B1施工现场临设布置方案

B1施工现场临设布置方案
B1施工现场临设布置方案

目录

1 工程概况 (1)

2 道路布置 (1)

2.1 施工方法 (1)

2.2 道路平面布置图 (3)

4 围挡布置 (5)

5 洗车池布置 (6)

1 工程概况

本项目位于蠡湖大道以西,南湖中路以北,建筑面积约35万㎡。

2 道路布置

1)桩基及土方开挖施工阶段,场内铺设10m宽200厚毛石道路,供机械行走。

2) 基坑周边布置10m宽C25混凝土临时道路,做法为:下层200mm砖渣垫层,上层200mm厚C25路面,中间2%向两边放坡。见图2-1、图2-2。

图2-1 现浇混凝土道路平面图

图2-2 1-1剖面图

2.1 施工方法

2.1.1 施工流程

基层碾压→砖渣回填→模板安装→混凝土浇筑→混凝土养护→切缝→灌缝

2.1.2 基层碾压

采用大挖机碾压基层。

2.1.3 砖渣回填

在碾压处理完毕的基层上,铺一层砖渣,在撒铺好砖渣的路面上再进行碾压,碾压至密实度0.94;砖渣层200mm厚。

2.1.4 模板安装

道路按宽10米分两幅施工完成,每幅分段支设模板浇筑混凝土,道路中心向两边按2%放坡。模板采用木模板,材料应平整、坚固。木模应先涂脱模剂,模板支撑必须牢固、位置正确,支设的模板体系应牢固,防止模板移位。模板立模拼装完毕后,进行侧向弯曲、垂直度等检查。按道路设计标高用水平仪控制好模板顶标高。

2.1.5 混凝土浇筑

1)混凝土下料

本工程混凝土采用混凝土运输车直接放料,混凝土浇筑200mm厚;路面保持平整,高出自然地面10cm左右。

2)振捣

使用插入式振捣棒和平板式振捣器联合振捣作业。施工中严格控制坍落度,不得任意加水,不得有离析现象,超过初凝时间的混凝土,不得使用(加缓凝减水剂后可适当延长)。浇捣用插入式和平板式同时振捣,保证混凝土浇捣的密实,并减少侧面气泡的产生,混凝土振捣后随时用水平仪检测模板水平情况,对偏差部位及时进行调整。

3)砼路面的抹面

混凝土路面初凝后立即用抹光机抹光,边角等局部抹光机打磨不到之处可用微型手动抹光器抹光,将凸出石子或不光之处抹平,最后用靠尺板检查路面平整度,符合要求后用铁抹子人工抹光。

4)压纹

抹面完成后进行表面横向压纹处理。压纹时应掌握好砼表面的干湿度,现场检查可用手试摁,当用力摁能摁出印迹即可进行压纹。在两侧模板上搁置一根槽木,槽木平面朝下,凹面朝上,提供压纹机过往轨道,压纹机压纹时保证路线顺直。

2.1.6 养护

抹面完成后在路口处设置防护围档,以防人踩、车碾破坏路面,阴雨天还应用草袋覆盖。砼浇注完成12小时后,可拆模进行养护,养护选择浇水、覆盖草袋等方法。

2.1.7 砼路面的切缝

伸缝应与路面中心线垂直,缝壁必须垂直,缝隙宽度必须一致,缝中不得连浆。

缩缝采用锯缝,伸缩缝间距不大于6m,缝深6cm,宽5mm。切割时必须保持有充足的注水,在进行中要观察刀片注水情况。

2.2 道路平面布置图

图2-3 B1地块桩基及土方开挖阶段道路平面布置

图2-4 B1地块主体及装饰阶段道路平面布置

3 出入口布置

本工程在蠡湖大道需开设4个出入口,以满足施工需要,出入口编号为1#、2#、3#、5#,见图2-3。大门净宽度均为12m(门柱、门楼、门扇宽度均按比例放大),其中1#、5#出入口为主出入口,出入口设门楼、门禁、品牌墙、宣传室,见图3-1、图3-2。2#、3#出入口为次出入口,见图3-3。

图3-1 主出入口布局图

图3-2 主出入口效果图(大门改为自动伸缩门)

图3-3 次出入口效果图

4 围挡布置

施工现场周边围挡采用彩钢板围墙、彩钢瓦围墙,外表面涂装统一按CI标准实施,见图4-1、图4-2。

图4-1 彩钢板围墙做法

图4-2 彩钢瓦围墙做法

5 洗车池布置

施工现场出入口位置设置洗车台,其中1#、5#出入口设置存水洗车池和工字钢洗车台,2#、3#次出入口仅设置排水沟式洗车台,见图5-1~图5.3。

图5-1 存水洗车池

图5-3 排水沟结构洗车台

施工现场总平面布置方案综述-如何进行施工总平面布置

第一节现场概况及部署 一、现场概况 本工程现场场地较为狭小,周边道路狭窄,现场平面布置考虑充分利用现有场地,按功能划分施工区域及办公区域,施工各区域用围墙隔断,严格按照公司的现场管理手册执行,为保证现场的井然有序,采用隔断、油漆画线、标志板等方式表示区域的使用功能,施工现场平面布置详见附图。

二、部署 针对施工现场场地的实际因素,我公司特作如下部署: 1、在场地西北面(与**加工场紧邻)布置办公区供管理人员办公和工人住宿、生活卫生等设施,并按规定分区分隔。 2、我公司根据本工程施工总体部署对其不同施工阶段的划分,按照“方便施工,就近布置,见缝插针”的原则,将现场周边除建筑以外的空地合理利用,布置施工场地。 在现场的基础设施布置及数量见下表:

