国投哈密能源开发有限责任公司副斜井井筒及配套巷道、硐室施工组织设计河南煤炭建设集团有限责任公司二O一一年八月九日施工组织设计会审表施工组织设计、方案、措施会审表表号:GC-002/A 编号:GTHMNY/GC/HS/ /2021目录前言··································································1、工程概况·····························································································································································································································································································2、施工准备···········································································································································································································································································································································3、施工方案及施工顺序····················································································································································································································4、施工关键技术······································································································································································4.3冬、雨季施工措施···················································5、施工辅助系统·························································································································································································································································································5.5通风、降尘系统····················································································································5.7通讯、信号、照明系统·····························································································5.9测量······························································6、劳动组织····························································································································································································································7、施工排队和工期···················································································································································································································································································8、质量保证体系与质量保证措施········································································································································································································9、平安保证体系和平安技术保证措施·······································································································································································································10、文明施工及环境保护措施························································································································································11、提高工程质量、保证工期及降低造价的合理化建议······················12、副斜井井筒工程施工机械设备配备一览表······························前言国投哈密能源开发有限责任公司为国家开发投资公司下属国投煤炭公司的全资子公司,于2021年4月在哈密注册成立。

副斜井施工组织设计5171

副斜井施工组织设计5171

副斜井施工组织设计一、工程概况(一)项目概述:温家庄矿位于山西省寿阳县城西北侧,工业广场设在温家庄乡盘沟底村北侧300米处,地理位置优越,回风井距工业广场约1公里,有临时土路通往温家庄乡盘沟村公路。

矿井设计年生产能力120万吨,计划建设工期27个月,矿井采用斜井开拓方式。

本招标井筒为副斜井工程。

副斜井工程量895.601米,工程量见综合单价报价表。

(二)地形地貌:本井田位于沁水煤田北部边缘,寿阳(东)详查勘探区的北部,为低山丘陵地貌,地表多被第四系黄土覆盖,土梁现冲沟发育,地形山峦起伏,沟壑纵横,地势东高西低,地面最低处在井田的西北角盘沟底村内,标高为1122米,最高在井田的中北部,标高为1345.7米,相对高差约220米。

(三)水文:井田内地表水系不发育,只发育一些冲沟,由于降雨量少,基本上无积水,在井田西北边界外有温家庄河,在上游温家庄村东北约2.5公里处建有郑家庄水库,水库坝高16米,坝长350米,最大库容量240万平方米,库内现存水很少,温家庄河基本干枯无水。

(四)气象:地处山西黄土高原东南部,气候干燥,气温昼夜变化较大,四季分明,为半干旱大陆性气候,年平均降水量476.7毫米,多集中在6-9月,冬春多风,霜期从9月中旬至次年4月中旬,长达7个月左右,年平均气温7.4℃,最低气温-26.2℃,全年平均无霜期151天,平均冻土厚度0.904米。

(五)地质特征:本井田暂未打地质钻孔,地质情况不详,估计元流砂层,无瓦斯积存区。

(六)地震:本井田地震烈度七度。

(七)工程内容及特征根据招标文件及工程图纸,本工程(副斜井)井筒长度约915.119m,井筒的主要工程特征如下表:(八)井筒涌水量:井筒涌水量小于5立方米/小时。

二、施工准备(一)技术准备1.组织技术与管理人员认真审阅图纸,学习技术规范,组织图纸会审,并在此基础上编制可行性施工组织设计、安全技术措施、项目质量计划、填报项目开工报告,准备好各种技术资料和表格,开工前对技术人员、管理人员及施工人员做好技术交底。

某煤业有限公司副斜井施工组织设计

某煤业有限公司副斜井施工组织设计

能源掘120101施工组织设计工作面名称:帽帽山煤业副斜井编制人:张锦如施工负责人:李连文总工程师:张锦如批准日期:2013年4月3日执行日期:2013年4月3日内蒙古神华建安有限公司会审意见1. 进一步完善帽帽山工程项目部领导机构,重要部门管理人员不得兼任。

