储罐充水试压方案

Tank Hydro-test Plan

2 2012年11月1日

Nov. 1, 2012

版次Edition 日期

Date

编制

Formulated

by

审核

Reviewed by

批准

Approved by

中国化学工程第十三建设有限公司

The 13th Construction Co., Ltd. of CNCE

储罐充水试压方案

Tank Hydro-test Plan

目录Contents

2

3

3

3

4

5

5

6

八人力计划VII. Planning for Labor Forces (18)

九机具准备VII. Preparations of Machines and Tools (18)

十工作危险源分析评估及预防Work-related Hazard Analysis Evaluation and Prevention (19)

一.适用范围Range of Application

1.本方案适用于塞拉尼斯(南京)乙酰基中间体有限公司工业乙醇项目八期改造扩建罐区4台储罐的充水试验的施工。This plan is applicable to the execution of the hydro-test for 4 tanks in the modification and expansion of the tank farm of Celanese China Fast Project.

二.编制依据Formulation Basis

1) 《钢制焊接常压容器》Steel Welded Atmospheric Pressure Vessels JB/T4735-1997

2) 《立式圆筒形钢制焊接油罐施工及验收规范》Code for Construction and Acceptance of Welded

Steel Oil Tank of V ertical Barrel Shape GB50128-2005

3) 《石油化工钢储罐地基与基础施工及验收规范》Specification for Construction and Acceptance of

Steel Storage Tank Subgrade & Foundation in Petrochemical Industry S H3528-93

4) 《大型焊接低压储罐设计与建造》Design and Construction of Large, Welded, Low-pressure Storage

Tanks API620-2009

5) 塞拉尼斯技术要求及相关过程规定Celanese technical requirements and related process regulations 三.工程概况General

序号No. 位号

Item

名称

Descrip

tion

规格Spec.

设备净重

Net

weight of

equipment

(t)

Weight

after

water

filling充

水后重

(t)

water

(m3)

设计压力Design

pressure Mpa

Filling

height充

水高度

(m)

1 V-73

2 产品罐

Product

tank

φ10795*9750763

2 V-73

3 产品罐

Product

tank

φ10795*9750763

3 V-74

4 倒液罐

Off-spe

c tank

φ10795*9750763

4

V-737

清洗罐Cleanin g tank

Φ8660*9750

488

四.施工工序Construction Procedure

施工准备

资料审查

试验系统建立

设备实体检查

上水条件确认

封 孔

上水

强度、严密性试验

放 水

罐体检验

沉 降 观 测

Preparations

Document review

Setup of test system

Physical examination of Equipment

Confirmation of filling condition

Sealing

Water filling

Intensity and tightness test

Settlement observation

Tank shell check

Water draining

五.施工步骤及方法Construction Procedure and Method

储罐已制作完成,且具备水压试验条件,充水试验前应对罐体进行联合检查,罐体无损检测机所有配件、附件安装检测完毕检查合格后对罐体内进行清扫封闭人孔等,开始充水,进行充水试验。充水过程中充水试验要求与土建基础沉降观测结合起来,设置专人对进水和放水时间进行监控,发现异常情况应及时处理,处理合格后方可继续上水。充水试验结束后,罐体内的水应按业主要求和排放位置及时排放。Before the hydro-test, the tank shell shall be jointly inspected. After NTD of the tank shell, and all fittings and accessories are installed, tested, inspected and accepted, clean the tank inside and close the manhole, fill water and take the hydro-test. During water filling, the hydro-test requirements shall be combined with the civil structure foundation settlement observation, personnel shall be specially assigned for monitoring the filling and draining time, any abnormality shall be treated in time, no water can be filled in before the treatment is accepted. After completion of the hydro-test, the water in the tank shell shall be promptly drained according to the owner’s requirements and the location for draining.

5. 1储罐制造完毕后,进行充水试验,并检查下列内容:Hydro-test will be taken after the tank is finished in fabrication, and the following content

shall be checked:

1)罐底严密性。Tightness of the tank bottom

2)罐壁强度及严密性。Strength and tightness of the tank shell

3)固定顶的强度及严密性。Strength and tightness of the fixed roof

4)固定顶的稳定性。Stability of the fixed roof

5)基础的沉降观测。Settlement observation for the foundation

压力试验前,首先做好以下准备工作:The following preparations shall be made before the pressure test:

1)检查罐外形尺寸、附件安装是否符合要求。Check if the tank outline dimension and accessory installation satisfy requirements.

2)充水前将罐内杂物清理干净后进行封闭,罐壁上的接管均用临时盲板封闭,人孔用人孔法兰盖封闭。Before water filling, clean out sundries in the tank and close it, close the nozzle on the tank shell with temporary blind, and close the manhole with the manhole flange.

3)检查罐管口、法兰是否已焊接完,是否有漏焊部位。Check if the tank nozzle and flange are finished in welding, and if the welding on any part is missed.

4)接管补强圈用压缩空气气密工作已做完,且合格。The airtight work of the compressed air used for the nozzle reinforcing ring has been completed and qualified.

5)水源采用消防储罐的低压消防水,压力为。The water is sourced from the low pressure fire water of the fire tank, and the pressure is .

6)沉降观测,储罐选定4个沉降观测点。Settlement observation: 4 settlement observation points are selected for tanks.

7)完成罐充水前沉降观测点和基准点的设置,并测量0水位时各测点的标高。Set up settlement observation points and reference points before water filling for the tank, and measure the elevation of every measuring point when the water level is 0.

8)碳钢储罐试验应采用洁净水,试验用水温不低于5℃。The CS tank test shall adopt clean water, and the water temperature used for the test shall not be lower than 5℃.

9)V-737不锈钢储罐试验用水氯离子含量不得超过25mg/L。The content of the chloride ion in water used for V-737 SS tank test shall not be more than 25mg/L.

10)完成罐充水前沉降观测点和基准点的设置,并测量0水位时各测点的标高。Set up the settlement observation point and the reference point before water filling for the tank, and measure the elevation of every measuring point when the water level is 0.

充水试验应符合下列规定:The hydro-test shall be in compliance with following regulations:

1)充水和放水过程中,打开放空孔,基础避免浸水。During water filling and draining, open the 2)充水时严格控制上水、停水的进程,随时检查水位。During water filling, strictly control the process of water filling and water cutoff, and check the water level any time.

3)当第一台储罐进行充水试验时,应充水时快速充水到罐高的1/2,进行沉降观测,当不均匀沉降量小于5mm/天时,继续充水到罐高的3/4进行观测,当充水到(设计液位—1米)进行正压试验,当不均匀沉降量仍小于5mm/天时,继续充水到最高操作液位,并保持48小时后进行观测,当沉降量无明显变化即可放水,放水时做负压试验,当沉降量有明显变化,则保持最高操作液面,每天进行定期观测,直至沉降稳定为止。When the hydro-test is taken for the first tank, the water shall be quickly filled to the point of 1/2 of the tank height during water filling, observe the settlement, when the unequal settlement is still less than 5mm/day, go on filling in water to the point of 3/4 of the tank height for observation; when the unequal settlement is still less than 5mm/day, go on filling in water to the highest operating level, and observe it after maintaining 48hrs, if the settlement doesn’t obviously change, the water can be drained, if the settlement obviously changes, keep the highest operating level, and observe it regularly every day, until the settlement is steady.

4)当第一台储罐罐基沉降量符合要求后,其余各罐充水试验时可取罐高的1/2和3/4进行两次观测。After the foundation settlement of the first tank meets requirements, when the hydro-test is taken for the rest tanks, the settlement will be observed twice respective at the point of 1/2 and 3/4 height of the tank.

5)基础沉降观测早、晚各观测一次,每次的沉降数据做好统计,并描绘出基础沉降变化图,便于分析。

罐基础沉降允许值(均匀沉降值)Allowable value of the tank foundation settlement (equal settlement value)

储罐位号Tank No. 罐内径(mm)

inner diameter

of tank

任意直径方向最终沉降差允许值(mm)

Allowable value of the final settlement

difference in any diametrical direction

V-732 10668 160mm

V-733 10668 160mm

V-744 10668 160mm

V-737 8534 128mm

Floating roof tank and inner floating roof tank Fixed roof tank

Inside diameter of tank

D(m)

Allowable value of the

final settlement

difference in any

diametrical direction

Inside diameter of tank

D(m)

Allowable value of the

final settlement

difference in any

diametrical direction 水压试验示意图:Hydro-test Diagram

φ108*6

φ108*6

消防带fire hose

储罐tank

另一台储罐

another tank

阀Valve 3

压力表pressure gauge

● 在罐区内的泡沫消防临时接入处,用临时管线(φ108*6)接到储罐泡沫降落

槽接口上;Connect the temporary pipe (φ108*6) to the access of the tank foam descending groove at the temporary access of foam fire-proof in the tank farm. ● 按上图所示建立试压系统;Establish the pressure test system according to the

above diagram.

