文档下载后可定制修改,请根据实际需要进行调整和使用,谢谢!本店铺为大家提供各种类型的实用资料,如教育随笔、日记赏析、句子摘抄、古诗大全、经典美文、话题作文、工作总结、词语解析、文案摘录、其他资料等等,想了解不同资料格式和写法,敬请关注!Download tips: This document is carefully compiled by this editor. I hope that after you download it, it can help you solve practical problems. The document can be customized and modified after downloading, please adjust and use it according to actual needs, thank you! In addition, this shop provides you with various types of practical materials, such as educational essays, diary appreciation, sentence excerpts, ancient poems, classic articles, topic composition, work summary, word parsing, copy excerpts, other materials and so on, want to know different data formats and writing methods, please pay attention!一、前言护坡植草是城市园林绿化建设中的重要环节,不仅美化了城市环境,还具有保护土壤、防止水土流失等功能。
拱形骨架护坡

1)混凝土拱形骨架护坡施工工艺流程见图混凝土拱形骨架护坡工艺流程图。
混凝土拱形骨架护坡工艺流程图①测量放样根据设计边坡与线路中心线的相对位置,由测量人员用全站仪放出边坡坡顶、坡脚线,边坡平台位置线,施工人员随后挂线进行边坡及平台的平整,清刷浮土、填补坑凹、并夯实坡面,坡面要平整、圆顺,然后根据设计形式、尺寸挂线放样要求放出骨架起终点侧边,底部和顶部镶边线、主骨架及拱骨架线,并洒白灰线标示。
②基槽开挖基槽采用人工开挖,开挖时从上到下进行开挖,并修筑方便施工人员上下的台阶。
基槽开挖沿线路方向长度不能太长,能保证两个伸缩缝间混凝土施工循环就可以,在基槽开挖完后应立即进行模板支设、混凝土施工,以防止基槽暴露时间过长造成边坡坍塌,从而破坏路基实体质量。
基槽挂线开挖,以确保基槽尺寸符合设计要求。
基槽在开挖时,严格按照挂线施工的作业要点进行施工过程控制。
一次开挖后,预留人工二次修整余地,二次修整到位,避免超挖现象,减少混凝土的超方量。
③基底检查基槽开挖完成后及时通知架子队技术员进行验槽,自检合格报现场监理工程师验收签证。
④设置泄水孔拱形截水护坡的下部镶边处应设置一排泄水孔,泄水孔采用孔径0.1m的PVC管,进水口采用0.3m×0.3m的透水无纺布(400g/m2)包裹,间距1~1.5m。
⑤模板安装骨架模板采用定型钢模拼装,镶边及踏步模板采用竹胶板,模板安装时采用双面胶带纸塞缝,确保接缝良好不漏浆。
模板支设完成后挂线对模板进行精调,确保模板支设尺寸符合要求。
模板调整好后,对模板进行加固。
模板支设好后要经技术员复核无误并报现场监理工程师确认后才能进行下道工序施工。
进行混凝土浇筑前,人工清除基槽表面松散颗粒,洒水湿润。
⑥浇筑骨架及镶边混凝土采用混凝土运输车运输,吊车吊送或混凝土泵车泵送入模。
混凝土运至现场后先对混凝土的工作性能进行检查,满足要求后方可进行混凝土浇筑。
对于拱形骨架混凝土的施工,从坡脚处逐层向路基顶面施工,混凝土施工过程中,施工人员应采用小型振捣设备对骨架及镶边混凝土进行振捣,截水缘在骨架混凝土施工完成后再进行浇筑。
拱形骨架护坡模板

拱形骨架护坡模板摘要:本研究深入探讨了拱形骨架护坡模板的设计原理与施工技术流程,并分析了其在路基边坡防护工程中的应用。
拱形骨架护坡作为一种高效的防护技术,已在水利工程、公路建设、铁路修筑等多个领域得到广泛应用。
研究首先阐述了拱形骨架护坡的设计原则与施工技术要求,随后详细论述了施工技术流程,涵盖了施工准备、测量放样、基础浇筑、拱架安装、模板支撑、混凝土浇筑、养护以及模板拆除等关键步骤。
通过对上述施工流程的深入分析,本研究旨在为拱形骨架护坡模板的设计与施工提供科学的指导和实践性建议。
