锅炉调试方案
燃气锅炉调试方案及流程

燃气锅炉调试方案及流程English Answer:Objective:The objective of this gas boiler commissioning plan and procedure is to ensure that the boiler is installed, commissioned, and operated in a safe and efficient manner.Scope:This plan and procedure applies to all gas boilers installed in commercial and industrial applications.Procedure:1. Pre-Commissioning:Ensure that the boiler is properly installed and connected according to the manufacturer's instructions.Check the electrical connections and wiring to ensure that they are correct and secure.Inspect the gas supply line to ensure that it is the correct size and type.Install and calibrate all necessary safety devices.2. Start-Up:Open the gas supply valve and turn on the boiler.Monitor the boiler's operation to ensure that there are no leaks or other problems.Adjust the boiler's operating parameters (e.g., temperature, pressure) to ensure that they are within the manufacturer's specifications.3. Calibration:Calibrate the boiler's temperature and pressure sensors.Check the combustion efficiency of the boiler and adjust the air-to-fuel ratio if necessary.Verify the operation of all safety devices.4. Testing:Perform a full load test to ensure that the boiler can meet the required heating load.Check the boiler's response to load changes and ensure that it operates smoothly.Conduct a safety test to ensure that the boiler shuts off properly in the event of a malfunction.5. Training:Provide training to the boiler operators on the safeoperation and maintenance of the boiler.Ensure that the operators are familiar with the boiler's controls and safety features.6. Documentation:Complete all necessary commissioning documentation, including a commissioning report and operator's manual.Keep all documentation on file for future reference.Frequency:The gas boiler should be commissioned annually by a qualified technician.Safety:All commissioning activities must be performed by a qualified technician in accordance with all applicable safety regulations.The boiler must be operated in a well-ventilated area and in accordance with the manufacturer's instructions.All safety devices must be inspected and testedregularly to ensure that they are working properly.中文回答:燃气锅炉调试方案及流程。
锅炉调试方案

130T锅炉调试方案目录一、锅炉简介二、烘炉三、煮炉四、漏风试验五、冲管六、蒸汽严密性试验七、安全阀调整八、72小时试运行前言锅炉本体安装结束,进入烘煮炉阶段亦即锅炉已基本进入了最后的调试阶段;为确保锅炉调试顺利进行,并确保锅炉将来的运行质量,特制定此方案,供调试中参照执行;同时,建设单位及安装单位会同锅炉厂及其他协作单位,成立锅炉启动验收小组负责锅炉的启动、调试、试运行的组织领导工作;以保证政令贯通,各工种职责分明,相互协作,相互配合,确保启动调试工作的顺利进行;确保锅炉如期顺利、优质的竣工投产;一、锅炉简介锅炉型号: CG-130/锅炉所采用的燃料为高炉煤气,煤气发热值低且着火温度较高,所以在炉膛下部采用了稳定燃烧和强化传热的炉内蓄热稳燃装置,保证了高炉煤气的充分燃烧;省煤器和空气预热器各为两级交替布置;空气预热器上级为管式,中级为管式,下级的下部为管式;构架采用钢结构,按7级地震校核;锅筒内部采用旋风分离器,采用集中下降管;过热器温度采用喷水减温调节装置;炉膛采用膜式水冷壁;平台采用栅栏式结构;主要技术参数名称单位数据蒸发量t/h 130工作压力MPa蒸汽温度℃450给水温度℃104热空气温度℃380排烟温度℃145锅炉设计效率% 87炉膛出口烟温℃897排污率% 2运转层标高m 8汽包中心线标高m 29适用燃料高炉煤气点火方式常规点火地震裂度度7二、烘炉1、烘炉的目的:由于新安装的锅炉,在炉墙材料中及砌筑过程中吸收了大量的水份,如与高温烟气接触,则炉墙中含有的水份因为温差过大,急剧蒸发,产生大量的蒸汽,进二由于蒸汽的急剧膨胀,使炉墙变形、开裂;所以,新安装的锅炉在正式投产前,必须对炉墙进行缓慢烘炉,使炉墙中的水份缓慢逸出,确保炉墙热态运行的质量;2、烘炉应具备的条件:2.1、锅炉管路已全部安装完毕,水压试验合格;2.2、炉墙砌筑及保温工作已全部结束,并已验收合格;2.3、烟风道都已安装完毕,保温结束,送引风机均已安装调试合格,能投入运行;2.4、烘炉所需的热工电气仪表均已安装,并校验合格;2.5、烘炉用的木柴、各种工具包括检查、现场照明等都已准备完毕;2.6、烘炉用的设施全部安装好,并将与烘炉无关的其它临时设施全部拆除,场地清理干净;2.7、烘炉人员都已经过培训合格,并排列值班表,按要求,准时到岗;3、烘炉工艺:1.根据本锅炉的结构特点可采用火焰烘炉方法;①在燃烧室中部堆架要柴,点燃后使火焰保持在中央,利用自然通风保小火,燃烧维持2~3天,火势由弱逐步加大;②第一天炉膛出口排烟温度应低于50℃,以后每天温升不超过20℃,未期最高温度<220℃,保温2~3天;③烘炉后期约7~12天改为燃气烘炉,点燃气前必须先启动送引风机;保持炉膛燃烧室负压要求;④烘炉时间以14~16天,结束燃烧停炉;⑤所有烟温均以过热器后的烟温为准;⑥操作人员每隔2小时记录一次烟温,严格按要求控制烟温确保烘炉质量;同时,做好锅炉的各处的膨胀记录;2、烘炉的具体操作:①关闭汽包两侧人孔门;②用除盐水经冷水系统向汽包内进水,并轮流打开各排污阀门疏水、排污、冲洗锅炉受热面及汽水系统和各阀门;③有炉水取样装置,取炉水样分析,确认水质达标后,停止冲洗关闭各疏水、排污阀门;④向汽包内缓慢送水,水位控制标准水位±20mm;⑤烘炉前,应适当打开各灰门和各炉门,以便及时排除炉内的潮气;⑥在燃烧室中央堆好木材,在木材上浇上柴油点火,用木材要求烘炉2—3天,烘炉时,可适当开启引风机,增大进风量,以维持一定的炉温,保证烟温,确保将炉墙烘干;⑦木材烘炉结束,可按要求进行烯煤气烘炉,此时,应增加送风机开度,微开引风机,关闭炉门、灰门,进一步提高烟温,烘干炉墙;⑧定期检查各膨胀指示器、水位计,确保锅炉运行正常,如有异常发现,应及时汇报,妥善处理;⑨定期定时检查,记录烟温,确保烘炉质量;⑩由灰浆放样处取样,进行含水率分析,当灰浆含水率≤7%时,表明烘炉已达要求,后期可转入加药煮炉阶段;烘炉曲线图附后;3.烘炉注意事项:①烘炉时,不得用烈火烘烤,温度的升速应缓慢均匀,要求最大升温速度小于20℃/天;②烘炉过程中要定期检查汽包水位,使之经常保持在正常范围;③烘炉中炉膛内的燃烧火焰要均匀,不能集中于一处;④烘炉过程中可用事故放水门,保持汽包水位,避免杂物进入过热器内;⑤烘炉过程中要定时记录烟气温度,以控制温升速度和最高温度,不超过规定要求;三.煮炉1.煮炉的目的:由于新安装的锅炉其受热面管系集箱及汽包的内壁上油锈等污染物,若在运行前不进行处理的话,就会部分附在管壁形成硬的附着物,导致受热面的导热系数减少;从而影响锅炉的热效率,另一部分则会溶解于水中影响蒸汽的品质,危害汽轮机的安全运行,根据电力建设施工及验收技术规范锅炉机组篇工作压力小于的汽包锅炉,可不进行化学清洗,而进行碱煮炉;2.煮炉已具备的条件:①烘炉后期耐火砖灰浆样含水率小于7%②加药、取样管路及机械已全部安装结束并已调试合格;③化学水处理及煮炉的药品已全部准备;④锅炉的各传动设备包括厂房内的照明设施均处于正常投运状态,⑤锅炉、化学分析等各部分的操作人员均已全部到岗;3.