楼地⾯(卫⽣间、阳台)防渗漏标准化⼯艺解析楼地⾯防渗漏标准化⼯艺1适⽤范围1.1本标准适⽤于XXX公司。

2编制⽬的2.1规范阳台、卫⽣间、空调板、屋⾯防渗漏做法,提升平⾯防渗漏过程管控能⼒,降低渗漏风险。

3编制依据3.1《建筑装饰装修⼯程质量验收规范》(GB50210-2001)3.2《混凝⼟结构⼯程施⼯质量验收规范》(GB50204-2002)(2011版);3.3《住宅建筑构造图集》(11G930);4 建筑做法及构造节点4.1 半封闭阳台做法(参照设计):1、10厚1:3⽔泥砂浆2、250g/m2聚⼄烯丙纶复合防⽔卷材,沿墙体上返300(完成⾯)3、最薄处30厚C15细⽯砼,向地漏找坡1%,表⾯随打随抹平。

4、⼲铺20厚XPS挤塑板。

5、钢筋砼楼板外墙下现浇250mm⾼与墙同宽C15导墙(门⼝处断开)4.1.1⼯艺流程:基层清理→保温层→找坡层→防⽔层→闭⽔试验→防⽔保护层→养护→⼆次闭⽔试验4.1.2构造做法:1、基层处理:管道安装及地漏、管根等部位封堵完成,将地⾯墙⾯的杂物、砂浆、积⽔等清理⼲净。

阳台有砌体墙时,应先完成墙体砌筑及抹灰。

2、找坡找平层最薄处30mm厚细⽯砼从阳台门⼝向地漏找坡压光,坡度1%,地漏周围250mm 范围内找坡5%,并在四周根部阴⾓处抹半径不⼩于50mm圆⾓。

找坡坡度和坡向应正确,不得出现向墙⾓、墙边及门⼝倒泛⽔,也不得出现积⽔现象。

阳台门下槛上表⾯做2%坡度向室外。

完成⾯应坚固、平整、压光,不得有酥松、起砂和起⽪。

3、防⽔层找平找坡层⼲燥后,在平⾯及⽴⾯分遍粘贴聚⼄烯丙纶复合防⽔卷材,接茬处搭界宽度100mm,四周遇墙上返300mm(成活⾯以上),阳台有门连窗时在门窗下⼝收头包过门槛,阴⾓、地漏、管根等处应先做防⽔附加层,地漏周边留20×20mm凹槽增加2mm厚JS防⽔。

4、闭⽔试验防⽔层完⼯后将门⼝与地漏封堵,进⾏24⼩时闭⽔试验,闭⽔⾼度30-50mm,并观察记录,确认⽆渗漏后⽅可排⽔。

卫生间防水施工工艺及做法

卫生间防水施工工艺及做法

卫生间防水施工工艺及做法以下是有关卫生间防水施工工艺及做法:1、防水工艺工序:清理基面→湿润基面→涂刷第一道聚合物水泥(基)防水涂料→涂刷第二道聚合物水泥(基)防水涂料→涂刷第三道聚合物水泥(基)防水涂料→闭水试验→质量验收→保护层及饰面施工工艺要点:① 基层清理:将基层表面的尘土、沙粒、砂浆、硬块等物清理干净,对所破坏地面处进行找平修补;地面、墙面阴角处做好圆弧形R角;② 涂膜防水施工:按照涂料的配合比配制基层处理剂。

在正式涂刷之前,先对上下水管根部、阴阳角处加纤维布进行水不漏加强处理,待干后再大面积刷第一遍。

等第一遍涂层终凝后再与第一遍垂直方向涂刷第二遍,以后按上述方法进行第三遍第四遍,确保涂层厚度不小于1.5mm 厚;③ 涂膜配合比准确,搅拌均匀,不允许出现空鼓、开裂、气泡、褶皱,粘结牢固;④ 闭水试验:待防水层完全千后进行24h闭水试验,确认不漏水后进行下道工序。

待所有装饰面层完工后做二次闭水试验,蓄水时间也为24小时;⑤ 保护层施工:闭水试验完成后,及时排干水进行防水砂浆保护层施工,施工时严禁破坏防水层;⑥ 厨卫间墙面防水涂膜建议刷至楼板底。

