向家坝水电站长距离带式输送机规划设计及安装调试

合集下载

带式输送机的设计计算

带式输送机的设计计算

第3章 带式输送机的设计计算设计胶带输送机时,要知道输送机的工作条件(如使用地点、运距、倾角及被运货载的性质,如散集容重、快度等),以及装载和卸载方式等,根据工作条件的要求合理地确定输送机的传动系统和结构方案。

第3.1节 原始数据(1) 输送机长度:1000m(2) 带速:v=2.5m/s(3) 选择带宽B=1.2m 的GX2000型钢丝绳芯胶带3.2输送机输送量的计算取v 表示胶带运动速度(m/s ),q 表示单位长度胶带内货载的重量(kg/m ),则胶带输送机的输送能力为3.6(/)Q v t h = (3-1)单位长度的载荷q 值决定于被运货载的断面积F (m 2)及其容重γ(t/m 3),对于连续货流的胶带输送机单位长度重量为1000(/)q F kg m γ= (3-2)将式(3-2)代入(3-1)式,则得3600(/Q F v t h γ= (3-3)货载断面积F 的大小主要取决于胶带的宽度。

如图3—1所示为槽形胶带上货载的断面。

图3—1 槽形胶带上货载断面货载断面由梯形断面F 1和圆弧面积F 2组成。

在胶带宽度B 上,货载的总宽度为0.8B ,中间托辊长为0.4B ,货载在带面上的堆积角为ρ,并堆积成一个圆弧面,其半径为r ,中心角为2ρ。

则梯形面积为12(0.40.8)0.2tan 3020.0693B B B F B +⨯== 圆弧面积为222(2sin 2)20.4()(2sin 2)/2sin r F B ρρρρρ⨯-==⨯- 总面积为12220.40.063()(2sin 2)/2sin F F F B B ρρρ=+=+⨯- 即 220.4[0.063()(2sin 2)/2]sin F B ρρρ=+⨯- (3-4) 式中 ρ——货载的堆积角,(弧度);将式(3-4)代入(3-3),化简后,可得胶带输送机的输送能力2(/)Q KB v C t h γ=式中 B ——胶带的宽度(m );Q ——输送量(t/h );v ——带速(m/s );γ——货载散集容重(t/m 3);K ——货载断面系数,K 值与货载的堆积角ρ值有关, C ——输送机倾角系数。

长距离大运量带式输送机关键技术及国内发展现状_王鹰

长距离大运量带式输送机关键技术及国内发展现状_王鹰

官地矿

90ห้องสมุดไป่ตู้0
1 200
5 600
3.5
3 ×630
CST
2003
上榆泉矿 煤 2 000 1 400 2 800
4
2 ×560
CST
平塑煤矿 煤 2 500 1 400 2 200
4
2 ×450
CST
上海青浦
表 2 所列的圆管带式输送机中 , 上海梅山钢铁 厂使用的圆管带式输送机 的输送距离最长 , L =2 230 m ;秦皇岛港矿石码头使用的圆管带式输送机 的输送量最大 , Q =4 500 t/ h ;而贵州瓮福肥厂使 用的圆管带式输送机是目前国内线路布置最复杂的 输送机 , 沿线共跨过 4 个山头和 1 条河 , 绕过 2 座 山 , 穿过 2 个建筑群 , 水平面转弯 3 个 , 垂直面转 弯 6 个 , 空间转弯 3 个 。
由于带式输 送机使用的特殊 性 , 大多 采用高 压 、 大容量鼠笼电机 , 同时要解决电气的一系列相 关问题 , 从而使其线路复杂 , 在这种情况下 , 采用 高压变频器投资大 , 价格高 , 可靠性差 , 而且需要 采用特殊电机 ;同时变频调速会产生强大的信号干 扰 , 影响其他电气控制设备的正常工作 。 这些都限 制了变频调速在某些场合中的应用 。
管径 :400 mm 额定输送量 :Q=3 500 t/ h 带速 :v =4.7 m/ s 角度 :0 ~ 11° 输送物料 :铁矿石 水平机长 :2117 m
管径 :300 mm 额定输送量 :Q=1 000 t/ h 带速 :v =3.15 m/ s 角度 :0 ~ 6° 输送物料 :铁矿石 水平机长 :2 230 m
专题综述 长距离大运量带式输送机 关键技术及国内发展现状

