PMP模拟题(一)

PMP模拟题(一)
PMP模拟题(一)

PMP模拟题习

PMP专用题习,题习总分合计:200 分,请学员通过打印机打印下来进行测试:

(1)The greatest of uncertainty is encountered during which phase of the project life cycle?

A. Concept

B.

性?

Planning C. Implementation D. Closeout项目生命期的哪个阶段具有最大的不确定

A. (2)概念阶段

B.规划阶段

C.执行阶段

D.收尾阶段Projects have the least attention in what form of organization:

A. Balanced matrix

B. Strong matrix

C. Coordinator

D.Functional项目在哪种组织中最不被重视?

A. 平衡矩阵型

B. 强矩阵型

C.项目协调员型

D.职能型

(3)The final project budget is created during which life cycle phase:

A. Initiation

B. It is given to the project manager before the project management life cycle

C. Planning

D.

Execution

最终的项目预算是在生命期的哪个阶段进行的?

A. (4)启动

B.在项目管理生命周期之前由项目经理进行的

C.

Who has the power in a strong matrix?

规划D.执行

A. Project manager

B. Senior management

C. Sponsor

D. Functional manager

谁在强矩阵中具有更多的权力?

A. 项目经理

B.高级管理层

C. 发起人

D. 职能经理

(5)Policies, methodologies, and templates for managing projects within the organization should be supplied by the:

A. Project sponsor.

B. Functional department.

C. Project management office.

D. Project manager.在

组织中管理项目时使用的策略、方法论和模板由谁来提供?

A.项目发起人

B. 职能部门

C.项目管理办公室

D. 项目经理

(6) A project stakeholder may include:

A. End users

B. Suppliers

C. Citizens

D. All of the above

项目利害关系者可能包括: A. 最终用户B.供应商C. 市民D.所有上述选项

(7)

A.

A. (8)The most important role of PM is:

Communication B. Integration C. Negotiating D. Leadership项目经理最重要的作用是: 沟通B.整体C.谈判D.领导

Which of the following BEST describes the major constraints on a project?

A. Scope of work, number of resources, cost

B. Scope of work, cost, and time

C. Customer satisfaction,

PMP模拟题习

quality, cost, scope of work, risk,and time D. Time, cost, and number of changes

下面哪项最好的描述了项目的主要制约因素?

A. 工作范围,资源数量,成本

B.工作范围,成本,时间

C.客户满意,质量,成本,工作范围,风险和时间

D. 时间,成本,和变更数量

(9)

A. In what organization project member feel most anxiety at closing phase Functional

B. Matrix

C. Projectized

D. D.Strong Matrix

在哪种组织中项目成员在收尾阶段最为焦虑?

A. 职能型

B. 矩阵型

C. 项目型

D. 强矩阵型

(10)Which of the following is the most important skills a project manager should have?

A. Negotiation skills

B.Influencing skills

C. Communication skills

D. Problem-solving skills

项目经理应该具备的最重要的技能是下列哪一种技能?

A.谈判B.影响C.沟通D.解决问题

(11)You are working on a product development project under contract to an automotive company that is building the “next-millennium Yugo.” Initially, the product was defined as “a state-of-the-art personal

transportation vehicle.” Later it was described as “a state-of-the-art personal transportation vehicle that

requires no gasoline.” Finally, after an all-night hot tub party with the design engineers, it was described as “a state-of-the-art personal transportation vehicle that requires no gasoline, costs less than USD $15,000, and

does not make any noise.”This shows the progressive elaboration of product characteristics. But, although the product characteristics are elaborated progressively, they must be coordinated carefully with the

A.Proper project scope definition B.Project stakeholders C.Scope change control system D.Customer’s strategic plan

你正在为一家汽车公司管理一个开发新产品的项目。起初,这个产品被定义为“艺术型的个人交通工具”。后来它又被描述为“不需要汽油的艺术型个人交通工具”。最后,经过与设计工程师的详细讨论后,又将其描述为”不需要汽油、花费低于15,000美元而且没有任何噪声的艺术型的个人交通工具”。这表明了产品特征的逐步细化。但是,尽管产品的特征得到了不断的细化,它们还是必须按照下列哪项内容来进行仔细协调?

A.适当的项目范围定义B.项目干系人C.范围变更控制系统D.客户战略计划(12)Project A is being administered using a matrix form of organization. The project manager reports to

a senior vice president who provides visible support to the project. In this scenario, which of the following

statements best describes the relative power of the project manager? A.The project manager will probably not be challenged by project stakeholders. B.In this strong matrix, the balance of power is

shifted to the functional line managers. C.In this tight matrix, the balance of power is shifted to the project manager. D.In this strong matrix, the balance of power is shifted to the project manager.