2、防水阴角处理:工艺要点:①先将结构楼板浮浆全面清理干净,洒水润湿墙地面,用1:1 水泥砂浆粉刷平整,阴角做成圆弧形,圆弧R=30-50mm 为宜;② 地面找平需从地漏口部位往外预留坡度,最少不小于3-5%o。

管根部位需用水泥砂浆包裹,高度50mm-80mm 为宜。

地漏管口应为地面最低部位,边缘收光抹平;③ 浴缸下部也需以排水管口向外预留坡度,管口部位为最低点。

3、管根部施工工艺工序:定位开孔→孔洞凿毛→管道安装→吊模灌浆→防水处理工艺要点:① 所有的管道吊模必须采用专业吊模件,严禁采用铁丝吊模;② 在分成浇捣C20 细石础时,须掺入聚合物水泥基防水涂料,分层浇筑,严禁一次浇筑完成;③ 吊模完成后管根部用堵漏王进行防水加强处理,必要时增加一层网格布,防止开裂;④ 面层用水泥砂浆做出馒头形状保护管根部,面层防水随卫生间一同涂刷。

工程成品地漏施工方案

工程成品地漏施工方案

工程成品地漏施工方案一、施工目的地漏是一种用于室内排水系统的设备,通常安装在地面下方,用于排放雨水、洗衣水、厨房水和浴室水等。

地漏施工方案的目的是确保地漏的安全、稳固、密封性和排水能力,保证室内排水系统的正常运行和使用。

二、施工前的准备工作1、设计定位:地漏的位置应按设计图纸确定,确保位置准确无误。

2、材料准备:地漏施工所需材料包括地漏本体、地漏上盖、防水胶、密封胶、密封垫等。

3、施工人员:确保有足够的施工人员,并且他们具备专业的施工技能和经验。

4、清理地面:在进行施工前,要对地面进行清理,确保地面平整,无灰尘和碎石等物质。

三、施工步骤1、准确测量地漏位置根据设计图纸确定地漏的准确位置,并用尺子和橡皮锤将地漏的安装位置标记出来。

2、切割地面使用电动切割机等工具,根据地漏的尺寸,切割出对应的安装孔。

确保切割的深度和尺寸符合要求,并且切割出的孔是方正的。

3、清理安装孔使用扫帚、吸尘器等工具,清理安装孔内的灰尘和碎石,确保安装孔内部干净、平整。

4、涂抹防水胶在安装孔的四周涂抹防水胶,确保地漏和地面之间的接触部位能够完全密封,避免水漏。

5、安装地漏本体将地漏本体放置在安装孔内,并用橡皮锤轻轻敲打,确保地漏本体能够与地面充分接触,并且垂直水平。

6、安装地漏上盖将地漏上盖放置在地漏本体上,使用螺丝刀将上盖螺丝固定在地漏本体上,确保地漏上盖能够完全密封,并且能够承受地面的负荷。

7、涂抹密封胶在地漏上盖与地面之间的接口涂抹密封胶,确保地漏与地面之间的接口能够完全密封,避免水漏。

8、进行水平调整使用水平尺等工具,对安装好的地漏进行水平调整,确保地漏水平。

9、测试排水能力在地漏附近倒入一些清水,测试地漏的排水能力,确保地漏排水顺畅。

10、清理工地清理施工现场,将现场垃圾、碎石等物质清理干净,确保施工现场整洁。

四、施工注意事项1、施工人员在进行施工时,应佩戴安全防护用具,确保施工过程中的安全。

2、施工前严格按照设计图纸确定地漏的准确位置,并使用合适的工具和设备进行施工。

楼地面防水工程施工工艺

楼地面防水工程施工工艺

楼地面防水工程施工工艺楼地面防水工程施工工艺采用单组份聚氨酯涂膜和JS聚氨酯涂膜,厚度均为1.5mm。

施工前需要满足以下条件:防水房间楼地面垫层已完成,立管、套管已固定并经过验收,管周围缝隙填塞密实,找平层标高符合要求且表面平整坚实,泛水坡度在2%以上,墙面基层抹灰要压光且平整无缺陷。