关键词:拱形骨架护坡;模板;施工流程;防护措施Abstract: This study delves into the design principles and construction techniques of arch-frame slope protection forms, and analyzes their application in subgrade slope protection projects. As an efficient protection technology, arch-frame slope protection has been widely applied in various fields such as water conservancy projects, road construction, and railway building. The study first elaborates on the design principles and construction technical requirements of arch-frame slope protection, followed by a detailed discussion of the construction process, which includes construction preparation, surveying and setting out, foundation pouring, arch frame installation, formwork support, concrete pouring, curing, and formwork removal, among other key steps. Through an in-depth analysis of the aforementioned construction processes, this study aims to provide scientific guidance and practical advice for the design and construction of arch-frame slope protection forms.Keywords: Arch-frame slope protection; Formwork; Construction process; Protective measures一、引言1.1 拱形骨架护坡的重要性拱形骨架护坡作为一种在现代土木工程中广泛采用的边坡防护形式,对于防止水土流失、维护路基边坡稳定具有极其重要的作用。
拱形骨架护坡施工技术交底

拱形骨架护坡施工技术交底本文是一份施工技术交底记录表,针对厦门至成都国家高速公路广西境桂林至三江(桂黔界)段工程中的路基拱形骨架植草护坡分部工程进行规范、指导和质量控制。
编制目的是为了明确施工工艺流程、操作要点和质量控制标准,以确保施工质量。
编制依据包括相关图纸、施工规范和验收标准。
施工准备分为技术准备和施工现场准备两个方面。
技术准备包括组织相关人员熟悉骨架设计图纸和施工规范要求,研究施工工艺要求、质量标准及操作要点等。
施工现场准备则包括清理修整坡面,填补坑凹,保持坡面大面平顺,挖方路基边坡提前做好截水天沟等排水设施。
拱形骨架边坡施工分为拱形骨架技术指标和施工工艺两个方面。
拱形骨架技术指标包括拱形骨架拱部骨架截面为L型,宽0.35m,主骨架截面为U型,宽0.36m,截水槽0.1m×0.1m。
骨架护坡起、终点侧边,底部基础及顶部设现浇C20砼镶边。
每3个拱设一道伸缩缝,缝宽0.02m,缝内填塞沥青麻絮,深0.2m。
为便于养护,在适当位置(每100m)设检查踏步。
施工工艺流程为施工准备→测量放样→基槽开挖→基底检查→浇筑骨架、镶边→混凝土养护→伸缩缝设置→骨架内客土→喷播植草→栽种灌木→验收。
在施工准备阶段,需要进行坡面整修,清刷表面松散土层及浮土,填补坑凹并拍实使坡面平整,基底的压实度应与同层路基压实度相同,以免下沉而使砌体产生裂缝,影响砌体的整体稳定。
施工现场准备阶段需要按设计图纸对拱型骨架轮廓挂线放样,准确定位基槽开挖范围。
对于弧形部分定出圆心位置后画出弧线。
根据设计边坡与线路中心线的相对位置,由测量人员用全站仪放出边坡坡顶、坡脚线,边坡平台位置线,施工人员随后挂线进行边坡及平台的平整,清刷浮土、填补坑凹、并夯实坡面。
坡面要平整、圆顺,然后根据设计形式、尺寸挂线放样(具体见附图)要求放出骨架起终点侧边,底部和顶部镶边线、主骨架及拱骨架线,并洒白灰线标示。
基槽开挖则是施工工艺流程中的一部分。
拱形骨架护坡施工技术交底

(3)施工机械设备应有专人负责保养、维修和看管,确保安全生产。
(4)施工现场各种机械操作手、电工必须持证上岗,同时加强对司机、电工的教育。
(5)现场操作人员必须按规定佩戴防护用具。
6、环保要求
施工现场100%湿法作业,施工作业面移动式雾炮车按照施工面积每100平方米或30米配备1台,确保作业时正常使用且保证雾炮车连续喷淋到作业区域。场地清理完成后,及时覆盖防尘网。
