台风 暴雨应急预案

合集下载

防台风暴雨应急预案完整版(通用12篇)

防台风暴雨应急预案完整版(通用12篇)

防台风暴雨应急预案完整版(通用12篇)(经典版)编制人:__________________审核人:__________________审批人:__________________编制单位:__________________编制时间:____年____月____日序言下载提示:该文档是本店铺精心编制而成的,希望大家下载后,能够帮助大家解决实际问题。

文档下载后可定制修改,请根据实际需要进行调整和使用,谢谢!并且,本店铺为大家提供各种类型的经典范文,如演讲稿、总结报告、合同协议、方案大全、工作计划、学习计划、条据书信、致辞讲话、教学资料、作文大全、其他范文等等,想了解不同范文格式和写法,敬请关注!Download tips: This document is carefully compiled by this editor. I hope that after you download it, it can help you solve practical problems. The document can be customized and modified after downloading, please adjust and use it according to actual needs, thank you!In addition, this shop provides you with various types of classic sample essays, such as speech drafts, summary reports, contract agreements, project plans, work plans, study plans, letter letters, speeches, teaching materials, essays, other sample essays, etc. Want to know the format and writing of different sample essays, so stay tuned!防台风暴雨应急预案完整版(通用12篇)防台风暴雨应急预案完整版范文(通用12篇)在生活中,有时会遇到无法预料的突发事故,为了可以及时作出应急响应,降低事故后果,往往需要预先编制好应急预案。

台风暴雨天应急预案5篇

台风暴雨天应急预案5篇

台风暴雨天应急预案5篇台风暴雨天应急预案【篇1】一、防台救灾工作指导思想:我校防台救灾工作,在鹿城区教育局统一领导下,以减轻国家财产损失和师生生命平安为目标,最大限度地降低损失,有效保障学校和师生的生命财产平安,维护学校正常的教学、生活秩序,本着预防为主、救助为辅的防台工作原则,依据国家的法律、法规和相关政策,结合本校实际,特制订防台风应急预案。

二、成立应急工作小组:学校防台领导小组:组长:副组长:组员:成员:全体老师三、防汛重点:1.教学楼、功能室、食堂、体育馆等建筑。

2.保证学校及周边的排水畅通。

3.加强台风、暴风雨、雷雨期间学生上、放学时的交通疏导。

4.提高师生对突发性天气变化(暴风雨、雷雨、雷电等)的自我保护能力。

四、台风前预备工作:1.思想预备:通过各种宣传工具,运用各种宣传形式,大力宣传防汛救灾学问,教育广阔师生,充分认识防汛抗灾抢险的重要意义。

坚决克服麻痹侥幸心理,树立“宁可信其有,不可信其无”的思想和“凡事予则立,不予则废”的观点,时刻预备,严阵以待。

2.组织预备:建立防台检查责任制,明确职责任务,做好台风前平安检查,对检查中发觉的问题、存在的隐患要提出处理意见。

高度重视防台救灾工作,加强防台值班和平安检查,落实各项防台措施,保证通讯畅通,并建立监督机制。

3.工作预备:加强对各类防洪、防汛、防风工作检查,发觉问题准时限期整改,高度重视台风期间学校平安工作,专心排查一切平安隐患,确保师生生命财产平安。

4.物资预备:依据可能发生的险情抢险要求,事先预备好抢险物资和器材,以备急用。

加强对重点防台部位的检查监督,在台风期间必需要有足够的排险抢修力气,有效的预防防汛突发事件。

五、防台救灾应急反应:1.学校接到上级政府发布做好紧急防台预备后,或依据台风情况即将发生灾情,立刻启动学校防台救灾系统,布置防灾工作,全面进入紧急状态做好各项应急工作。

2.依据本校防台救灾实际情况,组织实施应急反应工作预案,根据防台救灾机构设定,开展本校防台救灾工作,并开展救援抢险行动。

防范台风暴雨天气应急预案三篇

防范台风暴雨天气应急预案三篇

防范台风暴雨天气应急预案三篇【范文大全】在暴雨、雷电等恶劣天气下发生洪水和其他灾害时,为了尽量减少台风、暴雨可能造成的损失,必须提前制定暴雨应急预案,落实各项制定的措施。

