信管英语总复习题目
2020年软考高级信息系统项目管理师考试英语练习题及答案多套汇总

2020 年软考高级信息系统项目管理师考试英语练习题及答案多套汇总1. Project Quality Management must address the management of the project and the () of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.A.performanceB.processC.productD.object【答案】C【解析】项目质量管理必须解决项目的管理和项目的管理问题。
尽管项目质量管理适用于所有项目,无论其()的性质如何,但产品质量措施和技术是针对项目生产的特定类型产品的。
A、性能B、过程C、产品D、对象2.() is the budgeted amount for the work actually completedon the schedule activity or WBS component during a given time per i od.A.Planned valueB.Earned valueC.Actual costD.Cost variance【答案】B【解析】()是给定时间段内计划活动或WBS 组件实际完成的工作的预算金额。
A、计划值B、挣值C、实际成本D、成本差异3.() involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance. These other projects can be within the performing or gani za t i on or outside of it, and can be within the same or in another application area.A.MetricsB.MeasurementC.BenchmarkingD.Baseline【答案】C【解析】()将实际或计划的项目实践与其他项目的实践进行比较,以产生改进意见,并提供衡量绩效的依据。
信息系统项目管理师历年英语试题及模拟试题

信息系统项目管理师历年英语试题汇总2005年上半年●(66)is a method of constructing a project schedule network diagram that uses boxes or rectangles ,referred to as nodes, to represent activites and connects them with arrows that as ow the dependencies. This method includes following types of dependcies orprecedence relationships:(67)the initiation of the successor activity, depends upon the completion of the predecessor activity(68)the initiation of the successor activity,depends upon the initiation of the predecessor activity(66)A.PDM B.CPM C.PERT D.AOA(67)A.F-S B.F-F C.S-F D.S-S(68)A.F-S B.F-F C.S-F D.S-S●estimating schedule activity costs involves developing an(69)of the cost of the resources needed to complete each schedule activity. Cost estimating includes identifying and considering various costing alternatives. for example, in mostapplication areas, additional work during a design phase is widely held to have the potential for reducing the cost of the execution phase and product oprations. the cost estimating process considers whether the expected savings can offset the cost of the additional design work. cost estmates are generally expressed in units of(70)to facilitate comparisons both within and across projects. the(71)describes important information about prject requirement that is considered duing cost estimating.(69)A.accuracy B.approxination C.specification D.summary(70)A.activity B.work C.currency D.time(71)A.project scope statement B.statement of workC.project management plan D.project policy●The (72)technique involves using projecet characteristics in a mathematical model to predict total project cost.models can be simple or complex.(72) A.cost aggregation B.reserve analysisC.parametric estimating D.funding limit reconciliarion●(73)is a measurable, verifiable work product such as specification. feasibility study report, detail document, or working prototype(73) A.milestone B.deliverable C.etc D.BAC●(74)are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion; they may also exert influence over the project and its results.(74) A.controls B.baselinesC.project stakeholders D.project managers●(75)is the process of obtaining the stakeholdrs’formal acceptance of the completed projectscope .verifying the scope includes reviewing deliverables and work results to ensure that all were completed satisfactorily.(75) A.project acceptance B.scope verificationC.scope definition D.WBS Creation2005年下半年●__(66)__ means that every project has a definite beginning and a definite end.(66)A. Project phase B. Unique C. Temporary D. Closure●The __(67)__ defines the phases that connect the beginning of a project to its end.(67)A. schedule B. project life cycle C. temporary D. milestone●__(68)__ are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.(68)A. Project managers B. Project team membersC. SponsorsD. Project stakeholders●The __(69)__ Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project’s requirements.(69)A. Planning B. Executing?? ???????????C. Monitoring and ControllingD. Closing●The __(70)__ provides the project manager with the authority to apply organizational resources to project activities.(70)A. project management plan B. contractC. project human resource planD. project charter●The __(71)__ describes, in detail, the project’s deliverables and the work required to create those deliverables.(71)A. project scope statement B. project requirementC. project charterD. product specification●The process of __(72)__ schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.(72)A. estimating B. defining C. planning D. sequencing●PDM includes four types of dependencies or precedence relationships:...__(73)__. The completion of the successor activity depends upon the initiation of the predecessor activity.(73)A. Finish-to-Start B. Finish-to-FinishC. Start-to-StartD. Start-to-Finish●__(74)__ is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.(74)A. Planned value B. Earned valueC. Actual costD. Cost variance●__(75)__ involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance. These other projects can be within the performing organization or outside of it, and can be within the same or in another application area.(75)A. Metrics B. Measurement C. Benchmarking D. Baseline2006年下半年●(66)from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.(66)A.Process B.Milestone C.Work D.Deliverables●Organizations perform work to achieve a set of objectives.Generally, work can be categorized as either projects or operations, although the two sometimes are (67).