天府大道南延线道路照明工程(二期工程)电缆手孔井做法施工工艺标准编制:复核:总工程师:编制单位:成都天府大道南延线电气工程项目部编制日期:二0—三年六月十四日________________目录目录................................. -0 - 电缆手孔井做法施工工艺标准...................... -1 - 1施工工艺依据.......................... -1 -1.1施工设计图 ...................... -1 -1.2施工规程 ....................... -2 -2施工范围............................ -2 - 3施工准备............................ -2 -3.1劳动组织 ......................... -2 -3.2工机具 .......................... -2 -3.3主要材料 ......................... -3 -4操作程序............................ -4 -4.1 工序流程图........................ -4 -4.2 电缆手孔井做法图(见图号ZM-15).......... - 4 -5 操作要领 ............................ - 4 -5.1 准备工作........................ - 4 -5.2 定位放线........................ - 4 -5.3 挖基础坑........................ - 6 -5.4 铺滤水沙层....................... - 6 -5.5 架模.......................... - 6 -5.6 砂浆砖砌体....................... - 6 -5.7 找平.......................... - 6 -5.8 安装井座........................ - 7 -5.9 安装井盖........................ - 7 -5.10 拆摸......................... - 7 -5.11 成品保护....................... - 7 -5.12 清场退场....................... - 7 -6 注意事项 ............................ -7 -电缆手孔井做法施工工艺标准1 施工工艺依据1.1 施工设计图天府新区"三纵一横"重大基础设施项目天府大道南延线照明工程设计文件天府大道南延线一段K6+000- K8+440(修改审定稿)。
手孔井施工方案

手孔井施工方案手孔井施工方案一、项目背景手孔井是一种常用的水井形式,其施工方式相对简单,成本较低。
本方案将针对一处农村地区的手孔井施工进行详细阐述。
二、施工工艺1. 地面准备:找平井口附近的地面,清理杂物,确保施工区域干净整洁。
2. 挖掘井孔:根据设计要求,使用挖掘机挖掘手孔井孔,井孔直径根据设计要求确定,一般为1-1.5米。
挖掘至所需深度后,人工清理并整平井底。
3. 模板制作:根据设计要求,制作适用于手孔井的模板。
模板应具备强度高、使用方便、不漏水等特点。
4. 安装模板:在挖掘的井孔上方约0.5米处,安装制作好的模板,确保模板坚固稳定。
5. 浇筑混凝土:在模板内部逐层倒入混凝土,采用振捣机进行振捣,确保混凝土密实,无气孔。
6. 拆卸模板:混凝土刚浇筑完毕后,待其充分凝固后,拆卸模板。
7. 完善井口:在井孔上方设置井口护栏,并修整井口四周地面。
三、施工要点1. 施工人员必须具备一定的工程技能,熟悉挖掘机的操作和井孔施工的流程,保证施工质量和工期。
2. 施工过程中要保证施工现场的安全,并采取必要的防护措施,防止发生事故。
3. 混凝土的配比要按照标准进行,确保混凝土的强度和密实性。
4. 模板安装要牢固可靠,确保模板不松动,否则会影响混凝土的成型效果。
5. 在模板拆卸前,要确认混凝土已经充分凝固,以免影响施工结果。
四、安全措施1. 施工现场要设置警示标志,保持施工区域的秩序,防止行人进入施工现场。
2. 挖掘机操作人员必须持有相应的资格证书,熟悉挖掘机的操作规程。
3. 施工人员必须穿戴好安全帽、防护鞋等个人防护用品,做好人员防护。
4. 在挖掘井孔时,要注意井壁的稳定,防止发生井壁崩塌事故。
5. 施工过程中要注意用电安全,禁止乱接乱拉电线,防止触电事故的发生。
五、材料及设备清单1. 挖掘机2. 模板材料:木板、型钢等3. 混凝土4. 工具:锤子、锄头、板锯等5. 安全防护用品:安全帽、防护鞋、手套等六、工期整个手孔井施工工期一般为3-5天,具体工期根据项目规模和施工条件而定。
砖砌电缆手孔井施工工艺

砖砌电缆手孔井施工工艺
砖砌电缆手孔井施工工艺是指在电缆穿越建筑物或地下管道时,为便于电缆的接续和维护,开挖出一定深度和直径的手孔井,并在孔井周围砌筑砖墙,以保证孔井的稳定和安全。
其具体工艺步骤如下: 1. 确定手孔井的位置和尺寸,并用测量仪器进行测量、标志和校准。
2. 开挖孔井,在地面或地下深度挖出孔井,深度一般不少于电缆的埋深,直径为电缆直径的1.5倍左右。
3. 清理孔井,在孔井内清除杂物和泥土,使孔井内壁光滑平整。
4. 砖墙施工,在孔井周围用砖块砌筑墙体,砖墙高度一般不少于孔井深度的1.5倍。
5. 安装电缆,在孔井内穿过电缆,连接电缆两端,进行绝缘处理。
6. 进行验收,在施工完成后,进行验收,确保手孔井的质量和安全。
砖砌电缆手孔井施工工艺具有施工简便、结构稳定、安全可靠等优点,被广泛应用于建筑、市政、能源等领域。
- 1 -。
手孔、井井施工方案

手孔、井井施工方案一、前言手孔和井井是市政建设中常见的设施,其施工方案的合理性直接影响到日后的使用维护及周边环境。
因此,在制定施工方案时必须考虑完善的技术、细致的流程、严格的标准。
二、施工前准备1. 安全隐患排查:施工前要注意查看现场的安全隐患并加以排除。
2. 测量规划:根据设计图纸进行精确测量,确定井井或手孔的准确位置和下沉深度。
3. 材料准备:按照设计方案准备相应的材料和施工设备。
4. 现场布置:按照规定布置道路封闭等交通标志和警告牌,确保周边交通秩序不受影响。