皮带输送机安装课件

皮带输送机安装课件

(四)保护安装要求 1、防滑保护 1.1 安装要求 带式输送机防滑保护应安装在带式输送机回程带上面,或改向滚筒侧面。 固定带式输送机(钢丝绳芯胶带带式输送机、运输大巷铺设的带式输送 机,下同),应装在机头卸载滚筒与驱动滚筒之间;当两驱动滚筒距离 较远时,也可安装在两驱动滚筒之间。其它地点使用的带式输送机,应 安装在回程带距机头较近处。普通带式输送机(采掘工作面顺槽用带式 输送机、其它地点用800mm及以下可伸缩带式输送机,下同),防滑保 护可设在改向滚筒侧面,与滚筒侧面的距离不超过50mm。 防滑保护传感器应采用标准托架固定在带式输送机机头大架上,严禁用 铁丝或其它物品捆扎固定。 1.2 保护特性 当胶带速度10s内均在(50%~70%)Ve(Ve为额定带速)范围内、胶带 速度小于或等于50%、胶带速度大于或等于110%Ve时防滑保护应报警, 同时中止带式输送机的运行,对带式输送机正常启动和停止的速度变化, 防滑保护装置不应有保护动作。





3、跑偏保护 3.1 安装要求 固定带式输送机的跑偏保护应成对使用,且机头、机尾处 至少各安装一组。第一组距离机头卸载滚筒(机尾导向滚 筒)10~15m,当带式输送机坡度变化较大易造成胶带跑 偏时,应在变坡位置处安装一组。普通带式输送机跑偏保 护只需在距离机头10~15m处安装一组即可。 跑偏保护应用专用托架固定在带式输送机大架或纵梁上, 跑偏杆应垂直胶带边缘(所夹锐角不小于80度),对带式 输送机上带面的偏离情况进行保护。 3.2 保护特性 3.2.1 当运行的胶带跑偏超过托辊的边缘20mm(如使用三 联辊的带式输送机超过70 mm)时,跑偏保护装置应报警, 经延时5~15s后,跑偏保护装置应可靠动作,能够中止带 式输送机的运行。 3.2.2 对于使用接触式跑偏传感器之类的跑偏保护装置,其 保护动作所需作用于跑偏传感器中点正向力为20~100N。

向家坝二期工程研究报告1(施工布置)

向家坝二期工程研究报告1(施工布置)

向家坝水电站位于金沙江下游,是金沙江梯级开发的最后一级电站。

坝址位于峡谷出口处,左岸为四川省宜宾县,右岸为云南省水富县安边镇。

坝址距下游宜宾市32km,距水富县城约1.5km。

内昆铁路在坝址下游3km处设有水富站。

工程枢纽主要由挡水建筑物、泄洪消能建筑物、冲排沙建筑物、左岸坝后引水发电系统、右岸地下引水发电系统、通航建筑物及灌溉取水口等组成。

其中拦河大坝为混凝土重力坝,电站厂房分列两岸布置,泄洪建筑物位于河床中部略靠右侧,一级垂直升船机位于左岸坝后厂房左侧,左岸灌溉取水口位于左岸岸坡坝段,右岸灌溉取水口位于右岸地下厂房引水口右侧,冲沙孔和排沙洞分别设在升船机坝段的左侧及右岸地下厂房的进水口下部。

坝顶全长909.25m,最大坝高162m,电站设计正常蓄水位380.00m,左岸坝后及右岸地下厂房各安装有4台单机容量为750MW机组,总装机容量6000MW。

本次二期工程主要包括右非坝段、泄水坝段(含消力池)、厂房坝段(含坝后厂房)、升船机坝段、冲沙孔高程340.00m以上部分、左非①〜左非⑥高程280.00m 以上部分、导流底孔封堵、冲沙孔导流底孔段改造及二期导流工程。

本次施工组织研究的主要依据:a) 右岸施工区地形、地质、施工条件;b) 向家坝水电站可性行研究报告;c) 相关专题报告;d) 有关会议审查意见;e) 国家与行业现行有关规程规范。

2007年4月我局受向家坝工程建设部的委托,对《二期工程混凝土施工项目施工组织设计的八大技术难题》进行了研究,通过分析比较论证、主要结论如下:1、二期工程施工总布置中、施工场地规划基本能满足两个标段施工需要、在施工道路的规划设计中、由于本工程施工强度高、受下基坑的施工道路宽度的限制,车流量较大,为减少施工干扰,需进一步研究在大坝基坑内形成循环道路的可能性。