4.配备临时用电、混凝土振捣、养生设备。
三、施工工序
1.施工工艺流程
测量放样→基槽开挖→基底检查→模板安装→混凝土浇筑→混凝土养生→踏步及伸缩缝施工
测量放样
根据设计边坡与线路中心线的相对位置,由测量人员放出边坡坡顶、坡脚线,平台位置线,水沟位置线,附近设立临时水准点,挂线并进行边坡平整,根据设计形式放出骨架起终点侧边,镶边线,护脚线,骨架线,并撒白灰线标示。拱形骨架拱圈由上往下布设,由下向上砌筑,间距不足时调整拱间间距,增加设拱一道。
3.基槽开挖
基槽采用机械配合人工开挖,开挖时从上到下进行开挖,并修筑方便施工人员上下的台阶。基槽开挖沿线路方向不能太长,能保证两个伸缩缝混凝土循环施工即可,在基槽开挖清理后应立即进行模板支设,避免基槽暴露时间太长,遭受雨水冲刷。基槽挂线开挖,以确保基槽尺寸符合设计要求。
4.基底检查
基槽开挖完成后,及时通知现场技术员验槽,自检合格后报监理工程师现场验收,验收合格后,方可进行下道工序施工。
5.模板安装
骨架模板采用定型钢模拼装,镶边及踏步模板采用竹胶板拼装,模板安装是采用双面胶带纸塞缝,确保接缝良好不漏浆。模板支设完成后挂线进行精调,并对模板进行加固确保尺寸符合设计要求。经现场技术员复核无误后报监理工程师现场验收,验收合格后,方可进行下道工序施工。
拱形骨架护坡施工安全交底

拱形骨架护坡施工安全交底1. 施工概述本项目的施工目标是在指定区域内建造拱形骨架护坡。
该护坡结构是为了保护斜坡,防止土壤侵蚀和滑坡。
2. 安全要求2.1 施工人员必须具备相关的专业技能和经验,熟悉施工流程和安全规范。
2.2 施工现场必须设立明显的安全标识,包括警示牌和安全警戒线,以确保施工区域的安全。
2.3 施工现场必须保持整洁有序,避免杂物和障碍物妨碍施工和交通。
2.4 施工人员必须佩戴个人防护装备,包括安全帽、安全鞋、手套等,并且正确使用和维护。
2.5 施工现场必须配备必要的消防器材,并且进行定期检查和维护。
2.6 施工过程中,严禁酗酒、吸烟或使用任何影响工作安全的物品。
3. 施工措施3.1 施工前,必须进行必要的现场勘察和土壤分析,确定施工的可行性和安全性。
3.2 施工过程中必须按照相关规范和流程进行,确保施工质量和工期的可控性。
3.3 施工现场必须设立安全通道,方便人员和设备的进出,并确保通道的安全和畅通。
3.4 施工过程中必须按照操作规程进行,禁止擅自改变或省略施工步骤。
3.5 施工过程中必须定期检查施工设备和工具的安全状况,发现问题及时处理和修复。
3.6 施工结束后,必须进行相关的验收和整理工作,确保施工结果的合格和安全。
4. 突发事件应急措施4.1 如果发生火灾,立即启动紧急疏散计划,通知所有人员迅速撤离施工现场,并使用灭火器进行初期灭火。
4.2 如果发生天气恶化(如雷暴、大风等)或发生地震等自然灾害,立即停工并撤离施工现场,确保人员的生命安全。
4.3 如果发生人身意外伤害事故,立即进行紧急救治,并及时报告相关部门和上级领导。
5. 监督和检查5.1 监理人员必须定期对施工现场进行检查,核实施工质量和安全情况,并及时提出改进意见和建议。
5.2 施工单位必须配合监理人员的检查工作,并积极整改存在的问题和隐患。
5.3 监理人员和施工单位必须定期开展安全培训和交流,提高工作人员的安全意识和技能水平。
拱形骨架护坡施工解决方法
拱形骨架护坡施工解决方法无需目录。
拱形骨架护坡施工方案___编制:___分部审核:审批:二○一七年二月本文将介绍拱形骨架护坡施工方案,该方案由___。
拱形骨架护坡是一种新型的护坡结构,具有较好的稳定性和抗震性能,能够有效地保护铁路线路的安全运行。
拱形骨架护坡的施工过程需要经过多个步骤,包括基础处理、拱形骨架的制作和安装、填充土方的施工等。
在每个步骤中,都需要严格按照设计要求和规范进行施工,确保护坡结构的稳定性和安全性。
在施工过程中,需要注意以下几点:首先,要对施工现场进行认真的勘察和分析,了解地质条件和环境因素,为后续施工做好充分的准备;其次,要严格按照设计要求和规范进行施工,采取科学合理的施工方法和措施,确保施工质量和安全;最后,要加强施工现场管理,做好安全防护工作,确保施工过程中不发生安全事故。
总之,拱形骨架护坡是一种新型的护坡结构,具有较好的稳定性和抗震性能,能够有效地保护铁路线路的安全运行。
在施工过程中,要严格按照设计要求和规范进行施工,加强现场管理,确保施工质量和安全。
一、目的本文旨在编制一份路基拱形骨架边坡施工方案,明确施工的总体安排、施工工艺和施工质量控制措施,确保施工过程中的安全生产和环境保护。
二、编制依据本方案的编制依据包括相关法律法规、工程设计文件、技术规范和现场实际情况等。
三、适用范围本方案适用于路基拱形骨架边坡的施工,包括施工工期安排、施工组织机构、施工任务划分、临时工程和过渡工程、施工准备、路基拱形骨架边坡施工、骨架质量检验标准、人员及设备配置、质量控制措施、安全生产措施、环境保护及文明施工等方面。