项目通过一个组织矩阵进行管理。项目经理向一位高级副总裁汇报工作,后者对项目提供实际的帮助。在这种情况下,以下哪个陈述最好地说明了项目经理的相对权力? A.项目经理很可能不会受

PMP模拟题习

到项目干系人的责难B.在这个强矩阵中,权力的平衡倾向于职能经理

C.在这个紧密矩阵中,权力平衡倾向于项目经理D.在这个强矩阵中,权力平衡倾向于项目经理

(13)Major difficulties arise when projects need to be managed in the functional organizational structure because of-

A.The level of authority of the project manager B.Conflicts over the relative priorities of different projects in competition for limited resources C.Project team members who are focused on their functional specialty rather than on the project D.The need for the project manager to use interpersonal skills to resolve conflicts informally

当项目需要在职能组织结构中进行管理的时候,会出现很大的困难,因为:

A.项目经理的权限有限B.不同的项目在竞争有限资源过程中会发生冲突C.项目小组成员更关注职能部门的本职工作而不是与项目有关的工作D.需要项目经理运用个人交际能力非正式地

解决冲突

(14)Which of the following qualifications is the most important for a project manager?

A.Supervisory experience B.Negotiation skill C.

Education in a technical field D.Ability to work well with others

以下项目经理的资格要求中最重要的是:

A.监理经验

B.谈判技巧

C.技术领域的教育背景

D.与他人有效合作的能力

(15)You need to be both a leader and a manager in your project management work. You realize that leadership without management or management without leadership probably will produce poor results. Which one of the following key responsibilities best represents project leadership?

A.Establishing direction, aligning people, and motivating and inspiring others B.Getting things done through other people C.Using charismatic power to motivate others D.Using all types of power, as appropriate, as motivational tools

在你的项目管理工作组中你需要同时扮演一个领导者和管理者的角色。你认识到没有管理能力的领导或者没有领导能力的管理都会产生差的结果。下面哪一个主要的责任最好的代表了项目领导能力?

A.决定方向,分配人员,鼓舞和激励他人

B.通过别人完成事情

C.利用个人的人格魅力来激励别人

D.利用各种可用的力量来作为激励工具

(16)You have just been assigned to take over a project that your management has told you is "out of control." When you asked your management what the problems were, they had no specifics, but said that the project was behind schedule, over budget, and the client was dissatisfied. Which of the following should be of

PMP模拟题习

the MOST concern to you? A. The project is over budget and behind schedule. B. There is very little documentation related to the project. C. The client is very dissatisfied with the project’s progres s. D. Your management is looking for rapid and visible action on this project to rectify the problems.

你刚刚被任命接管了一个项目,你的管理层告诉你项目是“失控”。当你询问你的管理层问题是什么时,他们没有具体说明,只是说项目落后进度,超出预算,客户很失望。下面哪一项将是你最关注的?

A.

B.

C.

D. 项目超出预算和落后进度

和项目相关的非常少的文档

客户对项目进展非常失望

你的管理层正在项目上寻找快速的和见效的行动以解决问题

(17)Effective project integration usually requires an emphasis on: A. The personal careers of the team members. B. Timely updates to the project management plan. C. Effective communications at key interface points. D. Product control.

有效的项目整合通常要求强调:

A.

B.

C.

D. 项目团队成员的个人职业生涯及时更新项目管理计划

在关键接口点上有效沟通

产品控制

(18)In order to obtain the support from executive organization, which one is the best choice for the

project manager A. ensure that there is a communication plan. B. connects the project requirements with the strategy plan of the organization C. connects the project with the personal goal of the sponsor D. ensure that the management plan includes the managing of team members

为获得执行组织对项目的支持,如果项目经理是最佳选择。A.确保有一个沟通计划。B.把对项目的需求与组织的战略计划相联系。C.

团队成员的管理。

把项目与发起人的个人目标相联系。D.确保管理计划包括(19)You are managing a two-year project involving staff from several departments. The project is on

schedule and within budget. A key team member leaves for a four-week vacation without completing a highly technical and specialized activity assigned to him (activity A). The project team cannot begin activity B or activity

E (a critical path activity) until activity A is completed. Activity A has three days float and is not on the critical

path. A team member, a vendor, and a nonteam member work overtime to complete activity A within its float time. You need to reimburse t he nonteam member ’s department and pay the vendor at an overtime rate. What action should you take? A. Send a complaint letter to the key team member’s boss, and ask him to fund the extra cost expended. B. Reevaluate your communications management plan. C. Thank the others for filling in, but tell them not to waste time on noncritical path activities. D. Pay the cost out of your project reserves.

你正在管理着一个2年的项目,团队成员来自不同的部门。项目是按时的和在预算内的。一个关键的团队成员在没有完成一个分给他的高技术活动(活动A)时由于度假要离开4周。项目团队不能开始活动

B或者活动E(关键路径上的活动)直到活动A能够完成。活动A有3天的浮动时间,并且不在关键路径上。一名团队成员,一名外包商,和一名非团队成员在浮动时间内加班完成活动A。你需要补偿非团队成员的部门和付给外包商加班费。你要采取的行动是什么?A. 给关键团队成员的老板发一封抱怨信,管他要花费的额外的费用B.重新评估你的沟通管理计划C.感谢其他人的加入,告诉他们不要在非关键路径上浪费时间D. 付出的成本超出了你项目的储备金

(20)During the execution of a project, the project manager determines that a change is needed to

material purchased for the project. The project manager calls a team meeting to plan how to make the change.

This action is an example of: A. management by objectives. B. lack of a change control system. C. Good team relations D. lack of a clear work breakdown structure.