充水过程检查:Inspection for Water Filling Process

1)进水时专人看守进水阀门,严格控制水源大小,同时找专人通过U 型计

观察储罐实际充水量并与进水人员配合,过程为1/2液位高度→3/4液位高度 →满水高度-1米→满水高度

The secure water when the inlet valve, strict control of water the size of, at the same time to find someone through the U-meter Observe the the tanks actual charge water and influent personnel with the process for the liquid level of the liquid level → 1/2 3/4Heigh t -1 m → → full of water full of water height

2)充水试验中应加强基础沉降观测,如基础发生不允许的沉降,应停止充水,待处理后,方可继续进行试验。Do intensify settlement observation during the hydro-test, if unallowable settlement arises from the foundation, the water filling shall top, and do not go on the test before treatment.

3)充水和放水过程中应打开罐顶人孔Do open the manhole on the tank roof during the process of water filling and draining.

4)充水过程中应控制水的流速,水面上升的速度应不超过h 。Do control the flow speed of water during water filling, and the speed of water surface ascent shall not exceed h. 5)上水过程中在最高设计液位的50%和75%进行罐体检查。During water filling, check the tank body at the point of 50% and 75% of the highest design level.

临时管线接入口Temporary pipe access

Φ108×6

阀1 阀Valve 4

充水试验方法:Hydro-test method:

1)罐底的严密性,应以充水试验过程中罐底无渗漏为合格,若发现渗漏,应

放水后进行检查补焊。Tightness of the tank bottom: if the tank has no leakage during the hydro-test, it is acceptable, in case of any leakage, it shall be inspected and welding-repaired after water draining.

2)罐壁的强度及严密性试验,应以充水到设计最高液位并保持48h后,罐壁

无渗漏、无异常变形为合格,发现渗漏时应放水,使液面比渗漏处低300mm

进行修补。Strength and tightness test for the tank shell: if the tank shell is free of leakage, abnormality and deformation after the water is filled to the highest design level and maintains 48h, it is acceptable, in case of any leakage, the water shall be drained to make the water level 300mm lower than the leakage.

3)固定顶的强度及严密性试验,打开阀门1,关闭阀门2,通过消防带从罐顶部进行上水,在上水至设计液面高度下1米处时,用盲板封堵所有开孔,缓慢调节阀门1,缓慢上升,升压至试验压力()时,停止充水,进行固定顶强度及严密性试验,在罐顶涂以肥皂水检查,试验后应立即将罐顶孔开启,与大气相通,恢复到常压;Strength and tightness test of the fixed roof: open Valve 1, close Valve 2, and fill water from the tank top through the fire hose, when the water is filled to the point of 1m lower than the design level, block all openings by blinds, slowly regulate Valve 1, the pressure slowly rises, when the pressure rises to the test pressure , stop filling water, and conduct the strength and tightness test for the fixed roof, apply soapy water on the tank roof for inspection, and do open the tank roof hole immediately after the test, so as to contact the atmosphere and recover to normal pressure.

4)固定顶的稳定性试验,充水到设计最高液位时,用盲板封堵所有开孔,打开

阀门4、3,用放水方法进行固定顶的稳定性试验,缓慢降压,达到试验负压()时,观察罐顶(罐顶无异常变形为合格),试验后应立即将孔开启,与大气相通,恢复到常压;固定顶储罐在充水到8754mm液位前,应打开顶部人孔。Stability test for the fixed roof: when the water is filled to the highest design level, block all openings with blinds, open Valve 3 and Valve 4, conduct the stability test of the fixed roof by water draining, depressurized it slowly, when it is up to the test negative pressure , observe the tank roof (it is acceptable if the tank roof is free of abnormality and deformation), do open the hole immediately after the test, so as to contact the atmosphere and recover to normal pressure. The roof manhole shall be opened before the water in the fixed roof tank is filled to the level 8754mm.

试验项目Test item 试验方法Test method

合格标准Standard of

acceptability

罐底严密性tightness of tank bottom 充水试验,观察基础周边。Hydro-test,

observe the periphery of the foundation.

无渗漏为合格It is

acceptable if no

leakage.

罐壁强度及

严密性试验strength and tightness test for tank shell 充水至最高设计液面,保持48h。Fill

water to the highest design level and

maintain 48h.

无渗漏、无异常变形为

合格It is acceptable if

no leakage or

abnormality.

固定顶强度及严密性试验strength and tightness test for the fixed roof 罐内充水到最高设计液位下1m,将所

有开孔封闭,缓慢充水升压,当升至

试验压力时,暂停充水,在罐顶涂以

肥皂水检查,试验后应立即将罐顶孔

开启,与大气相通,恢复到常压When

the water in the tank is filled to the

point of 1m lower than the design level,

block all openings by blinds, slowly fill

water and boost pressure, when the

pressure rises to the test pressure,

suspend the filling of water, apply

soapy water on the tank roof for

inspection, and do open the tank roof

hole immediately after the test, so as to

contact the atmosphere and recover to

normal pressure.

a)罐顶无异常变形

The tank roof is free of

abnormality and

deformation.

b)未发现焊缝渗漏为

合格It is acceptable if

no leakage of welded

joints is found.

固定顶的稳定性试验充水到设计液位时,用放水方法进行

罐顶无异常变形The

tank roof is free of

stability test for the fixed roof 试验,缓慢降压,达到试验负压时,

观察罐顶,试验后应立即将孔开启,

与大气相通,恢复到常压。When the

water is filled to the design level,

conduct the test by water draining

method, depressurize it slowly, when it

is up to the test negative pressure, do

open the hole immediately after the test,

so as to contact the atmosphere and

recover to normal pressure.

abnormality and

deformation.

5)当考虑水的重复利用,第一台罐水压试验完毕后,缓慢打开阀3,将水直接排到第二台罐里,待两罐水位平衡后,关闭阀2,然后利用消防带进行上水;In view of recycling of water, after the first tank is finished in the hydro-test, slowly open Valve 3, directly drain the water to the second tank, after the water level in the two tanks is balanced, close Valve 2, and then fill water with the fire hose.

基础沉降观测Foundation Settlement Observation

1)根据储罐的体积和直径,确定储罐沉降观测的点数,见下图。Make sure the number of tank settlement observation points according to the volume and diameter of the tank, see the following drawing.

2)四台储罐分别选好基准点为控制点。Reference points are respectively selected for the four tanks as control points.

3) 空罐(上水前,第一次)→1/2液位高度(第二次)→3/4液位高度(第三次)→满水高度(1小时第四次)→满水高度-1米(第五次)→满水高度(48小时后,第六次)→空罐(放水后,第七次)

Empty tank (before water filling, the first time) →1/2 water level (the second time) →3/4 water level (the third time) →full water level (1hr, the fourth time)→full water level (after 48hrs, the fifth time)

→empty(after water draining, the sixth time)

4) 水压试验过程中,应紧密跟踪罐体每次的沉降量,检查其是否符合规范允许值。During the hydro-test, closely track the settlement of the tank body every time, and check if they satisfy the specified allowable value.

5)储罐基础沉降允许值:充水高度为:H/2(H为罐高),沉降量<5mm/d,充水高度为:3H/4,沉降量仍<5mm/d,充水到最高液位后,保持48h观测,总沉降量< value of the tank foundation settlement: the water filling level: H/2 (H is the height of the tank), the settlement <5mm/d, the water filling height is 3H/4, the settlement<5mm/d, after the water is filled to the highest level, observe it for 48h, and the total settlement <25mm.

6)为方便测出罐内液位的实际高度,从罐壁管口上接出一临时阀门,并将软管接从低接管接到罐顶,为防止塑胶管滑落,采用柔性材料将其临时绑扎到脚手架靠里侧。In order to measure the actual height of the water level in the tank, extend a temporary valve from the tank nozzle, and connect the hose to the tank roof from the lower nozzle, in order to prevent plastic pipe from sliding, bind it to the inner side of the scaffold temporarily with flexible material.

放水检查Inspection for Water Draining

1) 放水停留时间应符合土建专业设计文件的要求Water draining detention time shall be in

compliance with the requirements of design documents of the civil work discipline.

2) 储罐试压完毕后,放水应排放到指定位置(罐区围堰内部排水沟),不可就地排放使基

础浸水;After the tank pressure test is finished, the water shall be drained to the specified position, and cannot be drained locally for fear of foundation soaking.

3)罐内应彻底地进行清扫,除去锈蚀,底板不应有显著的变形和明显凸凹,各附件应符合图样要求,且无异常现象。The tank shall be completely cleaned, rust shall be removed, and bottom plates shall be free of significant deformation and obvious unevenness, all accessories shall be in compliance with drawing requirements, and be free of any abnormality.

