路基加宽施工方案2

路基加宽施工方案2
路基加宽施工方案2

随着我国经济的高速发展,近几年我国的交通流量急速增长。原双向四车道高速公路在通行能力和使用质量上都已经无法满足需求,结合当前通行需求,很多国家的主干道都进行了加宽拼接。旧路加宽处理不当,就会出现路面开裂、路基沉陷等病害问题。所以,新旧路基间的衔接以及新旧路面结构层的不均匀沉降都是路基加宽施工中的关键技术,同时,安全保通工作也是工作中的重中之重。

1路基加宽拼接施工工艺流程及操作要点

1.1施工工艺流程图

1.2主要施工操作要点

1.2.1施工前准备

(1)按照规范要求对沿线导线点和水准点进行复测和加密。如果是两侧拼接加宽,由于旧路基两侧导线点无法通视,需在旧路基两侧各布设一条附合导线,并且两条附合导线应闭合。

(2)路基开工前每隔20 m用全站仪准确放出旧路基外边缘点,并在老路基护栏上用喷漆标上桩号。

(3)每隔20m对旧路基和加宽路基原地面进行复测,核对或补充横断面,发现和设计图纸不符时,查明原因及时处理。

(4)加宽路基施工前,对旧路基填料和加宽路基基底土进行相关试验。每千米每侧至少取2个点;土质变化大时,视具体情况增加取样点数。

(5)按照规范要求对计划的路基填料进行相关试验,特别是对不同来源、不同性质的填料进行相关试验。填料尽量选取和旧路基填料性质相近的材料,避免和减少因新旧路基填料性质差异引起的不均匀沉降,确保新旧路基衔接处的施工质量。

1.2.2原地面清表、回填

(1)严格按照设计和规范要求将加宽路基基底范围内的树根全部清除,并将坑穴填平夯实。加宽路基基底范围内的水井和墓穴用优质填料换填处理。

(2)按照设计和规范要求的清表厚度,对加宽路基范围内原地面表层的腐殖土、草皮、表土等进行清理。

(3)按照设计和规范要求将加宽路基范围内的边沟、池塘等地段清淤要干净、彻底,然后按设计的地基处理方案施工。

(4)场地清理的范围为高速公路原路基坡脚至新加宽工程路基坡脚外1m的范围内。

(5)原地面清表的同时,将旧路的边沟和隔离栅等相关设施拆除。

(6)加宽路基基底清表完成后,按照设计要求进行原地面填前压实处理,压实度不小于90%,然后回填至原地面。

(7)对于部分基底含水量较高,清表后不易压实的路段,基底可采用翻挖、晾晒或掺灰处理,也可采用换填一定厚度的砂砾处理。

1.2.3台阶开挖

(1)台阶开挖前,先对老路基边坡进行清坡处理,清坡不易一次全部清理完成,应边挖台阶边清坡,以保证旧路基的稳定。

(2)边坡清理完成后,按照设计要求准确放样出每层台阶的开挖线,保证开挖台阶线型直顺、位置准确。

(3)旧路基台阶开挖针对老路不同的路基填料采用不同的台阶尺寸.对于老路基填料为黏土、亚黏土和卵砾石土时,拼接处的台阶高宜为1.0m。宽为1.5m;对于老路基填料为砂土、粉砂土时,拼接处的台阶高宜为0.4 m,宽为0.6 m。

(4)开挖拼接至路床底面的台阶时,根据路基填筑高度确定其台阶高度和位置,台阶面距离路床底面小于130 cm时作为一个台阶开挖,距离路床底面大于130 cm时分成100 cm 和>130 cm两个台阶高度开挖。路床部位作为一个台阶开挖,开挖位置为距离旧路硬路肩内侧向外30 cm处,台阶高度为80 cm。

(5)开挖过程中如出现土体较大位移时,应立即停止开挖,分析原因,采取措施防止塌方。

(6)对老路基结构物台背及砂砾石等透水性材料填筑的路基,在开挖时应根据具体情况,采取钢板支撑、钢木结合支撑、砼护壁支撑、砌砖等必要的防护措施。

1.2.4路基填筑

(1)路堤填料选择。加宽路基填料原则上应与老路基填料保持一致,并尽量采用砂砾等强度高、水稳定性好的材料填筑,禁止采用不符合规范要求的材料填筑路基。为节约工程造价和保护环境,对于老路基开挖台阶的土方及老路基边坡拆除的圬工和拆除的路面基层、底基层等材料,经改善处理,符合设计要求的也可用于路基填筑,但老路基的清坡土和基底清表土不得用于路基填筑。为使路基获得足够的强度、稳定性和抵抗路面荷载下产生的变形能力,保证路基、路面的综合服务水平,路基压实采用重型击实标准,路基压实度及填料强度应符合表1要求。

(2)施工放样。在路堤填筑前,测量人员首先应根据加宽路基设计宽度及其边坡坡度放样出加宽路基坡脚线,并用石灰撒出路堤填筑边线。为使路堤边缘压实度也能满足规范要求,路堤填筑边线应比加宽路基坡脚线超宽50 cm。

(3)路基填筑材料铺筑。施工时,施工人员事先根据运输路基填料车辆的运载量,路基试验段得出的填筑材料松铺厚度,计算出每车路基填筑材料的卸料间距。现场施工人员根据卸料间距在下承层上用白灰标示上土网格,并指挥运输车辆按照上土网格卸料。运至路基上的填筑材料首先由推土机粗平,粗平后应对路基填筑材料的含水量测定和调整。

(4)含水量调整。施工中,填筑材料摊铺后,及时安排试验技术人员对填筑材料的含水量进行检测,当填筑材料的含水量在试验确定的最佳含水量±2%以内时,可进行下道工序施工。如果路基填筑材料的含水量超过试验确定的最佳含水量的2%以上时,可采用犁靶翻晒等方法降低路基填筑材料含水量,直至路基填筑材料含水量降至最佳含水量的2%左右以内时,才可以开始下道工序施工。如果路基填筑材料的含水量小于试验确定的最佳含水量的2%以上时,可采用洒水车洒水的方法增加路基填筑材料含水量,直至路基填筑材料升至试验确定的最佳含水量的2%以内时,才方可开始下道工序施工。