哪些好的暴雨应急预案值得学习?下面是小编精心整理的防范台风暴雨天气应急预案三篇,仅供参考,大家一起来看看吧。

防范台风暴雨天气应急预案1一、总则:1、编制目的为切实做好防御台风的各项工作,及时处置因台风带来的各种灾害,最大限度地减省我施工现场的各种损失,维护正常施工,保障工程的顺利进行。

2、适用范围本预案适用于本标段施工范围内台风灾害的预防及应急处置。

3、工作原则台风灾害按施工区域实行属地管理,以各职能部门及施工队为主进行处置,并实行各职能部门对应施工队负责制。

各职能部门积极支持和指导、督促各对应施工队的应急处置工作。

要把台风灾害的预防放在突出环节,认真做好各项防范工作。

认真分析台风可能造成的大风和降雨,一旦发生险情,应迅速响应,及时启动本应急预案,组织人员力量全力抢险救灾。

4、工作重点(1)各基坑开挖施工现场的防水、防坑壁垮塌及滚石等;(2)施工道路的山体滑坡、崩塌等可能造成事故的灾害预防;(3)临时施工驻点和施工队驻点灾害来临前的人员设备转移;(4)各施工点材料库房的防洪排涝设施准备;(5)垂直运输设备、脚手架、施工用电安全防护措施;(6)各施工点及驻地在大风、大雨时期的生活保障;(7)台风、大雨天气的预测、预报和预警,及时向各施工队、施工现场发布台风预警信息。

二、防汛防台风灾害领导小组:项目部成立防汛防台风灾害领导小组,实行统一指挥,分部门对应各施工队进行具体负责。

防汛防台风灾害领导小组领导小组组长:副组长:成员:三、预防和预警机制:1、台风等灾害监控由项目部安全组负责台风、暴雨、风暴及山地灾害监控及信息收集,提前了解天气情况,及时汇总各施工现场基面、交通道路的各种信息上报领导小组。

2、各施工现场的安全巡检坚持各施工现场的安全巡检,将防风、防汛措施的`落实作为检查工作的重点,及时了解相关信息,对可能造成的危害的基面、道路提前安排人员进行处理,避免灾害发生时造成事故。

台风暴雨应急预案[优秀9篇]

台风暴雨应急预案[优秀9篇]

台风暴雨应急预案[优秀9篇]台风暴雨应急预案随着全球气候变化的影响,台风暴雨越来越频繁。

为了提高应对自然灾害的能力,必须制定完备的应急预案。

在此,我们就来谈一下《台风暴雨应急预案》。

一、拟定应急预案的重要性台风暴雨这种自然灾害,其往往具有突发性、破坏性、广泛性等特点。

因此,拟定应急预案就显得尤为重要,准确、及时、有效地应对灾害,是保障公共安全的关键步骤。

二、台风暴雨应急预案主要内容1.应急预案的制订者、颁布者和执行者,以及每个参与者的责任和义务;2.台风暴雨的等级及其威力、危险,以及在不同级别下要采取的措施;3.应急预案执行的指挥体系,包括总指挥部、各级指挥部和各责任部门的职能和权限;4.社会公众的应急行动计划,包括居民的疏散和救援;5.应急物资保障,包括食品、药品、水、衣物等必需品的存储和分配;6.应急医疗救援系统的组织和配备,包括保障医疗设备和消毒设备,组织医疗救援队;7.传媒应急预案,包括例如电视台、电台等媒体的使用和人员的协调;8.应急预案执行过程中的监督和评估,以及相关信息的统计和分析。

三、执行应急预案的具体步骤1. 组建指挥部和成员。

各级地方政府、单位必须设立领导亲自具有指挥权的危机管理领导小组,应指定合适数量的工作人员,明确责任范围,准备好必要设备和资源。

必须确保指挥部能够高效管理应急行动,包括快速汇聚和分配资源、执行任务、协调相关部门和群众行动。

2. 突发事件报告。

当获得突发事件的报告时,领导小组首先必须识别和评估事件的严重程度,确定使用应急预案的级别,采用适当的措施。

3. 突发事件响应。

根据应急预案,必须立即启动响应计划,并启动众包平台组织志愿者,调度相关单位的力量和资源,比如提供人员、设备等,确保及时响应以控制灾害。

4. 组织应急救援。

应急预案明确了必要的行动方案,根据突发事件的严重程度,或需别的行动方案,领导小组必须做好组织详细应蓝图,并要求所有支援和救援人员配备必要的装备和工具,以保障各自的安全和任务有效执行。