煮炉工艺:1烘炉后期,灰浆样含水率小于7%,用排污将水位降到中心线以下150mm.2NaOH 120KG,Na3PO4 120KG混合配成20%的药液由加药泵打入锅炉内;3开启给水旁路门,向炉内送水,控制水位在中心线以上130mm,停止进水,关闭给水旁路门,开启再循环门,进行煮炉;2煮炉共分3期:第一期:1再次检查锅炉辅机及各设备,处于启动状态,启动吸风机,保持炉膛负压49-98Pa5-10mm水柱,通风5分钟,然后将负压调小到3-5mm水柱;投入锅炉联锁装置及灭火保护装置;利用高炉煤气进行点火,具体程序详见规程:煤气系统;高炉煤气点着后,注意保持炉膛负压;根据燃烧情况及升压时间规定,投入高炉煤气进行升压;2当压力升到1MPa/cm2,敞开过热器疏水门,并冲洗就近水位计一只;3再次缓慢升压到4MPa/cm2,要求安装人员对所有管道、阀门作全面检查,并拧紧螺栓,在4MPa/cm2下煮炉8~12小时,排汽量为10%额定蒸发量;化验遇每隔4小时取样分析一次,并将分析结果通知运行有员;4根据现场确定全面排污一次的排污量和排污时间,排污时要严密监视水位,力求稳定,严防水循环破坏,并做好水位记录;5在第一期煮炉中,要求水位保持在+130mm下运行,运行人员对烟温、烟压、温度、水位及膨胀指示值等表计每小时抄表一次;第二期:1再次缓慢升压到达25 MPa /cm2,然后对各仪表管路进行冲洗;在25 MPa /cm2压力下煮炉10~12小时,排汽量为5%左右额定蒸发量;2运行值班人员应严格控制水位在+160 mm,并每隔2小时校对上下水位计一次,做好记录;3化验人员每隔断2小时取炉水验一次,炉水碱度不得低于45mgN/L,否则应加药液;同时根据经验通知,全面定期排污一次,在排污中要严格控制水位,要求水位波动小,并做好排污记录;4在25MPa/cm2压力下运行,测试各风机出力及总风压,并做好记录,同时要求运行人员应对汽压、水位、烟温进行调节、监视,必要时可用过热器疏水调节;第III期:1缓慢升压到32 MPa /cm2稳定燃烧,控制水位+160mm,汽温380℃~400℃,在此压力下运行12~24小时;2打开给水旁路门,来控制其进水量,然后采用连续进水及放水的方式进行换水;3根据化验员通知,适当打开排污阀,同时派专人监视汽包水位并及时联系;4化验人员每隔1小时取样分析一次,并作好详细记录,当炉水碱度在规定范围内一般≤18 mgN/L时,可停止换水,结束煮炉;3注意事项:一、煮炉注意事项1加药前炉水应在低水位,煮炉中应保持汽包最高水位,但严禁药液进入过热器内;2煮炉时,每次排污的时间一般不超过半分钟,以防止破坏水循环;3在煮炉中期结束时,应对灰浆进行分析,一般第I其他结束,灰浆样含水率应降到4~5%,在第II期结束应到2;5%以下,若没达到,可适当延长煮炉时间,确保灰浆含水率达到要求;4运行人员及化验人员必须严格按规范操作,并做好详细记录;二、点火注意事项1点火过程中,如发现煤气点不着或着火后熄灭了,应立即关闭煤气阀门,增大炉膛负压,通风3-5分钟,排净炉内混合气体后,按程序重新点火;2高煤火嘴投入应调整好,注意热风的配合投入;3点火升压过程中应随时监视排烟温度,发现异常,应查明原因消除;4.煮炉以后1煮炉结束,锅炉停炉放水后应打开汽包仔细彻底清理汽包内附着物和残渣;2电厂化验人员及调试人员应会同安装单位人员检查汽包内壁,要求汽包内壁无锈蚀、油污,并有一层磷酸钠盐保护膜形成;四、漏风试验1、漏风试验的目的:检查锅炉炉墙及空气流通通道的密封性;2、试验时间:在煮炉结束后再次点炉进行整套试运行前;3、试验方法:采用干石灰喷流及蜡烛试风;4、操作方法:1煮炉结束后,待炉适当冷却;2开启鼓风机,并在进风口加入干石灰,让其随同锅炉进风进入整个锅炉,微开引风机,保持炉膛正压;3将锅炉分成若干部位,主要包括炉膛、空预器、烟风道等,指定若干班组,检查各部位漏风情况;4若发现有白石灰渗出,则该部位漏风,应做好标记,待试验停止后,再行修复;对某一部位若有怀疑,则可点燃蜡烛进行测风,以确定该部位是否漏风;5漏风的各处应做好标记,并做好记录,在试验结束后检修;5、试验的合格要求:在炉膛正压的情况下,各被检查部位不漏风;五、冲管1、冲管的目的:冲管是利用具有一定压力的蒸汽吹扫过热器、主蒸汽管道,并将这部分蒸汽排向大气,通过蒸汽吹扫,将管内的铁锈、灰尘油污等杂物除掉,避免这些杂物对锅炉、汽机安全运行造成危害;2、冲管的参数方式:本次冲管压力采用3MP流量不低于45T/H,温度380---420℃,蒸汽冲管分两期,第一期8--10次,第二期10---16次,冲管方式采用降压冲管;3、冲管前的准备工作1煮炉结束,验收合格,关闭汽包阀门,调整进水操作,关闭再循环门;2启动给水泵,微开给水旁路门,冲洗汽包内残余化学药品,然后排污,其排污量由化学分析决定;3炉水取样分析,当水质达到要求时,停止冲洗;4将主蒸汽管道从母管隔离门前安装临时管道,接到主厂房外面,并在临时管道口安装“靶板”,靶板暂时可不安装上;5冲管管路:锅炉高温过热器出口集箱----电动截止门-----主汽门前电动截止门----主蒸汽管路---临时排汽管路排出;4、冲管操作程序:1向汽包里进水到-50MM,然后点火,缓慢升压;2当压力升到 MPa /cm2时,冲洗水位计并关闭空气门;3当压力升到2---3 MPa /cm2时调整水位在+20MM,进行全面排污一次4试冲管三次,汽压在6—8 MPa /cm2;5缓慢升压,调整风量和煤气量,严格控制烟温,当压力升到32KGF/CM2时,控制汽温380---420,打开过热器出口门,蒸汽流量应大于45T/H,采用降压式冲管;连续冲管8---10次,每次冲管时间5MIN,间隔 HOUR, 以便冷却主蒸汽管,使铁锈松脆;6停炉冷却24H以上,待过热器冷却;7以照上述冲洗程序10---16次;8然后,将管道出口装上“铝靶”,其宽度为排汽管内径的8%,长度纵贯内径;9依冲管程序再冲管3—4次;10关闭煤气、鼓、引风机,取出铝板,甲、乙双方有关人员检查,铝板表面有无斑点,决定冲管是否合格,并做好记录;5、注意事项及合格标准:1所用临时管的截面积应大于或等于被冲洗管的截面积,临时管应尽量短,以减少阻力;2临时管应引到室外,并加明显标记,管口应朝上倾斜,保证安全,放临时管时应具有牢固的支承承受其排空反作用力;3冲管前锅炉点火升压过程中,应按锅炉正常点火升压过程的要求严格控制升压、升温速度;4冲洗过程中,要严格控制汽包水位的变化,尤其在冲管开始前,将汽包水位调整到比正常水位稍低,防止冲管时水位升高而造成蒸汽带水;5连续两次更换铝板检查,铝板上冲击斑痕粒度≤,且肉眼可见凹坑不多于8点即冲管合格;六、蒸汽严密性试验蒸汽严密性试验是锅炉按运行操作规程点火升压到工作压力,进行严密性试验用以检验锅炉及附件热状态下即工作压力严密性的试验;1、试验中注意事项:1锅炉严格按操作规程点火升压到工作压力;2重点检查锅炉的焊口、人孔和法兰等的严密性;3重点检查锅炉附件和全部汽水阀门的严密性;4重点检查汽包,联箱各热面部件和锅炉范围内的汽水管路的膨胀情况及其支座、吊杆和弹簧的受力,位移和伸缩情况是否正常,是否有妨碍膨之处;5试验过程中,应确定一些部件进行测定,对水冷壁、过热器等壁温进行一次测量了解,有无管壁超温现象;2 严密性试验的缺陷处理:1对壁温有超温的,对管壁的保温要重新处理到无超温为止;2检查中如泄漏,轻微处难以发现和判断的,可用一块温度较低的玻璃或光谱的铁片等物靠近检查,若有泄漏,待降压后处理;3蒸汽严密性试验无泄漏为合格,合格后应做好记录,并做好签证;七、安全阀调整蒸汽严密性试验后,可对各安全阀进行调整;调整安全阀的压力以就近压力表为准,压力表经校验合格并有记录,在调整值附近若>%,应做误差修正;1、本锅炉安全阀动作压力动作压力:1汽包工作安全阀:=2汽包控制安全阀:=3过热器安全阀: =2、安全阀调整前的准备工作:1安全阀在安装就位前,应进行解体清洗、检查;2安全阀内部的锁紧装置,调试前应拆除;3对安全阀的有关支架,排汽管道支架等应仔细检查,所用电动阀应试验一次;4所有调整人员应了解安全阀的内部结构和调整安全阀的安全措施,进行组织分工,并做好噪声的防护工作;3.调整方法和步骤:1为了调节方便,宜采用不带负荷较正安全阀,即安排在冲管后升压阶段调整;2升压及检查:a冲管工作结束后要求运行值班人员,对锅炉机组全面检查,确定无异常后启动设备;B升压过程严格控制升压速度,并按操作规程进行;C.当压力升到 Mpa时,关闭空气阀冲洗水位计一次,压力升到 Mpa时,全面排污一次,压力升到 Mpa时,再次冲洗汽水管道,压力升到 Mpa mpa,要求全面检查锅炉及各设备确无异常时,继续升压,压力升到 Mpa,必须派专人监视水位,再次冲洗汽包水位于计并上下核对,做好记录,压力升到 Mpa 时,调整向空排汽,检查电动阀是否良好摇控,然后继续升压,将锅炉蒸汽切换到向空排气,调整风量、煤气量,继续提高汽压,第一个汽包工作安全阀,第二个校汽包控制安全阀,第三个校过热器安全阀;D.汽包工作安全阀运行压力:,等安全阀动作后,立即减少煤量,开大向空排汽泄压,并记录回座压力 ,验证是否符合要求,若不符合要求,或达到最大允许值仍末动作,应有立即降压,交付安装人员检查,调整后重新校对;E.然后校对汽包控制安全阀;动作压力: MpaF.最后校对过热器安全阀,动作压力:G.`调整过程中,严格控制汽温、水位变化,汽压控制可由向空排汽来调节排汽量;八、七十二小时试运行锅炉机组在安装完毕并完成分部试运行后,必须通过72小时整套试运行;1、试运行的目的:1在正常运行条件下对施工、设计和设备进行考核,检查设备是否有达到规定的出力,各项性能是否符合原设计的要求,同时可检验锅炉安装和制造质量,而且检验所有辅助设备的运行情况,特别是转动机械在运行时有无振动和轴承过热等现象;2锅炉在试运行前,应进行锅炉的热力调整试验;I调整试验的①调整燃烧的燃烧工况;②检查安装质量,有无漏风、漏水③找出锅炉额定蒸汽参数和蒸发量达不到的原因④确定锅炉效率,获取锅炉在最佳运行方式下的技术经济特性II调整试验的内容:1炉膛冷态空气动力场试验,风机及管道性能试验2炉膛吸烟风道漏风试验3安全阀校验及热效率试验2.锅炉机组启动前应具备的条件:试运现场的条件:1场地基本平整,消防、交通及人行道路畅通;厂房各层地面应做好粗地面,最好使用正式地面,试运场应有明显标志和分界,危险区应有围栏和警告标记;2试运区的施工脚手架全部拆除,现场清扫干净,保证运行安全操作;3试运区的梯子、步道、栏杆、护板应按设计安装完毕,正式投入使用;4新扩建部分的排水沟道畅通,沟道及洞盖板齐全;5试运现场具有充足的正式照明,事故照明应能投入正常使用,并备有足够的消防器材;6试运范围的工业、消防及生活用水系统应能投入正常使用,并备有足够的消防器材;7各运行岗位应有正式的通讯联络设施;下列系统中的设备、管道、阀门等安装完毕,保温完成;1锅炉范围内煤气管道、汽水系统、疏放水、放汽系统、加药系统辅助用蒸汽系统、排污系统;3.