(67)A.confused B.same C.overlap D.dissever●In the project management context,(68)includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements,and managing expectations.(68)A.integration B.scope C.process D.charter●Project (69)Management includes the processes required to ensure that the project includes all the work required, and only the work required,to complete the project successfully.(69)A.Integration B.Scope C.Configuration D.Requirement●On some projects,especially ones of smaller scope,activity sequencing, activity resource estimating, activity duration estimating, and (70)are so linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.(70)A.time estimating B.cost estimatingC.project planning D.schedule development●In approximating costs,the estimator considers the possible causes ofvariation of the cost estimates,including (71)。
信息管理专业英语试题及答案

信息管理专业英语试题及答案一、写出以下单词的中文意思(每小题0.5分,共10分)1 algorithm 11 object-oriented2 optimization 12 subsystem3 transportation 13 analogous4 dissemination 14 authorization5 evaluate 15 collection6 reliability 16 database7 verification 17 distributing8 computerize 18 payment9 practical 19 warehouse10 manipulation 20 agility二、根据给出的中文意思,写出单词(每小题0.5分,共10分)1 n.组件,群件11 adj.分布式的2 n.反馈,反应12 n.构造,配置3 n.增殖,扩散13 vt.维持,维修4 n.扩散,传播14 vt.使标准化5 n.全球化,全球性15 n.识别,鉴定6 adj.多国的,跨国的16 adj.可接受的7 vt.分配,指派17 adj.兼容的8 adj.交互式的18 n.防火墙9 n.变化,转化,转换19 n.基本设施10 n.应用,应用程序20 vt.& vi.使同步三、根据给出的短语,写出中文意思(每小题1分,共10分)1 application program interface2 back up3 bar code4 base upon5 Business Intelligence6 c loud computing7 commercial service provider8 c ustomer churn9 customer relations management10 data independence四、根据给出的中文意思,写出短语(每小题1分,共10分)1 数据挖掘2 数据转换3 数据仓库4 脏数据,废数据5 外部存储设备6 遗传算法7 网格计算8 投资决策9 知识发现10 最小冗余五、写出以下缩略语的完整形式和中文意思(每小题1分,共10分)缩略语完整形式中文意思1 B2B2 B2C3 CRM4 DBMS5 ERP6 GIS7 HTTP8 IS9 SCM10 SQL六、把以下句子翻译为中文(每小题1.5分,共15分)1) Do you have any idea how to promote the sales of this product?2) Peter is confident of winning the post as the assistant to the managing director.3) There must be fair play whatever the competition is.4) She showed strong leadership during her first term in office.5) If you have any requirements, ask me.6) The managing director's only concern was how to improve the quality of their products.7) The cost of consumption articles is the first consideration, as far as most ordinary people are concerned.8) Appreciation of works of art is bound to be dominated by a particular kind of interest.9) We sought an answer to the question, but couldn't find one.10) The program was implemented with great efficiency and speed.七、把以下句子翻译为英文(每小题1.5分,共15分)1) 没有好的管理,生意是不可能做好的。
信息管理专业英语第二版参考答案

信息管理专业英语第⼆版参考答案Unit 1【Ex1.】根据课⽂容,回答以下问题。
1.In human terms and in the broadest sense, information is anything that you are capable of perceiving.2.It includes written communications, spoken communications, photographs, art, music, and nearly anything that is perceptible.3.If we consider information in the sense of all stimuli as information, then we can’t really find organization in all cases. 4.No.5.Traditionally, in libraries, information was contained in books, periodicals, newspapers, and other types of recorded media. People access it through a library’s catalog and with the assistance of indexes, in the case of periodical and newspaper articles.6.Computerized “information systems”.7.The problem for most researchers is that they have yet to discover the organizing principles that are designed to help them find the information they need.8.For library materials, the organizing principle is a detailed subject classification system available for searching in an online “catalog”.9.The one thing common to all of these access systems is organization.10.No, it isn’t.【Ex2.】根据给出的汉语词义和规定的词类写出相应的英语单词。
信息管理与信息系统专业英语测试题Ch11Translation

Chapter 11 信息系统的管理如何组织信息系统的活动是一个重大的商业和管理信息系统战略问题。
计算的演变组织今天正面临着一系列艰难的问题,这些问题与管理计算功能相关。
不同组织数据处理的方式已经在过去几年里获得了发展。
在20世纪60年代,数据处理曾是一个后台职能,其职员主要是由直接为实现各种会计职能--如应收账款和应付账款—的自动化的部门工作的专家。
这些早期的系统实现了许多日常文书密集型运作的自动化而被认为是非常成功的。
会计系统项目的成功引发了发展更多数据处理系统的需求。
用户将这些系统的开发委托给了技术专家,这些技术专家并不总是了解他们正试图实现自动化的业务功能。
许多用户开始质疑这些数据处理项目的高额费用和令人失望的结果。
这些问题迫使高级管理人员开始直接参与数据处理项目的规划和控制。
由此导致了管理信息系统部的成立,并且管理信息系统的专业人员受到了使用项目管理的方法以确保系统在预算范围内如期开发完成的培训。
职能部门的管理者自己开始负责挑选最重要的项目和批准这些项目的费用。
20世纪70年代,计算技术开始变得更便宜。
带有软件包的小型机被供应商积极地直接销售给用户。
出于有机会控制自己的硬件和数据的动机的用户获得了大量的这种小型机系统。
其结果是导致了分散计算的纪元。
然而,诸如计算机设备不兼容、缺乏本地系统分析员、缺乏有能力的专业技术人才等问题开始使得用户重新考虑是否该自行运行管理计算机系统。
到20世纪70年代末,大部分组织已经集中了他们的数据中心业务。
集中的一群计算机专业人员管理着硬件、计算机操作、数据库和通讯系统的技术支持。
在许多企业,系统开发职能是分散的,由系统分析员和职能业务部门一起工作。
这种做法使用户对应用开发项目有更多的控制权。
20世纪90年代,大多数组织必须要管理多种技术。
计算技术实际上是以微型计算机、基于计算机的电话系统(程控电话系统)、CAD / CAM系统(计算机辅助设计/计算机辅助管理)和专家系统等形式掌握在几乎每一个经理人的手中。
管理信息系统(英文版第7版)题库chapter extension 16