第二节现场平面分阶段布置及说明 一、下部结构施工阶段 1、平面布置: 我公司进场后根据遵义市安全文明施工要求标准进行围墙全封闭砌筑,在围墙的西北侧设大门、门卫值班室,并根据实际情况布置大型机械设备、小型加工设备以及施工用水用电等。 2、机械设备配备布置: 本阶段机械设备主要包括:塔吊、混凝土输送泵等,本工程布置1台塔吊,混凝土输送泵布置2台,布置在道路畅通靠近施工部位,并配置相应的泵管等。 3、加工场地布置: 我公司尽可能利用周边空闲场地进行钢筋、模板的加工,各施工标段循环进行施工,材料运输利用塔吊进行配合。 二、上部结构施工阶段 1、平面布置: 根据遵义市安全文明施工要求标准进行全封闭砌筑,在主出入口通道处设大门、门卫值班室,并根据实际情况布置大型机械设备、小型加工设备以及施工用水用电等。在土方回填完毕后,将围墙一周边界之间的空地全部硬化形成一条环形道路,作为施工机械、物资运输道路用。在场地内布置一处钢筋、木工加工区作为钢筋、模板加工场地。 2、机械设备配备布置: 机械设备配备有:塔吊、钢筋加工设备、木工加工设备、混凝土输送泵等。 3、加工场地布置: 在塔吊范围内合理布置钢筋、模板加工场地,并配备相应的加工机械。 三、装修施工阶段 保留原有围墙、大门以及现场临时施工通道,在场地内集中设立两台砂浆搅拌机用于装修阶段水泥砂浆的制备,砂浆拌制完毕后由翻斗车或小推车运至

场地布置方案()

施工场地布置方案 一、场地布置的主要原则。 1、布置根据 根据图纸、结合现场勘察情况,并考虑进度的总体安排,按照文明施工、安全生产的要求,对施工现场进行布置。现场的平面布置要考虑施工区域的划分、施工通道的布置、现场临时水电的布置、现场生产设施、现场办公以及生活区等内容,以保证现场生产的需要以及满足施工进度为前提。 2、布置原则 2.1合理布置各项施工设施,科学规划施工道路,尽量降低运输费用。 “有利于施工、方便生活、安全防火、和环境保护”要求。 3、施工总平面图 3.1施工围挡 进场后,视现场需要,必要时设立施工围挡,确保施工安全。 3.2施工现场便道 经现场踏勘,综合考虑本工程的现场条件,为保证车辆人员进出现场通畅,所需物资能及时运至现场。必要时在施工现场修建临时施工便道,并在适当位置设置出入口通道。 3.3材料堆场、材料库房。 材料堆场要设在临近出入口的位置,材料堆放要整齐。 3.4行政办公、施工区及临时设施的搭设 为满足现场施工需要,同时减小施工区对办公区的影响。现场内大致分为两个区,办公区,材料、机具堆码区。具体临设搭建要求为: (1)本工程用工高峰区达220人左右。 (2)现场设置办公室,会议室,设置独立厕所,单独设置进出的通道。 (3)办公室为开间3.6m,其进深为5m。 4、施工给排水平面布置 本工程施工用水按甲方指定点碰头取水。现场内排水主要依地势走向。污水经沉淀排入市政管网。排水范围包括生活污水排放和施工生产污水排放。

5、施工现场临时用电布置 本工程施工现场的电源位置由甲方及总包确定,供电现场供电线路按二个回路铺设,具体布置方式如下述: 5.1施工现场临时用电量确定及各支线路电缆线确定 5.2用电量的计算 本工程施工期间最大用电容量的确定以最高峰浇筑砼垫层和挡墙的施工阶段的施工用电量为准,这一期间投入较多的施工机械,应选择额定电容量为20KV(1)的配电房,方可满足现场施工用电要求。 5.3施工用电线路截面的确定:根据计算,查表得: (1)、办公、照明导线选择4mm2(2)X型铜芯绝缘线。 (2)、机械用电:选择一根20mm2的(2)X型铜芯绝缘线。 通州建总集团有限公司 横岭拆迁安置复建房三期4#-8#楼工程

文明施工措施方案说明

XXX小区项目 文 明 施 工 方 案 施工单位: XXXXXX建设工程有限公司编制人: 审核人: 审批人: 时间:年月日

目录 一、各级单位、企业文明施工的责任和义务。 1、建设单位的责任和义务; 2、监理单位的责任和义务; 3、总承包单位的责任和义务; 4、分包单位的责任和义务。 二、文明施工管理目标和措施。 1、管理目标; 2、施工措施。 三、文明施工措施费的使用。 1、建设单位文明施工措施费拨付计划; 2、施工单位文明施工措施费使用计划。 四、施工图牌标识。 五、临时生活设施的建造。 1、宿舍; 2、食堂; 3、厕所。 六、施工现场和生活区的有关责任制度。 七、防治大气、水土、噪音污染和改善环境的措施。 八、卫生饮食、防暑降温、防寒保暖等工作的防范与应急措施。 九、施工现场总平面布置图。

一、各级单位、企业文明施工的责任和义务 1、建设单位的责任和义务 (1)建设单位应当按计划批准的开工项目向工程所在地县级以上地方人民政府建设行政主管部门办理施工许可证手续。未取得施工许可证不得擅自组织开工。 (2)建设单位经批准取得施工许可证后,应当自批准只之日起两个月内组织开工;因故不能按期开工的,建设单位应当在期满前向发证部门说明理由,申请延期。 (3)建设工程开工前,建设单位应当指定施工现场总代表人,并将总代表人的姓名及授权事宜书面通知施工单位,同时报发证部门备案。 (4)建设单位应按计划程序,按时进行文明施工措施费拨付。(5)建设单位向施工单位提供施工现场及毗邻区域内供水、排水、供电、供气等基本设施。 2、监理单位的责任和义务 (1)本着对业主、国家负责的精神,遵循守法、诚信、公正、科学的职业准则,尽职尽责,确保工程文明、安全施工,实现合同制定的质量、工期、投资三大目标。 (2)监理部要求施工单位推行全员参与文明施工管理,建立健全文明施工保证体系,做到开工之前有方案,施工过程有措施,操作安全有保障。 (3)监理单位相应制定安全、文明予控措施和管理程序。

施工现场总平面布置方案设计.

