箱式变压器检修检测方案及流程英文回答:Box-type transformer maintenance and testing plan and procedure.Box-type transformers are critical components in electrical systems, and regular maintenance and testing are essential to ensure their proper functioning andreliability. In this article, I will outline a comprehensive maintenance and testing plan for box-type transformers, including the necessary steps and procedures.1. Visual Inspection:The first step in the maintenance and testing processis a visual inspection of the transformer. This involves checking for any physical damage, loose connections, oil leaks, and signs of overheating. I will carefully examine the transformer's exterior, including the cooling system,bushings, and tap changer, to identify any potential issues.2. Oil Analysis:Next, I will conduct an oil analysis to assess the condition of the transformer's insulation system. This involves taking oil samples from the transformer andsending them to a laboratory for testing. The analysis will determine the presence of any contaminants, moisture content, and the overall condition of the insulation. Based on the results, further actions such as oil filtration or replacement may be required.3. Electrical Testing:Electrical testing is crucial to evaluate the transformer's performance and identify any electrical faults. This includes conducting tests such as turns ratio test, winding resistance test, insulation resistance test, and power factor test. These tests provide valuable information about the transformer's electrical characteristics and help identify any potential issues thatmay affect its operation.4. Dissolved Gas Analysis:Dissolved gas analysis (DGA) is a powerful tool for detecting and diagnosing potential faults in transformers. By analyzing the gases dissolved in the transformer oil, it is possible to identify the presence of certain fault types such as overheating, partial discharge, or arcing. DGA can help in early detection of faults and prevent major failures.5. Mechanical Inspection:In addition to electrical and oil analysis, a thorough mechanical inspection is necessary to ensure the transformer's mechanical components are in good condition. This includes checking the condition of the cooling system, fans, pumps, and other mechanical parts. Any signs of wear, damage, or abnormal noise should be addressed promptly.6. Functional Testing:Lastly, functional testing involves simulating various operating conditions to ensure the transformer performs as expected. This includes testing the tap changer, protective relays, and other control systems. Functional testing is essential to verify the transformer's overall functionality and ensure it can handle different load conditions.中文回答:箱式变压器检修检测方案及流程。