4)放水后及时将罐内的积水和杂物清扫干净,应打开所有的管口和人孔,以加强罐内的空气流通,当罐内水吹干后,及时检查,并用抹布清除干净罐内的水渍。Clean up accumulated water and sundries in the tank in promptly after water draining, all nozzles and manholes shall be opened, so as to strengthen ventilation in the tank, after the water in the tank is dried, inspect it in time and remove water stain in the tank with rags.

试压技术要求Technical Requirements for Pressure Test

1.一般要求general requirements

1)试压工作开战前,施工技术人员必须对参加试压的所有人员进行技术交底,安全交底,严格 遵守安全纪律和操作规程。Before start of the pressure test, technical personnel of construction shall give technical and safety presentation to all pressure test participants, and abide by safety disciplines and operating regulations strictly.

2)划定危险区,并安排人员负责警戒,禁止无关人员进入。Divide dangerous zones, and arrange persons to be responsible for alert, and no entry for unrelated personnel. 2.试验时的要求test requirements

1)水压试验时,严禁对罐身、接口进行敲打或修补缺陷,严禁带压修理,泄压后再进行修补, 缺陷消除后重新试压。During the hydro-test, neither knock the tank body or nozzle nor repair defects, repair with pressure is prohibited, and no repair before pressure release, repeat the pressure test after removal of defects.

2)罐顶稳定性试验时,确保安全装置良好。During the stability test for the tank roof, ensure the safety device is good.

3)负责降压的操作人员必须控制升压的速度,进水,泄压注意防空。Operators who are responsible for reducing pressure must control the speed of boosting pressure, water inflow and pressure relief, and pay attention not to emptying.

4)水压试验后,试压用水必须由管道排放至指定地点,不得就地排放。After the hydro-test, the water used for pressure test shall be drained to the specified location through the pipe, do not drain it locally.

6. 质量管理Quality Management

质量保证体系Quality Guarantee Measures

1 项目经理部质量保证体系见施工组织设计。For the quality guarantee system of the project manager department, see the construction organization design please.

2 作业层质量保证体系。Quality guarantee system of the operation level

工程项目部

公司质

安部

质量保证体系

施工责任工程师

质量专职质检员

施工班组长(兼职质检员)

施工班组

Project Department QS De pt.

Quality guarantee system

Responsible Engineer of the

construction

Full-time Quality Inspector

Construction Shift Leader (Part-time Quality

Inspector)

Construction shifts

质量保证措施Quality Guarantee Measures

1)试验时每台储罐应装设1块压力表,1块真空表,试验压力以装设在设备最高处的压力表 读数为准。During the test, each tank shall be provided with one pressure gauge and one vacuum gauge, and the test pressure shall be based on the reading of the pressure gauge mounted on the highest point of

the equipment.

2)压力表须经校准,精度不低于级,量程为最大被测压力的~3倍。The pressure gauge should be calibrated, the precision shall not be lower than , and the measuring range is ~3 times of the greatest pressure measured.

3)有专人看护压力表,严禁超过规定的试验压力。Personnel shall be specially assigned to watch the pressure gauge, the test pressure against regulations is forbidden. 4)严格控制上水、进水、放水的过程,以避免超压或抽空。Strictly control the process of water filling, water inflow and water draining, so as to avoid overpressure or emptying.

七. 安全管理 X Safety Management

安全保证体系Safety assurance system

项目经理部安全保证体系见施工组织设计;For the safety assurance system of the project manager department, see the construction organization design please. 作业层安全保证体系;Safety assurance system of the operation level

工程项目部

公司质

安部

安 全 保 证 体 系

施工责任工程师

专职安全员

施工班组长(兼职安全员)

施 工 班 组

Project Department QS De pt.

Safety assurance system

↓↓

Responsible Engineer of the

Full-time Safety Inspector

construction

Construction Shift Leader (Part-time Safety

Inspector)

Construction shifts

安全保证措施计划Planning for safety assurance measures

一般要求:General requirements:

1 压力试验的各项准备工作必须经过我方质量部门的自检合格,安全工作经过

HSE经理同意后方可开始进行试压工作。All preparations for the pressure test

shall be self-inspected by our quality department and acceptable, and the pressure

test cannot be conducted before the safety work is approved by HSE manager.

2 所有参与压力试验人员要进行岗位分工,责任明确;All pressure test participants’

duty shall be divided with clear responsibility.

3 试压时用警戒绳将储罐圈出安全范围,无关人员不得擅自靠近,以防止突发事

故。During the pressure test, the alert rope shall be used to ring the safety range of

the tank, and unrelated personnel shall not approach without authorization.

4 试压时随时注意环境温度的变化,监视压力表的读数,防止发生超压现象。

During the pressure test, pay attention to the variation of the ambient temperature

any time, so as to avoid overpressure.

5 试压过程中,如发现有异常响声、压力下降或加压装置发生故障灯不正常现象

时,应立即停止试验,并查明原因。During the pressure test, in case of any

abnormal noise, pressure drop or abnormality arisen from the trouble light of the

pressurizing device, the test shall be immediately stopped and the reason shall be found out.

6 试验时,压力试验人员应尽量避免站在储罐接管出口方向。During the

test, the pressure test personnel shall try to avoid standing at the direction of the tank nozzle outlet.

7 各接管应用耐压大于试验压力的密封件密封,各连接件部位的紧固螺栓

应按规定的材料规格、数量装备齐全。严禁在试验过程中,带压紧固螺栓及其他紧固件。Every nozzle shall be sealed by the sealing element whose pressure

resistance is more than the test pressure, the fastening bolt on every coupling

position shall be completely provided according to specified specification and

quantity of materials. During the test, do not fasten bolts and other fasteners with pressure.

8 试验用电必须有专职电工,非专职电工不得擅自接电。The electricity used

for test must be operated by full-time electricians, and non-full-time electricians

shall not connect the power supply without authorization.

9 试验过程中,如发现有异常响声,停止试验,查明原因。During the test,

in case of any abnormal noise, please stop the test and find out the reason.

10 试验时,各部位的紧固螺栓必须装配齐全。During the test, fastening bolts

on every position shall be completely assembled.

11 压力试验时,不得带压进行任何修理和紧固工作。During the pressure

test, do not execute any work of repair and fastening with pressure.

12 压力试验时,严禁人正对着法兰侧面站着。During the pressure test, do

not stand right opposite to the side of the flange.

文明施工Civilized construction

1 凡参加施工人员必须熟知本工种安全操作规程,并严格遵守。All construction staff should know well about safety operation regulations of their work and strictly abide by them.

2 进入施工现场戴好安全帽,高空作业系好安全带。Wear safety helmets in case of entrance into the job site, and safety belts shall be appropriately worn at elevated work.

3 各施工机械必须专人看管,定期维修,保持施工机械处于良好状态。All construction machinery must be attended by specially assigned personnel, and maintained regularly, so that the construction machinery keeps in good condition.

5 施工现场的材料、机具、工具放置应整齐,保持清洁Materials, machines and tools

on the job site shall be neatly placed and kept clean.

八人力计划VII. Planning for Labor Forces

工程负责人Project Directors 1人

试压人员Lifting

worker

6人

技术员Technician 2人

普工Unskilled worker 4人

安全员Safety

Inspector

2人

焊工Welding workers 3人

测量工Measuring

worker

2人

九.施工机具Construction Machine and Tools

名称Description 规格Spec. 数量Quantity 焊机Welding machine 2台pieces

压力表座Pressure gauge

stand

带缓冲弯with loop 4件pieces 压力表Pressure gauge ~ 4件pieces

负压表Negative pressure

gauge

2件pieces 聚四氟乙烯带

polytetrafluoroethylene

tape

30卷rolls 消防带Fire hose 200 m

截止阀stop valve 4个pieces

软管hose 100m

扳手wrench 若干multiple

盲板blind 若干multiple

十.工作危险源分析评估及预防Work-related Hazard Analysis Evaluation and Prevention

序号No. 基本工序/工作步骤

Basic work

process/work step

确定的HSE危险Certain HSE dangers 预防控制措施Prevention and control measures

执行人

Executor

1 作业前召开安全会

Safety meeting

before work

N/A

1确保所有人员熟悉与储罐安装作业相关的程序文件。Ensure all personnel are

familiar with program files related with tank installation.

2保存记录。Keep records.

2 高空作业Elevated

work

1.操作平台及扶梯operating

platforms and staircases

2. 关/开储罐顶人孔manhole for

closing/opening the tank roof

1.完善安全防护设施,杜绝“三违”。Improve safety protection measures, and avoid

“three offenses”.

2.定期检查平台、栏杆等安全设施,保持完好状态。Inspect safety facilities

regularly, such as platform and railing, and keep in good condition.

3. 按规定穿戴好劳动防护用品。Wear PPE properly as specified.

