组合而成后采用张拉预应力施工,预应力钢铰线,符合采用标准(GB/T 5224-2003)公称直径15.2mm的高强度低松驰钢绞线,抗拉强度标准1860MPa,公称面积为140mm2)。锚具采用M15-4、M15-5型圆形锚具及其配套的配件。钢绞线采用符合GB/T 5224-2003标准的低松弛高强度钢绞线,单根钢绞线公称直径Φ s15.20,钢绞线的面积A p=140mm 2,钢绞线的标准强度f pk=1860MP a ,松 弛率ρ=0.035,弹性模量E p=1.95×105Mpa。松弛系数ξ=0.3,管道摩擦系数μ=0.25,管道偏差系数k=0.0015;根据设计要求,配备YDC-1500千斤顶4台,压力表四块,上述设备均应在法定权威机构进行标定。 施工要求 1、预应力施工需计算书经审批且监理工程师在场的前提下才能进行张拉作业施工。 2、当气温低于+5℃或超过+35℃时禁止施工。 3、箱梁的砼强度应不低于设计强度等级值得90%,弹性模量不低于混凝土28d弹性模量的85%时,方可张拉预应力钢束。采取两端对称同时张拉,每次张拉一束钢绞线,张拉前应检查预应力钢束是否在管道内移动正常,张拉顺序为不少于7天且锚下砼达90%设计强度。张拉顺序为N1、N3、N2、N4号钢束。

20米箱梁张拉计算书。

20米预制箱梁张拉计算书 一、基础数据 本标段20米预制箱梁正弯矩预应力钢束共有N1、N2、N3各2束,负弯矩预应力钢束共有T1、T2、T3各2束, 1束,2束,设计锚下张拉控制应力:σcon=1860×0.75=1395MPa。按设计要求箱梁砼强度达到设计强度的90%后方可张拉,并采用两端对称张拉,张拉程序为: 0 初应力σcon(持荷2min)锚固,张拉顺序为N1、N2、N3, T3、T1、T2。 二、预应力钢束张拉力计算 1、因设计图中张拉控制应力已经考虑了预应力损失,故张拉力按公式:Fn=σcon×A×n进行计算,如下: N1 钢束锚下张拉力F1=σcon×A×n=1395 MPa×140㎜2×4 =781.2KN 其中:A为每根预应力钢绞线的截面积; n为同时张拉的预应力钢绞线的根数; F为钢绞线锚下张拉力。 其余钢束张拉力计算同N1,各钢束张拉力如下表:

三、压力表读数计算 本桥采用150吨千斤顶进行张拉,经校验: 编号为1号千斤顶对应的压力表编号为2R4172,线性回归方程为P=0.0326F+0.0492。 编号为2号千斤顶对应的压力表编号为2R4135,线性回归方程为P=0.0327F+0.0098。 编号为3号千斤顶对应的压力表编号为2R4197,线性回归方程为P=0.0327F+0.0044。 编号为4号千斤顶对应的压力表编号为2R4140,线性回归方程为P=0.0325F+0.0011。 故N1钢束采用1号千斤顶张拉时的压力表度数为: 1)压力表编号为2R4172:

P=0.0326F+0.0492=0.0326×585.9+0.0492=19.1 MPa 故N1钢束采用2号千斤顶张拉时的压力表度数为:2)压力表编号为2R4135: P=0.0327F+0.0098=0.0327×585.9+0.0098=19.2 MPa 故N1钢束采用3号千斤顶张拉时的压力表度数为:3)压力表编号为2R4197: P =0.0327F+0.0044=0.0327×585.9+0.0044=19.2MPa 故N1钢束采用4号千斤顶张拉时的压力表度数为:4)压力表编号为2R4140: P=0.0325F+0.0011=0.0325×585.9+0.0011=19.0 MPa 同理可得下表:

25m小箱梁后张法预应力张拉计算与应力控制

专项施工方案审批表承包单位:合同号:

工程 箱 梁 张 拉 伸 长 量 计 算 书 工程项目部 二0一五年十二月七日 工程25m箱梁

预应力张拉伸长量计算 1 工程概况 (1)跨径25m的预应力混凝土简支连续箱梁,梁体高度1.4m,宽度2.4m,采用C50混凝土, (2)钢绞线规格:采用高强低松驰钢绞线Φs15.2规格,标准抗拉强度fbk=1860Mpa,公称截面面积140mm2,弹性模量根据试验检测报告要求取Ep=1.93×105Mpa。钢束编号从上到下依次为N1、N2、N3、N4,其中: 中跨梁:N1为4Φs15.2,N2、N3、N4为3Φs15.2; 边跨梁:N1、N2、 N3为4Φs15.2, N4为3Φs15.2; (3) 根据施工设计图钢绞线张拉控制应力按75%控制,即σcon=1860×75%=1395Mpa,单股钢绞线张拉吨 位为:P=1395×140=195.3KN,3股钢绞线张拉吨位为:F=195.3×3=585.9KN,4股钢绞线张拉吨位为:F=195.3×4=781.2KN,采用两端张拉,夹片锚固。 (4) 箱梁砼强度达到90%以上且养护时间不少于7d时方可张拉,张拉顺序N1、N3、N2、N4钢束。 (5) 根据规范要求结合现场施工经验,为了有效控制张拉过程中出现异常情况,分级进行张拉:0~15% (测延伸量)~30%(测延伸量)~100%(测延伸量并核对)~(持荷2分钟,以消除夹片锚固回缩的预应力损失)~锚固(观测回缩)。 2 油压表读数计算 (1)根据千斤顶的技术性能参数,结合合肥工大共达工程检测试验有限公司检定证书检定结果所提供的线性方程,计算实际张拉时的压力表示值Pu: 千斤顶型号:YC150型编号:1 油压表编号:yw08007229 回归方程:Y=0.03377X+1.18 千斤顶型号:YC150型编号:2 油压表编号:yw05049806 回归方程:Y=0.03335X+0.51 千斤顶型号:YC150型编号:3 油压表编号:yw07023650 回归方程:Y=0.03358X+0.84 千斤顶型号:YC150型编号:4 油压表编号:yw05049788 回归方程:Y=0.03367X+0.01 (2) 钢束为3股钢绞线 张拉至10%控制应力时油压表读数计算: 1千斤顶,yw08007229油压表读数: Pu=0.03377X+1.18=0.03377×585.9*10%+1.18=3.2Mpa 2千斤顶,yw05049806油压表读数: Pu=0.03335X+0.51=0.03335×585.9*10%+0.51=2.5Mpa 3千斤顶,yw07023650油压表读数: Pu=0.03358X+0.84=0.03358×585.9*10%+0.84=2.8Mpa

20米箱梁预应力张拉伸长量计算(最终10.9)

20米箱梁预应力张拉伸长量计算 钢铰线强度:1860MPa 控制应力:1860×0.75=1395 MPa 钢铰线公称面积:140 mm2 单根控制力:1395×140.0=195300 N 伸长量计算公式:△L=Pp×L÷(Ap×Ep) 一、中跨 1#束 ①直线段长 0.537米②竖曲线段长 L=π÷180°×a×R= 3.1415926÷180°×5.5°×30.0=2.880米③直线段长 4.869 米④平曲线段长 L=π÷180°×a×R=3.1415926÷180°×1.8°×2 5.0=0.785÷COS5.5°=0.789 ⑤直线段长 0.728米⑥工具段长 0.74米(由于箱梁板顶预埋筋影响,千斤顶不能靠近锚环,为不弯曲板顶预埋筋,需增加一个过渡环,具体尺寸为:锚环0.046m+限位板0.035m+过渡环0.25m+千斤顶0.363m+锚环0.046m=0.74m) Pp=P×(1-e-(kx+μθ))÷(kx+μθ) Pp=P=195300 N Ep=198 GPa 得: ⑥的伸长量: e=2.718281828 k=0.0015 x=0.74 μ=0.25 θ=0° 195300×(1-2.71828-(0.0015×0.74))÷(0.0015×0.74) =195191.52 N 195191.52×740÷(140×198000)=5.21mm ⑤的伸长量: e=2.718281828 k=0.0015 x=1.468 μ=0.25 θ=0° 195300×(1-2.71828-(0.0015×1.468))÷(0.0015×1.468) =195085.00 N 195085.00×728÷(140×198000)=5.12mm ④的伸长量: e=2.718281828 k=0.0015 x=2.257 μ=0.25 θ=1.8°×0.017453293=0.03142 195300×(1-2.71828-(0.0015×2.257+0.25×0.03142))÷(0.0015×2.257+0.25×0.03142)=194206.34 N 194206.34×789÷(140×198000)=5.53 mm