箱式变电站验收标准

箱式变电站验收标准

箱式变电站验收标准一、前言。

箱式变电站是一种集变电设备、控制设备、安全设备和配电设备于一体的完整装置,广泛应用于城市、乡村、工矿企业等各种场所。

为了保证箱式变电站的安全运行和可靠性,对其进行验收是非常重要的。

本文将就箱式变电站验收标准进行详细介绍,以期为相关人员提供参考。

二、验收前准备。

1. 箱式变电站应符合国家相关标准和规定,设备应具备相应的合格证书和产品质量检验报告。

2. 验收人员应对变电站的技术文件和工程设计文件进行认真审查,了解箱式变电站的主要技术参数和性能要求。

3. 确保箱式变电站的安装、调试和运行记录齐全,设备运行稳定,无异常情况。

三、验收内容。

1. 外观检查,箱式变电站外观应无明显损坏,箱体表面应平整、无明显变形和腐蚀。

门、窗、通风口等应完好无损,密封性良好。

2. 内部设备检查,检查箱式变电站内部设备的接线是否牢固、电缆是否整齐有序、开关设备是否灵活可靠、绝缘电阻是否符合要求等。

3. 电气性能检查,对箱式变电站的绝缘电阻、电气接地电阻、绝缘电压强度、保护装置动作试验等进行检查,确保其符合国家标准和设计要求。

4. 运行性能检查,对箱式变电站的运行参数、开关操作、保护动作等进行检查,确保其性能稳定可靠。

5. 安全保护检查,对箱式变电站的安全保护装置进行检查,确保其在各种异常情况下能够及时、可靠地保护设备和人员安全。

四、验收标准。

1. 外观检查合格标准,箱式变电站外观无明显损坏,箱体表面平整、无变形和腐蚀,门、窗、通风口完好无损,密封性良好。

2. 内部设备检查合格标准,设备接线牢固,电缆整齐有序,开关设备灵活可靠,绝缘电阻符合要求。

3. 电气性能检查合格标准,绝缘电阻、电气接地电阻、绝缘电压强度、保护装置动作试验符合国家标准和设计要求。

4. 运行性能检查合格标准,箱式变电站的运行参数、开关操作、保护动作稳定可靠。

5. 安全保护检查合格标准,安全保护装置在各种异常情况下能够及时、可靠地保护设备和人员安全。

箱变检验规范

箱变检验规范

验)高/低压预装式变电站(欧式箱变)技术规范箱变试3.1 技术参数3.1.1 系统额定电压: 10kV ,最高电压: 12 kV ;3.1.2 变压器高压侧额定电压:城市变或靠近电源侧宜选 10.5 土 5%kV ,远离电源侧或农村变宜选 10 土 5%kV ;低压侧额定电压: 0.4 kV 。

3.1.3 额定频率: 50Hz3.1.4 额定热稳定电流及时间( kA/s ):高压回路 20kA/3 低压回路 30kA/1 ;接地回路20kA/3 。

3.1.5 额定动稳定电流及时间(峰值, kA ):高压回路 50 ;低压回路 63 ;接地回路 36 ;3.1.6 工频耐压 (kV) :高压回路 42 ;高压断口 48 ;低压回路 2.5 ;变压器 35 ;控制与辅助回路: 2.0 。

3.1.7 雷电冲击耐压 (kV) :高压回路 75 ;高压断口 85 ;低压回路 6 。

3.1.8 噪音水平:变压器容量 1250kVA 以内不大于 50dB 。

(除特别注明外)3.1 . 9 箱壳防护等级:不低于 IP3X ;箱体颜色军绿(除特别注明外)。

3.10 允许温升高压设备的允许温升值见 GB/T11022-1999 规定;变压器的允许温升值见 GB1094 或 GB6450 规定;低压设备的允许温升值见 GB7251 规定;3.11 1000kVA 及以下变压器采用高压负荷开关 - 熔丝保护, 1250kVA 及以上变压器采用高压断路器保护。

3.12 最大允许尺寸(深×宽×高: mm ): 630kVA 及以下变压器终端型3200 × 2000 × 2500 ,环网型3200 × 2500 × 2500 ; 1250 - 8000kVA 变压器终端型 3400 × 2300 × 2600 ,环网型3400 × 2700 × 2600 。

箱式变电站质量检验规章材料

箱式变电站质量检验规章材料

预装式箱式变电站检验规程(编号:GL/DY-QES-C51-2015)宁夏大有电器有限公司二零一五年预装式箱式变电站检验规程1适用范围本规程适用于本公司生产的预装式箱式变电站出厂检验标准。

2执行标准GB/7251.1-2013 《低压成套开关设备》GB/15576- 2008 《低压成套无功功率补偿装置》GB/17467- 2010 《高压/低压预制式变电站》3引用标准GB/10233- 2005 《低压成套开关设备基本调试方法》GB/3906- 2006 《3.6-40.5KV交流金属封闭开关设备和控制设备》GB/11022- 2011 《高压开关设备和控制设备标准》GB/700- 2006 《碳素结构钢》GB/4208- 2008 《外壳防护等级的分类》《本地供电部门验收规范》4箱式变电站外形检查4.1箱体成型后,应符合图纸要求,几何误差见下表。

表1对角线误差(单位:mm)表2外形尺寸及允许偏差(单位:mm)4.2箱式变电站的所有开孔应按图纸要求和《冷加工通用工艺规程》(编号:DY-01-GY)进行并满足箱式变电站自身结构及使用要求。