4严格执行登高作业的制度。Perform the system of elevated work strictly.

5 六级以上大风、暴雨、雷电等情况停止高处作业Stop the elevated work in the

event of strong breeze in a force more than six, storm, thunder.

3 噪声危害noise

hazard

1.储罐进水tank water trapping

1.采用隔声、消声、吸声措施。Take measures of noise insulation, silencing and sound

absorption.

2.定期巡检,避免长时间停留。Take regular inspection tours, and avoid staying

for a long time.

佩带耳罩等防护用品。Wear such PPE as ear muff.

2.试压过程中的杂音noise during the

pressure test

3.采用隔声、消声、吸声措施。Take measures of noise insulation, silencing and sound

absorption.

4.定期巡检,避免长时间停留。Take regular inspection tours, and avoid staying

for a long time.

- 19 -

储罐试压方案

1编制说明 为保证冷焦水缓冲罐(V501)、冷焦水储罐(V502)、冷焦水沉降罐(V503A/B)、污油收集罐水压(V504)试验顺利进行,特编制此方案。 2编制依据 2.1洛阳设计院储罐施工及验收工程技术条件(527071D0204-70-002/N4) 2.2《立式圆筒形钢制焊接储罐施工及验收规范》(GB50128-2005) 3试压准备 3.1试压前储罐必须按图施工完毕,安装质量符合图纸、储罐制造及验收工程 技术条件及规范的要求,并经甲方及甲方代表(监理)验收完毕,准许进行水 压试验。 3.2试压前所有资料必须齐全,试验用的压力表已经全校验,并在周检期内。试 压前储罐的所有敞口应安装或加焊牢固的临时盲板,顶部应设排气阀。 4储罐的水压试验 4.1储罐制造完毕,并按规定的项目检验合格后再按《立式圆筒形钢制焊接储 罐施工及验收规范》与洛阳设计院储罐施工及验收工程技术条件的要求 进行水压试验,试验之前应将设备内部赃物、碎片、焊渣等清扫干净。 4.2试验前,所有附件及其与罐体焊接的焊件,已经全部完工。 4.3与严密性试验有关的焊缝,不得涂刷油漆。 4.4充水试验中,要加强基础沉降观察,如基础发生不均匀沉降时,应停止充水, 待处理后方可进行试验。 4.5罐底的严密性,应以充水试验过程中罐底无渗漏为合格。发现渗漏时,应及 时将水排尽,找出渗漏部位,对渗漏部位补焊后再继续进行上水。 4.6罐壁的强度及严密性试验:充水到设计最高液位并保持48h后,罐壁无渗 漏,无异常变形为合格。发现渗漏时应及时放水,使液面比渗漏处低300

㎜左右后,再对渗漏部位进行补焊。 4.7储罐灌水应从下部接口缓慢灌入,灌入时在储罐的顶部应设排气阀,便于 储罐的气体排除。 4.8充水与放水过程中,应打开透光空,且不得使基础浸水。 4.9罐的稳定性试验充水到设计最高液位用放水法进行,试验时缓慢降压,达 到试验负压时,罐顶无异常变形为合格。试验后应立即使储罐内部与大气 相同,恢复到常压。 4.10固定顶的强度及严密性试验,罐内水位在最高设计水位下1m时进行缓慢 充水升压,当升至试验压力时,罐顶无异常变形,焊缝无渗漏为合格。试验后, 应立即使储罐内部与大气相通,恢复到常压。引起温度剧烈变化的天气, 不允许做固定顶的强度与严密性试验与稳定性试验。 4.11储罐内灌满水后,且确认储罐内气体已完全排除便开始进行试压。 4.12储罐水压试验升压过程中,当发现压力表表针摆动不稳,且升压较慢时应 重新排气后再升压。 4.13储罐升压时应随时检查储罐本体及接口,当发现异常时应停止升压,消除 缺陷后再升压。 4.14试验时,严禁对储罐本体、接口进行敲打或修补缺陷,遇有缺陷时,应作出明 显标记,在储罐卸压后方可修补。 4.15冷焦水储罐(V502)、污油收集罐水压(V504)试压采用在罐顶设置U型管 进行正压试验与负压试验检查。 5储罐V-501,V503A/B水压试验的特殊要求 5.1试压以前应首先将罐周围搭设好脚手架,以便焊缝的密封性检查,脚手架 搭设应牢固可靠。 5.2脚手架搭设在地面生根下设垫板,上设拦腰杆、护脚板等。

储罐充水试压方案

陕西延长石油 靖边能源化工综合利用启动项目 甲醇联合装置中间罐区 储罐充水试验施工方案 审批: 审核: 编制: 中国化学工程第六建设有限公司2012年9月20日

目录

1 概述 编制说明 本施工方案仅适用于陕西延长石油靖边能源化工综合利用启动项目甲醇联合装置195C中间罐区731V08A/B、731V10、731V11四台储罐充水试验的施工。工程概况 四台储罐的规格及试压要求如下: 2编制依据

1.《立式圆筒形钢制焊接油罐施工及验收规范》GB50128-2005 2.《石油化工钢储罐地基与基础施工及验收规范》SH3528-2006 3.《石油化工施工安全技术规程》SH3505-1999 4.《立式圆筒形钢制焊接储罐设计规范》SH3046-1992 5.《现场设备、工业管道焊接工程施工及验收规范》GB50236-2011 6.《工业安装工程质量检验评定统一标准》GB5025-94 7.施工图08051-1163、08051-1164和08051-1165 3 施工准备 压力试验前,首先做好以下准备工作: 1.检查罐几何尺寸、附件安装已符合设计和规范要求; 2.罐底真空试验检查完毕,且符合设计和规范要求; 3.检查罐内是否有遗留物品,内件已经安装完毕,且符合设计和规范要求; 4.检查罐管口、法兰已焊接完,是否有漏焊部位; 5.接管补强圈气密工作已做完,且合格; 6.因中间罐区毗邻R4路水井,故水源就近采用R4路的井水,水源自带水泵; 7.排水点定为195C甲醇中间罐区南面围挡的北侧,挖约深1m、宽3m、长20m 的排水坑; 8.水位高度通过罐顶下放标尺观测以及U型压力计的方法观测; 9.沉降观测,731V08A/B、731V10、731V11四台储罐选定8个沉降观测点。 4施工工序

储罐水压试验施工方案

中化泉州1200万吨/年炼油项目85万吨/年芳烃抽提安装工程储罐充水试验方案 编制 审核 审批 中国化学工程第九建设公司 年月日

目录 一、工程概况.............................................................. 错误!未定义书签。 二、编制依据........................................................................................... - 1 - 1 中国环球工程辽宁分公司设计的储罐图纸。............................ - 1 - 2 施工及验收规范 ............................................................................ - 1 - 三、储罐罐底真空箱试验 (2) 1 试验目的 (2) 2 试验前准备 (2) 3 真空箱试验方法及原理 (2) 4 试验后续处理 (3) 四、储罐充水试验 (3) 1 施工工序 (3) 2 施步骤及方法 (3) 3 施步骤及方法 (3) 4 试验技术要求 (6) 五、内浮盘升降试验 (7) 六、质量管理体系及控制措施 (7) 七、HSE管理体系及注意事项 (7) 八、施工机具 (8) 九、措施用料 (8) 十、施工周期安排及试验组织 (9) 十一、危险性分析(JHA表) (9)

一、工程概况 中化泉州1200万吨/年炼油项目85万吨/年芳烃抽提装置储运8台储罐底板真空试验及充水试验,各储罐详细参数如下表。 二、编制依据 1.中国环球工程公司辽宁分公司设计的储罐图纸。 1)311007B-00-B-24抽提进料缓冲罐2212-T301施工图 2)311007B-00-B-25新鲜溶剂罐2212-T302施工图 3)311007B-00-B-26湿溶剂罐2212-T303施工图 4)311007B-00-B-27混合芳烃缓冲罐2212-T304施工图 5)311007B-00-B-28笨检验罐2212-T305A/B施工图 6)311007B-00-B-29甲笨检验罐2212-T306B/B施工图 2.施工及验收规范 1)《压力容器焊接规程》NB/T47015-2011

水压试验方案(最终版)

缅甸60TD CTMP新闻纸厂 DHS65-3.82/450-Q 65T/H、3.82Mpa燃气锅炉 水压试验方案 编制: 赖毅坚 审核: 罗荣泉 批准: 赖桂生 南宁市宏能动力设备有限公司金浦分公司

2012年4月25日 目录 1、水压试验目的 2、水压试验范围 3、水压试验前的检查 4、水压试验准备 5、水压试验方法 6、水压试验的合格标准 7、水压试验应注意事项 8、水压试验人员名单