下列设备经调试合格:1送风机,引风机经调试接速并符合要求;2,热工测量,控制和保护系统的调试已符合点火要求;4,组织机构,人员配备和技术文件准备;1,电厂按试运方案措施,配备各岗位的运行人员及实验人员,并有明确的岗位责任制,运行操作人员应培训合格,并能胜任本岗位的运行操作和故障处理;2施工单位应根据试运方案措施要求,配备足够维护检修,并有明确的岗位责任制;维护检修人员应了解所在岗位的设备系统性能;并能再统一指挥下胜任检修工作,不发生设备,人身事故和中断试运工作;3 施工单位应备齐参加试运设备系统的安装验收签证和分部试运记录;4编制调整试运方案措施,经试运指挥部审定后,应打印完毕,并分别进行了交底和学习;5运行单位在试运现场挂符合实际的燃烧系统图,热力系统图,调试单位应在试运现场张挂试运,点火,升压等必要的图表;5锅炉的准备工作;启动的准备工作;上水注意事项;℃℃,超过50℃不得上水;点火前的要求点炉前的准备1送风机 1引风机吹扫风管操作如下;锅炉的点火与升压℃;℃;温差加大时,可开大对空排汽,减缓升压速度或加大排污量;锅炉的并汽℃范围内,汽包水位在±50mm左右;4锅炉的并列应注意:①并炉时保持主气压力底于蒸汽母管压力——,若锅炉气压高于母管压力时,禁止并炉;②并列时蒸汽温度应低额直30℃保持较低的水位,燃烧稳定;应注意保持气压、气温等参数,并缓慢增加蒸发量;③在并列过程中,如引起母管的气温急剧下降时或发生蒸汽管道水冲击时,应立即停止并列,减弱燃烧,加强疏水,待恢复正常后重新并列;④并列后,应对锅炉机组进行一次全面检查,并将点火到并列过程中的主要操作及新发现的问题;记录在有关的记录簿内;6、试运行消缺及再次24小时运行;①锅炉试运行结束,应对运行的缺陷当时无法消除的分析原因进行消缺;②消缺后按以上操作程序再进行二十四小时试运行;③整机试运行合格后,按火力电厂基本建设工程启动验收规程办理整套运行签证手续和设备验收移交工作;④,整套72小时运行结束,应将下列施工技术文件移交甲方;a.全部的安装验收记录、签证、分部试运行试验记录;b.主要设备缺陷及其修改记录或处理意见;c.主要设计缺陷及其修改记录或处理意见;d.主要施工缺陷及其处理意见;小时试运记录;f.施工未完成项目表及其处理意见;小时试运行总结;6、参与机组启动试运有关单位的主要职责建设单位全面协助试运指挥部做好机组启动试运全过程中的组织管理,参加试运各阶段的工作检查协调、交接验收和竣工验收等日常工作,协调解决合同执行中的问题和外部关系等;出任验收检查组和综合组的组长;施工单位完成启动需要的建筑和安装工程及试运中临时设施的施工;配合机组整套启动调试试运工作;按有关要求做好自检、迎检工作;做好试运设备与运行或施工中设备的安全隔离措施;负责试运现场的安全、消防、治安保卫、消缺检修和文明启动等工作;提交与机组配套的所有文件资料、备品配件和专用工具等;全面负责组织分部试运工作,出任分部试运组组长; 调试单位负责编制调试大纲、分系统及机组整套启动试运的调试方案和措施;参加分部试运工作及试运后的验收签证;全面检查机组所有系统的完整性和合理性;负责组织协调并完成机组启动试运全过程中的调试工作;负责提出解决启动试运中重大技术问题的方案或建议;填写调整试运质量验评表;提交调试报告;出任整套试运组组长;生产单位负责完成机组整套启动前各项生产准备工作;负责提供电气、热控等设备的运行整定值;参加分部试运及试运后的验收签证;做好运行设备与试运设备的安全隔离措施;负责试运中的操作、事故处理和文明生产;对运行中发现的问题提出处理意见或建议;移交试生产后,全面负责机组的安全运行和维护管理工作等;出任生产准备组和试生产组组长;设计单位负责机组试运过程中出现的必要的设计修改;提交完整的竣工图;制造单位按合同进行技术服务和指导,保证设备性能;及时消除设备缺陷;处理制造厂应负责解决的问题;协助处理非责任性的设备问题;电网调度部门及时提供归其管辖的主设备和继电保护装置整定值;核查机组的通信、远动、保护、自动化和运行方式等实施情况;及时审批机组的并网申请,以及可能影响电网安全运行的试验方案,发布并网或解列命令等;7反事故措施与安全注意事项反事故措施机组启动调试工作是新建机组的一个关键阶段,防止试运期间机组非计划停运反事故措施,是使机组顺利完成启动试运行,达到安全、稳定、经济的调整试运目的保证;试运期间机组非计划停机的因素很多,涉及设计、施工、调试、运行、制造厂家、监理、生产等参建单位;因此,必须以科学的管理方法来组织机组的启动调试和试运;在启委会的领导下,各单位责任落实,层层把关,以实现共同目标;我院在调试组织机构的运作中,明确调总是调试现场具体调试工作的总指挥,从分系统调试试运开始,负责各单位,各专业之间的调试和消缺协调工作;各专业负责人为各专业的安全、质量、技术第一负责人,我院安全体系、质量体系的有效工作是防止非计划停运的有力保证;工作重点是:1 落实质量验收制度,不合格的项目不能带到下道工序;2 严格执行工作票制度;3 加强试运中的指导、示范操作和监护;4调试人员必须以高度的责任心和责任感来对待调试工作,牢固树立“精心组织,确保安全,认真调试,精益求精,创造精品工程”的思想;。
最全的锅炉调试方案

锅炉调试方案目录第一章锅炉介绍.................................................................................................................................... - 4 -一、锅炉技术规范.................................................................................................................................. - 4 -1 锅炉参数.............................................................................................................................................. - 4 -2 设计燃料(劣质烟煤,煤质分析如下).......................................................................................... - 4 -3 技术经济指标...................................................................................................................................... -4 -4 设计数据.............................................................................................................................................. -5 -5 水质要求.............................................................................................................................................. - 5 -6 负荷调节.............................................................................................................................................. - 5 -7 其它技术指标...................................................................................................................................... - 6 -二、锅炉汽水系统.................................................................................................................................. - 6 -1 给水流程.............................................................................................................................................. - 6 -2 蒸汽流程.............................................................................................................................................. - 6 -3 其它流程.............................................................................................................................................. - 6 -三、锅炉结构.......................................................................................................................................... - 6 -1 锅筒及内部装置.................................................................................................................................. - 6 -2 水冷系统.............................................................................................................................................. - 