KV升压站工程电气监理实施细则

KV升压站工程电气监理实施细则一、前言为了保证KV升压站工程的质量和安全,有效监督工程施工过程中的电气工作,特制定本实施细则,以规范监理工作的流程和要求。
二、监理工作的职责1.监督施工方按照设计方案进行电气工程的施工,检查并验收电气设备和材料的质量,确保其符合相关国家标准和规范要求;2.检查施工方的电气工作计划和施工组织设计,确认其合理性和可行性;3.日常监督施工方的电气工作进展情况,及时解决工程中的技术问题,确保项目按时完成;4.建立工程质量档案,记录工程施工中的关键节点和质量控制要点,确保工程质量可追溯;5.提出合理的优化建议,提高工程施工的效率和质量,降低项目成本;6.协调相关参与方之间的沟通和协作,解决工程过程中的纠纷和问题;7.及时向业主汇报工程进展情况和存在的问题,并提供解决方案;8.参与工程的竣工验收,对工程施工过程中存在的问题提出整改要求。
三、监理工作的流程1.合同签订和工程准备阶段-在工程合同签订前,对工程的施工方案和设计方案进行审查,确保其合理性和可行性;-协助业主与施工方进行施工合同的签订,明确双方责任和权益;-参与工程筹备会议,了解工程的基本情况和目标,制定监理工作计划;-对施工方提交的施工组织设计和计划进行审查。
2.施工阶段-监督施工方按照设计方案进行电气工程施工;-检查施工方的材料采购和供货计划,确保材料的质量和供应能力;-每天进行现场巡查,检查电气工程施工的质量和进度;-定期组织施工方、设计方和监理方进行项目现场例会,共同讨论和解决工程中存在的问题;-对施工方提交的工程进度计划和质量控制方案进行审核和验收。
3.竣工验收和移交阶段-参与工程的竣工验收,并对工程中存在的问题提出整改要求;-协调施工方和业主进行工程的移交和交付手续;-进行工程质量评估,提供监理意见和建议。
四、监理工作的要求1.监理人员应具备相关电气专业的知识和经验,熟悉电气工程的施工规范和安全要求;2.监理人员应做到公正、客观、科学地履行监理职责,不受其他利益干扰;3.监理人员应及时报告工程中的问题和隐患,并提供解决方案;4.监理人员应与施工方和设计方保持良好的沟通和协作关系,共同推动工程的进展和高质量完成。
220kV架空输电线路工程监理实施细则

目录一、工程概况 (2)1、工程概况 (2)2、工程建设相关单位 (2)3、编制依据 (2)二、监理工作范围及服务内容 (3)三、监理工作目标 (4)四、监理工作方法及措施 (5)4.1质量控制 (5)4.2质量控制点的设置 (6)4.3安全及文明施工控制内容 (11)4.4进度控制措施 (12)4.5投资控制措施 (13)4.6监理方法 (13)五、施工过程中质量检查内容 (14)5.1基础分坑及开挖工程监理 (14)5.2基础浇制 (14)5.3基础养生及回填 (15)5.4杆塔组立 (15)5.5架线 (16)5.6接地装置 (17)一、工程概况1、工程概况1.1 工程名称双城万隆49.5MW风电项目1.2 工程建设地点:本输电线路起点为万隆风电场升压站,止于哈尔滨五家变电站,途经哈尔滨市双城区临江乡、农丰镇、公正乡、五家镇。
1.3 工程规模:本工程为双城万隆、杏山风电场220kV送出线路工程,线路亘长29.813千米,导线采用JL/G1A-240/30型钢芯铝绞线,光缆架设2根12芯OPGW光缆,全线93基铁塔基础,其中转角塔19基,直线塔74基,铁塔基础形式为灌注桩基础,基础混凝土量2858.16立方米。
1.4施工实施条件及自然环境分析双城万隆220kV线路工程位于哈尔滨市双城区境内,线路沿线主要地貌单元为松花江冲洪积平原及波状台地,平地90%,丘陵10%。
全线自然地面高程在131.1m~181.60m之间。
线路沿线松花江冲洪积平原地段上部地层主要为软塑状态、可塑状态的粉质粘土,稍密状态粉土及细砂,工程地质条件一般,可作为一般直线塔(荷载较小)天然地基持力层。
线路沿线波状台地地段勘探深度内多为硬塑状态的粉质粘土,仅少数低洼处为软塑、可塑状态的粉质粘土,硬塑状态的粉质粘土工程地质条件较好,可作为本工程杆塔天然地基持力层,软塑状态、可塑状态的粉质粘土工程地质条件一般,可作为一般直线塔(荷载较小)天然地基持力层。
35KV工程施工监理实施细则(新)

