二次结构进度计划
二次结构砌体细化进度

二次结构砌体细化进度二次结构砌筑完成施工进度计划序号单位工程分项工程计划开始时间计划完成时间劳动力、机械资源备注1 3#、5# 完成八层腰带以上砖墙砌筑 5.17 5.18 822 完成九层腰带以上砖墙砌筑 5.19 5.20 823 完成十层腰带以上砖墙砌筑 5.21 5.22 826 完成十二层腰带以下砖墙砌筑 5.23 5.24 827 完成十三层腰带以下砖墙砌筑 5.25 5.26 828 完成十四层腰带以下砖墙砌筑 5.27 5.28 829 完成十一层腰带以上砖墙砌筑 5.29 5.31 8210 完成十二层腰带以上砖墙砌筑 6.1 6.2 8211 完成十三层腰带以上砖墙砌筑 6.3 6.4 8212 完成十五层腰带以下砖墙砌筑 6.5 6.6 8213 完成十六层腰带以下砖墙砌筑 6.7 6.8 8214 完成十四层腰带以上砖墙砌筑 6.9 6.10 8215 完成十五层腰带以上砖墙砌筑 6.11 6.12 8216 完成十六层腰带以上砖墙砌筑 6.13 6.14 8217 完成十八层腰带以下砖墙砌筑 6.15 6.16 8218 完成十七层腰带以上砖墙砌筑 6.17 6.18 8219 完成十八层腰带以上砖墙砌筑 6.19 6.21 82202122 4# 完成十二层腰带以上砖墙砌筑 5.19 5.20 8223 完成十三层腰带以上砖墙砌筑 5.21 5.22 8224 完成十五层腰带以下砖墙砌筑 5.23 5.24 8225 完成十六层腰带以下砖墙砌筑 5.25 5.26 8226 完成十四层腰带以上砖墙砌筑 5.27 5.28 8227 完成十五层腰带以上砖墙砌筑 5.29 5.31 8228 完成十七层腰带以下砖墙砌筑 6.1 6.2 8229 完成十八层腰带以下砖墙砌筑 6.3 6.4 8230 完成十六层腰带以上砖墙砌筑 6.5 6.6 8231 完成十七层腰带以上砖墙砌筑 6.7 6.8 8232 完成十八层腰带以上砖墙砌筑 6.9 6.10 823#、5#楼构造柱完成六层构造柱浇筑 5.20完成七层构造柱浇筑 5.23完成八层构造柱浇筑 5.27完成九层构造柱浇筑 5.30完成十层构造柱浇筑 6.2完成十一层构造柱浇筑 6.6完成十二层构造柱浇筑 6.10完成十三层构造柱浇筑 6.13完成十四层构造柱浇筑 6.17完成十五层构造柱浇筑 6.20完成十六层构造柱浇筑 6.23完成十七层构造柱浇筑 6.27完成十八层构造柱浇筑 6.304#楼构造柱完成九层构造柱浇筑 5.20完成十层构造柱浇筑 5.23完成十一层构造柱浇筑 5.26完成十二层构造柱浇筑 5.29完成十三层构造柱浇筑 6.1完成十四层构造柱浇筑 6.4完成十五层构造柱浇筑 6.7完成十六层构造柱浇筑 6.10完成十七层构造柱浇筑 6.13完成十八层构造柱浇筑 6.16我项目部准备在6月10日,对地下室工程进行主体验收。
二次结构施工专项方案

二次结构施工专项方案一、工程概况和施工条件本工程为XX项目,位于XX市XX区,是一座高层住宅楼工程。
该工程的二次结构施工主要包括构造柱、圈梁、过梁、压顶等构件的浇筑和砌筑工作。
施工条件包括现场地形、气候、交通、能源供应、安全环境等因素。
在二次结构施工中,应充分考虑这些因素,确保施工顺利进行。
二、施工组织和任务分配为确保二次结构施工的顺利进行,我们成立专门的施工队伍,明确各岗位职责和任务分配。
同时,制定详细的工作计划和技术交底,确保施工过程有序、高效。
三、施工工艺和方法二次结构施工主要包括以下工艺和方法:1.钢筋绑扎:按照设计要求,对构造柱、圈梁等构件进行钢筋绑扎。
2.模板安装:根据设计图纸,安装相应的模板,确保模板的稳定性和密封性。
3.混凝土浇筑:将搅拌好的混凝土倒入模板中,用振捣器振捣密实。
4.砌筑施工:采用合适的砌筑砂浆和砖块,按照设计要求进行砌筑施工。
5.养护:完成浇筑或砌筑后,进行适当的养护,确保构件达到设计强度。
四、施工设备和材料要求为保证二次结构施工的顺利进行,我们需要以下设备和材料:1.搅拌机、振捣器、钢筋加工设备等施工设备。