Experiencing MIS, 7e (Kroenke)Chapter Extension 16 Systems Development Project Management1) Which of the following is a characteristic of large-scale systems development projects?A) short development intervalsB) single development siteC) avoidance of system localizationD) 50-100 development team membersAnswer: DAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.1: Why is formalized project management necessary? Classification: Concept2) Which of the following statements is true of large-scale systems development projects?A) They use simple computer programs to ensure consistency and speed in development.B) They use development teams of less than 20 members to reduce complexity.C) Their development can involve the integration of services from several companies.D) Their development is carried out in a single site to ensure consistency.Answer: CAACSB: Information TechnologyDifficulty: 2: ModerateCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.1: Why is formalized project management necessary? Classification: Concept3) The development of large-scale systems can involve the integration of products and services from different companies.Answer: TRUEAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.1: Why is formalized project management necessary? Classification: Concept4) Large-scale systems development requires extended development intervals as long as five or six years.Answer: TRUEAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.1: Why is formalized project management necessary? Classification: Concept5) What are the characteristics of information systems (IS) in large-scale systems development projects?Answer: Information systems (IS) in large-scale systems development project have many features and functions. They require substantial computer resources and necessitate the creation of multifaceted, complicated computer programs. They process databases with hundreds of tables; dozens, possibly hundreds, of relationships; and terabytes of data. Such large-scale systems affect many business processes and support hundreds, possibly thousands, of concurrent users.Because of their size, such systems require a large development team, often composed of 50 to 100 or more business and systems analysts, programmers, PQA engineers, and managers. To add further complexity, large-scale systems are often simultaneously developed at multiple sites. A project might involve teams in the United States, India, China, and other countries. Additionally, the development of large-scale systems can involve integrating products and services from different companies. In these larger development projects, some companies provide licensed software; others provide particular expertise, such as database design; and others provide development labor. Large-scale systems are frequently localized for different languages. Finally, large-scale systems development requires extended development intervals, sometimes as long as five or six years.AACSB: Information TechnologyDifficulty: 2: ModerateCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.1: Why is formalized project management necessary? Classification: Concept6) Systems development projects require the balancing of three critical drivers: requirements, cost, and ________.A) scopeB) timeC) performanceD) valueAnswer: BAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.2: What are the trade-offs in requirements, cost, and time? Classification: Concept7) Increasing the cost of a project can reduce the time required to complete the project up to a certain point, beyond which, the time required would increase due to ________.A) economies of scaleB) diseconomies of scaleC) economies of scopeD) diseconomies of scopeAnswer: BAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.2: What are the trade-offs in requirements, cost, and time? Classification: Concept8) In the context of a systems development project, which of the following statements is true of the relationships between requirements, cost, and time?A) Increasing the time for the completion of a project always increases the cost of the project.B) Increasing the cost of a project will always reduce the time required to finish the project.C) Reducing the requirements in a project rarely affects the time required to finish the project.D) Reducing the number of requirements in a project reduces the overall cost of the project. Answer: DAACSB: Information TechnologyDifficulty: 2: ModerateCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.2: What are the trade-offs in requirements, cost, and time? Classification: Concept9) Pete, a civil engineer, is appointed to build a state-of-the-art office building. He begins planning the design and construction of the building with his team. He estimates that the building would take six months to build and assigns work and material accordingly to the workers. In this scenario, Pete is specifying the ________.A) baselineB) data modelC) line of codeD) scatter plotAnswer: AAACSB: Reflective ThinkingDifficulty: 2: ModerateCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.2: What are the trade-offs in requirements, cost, and time? Classification: Application10) The time involved in a project can always be reduced by increasing cost.Answer: FALSEAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.2: What are the trade-offs in requirements, cost, and time? Classification: Concept11) Larger projects with longer development intervals will find it easier to meet baseline requirements.Answer: FALSEAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.2: What are the trade-offs in requirements, cost, and time? Classification: Concept12) What are the trade-offs in a systems development project's requirements, cost, and time? Answer: Systems development projects require the balancing of three critical drivers: requirements (scope), cost, and time. The requirements against the time and against the cost of a project can be traded off. If the requirements are reduced, a project would take less time to complete and the cost of the project will also decrease. The relationship between time and cost is more complicated. Normally, the time can be reduced by increasing cost, but only to a