第一节现场概况及部署 说明:因本工程规划设计尚未通过,此案根据现有规划总平面图结合现场勘察编制,仅作参考用途,待正式施工图纸审查通过后加以完善。 一、现场概况 本工程现场场地较为狭小,边道路狭窄,现场平面布置考虑充分利用现有场地,按功能划分施工区域及办公区域。格按照公司的现场管理手册执行,为保证现场的井然有序,采用隔断、油漆画线、标志板等式表示区域的使用功能,施工现场平面布置详见附图。 二、部署 针对施工现场场地的实际因素,我公司特作如下部署: 1、在场地东北角处面与(10F酒店紧邻)布置办公区供管理人员办公、生活卫生等设施,并按规定分区分隔。 2、我公司根据本工程施工总体部署对其不同施工阶段的划分,按照“便施工,就近布置,见缝插针”的原则,将现场边除建筑以外的空地合理利用,布置施工场地。 在现场的基础设施布置及数量见下表:

第二节现场平面分阶段布置及说明 一、下部结构施工阶段 1、平面布置: 我公司进场后根据市安全文明施工要求标准进行围墙全封闭砌筑,在围墙的东侧设大门、门卫值班室,并根据实际情况布置大型机械设备、小型加工设备以及施工用水用电等。 2、机械设备配备布置: 本阶段机械设备主要包括:塔吊、混凝土输送泵等,本工程布置4台塔吊,混凝土输送泵布置5台,布置在道路畅通靠近施工部位,并配置相应的泵管等。 3、加工场地布置: 我公司尽可能利用边空闲场地进行钢筋、模板的加工,各施工标段循环进行施工,材料运输利用塔吊进行配合。 二、上部结构施工阶段 1、平面布置: 根据市安全文明施工要求标准进行全封闭砌筑,在主出入口通道处设大门、门卫值班室,并根据实际情况布置大型机械设备、小型加工设备以及施工

临建场地布置施工方案

南京地铁七号线施工总承包D7-TA02标5工区 项目临建施工方案编制: 审核: 批准: 中铁上海工程局集团有限公司 南京地铁七号线工程D7-TA02标 土建五工区项目经理部 2017年11月

目录 1编制依据及原则.......................... 错误!未定义书签。 1.1编制依据 0 1.2编制原则 0 2工程概况 (1) 2.1临建施工概况 (1) 3施工部署 (1) 3.1施工现场条件 (1) 3.2主要工程数量 (2) 3.3施工总体部署 (2) 3.3.4施工进度安排 (9) 3.4施工资源配置 (9) 4临建施工 (10) 4.1施工流程 (10) 4.2项目驻地及民工院围挡 (11) 4.3项目驻地及民工院平整 (12) 4.4生活、办公区设施布置 (12) 5、质量保证措施 (16) 6、临建安全保证措施 (17) 7、施工现场文明施工 (18)

8、施工现场消防及交通保证措施 (20) 8.1消防保证措施 (20) 8.2维护交通措施 (20)

1编制依据及原则 1.1编制依据 (1)《施工现场临时建筑物技术规范》JGJ/T 188-2009 (2)《建设工程施工现场消防安全技术规范》GB 50720-2011 (3)《建设工程施工现场管理规定》中华人民共和国建设部令第15号 (4)《施工现场临时用电安全技术规范》JGJ46-2005 (5)《中铁上海工程局集团华海工程有限公司“职工小家”有形(标准化)建设指导手册》 (6)总包部下发南京地铁7号线部分标准化施工手册驻地及施工现场临建标准化手册 (7)本公司类似工程施工经验及本工程施工合同 (8)施工现场调查 1.2编制原则 (1)严格执行施工过程中涉及的相关规范、规程和技术标准。贯彻执行国家和地方政府的方针政策、法律法规。 (2)结合城市道路和可使用地块布置施工场地,对运输车辆的进出及走行线路合理规划,制定切实可行的交通组织方案。 (3)本着便民、利民的原则进行方案的选择,同时尽最大的可能为业主、周边环境、其他承包商提供方便。 (4)临时房屋及其他设施布置力求美观、安全、经济、合理、实用。

文明施工方案及措施

文明施工方案及措施 文明施工措施是实现文明施工目标,完成科学管理的重要途径。争取合理的措施,是落实本工程文明施工目标的根本保障,通过建章立制,组织管理、现场管理等措施达到文明施工的目的。文明施工措施费优先投入,保证文明施工顺利进行。 1、健全文明施工管理组织 施工现场成立以项目经理为组长,管理层全员参与的施工现场文明施工管理组织,从下至上层层分工管理,同时接受公司的监督检查。 2、健全管理制度 通过建立有效的约束机制和激励制,提高工地文明施工的积极性和创造性。 2.1按专业、岗位建立个人岗位责任制度,持牌子上岗,各负其责,做到文明施工,人人有责。 2.2推行奖罚制度,做到赏罚分明,调动职工的积极性,根据岗位、责任大小,制定奖、罚细则,坚持奖、惩兑现,形成责、权、利统一。 2.3严格按照《建筑施工安全检查标准》(JGJ59—99)中文明施工检查评分表,实行定期或不定期的检查制度,发现不足及时整改,检查结果张榜公布,互相对照,找出差距,达到共同促进,使文明施工良性循环。 2.4每周一次的会议制度,分析前段文明施工情况,协调解决存在的问题,布置下周布置文明施工计划,使文明施工有条不紊地开展下去。 2.5加强教育培训工作 人是文明施工的创造者,加强职工和民工的文明施工素质教育尤为重要,特别要注意对民工的岗位教育工作。通过短期培训,技术交底、登黑板报、看录相、电视等方法狠抓教育工作,提高全体人员的文明施工思想意识和理论水平。专业管理人员要熟悉掌握文明施工标准,经常性地对职工、民工宣传教育,使他们自觉地遵守文明施工各项制度,积极投入到工地文明施工中去。 3、制度文明 制定工地标准管理规定,结合本公司及工程实际情况,以安全为突破口,以质量为基础,狠抓“窗口”达标,推动“两新”活动和全面、全方位、全过程、全员开展创建文明工地活动,制定文明工地标准管理规定。

施工现场文明施工实施方案.