(5)精平。路基填筑材料碾压前按照计算的摊铺标高,每隔10 m做出标高台,用平地机进行精平,精平后路基填筑材料应保持整体平整,表面平整度应满足规范要求。精平时应使路基横坡向加宽路基外侧倾斜,以利于路基排水。

(6)路基填筑材料的碾压。施工前,通过试验段确定适宜的压实设备和合理的碾压方案。施工时严格按照试验段总结的碾压组合顺序和碾压方式进行碾压。

压路机碾压时最大行驶速度不宜超过4 km/h;碾压时直线段由加宽路基边缘向老路基拼接处碾压,超高段时由低处向高处碾压;压路机碾压时一般重叠1/2轮;碾压时应遵循先轻后重、由慢到快的原则;碾压遍数应不少于路基试验段确定的碾压遍数;严禁在未成型的路段急转弯或调头;碾压时安排专人负责,确保碾压均匀。无漏压、无死角。

新旧路基拼接处,需适当提高压实度,台阶处死角部分采用吨位较大的钢轮配合小型冲击夯密实处理

路基过渡段施工方案

过渡段施工方案 一、编制依据: 1、新建西宝铁路客运专线DIK519+596.97~DIK520+395.6、DIK520+444.4~DIK521+772.78两段路基施工图(图号)西宝客专施(路)02-01-02 2、新建铁路西安至宝鸡客运专线施工图路基通用结构详图(图号)西宝客专施通(路)-01。 3、设计技术通知单(编号)XBLJ-05。 4、铁路路基施工技术指南及相关技术规范。 5、参考中铁一局集团郑西、武广、京沪、哈大等路基施工经验。 二、使用范围: 本方案适用于DIK519+596.97~DIK521+772.78段所有桥涵过渡段填筑。 三、编制目的 1、明确过渡段改良土和级配碎石的填筑工艺流程、操作要点。 2、检验设计参数。 3、确定施工参数、施工设备及施工工艺,为过渡段填筑大面积施工提供科学依据。 四、工程概况: 本段路基范围内共设12处过渡段填筑,4处桥台过渡段和8处涵洞过渡段。台后路堤填筑采用倒梯形过渡的方案。过渡段基床表层填料采用级配碎石(掺5%P·C32.5水泥),基床表层以下倒梯形部分分层填筑掺入3%P·C32.5水泥长度不小于20m,过渡段后4m范围内基床表层级配碎石掺5%P·C32.5水泥。线路纵坡1‰,为直线段。过渡段下部地基为预钻孔冲扩挤密桩和CFG桩。 过渡段主要分两种类型,路堤与桥台过渡段和路堤与涵洞过渡段,施工时应进行过渡段工艺性试验。我部过渡段工艺性试验选于DIK521+716(1-4.0m×4.0m)涵洞和漆水河特大桥西安台,平均填土高度6.5m。 1、取弃土场 过渡段取土场设计位置位于DIK526+000右9.0km庞家村,取土场面积113亩。弃土场选定在本段路基附近废弃砖厂,进行地基处理中桩挖土弃土。设计取

桥梁加宽改建施工指南(1)

桥梁加宽改建 一、基本要求 1、本内容适用于T梁、空心板及小箱梁桥的加宽改建。 2、收集旧桥的设计、竣工资料和地质资料,对全线原有桥梁构造物进行归类分析和现场调查,进行必要的研究、论证,以选择合理可行的施工方案。 3、桥梁的拼接加宽宜采用与原桥同跨径、同结构型式,力求标准化、装配化、外观一致性。 4、在桥梁加宽改建时,应将拟实施的技术方案与施工期的交通组织统筹考虑,做到技术方案与交通组织方案的协调统一,努力实现“施工过程不中断交通”的目标,将施工期对现有交通的影响程度降到最低。 二、上部构造与下部构造均不连接 1、一般规定 (1)下部盖梁和上部梁板新旧结构间采用在连接处设纵向缝完全分离的形式,如图1.1所示,加宽后新旧结构间各自受力、互不影响。

图1.1 上部构造与下部构造均不连接示意(2)加宽桥与原桥各自受力明确、互不影响,减小连接的施工难度,桥墩基础的沉降差异对上部结构的受力影响小。 (3)汽车荷载作用和基础沉降差异,桥梁新旧结构连接处往往会出现纵向裂缝宽度扩大,新旧结构间有明显的挠度差等病害。由造成桥面沥青混凝土铺装破坏,增加后期养生费用;而且由于新旧结构明显的挠度差影响行车舒适性、使行车安全性受损。 2、施工工艺 上部构造与下部构造均不连接施工工艺流程见图2.1。

图2.1 上部构造与下部构造均不连接施工工艺流程 三、上部构造与下部构造均连接 1、一般规定 (1)为使加宽桥与原桥形成完整的整体,减小各种荷载(包括基础不均匀沉降、汽车活载、温度荷载等)作用下新老桥连接处产生过大的变形,减小上、下结构某些部位的内力,上部结构与下部结构均采用连接,如图1.1所示。 (2)将加宽桥梁的上部结构与原桥对应部位横向通过植筋、浇筑湿接缝等方式连接起来,原桥下部结构的桥墩、桥台帽梁及系梁也通过植筋技术将钢筋和加宽部分新桥相应部位钢筋连接,然后浇筑混凝土,将新老桥梁连为一体。

高速铁路路基过渡段施工方案

路基过渡段施工方案 一、编制依据和主要技术标准 1.1编制依据 1、《高速铁路路基工程施工质量验收标准》 2、《高速铁路路基工程施工技术指南》 3、《云桂线广西段施工图》 1.2适用范围 适用于新建铁路路基过渡段施工。 1.3主要技术标准 铁路等级:Ⅰ级; 正线数目:双线; 设计行车速度:250km/h; 二、工程概况 正线路基长度共计共12146米,其中过渡段长度2690米,包括以下六种形式:路基与桥台连接处过渡段、路堑与隧道连接处过渡段、路堤与横向结构物连接处过渡段、路堤路堑过渡段、半挖半填过渡段、两桥(隧道)之间短路基过渡段。 隧路过渡段采用级配碎石掺5%水泥填料填筑,路涵、路桥及路堤与路堑过渡段基床底层及基床以下路堤采用级配碎石掺3%水泥填料填筑,基床表层采用级配碎石掺5%水泥填料填筑。 过渡段填筑在结构物混凝土强度达到设计强度及基坑回填验收合格后进行施工。 三、施工准备 1、施工队伍配置 为确保本工程的安全、优质、高效、如期完成,项目经理部下设四个专业路基施工队伍。 2、设备配置 依据施工质量、施工工期等要求,配备足量机械设备,提高机械利用率,统筹安排各种资源。