2.水泥、砂、砖、钢筋等建筑材料。
3.相应的模板、支撑架等辅助材料。
4.安全设施和防护用品。
五、施工安全和质量控制在二次结构施工过程中,我们采取以下措施确保施工安全和质量控制:1.制定安全操作规程,加强安全教育和技术交底。
2.定期检查施工现场的安全状况,及时发现和处理安全隐患。
3.严格按照设计要求和相关标准进行施工,确保施工质量符合规范要求。
4.加强材料质量控制,对进场的材料进行严格检查和验收。
5.实行质量责任制,明确各岗位的质量控制要求。
6.定期进行质量检查和验收,对不合格的部位及时进行处理和整改。
7.加强与设计单位和相关部门的沟通协调,确保施工符合设计意图和规范要求。
8.做好施工现场的环境保护工作,减少对周边环境的影响和污染。
最详细的二次结构施工方案

最详细的二次结构施工方案目录一、前言 (3)1.1 编制依据 (3)1.2 工程概况 (4)二、施工准备 (5)2.1 施工材料准备 (6)2.2 施工设备准备 (7)2.3 施工人员准备 (8)2.4 施工现场布置 (9)三、二次结构施工工艺流程 (11)3.1 墙体砌筑 (12)3.1.1 砌筑前准备 (13)3.1.2 砌筑操作 (14)3.1.3 砌筑质量检查 (16)3.2 混凝土浇筑 (17)3.2.1 浇筑前准备 (18)3.2.2 混凝土浇筑 (19)3.2.3 混凝土养护 (21)3.3 砌块安装 (22)3.3.1 安装前准备 (22)3.3.2 安装操作 (24)3.3.3 安装质量检查 (25)四、二次结构施工要点 (27)4.1 墙体砌筑要点 (28)4.2 混凝土浇筑要点 (30)4.3 砌块安装要点 (30)五、安全生产与文明施工 (31)5.1 安全生产措施 (32)5.2 文明施工管理 (34)六、季节性施工措施 (35)6.1 防止雨水冲刷 (36)6.2 防止高温作业 (37)七、应急预案与风险管理 (38)7.1 应急预案制定 (40)7.2 风险因素识别 (42)7.3 风险控制措施 (43)八、施工进度计划与资源配置 (44)8.1 施工进度计划 (46)8.2 资源配置计划 (47)九、质量控制与验收标准 (49)9.1 施工质量控制 (50)9.2 工程验收标准 (51)一、前言在当前建筑行业中,二次结构施工对于整体建筑质量及安全至关重要。
本施工方案旨在提供关于二次结构施工最详细的技术指导与操作规范,确保施工过程科学、合理、高效。
本方案结合实际情况,对二次结构的施工流程、技术要点、质量控制及安全保障等方面进行全面阐述,旨在为相关施工单位提供有力的支持与参考。
随着现代建筑技术的不断进步与发展,二次结构施工在建筑整体建设中的地位日益凸显。
二次结构不仅承担着建筑物的承重功能,还涉及到建筑物的美观与舒适度。
工地二次结构施工方案

工地二次结构施工方案引言本文档旨在介绍工地二次结构的施工方案,包括施工准备、工序安排、材料使用等内容。
二次结构是建筑中的重要组成部分,对于建筑的安全和稳定性起着至关重要的作用。
因此,合理的施工方案对于工程的顺利进行具有重要意义。
施工准备在进行二次结构施工之前,需要做好充分的施工准备工作。
具体包括以下内容:1.施工人员:确定施工队伍,包括队长、技术人员、工人等,确保工地人员配备合理。
2.工程设备:准备所需的工程设备,包括吊装设备、混凝土搅拌设备等,确保施工过程中的顺利进行。
3.施工材料:准备所需的施工材料,包括钢筋、混凝土、砖块等,确保施工过程中材料供应充足。
4.安全措施:制定施工期间的安全措施,包括安全防护设施、施工交通指示等,确保施工过程中人员安全。
工序安排二次结构的施工主要包括以下工序:1.钢筋工程:首先进行的是钢筋工程,包括钢筋的剪断、焊接、固定等工作。
钢筋应按照设计图纸进行布置,并符合相关的安全规范要求。
完成钢筋工程后,需进行验收,确保质量合格。
2.混凝土浇筑:在完成钢筋工程后,进行混凝土浇筑。
在浇筑混凝土之前,需要对混凝土进行配比,并进行试验,确保混凝土的强度和质量。