三、施工方法1. 手孔施工方法:(1)开挖坑位:根据设计图纸确定开挖位置和深度,开挖孔位时要避免损坏其他地下管线。
(2)安装预制井圈:将预制的手孔井圈进行井室降下;(3)安装井盖:根据设计标准安装相应的井盖;(4)井壁加固:根据暴露的情况对井壁进行加固。
2. 井井施工方法:(1)开挖坑位:根据设计要求和环境条件确定开挖位置和井口直径;(2)安装钢模板:根据所挖掘的坑位安装井造模板并加固;(3)浇筑混凝土:根据设计要求浇筑混凝土并表面养护;(4)拆除模板:混凝土达到预设强度后,拆除钢模板,然后进行整体表面抹平和养护。
四、施工验收标准1. 施工质量:经验收合格后,手孔或井井边缘应平整:周边路面要平整,不得有起伏或断裂的现象。
2. 安全标准:手孔或井井盖正常使用情况下,应承受车辆或人员的负荷,不得出现松动或破损。
3. 环保标准:施工现场应清理干净,不得出现垃圾和污水等污染情况。
五、结论井井和手孔在市政建设工程中使用广泛,合理的施工方案和标准的验收标准至关重要。
只有尊重施工标准及技术规范,才能够确保设施的质量和长期稳定性。
手孔井施工工艺标准规范标准

''天府大道南延线道路照明工程(二期工程)电缆手孔井做法施工工艺标准编制:复核:总工程师:编制单位:成都天府大道南延线电气工程项目部编制日期:二〇一三年六月十四日目录目录.............................................................................................................................................................- 1 - 电缆手孔井做法施工工艺标准.................................................................................................................- 2 - 1施工工艺依据..................................................................................................................................- 2 -1.1施工设计图...........................................................................................................................- 2 -1.2施工规程...............................................................................................................................- 2 -2施工范围..........................................................................................................................................- 2 - 3施工准备..........................................................................................................................................- 2 -3.1劳动组织...............................................................................................................................- 2 -3.2工机具...................................................................................................................................- 3 -3.3主要材料...............................................................................................................................- 3 -4操作程序..........................................................................................................................................- 4 -4.1工序流程图...........................................................................................................................- 4 -4.2电缆手孔井做法图(见图号ZM-15) .................................................................................- 5 -5操作要领..........................................................................................................................................- 5 -5.1准备工作..............................................................................................................................- 5 -5.2定位放线..............................................................................................................................