台风雷雨天气应急预案(精选5篇)

台风雷雨天气应急预案(精选5篇)

台风雷雨天气应急预案台风雷雨天气应急预案(精选5篇)在日常学习、工作抑或是生活中,有时会出现一些意料之外的事件或事故,为了减小事故造成的危害,就有必要提前进行细致的应急预案准备工作。

应急预案的格式和要求是什么样的呢?以下是小编整理的台风雷雨天气应急预案(精选5篇),仅供参考,欢迎大家阅读。

台风雷雨天气应急预案1为贯彻xx地区管理局《关于做好防汛防台工作的通知》精神和地方各级政府有关要求,结合《xx防汛防台抢险应急预案》,制定本预案,机场防止台风正面袭击应急预案。

本预案与《xx防汛防台抢险应急预案》配合使用。

一、工作原则按照台风到来前以“防”为主,台风到来时以“避”为主,台风过后以“救”为主的原则,有条不紊地开展好防止台风正面袭击的应急处置工作。

二、组织机构xx防止台风正面袭击的应急处置工作在xx防汛防台抢险指挥部的统一领导下进行。

三、各部门职责当接到台风袭击的的预警通知后,在xx防汛防台抢险指挥部的统一领导下,各部门要迅速行动,按照各自的职责,做好各项“防”、“避”、“救”的准备与实施工作。

各部门职责如下:1、机场办公室:在接到台风袭击的预警通知后,及时通报公司领导和机场各部门。

在请示公司领导同意后,启动预案,安排人员值守,承担xx防汛防台抢险指挥部办公室职责。

2、现场指挥中心:在接到台风袭击的预警和启动预案通知后,及时会同机场建设管理处、机务保障处和安检站,做好停场飞机、机坪设施设备的系留、加固或移除工作,并及时将有关情况报告xx防汛防台抢险指挥部办公室。

3、航务管理中心:在接到台风袭击的预警通知后,做好预达航班备降和在场航班转场的联络事宜;导航台站点的防风除险、排水加固等工作;做好应急通讯保障;按照局方要求落实机场航管防止台风正面袭击的预案内容。

4、机务保障处:在接到台风袭击的预警通知后,按照《xx处防风害应急预案》的要求,系留停场航空器,特种车辆要入库存放,对不能入库存放的特车应远离系留的航空器,停放在背风处,要设置好刹车并添加轮挡。

防台风暴雨应急预案完整版(精选5篇)

防台风暴雨应急预案完整版(精选5篇)

防台风暴雨应急预案完整版(精选5篇)防台风暴雨应急预案完整版(精选5篇)防台风暴雨应急预案完整版篇1一、目的在台风暴雨自然灾害来临前,事先做好各项应急准备工作,迅速有效控制局面并妥善处理,把台风暴雨可能造成的损失降到最低。

二、组织机构(一)防台风暴雨工作领导小组:总指挥:__副总指挥:成员:(上述领导小组的成员,正常情况不可请假,如有特殊情况请假,由总指挥安排其他人员顶岗)下设抢险小分队:(二)防台风暴雨工作小组:1、设备、物资组:组长:组员2、保卫组:组长:保安队长组员:全体保安队员3、综合信息组:组长:组员:三、职责(一)防台风暴雨工作领导小组的职责:1、负责防台风暴雨工作的组织、协调、监督、检查等全面工作。