民机飞行作动系统开发项目 安 全 文 明 施 工 方 案 编制人: 审核人: 审批人: 日期: 一、工程概况 本工程为民机飞行控制作动系统开发项目。本开发项目共分3个单体结构,综合厂房,门卫房,地下水泵房等。 综合厂房:为3跨厂房,长度105米,宽度64米,建筑面积7238.38平方米。单层门式刚架结构, 最大屋脊高度为为10.875米,主要结构跨度为28米。基础采用静压管桩基础,钢柱及钢梁均为焊接H型钢;屋面板采用0.8mm厚彩钢板下铺100mm厚玻璃丝棉,墙面板采用双层彩钢板中间夹75mm厚玻璃丝棉。

门卫房:为单层框架结构,采用独立基础,长度12.5米,宽度2.5米,层高3.5米,建 筑面积31平方米。 地下水泵房:为剪力墙结构,采用筏板基础,长度11.75米,宽度9.35米,层高2.8米,建筑面积100平方米。 其临时设施规划位置详见施工现场平面布置图 二、编制原则及依据 1、以《建筑法》《建筑施工安全检查标准》《陕西省建筑施工安全技术资料管理规定》《建筑施工现场管理标准图解》等国家、地方法律法规及相关标准为准则。 2、依据建筑总平面图、工程概况、施工总平面图、技术规范和临时设施建筑标准、尺寸及建设计划编制。 3、按照施工现场的具体实际情况,满足现场施工和生活需要,本着物尽其用、合理利用施工现场有效空间,最大限度发挥其效用,同时尽量保持施工现场周边生态环境的原则。 三、现场布置 详见施工现场布置图 四、文明施工实施方案 (一现场围挡 A 现场新建围挡墙使用符合规定要求的砖砌体围墙。 B 围挡墙保持整洁,墙下不堆放物料、器具等,不用围挡墙做挡土、挡水墙或做宣传牌、机械设备等的支撑。

施工场地布置方案

施工场地布置方案 This manuscript was revised by the office on December 10, 2020.

施工场地布置方案 一、场地布置的主要原则 1 布置根据 根据图纸、结合现场堪察情况,并考虑进度的总体安排,按照文明施工、安全生产的要求,对施工现场进行布置。现场的平面布置要考虑施工区域的划分、施工通道的布置、现场临时水电的布置、现场生产设施、现场办公以及生活区等内容,以保证现场生产的需要以及满足施工进度为前提。 2 布置原则 合理布置各项施工设施,科学规划施工道路,尽量降低运输费用。 科学确定施工区域和场地面积,尽量减少专业工种之间交叉作业。各项施工布置都要满足“有利于施工、方便生活、安全防火和环境保护”要求。 3. 施工总平面布置

施工围挡 进场后,视现场需要,必要时设立施工围挡,确保施工安全。施工现场便道 经现场踏勘,综合考虑本工程的现场条件,为保证车辆人员进出现场通畅,所需物资能及时运至现场。必要时在施工现场修建临时施工便道,并在适当位置设置出入口通道。 材料堆场、材料库房。 材料堆场 材料堆场要设在临近出入口的位置,材料堆放要整齐。 . 行政办公、施工区及临时设施的搭设 为满足现场施工需要,同时减小施工区对办公区的影响。现场内大致分为二个区,办公区,材料、机具堆码区。具体临设搭建要求为:

(1)本工程用工高峰期达220人左右。 (2)现场设置办公室,会议室,设置独立的厕所,单独设置进出的通道。 (3)办公室为开间4m,其进深为5m。 4. 施工给排水平面布置 本工程施工用水按甲方指定点碰头取水。现场内排水主要依地势走向。污水经沉淀排入市政管网。排水范围包括生活污水排放和施工生产污水排放。 5. 施工现场临电布置 本工程施工现场的电源位置由甲方及总包确定,供电现场供电线路按二个回路铺设,具体布置方式如下述: 施工现场临时用电量确定及各支线路电缆线确定 用电量的计算 本工程施工期间最大用电容量的确定以最高峰浇筑砼垫层和挡墙的施工阶段的施工用电量为准,这一期间投入较多的施工机械,应选择额定电容量为20KV⑴的配电房,方可满足现场施工用电要求。施工用电线路截面的确定:根据计算,查表得: ⑴、办公、照明导线选择4mm2⑵X 型铜芯绝缘线。 ⑵、机械用电:选择一根20 mm2的⑵X型铜芯绝缘线。 2011-12-25

施工平面布置方案要点

施工平面布置方案要点 一.布置原则 1、施工平面布置应严格控制在建筑红线之内。 2、平面布置要紧凑合理,尽量减少施工用地。 3、尽量利用原有建筑物或构筑物。 4、合理组织运输,保证现场运输道路畅通,尽量减少二次搬运。 5、各项施工设施布置都要满足方便施工、安全防火、环境保护和劳动保护的要求。 6、在平面交通上,要尽量避免土建、安装以及其他各专业施工相互干扰。 7、符合施工现场卫生及安全技术要求和防火规范。 8、现场布置有利于各子项目施工作业。 9、考虑施工场地状况及场地主要出入口交通状况。 10、结合拟采用的施工方案及施工顺序。 11、满足半成品、原材料、周转材料堆放及钢筋加工需要。 12、满足不同阶段、各种专业作业队伍对宿舍、办公场所及材料储存、加工场地的需要。 13、各种施工机械既满足各工作面作业需要又便于安装、拆卸。 14、实施严格的安全及施工标准,争创省级安全文明工地。