9、水压试验所用材料清单 10、水压试验后的养护 1、水压试验目的: 根据锅炉本体安装施工说明要求,在安装完毕之后要进行水压试验。其目的是在冷态下检验各承压部件是否严密、强度是否足够。水压试验时,承压系统内部充满着高压水,由于水的可压缩性很小,因此压力能很均匀地传递到各个部位。如果受压部件上有细小空隙(如:焊口、阀门、法兰、门孔、管子沙眼等处不严密)水就会渗漏出来,或者承压部件某个部位,承受不住高压时,便会产生永久性变形,甚至破裂。通过水压试验,就可根据水压试验时的渗漏、变形和损坏,检查出承压部件及焊口的缺陷所在部位,以便及时处理、消除。所以说水压试验是检验锅炉本体受压部件安装质量的重要一环。 2、水压试验范围: 锅炉本体所有受热面(锅筒、汽水连接管、下降管、水冷壁、省煤器、高低温过热器、锅炉排污系统、所有锅炉集箱、锅炉一次阀门及管道); 3、水压试验前的检查: 检查:①承压部件的安装已全部完成; ②汽水系统管道上的所有阀门启闭位置正确,安全阀应隔离; ③组合及安装时用的临时加固和固定的支撑已清除干净; ④上水、升压、放水等系统已全部装好。试压用的压力表(两

储罐试压方案

1编制说明 为保证冷焦水缓冲罐(V501)、冷焦水储罐(V502)、冷焦水沉降罐(V503A/B)、污油收集罐水压(V504)试验顺利进行,特编制此方案。 2编制依据 2.1洛阳设计院储罐施工及验收工程技术条件(527071D0204-70-002/N4) 2.2《立式圆筒形钢制焊接储罐施工及验收规范》(GB50128-2005) 3试压准备 3.1试压前储罐必须按图施工完毕,安装质量符合图纸、储罐制造及验收工 程技术条件及规范的要求,并经甲方及甲方代表(监理)验收完毕,准 许进行水压试验。 3.2试压前所有资料必须齐全,试验用的压力表已经全校验,并在周检期内。 试压前储罐的所有敞口应安装或加焊牢固的临时盲板,顶部应设排气阀。4储罐的水压试验 4.1储罐制造完毕,并按规定的项目检验合格后再按《立式圆筒形钢制焊接 储罐施工及验收规范》和洛阳设计院储罐施工及验收工程技术条件的要 求进行水压试验,试验之前应将设备内部赃物、碎片、焊渣等清扫干净。 4.2试验前,所有附件及其与罐体焊接的焊件,已经全部完工。 4.3与严密性试验有关的焊缝,不得涂刷油漆。 4.4充水试验中,要加强基础沉降观察,如基础发生不均匀沉降时,应停止 充水,待处理后方可进行试验。 4.5罐底的严密性,应以充水试验过程中罐底无渗漏为合格。发现渗漏时, 应及时将水排尽,找出渗漏部位,对渗漏部位补焊后再继续进行上水。 4.6罐壁的强度及严密性试验:充水到设计最高液位并保持48h后,罐壁无 渗漏,无异常变形为合格。发现渗漏时应及时放水,使液面比渗漏处低

300㎜左右后,再对渗漏部位进行补焊。 4.7储罐灌水应从下部接口缓慢灌入,灌入时在储罐的顶部应设排气阀,便于 储罐的气体排除。 4.8充水和放水过程中,应打开透光空,且不得使基础浸水。 4.9罐的稳定性试验充水到设计最高液位用放水法进行,试验时缓慢降压, 达到试验负压时,罐顶无异常变形为合格。试验后应立即使储罐内部与 大气相同,恢复到常压。 4.10固定顶的强度及严密性试验,罐内水位在最高设计水位下1m时进行缓 慢充水升压,当升至试验压力时,罐顶无异常变形,焊缝无渗漏为合格。 试验后,应立即使储罐内部和大气相通,恢复到常压。引起温度剧烈变 化的天气,不允许做固定顶的强度和严密性试验和稳定性试验。 4.11储罐内灌满水后,且确认储罐内气体已完全排除便开始进行试压。 4.12储罐水压试验升压过程中,当发现压力表表针摆动不稳,且升压较慢时应 重新排气后再升压。 4.13储罐升压时应随时检查储罐本体及接口,当发现异常时应停止升压,消除 缺陷后再升压。 4.14试验时,严禁对储罐本体、接口进行敲打或修补缺陷,遇有缺陷时,应作出 明显标记,在储罐卸压后方可修补。 4.15冷焦水储罐(V502)、污油收集罐水压(V504)试压采用在罐顶设置U 型管进行正压试验和负压试验检查。 5储罐V-501,V503A/B水压试验的特殊要求 5.1试压以前应首先将罐周围搭设好脚手架,以便焊缝的密封性检查,脚手 架搭设应牢固可靠。 5.2脚手架搭设在地面生根下设垫板,上设拦腰杆、护脚板等。

罐体充水试验样本

罐体充水试验 施 工 方 案 审批: 审核: 编制: 项目部 2016-9-26

施工组织设计/方案审批页

工程名称: 槽罐试水试验专项施工方案 审批页审批意见: 建设单位: 部门批准: 建设单位负责人: 审批日期:年月日

目录 一.适用范围................................................................................................ - 1 - 二.编制依据................................................................................................ - 1 - 三.工程概况................................................................................................ - 1 - 四.施工工序................................................................................................ - 1 - 五.施工步骤及方法.................................................................................... - 1 - 六. 质量管理................................................................................................. - 7 - 七.安全管理.............................................................................................. - 8 - 八人力计划.............................................................................................. - 10 - 九.施工机具.............................................................................................. - 10 - 十.工作危险源分析评估及预防 ............................................................ - 13 -

储罐充水实验方案修订稿

储罐充水实验方案 WEIHUA system office room 【WEIHUA 16H-WEIHUA WEIHUA8Q8-

新疆美叶储运-克石化稠油输送管道项目储罐充水试验施工方案 编制: 审核: 批准: 江苏亚新石化建设集团有限公司 2015年08月21日

目录

1.编制说明 本方案仅适用于新疆美叶储运-克石化稠油输送管道项目末站稠油拱顶储罐及消防水罐水压试验施工。 2 .编制依据 国家及地方相关法律、法规、规章制度;行业部门的相关规程、规范、标准 《立式圆筒形钢制焊接油罐施工及验收规范》GB50128-2005 GB50128-2014 《石油化工建设工程施工安全技术规范》GB50484-2008 《钢制焊接常压容器》NB/T 新疆石油勘察设计研究院(有限公司)提供的设计文件及施工图纸 3.主要工程参数 4.储罐试压程序

5.水压试验准备及要求 技术准备 水压试验前已进行充水前检查验收,施工资料齐全; 水压试验前已做好沉降观测标记和记录;(此项工作由土建专业负责) 水压试验方案已经按程序上报并批准; 试验前已进行了技术交底。 现场准备 试压水源已经落实,水质符合要求并能满足试压要求; 储罐已按图纸完成所有与罐本体相焊的施工内容,并经业主、监理联合验收符合外观、几何尺寸、检测等质量要求; 所有与严密性试验有关的焊缝,均不得涂刷油漆; 罐内临时支架均已拆除完毕,罐内部都已清扫干净; 底板搭接焊缝已按照规范要求真空试漏检查合格;开孔的补强板应通入空气进行焊缝的严密性试验,并经检查合格; 罐壁所有管口均已用盲板封闭,并经检查核实均能满足试压要求; 水压试验所用的临时管线均已安装完毕,并随时可以投入使用。 水压试验要求 充水试验中应进行基础沉降观测;在充水试验中,如果基础发生设计规范不允许的沉降,应停止充水,待处理后,方可继续进行试验; 充水和放水过程中,应打开透光孔,且不得使基础浸水;

储罐检验试验措施方案-通用模版

罐体检验、检测及试验措施方案 2.5.1焊缝检验 2.5.1.1所有焊缝在检验和总体试验合格前,严禁涂刷油漆。 2.5.1.2全部焊缝均应进行外观检验。 ⑴检查前应将妨碍检查的渣皮、飞溅清理干净。将罐上所有工卡具痕迹清除干净,焊 疤打磨平滑。 ⑵焊缝的焊脚应符合设计要求,其外形应平缓过渡,表面不得有裂纹、气孔、夹渣等 缺陷。 ⑶对接焊缝表面质量应符合以下规定: ①不允许有表面裂纹、表面气孔、表面夹渣和熔合性飞溅。 ②咬边不得大于0.5mm,咬边的连续长度不得大于100mm;焊缝两侧咬边的总长度 不得超过该焊缝长度的10%。 ③焊缝余高:浮顶及内浮顶储罐内壁焊缝的余高不得大于1mm。其它对接焊缝的余 高应符合下表的规定: ④罐壁纵向对接焊缝不得有低于母材表面的凹陷;罐壁环向对接焊缝和罐底对接焊缝 的凹陷深度不得大于0.5mm,连续长度不得大于100mm,总长度不得大于该焊缝总长度的10%。 ⑤接头坡口错边量: 纵向焊缝:当板厚小于或等于10mm时不应大于1mm;当板厚大于10mm时,不应大于板厚的1/10,且不大于1.5mm。 环向焊缝:当上圈壁板厚度小于8mm时,任何一点的错边量均不得大于1.5mm; 当上圈壁板厚度大于或等于8mm时,任何一点的错边量均不得大于 板厚的2/10,且不大于3mm。 ⑷焊缝宽度:坡口两侧各增加1~2mm。 2.5.1.3外观检查合格的罐壁板焊缝按以下比例进行检测,对X射线探伤,检测结果不应低于《承压设备无损检测》(JB4730-2005)第二篇“焊缝射线透照检测”的Ⅲ级,