项目执行期间,项目经理发现材料采购方面需要做一个变更。项目经理开始召集团队成员讨论如何进行这个变更。这是什么的例子?A.目标化管理B.缺乏变更控制系统C.好的团队关系D.缺乏清晰的WBS (21)You are managing a multi-million dollar project that is a joint venture between your company and another organization. You have repeatedly tried to get the contract and the project charter finalized between the two organizations, but there has been a great deal of arguing over language and details. The project’s scope has been expanding, costs have been increasing, and the schedule has been regularly lengthening. You learn very suddenly that the project has been cancelled, because the other organization withdrew its share of the

funding for the project. What is the MOST likely reason that this occurred? A. Failure to understand the budgetary process B. Inadequate scope management C. Lack of sponsor commitment D. Poorly done initial cost-benefit analysis

你管理着一个你的公司和其他公司合营的一个上百万美元的项目。你试图在两个组织之间得到合同和项目章程,但是有大量的语言和细节上的争论。项目的范围被扩展,成本升高,时间延长。突然之间这个

没有理解项目被取消,因为另外一个组织从项目中撤资。这种情况最可能发生的原因是什么?A.

预算流程B.不充分的范围管理C.缺乏发起人的委任D.初始的成本绩效分析很差

(22)During closeout, many project managers tend to delay personnel reassignment as long as possible

because A. They are reluctant to confront any interpersonal conflicts that may occur in the process B. B They believe that no one will want to leave the project C. The functional managers do not want the team

members to return D. The team members do not want to move on to new assignments

在项目收尾阶段,很多项目经理都倾向于尽可能推迟人员的重新分配,这是因为: A. 他们被迫面对这一过程中可能发生的人际冲突B.他们相信没有人想离开项目C.职能经理不愿意让项目成员回到

职能部门D.项目队伍成员不愿意转到一个新分配的岗位上

(23)The sponsor has asked you to require that each piece of the project scope be planned, estimated,

and scheduled. The sponsor also wants to authorize each piece of the project management plan after the

documentation is assembled. What is the MOST appropriate response to these requests? A. Politely advise the sponsor to forego the authorization of work. B. Provide the sponsor with a schedule of when the

components will be ready for authorization. C. Ask the sponsor to authorize each piece before it is

completed. D. Tell the sponsor that the chance for authorization will come after the pieces of the project

management plan are compiled.

发起人已经给你了要求关于项目每一部分的项目范围的规划、估算和进度。发起人也想在文档写完以后授权项目管理计划的每一部分。对于这些要求最合适的反应是什么?A.礼貌的建议发起人放弃授权

工作B.当组件将要准备授权的时候给发起人提供进度表C. 在它被完成的时候,让发起人授权每一部分D.告诉发起人在项目管理计划的每一部分被完成以后,将可以进行授权

(24)During project closure a project sponsor complains that the project did not increase the department’s

knowledge of Java programming and therefore, the project is not complete. The customer has accepted the

project. The project manager determines that all stated objectives and deliverables have been met. He does

not find evidence that Java programming was an objective. A review of project correspondence shows no

mention of the deliverable. The project manager should: A.begin project closure. B. re-plan the project to

include the new objective. C. meet with the team to discuss the issue and find a resolution. D. get the project stakeholders involved to help resolve the issue.

在一个项目收尾阶段,投资人抱怨该项目没有提升部门的Java编程知识,因此该项目没有完成,但客户已经接受该项目。项目经理确定所有的规定目标和可交付成果均符合要求,没发现把Java程序设计列为项目目标,回顾项目的相关信件表明没有提到过这一事项,项目经理应该: A. 开始项目收尾

B. 重新规划项目以包含新的目标

C. 召开团队会议讨论问题并寻求解决方案

D. 通过相关项目

干系人解决问题

(25)In the meeting with several project stakeholders, the stakeholders ask the project manager to widen

the working scope. The project manager once read relevant project letters before the project charter being

signed and she remembers that the sponsor has denied the working scope mentioned by these stakeholders.

What is the most proper deed the project manager should do: A. Let the project sponsor know the

requirements of stakeholders B. Assess the influence of increasing working scope C. Tell the project

stakeholders that the scope cannot be widen. D. Add this work if there is usable time in the project schedule plan.

在与几个项目干系人的会议中,干系人要求项目经理将项目工作范围内容扩大,这个项目经理曾经接触过章程签字前有关项目的来往信函,她记得项目发起人明确地否定了这些项目干系人提到的工作范围,项目经理最恰当的做法是:A.让项目发起人知道项目干系人的要求。B. 评估增加工作范围的影响。C.告诉项目干系人,范围不能扩大。D. 如果项目进度计划中有可用的时间,就加入该项工作。(26)If you are a project manager who signs a large project with government and this two-year project with several millions of dollars’ investment was signed six months ago, you have participated neither in the

contract negotiation of this project, nor in the stipulation of management change process, but now you should handle with the change proposed by the sponsor and organizational members. Who usually is responsible for the formal auditing of the major change of the project contract? A. Change control board B. Purchase

department C. Project manager D. Senior management你是一个与政府签约的大型项目的项目经理,这个

为期两年、投资数百万美元的项目在6个月前签约的。你没有参加该项目的合同谈判,也没有参加为管理变更制定程序,但是现在你陷入了应付来自发起人和组织内人员提出的变更之中。通常谁负责正式审

项目经理。D. 高级管理核对项目合同的主要变更?A.变更控制委员会。B.采购部门。C.