25米箱梁张拉计算书

25米小箱梁预应力张拉计算书 编制: 复核:

2012年2月20日 一、张拉施工方案 我合同段施工的主线桥、A匝道桥、B匝道桥25米箱梁预应力钢绞线采用高强度低松弛钢铰线,f pk=1860Mpa,公称直径d=15.24mm,公称面积Ay=140mm2,弹性模量Ey=1.95×105Mpa。25米箱梁正弯矩钢束采用8股、9股,钢束控制张拉力σcon=0.75 f pk=1395Mpa。锚具采用15-8型、15-9型系列整套锚具,管道成孔采用钢波纹管。所有锚具及钢绞线按材料检验批量抽检,严禁使用无部级以上级别技术鉴定和产品鉴定的材料。材料要有厂方提供的质量说明书和出厂时间。钢铰线要防止生锈和影响水泥粘结的油污。 钢铰线下料采用砂轮切割机按加工长度下料。钢筋绑扎结束,装模前由专人对波纹管进行检查,若有孔眼须用胶布缠好,严禁进浆。 预应力张拉前先试压同条件养护砼试件,主梁达到设计强度85%以上且养护龄期不小于7天方可张拉,钢束张拉时应两端对称、均匀张拉,不得集中张拉,并观察主梁的侧弯情况,张拉前先对张拉千斤顶进行校核。张拉顺序为:50%N2、N3→100%N1→100%N2、N3→100%N4,张拉程序:0-初始应力(10%σk)-σk(持荷2分钟锚固)。张拉时实行双控,理论伸长量与实际伸长量相差应控制在-6%~+6%之间,否则应分析原因或重新张拉。张拉严格控制滑丝和断丝,每束不超过1根,累计全片梁小于1%。张拉完割除钢铰线头,及

时压浆。张拉时做好施工记录。 二、理论伸长值计算 1、理论伸长量计算 钢铰线采用15.24mm 单根截面面积140mm2 标准强度f pk =1860MPa 弹性模量Ey=1.95×105MPa 管道摩擦系数μ=0.25 管道偏差系数K=0.0015 锚下控制应力σcon=0.75×f pk=1860×0.75=1395MPa 每股控制张拉力1395×140=195300N 4股钢绞线控制张拉力N=193905×4=775620N=775.62KN 8股钢绞线控制张拉力N=193905×8=1551240N=1551.24KN 9股钢绞线控制张拉力N=193905×9=1745145N=1745.15KN 计算公式: P P=P(1-e-(kx+μθ))/(kx+μθ) △L=P P×L/AP×EP 式中:P P--预应力筋平均张拉力(N) P--预应力筋张拉端的张拉力(N) e—常数(e =2.7183) k—孔道摩擦系数(取0.0015) x—从张拉端至计算截面积的孔道长度(米) μ—孔道偏差系数(取0.2) θ—从张拉端至计算截面积曲线孔道部分切线的夹角之和(rad)