point, beyond which, the time to finish the project will actually increase due to diseconomies of scale. Thus, at some point, adding more people creates diseconomies of scale. In some projects, costs can be reduced by increasing time. However, this trade-off is not always true. By extending the project interval, one will need to pay labor and overhead for a longer period of time. Adding more time can, in this way, increase the cost of the project.AACSB: Information TechnologyDifficulty: 2: ModerateCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.2: What are the trade-offs in requirements, cost, and time? Classification: Concept13) Which of the following is a technique that stipulates phases and processes for constructing information systems (IS) but does not address the management of large-scale projects?A) systems development life cycleB) rapid application developmentC) agile software developmentD) structured system analysisAnswer: AAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.3: What are the dimensions of project management?Classification: Concept14) In the Project Management Body of Knowledge (PMBOK®) Guide, the different stages in the life of a project are referred to as ________.A) configuration controlsB) knowledge areasC) process groupsD) resource zonesAnswer: CAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.3: What are the dimensions of project management?Classification: Concept15) ________ is the knowledge area that refers to the management of an entire project and the construction of the final product.A) Project integrationB) Project managementC) Procurement managementD) Quality managementAnswer: AAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.3: What are the dimensions of project management?Classification: Concept16) ________ is a knowledge area that concerns the methods, media, and schedules for exchanging information with the project's sponsors within a team and with others who have an interest in the progress of the project.A) Procurement managementB) Communications managementC) Quality managementD) Project integrationAnswer: BAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.3: What are the dimensions of project management?Classification: Concept17) ________ is a knowledge area that concerns contracts with outside vendors for services, materials, and outsourcing of functions.A) Communications managementB) Quality managementC) Project integrationD) Procurement managementAnswer: DAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.3: What are the dimensions of project management?Classification: Concept18) The Project Management Body of Knowledge (PMBOK®) Guide identifies those practices that are known to be effective for different situations and briefly describes their use.Answer: TRUEAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.3: What are the dimensions of project management?Classification: Concept19) Knowledge areas of the Project Management Body of Knowledge (PMBOK®) Guide refer to the factors in a project that need to be managed throughout the life of the project.Answer: TRUEAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.3: What are the dimensions of project management?Classification: Concept20) What is the Project Management Body of Knowledge (PMBOK®) Guide for project management?Answer: Project Management Body of Knowledge (PMBOK®) Guide, compiled by the Project Management Institute (PMI), contains what many believe are the best project management processes, practices, and techniques. The document does not describe the details of each practice or technique but instead identifies those practices that are known to be effective for different situations and briefly describes their use. Versions of this document are denoted by the year in which they are published. As of 2015, the current version is "A Guide to the Project Management Body of Knowledge (PMBOK®) Guide, Fifth Edition."PMBOK® Guide is organized according to a grid, which shows five process groups and nine knowledge areas. The process groups refer to different stages in the life of a project. The nine knowledge areas refer to factors to be managed throughout the life of the project.AACSB: Information TechnologyDifficulty: 2: ModerateCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.3: What are the dimensions of project management?Classification: Concept21) Each task in a systems development project should culminate in one or more ________.A) deliverablesB) zonesC) segmentsD) designsAnswer: AAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.4: How does a work breakdown structure drive project management? Classification: Concept22) A(n) ________ is a hierarchy of the tasks required to complete a project.A) scatter plotB) work breakdown structureC) encryption algorithmD) virtual modelAnswer: BAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.4: How does a work breakdown structure drive project management? Classification: Concept23) A ________ defines the boundaries of a system in a work breakdown structure (WBS).A) trade-offB) codeC) scopeD) scaleAnswer: CAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.4: How does a work breakdown structure drive project management? Classification: Concept24) Which of the following tools shows the tasks, dates, and dependencies in a project?A) Gantt chartB) exception reportC) push reportD) DPlotAnswer: AAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.4: How does a work