4.3箱式变电站的骨架应按《焊接通用规程》(编号:DY-02-GY)进行,框架焊接要牢固,不得漏焊,焊缝平整光洁、没有焊穿裂缝、溅渣气孔。

4.3.1吊柱是箱式变电站工艺重点,必须焊接牢固,焊口要有一定深度焊口焊满突出、不得有溅渣,以防在起吊过程中脱落。

4.4箱式变电站的箱体、柜体及其零部件的金属表面的涂覆加工工艺应按《喷涂工艺规程》(编号:DY-03-GY)进行,在柜体和箱体一米处观察不应有明显的色差和反光。

4.5组装式箱式变电站,对接处的立缝,水平公差值应一致,连接孔偏差应不大于1mm,对接处应能保持整体性能。

4.6变压器室内应对母线、电缆连接洞口进行封堵,达到防误入、防鼠、防火的要求。

5 高、低压配电装置的检查5.1一般检查5.1.1所有电器设备及部件、元器件要符合图纸及相关技术要求的规定。

箱式变电站检验规章制度

箱式变电站检验规章制度

预装式箱式变电站检验规程箱式变电站外形检查4.1 箱体成型后,应符合图纸要求,几何误差见下表。

表1对角线误差(单位:mm)表2外形尺寸及允许偏差(单位:mm)4.2 箱式变电站的所有开孔应按图纸要求和《冷加工通用工艺规程》(编号:DY-01-GY )进行并满足箱式变电站自身结构及使用要求。

4.3 箱式变电站的骨架应按《焊接通用规程》(编号:DY-02-GY )进行,框架焊接要牢固,不得漏焊,焊缝平整光洁、没有焊穿裂缝、溅渣气孔4.3.1 吊柱是箱式变电站工艺重点,必须焊接牢固,焊口要有一定深度焊口焊满突出、不得有溅渣,以防在起吊过程中脱落。

4.4 箱式变电站的箱体、柜体及其零部件的金属表面的涂覆加工工艺应按《喷涂工艺规程》进行,在柜体和箱体一米处观察不应有明显的色差和反光。

4.5 组装式箱式变电站,对接处的立缝,水平公差值应一致,连接孔偏差应不大于1mm,对接处应能保持整体性能。

4.6 变压器室内应对母线、电缆连接洞口进行封堵,达到防误入、防鼠、防火的要求。

5 高、低压配电装置的检查5.1 一般检查5.1.1 箱式变电站的供配电系统应正确并符合设计要求,图纸产品保持一致。

5.1.2 所有电器设备及部件、元器件要符合图纸及相关技术要求的规定。

5.1.3 箱式变电站的供配电系统应正确并符合设计要求,图纸产品保持一致。

5.1.4 高、低压成套开关柜、低压成套无功功率补偿装置的导线截面和颜色、母线的制作应符合《大线制作通用工艺规程》(编号:DY-05-GY )、《二次线配置通用工艺规程》(编号:DY-07-GY )和《母线制作通用工艺规程》(编号: DY-06-GY )的要求。

5.1.5各电路导线端头的标识应与提供的原理图、接线图相一致5.1.6 计量柜的计量互感器、电度表等必须按供电部门的验收要求备案,同时计量柜的铅封或明挂锁扣必须安全可靠。

5.1.7 所用变压器规格、型号符合设计要求,安装符合规范及制造厂要求;油浸式变压器附件完好无损,变压器无渗漏油、油位正常,无锈蚀,油漆完好,相位标志正确;手动调压装置正常;所有密封良好,瓷件无损伤、裂纹。

箱式变压器检修检测方案及流程

箱式变压器检修检测方案及流程

箱式变压器检修检测方案及流程英文回答:As an electrical engineer with experience in transformer maintenance and testing, I can provide you with a comprehensive plan and procedure for inspecting and testing box-type transformers.1. Visual Inspection:The first step in the inspection process is a visual examination of the transformer. This involves checking for any signs of physical damage, such as cracks, dents, or corrosion. Additionally, I will inspect the cooling system, including fans and radiators, to ensure they are clean and in good working condition.For example, during a recent inspection, I noticed a small crack on the transformer casing. This indicated a potential issue with the insulation, which required furthertesting.2. Insulation Resistance Test:The insulation resistance test is conducted to measure the integrity of the transformer's insulation system. This test helps to identify any insulation breakdown or moisture ingress. I will use a megohmmeter to measure the resistance between the transformer windings and the ground.For instance, I performed an insulation resistance test on a transformer and found that the resistance value was below the acceptable limit. This indicated a potential insulation problem, which required further investigation.3. Turns Ratio Test:The turns ratio test is performed to ensure that the transformer is operating at the correct voltage ratio. This test involves comparing the ratio of the primary to secondary windings by applying a known voltage to the primary winding and measuring the resulting voltage on thesecondary winding.For example, during a turns ratio test, I discovered that the measured ratio was outside the acceptable range. This indicated a potential issue with the transformer's winding configuration.4. Winding Resistance Test:The winding resistance test is conducted to measure the resistance of the transformer windings. This test helps to identify any loose connections or faulty windings. I will use a low-resistance ohmmeter to measure the resistance of each winding.For instance, during a winding resistance test, I found that the resistance of one of the windings wassignificantly higher than the others. This indicated a potential problem with that particular winding.5. Dielectric Withstand Test:The dielectric withstand test is performed to assess the insulation strength of the transformer. This test involves applying a high voltage to the transformer for a specified duration to ensure that it can withstand the rated voltage without breakdown.For example, during a dielectric withstand test, I observed that the transformer experienced a breakdown at a voltage lower than the rated value. This indicated a potential insulation issue that needed to be addressed.中文回答:作为一名有着变压器检修和测试经验的电气工程师,我可以为您提供一份全面的箱式变压器检修和测试计划和流程。