7 -3 燃烧系统.............................................................................................................................................. - 7 -4 过热器.................................................................................................................................................. - 8 -5 省煤器.................................................................................................................................................. - 9 -6 空气预热器.......................................................................................................................................... - 9 -7 分离、回料系统................................................................................................................................ - 10 -四、仪表控制........................................................................................................................................ - 10 -五、锅炉所配安全附件........................................................................................................................ - 10 -六、锅炉辅机........................................................................................................................................ - 11 -(九)除渣系统滚筒冷渣机技术参数(见下表)................................................................... - 16 -(十一)除灰系统技术参数(见下表)................................................................................... - 17 -(十三)起重设备(电动葫芦、手拉葫芦)技术参数(见下表) ............................................ - 23 -第二章安装后的检查.......................................................................................................................... - 24 -一、检查燃烧室及烟道内部,符合下列要求: .............................................................................. - 24 -二、检查给煤机和油枪,符合下列要求: ........................................................................................ - 24 -三、检查电动机,符合下列要求:.................................................................................................... - 25 -四、检查飞灰循环系统,符合下列要求: ........................................................................................ - 25 -五、检查汽水管道及燃油管道,符合下列要求: ............................................................................ - 25 -六、检查各阀门、挡板、风门,符合下列要求: ............................................................................ - 26 -七、检查汽包水位计,符合下列要求: ............................................................................................ - 26 -八、检查压力表,符合下列要求:.................................................................................................... - 26 -九、检查安全阀,符合下列要求:.................................................................................................... - 27 -十、检查承压部件的膨胀指示器,符合下列要求: ........................................................................ - 27 -十一、检查操作盘,符合下列要求: ................................................................................................ - 27 -十二、检查现场照明,符合下列要求: ............................................................................................ - 28 -十三、其它检查:................................................................................................................................ - 28 -十四、冷渣系统、输渣系统................................................................................................................ - 28 -第三章锅炉冷态试验.......................................................................................................................... - 29 -一、冷态试验前需具备的条件............................................................................................................ - 29 -二、漏风试验........................................................................................................................................ - 30 -三、风机试验........................................................................................................................................ - 31 -四、布风板空板特性试验.................................................................................................................... - 32 -五、布风板均匀性试验........................................................................................................................ - 32 -六、流化特性试验................................................................................................................................ - 33 -七、返料器流化返料试验.................................................................................................................... - 33 -八、油枪出力试验................................................................................................................................ - 