四、施工组织及安排 4.1施工人员安排 1、主要管理人员 表1 主要管理人员 4.2施工机械设备安排 过渡段路基填筑主要采用拌和站集中拌合,自卸车装运土方,挖掘机整平,振动式压路机碾压。所需机械设备见下表2。

4.3检测仪器、测量设备的配备 五、主要施工方法 5.1、路堤与桥梁过渡段施工 设置方式图如下:

(1)过渡段沿线路纵向为倒梯形,采用级配碎石掺水泥填料分层填筑,底宽5m,纵向坡度根据实际地形进行计算,满足过渡段长度不小于20m。 (2)必须待桥涵砼强度达到设计强度要求并完成基坑回填及防水层施工验收合格后方可进行过渡段填筑。过渡段施工前,应根据场地情况,采取相应的防排水措施并在桥台或涵洞侧面画填筑分层线。 (3)过渡段路堤应与其连接的路堤同时施工,并将过渡段与连接路堤的碾压面,按大致相同的高度进行填筑。 (4)根据施工情况确定主要施工工艺参数,报监理单位确认。分层压实厚度按35cm控制,台后2.0m范围外采用大型压路机进行碾压,在过渡段的桥台台尾后2.0m范围内采用冲击夯夯实,防止施工过程中碰到桥台,松铺厚度按20cm控制。当过渡段比路堤先施工时,向路堤方向合理延长,在施工路堤时再进行刷坡处理。 (6)台后基坑采用C15素混凝土一次连续浇筑回填,浇筑后高程与原地面高程一致。 (7)路基过渡段的外包土应与过渡段同步施工,施工过程中注意控制填料质量,不得使用级配碎石掺水泥质土填筑,后期绿色植被不容易成活,b值取1.8m。 (8)加入水泥的级配碎石填料宜在2小时内使用完毕。

旧桥加宽施工方案

防护加固建议性方案 一、工程简介 包茂高速孙家湾收费站北迁工程涉及主线一座1-8m空心板小桥加宽,新建加宽桥下部结构设计采用钻孔灌注桩基础,每测为两排Ф1.2米6跟桩基,全桥共计24跟,桩顶承台纵向长5.4m,右侧宽9.0m,左侧宽11.0m,台身为伏壁桥台,台身高7.01m。 该桥左侧加宽10.5m,右侧加宽8.5m。采取将原桥上部边板悬臂打掉改为中板。新建桥台与原桥台分离,新旧桥台间距1cm。 经过现场测量知该桥桥面至桩顶面高差8.2m。 该段原路基填料为风积沙,坡比为1:3,植被防护。 二、加固的必要性 加宽桥采取将原桥八字墙拆除后紧靠旧桥台身沿横向接长。施工加宽桥桩基时,必须将原八字墙及其后路基填土进行挖除,这样就会扰动现有包茂高速路基和路面,随着开挖加深,甚至造成路基坍塌,进而危及路基路面的稳定性和安全性。为有效防止危害的发生,开挖前必须对该段路基进行有效的加固保护。

三、加固方案 1、采用抗滑桩加固 先将加宽段路基段填方全断面填筑至现有路面标高;再在新旧路基接茬处的新路基范围内沿纵向钻孔灌注钢筋混凝土桩基,此为抗滑桩。拟用桩径1.2m,桩长20m,桩距1.7m,单侧布置8根桩基。详见下页方案1图。 2、打入钢管桩加固 先在新旧路基接茬处的新路基范围内沿纵向将钢管桩打入测量指定位置及标高;然后在钢管桩内注入1:2水泥砂浆,再在外侧土方开挖清理后插入1cm厚钢板。拟用钢管直径为 0.6m,桩长20m,桩距0.3m,单侧布置15根桩基。钢管桩外 侧焊接1cm厚钢板,防止路基填料外漏。详见下页方案2图。 四、施工顺序 方案1、测量放线→路基加宽段填筑→抗滑桩施工→桩外挂网喷锚防护→桩外侧土方开挖→加宽桥下部施工。 方案2、测量放线→钢管桩施工→管内灌注C15砼→桩外侧土方开挖→插入1cm厚钢板→加宽桥下部施工。 后CRK1+299.831加宽桥抗滑桩(钢管桩)示意图4页。 Xxxx

旧桥拆除专项施工方案

旧桥拆除专项施工 方案

南皮向阳桥改建工程 旧 桥 拆 除 方 案

新乡市恒达建筑安装工程有限公司

旧桥拆除专项施工方案 一、编制依据 1.《建筑拆除工程安全技术规范》JGJ147— 2.《安全防范工程技术规范》(GB50348- ) 3. 施工图纸 4. 我单位多年来累积的施工经验 二、旧桥概况 向阳二桥位于沧州市南皮县乡道 CH14-王桥村公路上(路线编码 CH17130927),路线等级四级,桥梁中心桩号 K1+534,桥梁编码 CH17L00 0927,与水流方向自西向东成90°夹角,旧桥为3x10m钢筋混凝土双曲拱桥,重力式墩台,全宽 5.5m,净宽4.5m,沥青混凝土桥面,修建于1975年,桥梁病害较为严重,上部承重构件损坏,评定为四类桥,因此对该桥拆除改建。 三、施工准备 1.踏勘现场,了解建筑物或市政设施拆迁情况,对与工程相突的情况应及时报告建设单位,确定方案。 2.搭设临时设施,编制临时用水用电方案与有关部门联系。 3.根据方案确定交通封路及交通疏导、路线、修筑临时战备道路。

4.经调查施工现场无地下管线。 4.拆桥施工机具、机械进场。 5.施工管理人员进场后,会同各管线单位做好现场的移交工作。 6.做好安全防护,对拆除后产生的可回收旧料做好分类堆放,及时运走。 四、施工方案 1.施工技术措施 经我公司专业人员实地考察,本着确保安全、环保、高效拆除的思想,我公司结合多年的实践经验,认为该桥梁应采用全机械作业方式进行拆除。 2.拆除工程施工工艺框图 施工准备 现场勘查 人员到位设备进场