四、工程概况4.1 工程概况本工程是一项路基拱形骨架边坡施工工程,总长度为XX 公里,设计标准为XX级公路。
4.2 主要技术标准本工程的主要技术标准包括《公路工程施工质量验收规范》、《公路工程施工安全技术规程》、《公路工程施工组织设计规范》等。
五、施工总体安排5.1 施工工期安排本工程的施工工期为XX个月,具体施工时间安排详见施工计划表。
拱形骨架护坡施工方案
拱形骨架防护施工方案编制:审核:审批:集团有限公司目录一、编制依据 ............................................................................................................................................................ - 1 -二、总体要求 ............................................................................................................................................................ - 1 -三、拱形骨架护坡技术要求 .................................................................................................................................... - 1 -3.1、技术要求 .................................................................................................................................................. - 1 -3.2、材料要求 .................................................................................................................................................. - 1 -四、拱形骨架护坡施工方案 .................................................................................................................................... - 2 -4.1、刷坡、开挖 .............................................................................................................................................. - 2 -4.2、拱架施工 .................................................................................................................................................. - 3 -4.3、浆砌片石施工 .......................................................................................................................................... - 3 -4.4、预制块 ...................................................................................................................................................... - 5 -4.5、绿化 .......................................................................................................................................................... - 6 -五、质量控制要求 .................................................................................................................................................... - 6 -5.1 预制块 ........................................................................................................................................................ - 6 -5.2浆砌片石 ..................................................................................................................................................... - 7 -5.3施工要求 ..................................................................................................................................................... - 9 -5.4、验收标准 .................................................................................................................................................. - 9 -5.5、质量保证措施 ........................................................................................................................................ - 10 -六、安全保证措施 .................................................................................................................................................. - 10 -七、环境保护措施 .................................................................................................................................................. - 11 -八、文明施工措施 .................................................................................................................................................. - 12 -一、编制依据1、高速公路施工设计图第三册第三分册;2、路基施工技术规范(JTG F10—2006);3、公路工程质量检验评定标准(JTG F80/1-2004)4、现行的其它技术规范,技术标准、条例、法规及验收规范等;5、己进场的施工机械及施工技术能力;6、我公司相似工程施工中成熟的施工技术和管理经验,及相关项目管理办法。
拱形骨架护坡施工方案设计
1、我工区承当的K0+660~K0+820 右侧路基边坡设计采用拱形骨架护坡.截水骨架、根底、踏步均采用M7.5 浆砌片石就地砌筑,拱形截水骨架的主骨架应做成槽型,分流排除地表水.2、拱形骨架由主骨架和支骨架组成,主骨架与边坡水平线垂直, 间距4m;支骨架呈弧形,垂直线路方向的间距为4m.主骨架厚0.5m,支骨架厚0.4m.3、在两侧0.5mX 围内,应用M7.5 浆砌片石镶边加固;截水骨架内采用喷播植草,草籽混播比例:狗牙根:白芽:白三叶:黄蒂菊:桎木:云实=3:2:2:1:1:1.4、每40m 左右设置沉降缝一道,缝内填塞深度不小于0.2m 的沥青麻筋.5、砌筑骨架前应按设计要求在每条骨架的起讫点挂线放样,然后开挖骨架沟槽,沟槽尺寸根据骨架尺寸而定.6、如遇道路周边用地同时开发成此交叉口处另一规划道路近期内将实施时,可取消拱形骨架护坡.1、材料骨架防护的混凝土和浆砌片石材料主要是砂石、外加剂、水泥、砂、片石.