内蒙古华电二连浩特城市风光互补电场一期49.5MW风电场工程35kV集电线路工程监理实施细则内蒙古康远工程建设监理有限责任公司内蒙古华电二连浩特城市风光互补电场工程项目监理处二O一一年四月审批栏批准:年月日审核:年月日编制:年月日目录内蒙古华电二连浩特城市风光互补电场一期49.5MW风电场工程建设35KV集电线路工程(一)基础工程监理实施细则1 目的: (1)2 适用范围: (1)3 监理工作主要依据: (1)4 基础和接地工程设计特点: (1)5监理工作控制要点及目标值: (2)6. 监理工作方法: (5)7. 监理措施: (7)8 监理工作流程图: .........................................................................................内蒙古华电二连浩特城市风光互补电场一期49.5MW风电场工程35kV集电线路工程基础工程监理实施细则1 目的:为了对线路工程建设质量进行有效的监理,确保工程质量符合设计图纸文件、施工验收规范及本工程监理规划的要求,实现工程达标投产和创优,为业主提供满意的服务,特制订本细则。
2 适用范围:本细则适用于本工程35kV集电线路的基础和施工质量管理的监控管理。
3 监理工作主要依据:3.1 本工程建设《监理规划》;3.2 项目法人与各承包商签订的工程建设合同;3.3 已批准的工程初步设计、施工图设计及工程变更文件;3.4 GB50319—2005《建设工程监理规范》;3.5 《GBJ233—90》110~500kV架空电力线路施工及验收规范》;3.6 DL/T5168—2002《110~500kV架空电力线路工程施工质量及评定规程》;3.7 《输变电工程达标投产考核评定标准》3.8 《国家电力公司送变电优质工程评选办法》;3.9 本工程相关的原材料、产品的技术标准;3.10 GB50204-2010《混凝土结构工程施工及验收规范》;3.11 CECS40:《混凝土预制混凝土构件质量控制规程》;3.12 公司质量管理体系文件、《监理工作程序》、《监理工作制度》。
220kv输电线路工程建设监理实施细则

220kv输电线路工程建设监理实施细则实施细则是指对220kv输电线路工程建设监理的具体实施步骤和要求。
以下是220kv输电线路工程建设监理的实施细则:1. 监理人员的组织- 监理人员应具备相关的工程技术和管理经验,必须是注册监理工程师。
- 监理人员的人员构成应符合工程监理相关规定,包括主监理工程师、监理工程师和监理助理。
2. 施工前准备工作- 监理人员应与施工单位进行沟通,了解工程的施工准备情况。
- 监理人员应检查施工单位是否具备必要的施工许可证和资质。
3. 施工过程监理- 监理人员应按照工程设计和施工合同要求,对施工过程进行全程监理。
- 监理人员应检查施工单位的施工方案、施工图纸和材料等是否符合要求。
- 监理人员应每日对施工现场进行巡视,检查施工质量和安全生产情况。
4. 施工质量检查- 监理人员应按照施工图纸和规范要求,对施工质量进行检查。
- 监理人员应对施工单位的关键节点进行抽检,确保施工质量符合要求。
5. 安全生产监管- 监理人员应参与施工单位的安全生产管理,并监督施工单位履行安全生产责任。
- 监理人员应及时发现和纠正存在的安全隐患,并提出相应处理措施。
6. 施工变更管理- 监理人员应及时处理施工单位提出的施工变更申请,确保变更符合相关规定。
- 监理人员应核实施工变更对工程质量和安全的影响,并提出相应意见和建议。
7. 施工验收- 监理人员应参与施工单位的施工验收工作,并核实工程的合格性。
- 监理人员应编制施工记录和验收报告,并提出工程问题的处理意见。
8. 工程竣工管理- 监理人员应参与工程的竣工验收工作,并核实工程的竣工质量。
- 监理人员应协助施工单位编制工程竣工报告,并提出竣工验收意见。
以上是220kv输电线路工程建设监理的实施细则,通过严格遵守以上要求,可以确保工程的质量和安全。
35KV线路监理细则qian

朝阳协合万家营子风电场49。
5MW工程35KV集电线路监理实施细则批准人:审核人:编制人:南京苏安建设监理咨询有限公司朝阳协合万家营子风电场项目监理部二0一一年八月目录一、工程概况 (2)二、监理依据……………………………………………………………………。
3三、监理范围……………………………………………………………………。
3四、监理目标 (3)五、监理措施……………………………………………………………………。
4六、监理方法……………………………………………………………………。
8辽宁朝阳协合万家营子风电场49。
5MW项目工程监理处35kV集电线路监理实施细则一、工程概况:1、工程名称:朝阳协合万家营子风电场49。
5MW工程.2、工程建设地点:风电场位于辽宁省朝阳市建平县境内马场镇小北山丘陵地带,距离朝阳市区100多公里。
距离建平县城90多公里,距离内蒙赤峰市区100多公里,风电场区距马场镇10多公里。