3.拆除方法 旧桥拆除破碎时先将废弃物排入河道,再用挖机清除。三座桥桥面为现浇砼桥面,桥跨度较小,拟采用挖掘机拆除桥梁,采用液压破碎锤作业对桥面人行道栏、桥面、柱进行破碎,用挖掘机将废弃物挖运。拆除步骤从上而下依次为:护栏、破碎桥面、基础。 桥为钢筋砼,我公司采用破碎拆除法进行拆除,挖机必须随时待

路基加宽施工方案1

大兴区兴业立交改造工程 路基土方(五环加宽)分项工程施工方案 一、工程概况 兴业立交位于北京市大兴区南五环李营桥节点处,是大兴黄村地区与市中心区交通换转的重要节点。本工程西起五环路兴旺路出口,东至西红门南桥西侧,南起现况北兴路,北至现况南环路,包含五环路改造、新建Z1匝道、新建Z2匝道、新建1号地方路、改造2号地方路,共计5条道路。 本工程路基填筑主要工程数量:Z1匝道路基填方6200m3、Z2匝道路基填方6500m3、K13+427—K13+792(875)段路基填方14800m3。 二、施工计划 2014年10月15日~2015年04月20日 三、作业人员 工长3人、质检员3人,试验员4人,测量员5人,机械工20人,司机23人,工人40人。 四、施工机具 挖掘机5台,装载机7台,压路机8台,自卸汽车20辆,洒水车3辆。 五、路基填筑 1、填料的选择与试验 路基回填所用的填料为挖方段借用土石方,为碎石渣和碎石土填料,填料按规定要求进行鉴别试验。严格控制路基填料的强度、不符合规定的不能使用,挖方中非合适材料严禁用于回填路基。压路机压实填筑时分层压实厚度不大于20cm。 路基填料最小强度和最大粒径及最小压实度按照以下设计要求控制:

注:①表列数值为重型压实度标准;括号内为地方路CBR值;②新建管线肥槽回填时,须回填道路可用土,并分层回填压实,压实度不小于表列填方要求(重型击实标准),防止路基沉陷。 2、工艺流程 场地清理→测量放线→清表(挖除旧路边坡、清表及填筑前碾压、基底处理)→基底检测→分层填筑(填料选定与检测)→摊平(检查摊铺厚度)→整平→洒水或晾晒→碾压→成型检测验收 3、新旧路基衔接处理 (1)施工前截断流向拓宽作业区水源,开挖临时排水沟,保证施工期间排水通畅; (2)新旧路搭接处的旧路边坡应拆除老路路缘石、旧路肩、边坡防护、边沟等。将旧土路肩翻晒或掺灰处理重新碾压,以达到质量要求; (3)同时清除旧路肩边坡上草皮、树根及腐殖土等杂物,并由硬路肩开始下挖台阶,以消除旧路基边坡压实度不足,加强新旧路基的结合程度,减少旧路基结合处的不均匀沉降; (4)施工时,为保证老路堤与新路堤交界坡面搭接良好,需挖除清理法向厚度不宜小于30cm虚土,然后从老路堤坡脚向上按设计要求挖设50cm宽台阶。挖设断面见后附图“五环加宽新旧路基衔接处理断面图” 当老路堤高度小于2米时,老路堤坡面处理后,可直接填筑新路堤。严禁将边坡清挖物作为新路堤填料。 (5)加宽路堤填料选用与老路堤基本相同的填料作为填料,挡墙路基回填采用砂砾透水性材料回填。路基其它段落加宽部分若采用非透水性填料时,应在地基表面铺设砂砾或碎石垫层。 4、加宽部分路基基底清表(软基处理) (1)开工前,根据设计图纸尺寸放出路基坡脚、边沟位置,并结合施工现场实际情况,修建临时排水工程。同时沿加宽路基宽度外侧50cm左右设定边线,对此范围进行清表,平整压实,基底经监理工程师验收合格再进行回填填筑施工。 (2)首先在施工便道打通之后,推土机、平地机、挖掘机进场把路基填筑范围原地面的树木、草皮、腐殖土等杂料清除原地面,至合格基底。表土清除深度一般为10~30cm,清除的表土杂物堆弃于加宽路基坡脚线与道路红线之间。清表后树根须全部挖除

(完整版)旧桥维修施工方案

桥梁维修工程) 专项施工方案 编制单位:**建设集团有限公司 编制人: 审核人: 审批人: 编制日期:二〇一四年月 目录 1 ······························································································第一章编制依 据·········· 1 ··········································································

················第二章工程概 况··············· 1 ·······················································································第一节工程概况及地理位置 1 ····················································································第三章施工部 署···················· 1 ···············································································第一节·人员组 织·················· 2 ···························································第二节··················施工准 备····················· 2 ······································第三节···································材料用量计 划··················· 3 ························第四节··············································劳动力需用计划··················· 4 ···········第五节························································主要施工机具计划··················· 4 ···第六节······························································主要施工进度计划·····················4······························································第四章施工工艺、方法和技术························4···························································第一节处理方案··········································· :1. B2桥根据设计提出的桥梁现状病害,桥维修内容如下4··························································桥根据设计提出的桥梁现状病害,桥维修内容如下:2. B65··························································5···················································第二节维修材料及指标··········································混凝土 1.5 ·················································································································································钢材 2.5 ·····················································································································································浆砌片石 3.5 ·············································································································································.注入水泥原浆 45 ···································································································································.垫层砾(碎石)55·······························································································································5······················································第三节施工工艺、方法和技术要求························ .墩台基础处理 5 ····································································································1 ·······························.墩台身处理 7 ···················································································2 ····················································.上部结构8·························································································