breakdown structure drive project management? Classification: Concept25) A(n) ________ is the sequence of activities that determine the earliest date by which a project can be completed.A) Gantt chartB) critical pathC) encryption algorithmD) scatter plotAnswer: BAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.4: How does a work breakdown structure drive project management? Classification: Concept26) Prototypes are examples of deliverables in a systems development project.Answer: TRUEAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.4: How does a work breakdown structure drive project management? Classification: Concept27) The critical path determines the earliest date by considering the shortest path through the network of activities.Answer: FALSEAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.4: How does a work breakdown structure drive project management? Classification: Concept28) In case of task dependencies in a project, all tasks must begin and end at the same time. Answer: FALSEAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.4: How does a work breakdown structure drive project management? Classification: Concept29) Baseline work breakdown structures can be used for monitoring a project.Answer: TRUEAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.4: How does a work breakdown structure drive project management? Classification: Concept30) What is a critical path? How is a critical path analysis done?Answer: A critical path is a sequence of activities that determine the earliest date by which a project can be completed. The earliest date is the date determined by considering the longest path through the network of activities. Paying attention to task dependencies, a planner can compress tasks as much as possible. Those tasks that cannot be further compressed lie on the critical path. Microsoft Project and other project-planning applications can readily identify critical path tasks. Managers can use the critical path to perform critical path analysis. If a task is on the critical path, and if that task runs late, the project will be late. Hence, tasks on the critical path cannot be allowed to run late if the project is to be delivered on time. Additionally, tasks not on the critical path can run late to the point at which they would become part of the critical path. Hence, up to a point, resources can be taken from noncritical path tasks to shorten tasks on the critical path. Using critical path analysis, managers can move resources among tasks so as to compress the schedule.AACSB: Information TechnologyDifficulty: 2: ModerateCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.4: How does a work breakdown structure drive project management? Classification: Concept31) Odell is the lead software developer for a new security system that needs to be urgently developed for a client. The client is insistent that the software be as infallible as possible, therefore, Odell would have to plan the systems development with precision. Which of the following activities would be Odell's biggest challenge while planning?A) creatingB) schedulingC) analyzingD) testingAnswer: BAACSB: Reflective ThinkingDifficulty: 2: ModerateCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.5: What is the biggest challenge for planning a systems development project?Classification: Application32) Scheduling a large-scale project is more difficult than scheduling individual projects. Answer: TRUEAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.5: What is the biggest challenge for planning a systems development project?Classification: Concept33) One approach businesses take to address scheduling challenges in large-scale systems is avoiding the development of software in-house.Answer: TRUEAACSB: Information TechnologyDifficulty: 2: ModerateCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.5: What is the biggest challenge for planning a systems development project?Classification: Concept34) A function point is a feature or function of a new program.Answer: TRUEAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.5: What is the biggest challenge for planning a systems development project?Classification: Concept35) The biggest challenge in planning large-scale systems development is scheduling. Describe the three approaches that organizations can take to address this challenge.Answer: The first approach that organizations can take to address the challenge of scheduling large-scale systems development projects is to avoid all major schedule risks by never developing software in-house. Instead, they can license software from vendors. However, if no suitable software exists, companies can take one of two remaining approaches. They can admit the impossibility of systems development scheduling and plan accordingly. They can abandon the systems development life cycle and decide to invest a certain level of resources into a project, manage it as best as they can, and take the schedule that produces results. The third approach is to attempt to schedule the development project in spite of all difficulties. Several different estimation techniques can be used. If the project is similar to a past project, the schedule data from that past project can be used for planning. When such similar past projects exist, this technique can produce quality schedule estimates. If there is no such past project, managers can estimate the number of lines of code that