2. 地测人员必须由有多年测量经验的人员担任。

3. 补充“放炮警戒图”。

4. 排矸运输车辆必须有完善的安全技术措施。

5. 明确倒车硐室的规格尺寸、支护方式及间距。

会审意见:1、在确定长距离通风方案后,另行编制专项安全技术措施。

2、为加强施工进程,缩短工期,可采用从措施巷与目前工作面相向施工,贯通措施另编。

目录第一章工程概况 (5)第二章施工准备及场地布置 (14)第三章工程施工方案 (15)第四章施工组织及施工进度计划 (21)第五章工程质量保证系及质量措施 (22)第六章工程保证措施 (28)第七章文明施工措施 (29)第八章施工安全技术措施 (31)第九章井下灾害预防 (37)山西煤销集团帽帽山煤业有限公司副斜井施工组织设计第一章:工程概况第一节:概述一、井田概况山西煤炭运销集团帽帽山煤业有限责任公司井田位于大同市西南部40km处的左云县水窑乡杨家窑村东部,西北距左云县城约24km,行政隶属大同市左云县水窑乡,其地理坐标为:东经112°51′02″~112°53′55″。

北纬39°50′21″~39°52′01″。

井田面积,按山西省国地资源厅2009年12月9日换发的C1400002009121220047226号采矿许可证批准井田面积为17.4279km2,开采石炭系2、5、8号煤层以(2009年7月15日山西省煤矿企业兼并重组整合工作领导组办公室《晋煤重组办发[2009]9号》文件批准面积为17.4304 km2,矿区范围拐点坐标如下:西安1980坐标系北京1954坐标系1X Y1X Y24419032.5019661614.67244190791966168634416492.4919661677.67344165391966174944415489.4819661691.67444155361966176354414805.4819662433.68544148521966250564414770.4819660405.67644148171966047774413884.4719660418.67744139311966049084413884.4719660173.67844139311966024594413376.4719660149.679441342319660221104413348.4719658329.6610441339519658401114416435.4819658277.6611441648219658349124418975.4919658234.6512441902219658306批准生产规模180万吨/年,经济类型为有限公司,采矿许可证有效期限自2009年12月9日至2011年12月9日。

副斜井井筒施工组织设计概论

副斜井井筒施工组织设计概论

副斜井井筒施⼯组织设计概论第⼀章⼯程概况第⼀节设计概况XXXX副井井筒原设计倾⾓22°,斜长210m,宽3.0m,⾼2.7m,装备单钩串车。

由于原井巷断⾯较⼩,不符合矿井建设需要,为推进矿井建设,按照省煤炭厅批复的兼并重组矿井初步设计,利⽤原副斜井刷扩并延伸后作为兼并重组后的副井,扩⼤断⾯规格为净宽4.5m,净⾼3.9m,断⾯为直墙半圆拱,倾⾓为22°,净⾯积15.4m2,掘进断⾯积为17.7m2,装备轨道串车,架空乘⼈器,⽔沟位于井筒右侧,台阶、扶⼿位于井筒左侧,担负全矿辅助提升任务,井筒扩刷采⽤锚⽹喷砼,锚索补强⽀护,锚索间、排距为2.4×2.4m,Ф17.8×6500mm,砼强度等级C20,顶锚杆为Ф20×2400mm左旋⽆纵筋螺纹钢树脂锚杆,间排距:800×800mm,每根顶锚杆⽤三卷MSZ2330型树脂锚固剂锚固,每根帮锚杆⽤⼀卷MSZ3535型树脂锚固剂锚固,⾦属⽹采⽤φ6mm钢筋⽹,⽹格150×150mm,⽹⽚规格1500×900mm,喷射砼封闭,砼厚150mm,喷射砼、铺地砼强度等级C20。