路基过渡段施工方案

温福铁路福建段(Ⅰ标)路基过渡段施工方案报审表

路基过渡段施工方案 编制:郭志红 审核: 中铁十五局集团有限公司 温福铁路福建段(Ⅰ标)一工区 二〇〇八年四月三日

路基过渡段施工方案 我工区路基过渡段主要有桥路过渡段、路堤与横向结构物过渡段、隧路过渡段等,为确保过渡段施工质量,编制了过渡段施工方案,施工方案如下: 1、过渡段基底处理 过渡段基底处理应按设计要求与桥台、横向结构物、相邻路堤、相邻隧道的基底处理同时进行,过渡段基底原地面平整后,用振动碾压机碾压密实。 路堤与路堑过渡段按设计顺原地面纵向开挖,开挖坡面的纵向坡度及台阶开挖高度应符合设计要求。 2、基坑回填 桥台后基坑及横向结构物基坑应严格按照设计选用回填材料及时回填并分层压实,避免积水。 基坑采用混凝土回填时,回填材料和混凝土强度等级应符合设计要求。 3、基床表层以下过渡段级配碎石填层 3.1、过渡段应与相邻的路堤及锥体按一整体同时施工,并将过渡段与连接路堤的碾压面按大致相同的水平分层高度同步填筑并均匀压实。 3.2、桥台后2.0m范围外大型压路机能碾压到的部位应采用大型压路机碾压,大型压路机碾压不到的部位及在台后2.0m范围内应采用小型振动压实设备进行压实。

3.3、横向结构物两侧的过渡段填筑必须对称进行,并与相邻路堤同步施工。 3.4、涵背两端大型压路机能碾压到的部位宜采用大型压路机碾压。大型压路机碾压不到的部位宜采用小型振动压实设备进行压实。靠近横向结构物的部位,应平行于横向结构物背壁面进行横向碾压。 3.5、横向结构物的顶部填土厚度小于1m时,不得采用大型振动压路机进行碾压。 3.6、级配碎石中掺入水泥的品种、规格及质量应符合设计要求,加入水泥的级配碎石混合料宜在2h内使用完毕。 3.7、基床表层以下过渡段级配碎石填层的压实质量应采用地基系数K30、动态变形模量Evd和孔隙率n三项指标进行控制。 3.8、在填筑压实过程中,应保证桥台、横向结构物稳定、无损伤。 3.9、填料应分层压实。采用大型压路机碾压时,每层的最大压实厚度不宜超过30cm,最小压实厚度不宜小于15cm;采用小型振动压实设备碾压时,填料的虚铺厚度不应大于20cm,每压实层应平整无积水现象。 4、桥隧过渡段施工:当桥台与隧道进口较短时,设置刚性过渡段,基床表层为掺入5%水泥的级配碎石,表层以下1.7m范围内换填C20混凝土,顶宽10.5m(2.95+2.95+4.6)。 当需要设置无碴轨道时,整个基床厚2m、宽10.5m(2.95+2.95+4.6)范围内采用C20混凝土浇筑。

单侧路基加宽施工方案

单侧路基加宽施工方案 随着我国经济的高速发展,近几年我国的交通流量急速增长。原双向四车道高速公路在通行能力和使用质量上都已经无法满足需求,结合当前通行需求,很多国家的主干道都进行了加宽拼接。旧路加宽处理不当,就会出现路面开裂、路基沉陷等病害问题。所以,新旧路基间的衔接以及新旧路面结构层的不均匀沉降都是路基加宽施工中的关键技术,同时,安全保通工作也是工作中的重中之重。 1 路基加宽拼接施工工艺流程及操作要点 1.1施工工艺流程图 1.2主要施工操作要点 1. 2.1施工前准备 (1)按照规范要求对沿线导线点和水准点进行复测和加密。如果是两侧拼接加宽,由于旧路基两侧导线点无法通视,需在旧路基两侧各布设一条附合导线,并且两条附合导线应闭合。 (2)路基开工前每隔20 m用全站仪准确放出旧路基外边缘点,并在老路基护栏上用喷漆标上桩号。 (3)每隔20m对旧路基和加宽路基原地面进行复测,核对或补充横断面,发现和设计图纸不符时,查明原因及时处理。 (4)加宽路基施工前,对旧路基填料和加宽路基基底土进行相关试验。每千米每侧至少取2个点;土质变化大时,视具体情况增加取样点数。 (5)按照规范要求对计划的路基填料进行相关试验,特别是对不同来源、不同性质的填料进行相关试验。填料尽量选取和旧路基填料性质相近的材料,避免和减少因新旧路基填料性质差异引起的不均匀沉降,确保新旧路基衔接处的施工质量。 1.2.2原地面清表、回填(1)严格按照设计和规范要求将加宽路基基底范围内的树根全部清除,并将坑穴填平夯实。 加宽路基基底范围内的水井和墓穴用优质填料换填处理。 (2)按照设计和规范要求的清表厚度,对加宽路基范围内原地面表层的腐殖土、草皮、表 土等进行清理。 (3)按照设计和规范要求将加宽路基范围内的边沟、池塘等地段清淤要干净、彻底,然后按设计的地基处理方案施工。 (3)场地清理的范围为高速公路原路基坡脚至新加宽工程路基坡脚外1m的范围内。 (4) (5)原地面清表的同时,将旧路的边沟和隔离栅等相关设施拆除。 (6)加宽路基基底清表完成后,按照设计要求进行原地面填前压实处理,压实度不小于90%,然后回填至原地面。 (5) (7)对于部分基底含水量较高,清表后不易压实的路段,基底可采用翻挖、晾晒或掺灰 处理,也可采用换填一定厚度的砂砾处理。 1.2.3台阶开挖 (1)台阶开挖前,先对老路基边坡进行清坡处理,清坡不易一次全部清理完成,应边挖台阶边清坡,以保证旧路基的稳定。 (2)边坡清理完成后,按照设计要求准确放样出每层台阶的开挖线,保证开挖台阶线型直顺、位置准确。 (3)旧路基台阶开挖针对老路不同的路基填料采用不同的台阶尺寸.对于老路基填料为黏土、亚黏土和卵砾石土时,拼接处的台阶高宜为1.0m。宽为1.5m;对于老路基填料为砂土、粉砂土时,拼接处的台阶高宜为0.4 m,宽为0.6 m。 4)开挖拼接至路床底面的台阶时,根据路基填筑高度确定其台阶高度和位置,台阶面距离路床底面小于130 cm时作为一个台阶开挖,距离路床底面大于130 cm时分成100 cm 和>130 cm两个台阶高度开挖。路床部位作为一个台阶开挖,开挖位置为距离旧路硬路肩

旧桥改造施工方案(2)