2、总指挥__负责全面工作;副总指挥__协助总指挥做好防台风工作。

(二)各防台风暴雨工作小组的职责:1、设备、物资组:(1)负责落实公司现场的建筑物及设备设施的加固、防护、排水防涝工作。

(2)负责撤离、转移露天及低洼地方的设备。

(3)负责电力设备、设施的正常运行检查,确保安全。

(4)每年雨季来临前负责检查四周排水沟是否通畅和检查透明瓦是否超过使用期限,有无老化。

检查风球是否牢固。

2、保卫组:(1)负责厂区内安全保卫工作,做好固定岗和巡逻岗的应急抢险工作。

(2)负责落实抢险必备物资的准备工作。

(3)负责协助防台风、暴雨撤离的检查工作。

(4)负责对检查出的安全隐患进行处理工作。

(5)负责抢险工作中的人员救护工作。

3、综合信息组:(1)通过新闻、电视、电台、报纸、网络、气象台等在收到上级或相关单位的台风暴雨通知后,立即上报公司领导和总指挥,并传达到各部门。

(2)组织召开防台风指挥部成员会议,指挥部成员应在10分钟内到达会议现场,由总指挥安排落实抗台风暴雨的应急措施,并启动相应的应急预案。

(3)通知相关部门,由相关部门负责人通知驻外仓库人员做好防范。

(4)负责及时收集最新台风暴雨预警信息,关注台风最新动态,向总(副)指挥报告。

台风天气应急预案12篇

台风天气应急预案12篇

台风天气应急预案12篇(经典版)编制人:__________________审核人:__________________审批人:__________________编制单位:__________________编制时间:____年____月____日序言下载提示:该文档是本店铺精心编制而成的,希望大家下载后,能够帮助大家解决实际问题。

文档下载后可定制修改,请根据实际需要进行调整和使用,谢谢!并且,本店铺为大家提供各种类型的经典范文,如工作总结、演讲致辞、规章制度、应急预案、心得体会、合同协议、条据书信、教学资料、作文大全、其他范文等等,想了解不同范文格式和写法,敬请关注!Download tips: This document is carefully compiled by this editor. I hope that after you download it, it can help you solve practical problems. The document can be customized and modified after downloading, please adjust and use it according to actual needs, thank you!Moreover, our store provides various types of classic sample essays, such as work summaries, speeches, rules and regulations, emergency plans, insights, contract agreements, documentary evidence, teaching materials, essay summaries, and other sample essays. If you would like to learn about different sample formats and writing methods, please pay attention!台风天气应急预案12篇台风天气应急预案篇1沿海地区比较容易受到台风暴雨袭击。

防台风暴雨安全的应急预案范文(通用6篇)

防台风暴雨安全的应急预案范文(通用6篇)

防台风暴雨安全的应急预案范文(通用6篇)防台风暴雨安全的应急预案范文(通用6篇)在学习、工作或是生活中,有时会发生突发事件,为了避免造成重大损失和危害,常常需要预先准备应急预案。

我们该怎么去写应急预案呢?下面是小编帮大家整理的防台风暴雨安全的应急预案范文(通用6篇),仅供参考,希望能够帮助到大家。

防台风暴雨安全的应急预案1一、成立防大风、暴雨等恶劣天气应急领导小组二、指导思想:为了建立学校安全应急处理机制,迅速、及时、积极的开展各项处置工作,最大限度的降低损失,有效保障师生及学校生命财产安全,切实维护教育稳定和社会安定。

三、应急预案(一)台风、雷暴雨等恶劣天气来临之前1、注意天气预报,时刻关注台风、雷暴雨等异常天气的动向,随时向全校师生发布台风、雷暴雨等异常天气状况(许佳负责)。

2、加强巡查排除安全隐患(马冬云负责)。

3、关紧门窗,将阳台、窗台、屋顶等高处易坠落物取下或加固①由俞芳监督,②教师办公室由本周行政值周负责监督,③教学楼由陈美负责监督。

4、班主任加强对学生防台风、暴雨、雷电等异常天气知识的教育(各班主任负责)。

(二)防台风、雷暴雨等恶劣天气具体措施1、遇到下课,应延迟下课,由当时的课任教师联系班主任共同负责维持班级学生秩序,当确定天气好转时方可下课。

2、如果放学时,台风、雷暴雨仍旧不停,学校允许家长有秩序地进入班级接走孩子,班主任应在班级中并做好家长签字工作。

(行政值周和值周教师负责督促)3、学生在放学或放学途中遭遇雷暴雨等恶劣天气,应就近寻找避险处,等天气好转后再回家或上学,如有条件,可事先与家长或班主任联系(由班主任提前提醒学生)。

4、在家未上学时,如遇台风、雷暴雨,学生可以推迟上学时间,直至天气好转,家长可与班主任联系具体事宜(班主任电话让每个学生知道),班主任并将学生到校情况报学校安全保卫处。

(俞芳负责)5、如果有学生在校,行政值周安排好到校学生的看护工作。

让学生进入房屋避险,把人员活动限制在安全区域内。

  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

防汛、防洪应急预案
一、工程概况
美丽之冠珠海横琴梧桐树大厦项目,位于珠海市横琴岛国家级开发区中的口岸服务区。

项目所在区域北侧为横琴岛中心商务区,南侧为教育科研区,西侧为综合服务区,东侧与澳门特别行政区隔海相望。

项目总用地面积为25079.31平方米,总建筑面积168738.96平方米,建筑总高度188.8米。

地上40层,地上建筑面积为100317.31平方米,主要功能为商业、办公楼、七星级酒店,其中在10层和26层设置避难层;地下室建筑面积为68421.65平方米,地下三层(局部有夹层)。

