亚井大桥施工组织设计

合集下载

大小井特大桥施工流程

大小井特大桥施工流程

大小井特大桥施工流程下载温馨提示:该文档是我店铺精心编制而成,希望大家下载以后,能够帮助大家解决实际的问题。

文档下载后可定制随意修改,请根据实际需要进行相应的调整和使用,谢谢!并且,本店铺为大家提供各种各样类型的实用资料,如教育随笔、日记赏析、句子摘抄、古诗大全、经典美文、话题作文、工作总结、词语解析、文案摘录、其他资料等等,如想了解不同资料格式和写法,敬请关注!Download tips: This document is carefully compiled by theeditor. I hope that after you download them,they can help yousolve practical problems. The document can be customized andmodified after downloading,please adjust and use it according toactual needs, thank you!In addition, our shop provides you with various types ofpractical materials,such as educational essays, diaryappreciation,sentence excerpts,ancient poems,classic articles,topic composition,work summary,word parsing,copy excerpts,other materials and so on,want to know different data formats andwriting methods,please pay attention!大小井特大桥施工流程一、施工准备阶段。

在开始大小井特大桥的施工之前,一系列精心的准备工作必不可少。

公路工程总体施工组织设计(PPT)

公路工程总体施工组织设计(PPT)
道路工程一般路段采用双向四车道,路基顶宽26m,洋口港区路段采用双 向六车道,顶宽33.5m,路基设计标高为中央分隔带外侧边缘处路面标高。
26m路基标准横断面图
33.5m路基标准横断面图
1.工程简介及规模
桥涵工程大桥一座为洋口大桥全长536.22m,中桥一座为陆家河桥全长 48.10m,小桥一座为卫海闸河桥全长30.08m,圆管涵18道,箱涵1道,盖板 涵1道。后张法预制组合箱梁140片,先张法预制空心板梁192片。大桥洋口大 桥中心桩号为K47+738.03,桥跨布置形式为(3-25)+(4-25)+(50+80+50) +(4-25)+(3-25)m,总长536.22m。桥梁主桥采用50+80+50m三跨预应 力砼变截面连续箱梁跨越四贯河,两侧引桥采用两联先简支后连续部分预应力 砼组合箱梁。
4.编制安全施工方案,下发安全技术交底,施工时严格
按照技术交底执行。
梁板的预制与架设: 1.进场后进行详细的施工调查,不断优化、确定各种参
必须统筹兼顾,妥
3 善处理好桥梁制、
运、架与其他工程 施工进度及工序间 的合理衔接。
数(如运输半径、生产周期),完善预制场布局设计。 2.采用先进的桥梁制、运、架设备,优化制、运、架梁 设备的选型、配套和养护,提高设备的可靠性与生产率。 3.统筹安排路基、桥梁和制、架的施工,避免相互干扰, 确保工期目标。
四通一平
4)施工通讯 项目经理部、梁场及搅拌站等办公处均引入程控电话及传真机,并配备移动电话。
项目经理部开通宽带网线与各个区域设置计算机局域网,通过互联网与业主相连, 实现信息双向沟通。
5)施工场地 洋口大桥施工现场已完成清表和整平。并合理规划了钻孔桩泥浆池和沉淀池。我部

市政道路改造工程施工组织设计

市政道路改造工程施工组织设计

目录第一章总体概述 (4)一、工程概况 (4)1、工程概述 (4)2、施工条件 (4)二、施工总体方案 (5)1、施工分段 (5)2、施工总体方案 (5)三、新技术、新工艺、新材料、新设备的使用 (6)1、设计原则 (6)2、新建路面设计参数 (6)3、路面结构组合设计 (6)四、质量目标 (6)五、工期目标 (8)六、安全、文明施工目标 (9)七、编制依据及原则 (9)第二章施工进度计划和各阶段进度的保证措施 (9)一、施工进度计划 (9)二、各阶段进度的保证措施 (10)2。