- 5 -5.3挖基础坑..............................................................................................................................- 7 -5.4铺滤水沙层...........................................................................................................................- 7 -5.5架模.......................................................................................................................................- 7 -5.6砂浆砖砌体...........................................................................................................................- 7 -5.7找平.......................................................................................................................................- 7 -5.8安装井座...............................................................................................................................- 8 -5.9安装井盖...............................................................................................................................- 8 -5.10拆摸.....................................................................................................................................- 8 -5.11成品保护.............................................................................................................................- 8 -5.12清场退场.............................................................................................................................- 8 -6注意事项..........................................................................................................................................- 8 -电缆手孔井做法施工工艺标准1施工工艺依据1.1施工设计图天府新区"三纵一横"重大基础设施项目天府大道南延线照明工程设计文件天府大道南延线一段K6+000~K8+440(修改审定稿)。
手孔井施工工艺流程

手孔井施工工艺流程下载温馨提示:该文档是我店铺精心编制而成,希望大家下载以后,能够帮助大家解决实际的问题。
文档下载后可定制随意修改,请根据实际需要进行相应的调整和使用,谢谢!并且,本店铺为大家提供各种各样类型的实用资料,如教育随笔、日记赏析、句子摘抄、古诗大全、经典美文、话题作文、工作总结、词语解析、文案摘录、其他资料等等,如想了解不同资料格式和写法,敬请关注!Download tips: This document is carefully compiled by the editor. I hope that after you download them, they can help yousolve practical problems. The document can be customized and modified after downloading, please adjust and use it according to actual needs, thank you!In addition, our shop provides you with various types of practical materials, such as educational essays, diary appreciation, sentence excerpts, ancient poems, classic articles, topic composition, work summary, word parsing, copy excerpts,other materials and so on, want to know different data formats and writing methods, please pay attention!手孔井施工工艺是一项复杂而精细的工程,涉及到多个环节和步骤。
手孔井施工

1、施工前的准备轴线、位置、标高复测:砌筑前,应先检查井的位置是否符合设计要求,标高是否准确,管井、检查井、砖砌体开挖宽度是否符合设计要求及操作规程。
2、材料准备砖的选用,应选几何尺寸标准、外观整洁,颜色一致,打击有清脆声,并试验检测合格的方可使用。
应对进场的砖事先发水,发水深度以砖的周边湿润15mm为宜,不能边浇水边砌筑。
3、砖砌体砌筑沟槽开挖后,根据管井位置平面布置测出井位、具体桩号,根据图示尺寸留设井位,在井位留设过程中,如有支管井位需要及时埋设,不得留洞。