同时,在易发生渗漏的部位进行增补处理,穿过防水层的管道和固定卡具提前安装并做成半径为10mm的圆弧。

所需材料包括单组份聚氨酯涂膜和水泥基聚氨酯涂膜,需要经过见证取样和试验合格才能使用。

同时需要出厂合格证、备案证书、使用说明书、检测报告和材料复试报告等资料。

施工过程需要使用电动搅拌器、搅拌捅、小漆桶、塑料刮板、铁皮小刮板、橡胶刮板、弹簧秤、毛刷、滚刷、小抹子、油工铲刀、扫帚、消防器材、风机等机具。

施工流程为基层表面清理、修理、细部处理、配置底胶、涂刷底胶和细部附加层等步骤。

操作人员需要经过专业培训并持证上岗,先进行样板间施工并经过检查验收合格后再进行全面施工。

施工过程中,需要进行多次涂膜防水层施工,包括第一遍、第二遍和第三遍涂膜,以及防水层施工前的基层清理和细部附加层施工等步骤。

在施工过程中,需要注意保持涂膜厚度的均匀一致,并进行试水和验收等环节。

在基层清理阶段,需要将灰皮和杂物清除干净,并用湿布擦拭表面,以保证涂膜防水层与基层的结合牢固。

在涂刷底胶时,需要将底胶均匀涂布在基层表面上,并且在细部附加层施工时,需要注意在容易漏水的薄弱部位均匀涂刷涂料。

在涂膜防水层施工时,需要进行立面施工和平面施工,以保证涂层平整和能挂悬涂料。

涂膜防水层的施工需要进行多次涂层,包括第一层、第二层和第三层涂膜。

在涂层时,需要注意涂覆要尽量均匀,不能局部沉积,并要求多滚刷几次使涂料与基层之间不留气泡,粘结严实。

同时,需要注意防水涂料的配制和保质期,以确保施工质量。

为了确保防水的施工质量,需要建立和健全质量管理体系,并在施工过程中进行严格监控和管理,采取切实可行的施工措施。

卫生器具安装施工工艺标准

卫生器具安装施工工艺标准

卫生器具安装施工工艺标准1、总则本章适用于室内污水盆、洗涤盆、洗脸(手)盆、盥洗槽、浴盆、淋浴器、大便器、小便冲洗槽、妇女卫生盆、化验盆、排水栓、地漏、加热器、煮沸消毒器和饮水器等卫生器具的安装工程。

2、编制依据2。

1《建筑安装工程施工质量验收统一标准》(GB 50300-2001)2。

2《建筑给水、排水及采暖工程施工质量验收规范》(GB50242-2002)3、一般规定3。

1卫生器具的安装应采用预埋螺栓或膨胀螺栓安装固定。

3。

2卫生器具安装高度如设计无要求时,应符合表3。

2—1的规定。

卫生器具的安装高度表表 3.2—14。

1。

4卫生器具给水配件的安装高度,如设计无要时,应符合表3.2-2的规定.卫生器具给水配件的安装高度表 3.2-2注:装设在幼儿园内的洗手盆、洗脸盆和盥洗槽水嘴中心离地面安装高度应为700mm,其他卫生器具给水配件的安装高度,应按卫生器具实际尺寸相应减少。