1确保施工进度的总体措施 (14)2.2各分部分项工程施工进度计划保证措施 (15)三、项目部进度违约责任制度 (15)四、进度违约承诺 (15)第三章劳动力和材料投入计划及其保证措施 (17)第一节劳动力投入计划及其保证措施 (17)一.劳动力投入计划 (17)二、劳动力投入保证措施 (17)第二节材料投入计划及其保证措施 (20)一、材料投入计划 (20)二材料计划保证措施 (20)第四章机械设备投入计划 (19)第五章施工平面布置和临时设施布置 (20)一、布置原则: (22)二、施工场地布置 (23)三、临时道路 (23)四、临时水电 (23)第六章关键施工技术、工艺及工程项目实施的重点难点分析和解决方21第一节路基工程施工技术、工艺 (21)一、挖方路基施工技术、工艺 (21)二、路基填筑施工技术、工艺 (23)三、路基工程竣工 (30)第二节排水工程施工技术、工艺 (31)一、钢筋砼雨水管工程施工技术、工艺 (30)二、施工准备及测量放线 (32)三、沟槽开挖 (33)四、管道基础施工 (33)五、管道安装 (34)六、管座施工 (35)七、管道接口处理方法 (35)八、检查井、进水井施工 (36)九、闭水试验 (38)十、沟槽回填 (38)十一、施工难点、重点及解决方案 (39)第三节、路面工程施工技术、工艺 (39)一、级配碎石施工技术、工艺 (40)二、水泥稳定碎石基层施工技术、工艺 (41)三、水泥搅拌桩施工技术、工艺 (43)四、路缘石、平石施工方法 (48)五、土工格栅施工技术、工艺 (49)六、改性乳化沥青稀浆封层+透层施工技术、工艺 (50)七、改性乳化沥青粘结层施工技术、工艺 (51)八、沥青砼面层施工技术、工艺 (45)九、人行道工程施工技术、工艺 (49)十、施工难点、重点及解决方案 (55)第七章安全、文明施工措施 (56)第一节安全施工措施 (55)1、建立安全生产管理机构及安全保证体系 (55)2、落实安全生产责任制 (56)3、安全施工措施 (60)4、施工现场临时用电安全措施 (60)5、机械设备安全防护措施 (62)6、项目安全事故处理 (62)7、安全检查制度 (63)第二节文明施工措施 (65)1、文明施工保证体系 (65)2、文明施工措施方案 (65)3、施工现场文明施工管理 (66)4、文明施工检查措施 (68)第八章工程质量保证措施 (69)一、建立、健全完整的、严格的、科学的质量保证体系 (68)二、工程质量总体保证措施 (70)三、分项分部工程质量保证措施 (70)四、工程质量管理制度 (79)第九章减少扰民噪音、降低环境污染措施 (81)一、噪声 (81)二、振动 (81)三、施工粉尘 (82)四、排水 (82)五、垃圾清运 (82)第十章工期保证措施 (83)一、确保工期的总体措施 (83)二、各主要分部分项工程工期保证措施: (85)第十一章冬、雨季施工技术措施 (86)第一节冬季施工技术措施 (86)第二节雨季施工技术措施 (87)一、雨季施工的组织措施 (88)二、雨季施工的技术措施 (88)第十二章地下管线及其他地上地下设施的保护加固措施 (88)第十三章新技术应用 (90)一、SBS改性沥青技术 (93)1、SBS沥青混合料的配合比设计 (93)2、SBS沥青混合料的施工 (91)二、沥青稀浆封层 (98)附件: 施工平面图布置 (97)拟投入的主要施工机械设备表 (98)计划开、竣工日期和施工进度网络图 (101)项目管理机构配备情况表 (103)项目经理简历表 (104)项目技术负责人简历表 (105)第一章总体概述一、工程概况工程名称:南宁市云景路改造工程建设地点:南宁市云景路建设单位:南宁市城市建设投资发展总公司设计单位:南宁市城市规划设计院建设规模:本工程工程起点接凤翔路,终点至高坡岭路,设计路线全长4。