3、工程建设规模:集电线路经过现场初步勘测确定,本工程架空线路共有A\B\C三条35kV 线路。
总长25.993km:其中单回路21。
107km,双回路4。
886km,塔基总数123基.导线型号:主干线采用规格为LGJ—150/25型钢芯铝绞线,地线型号为:GJ—35镀锌钢绞线。
绝缘子组合形式:直线塔,塔均采用FXBW—35/70型合成绝缘子。
耐张塔均采用FXBW—35/100型合成绝缘子。
4、工程计划工期:自2011年8月开工至2012年7月竣工。
5、参建单位:建设单位:辽宁朝阳协合万家风力发电有限公司设计单位:北京聚合电力工程设计有限公司辽宁省电力设计院监理单位:南京苏安建设监理咨询有限公司施工单位:江苏汇泽电力工程公司质量监督单位:辽宁省电力质检站6、工程特点:本期风电场工程规划装机容量49。
5M W,计划安装33台单机容量1500KW的风力发电机组。
烧锅营子风场区域内计划随本期万家营子风电场工程新建一座220KV的建北风场升压站,变电容量300MVA。
35kV直埋电缆工程监理实施细则(集电线路)

目录一、工程概况及特点 (2)1.1工程概况 (2)1.2工程建设相关单位 (2)1.3专业工程特点 (2)二、监理工作范围和目标 (2)2.1监理范围 (2)2.2监理工作目标 (3)三、监理工作依据 (3)四、关于质量、进度、投资、安全控制 (3)五、各项工作流程 (5)5.1施工监理工作流程 (5)5.2单位工程监理及质量控制流程 (5)5.3施工图会审流程 (5)5.4原材料构配件及设备质量签认流程 (6)5.5隐蔽工程、分项工程认签流程 (6)5.6工程量计量流程 (6)5.7质量事故处理流程 (7)5.8工程停、复工流程 (7)5.9工程设计变更流程 (8)5.10工程竣工验收流程 (8)六、质量控制方针 (9)6.1保证项目 (9)6.2基本要求 (9)一、工程概况及特点1.1工程概况双城万隆49.5MW风电项目位于黑龙江省哈尔滨市双城区北约30km的永胜乡以南2公里,风电场处于丘陵地带与冲积平原的交汇处,为平原风电场。
地表植被为荒地、耕地和林地,地势较为平坦,场地地面高程123.10~129.40m,区内皆为草甸、沼泽。
整个风电场区域面积约27km²。
双城万隆风电场拟建15台单机容量为3200kW的风力发电机组和1台单机容量为1500kW的风力发电机组,总容量为49.5MW,每台风机配置一台箱式变电站。
双城万隆风电场35kV集电线路工程分为A、B两个回路,其中A回路带8座风机(A线:W19、W15、W3、W14、W01、W02、W03、X12),线路总长6.278km,B回路带8座风机(B线:W04、W05、W06、W07、W08、W09、W10、W11),线路总长4.833km。
两条回路电缆直埋敷设长度共计14.21km。
本期35kV电缆线路中箱式变电站至线路终端(转角)塔采用FS-YJL Y63-26/35kV-1×95mm²铝芯电力电缆,塔上加35kV跌落式熔断器。
电网工程线路施工监理细则

来宾大区域电网工程220kV线路施工监理细则1、工程概况1.1本工程自来宾220kV枢纽开关站GIS终端-至来宾银海铝进线构架止,共3回220kV架空线路, I、II回线路路径长度约33.8km,其中电缆线路0.3km,单回架空线路29.5k、双回架空线路4km,导线截面2×400 mm2。
Ⅲ回线路路径长度约33.8km,其中电缆线路0.3km,单回架空线路33.5km,导线截面2×400 mm2。
架空导线采用2×JL/G1A-400/35钢芯铝绞线,地线采用两根,一根OPGW-120光缆和一根JLB35-120铝包钢绞线。
至广西铁合金电力架空线路目前只设计,不施工。
至来宾A电厂(双回路),B电厂(双回路)采用电缆敷设方式(电缆桥架及浅沟敷设)。
所用电缆为阻燃交联聚乙烯绝缘铝包防水聚氯乙烯护套电力电缆 ZR-YJLW03 220kV 单芯 1600 ,共13350米(A电厂)。
B电厂(双回路)单芯 2500 ,共13350米。
1.2铁塔采用三角形排列的猫头型直线塔和干字型转角塔。
I回线合计使用铁塔94基,新建单回路铁塔84基,(其中单回路直线塔57基,占67.8%;单回路耐张塔27基,占32.2%)。
双回路段(I、II回线共用)本工程新建双回路铁塔10基,(其中双回路直线塔3基,占30%;双回路耐II回线合计使用铁塔94基,新建单回路铁塔84基,(其中单回路直线塔54基,占64.3%;单回路耐张塔30基,占35.7%)。