层。

(27)In an organization with strict hierarchy, the project manager is assigned to a very urgent important job. Under this circumstance, the best way to make an initial project charter is: A. Make a project charter by

holding a brainstorm meeting with potential team members and project stakeholders. B. Make a project charter and submit it to the potential team members and project stakeholders to ask for their opinions. C. Make a

project charter together with the project sponsor and hand it out to the potential team members and project

stakeholders. D. Make a project charter together with the functional manager and submit it to the sponsor for

his signing.

处在一个等级森严组织中,项目经理被分配到一个时间很紧的重要项目工作,在这种情况下制定一份初

始的项目章程的最佳的办法是:A.通过与潜在的团队成员和项目干系人召开头脑风暴会议制定项目

章程。B. 制定并向潜在的团队成员和项目干系人提交项目章程,征求他们的意见。C.与项目发

与职能经理一起制定项目章起人一起制定项目章程以便分发给潜在的团队成员和项目干系人。D.

程,然后提交发起人签字认可。

(28)You have a choice of four ongoing projects that you can take over as project manager. Project 1 has a benefit cost ratio (BCR) of 1.4, is a high priority project and has a critical path length of 16 months. Its cost

performance index (CPI) is 1.2. Project 2 has a schedule performance index (SPI) of 1.1, is using three critical

resources, has a low priority, and has a BCR of 1.1. Project 3 has a CPI of 1.2, an SPI of 0.89, a BCR of 1.6, and a

critical path length of 19 months. Project 4 has a CPI of 0.82, an activity with 33 days of float, a hard-to-get

resource assigned to activity L, and a priority of keeping cost low. Based on the above, which project would you prefer to take over? A. Project 1 B. Project 2 C. Project 3 D. Project 4

作为项目经理你可以选择4个正在进行的项目。项目1的效益成本率(BCR)是1.4,项目有很高的优先级,关键路径是16个月。它的成本绩效指数是1.2.项目2的进度绩效指数(SPI)是1.1,用3个关键资源,很低的优先级,BCR是1.1.项目3的CPI是1.2,SPI是0.89,BCR是1.6,关键路径长度是19个月。项目4的CPI是0.82,一个活动有33天的浮动时间,活动L上很困难的去分配资源,优先保持低成本。基于上面的信息,你优先承担哪个项目?A. 项目1 B. 项目2 C. 项目3 D. 项目4

(29)You are a project manager of an IT company. It is stipulated that when doing a project, the customers’requirements and the features of deliverables and performances shall be recorded in the configuration

management system. Here, the configuration management system refers to: A. Constraint B. Enterprise

environmental factors C. Summary of experience and lessons D. Assumed conditions

你是一家IT公司的项目经理。公司规定在做项目时,应将客户需求以及可交付成果的特征、性能记录

在配置管理系统中。在这里,配置管理系统是:A、制约因素B、事业环境因素C、经验教训总结D、

假设条件

(30)You are managing a petroleum engineering project with big risks. Now, you have successfully accomplished the first phase work. According to the project management theory in life cycle, the next step is

to: A. Audit risk management plan B. Audit deliverables and confirm its integrity and acceptability C. Officially

start the work of next phase D. Confirm the adopted management order in project phase

你在管理一个石油工程建设项目,该项目的风险很大。目前,你己成功完成了该项目第一阶段的工作。

根据生命周期中的项目治理理论,下一步你将:A、审查风险管理计划B、审查可交付成果,确定其完

整性和可接受性C、正式启动下一阶段的工作D、确定项目阶段要采取的管理稗序

(31)Over the last few weeks, the team has made three changes to the activities on the project. The project manager must be MOST careful to: A. Record all the changes. B. Provide documentation on all the changes to the sponsor. C. Make sure the changes are reflected in the project scope baseline. D. Prevent

more changes from occurring.

在过去几周里,团队成员对项目的活动做了三次变更。项目经理必须最小心什么?A.记录所有的变更。B.将所有变更文档提供给发起人。C.确保这些变更被反映在项目范围基准中。D.防止发生

更多变更。

(32)You’ve been assigned as a project manager on a research and development project for a new dental procedure. You are working out the project scope management plan. What is the purpose of the scope

management plan? A. It describes and documents a scope baseline to help make future project decisions. B.

It decomposes project deliverables. C. It describes how project scope changes will be incorporated into the project and how project scope will be managed. D. It describes how cost and time estimates can be

composed for project scope changes.

你被任命为一个新程序的研究发展项目的项目经理。你正在制定项目范围管理计划。范围管理计划的目

的是什么?A. 描述并记录了范围基准以帮助制定未来项目决策。B.分解项目可交付成果。C.

描述了如何估算成本与时间来应描述了如何管理项目范围以及如何将范围变化纳入项目。D.

对项目范围变更。

(33)Two months into a design project, the customer requested a modification to the product. The change was made without notifying the project manager. During the final testing phase, results were different than

what was planned for. This scenario is BEST thought of as an example of which of the following? A. Poor scope

control. B. Poor adherence to the communication management plan. C. Poor development of the quality management plan. D. Poor definition of the test plan.