4。

施工准备4。

1技术准备(1)认真审阅图纸资料,卫生器具的规格型号必须符合设计要求,并持有出厂合格证. (2)明确提出施工的范围和质量标准,并据此定出合理可行的施工周期。

(3)操作人员必须了解所施工卫生器具的性能、技术要求。

4.2.材料要求(1)进入施工现场的各种材料及配件必须全部合格、配齐并应略有富余。

(2)材料应根据计划需要及时运到现场,并存放在防避风、雨的室内或棚内,材料应放在垫木或货架上,按型号、规格堆放整齐、牢靠。

(3)不合格的材料,严禁运至现场.4。

3.主要机具(1)主要电动机具:套丝机、砂轮切割机、角向砂轮切割机、手电钻、冲击电钻、打孔机、电烙铁等。

(2)主要工具:管钳、手锯、活动扳手、呆扳手、手锤、布剪刀、手铲、錾子、钢丝钳、方锉、圆锉、螺钉旋具(螺丝刀)等。

(3)其他:水平尺、角尺、钢卷尺、划规、线坠等.4。

4作业条件(1)根据设计要求和土建确定的基准线,确定好卫生器具的标高.(2)所有与卫生器具连接的管道水压、灌水试验试验完毕,并已办好隐蔽、预检手续。

地漏施工方案范文

地漏施工方案范文

地漏施工方案范文一、施工准备1.1地漏的材料准备:根据设计要求,准备好所需的地漏材料,包括地漏本体、盖板、密封圈等。

1.2工具准备:准备好常用的工具,如锤子、电钻、扳手、测量工具等,以便进行施工操作。

1.3施工区域准备:清理施工区域的杂物,确保施工区域平整、清洁,便于施工操作。

二、施工步骤2.1清理施工区域:在施工区域铺设防护布,防止施工过程中地面受损或污染。

2.2确定地漏位置:根据设计图纸,在施工区域确定地漏的位置,并标出。

2.3切割地面:使用电钻或电锯等工具,按照地漏的尺寸,在施工区域上切割出地漏的位置。

2.4安装地漏本体:将地漏本体按照设计要求放入切割好的位置,确保地漏本体与地面齐平。

2.5安装密封圈:在地漏本体与地面之间放置密封圈,确保地漏与地面完全密封,防止漏水。

2.6测试地漏密封性:接通给排水管道,灌入适量的水,检查地漏是否存在漏水情况。

2.7安装盖板:待地漏安装完毕且密封性良好后,安装地漏盖板,确保盖板与地漏本体紧密贴合。

2.8清理施工区域:清理施工现场,将杂物和垃圾清理干净,确保施工区域整洁。

三、施工注意事项3.1施工前应仔细阅读地漏安装说明书,根据说明书进行施工操作。

3.2地漏的安装位置应准确测量,并按照设计图纸进行切割,避免浪费材料和造成不必要的损失。

3.3在安装地漏本体时,应确保其与地面齐平,以防止地漏本体与地面之间有空隙,影响密封效果。

3.4在安装地漏盖板时,应确保其与地漏本体紧密贴合,防止灰尘和异物进入地漏。

3.5施工过程中需佩戴好工作手套和安全帽,确保安全施工。

3.6在施工区域周围设置警示线,提醒他人注意,防止意外发生。

3.7施工完毕后需对施工现场进行清理,保持施工区域整洁。

四、施工质量控制4.1在施工过程中,应严格按照设计图纸进行施工,确保地漏位置准确无误。

4.2在安装地漏本体时,应检查地漏本体与地面是否齐平,确保安装质量良好。

4.3在安装密封圈时,应仔细检查密封圈是否完好,确保其能够有效防止漏水。

卫生器具安装施工工艺标准

卫生器具安装施工工艺标准

卫生器具安装施工工艺标准1、总则本章适用于室内污水盆、洗涤盆、洗脸(手)盆、盥洗槽、浴盆、淋浴器、大便器、小便冲洗槽、妇女卫生盆、化验盆、排水栓、地漏、加热器、煮沸消毒器和饮水器等卫生器具的安装工程。

2、编制依据2.1《建筑安装工程施工质量验收统一标准》(GB50300-2001)2.2《建筑给水、排水及采暖工程施工质量验收规范》(GB50242-2002)3、一般规定3。

1卫生器具的安装应采用预埋螺栓或膨胀螺栓安装固定.3。

2卫生器具安装高度如设计无要求时,应符合表3。

2—1的规定.卫生器具的安装高度表表 3。

2-14.1。

4卫生器具给水配件的安装高度,如设计无要时,应符合表3。

2-2的规定。

卫生器具给水配件的安装高度表3.2—2注:装设在幼儿园内的洗手盆、洗脸盆和盥洗槽水嘴中心离地面安装高度应为700mm,其他卫生器具给水配件的安装高度,应按卫生器具实际尺寸相应减少。