对超声波探伤,检测结果不应低于第三篇“超声检测”的Ⅱ级。射线及超声波探伤的比例应符合下列规定: ⑴厚度大于或等于10mm的罐底边缘板,每条对接焊缝的外端300mm范围内应进行射线探伤;厚度为6~9mm的罐底边缘板,每个焊工施焊的焊缝,应按上述方法至少抽查一条。 ⑵底板三层钢板重叠部分的搭接接头焊缝和对接罐底板的丁字焊缝的根部焊道焊完后,在沿三个方向各200mm范围内进行渗透探伤。全部焊完后,应进行渗透探伤或磁粉探伤。 ⑶纵焊缝:对于每一个焊工的每种板厚的焊缝(板厚差不大于1mm时可视为同等厚度),在最初3m范围内的任意部位取300mm进行射线探伤。以后不考虑焊工人数,对于每种板厚的焊缝,从每30m焊缝及其尾数部分内任意取300mm进行射线探伤。探伤部位中的25%应位于丁字焊缝处,且每台罐不少于2处。 ⑷环焊缝:对于每种板厚的焊缝(以较薄的板厚为准),在最初3m范围内的任意部位取300mm进行射线探伤。以后对于每种板厚的焊缝,从每60m焊缝及其尾数部分内任意取300mm进行射线探伤。上述检查均不考虑焊工人数。 ⑸底圈壁板当厚度小于或等于10mm时,应从每条纵向焊缝中任取300mm进行射线探伤;当板厚大于10mm小于或等于25mm时,应从每条纵向焊缝中取2个300mm进行射线探伤,其中一个应靠近底板。 ⑹厚度大于25mm小于或等于38mm的各圈壁板,每条纵向焊缝应全部进行射线探伤;厚度大于10mm的壁板,全部丁字焊缝均应进行射线探伤检查。 ⑺除丁字焊缝外,可用超声波探伤代替射线探伤,但其中20%的部位应用射线探伤进行复验。 ⑻若发现不合格者,应在该探伤长度的两端延伸300mm作补充探伤,如延伸部位的探伤结果仍不合格时,应继续延伸进行检查。对不合格焊缝,应进行返修,返修前应进行质量分析,制定出措施。返修后按原定方法进行探伤。同一部位焊缝返修不得超过两次。 2.5.1.4试漏检查 ⑴罐底板的所有焊缝应该采用真空箱法进行严密性试验,试验负压值不得低于53kPa,无渗漏为合格。试漏采用真空箱检查,先在焊缝表面刷肥皂水,把真空箱放在焊缝上,真空箱底部四周用玻璃腻子密封,用真空泵进行试压。 ⑵浮顶底板、单盘板的所有焊缝应经真空试漏合格,试验负压值不得低于53kPa。 ⑶船舱内外边缘板及各圈环向隔板、径向隔板的焊缝,应该用煤油试漏法进行严密性

储罐投用方案

储罐投用方案 T-301-02 罐自建罐至今未经过大规模检修,这次停工检修对该罐进行一次彻底检修。该罐进行了机械清洗,在清罐完成达到施工动火作业的基础上对油罐中央排水系统和加温盘管进行了检维修;油罐一二次密封的更换;雷达液位计的更换以及自动采样器和搅拌器的安装,这一系列的检修改动对这次油罐检维修再投用运行意义重大,做好这次油罐检维修后初次投用工作非常关键。 一、组织 1、工作小组 组长: 副组长: 组员: 2、安全环保组 组长: 副组长: 组员: 3、保运组 组长: 副组长: 组员: 4、职责 工作小组职责主要负责油罐投用方案的实施, 统筹组织各部门协调工作。 安全环保组职责主要负责整个投用运行中的安全环保工作。 保运组职责主要负责投用运行期间的检查、监督管理工作,及时解决在运行过程中出 现的故障。 二、技术规范

GB50128-2005 立式圆筒钢制焊接储罐施工及验收规范 三、施工交接检查 1.设备隐蔽组进行油罐内部检查,检查要求不允许油罐内有杂物,罐内清洁干净,油罐内部防腐 符合要求,安装设备符合设计技术要求。 2.质量组进行油罐浮盘检查,确认浮盘一二次密封安装合格,浮盘无塌陷现象,浮船浮舱检查无 泄漏点,浮盘支柱密封检查确认。 3.油罐区卫生检查,确保油罐进油前卫生良好。 四、油罐进油前准备工作 1.进行中央排水管的试压工作,确保中央排水管符合使用技术要求。 2.油罐加热盘管的打压试漏,确保加热盘管无漏点存在。并且对加温盘管进行测厚标定。 3.搅拌器安装确认,外部初步确认搅拌器安装符合技术要求。 4.自动采样器安装检查,外部检查自动采样器安装确认合格以及油罐内部安装检查。 5.人工雷达液位计安装检查,检查雷达液位计安装确认符合安装技术要求,并且检查雷达液位计 零液位准确性。 6.油罐各仪表检查,现场确认安装完好,以及确认仪表在检定周期内使用。 7.油罐容积重新标定,配合质检部门做好油罐检修后容积标定,以及确认油罐检尺孔安装是否标 准。 8.确保油罐内无杂物后封罐。对油罐人孔,排污孔,浮盘上人孔进行安装密封到达安装要求。 9.油罐静电接地设施是否完好,油罐走梯,操作平台检查,以及油罐消防设施检查要到位,泡沫 发生器检查及确认油罐喷淋能否正常开启。 10.油罐封罐后进行盲板拆除工作,拆除油罐进出口阀门处盲板,油罐加热盘管进出口阀门处盲 板。 五、进油前确认工作 1.油罐脱水阀确认关闭。 2.确认油罐加热盘管进出阀门处于关闭状态。 3.再次确认油罐盲板已完全拆除。 4.联系调度准备进油 六、进油及进油后检查工作 1.利用相邻油罐进行压油作业,进油时先打开罐根收油二次阀,再打开罐根收油一次阀,控制好 进油速度,在浮盘未起浮前,进油速度必须控制在1m/s 以内。 2.在进油时计量员协同仪表就雷达液位计进行进油液位校准工作,并随时确认进油量以及进油速 度。 3.在进油的同时将采样器、搅拌器、人孔、排污孔安装密封性进行确认,确认无渗漏现象。确认油 罐脱水阀无渗漏现象,继续进油。 4.仪表确认相关仪表运行正常,如有问题及时报告车间领导。在油罐进4 油到米时,投用加热 系统,调节油温,观察油罐温度计运行是否符合要求。 5.专人负责油罐浮盘起浮工作,该工作人员应及时与计量人员联系,确认油罐液位,确认油罐

储罐水压试验方法

文件类型Document type 文件页数 Pages 版次 Version 修订说明 Revision note 受控编号 Controlled number GH 20 1版 Version1 首次1st 储罐充水试压方案 Tank Hydro-test Plan 2 2012年11月1日 Nov. 1, 2012 版次Edition 日期 Date 编制 Formulated by 审核 Reviewed by 批准 Approved by 中国化学工程第十三建设有限公司 The 13th Construction Co., Ltd. of CNCE

储罐充水试压方案 Tank Hydro-test Plan 目录Contents 2 3 3 3 4 5 5 6 八人力计划VII. Planning for Labor Forces (18) 九机具准备VII. Preparations of Machines and Tools (18) 十工作危险源分析评估及预防Work-related Hazard Analysis Evaluation and Prevention (19)