箱变检验规范

箱变检验规范

验)高/低压预装式变电站(欧式箱变)技术规范箱变试3.1 技术参数3.1.1 系统额定电压: 10kV ,最高电压: 12 kV ;3.1.2 变压器高压侧额定电压:城市变或靠近电源侧宜选 10.5 土 5%kV ,远离电源侧或农村变宜选 10 土 5%kV ;低压侧额定电压: 0.4 kV 。

3.1.3 额定频率: 50Hz3.1.4 额定热稳定电流及时间( kA/s ):高压回路 20kA/3 低压回路 30kA/1 ;接地回路20kA/3 。

3.1.5 额定动稳定电流及时间(峰值, kA ):高压回路 50 ;低压回路 63 ;接地回路 36 ;3.1.6 工频耐压 (kV) :高压回路 42 ;高压断口 48 ;低压回路 2.5 ;变压器 35 ;控制与辅助回路: 2.0 。

3.1.7 雷电冲击耐压 (kV) :高压回路 75 ;高压断口 85 ;低压回路 6 。

3.1.8 噪音水平:变压器容量 1250kVA 以内不大于 50dB 。

(除特别注明外)3.1 . 9 箱壳防护等级:不低于 IP3X ;箱体颜色军绿(除特别注明外)。

3.10 允许温升高压设备的允许温升值见 GB/T11022-1999 规定;变压器的允许温升值见 GB1094 或 GB6450 规定;低压设备的允许温升值见 GB7251 规定;3.11 1000kVA 及以下变压器采用高压负荷开关 - 熔丝保护, 1250kVA 及以上变压器采用高压断路器保护。

3.12 最大允许尺寸(深×宽×高: mm ): 630kVA 及以下变压器终端型3200 × 2000 × 2500 ,环网型3200 × 2500 × 2500 ; 1250 - 8000kVA 变压器终端型 3400 × 2300 × 2600 ,环网型3400 × 2700 × 2600 。

集电线路箱变检修规程完整

集电线路箱变检修规程完整

6 集电线路设备检修与维护6.1 一般性要求6.1.1 电气工作人员应具备必要的安全知识、电气知识和业务技能,无妨碍工作的病症。

6.1.2 作业现场的生产条件、安全设施、作业机具和安全工器具等应符合国家或行业标准规定的要求。

6.1.3 线路作业时发电厂和变电站的安全措施应满足一般工作程序和安全要求。

6.2 箱式变压器设备基本参数 35kV箱式变压器6.2.1 检修周期a)每周应对设备全面巡回检查一次,并做好设备巡回检查记录。

b)大修周期:一般在正式投运后五年一次,以后每十年一次。

当承受出口短路后或运行中发现异常状况并经试验判明有部故障应考虑提前大修;c)小修周期:每年至少一次。

6.2.2 日常维护与检修工作容变压器各附件检修项目及标准:变压器常见故障处理:1检修作业卡(1) C级检修①安全措施:·所有进入施工现场工作人员必须严格执行《电业安全生产规定》,明确停电围、工作容、停电时间,核实站所做安全措施是否与工作容相符。