2、二期工程施工总进度与坝体分缝关系很大、采用一条纵缝、混凝土施工主导设备布置均能满足施工强度要求,坝体施工进度也能够满足节点工期的要求、采用二条纵缝、坝体强度加大、需考虑增加部分混凝土施工主导设备、施工风险较大。

向家坝水电站资料

向家坝水电站资料

向家坝水电站资料第一篇:向家坝水电站资料中国第三大水电站——向家坝水电站工程总投资:434亿元工程期限:2008年——2015年向家坝水电站是金沙江下游梯级开发中最末的一个梯级,坝址位于云南省水富县(右岸)和四川省宜宾县(左岸)境内两省交界的金沙江下游河段上,电站上距溪洛渡电站坝址157公里,下距水富县城区1.5公里、宜宾市区33公里。

静态投资434亿余元。

向家坝水电站正常蓄水位380米时,保证出电200.9万千瓦,年平均发电量307.47亿千瓦时。

正常蓄水位380米(现在水位约为270米),死水位(供水期未发电消落水位)370米。

水库面积95.6平方公里,水库为峡谷型水库。

控制流域面积45.88万平方公里,占金沙江流域面积的97%。

水库总库容51.63亿立方米。

回水长度156.6公里。

工程计划2008年截流,2012年首批机组发电,2015年建设完工,届时中国将新添三分之一个三峡工程。

工程枢纽结构:大坝、左岸坝后厂房、左岸升船机、河中泄水坝、右岸地下厂房、两岸坝后厂房、两岸灌溉取水口共7个部分。

大坝情况:坝型为重力坝,坝顶高程383米,最大坝高161米,坝顶长度909.3米。

向家坝电站装机容量600万KW(共8台机组,每台75万KW),正常蓄水位380米时,保证出电200.9万KW,多年平均发电量307.47亿KW.H,装机年利用小时数5125小时。