目录 第一章编制依据与原则 (1) 1.1 编制依据 (1) 1.2 编制原则 (1) 第二章工程概况 (2) 2.1 大桥概况. (2) 2.2 工程概况. (2) 2.2.1 加固改造的基本要求如下 (2) 2.2.2 设计技术标准 (3) 2.2.3 项目主要负责人 (3) 2.2.4 主要工程数量表 (3) 2.3 工程特点、重点、难点 (3) 2.3.1 工程特点、重点和难点 (3) 2.4 设备、人员动员周期和设备、人员、材料运到施工现场方法 (3) 第三章桥梁工程施工主要加固改造内容 (4) 3.1 上部构造. (4) 3.2 下部构造. (4) 3.3 基础工程. (4) 3.4 主要人员安排(见表02 表) (5) 第四章主要施工方法和工艺 (6) 4.1 改造加固施工顺序 (6) 4.1.1 陀市桥改造施工之前先进行临时汽车便道的施工,待完成可通车后,再 全封闭陀市桥进行改造施工 (6) 4.1.2 依据设计图纸并结合现场情况进行旧桥拱上建筑、桥台桥墩顶部部分的 拆除。 6 4.1.3 主拱圈施工 (6) 第五章分项工程的施工方案 (16) 5.1 汽车便道施工方案 (16) 5.1.1 工程概况 (16) 5.1.2 便道施工方案 (17) 5.2 悬挂吊架搭设方案 (17) 5.2.1 编制依据 (17) 5.2.2 工程概况 (18) 5.2.3 施工部署 (18) 5.2.4 搭设方案 (19)

5.2.5 搭设流程 (21) 5.3 钢筋制作与安装方案 (21) 连州市G323线城南大桥绿化工程施工组织设计 5.3.1 工程概况 (21) 5.3.2施工部署 (21) 5.3.3施工方法 (22) 5.3.4质量保障措施 (26) 5.3.5 安全保证措施 (26) 5.4植筋方案 (27) 5.4.1 工程概况 (27) 5.4.2施工部署 (28) 5.4.3施工方法 (30) 5.4.4质量保证措施 (32) 5.4.5施工安全措施 (32) 5.5主拱圈砼工程方案 (32) 5.5.1 工程概况 (32) 5.5.2施工部署 (33) 5.5.3施工方法 (35) 5.6其它部位改造施工工序 (36) 5.7质量保障措施 (36) 第六章确保工程安全、质量和工期的保障和措施 (37) 6.1安全组织机构保证 (37) 6.2安全保障体系框图 (38) 6.3安全生产重点注意的事项 (40) 6.4质量目标及管理 (40) 6.4.1建立健全质量保证体系 (40) 6.4.2 提高全员质量意识 (40) 6.4.3狠抓工序质量,确保整体质量 (41) 6.4.4选派具有丰富施工经验的队伍 (41) 6.4.5开展标准化作业 (41) 6.4.6 严格技术标准、切实尊重监理 (42) 6.4.7严把材料关 (42) 6.4.8技术措施 (42) 6.5确保工程质量的措施 (43) 6.5.1为确保上述目标的实现,并创造优良工程,具体拟采取以下管理 措施 (43)

旧桥拆除施工方案【最新】

旧桥拆除施工方案 第一章编制说明 一、本桥拆除方案编制依据1施工招标文件及承包合同书;2原西善桥竣工图;3前三次拆桥方案论证会的专家意见;4公路桥涵施工技术规范;5公路桥涵设计技术规范; 二、编制说明:1本方案编制时经项目部、公司有关部门讨论通过,经监理工程师和业主组织专家审查通过后,方能予以实施;2本方案通过后由G205宁芜公路养护改善工程B1标项目经理部负责实施。 第二章西善桥老桥概况 一、老桥概况:西善桥位于西善桥街道,跨秦淮新河,全长126m,桥型为5-23.6m连拱肋拱桥,桥面纵坡0.6%,桥面行车道宽9.0m,人行道宽2*1.75m,桥面总宽12.5m,两侧挑梁有煤气、自来水管道通过,人行道下有光缆、电缆、电讯光缆通过。设计荷载等级为汽车-15级、挂车-80级。因工程建设需要,需将老桥拆除。该桥下部结构为钢筋砼灌注桩基础,在桩顶(距河床2.5m)设一厚70cm、宽130cm、长1400cm的横向系梁,桩上接Φ1.0m钢筋砼柱,高度约4.1m,柱顶设厚170cm、宽160cm、长1400cm的钢筋砼盖梁。上部为钢筋砼拱肋,

横桥向6榀,间距244cm,拱上立柱最高约310cm,立柱上设盖梁,其上安装6.5cm厚预制微弯板,砼现浇基层最厚处约40cm,沥青砂面层10cm。 二、拱桥设计参数:五孔净跨22.2米等截面肋拱桥,f/l=1/6,m=1.347。 三、西善桥老桥现状:经现场调查,西善桥老桥拱肋完整,未发现裂缝;拱肋间的横隔板与拱肋连接完整,未发现裂缝;拱肋上的立柱与拱肋连接部位部分表层砼风化剥落,连接钢板外露。 第三章施工准备 一、竣工图纸审阅项目部组织拆桥有关人员进行老桥竣工图会审,认真阅图,了解老桥的基本概况及各部分构件的工程量,掌握桥梁的结构及受力特点。 二、测量定线项目部配专业测量人员对老桥进行现场测量定位,并与老桥竣工图一一核对,桥梁平面位置与老桥相符。在每孔桩顶盖梁中点、拱脚、1/4拱肋、拱顶布置7个观测点,以便在拆桥过程中及时观测墩顶、拱肋的变形情况。

路基与桥涵过渡段专项方案

表A.0.1施工组织设计(方案)报审表 工程项目名称:新建吉林至珲春铁路客运专线工程施工合同段:JHS-Ⅳ标编号

新建吉林至珲春铁路客运专线工程 (GDK172+152-DK176+847.92 路基工程)路基与桥涵(隧道)过渡段施工方案 项目名称:新建吉林至珲春铁路客运专线工程 建设单位:长吉城际铁路有限公司 设计单位:中铁工程设计咨询集团有限公司 监理单位:黑龙江中铁建设监理有限公司吉图珲客专监理二标监理站施工单位:中铁九局集团有限公司吉图珲客专JHS-Ⅳ项目部四工区 编制人:年月日 审核人:年月日 审定人:年月日 审批人:年月日