高速公路施工组织设计方案

高速公路施工组织设计方案

表施工组织设计文字说明一、工程概况(一)工程名称及规模本建设工程为叶集至信阳高速公路,总长185.4km,分为东西段。

东段为已建成的叶集至某某段半幅高速公路的扩建北半幅工程,长135.9km;西段为某某至信阳段新建全幅高速公路,长49.5km。

(二)标段工程范围及内容标段起讫桩号+~+,建设里程15.781km,建址于潢川县境域。

工程内容为路基、路面底基层和基层、结构物、防排水等土建工程。

(三)主要工程及数量:见下页?主要工程工程及数量表?。

(四)桥涵工程结构特征:见下页?桥涵工程结构特征表?。

(五)自然条件、地形及地貌:本标段路线经过地区属平原微丘区,地面高程▽~78.0m,相对高差36m。

多辟为旱田、水田,且水塘较多。

、地质及地震:本标段地表为第四系沉积物的中—低液限粘土,次层局部为中砂、砂砾,下伏泥岩、砂岩,断层不发育,区域稳定性较好;局部路段存在弱膨胀土或膨胀性土。

地震烈度为度。

本标段有淮河支流水系的多条小河,且沟渠纵横,水量充足。

垄岗地下水不发育,水位埋深>6m;谷地及阶地地下水丰富,以孔隙水为主,埋深~,主要补给来源为大气降水。

地表水及地下水水质对砼无侵蚀性。

、气象及气候:路区处于北亚热带向暖温带过渡气候区,四季清楚,冷暖适中、雨量充分。

年均气温15.1℃,月均温 1.9℃,月均温27.7℃,极端气温40.8℃、-20.5℃。

年均降水量1107mm,多集中于~月(占)。

多发暴雨,常发生在~月,尤以月最多。

暴雨强度大,易造成洪水灾害。

无霜期天。

(六)施工条件本标段系已建成的叶集至某某段高速公路扩建北半幅工程,国道及潢江、潢卜公路分别在中部及两端部穿过,并与国道在潢川县城相交,沿线乡道村路纵横连通,交通便利。

两端部跨京九、宁西铁路立交桥均已全幅建成,且台后已填土约15m,可接续路基施工。

沿线地方电源大局部可利用,零散小桥涵须自备发电机。

水源可就近低洼处打井或取用河渠、水塘洁净水。

该地区缺乏石料、白灰,盛产黄沙。

湖坑大桥基础及下部施工组织设计(分部)

湖坑大桥基础及下部施工组织设计(分部)

湖坑大桥基础及下部施工组织设计(分部)一、概述1、地质情况:本桥位处表层为约0.8~11.8米的砂质亚粘土覆盖,结构较密实,地层岩性主要为化钾长花岗岩,地层主要有:1、砂质亚粘土、2、全风化钾长花岗岩、3、强风化钾长花岗岩、4、弱风化钾长花岗岩、5、微风化钾长花岗岩。

2、基础构造:桥梁基础设计为桩基础。

桩径均为φ120CM,共8根;桩径均为φ150CM,共4根;桩径均为φ170CM,共12根;桩径均为φ180CM,共28根。

3、下部构造:全桥桥墩设计为双柱式墩,墩径均为φ150CM,共40根,墩长在7-15M。

全桥盖梁共40个,台帽(含耳墙)20个,在桩基与墩柱之间设计32个系梁。

4、主要工程量:1)、C25混凝土:3062.9M3;2)、C30混凝土:1313.4M3;3)、R235钢筋:55513.0kg;4)、HRB235钢筋:446573.1kg。

二、施工组织:1、施工队伍:本桥由我项目部下辖的二工区负责施工。

该队进场人员220人,人员组成为:技术及管理人员(含质检及测试人员)20人,技术工人60人,普工140人。

主要人员一览表职务人员岗位职责施工负责人(队长)黄瑞金负责全面施工组织管理技术负责人(项目总工)满泽玖全面技术管理质检工程师黄立忠全面质量管理桥梁工程师范德忠技术指导、过程控制、施工纪录安全负责人马靖安全生产测量工程师李小奇测量放样试验工程师陈贵湘现场试验现场管理杜赵成现场管理,组织施工技术员陈宁波现场技术2、主要设备:主要设备祥见一览表,其他设备根据需要配置。

主要设备一览表名称单位数量型号拌合设备套 1 强制式1000型砼搅拌机台 1 JS350发电机台 1 75KW振动棒、电机套20 φ50、1.1KW钢筋弯曲机 台 1 GW40 钢筋切割机 台 1 GQ40 钢筋调直机 台 1 φ10 交流电焊机 台 5 BE2000 串筒 套 1 45cm 砼运输车 辆 2 6m3 气焊设备 套 2 直螺纹连接机 台 1 对焊机 台 1 吊车辆 13、工期计划: 本分部工程计划开工时间为2006年5月09日,计划完工时间为2006年11月20日,工期190天,详见安排表。