项目设计开始了两个月,这时客户要求修改产品并在没有知会项目经理的情况下修改了产品。在最终测

试阶段,测试的结果与原计划要求不符。这个情况最可能是下列那项的例子?A.范围控制的不好。B.

没有遵守沟通管理计划。C. 质量管理计划制定的不好。D.测试计划的定义不好。

(34)All the following tools and techniques are helpful to accurately confirming customers’needs, except:

A. Affinity diagram

B. Questionnaire

C. Fishbone diagram

D. Prototyping approach

以下工具和技术都有助于准确界定客户需求,除了:A、亲和图B、问卷调查C、鱼骨图D、原型法

(35)After the completion of a new software function, the client complains that the function application is not comply with their expection.The quality control team successfully passes the test and the project team understand the function description well. What is the possible reason of this situation? A. The client did not receive the function description. B. The acceptance criteria was not sufficient developed, which the project stakeholder did not agreed with C.Not yet consider the risk which the client may not accept the function D.

The function description was not detail enough

一个新软件功能的实施完成后,客户抱怨该功能的实现与预期不符。质量控制团队成功地通过了所有测试,项目团队也理解该功能描述。出现这种情况的最可能原因是什么?A. 客户没有收到功能描述。

B. 验收标准的制定不够充分,也未得到项目干系人的同意。

C. 没有考虑到客户可能不接受该功

能的风险。D. 功能描述的不够详细。

(36)What is the document that forms the basis for an agreement between the project team and the project customer by identifying both the project objectives and the major project deliverables? A.

Implementation Plan B. Configuration Management Plan C. Project Scope Statement D. Work Authorization Plan

下列哪种文件是项目队伍与项目客户之间通过确定项目目标及主要的项目可交付成果而达成协议的基础? A. 实施计划B.配置管理计划C.项目范围说明书D. 工作授权计划

(37) A client has asked you to add to the scope of the project. The project is under budget and a little

ahead of schedule. When scope change comes into light, what should you often need to adjust? A. Change

control system. B. Time, cost, quality or other project deliverable facts. C. Scope change management. D.

Time, quality and lessons learned.

一个客户要求增加项目范围,该项目没有超支、进度比计划稍提前,当出现范围变更时,你通常需要调

时间、成本、质量或其他项目交付要素。C.范围管理计划。D.

整什么?A.变更控制系统。B.

时间、质量和吸取的教训。

(38)If a project team is subdividing project work packages into smaller, more manageable components, they are: A. Creating a WBS. B. Decomposing. C. Network diagramming. D. Activity sequencing.

如果项目团队将项目工作包细分为更小的更易于管理的部分,他们是:: A. 编制WBS。B. 分解

C. 绘制网络图

D. 给活动排序

(39)Your customer signed off on the requirements definition document and scope statement of your video game project last month. Today she requested a project scope change. She would like to make it an

interactive game that can be played on a person’s television and on a computer. This represents a scope change that, at a minimum A.Modifies the project’s agreed-upon scope as defined by the WBS B.Results in a change to all project baselines C.Requires adjustments to cost, time, quality, and other objectives D.

Results in a lesson learned

你在负责管理一个视频游戏的项目。上个月客户已经签署项目需求说明和范围说明。但是现在她提出了一项范围变更要求。她希望把这个游戏做成一种在电视和电脑上都能玩的互动式游戏。这种范围变更至少会表现在哪一个方面? A.对己批准的WBS项目范围做修改。B.导致所有项目基线的变更C.需要对成本、时间、质量以及其他目标进行调整D.得到一个经验教训

(40)You are assigned as a project manager to lead a new quality improvement project. Management is asking for a project plan. Which of the following should you create FIRST? A. Project scope statement B.

Quality plan C. Schedule D. Risk plan

你被分配为一个新的质量改进项目的项目经理。管理层要求创建一个项目计划。下面哪项是你必须先创建的?A. 项目范围说明书B. 质量计划C.进度表D. 风险计划

(41)The client agreed with the project scope statement at the beginning of the project, during the execution some more functions were requested and added. The uncontrolled scope changes are often referred to as A. Out of statistic control. B. Scope creep. C. Gold plating. D. Meet the stakeholder’s expectation.

客户在项目初期同意项目范围说明书,但是在项目实施期间要求增加产品功能。这些未得到控制的范围变更通常被称为:A.统计失控。B. 范围蔓延。C. 镀金D.满足干系人的期望

(42)Which of the following is not a good characteristic of an effective project objective? A. Specific completion date. B. Measurable C. Definitive associated costs D. Inconsistent with strategic organizational

objective.

下面哪项不是一个有效的项目目标的特征?A.具体的完成日期B.可衡量的C.确定性的相关成本D.与

组织战略目标不相一致

(43)The project team and their client fight for a long time for a quality acceptance standard and finally agree with the project deliverables and the measures for project success, which should be documented in

________? A. Quality checklist. B. Scope statement C. Project charter D. Project Code of accounts

项目团队和客户就一项产品的质量验收标准争论了很久,最终就项目的可交付成果和衡量项目成功的标准达成共识,这些应记录在哪里________?A. 质量核对表B. 范围说明书C. 项目章程 D.