4。

施工准备4.1技术准备(1)认真审阅图纸资料,卫生器具的规格型号必须符合设计要求,并持有出厂合格证。

(2)明确提出施工的范围和质量标准,并据此定出合理可行的施工周期。

(3)操作人员必须了解所施工卫生器具的性能、技术要求。

4。

2。

材料要求(1)进入施工现场的各种材料及配件必须全部合格、配齐并应略有富余。

(2)材料应根据计划需要及时运到现场,并存放在防避风、雨的室内或棚内,材料应放在垫木或货架上,按型号、规格堆放整齐、牢靠。

(3)不合格的材料,严禁运至现场.4。

3.主要机具(1)主要电动机具:套丝机、砂轮切割机、角向砂轮切割机、手电钻、冲击电钻、打孔机、电烙铁等。

(2)主要工具:管钳、手锯、活动扳手、呆扳手、手锤、布剪刀、手铲、錾子、钢丝钳、方锉、圆锉、螺钉旋具(螺丝刀)等。

(3)其他:水平尺、角尺、钢卷尺、划规、线坠等。

4。

4作业条件(1)根据设计要求和土建确定的基准线,确定好卫生器具的标高。

(2)所有与卫生器具连接的管道水压、灌水试验试验完毕,并已办好隐蔽、预检手续。

洁净地漏施工工艺流程

洁净地漏施工工艺流程

洁净地漏施工工艺流程英文回答:Clean floor drain construction process.The construction process for a clean floor draininvolves several steps to ensure a proper and effective installation. Here is a detailed explanation of the process:1. Preparation: Before starting the construction, it is important to gather all the necessary tools and materials. This includes a floor drain, PVC pipes, cement, sand, and other related supplies. Additionally, the area where the drain will be installed should be cleared and cleaned.2. Marking: The next step is to mark the location where the floor drain will be installed. This is typically doneby measuring the distance from the walls or other reference points. Marking the location accurately is crucial for the proper functioning of the drain.3. Excavation: Once the location is marked, the excavation process begins. This involves digging a trenchin the marked area to create space for the drain and pipes. The depth of the trench will depend on the specific requirements of the drain system.4. Installation of drain and pipes: After the trench is excavated, the floor drain is installed. This involves connecting the drain to the PVC pipes using appropriate fittings. The pipes are then laid in the trench and connected to the main sewer line or drainage system.5. Backfilling: Once the drain and pipes are properly installed, the trench is backfilled with sand or gravel. This helps to provide stability and support to the drain system. The backfill should be compacted carefully to avoid any future settlement issues.6. Cementing: After backfilling, the trench is cemented to ensure a secure and watertight seal. Cement is mixed according to the manufacturer's instructions and applied tothe trench using a trowel. The cement should be spread evenly and allowed to dry completely.7. Testing: Once the cement is dry, the floor drain system is tested for leaks and proper functioning. Water is poured into the drain to check if it flows smoothly anddoes not leak. Any issues or leaks are addressed and fixed before the final completion of the construction process.8. Finishing touches: Finally, any excess cement or debris is cleaned up, and the surrounding area is restoredto its original condition. This includes removing any construction materials and ensuring a clean and tidy finish.中文回答:洁净地漏施工工艺流程。

  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

地漏设置及安装工艺
目录
一、地漏设置的作用: (2)
二、地漏的分类: (2)
三、地漏的连接形式: (2)
四、地漏的选型: (2)
五、地漏的安装工艺: (2)
六、地漏的改装: (5)
七、案例分析: (6)
摘要:
工程建设项目中地漏的安装工艺、方法。

主要从地漏的品牌选型、设置位置,与土建、装修的配合,标高控制及本体、面板安装方法,以及以往施工过程中的案例进行了总结与分析。

关键词:
定位;与结构配合;标高控制;地漏本体及面板安装;案例分析;
“地漏”对于一项工程来讲,它不过是一个小小配件,安装在角落里,无足轻重,假设没有地漏,则地面会积水横溢;假设地漏高出完成面,则达不到排水效果;所以地漏虽小,却关联着每个人的生活品质。

一、地漏设置的作用:
1.有效地排除地面积水并阻止排水管路系统中的有害气体进入室内;
二、地漏的分类:
1.从工艺材质上分为:PVC(ABS)地漏、铸铁地漏、不锈钢地漏及铜质地漏等;从排水流向上分为:直通型、侧排型;从使用位置分为:卫生洁具旁地面地漏、洗衣机专用或两用地漏、室内明沟或室外排水地漏以及人防区域防爆地漏等;从使用功能分为:普通地漏、防臭地漏两种;
三、地漏的连接形式:
1.常规分为PVC胶水连接、丝扣连接、承插打口连接、不锈钢胶圈抱箍连接;
四、地漏的选型:
1.目前市场上的地漏种类繁多,是选铸铁的好还是不锈钢的好?水封的好还是重力机械式的好?如何选择一款真正的地漏,对于我们现场施工人员来讲,确实是一件比较难以抉择的事情。