桥梁施工组织设计

桥梁施工组织设计

黄陵至延安高速公路扩能工程试验段路基桥隧工程LJ-5标段桥子沟大桥李家洼沟大桥施工组织设计中铁港航局集团第三工程有限公司黄延高速公路LJ-5合同段项目经理部二〇一三年八月目录1、编制说明........................................................ 编制范围........................................................... 编制原则...........................................................2、工程概况........................................................ 工程地质概况....................................................... 设计概况...........................................................桥子沟大桥.......................................................李家洼沟大桥..................................................... 3施工总体方案...................................................... 总体目标...........................................................质量目标.........................................................安全目标.........................................................文明施工目标.....................................................环保、水保、节能目标.............................................工期目标......................................................... 施工组织...........................................................施工组织体系.....................................................施工队伍配备及任务划分...........................................劳动力需求.......................................................主要机械设备配备................................................. 4施工方案 ......................................................... 主墩施工...........................................................0号块施工.....................................................0号块结构尺寸................................................施工工艺流程..................................................... 0号块托架方案............................................... 墩顶托架....................................................... 主墩主托架设计................................................. 翼缘板托架设计................................................. 模板结构及支撑体系............................................... 外模结构....................................................... 内模结构....................................................... 托架预压....................................................... 钢筋绑扎及预应力管道定位....................................... 砼浇筑........................................................... 浇筑准备....................................................... 砼浇筑控制..................................................... 砼浇筑注意事项................................................. 挂篮............................................................. 设计依据....................................................... 挂篮的主要技术参数............................................. 挂篮的构成..................................................... 挂篮的安装.....................................................厂内试拼.....................................................现场拼装.....................................................准备工作:..................................................拼装程序:.................................................. 挂篮的施工..................................................... 挂篮的走行..................................................... 挂篮走行的注意事项............................................. 挂篮的拆除..................................................... 使用注意事项...................................................1~18号悬浇梁段..................................................每节梁段均按以下程序施工.........................................混凝土浇筑施工要点...............................................边跨现浇段施工...................................................合拢段施工.......................................................合拢顺序、温度、时间...........................................施工顺序.......................................................平衡重.........................................................劲性骨架.......................................................合拢段混凝土浇筑...............................................悬臂浇筑注意事项................................................. 主桥箱梁预应力张拉工艺及有关要求...................................纵、横向预应力钢绞线.............................................竖向预应力钢筋张拉工艺........................................... 临时支座安装.......................................................硫磺砂浆的熬制方法...............................................硫磺砂浆临时支座的制作工艺.......................................材料...........................................................制作工艺流程...................................................硫磺砂浆临时支座的安装...........................................落梁.............................................................施工措施......................................................... 5主桥监控要点...................................................... 施工监控的意义..................................................... 施工监控测量网的建立............................................... 基准点和梁段测点的埋设............................................. 箱梁悬浇施工控制测量工作........................................... 箱梁合拢的监测.....................................................浇筑过程中精度控制要求............................................. 标高调整方法....................................................... 监测点的布置和埋设................................................. 监测精度控制措施................................................... 监理工序质量关..................................................... 6雨季施工措施...................................................... 雨季施工安排.......................................................准备工作.........................................................雨季施工措施.....................................................雨季材料保障措施................................................. 7冬季施工措施...................................................... 编制依据........................................................... 编制原则........................................................... 冬季施工特点....................................................... 施工准备........................................................... 冬期施工测温.......................................................冬期施工测温的有关规定...........................................冬期施工的测温范围.............................................测温人员的职责.................................................冬期施工测温的准备工作.........................................人员准备.......................................................测温工具的准备.................................................测温孔的设置...................................................测温方法和要求.................................................测温管理....................................................... 冬期施工措施.......................................................混凝土工程冬季施工措施...........................................冬季施工混凝土对原材料的要求...................................混凝土的拌制...................................................混凝土的运输...................................................混凝土的浇筑...................................................混凝土的养护...................................................钢筋冬期施工.....................................................钢筋的冷拉和冷弯...............................................钢筋焊接.......................................................预制梁板的砼浇筑及养护...........................................梁板混凝土的蒸汽养护.............................................预应力梁板的张拉和压浆...........................................冬施安全与防火................................................... 8夏季施工措施...................................................... 9质量保证措施...................................................... 大体积混凝土质量措施............................................... 墩柱质量保证措施................................................... 预应力工程质量控制措施............................................. 悬臂浇筑梁施工质量保证措施......................................... 避免桥梁预埋件位移的措施........................................... 10安全保证措施..................................................... 高空作业安全管理措施............................................... 一般规定........................................................... 防止高空坠落....................................................... 防止物体打击....................................................... 11文明施工、文物保护保证体系及措施................................. 文明施工管理体系及措施.............................................文明施工目标.....................................................文明施工组织机构.................................................文明施工措施..................................................... 文物保护管理措施...................................................桥子沟大桥、李家洼沟大桥施工组织设计1、编制说明编制范围本方案编制范围为黄延高速公路LJ-5合同段K21+605桥子沟大桥、K27+230李家洼沟大桥预应力混凝土刚构-连续梁组合体系桥。