二、编制目的
在台风暴雨自然灾害来临前,事先做好各项应急准备工作,迅速有效控制局面并妥善处理,把台风暴雨可能造成的损失降到最低。

在台风、暴雨恶劣天气过后能迅速恢复生产,采取有效措施保证施工质量、施工工期。

三、编制背景
5月至6月是雨季的前汛期。

珠海市高空处于西太平洋副热带高压脊的西北侧,常受高空低压槽影响,多雷暴、骤雨等强对流天气,雨量增多。

盛夏,从7月至10中旬,为台风盛行期。

受热带天气系统影响,每年在南海和西太平洋形成的热带气旋(热带低压、台风的总称),有时会袭击和影响珠海市,并常因台风暴雨而成灾。

1)台风
台风是危害最大的灾害性天气。

珠海市濒临南海,除1--4月外,其他月份均可能受西太平洋和南海台风的影响。

影响全市的台风,不仅次数多,季节长,且强度较大。

台风袭击时,所经之处,往往出现狂风暴雨、巨浪和暴潮。

2)暴雨
日降雨量50.0--99.9毫米的称为暴雨。

珠海全年有两个明显的雨季:4—6月为前汛期雨季,降雨主要是受锋面低槽、低空急流、低涡或高空切变线等天气系统影响所致,平均总降雨量840毫米,占年降雨量的42%;7-10月为后汛期雨季,降雨主要受带热气旋等热带天气系统影响所致,平均总降雨量946毫米,占年降雨量的47%。

由于后汛期的台风雨强度大、降雨量多,一次降雨过程可达200-300毫米,极易造成局部洪涝。

根据上述资料,考虑到本工程跨年度施工,特编制此台风暴雨应急预案。

四、预案的启动?
收到珠海市气象台发布台风、暴雨预警信号,本预案正式启动。

五、组织机构
1、防台风暴雨工作领导小组:?
组??长:樊为民
副组长:沈建?
成??员:严伟飞、郭志福、杨磊、张平、袁忠飞、肖运龙、沈忠?、曹蒙
(上述领导小组的成员由经理室全体人员、各部门负责人组成,如有岗位调整,以防台风暴雨预案启动时的岗位负责人自动顶岗,无须另行改动此文件)
2、防台风暴雨工作小组:?
1)工程组:?
组长:张平
组员:施工科全体员工?
2)安全、设备组:?
组长:沈建
组员:安全科、设备科全体员工?
3)后勤保安机动组:?
组长:俞水洪??
组员:全体保安队员?
3、项目部应急预案小组主要人员联系方式:
六、职责
1、防台风暴雨工作领导小组的职责:
1)负责防台风暴雨工作的组织、协调、监督、检查等全面工作。