will need to be written. Then they can use industry or company averages to estimate the time required. Another technique is to estimate the function points in a program, use each function point to determine the number of lines of code, and use that number to estimate schedules.AACSB: Information TechnologyDifficulty: 3: ChallengingCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.5: What is the biggest challenge for planning a systems development project?Classification: Concept36) The challenges of managing large-scale systems development projects arise from ________.A) economies of scaleB) economies of scopeC) increase in configuration controlD) lack of coordinationAnswer: DAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.6: What are the biggest challenges for managing a systems development project?Classification: Concept37) ________ refers to a set of management policies, practices, and tools that developers use to maintain control over a project's resources.A) Perceptual mappingB) Coordination controlC) Critical path analysisD) Configuration controlAnswer: DAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.6: What are the biggest challenges for managing a systems development project?Classification: Concept38) A well-managed project will never face problems of diseconomies of scale.Answer: FALSEAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.6: What are the biggest challenges for managing a systems development project?Classification: Concept39) Unexpected events are a minor hurdle and are rarely considered while managing alarge-scale systems development project.Answer: FALSEAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.6: What are the biggest challenges for managing a systems development project?Classification: Concept40) The smaller and shorter a project, the greater the chance of disruption due to unanticipated events.Answer: FALSEAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.6: What are the biggest challenges for managing a systems development project?Classification: Concept41) What are the biggest challenges for managing a large-scale systems development project? Answer: The challenges of managing large-scale systems development projects arise from four different factors: coordination, diseconomies of scale, configuration control, and unexpected events. Large-scale projects are usually organized into a variety of development groups that work independently. Coordinating the work of these independent groups can be difficult, particularly if they reside in different geographic locations or different countries. An accurate and complete work breakdown structure (WBS) facilitates coordination, but no project ever proceeds exactly in accordance with the WBS. The coordination problem is increased because software ispure-thought stuff. Another problem is diseconomies of scale. Adding more people to a project increases coordination requirements. The number of possible interactions among team members rises exponentially with the number of team members. Ultimately, no matter how well managed a project is, diseconomies of scale will set in. Also, as the project proceeds, controlling the configuration of the work product becomes difficult. Problems can occur with designs, program code, database data, and other system components. Configuration control is vital here. The last major challenge to large-scale project management is unexpected events. The larger and longer a project lasts, the greater the chance of disruption due to an unanticipated event.AACSB: Information TechnologyDifficulty: 3: ChallengingCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.6: What are the biggest challenges for managing a systems development project?Classification: Concept42) ________ is the process by which users agree to one set of conditions, then add a bit more, then add a bit more, and so forth.A) Requirements creepB) Diseconomies of scaleC) Configuration controlD) CoordinationAnswer: AAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.7: What is the single most important task for users on a systems development project?Classification: Concept43) Taking responsibility for requirements is the single most important task a user can perform for a large-scale development project.Answer: TRUEAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.7: What is the single most important task for users on a systems development project?Classification: Concept44) Requirements creep is the process by which a project manager reduces his or her responsibilities for requirements through miniscule rollbacks.Answer: FALSEAACSB: Information TechnologyDifficulty: 1: EasyCourse LO: Discuss best practices for selecting, evaluating, and managing information systems projects.Learning Obj: LO 28.7: What is the single most important task for users on a systems development project?Classification: Concept。
(6)Unit 3《信息管理与信息系统专业英语》E-C

Part I--E-commerce I--E
《 SQL Server 数据库管理与开发》
--Limitations of electronic commerce --Limitations
Because electronic commerce relies on computer networks, the shipment (the action of sending, carrying, and delivering goods) of any physical good purchased using electronic commerce must still take place through traditional means, that is , when you buy a physical goods over the Web, it must be picked from a shelf in a warehouse, packed for shipment, and physically moved from the warehouse to the customer via a package delivery service.