井柱桥工程施工方案

井柱桥工程施工方案

井柱桥工程施工方案一、工程概况井柱桥工程位于XX市XX县,项目总用地面积为XX平方米,规划建设总用地面积为XX平方米。

项目东至XX路,南至XX路,西至XX路,北至XX路。

项目用地范围为XX县第五小学原址和周边用地,现状为村镇居民点和村组经营性建设用地。

井柱桥规划桥长XX米,桥面宽XX米,双向四车道桥,设计荷载等级为XX级,采用集成梁结构形式。

建设内容主要包括桥梁项目、道路改造、地下管线迁改等,并在工程一期内全部完成。

二、建设内容及范围井柱桥工程包括主桥桥梁工程、桥梁上下连接道路工程、配套排水设施及附属工程。

其中主要建设内容包括:1.主桥桥梁工程:井柱桥主要为钢筋混凝土梁式桥,共设置X个桥梁支座。

桥梁全长XX 米,其中主桥两侧引道长XX米。

2.桥梁上下连接道路工程:包括主桥两侧道路改造、引道工程、辅道及人行道。

3.配套排水设施及附属工程:包括雨水、污水排水系统、道路照明、交通标志标线等。

三、施工组织设计井柱桥工程施工组织将按照“先进的施工技术、严格的管理体系、完善的质量体系、有效的安全体系、精细的保障体系”的原则,制定科学的施工组织方案,确保工程具有较高的施工效率和质量保障。

1.施工组织机构项目部设总指挥、副指挥,分管项目管理、施工管理;安全管理负责人、质量管理负责人、材料管理负责人和财务保障负责人各一名;项目现场设主任工程师、总监理工程师、总监理工程师,总监理工程师分管项目管理、施工管理,总监理工程师分管安全管理和材料管理;下设技术、机械、进度、资料、财务和实验等部门。

具体人员构成及其职责分工详见项目组织结构图。

2.施工管理施工现场实行专人、专岗、专责制度,由总监理工程师、总指挥指挥施工,具体执行由各分管工程师负责。

施工过程中,项目部将严格按照设计图纸和规范进行,做到施工安全、质量保证。

人员上岗前经过专门的技术培训和考核,所有设备必须经过检测合格方可使用。

3.安全管理工程施工过程中将建立健全安全生产管理制度,加强安全教育培训,落实各项安全措施,确保工程施工安全。

桥梁工程施工组织设计

桥梁工程施工组织设计

施工组织设计、施工方案一)工程名称本标段工程名称为:浏阳市金刚镇人民政府金刚大桥建设工程二)工程地点浏阳市金刚镇三)工程概况本工程为浏阳市金刚大道灌江河金刚大桥新建工程,位于浏阳市金刚镇,跨越灌江河,桥梁所在线路为金刚大道;新建桥梁上部结构形式采用2*22m简支后张预应力空心板,桥面连续;桥梁斜交角度20度,下部结构采用双柱式桥墩台桩基础,桥梁总长50.08m,桥宽22m 四)水文气象及工程地质条件本项目所在地浏阳市金钢镇属亚热带季风气候区,四季分明,冷热有节,雨量充裕,雨热同季,无霜期长,年平均气温在摄氏15度至16.6 度之间,年降雨量1100至1300毫米,4-10 月份,降雨量占全年降雨量的80%,年日照时数为1800 至2000小时。