材料进场前需各种原材料的品质进展试验,合格后方可进场, 在材料进场后还要对混凝土的原材料进展抽检,其各项指标均要符合设计的要求.2、施工设备小型运输设备、混凝土拌合机.3、施工场地对路堤边坡清理完毕后,将场地清理平整,合理解决原材料的堆放、电力、水源的问题.1、施工工艺片石砌筑采用挤浆法分层、分层砌筑:分段位置设在层降缝或伸缩缝处,两相邻段的砌筑高差不大于120mm,分层水平砌缝大致水平. 各砌块的切缝相互错开,切缝饱满.各砌层先砌外圈定位砌块,并与里层砌块连成一体.定位砌块选用外表较平整且尺寸较大的石料,定位砌缝满铺砂浆,不得镶嵌小石块.定位砌块砌完后,先在圈内底部铺一层砂浆,其厚度使石料在挤压安砌时能严密连接,且砌缝砂浆密实、饱满.砌筑腹石时,石料间的切缝互相交织、咬搭,砂浆密实.石料不得无砂浆直接接触,也不得干填石料后铺灌砂浆;石料大小搭配,较大的石料以大面为底,较宽的砌缝可用小石块挤塞,挤浆时用小锤敲打石料,将砌缝挤紧,不得留有孔隙.定位砌块外表砌缝的宽度不大于4cm.砌体外表三块相邻石料相切的内切圆直径不大于 7cm,两层间的错缝不小于 8cm,每砌筑 120cm 高度以内找平一次.填腹局部的砌缝减小,在较宽的砌缝中用小石块塞填.砌体外表的勾缝符合设计要求,并在砌体砌筑时,留出 2cm 深的空 缝.勾缝采用凹缝或平缝,勾缝所用砂浆强度不得小于砌体所用砂浆强 度.当设计不要求勾缝时,随砌随用灰刀刮平砌缝.砌体砌筑完毕与时覆盖,并经常洒水保持湿润,常温下养护期不得 少于 7d.2、砌体质量检查每 100m ³〔小于 100m ³按 100m ³计〕砌体,做 1 组砂浆强度检查 试件,并与砌体一起养护.同批次试件强度平均值不小于设计值且任意 1 组试件的强度最 低值不小于设计值的 85%.砌体各项材料符合要求;砌缝宽度、错缝距离符合规定,砂浆铺 填饱满,勾缝坚实、整齐;砌体位置、尺寸在允许偏差 X 围内.3、施工工艺流程测量放样碎石垫层 配合比 选择 挂线 运 调平 料 砌体 砂浆 各局部 养 运走 运走 材质检查 碎石 水泥 质浆量砌片石质砌量体 勾 伸缩 缝 缝 清理场地 质量 标号 尺寸 片石质量浆砌片石保 余土 余料工程师检查 边坡修整检查验收签证1、施工前,项目部召集项目部与施工队相关人员,进展施工技术交底.2、所有砂浆必须机械拌和,片石的厚度不应小于150mm 〔卵形和薄片者不得使用〕.镶面石料应选择尺寸稍大并具有较平整外表,且应稍加粗凿.在角隅处应使用较大石料,大致粗凿方正.3、水泥,对免检厂供给的水泥也应抽检,不合格不得使用,砼用砂、碎石应于配合比试验相一致,使用添加剂、砂石材料变更时应通过试验确定.4、严格施工报验程序,施工队自检,经理部复检合格后,才能报监理工程师验收.1、安全施工要求〔1〕所有进入施工现场的施工人员必须佩戴安全帽. 〔2〕作业人员不得穿拖鞋、高跟鞋、硬底易滑鞋进入施工现场. 〔3〕施工现场设置"施工重地,非施工人员严禁进入〞的警示牌,作业现场必须有安全施工责任牌.〔4〕夜间施工必须有充足的灯火照明.〔5〕禁止酒后作业.〔6〕所有进场施工的机械设备必须持有出厂合格证,机械操作手必须持有特种操作人员上岗证件.〔7〕现场施工用电严格三级配电、二级保护, 电缆采用五芯电缆,做到一机、一闸、一箱、一漏.2、环保施工要求〔1〕施工便道途径村庄等人口集聚区时,运输车辆严禁鸣笛.施工便道派洒水车定期洒水,保证整个线路平整、干净,在风沙、扬尘天气勤洒水.〔2〕施工现场垃圾不得随意丢弃.〔3〕施工机械产生的废油不倒入水中,对于受污染的场地与时进展清理.〔4〕加强机械设备的维修保养和达标活动,减少机械废气、排烟对空气环境的污染.〔5〕施工完成后,植被破坏地段须恢复植草绿化.3、文明施工要求〔1〕合理布置场地,材料堆放整齐,整洁有序,标识牌与宣传标语牌统筹设置.〔2〕各种资料填写准确、与时、规X、收集齐全,归档有序.〔3〕施工场地标牌醒目,各种规章制度健全.〔4〕挂牌上岗,统一服装,精神饱满,遵守劳动纪律.〔5〕做到施工文明,言行文明,处理好各种关系.。
拱形骨架护坡施工方案
拱形骨架护坡施工方案拱形骨架护坡施工方案一、编制依据本方案编制依据国家相关法律法规及行业标准,结合实际工程情况,经过多次会商和论证确定。
二、总体要求本方案旨在保证施工过程中的安全、质量和进度,确保工程顺利完成。
施工人员必须遵守相关规定,严格按照方案施工。
三、拱形骨架护坡技术要求3.1 技术要求拱形骨架护坡是一种常用的防护措施,其技术要求如下:1)拱形骨架的材料必须符合国家标准,具有足够的强度和稳定性。
2)拱形骨架的制作必须精确,尺寸要符合设计要求,焊接要牢固。
3)拱形骨架的安装必须符合施工图纸和设计要求,严格按照程序进行,安装前必须进行检查。
4)拱形骨架的防腐处理必须符合国家标准,确保其防腐性能。
5)拱形骨架的固定必须牢固可靠,不得出现松动或变形等情况。
6)拱形骨架的使用寿命必须符合设计要求,不得出现损坏或失效的情况。