向家坝加上1260万千瓦的溪洛渡电站,其总发电量约大于三峡水电站。

向家坝、溪洛渡电站建成后可以解决三峡最大的心病——泥沙淤积。

专家认为,金沙江中游是长江主要产沙区之一,多年平均含沙量每立方米达1.7公斤,约为三峡入库沙量的1/2。

利用金沙江输沙量高度集中在汛期的特性,合理调度可使大部分入库泥沙淤积在死库容内。

而溪洛渡正常蓄水位达600米,死水位高达540米,拦淤泥沙后不影响电站效益。

据分析计算,溪洛渡竣工投用后,三峡库区入库含沙量将比此前天然状态减少34%以上。

长距离带式输送机与翻带装置

长距离带式输送机与翻带装置

长距离带式输送机与翻带装置摘要:本文首先分析长距离带式输送机的特点及应用,接着分别用失败案例及成功案例分析翻带装置的作用及设置的必要性。

关键词:长距离;带式输送机;翻带装置引言随着我国经济的持续发展,各行各业对物资运输提出了新的要求。

它是一种能够和汽车运输相媲美的输送装置。

设置翻滚装置能够有效解决长距离输送机运行很多问题,对输送机的稳定运行发挥了直观重要的意义。

1、带式输送机特点经过一个世纪的发展,皮带输送机已成为物料搬运的设备。

当前现代农业不断发展,同时工业,运输和运输规模扩大,加上对物资运输要求不断提高,增加了诸如经济性,可靠性和材料处理效率等要求。

带式输送机在输送能力,经济效率,安装和维护等方面优势显著,并已成为优选的输送设备之一。

它也越来越广泛地使用,并且带式输送机功能性也在增加。

与其他输送设备相比,普通带式输送机具有以下特点:1. 1输送机优点(1)较大能力的输送功能。

该材料能够不间断地输送,并且能够在运输中不停机而进行装卸,并且不会由于空载而中断运输。

此外,因为不频繁的起动和制动,可以实现快速运转。

连续和高速输送功能是其他设备难以相媲美的。

(2)结构简单。

皮带输送机的线范围内设置和输送物料,单一动作,重量轻,成本低。

由于负载均匀且速度稳定,工作期间消耗的功率变化较小。

在相同的输送条件下,该类输送机功率通常很小。

(3)较长的输送距离。

单机运输长度较长,而且多个单机系列可以串联连接到长距离传输线。

1. 2输送机缺点(1)通用性较差。

每种类型的机器只能运输某种类型的物料和一定的输送能力。

(2)输送线路存在较大局限性。

具有固定的输送线路,一旦输送线改变,输送线必须重新排列。

如果您需要经常更改装载和卸载点的位置,则需要将传送带安装在特殊的机架上并使用它们的运动来适应传送要求。

(3)不能自动取料。

除了一些可以自动从堆中拾取物料的皮带输送机外,其中大部分都是通过辅助设备回收的。

1.3长距离皮带输送机的应用长距离带式输送机在使用过程中通常会消耗大量的投资成本,并且该项目带来的经济效益也相当可观。

带式输送机传动滚筒的设计-精品

带式输送机传动滚筒的设计-精品

目录摘要 (Ⅰ)Abstract (Ⅱ)第一章绪论 (01)1.1概述 (02)1.2传动滚筒的研究目的和意义 (03)1.3国内外研究现状 (04)1.4本文研究的主要内容 (04)第二章带式输送机传动滚筒的结构 (05)2.1 结构与种类 (07)2.2 运行阻力 (10)2.3 传动滚筒轴功率 (10)2.4 传动理论 (13)2.5 传动滚筒的受力分析 (15)第三章传动滚筒的结构设计 (16)3.1 滚筒失效形式与许用应力的确定 (18)3.2 传动滚筒结构设计 (30)第四章传动滚筒有限元模型的建立与结果分析 (31)4.1 传动滚筒有限元模型的建立 (35)4.2 节点耦合与约束方程 (37)4.3 载荷和约束 (38)4.4 求解和后处理 (39)4.5 结果分析 (41)结论与建议 (42)参考文献 (43)致谢设计图纸摘要带式输送机是现代最主要的散状物料输送设备之一。

滚筒是带式输送机的主要传部件,它的作用有两个:一是传递动力,二是改变输送带运行方向。

带式输送机滚筒的设计质量,关系到整个输送机系统的性能、安全性和可靠性。

目前,国内滚筒的设计一般采用近似公式,对于中小型滚筒已经能够满足工程需求,但对于大型滚筒这种设计方法其结果与工程实际有一定的差距,它的安全性和可靠性难以保障。

由于缺乏精确的计算方法,如果盲目的增大安全系数,会使结构尺寸变大,重量增加,强度得不到显著的提高同时又增加了成本。

本文主要包括以下几方面内容:首先,对带式输送机滚筒结构的设计计算方法进行了分析研究,修正了有关计算公式,完善并统一了设计计算内容。

其次,滚筒采用实体单元,为了提高运算速度和精度,采用映射网格划分方式;分析并确定滚筒载荷;结果后处理对滚筒的各个部件的应力和应变进行分析。

本文关于带式输送机滚筒的设计计算方法具有一定的实用价值和指导意义,可以大大提高滚筒的设计质量,缩短设计的周期。

关键词:带式输送机传动滚筒有限元AbstractBelt-conveyor system is the most important transport equipment which can carry bulkmaterial. Belt-conveyor Pulley is the key transmission part in Belt-conveyor system. It hastwo functions, one is transferring power, and another is altering the operation direction of thebelt. The design quality of Belt-conveyor Pulley connects with systems security and reliabilityof the whole conveyor. At present, in our country, the design of the pulley usually adopts theapproximate formula, however, pulley that be designed out with such method can not meet theneed of manufacture, its security and reliability are difficult to guarantee. While lacking thesuitable calculation method of strength and stiffness about the pulley, if we increase the safecoefficient without enough reasons, the pulley become bigger and heavier. However thereliability of the pulley can’t be increased.The main content includes the following respects: Firstly, the paper discusses structuraldesign and calculation of the belt conveyor pulley. The related formulas are corrected and acomplete design and calculation method are provided. Secondly,in order to improving the precision, the mapping gridmethod is carved up. After disperse the load on the pulley surface, we added the points load on the pulley node. The design methods are very important to thedesigner, and can shorten the design cycle and improve working efficiency.Key Words: Belt-conveyor Driving Pulley Finite Element Method第一章绪论1.1 概述连续输送机械是物料搬运机械的重要组成部分,是其中的一大类别。