质量测量指标

(44)The work breakdown structure is created by: A. The team B. The project manager C.

Management D. The sponsor

工作分解结构由谁来编制:A.团队B.项目经理C.管理层D. 发起人

(45)One of examples of scope verification is A. Review the performance of an installed software module B. Managing changes to the project schedule C. Review an installed software module to

validate defect repairs D. Performing a benefit/cost analysis to determine if we should proceed with the

project

核实范围的一个实例是: A.检查一个已安装的软件模块的特性。B.管理对项目进度计划的变更。C.

检查已安装软件模块的缺陷修复情况。D. 进行收益/成本分析以决定项目是否进行下去。

(46)( ) contains detailed descriptions of work packages. A. WBS Dictionaries B.Scope of work C.

Budget estimates D. Cost estimates ( )

包含了工作包的详细说明。A.工作分解结构词典B.工作范围C.预算估计D.成本估算

(47)The process of creating a work breakdown structure results in? A. A project schedule B. Team

buy-in C. A project completion date D. A list of risks

创建工作分解结构过程的结果是: A.项目进度计划B.团队共识C.项目完成日期D.风险清单(48) A project manager may use ( )to make sure the team clearly knows what work is included in each of the tasks A. A project scope of work B. A project charter C. A WBS dictionary D. A task management

plan

项目范围说明书 B.

项目经理可能会用( )来确保团队清楚地了解每项任务包括的工作内容。A.

项目章程C.工作分解结构词典D.任务管理计划

(49) A work package is a A. Deliverable at the lowest level of the WBS B.Task with a unique identifier C.

Required level of reporting D. Task that can be assigned to more than one organizational unit 工作包是: A.工作分解结构最低层次的可交付成果B.具有惟一标识的任务C.

报告的要求水平D.

可以被分配到一个以上组织单位的任务

(50)Which one of the following is the critical input to identify risks? A. Acceptance criteria B. Scope baseline C. Risk register D. Scope creep

下列哪项是识别风险的关键输入?A.验收标准B.范围基准C.风险登记册D.范围蔓延

(51) A project manager is scheduling a project where the performing organization has currently many projects and there are serious resource conflicts among other projects.In this environment, which tool is the least effective? A. Critical Chain Method B. Reverse resource allocation C. CPM D. Simulation

项目经理正在安排一个项目进度,与此同时公司有几个同时进行的项目,并且该项目与其他项目之间存在着严重的资源冲突,在此情形下,哪个工具最无效?A.关键链方法B. 储备资源分配C.关键路径法D. 模拟

(52)The project sponsor has approached you with a dilemma. The CEO announced at the annual stockholders meeting that the project you’re managing will be completed by the end of this year. The problem is that this is six months prior to the scheduled completion date. It’s too late to go back and correct her mistake, and stockholders are expecting implementation by the announced date. You must speed up the delivery date of this project. Your primary constraint before this occurred was the budget. What actions can you take to help

PMP模拟题习

speed up the project? A. Hire more resources to get the work completed faster. B. Ask for more money so that you can contract out one of the phases you had planned to do with in-house resources. C. Utilize negotiation and influencing skills to convince the project sponsor to speak with the CEO and make a correction to her announcement. D. Examine the project plan to see if there are any phases that can be fast tracked, and then revise the project plan to reflect the compression of the schedule.

项目发起人已使你进入一个进退两难的阶段。CEO在一年一次的股东大会上宣布了你负责的该项目必须在今年年底前完成。问题是这比计划完成时间提前了6个月。回头更改错误都太晚了,并且股东要求按宣布的日期完成项目。你必须提前项目交付日期。在此发生前你的主要约束是项目预算.你采用哪种方法来加快项目进程?A.用更多的资源来加快工作完成B.申请更多的资金以便将本应该内部完

成的工作外包出去C.利用谈判和影响力技巧说服项目发起人去告诉CEO更正她的声明D.检查项目计划看是否有阶段能够快速跟进,然后更新项目计划反映进度的压缩

(53)The total float for a path is -20 (minus 20) days. What may this mean? A. The critical path must be

evaluated to determine the actual float. B. Project is expected to finish 20 days earlier. C. Each activity has -20 days float D. Duration Compression may be required to satisfy the project completion.

一条路径的总时差是负20天,它的含义可能是什么?A. 必须对关键路径进行分析以确定实际总时

每个活动时差为负20天D.为了达到项目完工工期,需要压缩差,B.项目预期会提前20天完成C.

历时

(54)You are busy completing the software development project, suddenly the client requested you to

deliver the product earlier as their competitor would launch a new product at the same time. If you decider to crash your project, you would focus attention on A. All non-critical activities. B. Only those on the critical path without concern for cost C. Accelerating performance by minimizing cost D. The critical activity with

the least cost first.

你正忙于实施软件开发项目,突然,客户要求你提前交付产品,因为他们的竞争对手也会同时推出一个新产品。如果你决定为项目赶工,你应该集中精力于: A. 所有非关键的活动B.不惜成本,仅考虑关键路径的活动C.通过减少成本来加速绩效D. 首先考虑花费最少的成本在关键活动上

(55)Which of the following BEST describes the relationship between standard deviation and risk? A.