33 -第四章转动机械的试运行.................................................................................................................. - 34 -一、试运前提........................................................................................................................................ - 34 -二、拉合闸试验.................................................................................................................................... - 35 -四、联锁试验........................................................................................................................................ - 35 -第五章锅炉机组启动应具备的条件.................................................................................................. - 39 -第六章压缩空气吹扫和水系统、过热器冲洗方案 .......................................................................... - 43 -一、压缩空气吹扫................................................................................................................................ - 43 -二、水系统冲洗要求............................................................................................................................ - 43 -1 除氧器系统管道冲洗........................................................................................................................ - 44 -2主给水管道系统冲洗.......................................................................................................................... - 44 -3 冲洗过热器........................................................................................................................................ - 44 -第七章高温烘炉、煮炉开车方案...................................................................................................... - 46 -五、烘煮炉的操作步骤........................................................................................................................ - 54 -六、烘煮炉过程中的安全注意事项及安全技术措施 ........................................................................ - 56 -第八章锅炉机组的启动...................................................................................................................... - 57 -一、锅炉机组启动前的检查与准备.................................................................................................... - 57 -二、锅炉上水........................................................................................................................................ - 58 -三、锅炉点火........................................................................................................................................ - 59 -四、锅炉的升压.................................................................................................................................... - 62 -第九章蒸汽严密性试验方案.............................................................................................................. - 64 -一、试验目的........................................................................................................................................ - 64 -二、蒸汽严密性试验应具备的条件: ................................................................................................... - 64 -三、蒸汽严密性试验检查项目及检查方法 ........................................................................................ - 65 -四、蒸汽严密性试验的验收确认........................................................................................................ - 66 -五、升压过程注意事项及安全措施.................................................................................................... - 66 -第十章安全阀调整方案...................................................................................................................... - 68 -一、校验目的........................................................................................................................................ - 68 -二、安全阀调校应具备的条件: ........................................................................................................... - 68 -三、校验的规定: ................................................................................................................................... - 69 -四、校验原则: ....................................................................................................................................... - 69 -五、校验前的检查与准备.................................................................................................................... - 69 -七、安全阀整定参数............................................................................................................................ - 71 -八、技术标准........................................................................................................................................ - 71 -九、安全技术措施................................................................................................................................ - 71 -第十一章蒸汽吹扫及试运行方案...................................................................................................... - 72 -四、吹管前应具备的条件.................................................................................................................... - 74 -五、管道吹管步骤................................................................................................................................ - 75 -第十二章锅炉试运方案...................................................................................................................... - 78 -一、启动试运行的目的........................................................................................................................ - 78 -二、锅炉整套启动应具备的条件........................................................................................................ - 78 -三、锅炉整套启动前需要检查及试验项目、准备工作 .................................................................... - 80 -四、锅炉的启动.................................................................................................................................... - 83 -五、启动要求及注意事项:................................................................................................................ - 85 -六、锅炉运行中的监视与调整:........................................................................................................ - 86 -七、锅炉的升压与热启动:................................................................................................................ - 87 -八、锅炉机组的正常停止:................................................................................................................ - 88 -第十三章、事故应急预案.................................................................................................................... - 90 -第十四章安全注意事项.................................................................................................................... - 99 -第十五章、组织管理措施及试车计划 .............................................................................................. - 100 -第一章锅炉介绍本锅炉是采用循环流化床洁净燃烧技术的130t/h次高温高压蒸汽锅炉,具有燃烧效率高,低污染和节约燃料、便于调节等特点。
锅炉调试技术措施

锅炉调试方案(印尼拉法基2×16.5MW电厂工程)一、引用标准:1、《火力发电厂基本建设启动及竣工验收及规程(1996年版)》2、《火电工程启动调试工作规程》3、《火电工程调整试运质量验收及评定标准》4、《电力建设施工及验收技术规范》5、制造厂图纸,安装和使用说明书等6、设计文件、图纸、说明书等二、总则:1、编写目的:锅炉启动调试是保证锅炉高质量投运的重要环节,特编写本调试措施。
2、组织形式(1)机组启动调试工作由试运指挥部全面组织、领导、协调,锅炉启动调试由锅炉调试专业小组负责具体调试项目的开展。
(2)锅炉专业调试小组由调试、施工、生产、建设、监理、设计及制造等单位的工程技术人员组成,由调试单位任组长。
1、通则(1)、试运条件A、相应的建筑和安装工程已完成,记录齐全,并经验收合格。
B、相关系统设备的阀门已挂牌C、试运设备系统保护整定值已确定(2)、试运内容A、分部试运是锅炉启动的调试的重要组成部分,认真做好这项工作是锅炉顺利启动的保证。
是从厂用电受电开始到机组首次整套启动前必须完成的关键工作。
B、分部试运包括单机试转和分系统试运两部分。
单机是指锅炉各辅机设备单台试转。
分系统试转是指锅炉各辅机设备按系统对其动力、电气热控等设备及其系统进行的空载和带负荷的调整试运。
(3)、试运程序A、编写调试措施B、组织学习、讲座及审批方案或措施C、建立分部试运文件包D、设备单机静态检查验收F、单机试转收签证G、系统静态检查验收H、分系统试运I、分系统试运验收签证J、调试简报K、移交生产单位保管2、单机试转(1)、试转条件:A、校验电动机本身的保护合格,并具备投入运行条件B、机械部分安装结束,安装质量符合该设备安装说明书的要求(2)、试转要点辅机设备在首次试转时对能与机械部分断开的电动机,应先将电动机单独试转,并确认转向,事故按钮,轴承振动、温升等正常。
(3)、试转标准(4)、行成文件(1)试转条件(2)试转要点(3)试转标准(4)行成文件4、分部试运控制要点风机及其系统四、锅炉系统调试1、锅炉冷态通风实验和内容(1)、送风系统流量表的标定(2)、给煤机给煤量标定(3)、标定一、二次风量(4)、布风板阻力试验(5)、料层阻力试验(6)、临界流化风量(布风板均匀性检查)的测定(7)、试验期间安全注意事项(1)煮炉应具备的条件(2)煮炉前的准备(3)工艺要求(4)注意事项3、主蒸汽管的吹扫(1)吹扫目的(2)吹扫前的准备工作(3)吹扫方案和参数(4) 吹扫步骤(5)验收标准(6)吹扫注意事项4、锅炉蒸汽严密性试验(1)(2)(3)5、安全阀整定(1)整定安全阀的准备工作(2)安全阀调整压力标准(3)整定程序及注意事项五、机组整套启动时的锅炉调试:(336小时)1、试验现场条件2、设备系统条件3、锅炉点火,升温、升压的工作要点,安全注意事项等六、试运期间的安全注意事项:锅炉冷态试验方案1 目的烧技术,床下启动的方式,全钢架支吊结合的固定方式,半露天布置,平衡通风,运行时燃烧室处于正压工况,固态机械除渣,气力除灰。
锅炉安装调试方案范文

锅炉安装调试方案引言锅炉作为工业生产中的能源装备,承担着生产过程中的供热或供能任务,因此其安装和调试工作非常重要,牵扯到安全、效率和经济等多个方面。
本文将针对锅炉的安装和调试方案进行详细介绍。
第一部分:锅炉安装1.安装前的准备工作在安装锅炉前,需要进行一系列的准备工作,包括:•确定锅炉的类型、型号和技术参数,以及锅炉的安装位置和基础设施的布置。
•对安装地面进行平整处理,确保锅炉的安装位置平稳、牢固。
•安装前需要对锅炉进行详细的检查,包括检查锅炉的各项技术参数是否符合要求;检查锅炉本身以及安装设备的完好性等。
2.安装过程锅炉的安装过程中,需要注意以下几个方面:•采用齐平式安装,确保锅炉存在于同一平面,不得有倾斜、变形的现象。
•对锅炉本身和附属设备进行精细的安装、连接、疏通和调整工作。
确保管路系统密封性良好,各组件之间运转顺畅。
•安装注意事项:(1)对于燃煤锅炉而言,需要注意煤粉的送风方向和风量,以及空气预热器的设置;(2)对于燃气锅炉而言,需要注意燃气的配气,以及燃气管道的选择和布置;(3)对于工业锅炉而言,需要注意锅炉房的防火和通风。
第二部分:锅炉调试1.调试前的准备工作在进行锅炉调试之前,需要进行一系列的准备工作,包括:•清洗锅炉本身和附属设备,确保存在无污染问题。
•开始各个设备的操作,并对操作过程进行详细的检验和试运转。
•检查锅炉各项参数,调整各个参数以符合运行要求。
2.调试过程在进行锅炉调试的过程中,需要注意以下几个方面:•对于新安装的锅炉,需要在进行调试前先进行预热处理,也就是将锅炉的各个部件进行一遍较长时间的加热,以消除设备运输和安装过程中的残留物质,确保设备的正常运行。
•在调试过程中,需要对各项参数进行仔细调整和监测,对存在问题的参数进行及时处理和调整。
•在调试结束后,需要对锅炉进行全面的检验和测量,确保设备的正常运行和可靠性。
第三部分:锅炉操作维护1.操作注意事项对于锅炉的操作,需要注意以下几个方面:•对于锅炉的供水,需要定期检查供水管道是否通畅,对于存在污垢和杂质的管道要及时清理。
锅炉调试方案之十三--燃烧调整试验方案