每隔40m在⼈⾏侧掘净宽1.5m,净⾼2m,深1.0m的拱形躲避硐室,⽀护形式与副井筒相同。

扩到穿煤及受采动影响区域、巷道超⾼、超宽地点采⽤锚⽹喷和钢棚联合⽀护,钢棚采⽤29“U”钢,棚距900mm,密背砼背板刹顶,背邦。

四周未接顶、邦区域采⽤长不⼩于1.2m,厚不⼩于0.12m 的半圆⽊打“井”字型⽊垛接实顶板。

半圆⽊材质必须是红松。

锚⽹喷双重⽀护,如遇顶板破碎或过断层时,应缩⼩棚距,表⼟段钢筋混凝⼟⼯程去年已完⼯,延伸段与井底车场施⼯另外编写。

第⼆节井筒地质及测量⼯作⼀、地质从井筒揭露的煤岩层分析,本区地质特征复杂程度应属于构造破碎带裂隙发育,地层岩⽯完整性差,地质条件中等类型,井筒⽬前未见有涌⽔。

(1) 各地层主要特征本井⽥位于宁武轩岗矿区的北端,⼤部分为黄⼟覆盖区,仅在沟⾕中出露⼆叠系上下⽯盒⼦组、⼭西组和⽯炭系太原组,零星可见本溪组。

副斜井施工组织设计(自编)

副斜井施工组织设计(自编)

第一章工程概况1.1井田位臵山西煤炭运销集团盛泰煤业有限公司井田位于高平市陈区镇建宁乡,南西距高平市15Km,其地理座标为东经113º03´35"~113º05´49",北纬35º50´07"~35º53´22"。

井田南北长6.0Km,东西宽3.35Km,面积14.56Km²。

1.2井田交通井田北部和长治县相临,北距长治市直线距离38Km,西南距高平市直线距离15Km。

井田及周边交通发达,长(治)-晋(城)二级公路,长(治)-晋(城)高速公路从井田西侧约9Km通过,西距太(原)-焦(作)铁路线高平站约15Km。

曲(沃)-辉(县)公路从井田南侧通过,交通极为方便。

1.3自然地理1.3.1地形及地貌特征井田地处太行山中南段的高平山间盆地北东缘,属中低山区。

总体地势表现为北缘及中部高,东、西部低。

井田内最高标高为1239.55m(井田北缘山梁最高点),最低标高为973.5m(东窑头村西本井田西缘冲沟内),相对高差266.05m。

区内及周边无大的地表水体和地表径流,大气降水沿沟自然排泄。

1.3.2水系井田内较大沟谷近几十年来的最高洪水位一般高出沟底河床1.5-2.5m。

11.3.3气候本区属暧温性大陆性季风气候,四季分明。

春季干燥多风,夏季炎热多雨,秋季天高气爽,冬季寒冷少雪。

据井田周边区域气象资料,年均气温9.8ºC,一月最冷,平均-5.5 ºC,七月最热平均23.2 ºC,极端高温38.6 ºC。

无霜期180天,年均冻结天数100天,最大冻结深度56cm,全年平均日照时数2482.34小时,年均降水量617.1mm,年蒸发量为1631.6mm,年均风速2-3m/s,以东北风为主。

自1971年以来,晋城市地区最大积雪厚度达到28.2cm。

1.4地层及构造井田位于山西省沁水煤田东南部,晋城煤炭国家规划矿区高平西区的北东部。

付斜井井筒施工组织设计

付斜井井筒施工组织设计

目录第一章地面位置及地质情况.......................................................................... - 3 -第一节地面位置 (4)第二节水文地质 (4)第二章工程概况.............................................................................................. - 3 -第一节概述 (4)第二节编制依据 (4)第三章巷道布置及支护说明.......................................................................... - 5 -第一节巷道布置 (5)第二节支护设计 (5)第四章施工工艺.............................................................................................. - 7 -第一节表土段及基岩风化段施工.. (7)第二节基岩段施工 (9)第五章劳动组织及主要技术经济指标...................................................... - 15 -第一节劳动组织. (15)第二节循环作业图表 (15)第六章生产系统............................................................................................ - 16 -第一节提升运输. (16)第二节排水 (16)第三节压风 (16)第四节通风 (16)第五节井上下信号、通讯与电视监控 (17)第六节拌料 (17)第七节测量 (17)第八节通风 (17)第七章灾害预防及避灾路线........................................................................ - 20 -第八章质量目标及质量保证措施................................................................ - 21 -第九章安全技术措施.................................................................................... - 26 -第一节一般规定. (26)第二节表土施工安全措施 (27)第三节防、治水安全措施 (27)第四节顶板管理措施 (28)第五节钻眼爆破与通风措施 (28)第六节装矸安全措施 (31)第七节提升运输 (31)第八节永久支护 (33)第九节瓦斯管理 (34)第十节设备管理 (34)第十一节过断层破碎带和陷落柱时安全措施 (35)第十二节挖掘机使用安全措施 (36)第十三节冬雨季施工措施 (37)第十四节、安全管理体系.................................................... 错误!未定义书签。