二、布置内容 ▲▲▲ 1、拟建的建筑物或构筑物,以及周围的重要设施。 2、施工用的机械设备固定位置。 3、施工运输道路。 4、水源、电源、变压器位置,临时给排水管线和供电、动力设施。 5、施工用生产性、生活性设施(加工棚、操作棚、仓库、材料堆场、行政管理用房、职工生活用房等) 6、机械站、车库位置 7、一切安全、消防设施位置。

三、布置步骤▲▲▲ 场外交通的引入(铁路运输、水路运输、公路运输)→仓库与材料堆场的布置→加工厂布置→布置内部运输道路→行政与生活临时设施布置→临时水电管网及其他动力设施的布置 1、场外交通的引入

设计全工地性施工总平面图时,首先应从研究大宗材料、成品、半成品、设备等进入工地的运输方式入手。当大宗材料由铁路运来时,首先要解决铁路的引入问题; 当大批材料是由水路运来时,应首先考虑原有码头的运用和是否增设专用码头问题;当大批材料是由公路运入工地时,由于汽车线路可以灵活布置,因此,一般先布置场内仓库和加工厂,然后再布置场外交通的引入。 2、仓库与材料堆场的布置 通常考虑设置在运输方便、位置适中、运距较短并且安全防火的地方。区别不同材料、设备和运输方式来设置。 (1)当采用铁路运输时,仓库通常沿铁路线布置,并且要留有足够的装卸前线。如果没有足够的装卸前线,必须在附近设置转运仓库。布置铁路沿线仓库时,应将仓库设置在靠近工地一侧,以免内部运输跨越铁路。同时仓库不宜设置在弯道处或坡道上。 (2)当采用水路运输时,一般应在码头附近设置转运仓库,以缩短船只在码头上的停留时间。

施工现场安全文明布置方案-文档

XXX商住楼项目施工总承包 施工现场安全文明布置实施方案 编制人: 编制日期: 审核人: 审核日期:

目录 一、工程概况 (2) 二、施工总平面布置原则 (2) 三、施工现场场地布置 (3) 四、人员组织架构 (14) 五、现场平面布置图 (15)

XXX商住楼项目施工总承包 施工现场安全文明布置实施方案 一、工程概况 二、施工总平面布置原则 施工总平面布置合理与否将直接关系到施工进度并能反映现场安全文明管理水平,为保证现场施工顺利进行,确定平面布置原则为: 1、在满足施工的条件下尽量节约施工用地; 2、在满足施工要求和文明施工的前提下,尽可能节约临时设

施的建设投资; 3、在保证场内交通运输畅通和满足施工对材料要求的前提 下,最大限度地减少场内运输,特别是减少场内二次搬运; 4、在平面交通上,要尽量避免土建、安装及其它生产单位相 互干扰; 5、符合施工现场卫生及安全技术需求和防火规范; 三、施工现场场地布置 1、施工临时围墙建设 ⑴、临时围墙采用彩板、钢管搭设,抗风6~8级,钢管间距2.5米,用短钢管打入土中,确保牢固,外冒长度不小于700,间距5m 立杆,设置底座,用混凝土灌注,上部立杆与水平杆连接。离地200。钢管长1.8m间距2.5米,见下图:

⑵、每一立杆背后用斜钢管支撑,斜钢管与立杆形成60度角,具体见下图: 钢管,长1.8米,间距1800 短钢管打入土中,保证牢 固,外冒长度不小于700埋设钢管时必须拉线,保证钢管纵向一线 水平钢管 天蓝色彩钢板,900*2000彩钢板搭接不少于100mm 自然土面 天蓝色彩板,900*2000 彩板搭接不少于100mm 钢管,长1.8m ,间距2.5m 间距5m 立杆,设置底座

文明施工及场地布置方案

XXXXX项目 文明施工及场地布置专项 方案 XXXXX项目经理部 XXX年XX - 1 -

目录 1.工程概述········································································································ - 3 - 2.编制依据········································································································ - 3 - 3.安全文明施工·································································································· - 3 - 3.1文明施工组织机构设置 ············································································· - 3 - 3.2组织人员名单 ························································································· - 3 - 3.3组织人员职责 ························································································ - 4 - 3.4安全文明施工组织机构图 ·········································································· - 5 - 3.5联系方式 ······························································································· - 5 - 3.6安全文明施工管理措施 ············································································· - 6 - 3.6.1封闭管理······················································································· - 6 - 3.6.2施工场地 ······················································································ - 6 - 3.6.3材料堆放 ······················································································ - 6 - 3.6.4现场防火······················································································· - 7 - 3.6.5治安综合治理 ················································································ - 7 - 3.6.6施工现场标牌················································································· - 7 - 3.6.7宿舍管理 ······················································································ - 7 - 4.施工场地部署·································································································· - 7 - 4.1布置根据 ······························································································ - 7 - 4.2布置原则 ······························································································ - 7 - 4.2.1经济性原则: ··············································································· - 8 - 4.2.2实用性原则: ··············································································· - 8 - 4.2.3方便管理原则: ············································································ - 8 - 4.2.4安全性原则: ··············································································· - 8 - 4.2.5环保性原则: ··············································································· - 8 - 4.3、施工场地布置 ······················································································ - 8 - 4.3.1大门布置 ····················································································· - 8 - 4.3.2施工围挡 ····················································································· - 9 - 4.3.3施工现场便道 ··············································································· - 9 - 4.3.4、施工给排水平面布置 ···································································· - 9 - 4.3.5、施工现场临时用电布置 ································································· - 9 - 4.3.6、施工现场消防布置 ····································································· - 10 - 4.4临边防护、区域隔离围挡········································································ - 10 - 4.4.1大网片式工具化防护围栏 ······························································ - 10 - 4.4.2斜网片式工具化防护围栏 ······························································ - 11 - 4.5标示标牌 ···························································································· - 12 - 4.5.1安全警示标志 ············································································· - 12 - 4.5.2材料标识 ··················································································· - 12 - - 2 -