混凝土浇筑过程中需要注意浇筑的均匀性和充实性,避免出现空鼓和裂缝。
3.砌体工程:在混凝土浇筑完成后,进行砌体工程。
砌体工程主要包括墙体的砌筑和柱、梁的砌筑。
在进行砌筑工作之前,需要制定详细的工艺方案,按照设计图纸进行施工,确保墙体、柱、梁的垂直度和水平度符合要求。
4.面层处理:在完成砌体工程后,进行面层处理。
面层处理包括刮腻子、粉刷等工作。
在进行面层处理之前,需要进行基层处理,确保基层平整、无杂物。
面层处理过程中需要注意材料的选用和施工方法,确保面层质量达到设计要求。
材料使用在二次结构的施工中,需要使用各种材料,包括钢筋、混凝土、砖块、腻子等。
在使用这些材料时,需要注意以下几个方面:1.品质检验:在使用材料之前,对于各类材料,需要进行品质检验,确保材料符合相关的标准和规范要求。
二次结构工期计划表

二次结构工期计划表English Answer:Secondary Structure Schedule.Phase 1: Planning and Design.Conduct site surveys and geotechnical investigations. Develop detailed design drawings and specifications. Obtain building permits and approvals.Phase 2: Foundation and Substructure.Excavate and prepare the site.Install foundations (footings, piers, etc.)。
Construct substructure elements (walls, columns,beams)。
Phase 3: Superstructure.Erect structural framing (beams, columns, slabs)。
Install windows, doors, and exterior cladding.Conduct roofing and waterproofing.Phase 4: Interior Construction.Install interior partitions, ceilings, and finishes. Complete mechanical, electrical, and plumbing systems. Perform inspections and testing.Phase 5: Sitework.Grade and landscape the site.Install hardscaping (pavers, walkways, etc.)。
Plant trees and shrubs.Phase 6: Finalization.Conduct punch list inspections.Obtain final building inspections and approvals.Hand over the completed structure to the owner.Timeline.The estimated timeline for the secondary structure construction project is as follows:Phase 1: Planning and Design: 4 months.Phase 2: Foundation and Substructure: 6 months.Phase 3: Superstructure: 10 months.Phase 4: Interior Construction: 8 months.Phase 5: Sitework: 2 months.Phase 6: Finalization: 1 month.Note: This timeline is subject to change based on factors such as weather conditions, material availability, and unforeseen circumstances.Budget.The estimated budget for the secondary structure construction project is as follows:Phase 1: Planning and Design: $50,000。