注:双回终端塔在枢纽站与III线共用1基,在来宾铝与III线共用1基。
III回线合计使用铁塔93基,(其中单回路直线塔58基,占62.36%;单回路耐张塔33基,占33.67%;双回路终端塔2基,占2.15%)。
注:双回终端塔在枢纽站与II线共用1基,在来宾铝与II线共用1基。
塔位桩位桩号由现场确定,施工时,塔号应与桩号相对应。
系统示意图:1.3本线路交叉跨越较多,具体情况见下表1.4导线和地线均采用防振锤防振。
35KV集电线路监理细则

宁夏恒安监理公司风电项目专业监理实施细则编号:XX FD/HA-B-001-2012恒安监理风电工程35KV集电线路监理实施细则(项目监理机构名称)(加盖项目监理机构公章)年月宁夏恒安监理公司风电项目专业监理实施细则批准:(总监理工程师)年月日审核:(总监代表或专业组长)年月日编写:(专业监理工程师)年月日宁夏恒安监理公司风电项目专业监理实施细则目次1工程概况及特点 ·············································································································1.1工程概况 ··············································································································1.2工程特点 ··············································································································2编制依据 ······················································································································3监理目标 ······················································································································3.1质量控制目标 ········································································································3.2进度控制目标 ········································································································3.3造价控制目标 ········································································································4监理工作流程及重点工作 ·································································································4.1质量控制流程及重点工作 ·························································································4.2进度控制重点工作 ··································································································4.3造价控制重点工作 ··································································································5监理工作内容、措施及方法 ······························································································5.1作业人员控制 ········································································································5.2材料、设备控制 ·····································································································5.3施工机具、检测、计量器具的控制 ·············································································5.4作业方案(措施)的控制 ·························································································5.5作业过程控制 ········································································································5.6作业环境控制 ········································································································6质量通病防治专项措施 ····································································································7质量控制标准及验评 ·······································································································8附件·····························································································································附件1:质量控制流程图(略)························································································附件2:W、H、S点的设置(略) ···················································································附件3:有关监理过程控制、检查、记录表(略) ·······························································宁夏恒安监理公司风电项目专业监理实施细则35KV集电线路监理实施细则1工程概况及特点1.1 工程概况【编写说明】本部分描述的工程概况应在《监理规划》的描述基础上继续细化,侧重从专业层面多使用数据对本专业工程进行描述,而不能像监理规划中那样仅对工程总体情况作概述。
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
大唐齐齐哈尔碾子山风电场工程35kv集电线路工程监理实施细则黑龙江正信建设工程监理有限公司2011年3月20日目录1. 监理依据 (1)2. 监理范围 (1)3. 监理目标 (1)4. 质量控制 (1)4.1施工阶段质量控制程序 (1)4.2质量控制的一般原则 (3)4.3各分部工程质检内容及要求 (5)4.3.1 基础施工 (5)4.3.2 杆塔组立 (8)4.3.3架线施工 (9)4.3.4接地工程 (10)5 •进度控制 (10)6. 投资控制 (12)7. 安全控制 (12)8. 监理方法 (12)附表1:工程项目质量检查验收分级项目表 (14)附表2:输电线路工程施工项目监理质量管理点明细表…1 7-1835kv 集电线路工程监理实施细则(审批页)批准:(总监理工程师)______ 年_______ 月______ 日审核:(总监代表或专业组长)______ 年_______ 月______ 日编制:(专业监理工程师)______ 年_______ 月______ 日1 监理依据1. 1建设工程监理规范(GB50319- 2000)1. 2本工程建设监理规划1. 3国家和地方政府的法律、法规及电力行业的有关政策规定和技术规范、标准、规程验评标准等。