聚酯输送带埋线缝补工艺在向家坝水电站1#供料线系统施工中的应用

聚酯输送带埋线缝补工艺在向家坝水电站1#供料线系统施工中的应用

聚酯输送带埋线缝补工艺在向家坝水电站1#供料线系统施工中的应用摘要塔带机供料线系统是大坝混凝土浇筑专用设备,其运行的突出特点是供抖连续、强度高,并具有仓面布料功能,但存在胶带机输送带因自然磨损、故障损伤以及高强度运行导致输送带老化迅速的问题,因此针对如何快速有效的处理输送带损伤,从而缩短设备非正常停机时间,保障生产施工的连续性,是需要研究探讨的课题。

本文就供料线系统输送带损伤的应急处理工艺进行阐述,为保障供料线系统输送带的安全运行提供可参考意见。

关键词:输送带工艺应用1 施工概述向家坝水电站施工用供料线系统是美国罗泰克公司(ROTEC)开发出的大坝混凝土浇筑专用设备,是塔机与胶带机的有机结合。

它将混凝土水平运输、垂直运输及仓面布料功能融为一体,具有很强的混凝土浇筑能力。

供料线系统配备了一系列混凝土输送专用设备,如刮刀、转料斗及下料皮筒等,基本上克服了普通胶带机输送混凝土时存在的骨料分离、灰浆损失等大的缺陷,提高了混凝土输送质量,使其在大坝混凝土浇筑中有了较大发展。

向家坝水电站TB1#塔带机供料线系统(以下简称供料线系统),主要承担向家坝水电站二期左岸主体、导流工程高程352.30m以下主体工程混凝土输送、浇筑任务。

供料线系统全线长度为755.5m,使用EP350高强聚酯输送带(以下简称胶带),带宽762mm(计量输送带和转料输送带除外),最高带速4m/s,胶带总长度约为1625m,理论最高输送强度为6.5 m3/min(即390 m3/h)。

供料线系统是向家坝水电站左岸主体工程的重要施工设备,其生产施工能力和完好率将直接决定着左岸主体工程施工的进度和质量。

2 设备运行2.1 运行概述TB1#供料线系统自安装运行至拆除,其生产能力为向家坝水电站三台供料线系统中最强,自2010年4月安装运行,至2013年3月拆除,累计完成混凝土输送总量约为1839050 m3 ,单月输送混凝土最高总量为133443 m3,单日最高输送混凝土总量为9924 m3,单班最高输送混凝土总量为3648 m3,小时最高混凝土输送量为527m3/h。

  1. 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
  2. 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
  3. 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。

向家坝水电站长距离带式输送机规划设计及安装调试 摘要:向家坝水电站骨料输送线应用5条头尾相接的长距离带式输送机,总长约31km,是我国水电、煤炭、矿山等行业散装料物输送中最长的带式输送机,能够在短时间内安装调试成功,为我国水电工程散装料物输送提供了很好实践经验。长距离带式输送机应用于砂石料骨料输送系统,具有输送速度快、输送量较大,投资省等优点。 关键词:向家坝水电站;长距离带式输送机;砂石;规划设计;安装调试 中图分类号:TV62+2,U215 文献标识码:B

1 概述 向家坝水电站位于金沙江下游峡谷出口河段,是金沙江梯级开发的最后一级电站,是一座以发电为主,兼顾防洪、拦沙、灌溉、航运等综合效益的巨型水电站。工程枢纽建筑物主要由大坝、左岸坝后厂房、右岸引水发电系统及升船机等组成。大坝为混凝土重力坝,水库正常蓄水位380m,坝顶高程384m,最大坝高162m;左岸坝后厂房与右岸引水发电系统各安装4台水轮发电机组,总装机容量6400MW;大坝坝体混凝土总量约1220m3,共需生产混凝土骨料约2680万t,其中粗骨料约1820万t、细骨料约860万t。 根据区域地质资料,结合公路、铁路、水路等交通运输条件,以向家坝水电站坝址为中心,在周围近100km范围内进行了全面的建筑材料勘察工作。结果表明,向家坝工程可供选择的混凝土骨料料源有天然砂石料、砂岩料和灰岩料,料场有10个。通过对不同料源组合方案进行综合技术经济比较,选择太平料场作为向家坝水电站主体工程混凝土骨料料源。太平料场距向家坝水电站坝址公路里程约59km,直线距离约30km。砂石运输方案采用头尾相接的5条长距离带式输送机。