路基与桥涵(隧道)过渡段施工方案 一、编制依据 1.编制依据 (1)《高速铁路路基工程施工质量验收标准》TB 10751-2010/J 1147-2011 (2)《高速铁路路基施工技术指南》铁建设[2010]241号 (3)新建吉林至珲春铁路施工图路基设计大样图集《路基与横向结构物过渡段设计图》吉珲大样图施路-04 二、工程概况 GDK172+152~DK176+847.92段路基全长4695.92m,本施工段落位于吉林省敦化市境内,前接西山隧道,后接大石头特大桥以填方、挖方形式通过。本段路基过渡段形式包括路隧过渡段、堤堑过渡段、路涵过渡段及路桥过渡段四种形式。过渡段位置统计如下:

三、设计文件说明 1. 路桥过渡段设计如图所示 2. 路涵过渡段设计如图所示

3.路堤与路堑设计如图所示 四、施工人员、机械设备及测量、检测仪器投入情况 1.施工人员情况: 为确保过渡段的顺利进行,中铁九局吉图珲项目部四工区路基架子队专门成立了过渡段试验段施工组织机构。如表 管理机构成员

拼宽路基标准化施工工艺工法

拼宽路基标准化施工工艺工法 1、施工前准备 1.1技术准备 1.1.1在旧路路基加宽前,对旧路路况进行详细调查,掌握路基病害成因并对路基病害进行处理。 1.1.2熟悉和掌握施工图设计文件及沿线地质、地形地貌资料,编制单项施工组织设计,向现场施工技术人员、进行书面的技术交底和安全较低。 1.1.3试验准备 (1)路基施工前、必须对路基填料土样进行相关试验。每公里至少取2个点;土质变化大时必须按实际情况增加取样点数。 (2)对来源不同、性质不同的拟作为路堤填料的材料进行复查和取样试验。土的试验项目包括天然含水量、液限、塑限、标准击实试验、CBR试验、颗粒分析、比重、有机质含量等。 (3)路基填料每5000m3或土质变化时必须重新取样进行试验。 1.1.4测量放样 (1)按照规范要求对沿线导线点和水准点进行复测和加密。如果是两侧拼接加宽,由于旧路基两侧导线点无法通视,需在旧路基两侧各布设一条符合导线,并且两条附合导线应闭合。 (2)路基开工前每隔100m用全站仪准确放出旧路基边缘点,在旧路基边坡上设置桩号牌,在加宽路基边缘放出路基边线,边线为设计坡脚线外0.5米处。 (3)每隔20m对旧路基和加宽路基原地面进行复测,核对或补充横断面,发现和设计图纸不符时,应查明原因及时处理。 1.1.5试验路段的施工 (1)试验段填筑的目的:找出填料在最佳含水量下达到各压实区规定的压实度和压实沉降差时,施工机械最佳组合方式、碾压速度、碾压遍数、松铺厚度、施工工艺等。 (2)试验段结束后对平整度、横坡、高程、压实质量等各项指标检查验收,满足规范要求及时将施工情况及检测结果编制试验段施工总结报监理工程师

桥梁加宽施工方案

成安渝高速公路四川段工程桥梁加宽施工方案 批准: 审核: 复核: 编制: 中电建路桥集团有限公司 二○一六年七月

目录 1工程概况 (1) 2施工日期及范围 (1) 2.1施工日期 (1) 2.2施工范围 (1) 3资源配置 (1) 3.1组织机构 (1) 3.2施工机具设备 (3) 4施工工艺及要点说明 (3) 4.1桩基施工 (3) 4.2墩柱施工方案 (7) 4.3盖梁施工 (9) 4.4支座垫石施工 (11) 4.5空心板梁桥 (11) 4.6桥面铺装 (12) 5施工注意事项 (12) 6安全施工措施 (14)

桥梁加宽施工方案 1工程概况 新老桥拼接采用上连下不连方案进行拼接,新老桥上部结构通过拼接形成整体共同受力,下部结构分离,独立受力,桥墩为柱式墩,桥台为柱式台,桩基为钻孔灌注桩。 2施工日期及范围 2.1施工日期 2016年8月20日至2016年10月20日。 2.2施工范围 本合同段桥梁加宽为成洛互通区朱家老药铺桥和绕城服务区桥,桥梁加宽包括老桥的护栏拆除、老桥两边边板的切除、老桥多余盖梁的切除、部分老桥铺装层的凿除(注:老桥铺装层网片筋不要切除) 和新建加宽桥的桩基、墩柱、桥台、盖梁、空心板、波形护栏等施工。 表2.2-1 新建加宽桥主要工程量 3资源配置 3.1组织机构 ⑴项目组织机构框架

图3.1-1 项目组织机构框图⑵项目班子成员及其简历 表3.1-1 工程项目班子成员一览表 ⑶项目部部门设置及人员配置 表3.1-2 部门设置及人员配置表

3.2施工机具设备 表3.2-1 施工机具设备表 4施工工艺及要点说明 4.1桩基施工 ⑴旋挖灌注桩的的工法及工艺流程 本工程钻孔灌注桩采用旋挖钻机成孔法进行施工,施工工艺流程图见下图,具体

高速互通与高速交汇加宽路基施工方案

高速互通与高速交汇加宽路基施工方 案

XX高速公路 XX段交汇路基加宽 施 工 组 织 设 计 路桥集团公路一局XX项目总承包一分部 XX年XX月XX日 XX公路XX互通与XX高速公路

XX段交汇路基加宽施工组织设计 一、工程概况 江西萍乡至上栗高速公路萍乡(青山)至妙岭段、妙岭至洪口界段是国家高速公路上海至昆明、泉州至南宁国家高速公路的重要联络线,是国道主干线京珠高速公路和大庆至广州国家高速公路的重要补充,本项目建成将大大改进萍乡市的内外交通的投资环境,有利于萍乡与长株潭地区的联系及提升长株潭城市群的辐射作用,促进萍乡市和赣西地区的社会经济的发展,对进一步完善国家和江西省干线公路网络、加快国家与江西省高速公路网的建设都具有十分重要的作用。 萍洪高速公路全长33.795公里,主线设计速度为100Km/h,路幅宽度为26米,双向四车道,设计荷载为公路-I级,与现有的昌金高速在昌金高速公路中心桩号为K506+336.773交汇,将主线和匝道与昌金高速公路连接段挖除,设置两座桥梁,主线、B匝道从昌金高速公路下穿,设置双山互通和昌金高速连接。本项目建设、设计、监理、施工单位如下: 建设单位:大益萍洪高速公路(江西)发展有限公司 设计单位:江西省交通设计院 监理单位:天津国腾监理咨询有限公司 施工单位:路桥集团公路一局七公司 为使萍洪高速公路与当前已经运营的昌金高速连接,在A1标段内施工图中设计了双山互通,双山互通和昌金高速交汇处采用了将原来昌金高速K506+529.204、K506+336.773段原有主线路基改为桥梁,增加了