BT-GL-02-13XXXXXXXX扩建工程#3机组锅炉燃烧调整试验方案XXXXXXXX科学研究院二〇二四年一月签字页批准:审核:编写:目录1.编制依据 (5)2.调试目的 (5)3.系统及主要设备技术规范 (5)4.试验内容 (7)5.锅炉燃烧调整应具备的条件 (7)6.试验程序 (8)7.试验方法和步骤 (8)8.职责分工 (9)9.环境、职业健康、安全、风险因素控制措施 (10)1.编制依据1.1《火力发电厂基本建设工程启动及竣工验收规程(1996年版)》1.2《电力建设施工及验收技术规范》锅炉篇(1992年版)1.3《火电工程调整试运质量检验及评定标准》(1996年版)1.4《火电工程启动调试工作规定》(1996年版)1.5设计图纸及设备设明书2.调试目的锅炉燃烧的好坏对锅炉及电厂运行的安全性和经济性都有很大的影响,锅炉燃烧调整可以确保着火稳定,燃烧中心适中,火焰分布均匀,配风合理,避免结焦等,维持锅炉汽温、汽压和蒸发量稳定正常,使锅炉保持较高的经济性运行。
本措施的制定是为了在整套启动阶段指导锅炉燃烧调整,保证在锅炉试运中能够安全正常运行。
3.系统及主要设备技术规范3.1系统简介XXXXXXXX扩建工程#3机组锅炉是由东方锅炉有限责任公司制造的DG1065/18.2-Ⅱ6型亚临界压力一次中间再热自然循环汽包炉。
锅炉采用摆动式燃烧器、四角布置、切向燃烧。
单炉膛、全钢架悬吊结构、平衡通风、固态排渣。
锅炉采用正压直吹式制粉系统,配五台HP863型中速磨煤机,布置在炉前,四台磨煤机可带MCR负荷,一台备用。
燃烧器为可上下摆动的直流燃烧器,采用四角布置、切向燃烧。
上组所有喷口均可上下摆动±30°,下组所有喷口均可上下摆动±15°。
油燃烧器共12个,分三层布置。
燃用轻柴油。
油枪采用简单机械雾化型喷嘴3.2 锅炉主要技术规范3.2.1煤质分析3.2.2 锅炉主要技术参数如下过热蒸汽流量 1065 t/h过热蒸汽压力 17.36 MPa过热蒸汽温度 540 ℃再热蒸汽流量 875 t/h再热蒸汽进口温度 332 ℃再热蒸汽出口温度 540 ℃再热蒸汽进口压力 3.94 MPa再热蒸汽出口压力 3.78 MPa给水温度 281 ℃排烟温度(修正前) 132 ℃排烟温度(修正后) 126 ℃过热器喷水量(一级) 36.61 t/h过热器喷水量(二级) 9.15t/h二次气喷水量 21.96t/h锅筒工作压力18.77 MPa锅炉效率 92.93 %3.2.3燃烧器规范4.试验内容4.1 锅炉主保护的检查确认;4.2 燃烧调整;5.锅炉燃烧调整应具备的条件5.1 在锅炉启动前必须对FSSS系统的各项功能进行试验,确保其动作正确可靠。
锅炉设备调试运行方案范文
锅炉设备调试运行方案概述锅炉设备调试和运行是工业生产过程中的关键环节,它涉及到工业生产的效率、安全和产品质量。
本篇文档旨在介绍锅炉设备调试和运行的方案及注意事项,以帮助工程师更好地进行锅炉设备调试和运行。
设备调试方案锅炉设备调试主要包括如下几个方面:1. 炉膛调试炉膛调试是锅炉设备调试的重要环节。
在进行炉膛调试时,需要注意以下几个方面:•检查炉膛砖瓦是否全部安放稳妥•检查炉膛砖瓦是否完好,如有损坏须及时更换•检查炉膛绕管是否完好•在开炉前,先行进行缓慢升温,使炉膛向燃烧状态转化•在升温时需通过开启废气通道,保证废气正常排放•当炉温达到设计温度后,需检查是否有异常情况出现•在出现异常情况时,需及时根据具体情况调整炉膛出口温度、炉内热平衡等参数2. 燃烧系统调试燃烧系统是锅炉设备的核心部分,因此对其进行调试是非常重要的。
在进行燃烧系统调试时,需要注意以下几个方面:•检查燃料电子控制,确保稳定可靠•检查点火状态,确保完全开启•需要根据设计要求设定燃料进料量、点火辅助燃料量等参数•需要根据燃烧系统的温度、氧气含量、空气含量等参数进行动态调整•当发现燃烧过程出现异常时,需及时调整燃烧机补偿量、进气系统打火、压力控制、可燃气体浓度等参数3. 补给水系统调试补给水系统是维持锅炉设备正常运行的重要环节,需要进行调试,以确保系统的良好运行状态。
在进行补给水系统调试时,需要注意以下几个方面:•检查补给水阀门是否打开•检查水源是否有足够水量,如无需及时调整水源•需要根据水位变化情况调整补给水速度和补给水量•需要根据锅炉系统的工况情况调整补给水温度•当发现补给水系统发生异常时,需及时调整补给水温度、水位控制、给水泵、回水系统等参数设备运行方案锅炉设备的正常运行是保障工业生产的重要前提,只有制定科学合理的设备运行方案,才能保证锅炉设备的安全高效运行。
在制定锅炉设备运行方案时,需要注意以下几个方面:1. 清洁保养锅炉设备的清洁保养是设备长期稳定运行的重要环节,需要进行定期清洗和保养。
锅炉空气动力场试验调试方案
目录1 编制目的 (02)2 编制依据 (02)3 设备及系统简介 (02)4 调试内容及验评标准 (04)5 组织分工 (04)6 使用设备仪器 (05)7 调试应具备的条件 (06)8 调试步骤 (06)9 优化措施及建议 (07)10 平安安康及环境要求 (07)1 编制目的通过锅炉冷态通风试验,检查燃烧器和烟风道的安装是否符合标准;检查烟风系统和制粉系统的严密性;对锅炉机组中的风烟、燃烧系统有关测点进展检查,并对一次风和二次风的测量元件进展标定;检查并调平每台磨组出口4根一次风管的风速;冷态模拟炉内燃烧动力工况,观察一次风喷口射流情况和炉内空气动力状况,为下一步整个锅炉燃烧调整提供依据,确保锅炉燃烧充分,从而到达平安、经济运行的目的。
2 编制依据2.1 ?火力发电建立工程启动试运及验收规程?〔DL/T5437-2021〕;2.2 ?火电工程启动调试工作规定?〔建质[1996]40号〕;2.3 ?火电工程调整试运质量检验及评定标准?〔建质[1996]111号〕;2.4 ?电力建立施工及验收技术标准〔锅炉机组篇〕?;2.5 ?防止电力生产重大事故的二十五项重点要求?〔国电发[2000]589号〕2.6 ?电力建立平安安康与环境管理工作规定?〔国家电网工[2019]168号〕2.7 ?锅炉启动调试导那么?DL/T852-2019;2.8 ?新疆天富东热电联产技改工程2×135MW机组调试大纲?;2.9 设计院有关锅炉专业的图纸。
3 设备及系统简介3.1 锅炉概括本工程装设3台由四川川锅锅炉制造的CG-480/9.81-M4型高温高压自然循环汽包、单炉膛四角切圆燃烧、平衡通风、固态排渣、全钢构架紧身封闭、管式空预器、悬吊煤粉锅炉。
燃烧及制粉系统采用中速磨正压冷一次风机直吹式制粉系统,每台锅炉配4套中速磨煤机,脱硫采用生石灰半干法烟气脱硫工艺,预留烟气脱硝系统。
3.2 制粉系统本期工程制粉采用正压直吹冷一次风机制粉系统,每台锅炉配4台中速磨煤机,其中1台备用。
烧结余热发电工程锅炉整套调试方案
烧结余热发电工程锅炉整套调试方案一、调试目标:1.验证锅炉烧结余热发电的性能指标,确保其达到设计要求;2.测试锅炉各部分的运行情况,排除潜在故障和问题;3.调整锅炉参数,达到最佳的运行效果;4.确保锅炉安全可靠地运行。
二、调试内容:1.检查各部分的设备安装和接线情况,确保无疏漏或错误;2.检查各部分系统的润滑和冷却水系统;3.检查辅助设备和仪表的安装和接线情况,确保工作正常;4.检查锅炉燃烧器和炉膛的结构和材质情况;5.检查锅炉烟道和烟气处理系统;6.进行燃烧系统的调试,包括燃烧器效率、燃烧稳定性等;7.调整锅炉参数,包括供水温度、蒸汽压力等;8.进行锅炉的启动和停机测试,检查各个传感器和控制器的运行情况;9.对发电机进行调试,包括额定负荷运行和过载运行等;10.测试锅炉的热量和烟气排放等性能指标,检查是否达到设计要求;11.进行安全保护和应急措施的测试,确保在故障情况下锅炉能正常停机。
三、调试步骤:1.检查设备安装和接线情况,确保无错误;2.检查润滑和冷却水系统,确保工作正常;3.检查辅助设备和仪表,确保工作正常;4.检查燃烧器和炉膛的结构和材质;5.检查烟道和烟气处理系统,确保工作正常;6.启动锅炉,进行燃烧系统调试,调整燃烧器效率和稳定性;7.根据设计要求调整锅炉参数,包括供水温度、蒸汽压力等;8.进行锅炉启动和停机测试,检查传感器和控制器运行情况;9.调试发电机,进行额定负荷和过载测试;10.测试锅炉的性能指标,包括热量和烟气排放等;11.测试安全保护和应急措施,确保在故障情况下正常停机。
四、调试方案:1.确定调试团队,包括设备供应商、工程施工方和用户代表;2.确定调试计划和进度,分配任务和工作重点;3.制定调试标准和要求,确定性能指标和安全保护措施;4.组织人员和资源,准备调试所需的工具和设备;5.按照调试步骤和方案,逐步进行调试工作;6.记录和分析调试数据,及时发现和解决问题;7.根据调试结果进行调整和优化,确保锅炉达到设计要求;8.培训操作人员,确保他们熟悉锅炉的运行和维护。
余热锅炉调试方案
发电三期CCPP 大修后余热锅炉的调试方案一、检修后的检查1.锅炉机组检修后,运行人员应按本规程的有关规定对设备进行重点检查。
2.外部检查2.1工地安装接口必须仔细检查以确保安装的正确,必要时验证安装接口是否满足膨胀的要求。
2.2检查烟气挡板和挡板的穿孔处,侧墙的烟气挡板应部分遮蔽至外侧管子的翅片,穿过集箱挡板的管线盖板允许管线向下热膨胀,同时不会损坏挡板装置。
2.3外部绝热层完好,炉墙板应无或只有很小变形。
2.4支柱及加强筋与炉墙板的焊缝应合格且无裂纹迹象。
2.5现场接口应正确安装且施密封焊。
2.6检查门开关灵活,垫圈应处于良好的状况并正确安装。
如果检查门垫圈安装正确,则可多次使用门应用螺栓把紧,使密封表面受压均匀。
2.7钢结构的柱脚、地脚板、灌浆及墩子应处于良好状态。
检查地脚板、限位板、汽包支座之间的缝隙尺寸包括热膨胀所需的尺寸。
2.8检查所有的外保温和人身保护网已安装。
3.烟气侧的检查3.1护板衬里①在能够见到保温的地方检查其弯曲、过紧或过松情况。
②检查脱离保温钉被置换的衬板。
③在能够见到保温的地方检查大于25mm 的间隙。
④检查过渡点(膨胀节、现场结合部分)的间隙。
⑤检查暴露的或未见的保温。
⑥检查损坏的螺栓、垫片、保温钉和其他五金。
⑦检查不正常数量的腐蚀,对冷端衬里给予特别关注。
3.2护板贯穿①检查可见密封的泄漏(烧损、裂纹、撕裂)。
②检查排气和排水管线是否有碍,并留有热膨胀的余量。
③检查非正常量的腐蚀(内部和外部)。
3.3烟气挡板①检查烟气挡板是否可靠(夹住的和焊住的)。
②检查是否有间隙导致烟气旁路。
③检查管子和挡板的热膨胀是否受到阻碍。
4.管夹检查有没有丢失或损坏。
5.隔音挡板①检查所有隔音板被有效支撑。
②检查有没有由于热膨胀引致的缠绕或干涉现象。
③检查有没有由于隔音板导致的翅片或管子的损坏。
6.联箱吊架检查所有板、杆和焊缝良好。
7.仪表①检查防护罩完好。
② 查有没有影响热点偶精确读数的因素(例如污垢或护罩上有外部杂质)。
- 1、下载文档前请自行甄别文档内容的完整性,平台不提供额外的编辑、内容补充、找答案等附加服务。
- 2、"仅部分预览"的文档,不可在线预览部分如存在完整性等问题,可反馈申请退款(可完整预览的文档不适用该条件!)。