一.适用范围Range of Application 1.本方案适用于塞拉尼斯(南京)乙酰基中间体有限公司工业乙醇项目八期改造扩建罐区4台储罐的充水试验的施工。This plan is applicable to the execution of the hydro-test for 4 tanks in the modification and expansion of the tank farm of Celanese China Fast Project. 二.编制依据Formulation Basis 1) 《钢制焊接常压容器》Steel Welded Atmospheric Pressure Vessels JB/T4735-1997 2) 《立式圆筒形钢制焊接油罐施工及验收规范》Code for Construction and Acceptance of Welded Steel Oil Tank of V ertical Barrel Shape GB50128-2005 3) 《石油化工钢储罐地基与基础施工及验收规范》Specification for Construction and Acceptance of Steel Storage Tank Subgrade & Foundation in Petrochemical Industry S H3528-93 4) 《大型焊接低压储罐设计与建造》Design and Construction of Large, Welded, Low-pressure Storage Tanks API620-2009 5) 塞拉尼斯技术要求及相关过程规定Celanese technical requirements and related process regulations 三.工程概况General 序号No. 位号 Item 名称 Descrip tion 规格Spec. 设备净重 Net weight of equipment (t) Weight after water filling充 水后重 (t) 水 water (m3) 设计压力Design pressure Mpa Filling height充 水高度 (m) 1 V-73 2 产品罐 Product tank φ10795*9750763 2 V-73 3 产品罐 Product tank φ10795*9750763 3 V-74 4 倒液罐 Off-spe c tank φ10795*9750763

液化气储罐检验方案

液化石油气卧式储罐检验方案 编制: 审核: 批准: 2017年08月 xxxxxxxxxxxxxxxxxxxxxxxxxxxxx

液化石油气储罐检验方案 一、设备基本情况 具体视所检设备情况定。 二、检验及制定检验方案的依据 1、《固定式压力容器安全技术监察规程》 2、《压力容器》 3、容器原始资料及其它相关标准 4、《钢制液化石油气卧式储罐》 三、检验单位检验前准备工作 1、参加人员 检验人员组成及资格: 具体视现场检验人员定。 2、仪器设备 射线探伤机、磁力探伤机、硬度检测仪、渗透探伤、测氧仪、测厚仪、检验尺、放大镜、手电筒及其他检测工具 3、资料审查 (1)设计单位资格;设计、安装使用说明书;设计图样、强度计算书等;(2)制造单位;资格制造日期;产品合格证;质量证明书;竣工图;监督检验证书等; (3)安装单位资格;安装质量证明书;监督检验证书等; (4)使用登记证、历次检验报告、年度检查报告等; (5)有关修理、改造方案;告知文件、竣工资料等。 (6)资料审查中若发现达到设计使用年限的压力容器(未规定设计使用年限,但是使用超过20年的压力容器视为达到设计使用年限),如果要继续使用,使用单位应当委托有检验资格的特种设备检验机构参照定期检验的有关规定对其进

行检验,必要时按照《固定式压力容器安全技术监察规程》8.9要求进行安全评估(合于使用评价),经过使用单位主要负责人批准后,办理使用登记证变更,方可继续使用。 四、检验前使用单位准备工作 使用单位应当按照要求做好停机后的技术性处理和检验前的安全检查,确认现场条件符合检验工作要求,做好有关的准备工作。检验前,现场至少具备以下条件: (1)影响检验的附属部件或者其他物体,按照检验要求进行清理或者清除。(2)为检验搭设脚手架、轻便梯等设施必须安全牢固,(对于离地面2米以上的脚手架必须设置安全护栏)。 (3)需要进行检验的表面,特别是腐蚀部位和可能产生裂纹性缺陷的部位,必须彻底清理干净,母材表面应当露出本体,进行磁粉渗透检测的表面应当露出金属光泽。 (4)要进入压力容器内部进行检验,将内部介质排放、清理干净,用盲板隔断所有液体、气体或者蒸汽的来源,同时设置明显的隔离标志,禁止用关闭阀门代替盲板隔断。 (5)需要进入盛装易燃、易爆、助燃、毒性或者窒息性介质的压力容器内部进行检验,必须进行置换、中和、消毒,取样分析,分析结果达到有关规范、标准规定;取样分析的间隔时间应当使用单位的有关规定;盛装易燃、易爆、助燃介质的严禁用空气置换; (6)人孔和检查孔打开后,必须清除可能滞留的易燃、易爆、有毒、有害气体和液体,压力容器内部空间的含氧量保持在0.195以上;必要时,还需要配备通风、安全救护等设施; (7)切断与压力容器有关的电源,设置明显的安全警示标志;检查照明用电电压不得超过24V,引入压力容器内的电缆必须绝缘良好、接地可靠;

储罐水压试验方案终版

表B.0.1施工组织设计/(专项)施工方案报审表 工程名称:中国石油云南销售分公司 清华洞油库扩建工程编号:YNXS-PTYK-QHD-FA-035致:青岛华油工程建设监理有限公司中油云南销售清华洞油库扩建工程监理部我方已完成中国石油云南销售分公司清华洞油库扩建工程储罐充水试验工程施工组织设计/(专项)施工方案的编制,并按规定已完成相关审批手续,请予以审查。 附:□施工组织设计 □专项施工方案 □施工方案 施工项目经理部(盖章) 项目经理(签字) 年月日审查意见: 专业监理工程师(签字) 年月日审核意见: 项目监理机构(盖章) 总监理工程师(签字、加盖执业印章) 年月日审批意见(仅对超过一定规模的危险性较大分部分项工程专项方案) 建设单位(盖章) 建设单位代表(签字) 年月日填报说明:本表一式三份,项目监理机构、建设单位、施工单位各一份。

方案编制及审批表 工程名称中国石油云南销售分公司清华洞油库扩建工程 计划开工日期计划竣工日期 施工单位中国石油天然气第一建设公司武汉项目经理部 编制人 编制日期年月日 审核人 年月日 批准人职务: 签名: 年月日

文件编号:WHXM-QHDYK-SGFA-027-2015 中国石油云南销售分公司 清华洞油库扩建工程 储罐充水试验方案 中国石油天然气第一建设公司 武汉项目经理部 2015年06月09日 版次:第A/1版

目录 1 工程概况 (1) 2 编制依据 (1) 3 充水方案 (1) 4 充水试验 (1) 4.1 上水试验前准备 (2) 4.2 充水试验 (3) 4.3 试验完毕后系统放水 (4) 5 HSE措施及管理 (4) 6 质量保证措施 (5) 6.1 试压小组 (5) 6.2 施工质量措施 (5) 7 手段用料及机具 (6) 8 JSA分析报告 (8)

球罐水压试验方案

球形储罐水压试验 施工方案 编制:________ 审核:________ 批准:________ 二0一一年六月十二日

目录 1 概述 (1) 2 试验条件 (1) 3 试验准备 (1) 4 基础沉降观测 (1) 5 水压试验 (1) 5.1试验步骤 (1) 5.2排水 (2) 6 人力计划 (2) 7 安全措施和注意事项 (2) 8 JHA分析 (2)

1 概述 根据设计要求和有关标准、规范规定,在球罐和零部件焊接工作完成后对球罐进行水压试验。水压试验由工艺责任师主持,质保工程师、质检责任师等有关人员到场参加,在劳动部门、建设单位和监理单位代表监督下进行。 仪表空气球罐试验压力为1.3 Mpa 2 试验条件 应具备下列条件方可进行水压试验: a)球罐和零部件焊接工作是否全部完成并经检验合格 b)基础二次灌浆达到强度要求; c)支柱找正固定,拉杆调整好; 3 试验准备 a)配制人员应具备较强的专业技术知识和经验,其他人员不得擅自操作 b)施工前由班长负责对施工人员的防护用品仔细检查,以防发生意外事故 c)水压试验前,球罐各连接部位紧固螺栓必须装配齐全,紧固; d)每根支柱上按规定焊接永久性的水平测定板; e)水压试验水源利用临时管道泵从北面小河里抽水至球罐 f)试验机具安装 罐顶部和罐底部各安装一块经检验合格的压力表,量程为2.5MPa,精度等级不低于1.5级,试验时压力以球罐顶部压力表读数为准。 4 基础沉降观测 球罐充水/排水过程中,在下列阶段对基础进行沉降观测; a)充水前; b)充水高度达到1/3球壳直径时; c)充水高度达到2/3球壳直径时; d)充满水后; e)充满水24小时后; f)放水后。 每个支柱基础都应测量沉降量,支柱沉降应均匀。放水后,各基础沉降差应不大于10mm,相邻支柱基础沉降应不大于2mm。不均匀沉降量如大于上述要求时,应采取必要的措施进行处理。 5 水压试验 5.1 试验步骤 a)试验时球罐顶部应设排气口。充液时应将球罐内的空气排尽,试验过程中,应保持球罐外表面 干燥。

液化石油气储罐水压试验安全操作规程通用版

操作规程编号:YTO-FS-PD840 液化石油气储罐水压试验安全操作规 程通用版 In Order T o Standardize The Management Of Daily Behavior, The Activities And T asks Are Controlled By The Determined Terms, So As T o Achieve The Effect Of Safe Production And Reduce Hidden Dangers. 标准/ 权威/ 规范/ 实用 Authoritative And Practical Standards