2)总指挥组长樊为民(副总指挥组长曹成新)负责全面指挥工作。

?
2、各防台风暴雨工作小组的职责:?
1)工程组:
a)负责所辖工作范围内的业主、监理、施工等单位的防台风暴雨工作的布置、
检查、协调等全面工作。

b)负责落实施工现场的建筑物及设备设施的加固、防护、排水防涝工作。


责施工现场的人员撤离的组织、检查、落实等工作。

c)负责组织一支由施工单位组成的紧急抢险机动小组随时待命,作为处理紧
急事件的预备队,由领导小组直接调遣。

2)安全、设备组:
a)明确防台风暴雨工作的重点工作内容,上报领导小组。

b)负责落实安全、设备科所辖施工现场的建筑物及设备设施的加固、防护、
排水防涝工作。

c)负责安全、设备科所辖施工现场的人员撤离的组织、检查、落实等工作。

3)后勤、保安机动组:
a)负责辖区内治安保卫工作,做好固定岗和巡逻岗的应急调整工作。

b)负责落实抢险必备物资的准备工作。

c)负责生活、办公区内防台风暴雨加固、撤离工作的验收和检查工作。

d)负责协调相关工作小组,对检查出的安全隐患进行处理工作。

e)负责抢险工作中的人员救护工作。

f)负责及时收集最新台风暴雨预警信息,宣布预案的启动与终止。

g)汇总各工作小组上报的防台风暴雨的重点部位,上报工作领导小组。

h)负责行政、后勤的组织、协调、检查及督导。

i)负责解决撤离人员及工作人员的食、宿安排。

j)负责行政车队的车辆调度,安排好救护的应急用车。

?
k)联系医疗救护机构,协调安排医务人员。

?
l)负责做好各工作小组的协调工作。

?
m)负责台风暴雨过后的人、财、物的清点工作。

?
n)负责保险的理赔工作。

七、工作程序
1、后勤行政科、安全科在收到上级或相关单位的台风暴雨通知后,立即上报有关
领导并传达到各部门。

2、后勤行政科、保安大队、施工科、财务科、设备科及相关部门成立防台风暴雨
工作小组,经理室值班领导任总指挥。

各部门负责人组织成立应急小组,带领本部门落实抗台风暴雨的应急措施。

3、全体员工能识别台风暴雨信号及含义,各部门在接到通知后,应立即组织本部
员工做好防风抗洪的预防工作。

4、后勤行政科安排好救护或应急用车,医务室负责抢救受伤人员。

5、若台风暴雨信号中出现大风增强信号、台风红色信号或红色暴雨预报信号,保
安大队应组织15人以上的义务抢险队,在岗位待命,随呼随到,以作为抗台
风暴雨的机动力量。

6、项目经理部领导根据台风暴雨的大小,决定是否提前停工。

若提前停工,应做
好施工现场的安全防护工作,施工材料、机械有序堆放。

7、台风暴雨过后,由后勤行政科协调,财务科应拍照取证,清点损失的物资,并
负责办理保险索赔事宜。

8、台风暴雨过后,施工科、安全设备科组织人员抢修损坏的现场施工部位,并及
时恢复安全生产。

9、对防台风暴雨过程中表现突出的部门及人员,按照《员工奖惩条例》给予表彰
奖励。

对工作严重失职,造成重大损失和严重后果,按有关规定追究责任。

八、安全生产防护措施
1、生活、办公区
1)生活、办公区板房采用珠海信誉和质量都较好的雅致板房,基础作了400*400
的钢筋混凝土地梁,板房顶部采用钢管压顶、粗铁丝斜拉与地锚钢筋连接处
理,具有抵抗十级台风的能力。

2)平时由后勤、保安部门对生活、办公板房进行定期检查,及时加固受损部位。

3)对板房的压顶定期派人检查,拉紧铁丝,做到台风来时人员不慌不乱。

4)生活、办公区在建设时已设计、施工了排水管道及排水沟,排水流向明确。

5)生活、办公区的排水设施定期派人检修,保证排水沟的畅通,能及时排除暴
雨带来的积水。

2、施工现场
1)高压线采取搭设钢管加毛竹架全封闭措施,配电房为砖砌、顶部现浇钢筋混
凝土板。

基坑底部设置盲沟,周边设集水坑,现场备好大功率水泵,及时将
雨水有序抽排。

2)塔吊基础设计时进行了抗倾覆验算,上部塔身按照塔吊说明书要求设计附
墙,收到气象部门发布的台风、暴雨警报后,应停止塔吊等高空危险作业。

3)场地四周围护,在台风、暴雨来临前,对围墙进行两侧斜拉的临时加固措施,
以抵抗台风的袭击。

4)本工程脚手架采用落地架结合部分悬挑架,进行风载验算,对超过20m高度
进行专家论证后再施工。

5)对脚手架、塔吊、施工电梯进行定期检修,做到承受台风、暴雨后将损失降
到最低限度。

6)现场模板、钢管、扣件平时做到不乱堆乱放,以防暴雨袭击后,造成材料的
丢失。

7)对加工好的钢筋要用塑料布覆盖,防止雨水对钢筋产生锈蚀,堆放钢筋用木
方、钢材支垫,防止积水浸泡钢筋。

8)对气象部门发布台风、暴雨警报后,准备浇筑混凝土的部位按实际情况调整
浇筑时间,避开暴雨期间浇筑混凝土,影响浇筑质量。

9)施工场地内有明确的排水流向,准备好抽水设备,以应对暴雨产生的现场积
水现象。

10)台风、暴雨过后,立即组织人员进行清理,恢复生产。