- 3、如文档侵犯您的权益,请联系客服反馈,我们会尽快为您处理(人工客服工作时间:9:00-18:30)。
锅炉启动、调整、试验方案(TG80/3. 82-M5)内蒙古佳辉硅自备电厂2013年1月目录1.前言2.设备概况3.启动前的检查,准备4.锅炉水压试验5.转动机械试运行6.漏风试验7.鉴定风机岀力,连锁试验,事故按钮8.锅炉冷态试验9.锅炉烘炉10.锅炉煮炉11 •蒸汽吹管12.蒸汽系统严密性试验13.安全门整定14.机组满负荷试运15.反事故措施16.组织分工17.调试期间所需工器具1.前言内蒙古佳辉硅化工有限公司投资新建的发电厂锅炉是太原锅炉厂制造的型号为TG80/3.82—M5型循环流化床锅炉,为搞好本锅炉的调整试验工作,为锅炉运行提供最佳运行工况数据,保证今后的安全稳定运行,特编写《锅炉启动、调整、试验方案》,本方案经启动指挥部批准后方可实行。
2 •设备概况2・1本锅炉采用单锅筒,自然循环,膜式壁炉膛,前吊后支, 全钢架兀型结构,电布联合除尘。
锅炉布置在厂房内。
2.2循环流化床锅炉燃烧室内飞灰浓度极高。
因而炉内需要良好的密封和防磨性能。
本炉采用了膜式壁结构。
2.3锅炉燃烧室所需的空气由一、二次风机提供,一、二次风比及煤种有关。
大致分为6 0:4 0, 一次风经空气预热器引入预热后,进入水冷风室中通过安装在水冷布风板上的风帽进入燃烧室,保证流化质量和密相区的燃烧。
二次风经空气预热器预热后,由前、后墙的二次风口进入炉膛,补充燃烧所需空气并加强扰动混合。
燃煤经三台刮板式给煤机及一次风混合播撒吹散进入炉膛。
燃煤在炉膛内燃烧产生大量的烟气和飞灰,烟气携带大量未燃尽的碳粒子在炉膛上部进一步燃烧放热后,进入分离器,烟气和物料分离,被分离岀的物料经料斗、料腿、J型阀返回炉膛,实现循环燃烧。
烟 气经转向室进入高温过热器、低温过热器、省煤器、预热器、 电袋除尘器、经引风机排出烟囱。
燃煤经燃烧后形成的粗渣 由炉底部放渣管排岀。
2・4锅炉给水经省煤器加热后进入汽包,汽包内的饱和水经 集中下降管,分配到水冷壁下集箱,经上升管加热后进入上 联箱,然后进入汽包,经主汽阀送入汽轮机。
2・6、锅炉规范 2.6.1技术规范氧 Oy % 1 0 . 1 0氮 Ny % 0.80锅炉额定蒸发量 t / h 8 0锅炉额定蒸汽压力 M p a 3 . 8 2锅炉额定蒸汽温度 °C 4 5 0汽包给水温度 °C 1 0 5锅炉连续排污率 % 2排烟温度 °C 1 3 3锅炉计算热效率 % 90.96燃煤粒度 mm 0 — 86・2燃料选择及特性指标燃料选择 中煤+肝石燃料特性(应用基)碳 6 % 4 7.8氢 Hy % 2.502 .硫Sy% 0.60灰分Ay% 19.45水分My% 18.75可燃基挥发物Vy% 3 9.06低位发热量Qdw y KJ/KG 4137大卡/公斤3、启动前的准备、检查3.1、锅炉安装后期,应组织全体人员对安装的设备、系统进行其构造、规范、特性、介质走向的熟悉,并按有关规定进行全面系统的检查。
3.2、检查锅炉本体及烟道内部321、水冷壁管、过热器管、省煤器管及空气预热器的外形应正常,内部清洁,还应对照有关图纸、有关技术资料,检查所有防磨部位,主要有沸腾层,分离器内防磨,过热器,省煤器的防磨盖压板及防磨罩。
空气预热器防磨导管是否达到图纸及有关技术资料的要求。
3.2.2检查烟气发生器内浇注料是否光滑,风室内耐火混凝土敷设是否光滑完整,风门应有正确标注开关方向。
323检查烟气发生器内是否有杂物,如有应清除干净,排渣管应清洁干净畅通,挡板开关灵活,并便于操作,水冷放渣管进、出水管连接是否正确,并进行通水试验。
324、检查和清理燃烧床,首先是风帽安装位置是否正确,风帽高低是否恰当,风帽及布风板应基本垂直,风帽出入口应无异物,床面耐火材料及炉膛四周防磨浇注料不应有裂纹等缺陷。
3.2.5检查分离器及炉膛四周防磨浇注料的安装质量是否达到要求,分离器是本炉的关键,直接影响锅炉的出力,效率以及运行寿命,特别要注意分离器入口,返料器中间隔墙及四周的施工质量,应达到下列要求:3.2.5.1涂层厚度不低于图纸规定尺寸。
3.2.5.2涂层平整、交界处应平滑过渡。
3.2.5.3防磨层及受热面不得有脱层的现彖。
3.2.5.4养护后不得有大于3mm的裂纹,更不应有脱离金属的现象。
v>326检查返料灰斗及回料腿,保温砖,耐火砖,浇注料的安装要求平整,灰斗及回料阀J型阀内送风管安装位置应正确,小孔应畅通,放灰挡板开关应灵活且方便操作,阀后压力表应安装就位,便于观察。
327检查风道、烟道挡板门的调节是否灵活可靠,开关位置是否正确,传动电控装置是否良好。
3.2.8检查各部炉墙,有效的堵塞所有的漏缝,以确保密封质里。
329检查所有人孔门,检查门等是否完好;开关是否到位。
3.2.10平台、扶梯上应无妨碍行走的杂物和垃圾。
脚手架等安装附件等应及时清除,井、坑、孑L、洞应有盖板、围栏。
短期不能解决的应设临时围栏等,并树标示牌,以便告示、警戒。
3.3锅炉汽、水系统阀门、仪表的检查。
331锅炉就地水位计汽、水阀门开关灵活,安装位置及标尺正确,汽水管道保温良好。
水位计照明充足,安装位置得当。
3.3.2汽、水压力表,表盘清晰,汽包、过热器压力表在压力范围应划有红线且照明充足。
3.3.3安全阀的排气管和输水管完整,畅通,定压螺丝,弹簧良好,并适当压紧,并装有防止烫伤人员的防护罩。
334膨胀指示器完整,刻度正确,清楚。
全板的基准点上涂有红点标记,指针应及板面垂直,指针移动不得被外物卡住, 针尖及板面距离3-5mm,锅炉冷态时,指针应在基准点。
3.3.5操作盘,压力、温度等仪表齐全、完整好用。
3.3.6汽、水管道各手动阀,电动阀、调整阀,手轮完整,固定牢固,门杆清洁,无弯曲及锈蚀现象,开关灵活,阀门的填料处应用适当的压紧间隙,主要阀门保温良好。
传动装置的连杆,接头完好,各部销子牢固。
各阀门有完整的指示牌, 名称,编号,开关方向,位置指示及实际一致。
3.4给煤系统检查3.4.1原煤斗斗壁是否光滑,内部应通畅,无杂物,严密不漏。
342给煤机传动链条松紧度适中,下煤挡板开关灵活。
3.4.3给煤机刮板安装正确,转动灵活。
3.5转动机械的检查(考试)3.5.1所有安全围栏,保护罩完整牢固,靠背轮连接完好。
3.5.2地基地脚螺丝不松动,轴承内润滑油洁净,油位计完整, 指示正确,油位线清晰,结合面不漏油。
3.5.3冷却水畅通,并试投冷却水,判断冷却管是否漏。
3.5.4电动机符合《电动机运行规程》的有关规定。
3.5.5调整挡板和传动装置,拉杆销子完整、无脱落,并进行就地手动试验。
3.5.6转机周围无妨碍转动的异物,转动设备处照明充足,明亮3.6燃油点火系统的检查。
3.6.1点火油枪就位,配件齐全。
3.6.2燃油罐应有足够的储油量,并配有足够的消防器材,燃油管道保温良好。
363连接软管齐全,并能随时投入。
3.6.4并有观察着火的看火实施,备有合适的点火把。
3.6.5油管路应提前进行蒸汽或压缩空气的吹扫。
应保持油管路无杂物。
3.7现场照明充足,明亮,安全设施应完善,特殊部位有明显的指示牌。
3.8锅炉房配备有足够的合格的消防器材。
4、锅炉水压试验,v>4.1锅炉承压部件经过安装后,须进行水压试验,用以检查在冷状态下受热面,汽水管道及阀门的严密性。
4.2锅炉水压须做超压试验,其压力为工作压力的1.25倍,即4.8mpa。
4.3水压试验的锅炉其汽水系统必须及其他系统隔离。
除给水,蒸汽压力表门开启外,其它阀门全部关闭,炉内如处于上水阶段,各处空气门应开启。
4.4水压试验时(超压)应做好防止安全门动作的措施。
4.5室内温度不得低于5°C,低于5°C确需水压试验必须做好防冻措施。
4・6锅炉水压试验前的检查及准备工作完毕后,可向锅炉上水,锅炉从无水到上满水冬季不少于4小时,夏季不少于2 小时。
上水温度有条件可控制在20°C——70°C为宜。
水压前后各纪录膨胀指示一次。
4・7锅炉充满水,空气门冒水后关闭。
4. 8做锅炉超压试验时必须解列就地水位计。
4. 9锅炉升压时,需用给水小旁路门控制上水量,升压速度控制在工作压力为0. 1—0. 3M pa/min,超高压为0. lM pa/min, 并有防止超压的措施。
4・10当压力升至工作压力时,应维持压力稳定,进行全面检查,无异常后,继续升压至超高压试验压力,保持20分钟, 降压至工作压力后进行全面检查。
4. 11停止上水后,确证无漏水和阀门渗漏,压力下降值不超过0. 5Mpa/5min o4.12承压部件及焊口部位无漏水,及湿润现彖,承压部件无残余变形。
5.转动机械试运行5.1安装后的转动机械必须经过试运行,鉴定安装是否符合要求,以验证转机工作的可靠性。
5.2试运设备确已安装完毕,无妨碍转动的杂物,场地干净, 照明充足。
5.3地脚螺丝紧固无松动,保护罩和安全围栏齐全,固定牢固。
5.4油位计完整不漏油,最高,最低油位线表示清晰,润滑油质符合标准。
15OOr/min以下的机械装油量基本在整个轴承室容积的2/3,15OOr/min以上的装油量基本在整个轴承室容积的1/2.5.5电动机的冷却通风装置良好,无堵塞,电动机接地良好。
转机轴承冷却水畅通,水量充足。
5.6转机事故按钮完好,并附有防止误操作的保护罩。
5.7电动机应单独试转,检查电动机方向是否正确,并验证事故按钮的可靠性。
5.8带负荷的第一次启动须在静止时盘动联轴器检查是否有异常声音。
5.9新安装的转动机械应进行不少于带负荷8小时的连续运行。
5.10试运行期间,轴承及转动部分无异常现象,各部无异常现象,各部无漏油和漏水,滚动轴承温度不超过80°C滑动轴承温度不超过70°C震动不超过0.10mm(合格),窜轴不大于2— mmo6.漏风试验6.1安装后的锅炉机组投产前应在冷态下进行燃烧室,风道, 烟道,预热器,电除尘及所有孔门。
挡板严密性的试验,找出漏点予以消除。
6.2启动引风机维持炉膛负压在200pa以上,用火把靠近接缝、炉门等可能漏风处,若漏风则火光会被负压吸向不严密处,将漏风处做记号,及时消除。
6.3空预器,风道,风挡板采用正压试验方法。
6.3. 1启动引风机,调整入口挡板,保持炉膛50-100pa负压,关闭预热器出口风道上的总风门。
6.3.2将一二次风机入口挡板及各风门全部关闭,分别启动一二次风机,观察其启动时间和电机运行电流。
然后缓慢开大一二次风机入口挡板,观察电动机电流变化情况,如果此时电动机电流及空转时电流相等或接近时,则表明一、二次风机起经空预器到风门止,这段区域的送风严密不漏,如果电流增大较大,则系统有漏风处,应仔细检查,予以消除。