管井、检查井应按设计要求的几何尺寸、技术标准开挖检查、管井基坑,经验槽合格及监理工程师签认后,才允许进行施工。
砖砌浅沟的砖砌体砂浆应满足设计强度,铺砌饱满,保证管井、检查井、砖砌浅沟四周回填施工压实度能够达到设计要求。
4、管井的抹灰砂浆标号必须符合设计强度要求,把握好配合比,水泥、砂和水不能过多或过少,要拌合均匀,稠度要适当。
抹灰时,要先将砖砌体表面清扫干净,湿度不够时应先浇适当的水湿润,以保证砂浆和砖砌体粘接牢固,避免脱落、空鼓。
抹灰要分层进行,一次打底、二次找平、三次而成,这样才能保证抹灰的质量。
一、施工工序:测量放线---手孔井开挖---手孔井砌筑---回填二、施工工艺:1、测量放线,定出手孔井中心线及开挖线2、手孔井开挖,基底为1.4*1.4米,高度1.44米,根据现场情况放坡开挖。
开挖后经验槽合格及监理工程师签认后,才允许进行下不施工。
3、井盖井座均为钢纤维混凝土材料,井盖在安装前应先在盖板槽内做1:2水泥砂浆厚15mm,待标高校正后,用C20细石混凝土将盖座窝牢。
4、井座与井口接触面应采用M5水泥砂浆找平,然后把井座平整安装在井口上面,并用M5水泥砂浆填满缝隙。
5、手孔井采用MU10青砖,M5水泥砂浆砌筑,内壁1:2水泥砂浆抹面10mm 厚。
砖砌体砂浆要满足设计强度,铺砌饱满,保证四周回填压实度满足设计要求。
砂浆标号要符合设计要求,拌合均匀,稠度要适度。
室外手孔井施工工艺

室外手孔井施工工艺手孔井是指用于室外的一种简易井口结构,它通常用于电力、通信、给水等管线的敷设和维护工作。
在室外手孔井的施工过程中,需要遵循一定的工艺流程和操作规范,以确保施工质量和安全性。
在施工前需要对施工现场进行勘测和规划。
确定手孔井的位置和数量,根据工程需求进行合理布置。
同时,要考虑到井盖的便捷开启和关闭,以及井盖的承载能力等因素。
接下来,进行地面开挖工作。
根据设计要求和井孔尺寸,在施工现场进行地面开挖,将井孔的位置挖出来。
在开挖的过程中,要注意土壤的稳定性和周边建筑物的安全,避免发生地质灾害和工程事故。
然后,进行基础施工工作。
在井孔的底部铺设一层砂浆,然后将井筒和井壁逐层垂直放置。
井筒和井壁可以使用混凝土、砖石等材料进行搭建,要保证结构牢固和耐久性。
在井孔的顶部留出出口孔和电缆穿线孔,方便后续的管线敷设和维护。
井孔内部的施工也需要注意细节。
首先进行井孔的清理工作,将井孔内的杂物和泥土清除干净。
然后进行井壁的抹灰和防水处理,以保护井壁不受潮湿和腐蚀。
最后,安装井盖和防护设施,确保井孔的安全性和使用便捷性。
在施工过程中,需要注意以下几点。
首先,要严格遵守施工规范和安全操作规程,确保施工人员的人身安全。
其次,要使用合适的工具和设备,保证施工质量和效率。
同时,要加强施工现场的管理和监督,防止出现质量问题和安全事故。
室外手孔井施工工艺是一项综合性的工作,需要施工人员具备一定的专业知识和技能。
在实际施工中,要根据具体情况和工程需求,灵活调整施工工艺和操作方法。
只有通过科学规范的施工工艺,才能保证室外手孔井的质量和安全性,为后续的管线敷设和维护提供良好的基础。
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
天府大道南延线道路照明工程(二期工程)电缆手孔井做法施工工艺标准编制:复核:总工程师:编制单位:成都天府大道南延线电气工程项目部编制日期:二〇一三年六月十四日目录目录............................................................................ - 1 -电缆手孔井做法施工工艺标准...................................................... - 2 -1施工工艺依据............................................................... - 2 -1.1施工设计图........................................................... - 2 -1.2施工规程............................................................. - 2 -2施工范围................................................................... - 2 -3施工准备................................................................... - 2 -3.1劳动组织............................................................. - 2 -3.2工机具............................................................... - 3 -3.3主要材料............................................................. - 3 -4操作程序................................................................... - 4 -4.1工序流程图........................................................... - 4 -4.2电缆手孔井做法图(见图号ZM-15) ...................................... - 5 -5操作要领................................................................... - 5 -5.1准备工作............................................................. - 5 -5.2定位放线............................................................. - 5 -5.3挖基础坑............................................................. - 