施工组织设计(副斜井)XXXX-4-24

施工组织设计(副斜井)XXXX-4-24

施工组织设计(副斜井)XXXX-4-24能源掘120101施工组织设计工作面名称:帽帽山煤业副斜井编制人:张锦如施工负责人:李连文总工程师:张锦如批准日期:2013年4月3日执行日期:2013年4月3日内蒙古神华建安有限公司会审意见会审意见:1、在确定长距离通风方案后,另行编制专项安全技术措施。

2、为加强施工进程,缩短工期,可采用从措施巷与目前工作面相向施工,贯通措施另编。

目录第一章工程概况 (5)第二章施工准备及场地布置 (14)第三章工程施工方案 (15)第四章施工组织及施工进度计划 (21)第五章工程质量保证系及质量措施 (22)第六章工程保证措施 (28)第七章文明施工措施 (29)第八章施工安全技术措施 (31)第九章井下灾害预防 (37)山西煤销集团帽帽山煤业有限公司副斜井施工组织设计第一章:工程概况第一节:概述一、井田概况山西煤炭运销集团帽帽山煤业有限责任公司井田位于大同市西南部40km 处的左云县水窑乡杨家窑村东部,西北距左云县城约24km,行政隶属大同市左云县水窑乡,其地理坐标为:东经112°51′02″~112°53′55″。

北纬39°50′21″~39°52′01″。

井田面积,按山西省国地资源厅2009年12月9日换发的C1400002009121220047226号采矿许可证批准井田面积为17.4279km2,开采石炭系2、5、8号煤层以(2009年7月15日山西省煤矿企业兼并重组整合工作领导组办公室《晋煤重组办发[2009]9号》文件批准面积为17.4304 km2,矿区范围拐点坐标如下:西安1980坐标系北京1954坐标系1 X Y 1 X Y2 4419032.50 19661614.67 2 4419079 196616863 4416492.49 19661677.67 3 4416539 196617494 4415489.48 19661691.67 4 4415536 196617635 4414805.48 19662433.68 5 4414852 196625056 4414770.48 19660405.67 6 4414817 196604777 4413884.47 19660418.67 7 4413931 196604908 4413884.47 19660173.67 8 4413931 196602459 4413376.47 19660149.67 9 4413423 1966022110 4413348.47 19658329.66 10 4413395 1965840111 4416435.48 19658277.66 11 4416482 1965834912 4418975.49 19658234.65 12 4419022 19658306批准生产规模180万吨/年,经济类型为有限公司,采矿许可证有效期限自2009年12月9日至2011年12月9日。