盾构施工场地临建布置方案

昆明轨道交通* **盾构区间临建方案 1.编制说明及依据 为高起点、高标准地建设好 * **盾构区间工程,按照总体施工方案的要求,根据昆明轨道交通有限公司及股份有限公司的相关管理标准及要求,编制了《昆明轨道交通 * **盾构区间临建方案》,以实现施工现场的标准化、规范化管理。 主要编制依据如下: (1)昆明地铁建设工程安全和文明工地标准; (2) 股份有限公司企业视觉识别系统管理手册; (3)昆明轨道交通3号线工程招标文件及投标文件; (4)施工设计图纸及其他收集的工程资料等。 2.工程概况 2.1区间概况 昆明市轨道交通3号线工程西标段起点石咀站,终点市体育馆站,线路沿春雨路、人民西路敷设,全长。 盾构区间施工 场地人民西路 春雨路 图2-1 **盾构区间位置示意图

昆明轨道交通3号线工程西标段 **盾构区间,区间工程起点为云南冶炼厂专有铁路线东侧的眠山站,沿人民西路向西南方向左拐,经过春雨路、昆瑞路和人民西路三路交汇处,进入春雨路, 并沿春雨路行进, 绕过大沙沟桥后抵达西山盐政管 理所东侧的马街站。 区间线路右线起止里程为YCK6+~YCK8+,长(含短链),左线为ZCK6+~ZCK8+,长(含长链)。全线长。 3驻地建设 **盾构区间项目经理部驻地建设 驻地建设分为现场驻地与经理部办公驻地,现场驻地主要用于现场管理人员住宿、工作,经理部驻地为生活区和办公区。 **盾构区间经理部办公及生活区租赁昌源中路路与石武客运专线交汇处的高新综合执法大楼5、6层。 图3-1 **盾构区间经理部办公楼位置示意图

图3-2 **盾构区间经理部办公楼外貌 图3-3 5楼宿舍区示、办公室示意图 图3-4 6楼办公室示意图 经理部办公区5层为生活区及会议室,6层为办公室。 图3-6 上墙制度图片 图3-5 大门门牌图片 图3-7 办公室布置 楼梯 电梯 经理办公室 厕所食堂 工程部、机电部等部门办公室 厕所 楼梯 天台 非项目部区域 非项目部区域 非项目部区域 财务部 合同部总工室 非项目部区域 楼梯 电梯 厕所厕所 楼梯 非项目部区域 非项目部区域 宿舍宿舍宿舍 宿舍 宿舍 宿舍 宿舍 会议室 洗漱间 ⑤

(完整word版)施工现场总平面布置

4施工现场总平面布置 2.4.1施工总平面布置的原则 (1)整体规划 根据业主的整体规划部署,合理安排施工临建的位置。 施工总平面的布置应符合国家、市有关建筑工程施工现场安全文明的规定,同时应根据施工组织设计分阶段进行规划; 对涉及总平面的场地进行区域划分,使办公、生活、施工等区域独立、便于管理。详见附表五《施工总平面图》。 (2)用地规模及范围 临时设施的布局既要符合施工组织设计对人员、物资的要求,又要最大限度地缩短工地内运输距离,以减少二次搬运,降低工程成本,加快施工速度。因此我们在投标过程中考虑尽量紧缩综合楼工程的临时用地,使其布置合理、紧凑,并能充分满足施工期间人员居住及物资存储、加工及调配,附表六《临时用地表》。(3)道路布置 在施工期间,建筑物四周应保证道路畅通,道路做法应满足车辆运行要求,在施工现场平面交通上,尽量避免土建、安装交通运输的相互干扰。 (4)涉及职业健康内容 为保证施工人员有安全、良好的休息环境,工人生活区域应与施工区域分离,降低夜间施工产生的噪音对工人休息的不良影响;生活区及施工区都应该符合国家、地方对施工现场卫生、安全、防火、劳动保护的要求和规定。 (5)现场平面布置的时效性 应根据不同阶段进行调节,这种调节应符合阶段性施工对现场的要求,现场平面随着工程施工进度进行布置和安排,阶段平面布置要与阶段施工重点相适应。在现场平面布置时,各类建筑物、大型机械的位置尽可能避开室外管道等施工的位置,如不能避开,在室外工程施工时必须拆除临时设施,确保室外工程提前插入施工。 (6)现场机械布置

机械的选择及施工场地的布置应满足施工需要,紧凑布置,垂直运输机械的布置位置应充分考虑其覆盖或影响范围;钢筋、木工等加工机械的布置应满足施工高峰时期的需要。 (7)临电、临水 场地配备的一级、二级配电箱的数量及位置可以满足相应机械的功率要求,各类线路的敷设及配电箱(柜)应满足国家规范及济南地区安全监督部门的规定。配备的供水线路及终端设施应满足施工阶段现场及生活需要;消防设施的布置满足防火要求。 排水沟应通畅,以保证大雨时工地无积水;现场设排污、废弃物处理设施的布置,在混凝土地泵及砂浆搅拌机处设沉淀池,污水经处理后流入渗井进行排水。(8)门卫设置 现场主要出入口处设门卫室。重要材料堆放场地面进行硬化处理特殊材料要入库保存,并做好防腐、防锈等保护措施。 (9)有利于安全文明施工 重点加强环境保护和文明施工管理的力度,使现场始终处于整洁、卫生、有序合理的状态,使该施工现场在环保、节能等方面成为一个名副其实的绿色环保工地。 2.4.2临时道路、现场交通组织方案 (1)交通道路设计 a外围道路 经过现场踏勘,建设单位提供的临时外围道路,可以作为主要交通道路使用。 b场区内道路 场区内沿建筑物外围设置道路,路宽4.5米,做法为800mm厚山皮石,各区施工时便于混凝土布料车通行临时道路采用1000mm厚山皮石。 (2)现场交通组织方案 a现场管理 1)首先按批准的施工组织设计的施工总平面图布置要求布置临时施工道路;2)建立临时道路管理制度,车辆进场后必须遵守各规章制度。