五)供电与供水1、供电:本项目位于浏阳市金钢镇区域,均有供电网,项目部设置电力线路与施工驻地、拌合场等相接。

工地配备50kw、30kw发电机组各2台,备施工生产和生活所需。

2、供水:本项目沿线河渠纵横,且地下水丰富,埋深一般1-2m。

经调查,沿线水质良好,可作为工程用水和生活用水。

六)建筑材料的供应施工用水泥可从浏阳水泥厂购买;钢材、木材、石料均在浏阳、长沙等地购买;路基土方一般考虑就近取土原则;所有材料均采用汽车运输至现场。

水泥、钢材、木材从购货点运至工地后堆放在临时仓库内,设专人保管,注意防雨、防潮,以免材料腐蚀。

七)工期招标文件规定本工程计划日历天240 天八)施工总目标1 、质量目标:工程质量要求符合国家有关公路工程施工规范、验收标准,并达到合格工程标准。

2 、安全目标:无死亡重伤事故和重大机械事故。

3、文明施工目标:施工环境优美,施工行为规范。

1 .主要设计指标、编制依据及原则一)主要设计指标本工程采用计算行车速度60 公里/ 小时的标准设计,三级公路等级,桥梁宽度12m双车道。

桥梁荷载:公路二级、人群-3.0kn/m 3. 设计洪水频率:小桥1/50. 地震:VI 度,按VII 度设防。

  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

亚井大桥施工组织设计
一、工程概况
⑴工程简介
亚井大桥中心里程桩号为K63+697.00,里程桩号K63+580~K63+817,全长237m。

为双幅四车道,桥面宽2×12.25m,桥型为11×20m预应力砼T梁。

设计荷载:汽车-超20级,挂车-120。

⑵构造型式
①下部构造
桥墩为单排双柱式墩,直径为130cm。

桥台为重力式U型台。

桥墩基础为直径140cm的钻孔灌注桩,桩面以系梁联接,系梁截面为140cm×110cm。

0号桥台基础为直径150cm的挖孔灌注桩,桩顶以承台联接。

11号桥台基础为扩大基础。

②上部构造
上部结构为11×20m后张法预应力砼T梁,T梁在桥横断面上布置为10片,全桥共110片;桥面铺装底层为钢纤维混凝土,面层为沥青混凝土。

支座采用板式橡胶支座和四氟滑板支座两种。

⑶桥位处自然条件
桥位地处亚热带气候区,属中亚热带温暖湿润气候,气象详情见前面所述。

桥位区地处贵州高原东部苗岭山区,位于三穗县城南5Km。

桥位区附近海拔616.60m~682m之间,相对高差65.40m,大桥横跨寨里河,高程在616.60m~644.50m,相对高差27.9m。

桥位为一宽阔的河流及稻田坝子地带,三穗岸桥台位于一小山脊上,地形较陡,坡度30°~40°。

凯里岸桥台位于河流水稻田上,距320国道主干线400m,交通便利,为构造侵蚀低山、丘陵地貌。

⑷工程水文、地质条件
桥位处覆盖层主要为耕植土、亚粘土、卵石土、碎石土。

基岩为
泥岩,其风化程度分为强风化和中风化两层。

亚井大桥斜跨寨里河,河宽3.5m,枯水季节0.0~0.20m,丰水期水位猛涨,水深较大,但持续时间较短,对大桥施工影响不大。

桥位位于河流部位近地表浅层地下水丰富,浅层地下水由河流补给。

二、主要工程数量
挖孔灌注桩:
D=1.5m共12根,总长度120米;
钻孔灌注桩:
D=1.4m共40根,总长度340m。

预制20m后张法预应力砼T梁110片;
主要工程数量表
三、施工队伍安排
1、施工队伍安排
根据本桥工程数量、工期进度等情况,安排桥梁工程一队(112人)负责施工(见下页框图)。