新楼盘二次结构施工方案

新楼盘二次结构施工方案1. 引言本文档将详细介绍新楼盘二次结构施工方案。
二次结构是建筑工程中的重要组成部分,负责承载建筑的重力荷载并提供稳定的支撑和结构。
通过本方案,旨在确保新楼盘的二次结构施工过程顺利进行,保证建筑工程的质量和安全。
2. 施工流程2.1 基坑施工基坑施工是二次结构施工的首要步骤。
首先,确定基坑的位置和尺寸,并进行地质勘察和土壤测试。
然后,按照设计要求进行挖土和边坡支护。
确保基坑的稳定性和安全性。
完成基坑施工后,开始进行基础施工。
根据结构设计图纸,进行基础的浇筑及强度检测。
在完成主体结构的基础后,进行地板和地下室的施工。
2.3 梁柱施工在基础完成后,进行梁柱施工。
首先,安装脚手架和施工模板,然后进行钢筋的制作和安装。
完成钢筋的安装后,进行混凝土的浇筑和养护。
2.4 楼板施工梁柱施工完成后,开始进行楼板的施工。
先进行楼板底模板的安装和调整,然后进行钢筋的制作和安装。
最后,进行混凝土的浇筑。
完成楼板施工后,进行墙体的施工。
首先,安装墙体的模板,并进行精确定位和调整。
然后,进行墙体的钢筋制作和安装。
最后,进行混凝土的浇筑和养护。
2.6 屋面施工墙体施工完成后,进行屋面的施工。
先进行屋面的防水处理,然后安装檐口、排水系统和防护层。
最后,进行屋面的封顶和养护。
3. 质量控制为确保新楼盘二次结构施工质量,需要进行严格的质量控制措施。
3.1 施工材料质量检验在施工过程中,对所有使用的施工材料进行质量检验。
例如,钢筋要满足设计要求,混凝土要符合强度要求。
3.2 施工工艺控制对施工工艺进行控制,确保每个工序按照规范和设计要求进行。
例如,混凝土浇筑要注意均匀性和浇注层次,墙体施工要注意模板的精确度和钢筋的安装质量。
3.3 结构安全检测在不同施工阶段进行结构安全检测,确保结构的稳定性和安全性。
例如,进行基础的强度检测、梁柱和楼板的承载力检测等。
3.4 配合与协调各施工工序之间要进行良好的配合与协调,确保施工进度和质量。
二次结构施工方案

第1篇
二次结构施工方案
一、项目概述
1.1项目背景
为实现建筑物的功能布局和使用需求,在主体结构完成后,需进行二次结构施工。二次结构施工主要包括墙体、楼地面、屋面等部位的砌筑、浇筑和安装工作。
1.2项目目标
确保二次结构施工质量、安全、进度和成本控制,满足设计要求及规范标准。
二、施工准备
2.1技术准备
-对设备进行定期维护、保养,确保设备正常运行。
四、施工工艺及要求
4.1砌筑工程
-砌体材料:烧结普通砖、轻骨料混凝土小型空心砌块等。
-砌筑砂浆:水泥砂浆,强度等级符合设计要求。
-施工要求:墙体垂直度、平整度、灰缝厚度等符合规范。
4.2浇筑工程
-混凝土:符合国家标准的混凝土,强度等级满足设计要求。
-浇筑要求:确保混凝土浇筑连续、密实,避免蜂窝、麻面等现象。
---
第2篇
二次结构施工方案
一、工程背景
在主体结构施工完成后,为满足建筑物的使用功能和美观要求,需进行二次结构施工。二次结构主要包括墙体、楼地面、屋面等部位的细部构造,其施工质量直接影响到建筑物的整体性能和使用寿命。
二、施工目标
确保二次结构施工符合设计规范,达到质量优良、安全可靠、进度合理和经济高效的目标。
4.3施工验收
(1)施工完成后,组织自检、互检和专检。
(2)按照验收标准,对工程质量进行评定。
五、安全文明施工
5.1安全管理
(1)建立健全安全生产责任制,明确各级管理人员和施工人员的安全职责。
(2)对施工现场进行安全巡查,消除安全隐患。
5.2文明施工
(1)加强施工现场环境保护,降低施工噪音、粉尘、废水等污染。