2 长距离带式输送机输送线规划设计 2.1 总体布置方案 根据料源的选择及技术经济比较,向家坝水电站砂石加工系统采取分散布置方式,半成品加工区布置在太平料场,成品加工区布置在坝区马延坡,太平料场到坝区马延坡之间采用长距离带式输送机输送半成品骨料。 太平料场骨料输送线由5条长距离带式输送机组成,总长约31.1km;沿线穿越高山深谷,形成9段输送隧洞,总长约29.3km,分别为6661m、6451m、2383m、3220m、1199m、822m、3767m、4633m、170m。主洞断面净空尺寸办5m(宽)×4m(高)。按混凝土浇筑高峰时段强度34.7万m3/月,确定带式输送机输送线的输送能力为3000t/h。长距离带式输送机主要技术参数见表1。 长距离带式输送机输送线长距离带式输送机输送线平面布置见《长距离带式输送机输送线规划示意图》。

2.2 带式输送机运行可靠性分析 根据国内外煤炭、矿山带式输送机使用情况调研,带式输送机是一种运行稳定、可靠的运输设备,目前大型带式输送机最大输送能力达到7000-8000t/h,带宽在2.0m以上,带速在5.0m/s以上,单机长度为5-15km。目前,带式输送机关键部件(驱动装置、拉紧装置、滚筒、托辊、钢绳芯输送带、中间架等)均采用国产设备。 国内有数家大型带式输送机和钢绳芯输送带的设备制造厂家,分别引进了国际先进水平的托辊制造装配线和钢绳芯输送带生产线,具备长距离带式输送机设备的总体制造、安装及调试的能力。

长距离带式输送机的关键技术有以下几点: 1)输送带制造技术钢绳芯输送带与其它类型输送带相比,具有强度高、弹性伸长小、易成槽、耐冲击、寿命长、所需滚筒直径小、接头寿命较长等优点。 2)输送带防撕裂技术钢绳芯输送带的使用寿命与磨损和撕裂有重大关系。为了防止输送带遭到破坏或撕裂,钢绳芯输送带都加有柔性钢丝网的防撕裂层。 3)驱动方式长距离带式输送机的启动和制动力矩很大,必须选用技术性能较好的驱动装置来实现输送机正常的启动、运行和制动过程。理想的启动过程是加速度由零逐渐增大,再逐渐减少到零,速度曲线是S曲线,这样的启动将是平稳且无冲击的,制动则正好相反。 4)自动化控制物料输送系统一般由若干台装卸设备及输送设备组成。采用可编程序控制器(PLC)对整个输送系统实行自动控制,提高了系统运行的可靠性和自动化水平。

3 主要设备选型 长距离带式输送机主要由驱动装置;制动器;拉紧装置;钢绳芯输送带;托辊、滚筒;电气及控制设备组成。

3.1 驱动装置组合方案的特点 3.1.1 调速型液力耦合器 调速型液力耦合器安装在电动机和减速器之间,可改善驱动装置启动的性能、具有过载保护作用;能提高电机和带式输送机的寿命;能平衡各电机的功率输出;设备价格相对略低。但多机驱动时各驱动装置的输入功率平衡和同步控制较困难;低速时传递的扭矩小、不能提供稳定平滑的加速度。 3.1.2 可控驱动系统 CST可控驱动系统能提供稳定平滑的加速度,使带式输送机平稳启动;能在紧急停车时或突然断电时,提供可控停车;能控制输送带的速度,多机驱动时能实现输入功率平衡,并保持同步运行;输出转速能在10%-100%的范围内任意调节;可对减速器和负载实现双向过载保护;电动机可空载顺序启动,使电机寿命大大提高,可降低启动电流对电网的冲击。但设备内部结构相对复杂,造价相对略高。 3.1.3 变频调速驱动系统 变频调速驱动系统能提供稳定平滑的加速度,使带式输送机平稳启动;能在紧急停车时或突然断电时,提供可控停车;能控制输送带的速度,多机驱动时能实现输入功率平衡,并保持同步运行;输出转速能在10%-100%的范围内任意调节;可对减速器和负载实现双向过载保护。但变频电机不能实现无负载启动;变频电机运行时产生的谐波对电网有一定影响;变频电机的电压为非标准电压,需配置专用变压器,造价相对略高。 经综合分析比较,选用技术先进、运行平稳、可靠性高、在国内煤炭、矿山工程已使用了几百台(套)的CST可控驱动系统作为驱动装置的关键设备。 3.2 制动器 选用大型、重载带式输送机的可控制动系统――CSB630KTS液力制动器和盘式制动器,制动器可有效控制带式输送机的制动力矩及制动时间,响应速度快,保证带式输送机在重载突然断电工况下实现平稳停机。