sqlserver数据库管理与开发安徽财贸职业学院计算机系parteecommercecommerce电子商务electroniccommerce计算机应用软件computerapplications在网络上通信communicatingovernetworks交易双方twoparties整个交易或部分交易atransaction电子通信手段进行交易electroniccommunicationselectronicdatainterchange安全交易协议securetransactionagreement网络的成熟与普及thematuritywideadoption信用卡的普及thepermeationcreditcards作为assqlserver数据库管理与开发安徽财贸职业学院计算机系parteecommercecommerce电子商务定义为
管理类专业学位联考英语(知识运用)历年真题试卷汇编2

管理类专业学位联考英语(知识运用)历年真题试卷汇编2(总分:80.00,做题时间:90分钟)一、 Cloze(总题数:2,分数:80.00)The Internet affords anonymity to us users, a blessing to privacy and freedom of speech. But that very anonymity is also behind the explosion of cyber crime that has【1】across the Web. Can privacy be preserved【2】bringing safety and security to a world that seems increasingly 【3】? Last month, Howard Schmidt, the nation"s cyber-czar, offered the federal government a【4】to make the Web a safer place - a "voluntary trusted identity" system that would be the high-tech【5】of a physical key, a fingerprint and a photo ID card, all rolled【6】one. The system might use a smart identity card, or a digital credential【7】to a specific computer, and would authenticate users at a range of online services. The idea is to【8】a federation of private online identity systems. Users could【9】which system to join, and only registered users whose identities have been authenticated could navigate those systems. The approach contrasts with one that would require an Internet driver"s license【10】by the government. Google and Microsoft are among companies that already have these "single sign-on" systems that make it possible for users to【11】just once but use many different services.【12】the approach would create a "walled garden" in cyberspace, with safe "neighborhoods" and bright "streetlights" to establish a sense of【13】community. Mr. Schmidt described it as a "voluntary ecosystem" in which "individuals and organizations can complete online transactions with【14】, trusting the identities of each other and the identities of the infrastructure【15】which the transaction runs." Still, the administration"s plan has【16】privacy rights activists. Some applaud the approach; others are concerned. It seems clear that such a scheme is an initiative push toward what would【17】be a compulsory of Internet "driver"s license" mentality. The plan has also been greeted with【18】by some computer security experts, who worry that the "voluntary ecosystem" envisioned by Mr. Schmidt should still leave much of the Internet 【19】. They argue that all Internet users should be【20】to register and identify themselves in the same way drivers must be licensed to drive on public roads.(分数:40.00)(1).【1】A.swept √B.skippedC.walkedD.ridden词汇题(词义选择)。
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
信管英语复习试题参考答案(第一部分)一、翻译(课本P1-3)1、The study of information systems is usually a commerce and business administration discipline. “and frequently involves software engineering, but also distinguishes itself by concentrating on the integration of computer systems with the aims of the organization.2、Information systems support business processes and operations by the ways 1) Processing these accounting records into income statements, balance sheets,ledgers,management reports,and other forms of financial information 2) Recording and storing inventory data,work in process data, equipment repair and maintenance data,supply chain data,and other production/operations records3、More sophisticated programs often seamlessly incorporate statistical decision making tools like sensitivity analysis,Monte Carlo analysis.risk analysis, breakeven analysis and Bayesian analysis.4、If,for example,you are using the information system to decide about a new product introduction,the program should incorporate tools like logic analysis, conjoint analysis, contribution margin analysis.multi-dimensional scaling,multi-factor analysis. factor analysis,cluster analysis, discriminant analysis, Quality Function Deployment,preference regressions,and preference-rank translations。