·学习有关工作围、安全措施。

·检修前必须对检修工作危险点进行分析。

每次检修工作前,应针对被检修隔离开关的具体情况,对危险点进行详细分析,并做好充分的预防措施,并组织所有检修人员共同学习。

②使用工器具:检修工器具、备件及材料准备、个人常用工具、试验检测仪器、专用拆装扳手等。

③其他:·检修前应对检修的设备运行情况、故障情况、缺陷情况及设备近期的试验检测等方面情况进行详细、全面的调查分析为现场具体的检修方案的制订打好基础。

·检修前的检查和试验:为了解设备在检修前的状态以及为检修后试验数据进行比较,在检修前应进行检查和试验。

④C级检修作业卡:B级检修作业卡:2验收⑴验收方式为三级验收:作业组为第一级验收方,技术专工为第二级验收方,运行组为第三级验收方。

⑵试运行前检查项目·变压器本体、冷却装置及所有附件均完整无缺不渗油,油漆完整。

·接地可靠。

  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

预装式箱式变电站检验规程(编号:GL/DY-QES-C51-2015)宁夏大有电器有限公司二零一五年预装式箱式变电站检验规程专业知识编辑整理WORD完美格式1适用范围本规程适用于本公司生产的预装式箱式变电站出厂检验标准。

2执行标准GB/7251.1-2013 《低压成套开关设备》GB/15576- 2008 《低压成套无功功率补偿装置》GB/17467- 2010 《高压/低压预制式变电站》3引用标准GB/10233- 2005 《低压成套开关设备基本调试方法》GB/3906- 2006 《3.6-40.5KV交流金属封闭开关设备和控制设备》GB/11022- 2011 《高压开关设备和控制设备标准》GB/700- 2006 《碳素结构钢》GB/4208- 2008 《外壳防护等级的分类》《本地供电部门验收规范》4箱式变电站外形检查4.1箱体成型后,应符合图纸要求,几何误差见下表。

表1对角线误差(单位:mm)前、后面两侧底、顶面5 3 5专业知识编辑整理WORD完美格式表2 外形尺寸及允许偏差(单位:mm)外形尺寸允许偏差变压器容量长宽高长宽高1000~630KVA 5800~470630~315KVA 4700~450 2600 0 2200±±±315~100KVA 4500~4003.0 5.0 3.0 0100~50KVA 4000~2204.2箱式变电站的所有开孔应按图纸要求和《冷加工通用工艺规程》(编号:DY-01-GY)进行并满足箱式变电站自身结构及使用要求。

4.3箱式变电站的骨架应按《焊接通用规程》(编号:DY-02-GY)进行,框架焊接要牢固,不得漏焊,焊缝平整光洁、没有焊穿裂缝、溅渣气孔。

4.3.1吊柱是箱式变电站工艺重点,必须焊接牢固,焊口要有一定深度焊口焊满突出、不得有溅渣,以防在起吊过程中脱落。

专业知识编辑整理WORD完美格式4.4箱式变电站的箱体、柜体及其零部件的金属表面的涂覆加工工艺应按《喷涂工艺规程》(编号:DY-03-GY)进行,在柜体和箱体一米处观察不应有明显的色差和反光。

4.5组装式箱式变电站,对接处的立缝,水平公差值应一致,连接孔偏差应不大于1mm,对接处应能保持整体性能。

4.6变压器室内应对母线、电缆连接洞口进行封堵,达到防误入、防鼠、防火的要求。

5 高、低压配电装置的检查5.1一般检查5.1.1所有电器设备及部件、元器件要符合图纸及相关技术要求的规定。

高压成套开关设备符合GB/3906-2006,低压成套开关设备符合GB/7251.1-2005,低压成套无功功率补偿装置符合GB/15576-2008。

5.1.2箱式变电站的供配电系统应正确并符合设计要求,图纸产品保持一致。

5.1.3高、低压成套开关柜、低压成套无功功率补偿装置的导线截面和颜色、母线的制作应符合《大线制作通用工艺规程》(编号:DY-05-GY)、《二次线配置通用工艺规程》(编号:DY-07-GY)和《母线制作通用工艺规程》(编号:DY-06-GY)的要求。