副斜井井筒施工组织设计

副斜井井筒施工组织设计

副斜井井筒施工组织设计一、前期工作1.项目技术准备工作(1)进行项目立项,明确项目目标和需求。

(2)开展地质勘查和现场勘察,确定地质条件和目标井筒位置。

(3)进行工程设计,包括各种施工方案、施工工艺和施工方法的确定。

2.组织准备工作(1)成立项目管理团队,明确各个岗位的职责和任务。

(2)编制施工组织设计方案,确定施工过程中的各项指标和安全要求。

(3)制定施工计划,包括施工时间、资源配置和工作任务等。

二、施工方案的确定施工方案是副斜井井筒施工的核心内容,其合理性和科学性直接影响到施工效果和质量。

根据地质条件和工程要求,选择最合适的施工方案。

1.方案设计(1)确定井筒开挖的方式,可以采用机械开挖还是人工开挖。

(2)选择开挖的方法,可以采用顺垂、逆垂或者平行开挖等方式。

(3)确定支护措施,包括井壁衬砌、钢筋混凝土灌注桩等。

(4)确定排水和通风的方法,保证施工现场的安全和顺利进行。

2.施工工艺(1)制定施工工序和作业流程,明确各个作业环节的顺序和时间。

(2)确定施工的关键技术,包括土方开挖、支护施工、灌浆充填等。

(3)建立施工质量控制体系,包括施工过程中的检测和验收。

三、施工组织的安排施工组织的安排是确保施工过程中各项工作有条不紊进行的关键环节。

1.人员安排(1)组织施工人员的培训和技术交流,提高施工队伍的整体水平。

(2)明确施工人员的职责和任务,确保施工过程中各项工作的顺利进行。

(3)落实施工人员的安全教育和培训,提高他们的安全意识和应急能力。

2.设备安排(1)选择合适的机械设备,包括挖掘机、钻机和灌浆设备等。

(2)对设备进行检修和保养,确保设备的正常运行。

(3)合理安排设备的使用顺序和时间,避免重复使用或者闲置。

3.材料安排(1)确定施工所需的材料种类和数量,保证材料供应充足。

(2)对材料进行检验和验收,确保材料符合施工要求。

(3)合理安排材料的运输和储存,避免材料的浪费和损失。

四、施工安全及质量控制措施施工安全和质量控制是副斜井井筒施工的重要环节,必须严格按照标准进行操作。

  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

计划投入的主要施工机械设备表序号机械或设备名称规格型号数量国别产地制造年份额定功率KW生产能力备注1 提升绞车XTK1×2.5×2B-201 洛阳2007 3952 耙斗机P-90B 1 徐州2008 453 局扇2BKJ№6.3/60 2 湘潭2007 30×24 空压机4L-20/4 3 江苏2005 1305 喷射机PZ-5 1 河南2009 5.5×56 搅拌机JS-350 1 兴平2007 15×27 配料机HPB-1600 1 兴平2006 5.58 矿车1T 1 铜川20039 变压器KSGZY-500KVA 2 河南200410 自卸车康明斯8T 6 湖北200511 箕斗3M3 3 铜川2006 812 水泵100D45×4 2 西安2009 4513 潜水泵 2 西安2009 414 锚杆拉力计T52 1 湘潭200515 小绞车JD-4 3 常州2003 55kW山西山阴宝山腰寨煤业有限公司副斜井施工组织设计编制单位:山西宏图建设工程有限公司编制时间:2011年7月8日编制人:李学奎批准时间:2011年7月23日执行日期:2011年7月30日目录第一章概况 (5)第一节地理位置与交通情况 (5)第二节自然环境 (5)第三节地质及水文地质 (6)第四节井筒技术特征 (6)第二章施工现场组织机构 (7)第三章施工方案 (8)第一节施工准备 (8)第二节施工工序安排 (12)第三节施工方案 (12)第四节施工方法 (13)第五节砼搅拌和运输 (18)第六节提升运输管理 (18)第七节地质测量工作 (19)第八节井筒通过破碎带的措施 (20)第九节防治水 (21)第十节防汛 (22)第十一节冬、雨季施工措施 (22)第四章辅助生产系统 (23)第一节提升系统 (23)第二节运输系统 (24)第三节压风系统 (24)第四节通风系统 (24)第五节排水系统 (24)第六节供电系统 (24)第七节信号、通讯、照明系统 (25)第五章施工进度、工期及保证措施 (27)第一节进度安排原则 (27)第二节作业方式 (27)第三节进度及工期 (30)第四节工期保证措施 (30)第六章质量标准及施工保证措施 (31)第一节质量标准 (31)第二节施工验收 (33)第三节保证工程质量的技术措施 (35)第七章施工安全技术措施 (37)第一节安全目标 (37)第二节安全保证体系 (37)第三节施工安全技术措施 (38)第八章环境保护及文明施工 (42)第一节减少扰民噪音、降低环境污染措施 (42)第二节文明施工措施 (42)第九章计划、统计与信息管理 (45)第一节计划、统计 (45)第二节信息管理 (45)第一章概况宝山腰寨煤业有限公司是一座正在技改的、年规划生产能力120万吨的煤炭企业。