场地布置规划方案

施工场地布置规划方案 本场地规划方案的编制是为南通兴东机场跑道沥青砼加盖工程施工场地营建提供系统的技术文件,藉此指导该营建工作的技术和施工管理,以确保优质、安全、快速、文明、地完成施工场地营建任务。 一、编制原则 1、安全第一的原则 本工程属于白天不停航夜间施工,必须确保飞行安全。在编制中始终按照技术可靠、措施得力、确保安全的原则确定施工规划方案。 2、优质高效的原则 加强领导,强化管理,优质高效。根据我们在施工组织设计中明确的质量目标,施工强化标准化作业,控制成本,降低工程造价。3、确保工期的原则 根据业主对本合同段得工期要求,编制科学的、合理的、周密的施工方案,合理安排进度,按网络控制,搞好工序衔接,实施进度监控,实现工期目标,满足业主的要求。 4、科学配置的原则 根据本合同段的工程量及各项管理目标的要求,在施工组织上按科学配置人员、设备,选派有施工经验的管理人员,专业化施工队伍施工。投入高效先进的施工设备,确保流动资金的周转使用,建设资金做到专款专用。选用优质材料,确保人、财、物、设备的科学合理配置。 5、合理用地的原则 从节省临时占地、满足施工需要、搞好排水、排污设备,认真实施科学施工、文明施工等多角度出发,合理安排生产、生活场地、房屋布置。工程完成后,及时清理、平整、恢复场地。 6、保障有力的原则 制定周密详细的工期保证措施。如雨季、节假日施工措施、物资设备保证措施、劳动力保障措施等。有力的保障施工的正常进行。7、协调一致的原则 在施工全过程中,将服从业主、监理、设计的统一协调,听从业主、监理、设计的指令,并确保指令得到有效的实施。 二、施工特点 本工程属于白天不停航夜间施工,必须确保飞行安全,工期较紧,

场地布置方法

精心整理成都地铁四号线六标场地规划施工方案 一、施工场地布置原则 根据施工项目、施工方案和周围环境,本着“节约用地,施工必需”的原则进行临时工程布设,并注意环境保护和水土保持工作。对于成都地铁4号线一期工程土建6标场地布置,我们遵循以下几点原则: (1 (2 (3 (4 (5 (6 (7 (8 ( (2 (3 (4 成都地铁4号线土建6标区间包含骡马市站~太升路站~省文联站两个区间,区间总长3199.319m。其中骡马市站~太升路站区间,起止里程为YDK29+617.444~YDK30+488.600,右线长871.156m,左线长878.411m。区间线路曲线半径R=400m,最大线间距15m,线路在该区间线间距由15m过渡到13m。线路最大埋深16.6m,最小坡度2‰(站坡度2‰),最大坡度7‰。太升路站~省文联站区间,起止里程为YDK30+674.700~YDK30+902.340,YDK30+933.363~YDK31+430.949,右线长725.226m,左线长724.526m。区间线路最小曲线半径R=400m,最大线间距15.0m,线路在该区间线间距由13m过渡到15m。线路最大埋深16.35m,最小坡度2‰(站坡度2‰),最大坡

度5‰;太省区间设置盾构风机房。主要施工布置在太升路站实现。 骡马市站 太升路站省文联站通风井878.411m 871.156m 494.190m 497.586m 230.336m 227.640m 四、施 工现场平面布置 6标段按招标文件提供的场地,和施工计划安排在太升路站进行场地布置,由于施工场地作业1C252、布2.5米,34512底) 6识,7却塔设置在水箱上方。 8、轨道梁:轨道梁采用现场目前的轨道基础,(充分满足施工要求) 9、拌和站:拌和站设置在中板位置,施工材料放置在车站顶板和拌和站同侧的位置方便下料。 10、水塔:方便施工场地内用水不间断,特意在施工现场设置水塔水塔采用钢板焊接长宽高分别为3*2.5*2.5(详见加工技术交底) 11.、大门设置:场地内大门严格按照标准制作,上面喷刷有企业标识和宣传字样。

施工现场平面布置方案

施工现场平面布置 1 总平面布置目的及原则 1.1 总平面布置目的 1、本章主要阐述了施工现场平面布置、施工机械、施工临时水电布置等。 2、本项目在总平面布置时,对总平面进行了区域划分、平面布置,这样有利于对总平面实施有效管理,促进施工现场的文明施工水平。 1.2 施工现场总平面布置原则 施工总平面布置合理与否,将直接关系到施工进度的快慢和安全文明施工管理水平的高低,为保证现场施工顺利进行,确定具体的施工平面布置原则为: 1、总平面布置合理,场内做到硬化、亮化。 2、在总平面布置上,实行明确施工区域的划分。 3、在满足施工的条件下,尽量节约施工用地。 4、满足施工需要和文明施工的前提下,尽可能减少临时建设投资。 5、在保证场内交通畅通和满足施工对材料要求的前提下,最大限度地减少场内运输,特别是减少场内二次搬运。 6、在施工现场总平面利用上,要尽量减少各工种间相互干扰。 2 施工现场围墙、大门、临时道路设置 2.1围墙及大门 1、围墙 我方进场后拟采用砖砌围墙对本工程的施工区域进行围挡,封闭管理,并对围墙进行美化工作,美化宣传内容报甲方批准后方可实施。 2、大门 我公司进场后现场北面设置二个大门入口,方便车辆进出,以供材料运输,现场大门按照公司制定的统一标准门图设计制作,采用双扇钢制密闭门,门高2.50m,宽大于6.0m,门柱尺寸为60×60cm正方形红砖砌筑,在入口处设置门卫室,人员和车辆均凭工作证或出入证进出;