3.2 材料要求在进行拱形骨架护坡施工之前,需要准备以下材料:1.钢筋:采用HRB335或以上等级的钢筋,直径不小于12mm。
2.混凝土:采用强度等级为C30或以上的混凝土。
3.砖块:采用规格为240mm×115mm×53mm的砖块,强度等级为MU10.4.砂浆:采用强度等级为M5或以上的水泥砂浆。
5.片石:采用规格为300mm×150mm×150mm的片石,强度等级为MU10.6.预制块:采用规格为600mm×300mm×200mm的预制块,强度等级为C30.四、拱形骨架护坡施工方案4.1 刷坡、开挖在施工前,需要将施工现场进行清理,确保施工区域没有杂物。
然后按照设计要求进行坡度刷坡和开挖。
4.2 拱架施工在进行拱架施工之前,需要先进行钢筋加工和制作模板。
然后将钢筋按照设计要求进行焊接,将模板固定在钢筋上,最后进行混凝土浇筑。
4.3 浆砌片石施工在进行浆砌片石施工之前,需要先进行片石的分类和清洗。
然后按照设计要求进行浆砌,注意石缝应该填满,表面应该平整。
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
1 / 3
拱形骨架护坡
拱形骨架护坡施工技术交底记录
工程名称延吴高速LJ-08合同段交底日期2010年月日技术交底项目拱形骨
架护坡技术交底工程部位防护工程拱形骨架护坡
交底对象及人数交底提要拱形骨架施工技术交底防护工程施工人员交底内
容:
一、工程概况
延安安塞经志丹至吴起高速公路LJ-8合同段路基防护拱形骨架护坡,设计
坡度为1:1,挖方段相邻级护坡间设3.0m宽平台,并加设C20混凝土平台排水
沟。
拱形骨架内部采用喷播植草防护,主骨架间距0.4m,拱高3.0m。主骨架断
面尺寸为0.4m×0.3m(不含镶边石)。
二、施工准备
1、原材料准备
1)、砂子:砂子采用新丰砂,所用中砂必须洁净,不得含有草根、泥块等杂
物。
2)、水泥:统一采用声威牌P?C32.5R水泥。
3)、碎石:碎石的选择应符合设计(配合比报告)及规范要求。
4)、模板:所用模板必须光滑、平整。
2、施工现场准备
1)、施工现场做好临时防排水系统、架设合理的电力系统及混凝土养生设
备等。
三、施工方案
2 / 3
拱形护坡采用小型机具配合人工挖方,支架模板法逐级施工的次序。1
1、施工放样
合理布置,特别注意边坡边角处的放样。保证横、竖梁的顺畅性及整体线
型的圆顺性。测量放样过程中及时做好护桩工作,以便后期准确使用。测量放
样后,经测量监理工程师认可后方可进行坡面挖方施工。
2、坡面挖方施工
施工前先清刷坡面浮土,填补坑凹,使坡面大体平整。对相邻级边坡间的
平台要做整平夯实处理,同时要保证一定的单向纵坡,以保证平台水沟的稳定
性及排水顺畅性。根据放样后的横、竖梁位置,采用小型机具配合人工挖方。
对不稳定的挖方槽底及坡面要做换填夯实处理。同一级边坡挖方顺序是:由上之
下,一步到位,槽底密实平顺,禁止超挖。
3、脚墙设计为M7.5砌筑片石,较大石料用于下部,坐满砂浆后再依次砌
筑上层,砌筑上层时,不得扰动下层的石料。
4、模板施工
模板安装前,先安装钢管架的稳固架。稳固架采用钢管临时锚固坡面内的
方法。然后安装模板的支架,再进行模板安装。模板表面必须光洁、平整。模
板安装中要保证接缝紧密,板体顺直,严格控制模板错台,安装后的模板要保
证一定的整体稳定性。模板施工时,要保证整体线型的直顺性,总体坡面的圆
顺性。模板脱模剂必须涂抹均匀,严禁使用废弃的机用油。模板拆除时,要按
照混凝土的浇筑顺序逐级拆除,拆除后的模板要集中放置,并对模板面板进行
清理,以便下次使用。
5、混凝土施工
拱形护坡混凝土浇筑顺序为:由底级到上级,先基础后竖梁再平台,最后进
行拱形架和分水镶面石施工。混凝土的浇筑运输采用车载+滑槽形式。为保证混
凝土的搅拌质量,在混凝土搅拌过程中严格控制混凝土的和易性及坍落度。混
凝土浇筑时,严格控制振捣质量,以混凝土停止下沉,不再冒出气泡,表面呈
现平坦、泛浆现象为振捣标准。
3 / 3
2
浇筑后的混凝土示实际天气情况,做好必要的洒水养生工作。四、施工注
意事项
1、护坡每隔10.6m设置一道沉降缝,缝内采用沥青棉絮或沥青木板条填
塞。
沉降缝宽2cm。
2、对干燥的挖方槽底要适当洒水润湿,以防混凝土水分过多流失,造成混
凝土开裂。
3、对拱形梁与竖梁的接触面要做凿毛或拉毛处理,并用清水清洗干净,以
便混凝土的良好结合。
4、竖梁和拱形梁上预镶分水石位置处,要做拉毛或凿毛处理,并于镶分水
石前用清水清洗干净,以防分水石与梁结合性差,造成后期分水石脱落。
5、平台排水沟施工时,注意曲线线型的圆顺性及排水顺畅性。
6、在混凝土振捣时,注意过振及漏振现象。
7、待砼强度达到2.5MPa时,方可拆模。以防混凝土掉角、啃边等。8、保
证护坡整体的圆顺性及拱形梁的布置美
交底人:接交人:技术负责人:
2010年月日2010年月日2010年月日