多层民用建筑框架结构施工组织设计
多层民用建筑框架结构施工组织设计
目录
第一章: 工程概况···············································( 1)
1.1 现状概况················································( 1)
1.2 布局规划················································( 1)
1.3项目部组织机构及职责·····································( 3)
第二章: 施工部署···············································( 9)
第三章: 主要施工保证措施······································( 10)
3.1内业准备················································( 10)
3.2轴线引测················································( 10)
3.3新上岗人员进行培训到位··································( 10)
第四章: 工程测量与施工放线···································( 12)
4.1 测量放线的基本要求·····································( 12)
4.2 施工测量前的准备工作···································( 13)
第五章: 施工方法及技术措施···································( 14)
5.1 三合土场地·············································( 14)
5.1.1施工方法·············································( 14)
5.1.2技术措施·············································( 14)
5.2砼场地·················································( 14)
5.3花岗岩广场··············································( 15)
5.4 铺装场地···············································( 16)
5.5 人工挖基坑槽···········································( 16)
5.6 土方回填工程···········································( 16)
5.7 砌砖工程···············································( 17)
5.8 砌石工程···············································( 17)
5.9 钢筋砼工程·············································( 17)
5.10 外墙装饰面施工········································( 19)
5.11 给水管道安装··········································( 19)
5.12 排水管道安装··········································( 20)
5.13 草坪灯、投光灯、水下灯安装······························( 20)
5.14 地埋灯及庭院灯安装····································( 21)
5.15 绿化工程··············································( 21)
第六章: 质量保证措施···········································( 23)
6.1 各项质量管理制度·······································( 23)
6.2质量通病防治措施·············································( 26)
6.3 季节性施工技术措施·····································( 26)
6.3.1 雨季施工技术措施·····································( 26)
6.3.2 高温季节施工技术措施·································( 27)
6.4 确保工期组织措施·······································( 27)
6.5 安全生产技术措施及消防保证措施·························( 28)
6.6 文明生产、文明施工措施··································( 33)
6.7 环保措施···············································( 34)
6.7.1 环境管理控制点·······································( 34)
6.7.2 环保保护措施·········································( 37)
6.8 HSE管理体