5.1.4各电路导线端头的标识应与提供的原理图、接线图相一致。

专业知识编辑整理WORD完美格式5.1.5计量柜的计量互感器、电度表等必须按供电部门的验收要求备案,同时计量柜的铅封或明挂锁扣必须安全可靠。

5.1.6所用变压器规格、型号符合设计要求,安装符合规范及制造厂要求;油浸式变压器附件完好无损,变压器无渗漏油、油位正常,无锈蚀,油漆完好,相位标志正确;手动调压装置正常;所有密封良好,瓷件无损伤、裂纹。

5.1.7箱式变电站的铭牌符号及吊装接地等标志要正确、牢固、清晰、齐全。

5.1.8箱式变电站的箱体外部表面应美观、平整、光洁和防止磕碰损伤导致喷涂层脱落,影响整体防雨、防腐的性能。

5.2功能检查5.2.1箱式变电站变所有门应向外开,并具有防水防雨功能、门锁为暗锁,确保开关门轻松自如,低压室检修通道应不小于600mm。

5.2.2箱式变电站的箱体及柜体内的行程开关和照明装置应安装牢固并正常运行,系统闭锁功能完整,且便于维修更换。

5.2.3箱式变电站的箱体及柜体需有足够的自然通风或强制通风措施,换气扇、百叶窗的安装要牢固并正常运行,确保设备运行温升不超标。

5.2.4箱式变电站变压器室内的温度控制器应装设在调控方便、不影响正常运行的地方且安装牢固。

5.2.5变压器室内变压器必须固定牢靠;安全防护网应具有专业知识编辑整理WORD完美格式防误入功能,带电标识应醒目、清晰,便于装卸。

5.2.6变压器接地必须是硬连接,而且连接牢靠。

5.2.7箱式变电站的箱体及柜体的过门接地应牢固并留有一定余量。

5.2.8高压柜的微机型继电保护额定值的出厂估算值设置见附录1。

6出厂试验项目6.1箱变中高压、低压电器设备和变压器的工频耐压试验值、电气间隙、爬电距离试验值分别见下表。

表1高压开关设备工频耐压试验值额定电压(KV)相间对地(KV)隔离断口(KV)3.6 25 27 7.2 30 34 12 42 48 24 65 77 40.5 95 118表2:低压开关设备的工频耐压试验值额定绝缘电压Ui 试验电压(V) Ui≤60 100060<Ui≤300 2000 300<Ui≤690 2500专业知识编辑整理WORD完美格式690<Ui≤800 3000 800<Ui≤1000 3500表3:变压器工频耐压试验值低压对高压及地 3 名称试验位置工频电压(KV)高压对低压及地 28 干式变压器高压对低压及地 35 油式变压器低压对高压及地 5表4高压裸露带电体电气间隙及爬电距离电压等级电气间隙爬电距离(mm)(mm)6(7.2) 100 144(有机绝缘)20mm/KV 10(12) 125 240(有机绝缘)20mm/KV 24 180 480(有机绝缘)20mm/KV 35 310 (有机绝缘)20mm/KV表5 低压裸露带电体电气间隙及爬电距离专业知识编辑整理WORD完美格式电气间隙(mm) 爬电距离(mm) 额定绝缘电压UiI≦63A I≧63A I≦63A I≧63A(V)60<Ui≤300 5(10) 6 4(10) 8 300<Ui≤660 8(10) 10 12(14)14 660<Ui≤800 14(16) 14 14(20) 20注:此表括号内数据为低压成套无功功率补偿装置的要求。

6.2机械特性试验及机械操作高、低压开关设备机械操作和机械特性试验分别按《3.6-40.5KV交流金属封闭开关设备和控制设备》GB/3906-2006中的6.102、7.102、《低压成套开关设备和控制设备》GB/7251-2013细则进行。

6.3仪表、继电器及指示元件检查所有测量仪表、继电器均应经过单个元件的检验并有明显的标志,结合机械操作试验进行通电操作试验,以验证内部接线,动作元件和仪表指示等均符合技术要求。

6.4. 铭牌6.4.1 每台箱变的箱体应装有符合标准要求的铭牌,内容包括:a)产品名称和型号b)变压器额定容量(KVA)c)额定频率专业知识编辑整理WORD完美格式d)出厂编号e)外形尺寸f)设备重量g)额定电压h)出厂日期J)制造厂名5.4.2 各附件准备齐全。