矿井采用斜井开拓方式,在同一工业广场内设主斜井、回风竖井。

第一节地理位置与交通情况本公司位于山阴县马营乡腰寨村西,距山阴县城30公里,距北同蒲铁路和208国道20公里,交通运输条件便利。

其地理坐标为东径112°40′20″,北纬39°41′09″,位于大同煤田西北端。

井田走向长3.1kM,倾向长3.kM,面积6.68K㎡。

第二节自然环境本矿属典型的大陆性气候,半干旱地区,其特点冬季严寒,夏季炎热,风沙严重,昼夜温差较大,现将具体资料分述如下:⑴气温:一般较低,以年温差大为特点,年平均气温为5.1℃,极端最高气温在39.9℃,极端最低气温在-35℃。

⑵冻土:历年来冻土月份为11月至第二年4月份,最大冻土深度1610mm。

⑶降水量:降水多集中在7、8、9三个月,约为全年降水量的60-75%,历年平均最大降水量为628.3mm,历年平均最小降水量为259.3mm,历年平均降水量448.7mm,最大日降水量为79.90mm。

⑷蒸发量:历年来蒸发量大大超过降水量,年一般蒸发量在1644-2105mm之间,平均蒸发量为1847.8mm。

⑸风:朔州地区一向以风沙多而著称,西北风几乎贯穿全年,每年有风时间占全年总时间的70%,多集中在冬春季节,年平均风速为3.2m/s,最大可达17m/s。

第三节地质及水文地质1、含水层情况本井田水文地质条件简单。

含水层主要有三个:覆盖层及风化层段含水层,为孔隙、裂隙含水层,水位不稳定,出水量47~95m3/d;石炭二叠系煤系地层含水层,主要为砂岩裂隙含水层,水量微弱,仅为0.01m3/d;奥陶系灰岩含水层,主要为岩溶、裂隙含水层,伏于井田深部,水位深度为215.01~250.24m,水位标高为1161.58~1200.58m。

抽水试验结果,降深3.18m,单位涌水量0.934L/min。

`井田所属区域属于高寒地带,本区岩层微含水,其它均无含水层。

2、矿井涌水量本区岩层微含水,地表雨水通过断层裂缝渗入井下,开采过程中,煤层的滴水和淋水是矿井水的主要来源。

据记载目前矿井正常涌水量为2300 m3/d,最大涌水量为6000m3/d,含水系数0.4~0.5,不随产量增加而增加。

3、矿井主要水害及其防治措施矿井充水因素主要为顶板以上砂岩裂隙水,由于山西组砂岩含水层在井田范围含水性不强,水量有限,只要正常进行抽排,一般不会发生水害事故。

另一个因素为邻近生产矿井废弃巷道和采空区积水。

今后若靠近边界附近开采时,应详细调查相邻煤矿开采情况和废弃巷道和采空区积水情况,以防巷道相互贯通引发水害事故。

第四节井筒技术特征井筒主要特征表井筒名称井口坐标井筒倾角井筒斜长(m)井筒宽度(m)井筒断面(m2)支护方式纬距(X) 经距(Y)标高(Z)净掘净掘主斜井4397228.0019645549.001571.000 -23°260.8374 5 12.28 16.07 砌碹第二章 施工现场组织机构一、 组织机构施工组织机构图二、工程主要负责人项目经理项目工程师项目副经理 综合部工程部 经营部 劳动人事 安全检查施工测 量质量 检查 技 术资料 计划统计 设 备计划 材料计划 财 务后 勤施 工 队工程主要配备项目经理一名,技术副经理一名,安全副经理一名。