2、机械配置
四、施工计划
预计2003年6月5日开工,工期历时490天,于2004年9月30日完工。

各部分具体的进度计划分述如下:
施工准备:2003年6月5日~2003年6月15日;
钻孔灌注桩:2003年6月15日~2003年9月30日;
挖孔灌注桩及桥台扩大基础:2003年6月15日~2003年8月19日;
桩系梁、墩柱及盖梁施工:2003年7月25日~2004年2月25日;
桩基承台、台身及台帽施工:2003年8月24日~2004年2月25日;
20mT梁预制及安装:2003年11月7日~2004年5月31日;
桥面系、防撞墙、搭板、锥坡施工:2004年5月31日~2004年9月18日。

各分项工程施工的先后顺序见《亚井大桥施工计划网络图》。

五、临时设施及施工现场平面布置
1、营房及施工场地
桥梁工程一队营房及施工场地设凯里岸填方段路基上,占地2000平方米。

2、临时工程
⑴施工便道
自320国道引入一条施工便道(便道1)至营房和施工场地,便道长500m宽4.5m,采用15~20cm厚砂砾路面,路面高出地表30cm。

桥区内沿着等高线修建通向贯通全桥的施工便道,跨越冲沟埋设砼涵管通过。

⑵施工用电
就近利用当地电源,安装一台315KVA的变压器。

为了保证施工正常进行,并自备1台120kw发电机。

⑶施工用水
本桥下常年有水,可满足施工及生活用水需要。

六、施工方法及施工工艺
(一)施工准备
a. 组织参与本工程施工的全体员工现场调查。

内容:核对设计图纸;临时房屋及临时设施的布置和施工;调查施工界内障碍物和拆迁情况;施工生活用水用电供应方法和大致数量;施工便道的引入;熟悉施工图纸和预算;明确本工程的施工范围以及修建意义;测量放
线。

b.在现场调查的基础上研究本工程的总体布置和施工方案,群策群力,集思广益,力求施工方案合理、可行,达到确保工期的要求。

c.编制施工技术交底,层层进行技术交底。

d.会同监理工程师、设计人员研究确定本工程的试验办法和质检措施等。

e.联系当地政府部门和公安部门,通报我们的施工计划和措施以及干扰情况,取得他们的支持和谅解。

f.填写开工报告,取得监理工程师同意后施工。

(二)挖孔桩施工工艺
桥台桩基础采用人工挖孔,孔壁支护类型选择混凝土(15cm厚)护壁。

为防止孔口坍塌,锁口混凝土厚度采用50cm,高1m。

桩身砼采用漏斗、套筒一次性灌注完成。

1、施工准备
⑴对于斜坡上的挖孔桩,施工前按设计要求进行刷坡处理,及时做好边坡的防护工作。

⑵施测桩位十字线,定出桩孔准确位置,设置“米”字型护桩并经常检验校核。

⑶孔口四周挖排水沟,做好排水系统。

及时排除地表水,雨季施工时,孔口搭设雨棚。

2、制作井圈锁口混凝土
以桩基外轮廓尺寸每侧外延40cm开挖土体,开挖深度达1m时,立模板,灌注锁口混凝土,锁口混凝土高出地面30cm,防雨水流入孔内。

挖孔灌注桩施工工艺框图
3、挖掘方法
采用人工挖孔,组织两班连续作业,为防止支护不及时造成挖孔坍塌,每班必须完成挖孔及护壁混凝土支护才能交接班,而不以时间作为交接班控制。

每个孔位安排开挖2人,提升出土及排水2人,装碴运输2人,浇筑护壁混凝土6人(由上述人兼)。

每次开挖1.0m~1.2m即施作护壁混凝土。

护壁混凝土施工详见下面所述。

4、挖掘的一般工艺要求
⑴挖掘时,不必将孔壁修成光面,要使孔壁稍有凹凸不平,以增加桩的摩阻力。

⑵在挖孔过程中,经常检查桩孔尺寸和平面位置:桩位误差不得大于30mm;倾斜度不超过2‰;孔径与孔深必须符合设计要求。

⑶挖孔时如有水渗入,及时灌注护壁混凝土,防止水在孔壁浸淌。

相关文档
最新文档