包括电缆、灭弧罩、机构操作把手、钥匙、等。

5.4.3箱变出厂时应将各元器件的合格证、使用说明书、成套开关柜的图纸及附件清单等资料准备齐全,装入资料袋中,放置于规定位置。

5.5 以上检验试验项目全部合格才允许发合格证。

编制:王超审核:曹玉柱批准:曹玉柱二零一五年六月附录1专业知识编辑整理WORD完美格式电力系统微机型继电保护额定值2.速断定值:26.7A 2.定时线过流定值:4A 2.过负荷定值:5A额定容量额定参数及二次定值KVA/KW 电流速断保护定时限过流保护过负荷保护1.电流速断保护:投入1.定时限过流保护:投入1.过负荷保护:投入告315 跳闸TAR 跳闸TAR 警ALM2.速断定值:25.2A 2.定时线过流定值:3.78A 2.过负荷定值:4.72A3.速断时间:0S 3.定时限过流时间:0.2S 3.过负荷时间:6S1.电流速断保护:投入1.定时限过流保护:投入1.过负荷保护:投入告跳闸TAR 跳闸TAR 警ALM400 3.速断时间:0S 3.定时限过流时间:0.2S 3.过负荷时间:6S1.电流速断保护:投入1.定时限过流保护:投入1.过负荷保护:投入告跳闸TAR 跳闸TAR 警ALM500 2.速断定值:25A 2.定时线过流定值:3.75A 2.过负荷定值:4.7A 3.速断时间:0S 3.定时限过流时间:0.2S 3.过负荷时间:6S1.电流速断保护:投入1.定时限过流保护:投入1.过负荷保护:投入告跳闸TAR 跳闸TAR 警ALM630 2.速断定值:25.2A 2.定时线过流定值:3.78A 2.过负荷定值:4.72A 3.速断时间:0S 3.定时限过流时间:0.2S 3.过负荷时间:6S800 1.电流速断保护:投入1.定时限过流保护:投入1.过负荷保护:投入告专业知识编辑整理WORD完美格式跳闸TAR 跳闸TAR 警ALM2.速断定值:26.7A 2.定时线过流定值:4A 2.过负荷定值:5A3.速断时间:0S 3.定时限过流时间:0.2S 3.过负荷时间:6S1.电流速断保护:投入1.定时限过流保护:投入1.过负荷保护:投入告跳闸TAR 跳闸TAR 警ALM1000 2.速断定值:20A 2.定时线过流定值:3A 2.过负荷定值:3.75A3.速断时间:0S 3.定时限过流时间:0.2S 3.过负荷时间:6S1.电流速断保护:投入1.定时限过流保护:投入1.过负荷保护:投入告跳闸TAR 跳闸TAR 警ALM1250 2.速断定值:20A 2.定时线过流定值:3A 2.过负荷定值:3.75A3.速断时间:0S 3.定时限过流时间:0.2S 3.过负荷时间:6S1.电流速断保护:投入1.定时限过流保护:投入1.过负荷保护:投入告跳闸TAR 跳闸TAR 警ALM1600 2.速断定值:21.3A 2.定时线过流定值:3.2A 2.过负荷定值:4A 3.速断时间:0S 3.定时限过流时间:0.2S 3.过负荷时间:6S1.电流速断保护:投入1.定时限过流保护:投入1.过负荷保护:投入告跳闸TAR 跳闸TAR 警ALM2000 2.速断定值:20A 2.定时线过流定值:3A 2.过负荷定值:3.75A3.速断时间:0S 3.定时限过流时间:0.2S 3.过负荷时间:6S1.电流速断保护:投入1.定时限过流保护:投入1.过负荷保护:投入告2500 跳闸TAR 跳闸TAR 警ALM2.速断定值:21A 2.定时线过流定值:3.2A 2.过负荷定值:3.75A专业知识编辑整理WORD完美格式3.速断时间:0S 3.定时限过流时间:0.2S 3.过负荷时间:6S1.电流速断保护:投入1.定时限过流保护:投入1.过负荷保护:投入告跳闸TAR 跳闸TAR 警ALM3000 2.速断定值:22A 2.定时线过流定值:3.78A 2.过负荷定值:4A 3.速断时间:0S 3.定时限过流时间:0.2S 3.过负荷时间:6S专业知识编辑整理。