Nothing B. Standard deviation tells you if the estimate is accurate. C. Standard deviation tells you how unsure the estimate is. D. Standard deviation tells you if the estimate includes a pad.

下面哪一项最好地描述标准差和风险之间的关系?A.没有B.标准差告诉你估算是否准确C.标准

差告诉你估算多么不确定D. 标准差告诉你估算是否包括故意拉长

(56)After analyzing the status of your project, you determine that the project is two weeks behind

schedule. You want to recover the original schedule if possible, and there is plenty of remaining budgets in the current plan. What is the BEST option? A. Crash the schedule. B. Inform the team that overtime will be required for a short time to recover the schedule. C. Reduce the project scope with a change request. D.

Compress the testing and quality management portion of the project.

在分析了你的项目的状态以后,你确定项目落后进度计划2周。如果可能,你想恢复原先的进度,并且在当前的计划中有足够的剩余预算。最好的建议是什么?A. 赶工进度B.通知团队为恢复进度将要求短期加班C.用一个变更请求减少项目范围D. 压缩项目的测试和质量管理部分

(57)When the project manager completes the detailed project schedule, it would be MOST important to

get it approved by the: A. Project sponsor. B. Team. C. Functional managers. D. Customer.

当项目经理完成详细的项目进度时,得到谁的批准将是最重要的?A. 项目发起人B. 团队 C.

职能经理D.客户

(58) A project deadline is the end of the year. The project consists of two activities.Activity A has a duration

of two months and activity B has a duration of three months. Activities A and B can be performed concurrently.

The start date for the project is set for the beginning of July. What is the MAXIMUM duration for the critical

path? A. Two months B. Three months C. Five months D. Six months

某项目的完成时间是年底,项目由两个活动组成。活动A的历时为两个月、活动B的历时为3个月。活动A和B可以并行进行。项目开始日期设在7月。项目最长情况下的关键路径历时是多少。A.2 个月B. 3个月C. 5个月D. 6个月

(59)The customer on a project tells the project manager he has run out of money to pay for the project.

What should the project manager do FIRST? A. Shift more of the work to later in the schedule to allow time

Enter project closure. C. Stop work. D. Release part of the project for the customer to get the funds. B.

team.

项目的客户告诉项目经理他已经花光了支付此项目的所有钱。项目经理首先应该做什么?A. 移动更多的工作到进度后期,以为客户留出时间获得资金B.

进入项目收尾C.停止工作D.释放一部分项目团队成员

(60)During the planning processes, activity G was estimated to take five days.activity G is on the critical

path. On day 2, it becames clear that activity G would take 15 days, which will impact the imposed project end date. The project team meets to perform root cause analysis to identify the cause of the variance and to plan schedule recovery with activities performed later in the schedule. Which of the following should ALWAYS be

WBS updates C. Activity list the output of this kind of meeting? A. Recommended corrective action B.

updates D.

Schedule updates

在规划期间,活动G的历时估算为5天,该活动在关键路径上,开工第二天,就很清楚知道活动G要花15天,这会影响项目的强制完工期。项目团队开会分析产生偏差的根原因并计划采取措施在随后的

建议的纠正措施B. WBS更新C.活动实施来恢复进度。下列哪项总会是这类会议的输出?A.

清单更新D.进度更新

(61) A project plan results in a project schedule that is too long. If the project network diagram cannot

change but you have extra personnel resources, what should you do? A. Fast track the project B. Level the resources C. Crash the project D. Perform a value analysis

一个项目规划的结果发现项目的规划进度要比预计要求的进度表需要更多时间,如果项目的网络图不能

够修改,但是你有额外的职员资源,你应该做什么?A.

此项目D.

-23进行价值分析

快速跟进此项目B. 资源平衡C.赶工

(62)If activity A has 15 days of free float and 25 days of total float, and the early start date of activity A is delayed 30 days, how is the project affected? A. The next dependent activity’s start date will be delayed 15

days. B. The duration of the activity will be shortened 15 days. C. The completion date of the project will

be pushed out 5 days D. Both A and C.

如果活动A有15天的自由浮动时间和25天的总浮动时间,并且该活动的最早开始时间延迟了30天,

对项目有什么影响?A. 下一个依赖的活动会延迟15天B. 该活动的历时会缩短15天C. 项目

会推迟5天完成D. A和C

(63)Which of the following is a benefit of an analogous project estimate? A. The estimate will be closer to what the work will actually require. B. It is based on a detailed understanding of what the work requires.

C. It gives the project team an understanding of management’s expectations.

D.It helps the project

manager determine if the project will meet the schedule.

下列哪个是类比的项目估算的一个好处?A.估算将比较接近工作真实需要的B.它基于工作要求的

详细理解C.它给项目团队一个管理层期望的理解D.它帮助项目经理确定项目是否符合进度

(64)During planning you discover that the time needed to complete the project is longer than the time available. What do you do? A. Contact the customer and tell them that their required date can not be met.

B. Meet with management and tell them that their required date cannot be met.

C. Crash or fast track

the project D. Crash or fast track the project and go to management with options

在计划编制过程中,如果你发现项目完成所需时间超过了可利用的时间,你该做些什么呢? A. 与客

户碰头,告诉他们不能按要求的日期完成B.与管理层会面,告诉他们不能按要求的日期完成C.