三、施工工艺及要求
二次结构施工方案(1)

二次结构施工方案(1)第一章、编制依据本施工组织设计的编制依据如下:1.1、唐山市曹妃甸宏丰宾馆工程设计文件。
1.2、唐山市曹妃甸宏丰宾馆工程工程建筑、结构及水电等各专业施工图。
1.3现行国家有关施工规范及规程和规定及河北省地方性施工规范、验收规范、结构规范。
1.4、政府有关的法规、法令和条例。
1. 5.施工规范及检验标准工程测量规范《GB50026—93》地基与基础工程及验收规范《GB50202—2002》砌体工程施工及验收规范《GB50203—2011》混凝土结构工程施工及验收规范《GB50204—2011》建筑装饰工程验收规范《GB50210—2001》门窗安装及验收规范《JGJ103—2008》混凝土强度检验平定标准《GBJ107—87》钢筋焊接及验收规范《GBJ18—2003》建筑地面工程施工及验收规范《GB50209—2010》建筑工程质量评定标准《GB301—88》建筑工程施工质量验收统一标准?GB50300-2001?建筑机械使用安全技术规程?JGJ33-2001?施工现场临时用电安全技术规范?JGJ46-2005?12J系列河北建筑标准设计图集第二章、工程概况2.1、曹妃甸宏丰宾馆工程。
位于唐山市曹妃甸临港商务区休闲商业街滨水东街以东,北二道以北区域。
工程总建筑面积为12280m2。
四层框架结构,建筑高度17.4m,设计使用年限为50年,抗震设防烈度为7度,耐火等级为二级。
宾馆建筑等级为一级,总客房数125间(三层63间,四层62间,其中无障碍客房2间)。
屋面防水二级,建筑等级为一级,室内外高差0.3m,±0.00为绝对标高5.05m。
2.2、设计主体为四层框架结构,其基础为管桩桩基,管桩为C80预应力砼管桩。
桩径0.4m,桩长24m,防腐蚀要求抗渗等级不应低于P10,钢筋保护层厚度不应小于35mm。
上有承台、框柱.框梁、现浇楼板。
安全等级为二级,,内外墙为A3.5加气混凝土块采用专用砂浆砌筑,±0.00以下墙体采用MU10水泥砂浆,MU10页岩烧结的实心砖砌筑。
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
度计划
完成时间
2019/6/6 2019/7/21 2019/9/14 2019/6/19 2019/8/20 2019/9/30 2019/5/17 2019/6/21 2019/7/21 2019/5/30 2019/6/30 2019/7/30 2019/5/24 2019/5/29 2019/5/30 2019/6/2 2019/6/16 2019/6/6 2019/5/26 2019/6/16
邳州熙悦府75号地块二次结构进度计划
楼栋
项目
名称内容
1-10层二结构砌筑完成
二结构工程 11-20层二结构砌筑完成
21-34层二结构砌筑完成
ห้องสมุดไป่ตู้
主体验收(1-10层)
主体验收 主体验收(8-20层)
主体验收(21-34层)
1-7层二结构砌筑完成
二结构工程 8-20层二结构砌筑完成
21-30层二结构砌筑完成
开始时间
2019/5/16 2019/6/6 2019/7/21 2019/6/19 2019/8/20 2019/9/30 2019/5/16 2019/5/17 2019/6/21 2019/5/30 2019/6/30 2019/7/30 2019/5/16 2019/5/24 2019/5/16 2019/5/31 2019/6/16 2019/5/16 2019/5/16 2019/6/16
主体验收(1-7层)
主体验收 主体验收(8-20层)
主体验收(21-34层)
16-18层二结构砌筑完成
二结构工程
1层二结构砌筑完成 15-18层二次结构
1层二次结构
主体验收
主体验收
东单元4-10层二结构 二结构工程
中、西单元8-10层二结构
主体验收
主体验收
工期
21 45 55 1 1 1 1 35 30 1 1 1 8 5 14 3 1 21 10 1