精品规程范本编号:YTO-FS-PD840 2 / 2 编写人:xxxxx 审核人:xxxxx 液化石油气储罐水压试验安全操作 规程通用版 使用提示:本操作规程文件可用于工作中为规范日常行为与作业运行过程的管理,通过对确定的条款对活动和任务实施控制,使活动和任务在受控状态,从而达到安全生产和减少隐患的效果。文件下载后可定制修改,请根据实际需要进行调整和使用。 第一条水压试验压力要为设计压力的1.25倍。 第二条受试验的储罐必须与运行的工艺管线断开,加等强度的盲板。 第三条水泵应有止回阀、泄水阀、压力表(2.4 MPa 以上) 第四条水泵出口要采用高压胶管或钢管。 第五条接近试验压力时,注意不要超压。 第六条保压5分钟巡查,无压降、变形、渗漏则降到设计压力,保压15分钟再检查,无问题后泄压。 第七条由排污阀排水,记录全部试压过程,指挥者签字存档。 该位置可输入公司/组织对应的名字地址 The Name Of The Organization Can Be Entered In This Location

储罐水压试验施工方案

储罐充水试验 施 工 方 案

目录 1 适用范围 (1) 2 编制依据 (1) 3 工程概况 (1) 4 施工工序 (3) 5 施工步骤及方法 (3) 6 充水试验要求 (9) 7 质量控制措施 (9) 8 紧急处理措施 (12) 9 HSE管理措施 (14) 10 施工机具及措施用料 (14)

1适用范围 本施工方案仅适用于XXXXXXXXXXXXXXX项目XXXXXX储罐的充水试验的施工。 2编制依据 2.1《立式圆桶形钢制焊接油罐施工及验收规范》GB50128-2005 2.2《大型储罐施工技术》 2005SB-766/SM 2.3业主提供施工图:0909-EQ2-V0303A~D-13-01~07、EQ2-0401— 25-04-01~011 2.4《设计文件修改通知单》 2.5《石油化工施工安全技术规程》SH3505-1999 3工程概况 XXXXXXXXXXXXXXXXXXXXX项目7万吨储油罐区包括5000m3油罐10个、2000m3油罐10个。主体安装已快完工,其中5000m3油罐V0301A、B、C、D

罐扫尾已经接近尾声,根据目前施工进展情况,计划于XXXX年XX月XX日陆续对这XX个罐进行上水试验。 油罐位号及参数表:

4施工工序 5施工步骤及方法 5.1储罐制造完毕后,进行充水试验,并检查下列内容: 1)罐底严密性。

2)罐壁强度及严密性。 3)固定顶的强度及严密性。 4)排水管的严密性。 5)基础的沉降观测。 5.2压力试验前,首先做好以下准备工作: 1)检查罐外形尺寸、附件安装是否符合要求; 2)检查罐内是否有遗留物品,内件是否已经安装完毕; 3)检查罐管口、法兰是否已焊接完,是否有漏焊部位。 4)水源采用罐区东面的全厂生产、消防水,压力为0.4Mpa; 5)沉降观测点设置,每个储罐选定4个沉降观测点,沿圆周方向均布。 储罐沉降观测点布置如下图:

储罐充水实验方案教学内容

新疆美叶储运-克石化稠油输送管道项目储罐充水试验施工方案 编制: 审核: 批准: 江苏亚新石化建设集团有限公司 2015年08月21日

目录 1.编制说明 (3) 2.编制依据 (3) 3.主要工程参数 (3) 4.储罐试压程序 (3) 5.水压试验准备及要求 (4) 6.试水检查内容及顺序 (5) 7.水压试验过程 (5) 8.水压试验合格要求 (6) 9.试压组织机构 (8) 10.水压试验劳动力安排计划 (8) 11.水压试验主要机具、材料安排计划 (8) 12.安全管理措施 (9) 13.环境管理措施 (9)

1.编制说明 本方案仅适用于新疆美叶储运-克石化稠油输送管道项目末站稠油拱顶储罐及消防水罐水压试验施工。 2 .编制依据 2.1 国家及地方相关法律、法规、规章制度;行业部门的相关规程、规范、标准 2.2《立式圆筒形钢制焊接油罐施工及验收规范》GB50128-2005 GB50128-2014 2.3《石油化工建设工程施工安全技术规范》GB50484-2008 2.4《钢制焊接常压容器》NB/T 4700 3.1-2009 2.6新疆石油勘察设计研究院(有限公司)提供的设计文件及施工图纸 3.主要工程参数 4.储罐试压程序

5.水压试验准备及要求 5.1技术准备 5.1.1水压试验前已进行充水前检查验收,施工资料齐全; 5.1.2 水压试验前已做好沉降观测标记和记录;(此项工作由土建专业负责) 5.1.3 水压试验方案已经按程序上报并批准; 5.1.4 试验前已进行了技术交底。 5.2 现场准备 5.2.1试压水源已经落实,水质符合要求并能满足试压要求; 5.2.2 储罐已按图纸完成所有与罐本体相焊的施工内容,并经业主、监理联合验收符合外观、几何尺寸、检测等质量要求; 5.2.3所有与严密性试验有关的焊缝,均不得涂刷油漆; 5.2.4 罐内临时支架均已拆除完毕,罐内部都已清扫干净; 5.2.5底板搭接焊缝已按照规范要求真空试漏检查合格;开孔的补强板应通入空气进行焊缝的严密性试验,并经检查合格; 5.2.6罐壁所有管口均已用盲板封闭,并经检查核实均能满足试压要求; 5.2.7水压试验所用的临时管线均已安装完毕,并随时可以投入使用。 5.3 水压试验要求 5.3.1 充水试验中应进行基础沉降观测;在充水试验中,如果基础发生设计规范不允许的沉降,应停止充水,待处理后,方可继续进行试验; 5.3.2 充水和放水过程中,应打开透光孔,且不得使基础浸水; 5.3.3 试验过程应严格按图纸及规范要求进行,并做好相关记录。 5.4水压试验用水源计算 5000m3稠油拱顶储罐试验用水量,现以单台5000m3储罐充水进行水源核算 总充水量V=5000m3,充水期t按7天考虑,上水管水流速选1.65m/s,则对于水源管径要求为:V=S*d*t----(1) 其中S=(d/2)^2*π ----(2)有以上两式得: d 根据以上计算,可将流速选用1.65m/s,管径选用DN200mm可满足上水要求,如果现场进水管道不能达到DN200mm的情况下为了缩短进水时间,可采取在进水临时管线上加设一台管道泵来增加进水流速,使其进水时间尽量缩短。

(水压试验方案)

高(中)温厌氧发酵罐水压试验方案 编制依据: 1. 发酵罐安装图纸; 2.《钢制压力容器》GB150-1998; 3. SY/T0608-2006 大型焊接低压储罐的设计与建造; 4. GB50128-2005立式圆筒形焊接油罐施工及验收规范; 5. SH3514-2001石油化工设备安装工程质量检验评定; 6. GB50235-97 工业金属管道工程施工及验收规范。 编制说明: 根据集团公司对日产50万立方米民用沼气工程总体工程进度要求,为保障11月底顺利接纳乙醇公司、股份公司、玉米项目废水进入厌、好氧系统,保证系统正常运行,达到设计要求,产生沼气,废水达标排放的最终目标。在工程建设、安装等相关方面条件不具备的情况下,进行高(中)温发酵罐试水、试漏方案,目的是为了保证设备高温、中温厌氧发酵罐充水、水压、试验的顺利进行,并为下步菌种培养,逐步加大进水负荷提供条件,特编制本方案请生产部审核批准。 简述: 一、充水试验应具备的条件 1、充水试验,罐体所有附件及其它与罐体焊接的构件全部施工完后进行(与储罐壁连接的管道,支、托、吊架电气、仪表支架); 2、充水试验前,所有与严密性试验有关的焊缝,均不得涂刷油

漆; 3、焊缝的无损检测应进行完毕,且全部合格; 4、必须准备2块量程相同的U型压力表,且必须经过检验认可合格; 5、应采用淡水,且水温不应低于5°C; 6、充水过程中,如基础发生不允许的沉降,应停止充水,待处理后方可继续进行试验; 7、充水和放水过程中,应打开放气孔,且不得使基础浸水; 8、发酵罐沉降观测需在设备下部均匀设置4个基础沉降观测点。 二、充水试验,应检查下列内容: a .罐底严密性; b .罐壁强度及严密性; c .拱顶的强度、稳定性及严密性; d .设置基础的沉降观测参照点; e .充水试验用水应使用排放达标水。 三、水压试验参照点001表(略) 四、水压试验人员名单(略) 五、水压试验使用的仪器及沉降观测参照点平面示意图(略) 六、试验流程: 管道架设充水试漏沉降观测排水清扫封闭交工验收。 七、发酵罐试验过程