昌金高速主线上跨现设计主线K506+336.773处的上跨桥梁,桥跨结构为4×22.5米后张法预应力砼空心板,桥跨长为89米;增加了昌金高速主线上跨现设计B匝道K506+529.773处的上跨桥梁,桥跨结构为3×20米后张法预应力砼空心板,桥跨长为60米,并设置了 A、B、C、E、F、G、H七条匝道与昌金高速连接,匝道连接处和现有的昌金高速公路进行拼宽处理。 二、双山互通内昌金高速路基加宽工方案 (一)、拼宽路基施工及安全防护 由于昌金高速K506+336.773跨线桥和K506+529.604上跨B匝道两座桥按照前期半幅施工半幅通车方案施工已经结束,昌金高速在 6月20日后能够恢复正常通车,双山互通内A、B、C、E、F、G、H七条匝道与昌金高速连接处主要是昌金高速公路拼宽施工和拼宽施工时的交通安全防护,设计影响范围为昌金高速K505+270-K507+460段落,共长2190米。 为不影响昌金高速公路的正常通车,同时保证昌金高速拼宽路基施工的正常进行,我部按照匝道施工先后顺序进行昌金高速对应拼宽处交通管制,保证昌金高速正常通车和安全,具体如下: 昌金高速开放双向交通后,右幅在距双山互通拼宽1600m处(K503+670)车辆前进方向设“前方施工”提醒标志,而且在距施工现场的硬路肩米内设置五道标志牌,分别是米处“前方施工”标志牌,

公路桥梁加宽改建工程施工方案

公路改建工程 桥 梁 施 工 方 案 申报单位: 工程名称: 编号: 申报日期:

K32+019.5桥施工方案 一、工程概况 本桥为老桥两侧加宽桥梁,桥位处现有一座3×16m预应力空心板桥,桥梁中心桩号为K32+019.5,设计交角为0度,老桥宽21m,桥长53.54m,因老桥梁板铰缝损坏较多,出现单板受力断裂现象,不满足通行要求。 本次对老桥进行改造,方案为加宽下部结构,预制加宽空心板,拆除老桥桥面系,检查梁板,对损坏的梁板进行更换,全桥更换支座。改造后设计标准:主线通行速度为80公里/小时;汽车荷载:新桥采用公路—I级,老桥维持现有老桥标准。改造后新老桥面结合采用∏板上部抬高,标准宽度:0.5m(护栏)+10.75m(行车道)+0.5m(护栏)+1m(中央分隔带)+0.5m(护栏)+10.75m (行车道)+0.5m(护栏),全宽24.5m,上部结构为3×16m预应力空心板。 二、施工准备 1、复查和了解现场:复查和了解现场的地形、地质、水源、电源、料源或料场、交通运输、农田水利设施、环境保护等有关情况在施工中要采取保护措施,防止损坏。 2、确定工程用地范围:根据施工图纸和施工临时需要确定工程用地范围,并与地方有关人员到现场一一核实、设立标志。 3、清除现场障碍:施工现场范围内的障碍以利施工的全面展开,特别是地上、地下电线、光缆、居民房屋、等设涉居民利益的障碍物,及时统计上报总监办、业主寻求解决。 4、办妥有关手续:上述占地和障碍物的拆迁等都必须事先与有关部门协商,办妥一切手续后方可进行。 5、作好现场规划:按照施工组织设计要求,设置料场、修筑临时道路。 6、设备、人员 (1)由项目经理部组织施工队负责人、技术人员、物资、设备等先遣人员进场,查看沿线情况。为全线开工作好前期准备工作。 (2) 桥梁施工人员已在12日至20日陆续赶到现场,参与施工准备及部分

路基过渡段施工技术方案

路基过渡段施工技术方案 1. 编制依据 根据新建福州至厦门铁路设计说明书《路基》的要求:“隧道与土质路基过渡、桥与路基、两桥(隧)之间短路基、路堤与横向结构物、半填半挖路基、路堤与路堑等均需要设置过渡段”。因此,对一般路基过渡段填筑压实施工进行方案设计。过渡段施工的技术标准依据现行的相关铁路路基施工与验收规范和标准。 2. 措施要求 根据新建福州至厦门铁路路基过渡段设计要求,对各种不同地段的路基过渡应采取如下工程技术措施: 1. 200km/h 时速地段路堤路堑过渡:当路堤与路堑连接处为坚硬岩石路堑时,在路堑一侧顺原地面纵向开挖台阶,台阶高度≥0.6m ,且应在路堤一侧设置过渡段,过渡段采用级配碎石填筑。当路堤与路堑连接处为软质岩石或土质路堑时,应顺原地面纵向挖成1:1.5的坡面,坡面上开挖台阶,台阶高度≥0.6m ,其开挖部分填筑应同路堤各相应要求。 2. 200km/h 时速地段桥台与路基过渡: 1) 过渡段长度:()20.6L h A =-+ 式中,L -过渡段长度(m );h -路堤高度(m );A -常数,取5m 。 2) 桥台与填方路基过渡段采用级配碎石填筑,过渡段应与其连接的路堤按一体同时施工,桥台后2m 范围内填筑的级配碎石内掺入3%水泥。 3) 桥台与挖方土质路基过渡段设C20混凝土及级配碎石掺3%水泥处理。 3. 200km/h 时速地段路堤与横向结构物(立交框构、箱涵等)过渡:除横向结构物顶面距地面高度小于1.0m 且不足路堤高度的一半时不设置过渡段,其他情况均设置过渡段,采用级配碎石填筑。当涵洞顶与路肩高差小于1.0m 时,涵洞顶以上填筑级配碎石掺3%