主要负责人情况详细见附表。

第三章施工方案第一节施工准备一、施工场地布置及要求1、生活场区设在工业场院区外,房屋建筑利用原有的房屋。

2、在工业广场布置压风机房、绞车房、井口调度室、井口值班房、机电维修房。

3、混凝土拌和站设在井口附近,要求将砂、石料堆放场、水泥库布置在搅拌站附近,库内应做防潮处理。

拌和站尽量利用有利地形,便于砂、石料、混凝土的机械运输。

4、所有临时设施尽量避开永久设施。

措施工程一览表序号名称结构单位数量备注1 压风机房砖木结构M21002 绞车房砖木结构M21803 井口值班房活动房M2304 机修房活动房M2605 配电房砖木结构M2406 信号房砖木结构M2107 材料棚简易M250 砖围墙石棉瓦顶8 砼搅拌站简易M2100 砖木结构9 绞车基础砼M310010 压风机基础砼M34011 水池砖砼M350 压风机冷却12 施工用水池砖砼M32013 材料库活动板房M36014 水泥棚简易M36015 砂、石料场砼M2200 150MM砼铺底临时工程一览表序号名称结构单位数量备注1 办公室活动房M2602 宿舍活动房M23003 食堂餐厅活动房M2604 澡堂活动房M2605 茶炉房活动房M2206 院子硬化石M2200 石铺地7 厕所砖砼M230依建设单位所提供场地进行布置二、劳动力准备根据工程要求组建强有力的施工项目部,组织精干、施工力量强的成建制施工队进行施工。

施工实际需要配员57(人),考虑85%出勤率,总配员74/0.85=67(人)。

施工队劳动力配备表三、技术准备类别工 种 人数 备 注类别工 种 人数 备 注管 理 人 员队长1 辅 助 生 产 工 人电钳工 2×3技术员 1 锻工 1小计 2信号工 1×3生 产 工 人班长 3×1 压风司机 1×3领钎工 3×2 汽车司机 1×3打眼工3×2 绞车司机 2×3放炮员1×2 瓦检员 1×3耙斗司机 1×2 钢绳工 1锚喷工 6×1 电焊工 1质量员 1×3 小计 27小计 30 合计 571、组织该工程所需的机电、测量、地质、矿建工程技术人员对施工图纸进行会审,精心编制施工作业规程,针对该工程制定质量措施和安全措施。

2、根据《矿山井巷工程施工及验收规范》GBJ213-90、《工程测量规范》GB50026-93、《土方与爆破工程施工及验收规范》GBJ201-83、《钢筋焊接及验收规范》JGJ18-84、《煤矿井巷工程质量检验评定标准》MT5009—94的要求备齐各种施工原始记录表。

3、依据施工准备的实际情况,及时如实填写开工申请报告单,经甲方、监理工程师批准后立即开工。

四、施工机具准备根据施工图纸的要求,制定详细的材料、设备进场计划,调运工程所需的配套设备,所需地材由供应部门及时统一货源,保证工程施工顺利进行。

第二节施工工序安排先进行表土层明槽开挖,然后进行明槽段混凝土砌碹,接着基岩段掘进。

第三节施工方案根据工程特点及业主要求:结合我公司施工多条同类斜井的经验,并结合我公司施工设备情况及施工队伍技术水平,本工程采用机械化作业线组织快速施工。

拟采用P-90B耙斗装岩机装岩,3m3箕斗运输,XTK1×2.5×2B-20绞车提升,地面设大型矸仓,自卸汽车翻矸为主的机械化作业线组织施工。

第四节施工方法一、表土段施工方法本矿井井筒表土段设计采用明槽开挖,水平开挖长度77.6m,边、仰坡均按50°放坡,开挖土方共计7362m3,施工采用大型液压反铲挖掘机挖土,自卸汽车排土,土质坚硬时辅以松动爆破。

开挖完成后,按要求进行三七灰土回填,回填时分层摊铺、分层夯实,分层厚度300mm,然后支模浇注砼。

按要求留设伸缩缝。

井筒明槽段碹体外部涂刷沥青聚氨酯防水涂料,然后回填巷道外围。

二、风化基岩段施工方法为保证施工安全,遇围岩破碎时采用管棚法通过该区域。

即用φ42mm 钻头超前打2.0深的钻眼,然后楔进φ42mm长2.0的钢管,钢管及棚子打安好后,通过钢管口注浆,然后用风镐配合手镐掘进,掘进1.0m以后继续扶棚,如此循环直到通过松散破碎带。

临时支护采用Ф16×1600mm钢筋树脂锚杆,围岩破碎时辅以喷射砼支护,喷砼厚度50mm。

永久支护采用混凝土支护,浇筑砼强度C25,厚度400mm,短掘短砌,每掘进6-9m后立模浇注砼。