3.3 拉紧装置 选用具有国内先进水平的液压自动拉紧装置,该装置的关键部件(液压元件)为进口件,可根据输送机不同工况时的张力需要,在设定的范围内任意调节输送带拉紧力;还可实现启动拉紧力比正常运行时拉紧力大1.2-1.5倍的功能。该拉紧装置动态响应速度快,可以补偿输送带在输送机启动时的伸长量,降低输送带的张力、减小冲击,保证带式输送机正常启动、平稳运行、停机。

3.4 钢绳芯输送带 带式输送机采用耐磨性能好的优质钢丝绳芯输送带,伸长率 不大于0.2%。输送带应采用耐磨、耐;中击的覆盖胶,上、下覆盖胶层厚度依输送带强度不同在6-8mm之间。钢丝绳芯输送带内铺设横向钢丝抗撕裂层,使输送带能大量吸收能量,具有优良的抗冲击、抗撕裂性能。 主要原材料均为天然胶、合成胶从泰国、美国进口;钢丝绳采用国内知名企业优质开放式钢丝绳;防撕裂钢丝绳网为比利时进口。

3.5 托辊 托辊生产线为全自动化,产品质量稳定。托辊密封形式采用双道密封。托辊的设计寿命应不低于30000h;托辊生产所需主要原材料均为优质产品(其中轴承采用JRC轴承,钢管采用国内知名企业生产的优质托辊专用电焊钢管)。

3.6 滚筒 滚筒采用整体式轴承座,采用调心滚子轴承,油杯式润滑,其轴承设计寿命>5万h。本工程所用滚筒由国内大型带式输送机企业制造,滚筒选用日本进口NSK轴承,钢材选用国内知名企业的产品。

4 供配电及电气控制 4.1 供配电 长距离带式输送机输送线(以下简称输送线)供配电系统的上一级供电电源为太平料场35kV变电站、茶林沟35kV变电站及坝区110kV变电站。从3个变电站的低压侧采用10kV电缆(或架空线路)接线至输送线沿线的7个10kV配电站。 7个10kV配电站分别布置在输送线沿线各驱动装置附近,主要向B1-B5号带式输送机的驱动装置和10kV箱式变电站供电,同时还对配电站两端一定范围内(900-1225m)的通风、照明、检修等设备供电。 在输送线沿线隧洞内共配置9个10kV箱式变电站。各箱变对其两端一定范围内(900-1225m)的通风、照明、检修等设备供电。

4.2 电气控制 长距离带式输送机输送线实施自动监控管理,主要包括以下部分: 4.2.1 监控系统网络 监控系统共设5个现地PLC系统,分别负责B1-B5号带式输送机的监视控制,控制网络采用冗余工业以太网。介质采用单模光纤。网络交换机配置7台,分别设置在7个配电站内。3台监控计算机、7个触摸屏、5个PLC主机连接在100M以太网上,通过以太网,实现对整个系统的监控管理。 中央控制室设在B5带式输送机的头部配电站内,有3台监控管理计算机和一套工业电视系统组成,是整个系统的控制中心,实现对整个系统的监视、操作、运行记录等。 4.2.2 现地PLC系统(包括CST接口)及远程PLC单元

现地控制单元每条带式输送机设置一套PLC系统,共5套。 沿带式输送机,每隔1152m设置一台远程PLC站,负责该区域的信号采集和报警控制。 4.2.3 设备运行控制方式 由电气控制室对骨料输送线上的各条带式输送机的启动、运行及停机进行有效控制,具有集控、就地、检修、手动及闭锁五种工作方式。 4.2.4 保护系统 1)跑偏开关、紧急停机用的拉绳开关,沿带式输送机全长布置在机架的两侧,每隔48m安装1组开关。跑偏开关沿带式输送机全长布置在机架的两侧,每隔96m安装1组开关。 2)皮带带速检测装置 带速检测装置用于监视带式输送机的运行速度,并能检测带式输送机打滑故障,防止打滑所造成的恶性事故。 3)溜槽堵塞检测器:为了检测带式输送机的头部漏斗、溜槽内是否发生堵塞。 4)输送带纵向撕裂保护器 为避免皮带纵向撕裂,系统共设置6套纵向撕裂保护开