另外出入口处设立洗车池,保证出入现场车辆不污染外部道路与内部道路,大门设有明显的交通警示标志,大门安装监控探头进行人员、车辆的出入监控。洗车池样式见下页图: 现场入口处布置“七牌一图”,即:(1)施工单位及工地名牌(附监督电话);(2)工程概况牌;(3)安全生产六大纪律;(4)防火须知牌;(5)十项安全技术措施牌;(6)工地管理人员名单牌;(7)安全生产无重大事故计数牌;(8)施工现场平面图。 2.2 现场道路 施工现场进行全硬化处理,沿现场围墙四周预留宽5米宽区域作为施工道路使用,其厚度和强度应满足施工和行车需要,以供现场材料运输,施工道路保证时时畅通,不可堆放任何材料。现场交通路线由项目副经理统一规划,土建施工员统一指挥调度,平时由警卫统一指挥调度。并配专人随时清扫。 硬化场地及路面应控制好标高,确保表面平顺,做到场内排水畅通,无积水现象,并在整个施工过程中加以维护。 具体布置计划详见附图“施工总平面布置图”。 3.3 办公、生活区设施 1、办公区 办公区布置按照业主提供的位置进行,办公区设有办公室、仓库、茶水室及厕所等,办公区内地面全硬化,便于施工生产的组织和施工现场安全文明施工的实施。现场厕所均设有自冲水,由专人保洁。为了给办公区创造一个整洁优美的办公环境,办公区内布置花坛和绿化带。 2、生活区 生活区不设置在场内。 3.4 主体结构施工阶段平面布置说明 1、地下室阶段 现场布置3台TC6013A和1台TC5713A塔吊作为主要材料吊运机械,在地下室施工阶段,钢筋及木工加工房布置在工程的南侧处,通过塔吊转运的方式转送

钢筋场地布置具体施工方案

沪昆客运专线HKJX-3标项目经理部 钢筋加工场施工方案 编制: 复核: 审核: 中交隧道局沪昆客运专线三标项目经理部一分部 2010年6月9日

钢筋加工场施工方案 一、编制原则 1、钢筋加工场应按照“因地制宜,综合利用”的原则复垦。 2、符合国家强制性标准、业主和本局项目标准化等相关管理办法规定。 3、钢筋加工场建设规模应符合施工使用要求,具备足够的原材料及半成品存放空间。 4、钢筋加工场建设应体现符合标准、节约用地、节省投资、环保节能、合理实用的原则。 二、编制依据 1、根据中交隧道局沪昆项目客专三标项目部钢筋加工场建设标准。 2、根据管段工程施工进度计划控制。 3、管段内桥梁、路基施工组织设计。 三、钢筋场选址 根据施工进度和工程量情况,共设置8个钢筋加工场,具体情况见下表:

1#钢筋场位于DK431+700线路的右侧,靠近滨江前沿的乡村水泥路,为山林地。主要负责童家塘大桥与山背特大桥的钢筋加工制作任务,距离童家塘大桥桥尾500米,距离山背特大桥桥头200米。 2#钢筋场位于DK434+600线路的右侧,为山林地。主要负责桥背特大桥的钢筋加工制作任务。 3#钢筋场相对线路里程为DK440+100,线路左侧20m,占地约8亩,成品供应范围为DK437+200~DK440+700,包括桩基、承台、墩身钢筋。 4#钢筋加工场满足首开工点要求,设在鹰东大道西侧,相对线路里程为DK441+450,靠近线路右侧红线,占地约5亩,成品供应范围为DK440+700~DK441+550,包括桩基、承台、墩身、鹰东大道立交特大桥(40+64+40)m连续梁钢筋。 5#钢筋加工场相对线路里程为DK446+400,靠近线路右侧红线,占地约8亩,成品供应范围为DK444+226~DK446+647,包括桩基、承台、墩身、鹰潭信江特大桥(72+3×116+72)m连续梁钢筋。 6#钢筋加工场设在鹰潭信江特大桥西岸,相对线路里程为DK447+150,靠近线路右侧红线,占地约8亩,成品供应范围为DK446+647~DK449+100,包括桩基、承台、墩身、鹰潭信江特大桥(72+3×116+72)m连续梁钢筋。 7#钢筋加工场相对线路里程为DK450+000,靠近线路右侧,占地约5亩,成品供应范围为DK449+100~DK452+000,包括桩基、承台、墩身。 8#钢筋加工场相对线路里程为DK452+000,设在线路右侧,占地约5亩,成品供应范围为DK452+000~DK453+000,包括桩基、承台、墩身。 四、工程进度控制 为满足架桥机按期通过,鹰东特大桥必须首先开工,提前完成线下工程,鹰潭信江特大桥为全标段控制性工程、重难点项目,按照工期,必须抢先施工赶上进度。 ⑴鹰东大道立交特大桥 钻孔桩基础:2010年6月1日~2011年2月28日 承台基础:2010年7月20日~2011年3月31日 桥梁墩(台)身:2010年8月1日~2011年4月30日 ⑵鹰东大道立交特大桥(40m+64m+40m连续梁) ①主墩(2个) 钻孔桩基础:2010年6月1日~2010年7月20日 承台基础:2010年7月21日~2010年8月10日