二、选择(课本P4)As the strategic support role,information systems can support a company's competitive positioning (l)The supports of help in the piloting of the chain of internal value. They are the most recent,the most__________ and are within the reach of the manager They are the solutions of reductions of costs and management of the__________. One___________ them under the name of “Business Workflow Analysis”( BWA) or of“Business Management Sys tems Peer To Peer(p2p)”Tools netw orks,they assure the control of the piloting of the___________ of the functions of the company,the mastery in real time of the costs of dysfunctions cause distances from accounts,evaluation and reporting of accounting results___________ in the evaluation and in the reporting of results quality①indicates ②articulated ③pragmatic ④performance ⑤set三、判断(课本P33-34)From time to time, organizations need to change their information systems, in response to new marketing opportunities, modified government regulations, the introduction of new technolog, merger with another company, or other developments. For instance, a major cable-TV company may need to set up a billing system for movies-on-demand, or, on a smaller scale, a two-person graphic design business may want to change its invoice and payment system. When change is needed, the time is ripe for applying the principles of systems analysis and design.The formal process by which organizations build systems is known as the Systems Development Life Cycle (SDLC). The extent to which your job brings you in contact with your company's SDLC will vary depending on a number of factors, such as the size of the organization, your job description, your relevant experience, and youreducational background. In large companies the SDLC usually involves clearly defined standards and procedures. Although the technical aspects of each phase of the cycle will undoubtedly be handled by information specialists, users will always interface with these specialists As we'll see, users play a vital role in systems development.1、Organizations only need to change their information systems for a long time.()2、When change is needed, applying the principles of systems analysis and design is not needed.()3、The extent to which your job brings you in contact with your company's SDLC will vary depending only on the size of the organization()4、In large companies the SDLC usually involves vague defined standards and procedures. ()5、The technical aspects of each phase of the cycle will undoubtedly be handled by users四、阅读理解(课本P38、39、45、46)Different organizations may refer to the systems development life cycle by different names - such as applications development cycle.systems development cycle, or structured development life cycle - or, indeed, sometimes by no name at all. However,the general objectives remain the same. the number of steps necessary to complete the cycle may also vary from one company to another, depending on the level of detail necessary to effectively administer and control systems development. One way to look at systems development is to divide it into six phases The FIrst Phase: Conduct a Preliminary Investigation In this step, you need to find out what the organization's objectives are and to explore the nature and scope of the problems under study. Determine the organization' s objectives: Even if a problem pertains to only a small segment of the organization, you cannot study it in isolation. You need to find out what the overall objectives of the organization are and how groups and departments within the organization interact. Then you need to examine the problem in that context.Note that systems analysis does not focus only on information technology. In Business Process Redesign(BPR) , principles of systems analysis are applied to the goal of dramatically changing and improving the fundamental business processes of an organization. Interest in BPR was driven by the discovery that most current information systems and applications have merely automated existing inefficient business processes. BPR analysis focuses almost entirely on non-computer processes. Each process is studied and analyzed for bottlenecks, value returned, and opportunities for elimination or streamlining. The last stop is to examine how information technology might best be applied to the improved business processes. In this chapter, however, we are focusing on computer-based information systems.1、The number of steps necessary to complete the cycle depending on the _____ of detail necessary to effectively administer and control systems development.A.objectivesB.levelC.applicationD.structure2、Even if a problem _____ only a small segment of the organization, you cannot study it in isolation.A.conductB.indentifiedC.pertains toD.suggested3、You need to find out how groups and departments within the organization _____.A.interactB.indentifiedC.appliedD.existed4、In Business Process Redesign(BPR) , _____ of systems analysis are applied to the goal of dramatically changing and improving the fundamental business processes of an organization.A.objectivesB.problemsC.technologyD.principles5、Each process is studied and analyzed for _____, value returned, and opportunities for elimination or streamlining.A.objectivesB.problemsC.technologyD.bottlenecks参考答案一、翻译(非精确答案,仅供参考)1、信息系统研究通常是一个商业和商务管理的学科,经常涉及软件工程的内容,但是信息系统集中于将公司内部的计算机系统整合,这又与软件工程有很大的不同。