7 -5.4铺滤水沙层........................................................... - 7 -5.5架模................................................................. - 7 -5.6砂浆砖砌体........................................................... - 7 -5.7找平................................................................. - 7 -5.8安装井座............................................................. - 8 -5.9安装井盖............................................................. - 8 -5.10拆摸................................................................ - 8 -5.11成品保护............................................................ - 8 -5.12清场退场............................................................ - 8 -6注意事项................................................................... - 8 -电缆手孔井做法施工工艺标准1施工工艺依据1.1施工设计图天府新区"三纵一横"重大基础设施项目天府大道南延线照明工程设计文件天府大道南延线一段K6+000~K8+440(修改审定稿)。
1.2施工规程《城市道路照明工程施工及验收规程》(CJJ89-2012)。
2施工范围天府大道南延线(二期)照明工程,其里程:K6+000~K17+314,且必须在绿化带或人行道、公交停靠站台、中央分隔带、主辅分隔带内。
3施工准备3.1劳动组织3.2工机具3.3主要材料4操作程序4.1工序流程图4.2电缆手孔井做法图(见图号ZM-15-1、2)5操作要领5.1准备工作(1)首先熟悉电缆线路的图纸及电缆手孔井做法图,并准备材料工机具等。
(2)在施工现场对照图纸进行现场调查,确认电缆经过的手孔井的地点,仔细审核施工放线的依据。
(3)对本工程使用的测量仪器进行复核,确保精度要求。
没有检验合格证或仪器超出检验时效地严禁使用。
5.2定位放线5.2.1手孔井位置及预埋管位置示意图(附后);5.2.1.1施工设计图里程及电缆手孔井做法图,图号ZM-15一1、2;5.2.1.2手孔井设置在人行道上:手孔井中心点距道路边缘距离1500mm,且距灯基础(或人行道的断口处)边缘距离不小于1500mm;5.2.1.3手孔井设置在主辅分隔带上:手孔井中心点距道路边缘为4750mm,且距灯基础(或主辅分隔带的断口处)边缘的距离不小于1500mm;5.2.1.4手孔井设置在中央分隔带上:手孔井中心点距距道路边缘为4000mm,且距灯基础(或中央分隔带的断口处)边缘的距离不小于1500mm;5.2.1.5手孔井设置在公交停靠站台上:手孔井中心点距距道路边缘为1250mm(或站台中心),此处三个手孔井的过道管均进入井内50mm,且三井中心连线垂直道路。
5.2.1.6绝不允许手孔井设在道路上。
5.2.1.6手孔井内无钢管进入时,必须预埋好镀锌扁钢-40*4,各伸出手孔井外100mm,并预埋好PVC管φ75*1000,PVC管井内50mm;手孔井内有钢管进入时,必须镀锌扁钢-40*4与钢管焊接后一起预埋。
5.2.2手孔井放线测量(与过街管道预埋测量同步进行):根据设计图纸、已知座标体系点N(含里程、高程、偏距、X、Y等相关数据),利用全站仪、花杆等测量仪器和工具,准确测定预埋管道的位置(含里程、高程、偏距、X、Y等相关数据),在主车道(辅道、道口等)路面预埋处上放出N1路面中心点及N2、N3路面边线点,又放出手孔井中心点N4、N5两点,并在同一中心线路面两边放出N6、N7两个备查点,分别在各点用标桩及小红旗作好标记,同时要做好闭合校验。
为保证测量的准确性,控制点的传递使用全站仪进行引侧。
定位放线示意图如下:已知座标体系点路面中心线5.3挖基础坑5.3.1采用人工开挖宽度=长度:1180+模具厚度。
5.3.2采用人工开坑深度(过街道道沟深+滤水砂层150+200):钢管进入手孔井时,预埋二、三根管的沟底距主车道路面1408mm;预埋四、五、六根管的沟底距主车道路面1616mm;预埋七、八根管的沟底距主车道路面1824mm;钢管不进入手孔井时,沟底距主车道路面1408mm。
5.4铺滤水沙层按图上的在圆坑内铺上粗砂150mm厚。
5.5架模按图要求,采用木板厚20毫米加工好的模型,架模具,并调好模具的位置加以固定。
5.6砂浆砖砌体按图要求,采用砌砖,并在砖空隙处填100#砂浆,注意要同时把过街镀锌钢管φ100*4及PVC管φ75*1000按要求安放上,井内壁按1:2.5水泥砂浆抹面,厚度10mm。
5.7找平按图要求,采用水泥砂浆找平,同时要求井盖顶部距人行道路下60mm,井盖顶部与绿化土地面相平。
5.8安装井座等待水泥砂浆干后,安装井座,并调好井座的位置,上锁的位置应在道路反侧。
5.9安装井盖按要求安装上井盖并上锁,井座井盖样式(见图),再用水泥砂浆抹平四周。
5.10拆摸等待水泥砂浆干后,拆除摸具。
5.11成品保护验收合格后,将镀锌钢管口用棉纱安全封好,防止污水及杂物的进入,在手孔井四周设有安全防护网和标牌。
5.12清场退场工作完毕后,清洁场地去除杂物后,方可退场。
6注意事项(1)进入施工现场的工作人员,必须穿防护服,配戴安全帽。
(2)施工所用材料、工具的随意堆放。
在路基上放置的机具及材料,安装前必须设专人昼夜监护,确保行车及行人安全。
(3)施工时,在道路两侧各设防护员,有车辆通过时,及时通知作业人员,确保人身安全。
(4)手孔井做好后,没拆模前一定要设有安全防护标示。
(5)严格按施工设计图的位置及施工工艺标准施工,未经工程部书面同意,不准擅自变动。
(6)二期工程手孔井做法全按此施工,若有改动,另行出其标准。