其实,在实际施工过程中,对于地漏的选型,除非设计或者业主有专门的要求,否则,对于地漏的选型我们要把握两个原则:第一、首先要熟悉图纸,了解地漏的管径、使用部位及功能;第二、在满足规范的前提下,要有成本意识;这样,PVC 地漏就不会装在人防区域内,铸铁地漏也就不会出现在卫生间了;
五、地漏的安装工艺:
1.地漏安装工艺:
1.1.前期准备:
1.1.1.仔细审阅图纸,针对地漏的敷设位置及数量,结合系统功能判别图纸中是否存在疏漏之处,如有,应及时与相关设计进行沟通解决;
1.1.
2.结合图纸与招标文件精神,对本工程不同部位的地漏所选用的材质、品牌有个初步的了解;
1.2.现场勘察:
1.2.1.结合图纸,对地漏的安装坐标要有大体的了解;
1.2.2.针对施工现场实际情况,对地漏所在位置的结构应有所了解,必要时与土建、结构单位进行沟通;
1.2.3.对于特殊部位的地漏敷设,要尽早掌握周围的地理环境;
1.3.安装位置的确定:
1.3.1.对于前期土建预埋预留的地漏孔洞,要及时进行复核,发觉有误,及时进行孔洞的调整;
1.3.
2.对于特殊部位,如机房内的排
水沟地漏,要结合现场实际,复核坡度,
视实际情况及时调整安装位置(例如:
土建砌筑排水沟明沟时,排水沟地面坡
度没有坡向地漏一侧,这样,为了保证
排水沟内积水流向畅通,必须重新调
整,要么土建重新找坡度,要么排水管
地漏安装位置加以调整);
图1 离壁墙地漏
1.3.3.针对地铁车站离壁墙周边地漏
的安装(见图1所示),要及时与装饰单位沟通,掌握装修的施工方案及具体尺寸;
1.3.4.对于卫生间等部位的地漏安装,既要保证安装美观,又要保证有足够的维修空间;
1.4.连接形式的确定:
结合施工现场实际情况,地漏安装部位不同,所采用的连接形式也有所不同,例如:卫生间、茶水间PVC地漏一般采用胶水连接;离壁墙、积水明沟铸铁地漏一般采用承插连接;人防区域内的铜质防爆地漏一般采用丝扣连接;需要在施工过程中灵活掌握;1.5.过程跟踪;
1.5.1.现场施工过程中,地漏安装比较繁琐,特别是标高控制,很大程度上要与土建、装修施工交叉配合,另外还需要我们随时了解、掌握其施工计划,以便合理安排材料的进货与劳动力的分配;
1.5.
2.对于屋面等特殊部位的施工,还应随时掌握近期的天气情况;
1.6.地漏安装:
1.6.1.地漏安装前,与地漏相连的排水管线已安装完毕,并已进行通水、通球试验。

试验的程序为由上而下,以不漏、不堵为合格。

1.6.
2.地漏安装前,应检查排水管线立管敞口部位是否包扎,其内垃圾油污等是否清理干净;
1.6.3.地漏安装前,应检查、复核所在安装位置空间的装修完成面,如:卫生间比室外地坪低2cm;其余部位地漏安装面板比完成面低5mm为宜,且地坪的坡度要坡向地漏;
1.6.4.部分地漏的装饰盖比较昂贵,所以为了防止丢失,在施工过程中先将地漏本体安装到位,待装饰地面施工时相互配合将地漏面板一次性安装到位;
1.6.5.地漏安装完毕,应配合土建、装修单位在地漏下方支撑模板或模具,将地漏周边孔洞用混凝土砂浆严密捣实,严禁结合部位发生渗漏现象;
1.6.6.对于pvc胶水连接的地漏安装,在安装前,管道粘接宜在常温环境下进行,操作场所应远离火源,防止撞击和阳光直射(在零下20度以下的环境中不得操作);为了避免将PVC碎末掉入管内,应先将PVC水管内临时封堵,根据安装标高,用锯弓将PVC 排水管锯断,用干布将PVC地漏、排水管承插口处粘接表面擦净。