1. 4 “大唐黑龙江新能源开发有限公司”与“黑龙江正信建设工程监理有限公司”签订的《大唐齐齐哈尔碾子山风电场工程建设监理合同》及《大唐齐齐哈尔碾子山风电场工程建设监理合同〉补充协议》1.5已批准的施工图设计及设计修改通知单等有关设计技术文件和工程协调会等施工过程文件1. 6输变电工程达标投产考核评定标准(2000年版)1. 7电力线路线路工程110kV~500kV线路施工质量检验及评定标准1. 8 OPGV工程施工质量检验及评定标准工程1. 9政府批准的工程建设文件1. 10制造厂提供的商品说明书及安装工作指导书1. 11业主对工程质量、进度等提出的要求1. 12为实现大唐新能源开发有限公司对大唐齐齐哈尔碾子山风电场工程建成精品工程的目标,贯彻落实企业各项规章制度及强制性条文。
2监理范围35KV集电线路建设的设计、施工、调试、竣工验收及保修过程的质量、进度、投资、安全控制,工程建设合同管理、信息管理,协调甲乙方间的关系。
3监理目标3. 1质量目标:工程建设质量达到国家电力公司电网建设分公司关于“输变电工程创一流考核评定标准”的要求。
分项工程合格率100%分项工程创优率100%不发生重大质量事故。
实现工程高水平达标投产,创电力行业优质工程,争创国家级优质工程。
3. 2进度目标:认真管理和执行工程进度计划,在无不可抗拒因素影响前提下,保证工程阶段性目标的实现,线路施工总工期控制为194个工作日,确保工程按期竣工。
3. 3投资控制:按合同中条款中执行。
3. 4安全目标:贯彻“安全第一,预防为主”的方针,杜绝死亡事故和人身、设备、1________ __________________ L承包商申报承包商申报分项分部工程方案材料合格证、复验单T~rr整改监理审批j F合格下达开工令分部、分项工程施工施工试验及监理取样1各分项隐蔽工程自检1填报工程扌报验单不合格监理工程师现场检查及审查试验报告1F签发工程检验认可书、自检资料上签字附:1. 隐蔽单2. 预检单3. 质量保证资料4. 分项工程质量评定表交通等安全事故3. 5环保控制:工程开工前必须熟悉设计说明书和招标文件,了解、环保有关要求、制定相应的措施尽可能在工程竣工且恢复地表原貌。
力争作到绿色环保工程。
4. 质量控制:4.1施工阶段质量控制监理程序审批开工申请不合格加倍复试或换材料h不合格I不合格不合格4.2质量控制的一般原则421审查、熟悉施工图纸,积极参加施工图会审和技术交底,提出监理意见并形成纪要。
4.2.2对主要材料(铁塔、导地线、OPGW金具、绝缘子等)的质量控制主要通过审查供应商的资质(营业执照、企业资质证书、有关许可证)及到达现场的材料的检验。
对施工承包商报审的《主要材料、构配件及设备供应商资质报审表》及《工程材料/构配件/设备进场报审表》签署监理意见。
4.2.3对水泥、砂石及基础钢材(包括接地装置)的质量,检查供货单位的资质、产品合格证;审查承包商选择的对上述材料进行抽检复试的试验单位及实验人员的资质并认可,监督和见证施工承包商对上述材料抽检复试。
4.2.4把好材料进场验收的质量和数量关,督促施工承包商按质量验收规范和计量检测规定对材料的质量和数量进行验收(包括品种、规格、型号、数量、外观、出厂合格证明等),并检查施工承包商的验收记录。
不符合设计图纸规格要求或质量不合格的材料不得进场。
4.2.5对材料存储、保管与发放进行检查,确定是否造成质量下降或损失。
4.2.6对施工组织设计进行审查(其要点是质量保证体系、人员配备、施工技术方案、W点H点S点的划分确定、工机具、质量标准等),合格后予以批准。
4.2.7对施工技术方案措施进行审查(包括对施工质量的保证、施工安全可靠及技术的先进性等)后在《特殊施工技术方案措施报审表》上由监理工程师及总监理师会同签署审查意见。
4.2.8对施工承包商上报的《特殊工种/特殊作业人员报审表》及《主要测量计量器具/ 试验设备检验报审表》进行检查认可。
4.2.9由设计院提出的设计变更,经审查提出监理意见,上报业主批准后监督贯彻执行。
4.2.10由施工单位提出的设计变更,施工单位先与设计单位研究后,经监理单位进行核实签署意见并上报业主批准后监督贯彻执行。
4.2.11工程施工分项工程、分部工程及单位工程完成后监理人员进行预验收,对发现的缺陷或质量问题在《分项工程质量报验申请表》、《分部(子分部)工程质量报验单》及《单位(子单位)工程质量报审表》上签署监理意见,并附《监理工程师通知单》通知施工承包商进行整改。
整改后,施工承包商填报《监理工程师通知回复单》,监理人员进行复查并签署复查意见。
最后报请项目法人进行竣工验收。
4.2.12审查施工承包商的竣工资料。