若粘接表面有油污,可用干布蘸清洁剂将其擦净。

然后沿PVC排水管周边均匀涂抹专用胶水,涂抹胶水时,必须先涂承口,后涂插口。

涂抹承口时,应由里向外,胶粘剂应涂抹均匀,并适量。

(冬季施工期间,应采取可靠的防冻防寒措施,以保证胶粘剂的粘结质量),涂抹胶粘剂后,应在20s内完成粘接。

粘接时,应将插口轻轻插入承口中,对准轴线将地漏迅速、均匀定位;
1.6.7.对于地漏采用承插接口的连接,施工时禁止切削管口外径进行插接;
1.7.地漏安装完毕的检验校验:
1.7.1.地漏安装完毕、周边封堵完成后,灌
水进行渗漏检验,一来检验地漏周边是否渗
漏,二来检验排水管线是否畅通;
1.7.
2.另外从美观学角度考虑,地漏安装时,
不仅要保证使用功能,又要保证不被人踩踏损
坏,特别是对于PVC地漏而言;并且要结合现
场装修布局进行敷设(见图2所示)。

1.8.地漏的维护与检修:
图2
1)地漏投入使用一段时间后,为了防止细小
杂物堵塞地漏,要定期经行检查与清理;
2)为了防止固定地漏面板的螺栓松动,也要定期检查、更换;
3)为了保证地漏面板不易损坏,连接地漏
的排水管在施工过程中,关键处转弯部位的
弯头要自带检查口(见图3所示),也可进
行排水系统的检查、疏通;
六、 地漏的改装:
1. 增加地漏:
在工程施工过程中,由于甲方、设计等原因,
结合工程使用功能,在局部施工区域没有地
漏的区域加设地漏;通常有两种方法:一是
将原完成面地地坪抬高重新敷设下水管(见图4所示),主要是该部位没有合理的排水
位置,通过抬高地面完成面来达到排水的
目的,这样的施工方法法影响排水效果;
二是楼板上就近开洞,增加排水管(见图5所示),这样的做法比较麻烦,还要到下层楼
层施工,但效果比第一种要好;
2. 利用原卫生洁具排水管改装地漏:
例如用浴缸的排水管改成淋浴房用的地漏,存在
的问题是浴缸的排水管口径为De40,好在目前
市场上有口径小的地漏,所以这个问题也可以解
决了;
3. 改装成薄型地漏:
安装薄型地漏(水封1~2CM 的),排水没问题(见
图6所示),但水封高度不够,水会很容易蒸发,
会返臭味,所以要经常的往地漏里灌水或用湿布图3 地漏配管弯头部位加设检查口
图5 楼板开洞敷设地漏
图6 薄壁地漏 图 4 地坪加高情况下地漏安装
盖上,防止水的蒸发。

解决的方法很容易,
换个内置式地漏芯即可;
4. 改装原有老式地漏:
现在很多家庭住宅里的老式地漏密封失效,
如果要换地漏非常麻烦,目前市场上推出了
很多型号的地漏芯,无水封的管径规格也比
较多,可以直接插到地漏里,就能起到密封
的作用(见图7所示);
七、 案例分析:
1. 地铁项目施工过程中离壁墙周边地漏
敷设;
1.1. 该离壁墙处地漏(见图8所示)距
离离壁墙装饰边沿太近,导致装饰材料受
损,外观不美观,并且地漏铜面板更换检
修不方便;
1.2. 该离壁墙处地漏(见图9所示)距离
离壁墙装饰边沿合理,外观美观,并且地漏
铜面板更换检修方便;
2. 地铁项目施工过程中站台层屏蔽门周边地漏敷设;
2.1. 该地漏(见图10所示)安装位置恰巧在屏蔽门正对面,违反了申通地铁的规定图8 离壁墙边地漏 图9 离壁墙地漏
图7 改装式地漏
(为了保证屏蔽门侧疏散导向标志的
安装,该位置严禁安装地漏);
2.2. 该地漏(见图11所示)安装位
置在屏蔽门一侧,符合申通地铁的规
定;
综上所述,工程施工过程中,地漏位置设置合理,则地面积水能及时快速排放;与土建、装饰单位配合默契,从而避免标高有误引起的不必要返工,从而使地漏外表更加漂亮、美观;所以不论在现场施工过程中还是居家生活当中,对于地漏品牌的选用、位置确定及过程安装,都要引起我们大家足够的重视。