4.2.13施工中发生质量事故,应由施工承包商先填报《工程安全/质量事故报告单》,经组织有关单位调查、分析研究后,填报《工程安全/质量事故处理方案报审表》,上述报告分别经设计单位、监理、项目法人审查认可后由施工承包商进行处理。
处理后填报《工程安全/质量事故处理结果报验表》经监理单位查验认可。
4214发生下列情况之一,且经监理工程师通知施工承包商整改无效时,总监理工程师可在征得业主同意后签发《工程暂停令》。
4.2.14.1 不经审查的设计图纸施工。
4.2.14.2 特殊工种无证操作4.2.14.3 发现不合格材料、半成品、构配件或机具设备有问题。
4.2.14.4 隐蔽工程未经验收签证。
4.2.14.5 上道工序未经检验签证,便进入下道工序。
4.2.14.6 发现不合格项及质量问题整改不力。
4.2.14.7 发生重大质量、安全事故、危及环保及职业健康。
4.2.15对停工的工程需要复工时,施工承包商应填报《工程复工申请表》经监理检查认可后,方可复工。
4.2.16 正式竣工验收4216.1 竣工验收报验条件•施工承包商已进行了“三级自检”;•施工承包商已按消缺方案对工程缺陷处理完毕并经复查合格;•竣工验收资料已全部整理准备齐全(签证齐全、编目齐全);•影响线路运行安全的通道障碍处理完毕。
如符合以上条件,施工承包商可填写《交付中间验收交接表》报监理单位审核,然后报项目法人审批。
4.2.16.2 验评办法•竣工验收由项目法人组织、质监中心站、监理单位、设计承包商、施工承包商及运行单位共同参加。
•检查验收分内业资料检查和外业现场检查;•质量检验和评定按GBJ23J 90《110-500kV架空送电线路施工及验收规范》和《110-500kV架空电力线路工程施工质量检验及评定标准》DL/T6168—2002进行。
•线路经竣工验收应符合已颁布的现行规范、验评标准,质监中心站对工程质量予以评定、项目法人、运行、监理、设计承包商、施工承包商等单位应在竣工验收书上签字4.2.17工程试运行阶段4217.1 督促施工承包商配合线路试验的进行,并及时处理各种突发事故4217.2 参与工程投产前的下列试验活动:•测定线路绝缘电阻;•核对线路相位;•测定线路参数的高频特性;•电压由零升至额定值;•以额定电压对线路进行冲击合闸试验;•带负荷试运行。
4.2.17.3 对投产前的各种试验进行签证。
4.2.18工程项目保修阶段监理。
4.2.18.1 审核施工承包商的《工程保修证书》;4.2.18.2 回访了解工程投运后保修阶段的质量状况;4218.3 对出现的质量缺陷,确定责任方;4218.4 督促施工承包商对施工保修期内的质量问题进行处理;4.2.18.5 对设计原因引起的质量问题,在经过项目法人与设计承包商认可后,协助处理;4.2.18.6 对保修期间发生的质量问题及修复结果,提出监理意见并以书面资料报工程有关单位。
4.3各分部工程施工质检内容及要求4.3.1 基础施工基础工程是送电线路中的重要隐蔽工程,因此也是监理工作的重点。
现场监理人员必须做到跟踪、旁站监理。
4.3.1.1 送电线路路径、塔位复测监理4.3.1.1.1 线路路径、塔位复测由施工承包商进行,监理工程师可随机抽检其结果。
当发现超过允许偏差时,请其重测。
4.3.1.1.2 基础分坑及开挖工程监理4.3.1.1.2.1 普通铁塔基础分坑时应注意设计给定的施工基面及坑位附近的地形条件,保证基础的边坡稳定431.122 分坑前施工技术人员应核对基础施工图与铁塔加工图的有关尺寸是否相符,尤其是插入式角钢基础。
分坑时要特别注意不等高腿,尤其是四腿皆不等高的基础间的高差及根开,依据施工承包商编制的分坑手册(或作业指导书)进行检查。
431.1.2.3 分坑时,基础中心桩位和控制桩必须明确、稳固,基础验收前不准丢失。
无论等高或不等高腿基础,都必须控制单腿及整基基础的扭转。
4.3.1.1.2.4 基础开挖时,监理工程师应根据不同的基础形式,不同的地质条件进行巡视检查,基坑开挖结束时进行验坑。
4.3.1.1.2.4.1 普通土坑开挖时应按土质留有偏坡,坑口周边及坑底留有操作余度。
基坑形状力求规整、坑底平坦。
坑外土应有组织堆放,不得随意扬弃、占用农田及破坏环境。
4.3.1.1.2.4.2 地下水位很高或流砂坑开挖时,应采取降低水位、挡土板、投石压砂等措施完成基坑开挖工作。
监理人员应强调安全施工,防止坑壁坍塌伤人。
当挖掘工作实在困难,不能达到要求坑深,施工承包商要求减少坑深或改变设计时,监理人员应视情况及时向总监理师报告。
在没有得到肯定答复时,施工人员、监理人员无权改变设计,现场停工待命。