项目进行赶工或快速跟进D. 项目进行赶工或快速跟进,并且向管理层提出选择方案

(65) A task has an early start of day three, a late start of day 13, an early finish of day nine, and a late finish of day 19. What is the task’s float? A. 10 B. 6 C. 3 D. 19

一个活动最早开始日期为第3天,最迟开始日期为第13天,最早结束日期是第9天,最晚结束日期是

第19天。这个任务的历时是?

A.

B.

C.

D. 7 6 3 19

(66)Activity A has duration of 3 days and begins on the morning of Monday the 4’". The successor activity, B, has a finish-to-start relationship with A. The finish-to start relationship has 3days of lag, and activity B has duration of 4 days. Sunday is a non work day. What can be determined from these data? A. The total

duration of both activities is 8 days. B. Calendar time between the start of A to the finish of B is 11 days. C. C

The finish date of B is Wednesday the 13’". D.Calendar time between the start of A to the finish of B is 14

days.

活动A工时为3天并开始于星期一早晨,4号。后继活动B与A具有完成--开始依赖关系。完成--开始关系有3天的滞后,而且活动B工时为4天,星期日是非工作日。从这些数据可以得出什么结论? A.

活动B完成日两项活动总工时为8天B.活动A开始到活动B完成之间的日历时间是11天C.

期是星期三,13号D.活动A开始与活动B完成之间的日历时间为14天

(67) A project has five activities: A, B, C, D, E. A can start anytime, A takes three days, B takes fifteen days and C takes ten days. B and C will start after A is completed and B can be completed before D start. D takes

fifteen days. D can be completed before E can start. E takes five days. C and E must be completed for the project

to be completed. This information for question 67-68

一个项目有5个活动:A, B, C, D, E。A可以随时开始,活动B和C可在活动A完成后开始,活动A历时3天,活动B历时15天,活动C历时10天。活动B可在活动D开始前完成。活动D历时15天,活动D完成可开始活动E,活动E历时5天,活动C和E的完成表示项目完成。运用此信息回答67 68题67.If the project team chose a way to fast track the project by starting activity D five days after activity B has

started, and working both activities in parallel for 10 days. How will this affect the project? A. The project will

complete ten days sooner B. The critical path will not change C. The project will complete five days sooner D.

The float of activity C will be reduce

(67题接上题的问题)如果项目团队选择了快速跟进的方法,在活动B开始5天后启动活动D,然后用10天同时运作两个活动。这对项目有什么影响A.项目会提前十天完成B. 关键路径不变C.

项目会提前5天完成D. 活动C的浮动时间将会减少

(68)If project team add F activity after activity C, activity F takes fifteen days ,if activity F delay two days for completion, How will this affect the project? A. The project delay for 2 days B. No impact for the

critical path. C. The critical path changed. D. The project float increase 2 days

(68题接上题的问题)如果项目团队在活动C完成后增加活动F,活动F的历时是15天。假如活动F 推迟两天完成。这对项目有什么影响?A. 项目延迟2天完成。B. 关键路径没有改变。C.

关键路径改变了。D.项目浮动时间增加了2天。

(69)An activity has an early start date of the 10 and a late start date of the 19. The activity also has duration of 4 days. There is no weekend. From the information given, what can be concluded about the activity?

A. Total float for the activity is 9 days.

B. The early finish date of the activity is the end of the day on the l4.

C. The late finish date is the 25

D. The activity can be completed in 2 days if the resources devoted to it

are doubled.

一项活动最早开始日期为10号,最晚开始日期为19号,该活动的历时为4天。没有周末休息日。根据

已知信息可得出该活动: A.该活动的总浮动时间为9天B.该活动的最早完成日期为14号那天结束时

C. 最晚完成日期是25号

D. 如果投入到该活动的资源加倍的话,活动可以在2天内完成

PMP模拟题习

(70)Rearranging resources so that a constant number of resources is used each month is called: A.

Crashing. B. Floating. C. Leveling. D. Fast tracking.

重新安排资源,以便每月使用常数数目的资源,这叫做:A. 赶工B.浮动C.平衡D.快速跟进(71)If the optimistic estimate is one, the pessimistic estimate is nine, and the most likely estimate iseight,

what is the three point estimate? A. 9 B. 7 C. 8 D. 3

如果乐观估算为1,悲观估算为9,最可能的估算为8,那么通过三点估算法计算的结果为? A. 9 B. 7

C. 8

D. 3

(72)You are a project manager of an engineering design project. During planning activity, you and your

attributes. B.

team should check which of following to see the potentially available resources? A. Activity

Activity calendars. C.

Activity list. D. Enterprise environmental factors.

你是一个工程设计项目的项目经理,当作活动计划时,你和团队应查看下列哪项来了解可用资源的周期、能力和技能等信息?A. 活动属性B.资源日历C.活动清单D.事业环境因素

(73)When planning resources, if one activity needs more resource and only lower-skilled resources are available to be assigned to the activity, what affect on the activity? A.Activity starts and end dates B.

Expected durations C. Dependencies

当规划资源时,如果项目的某个活动需增加人员,而仅有低技能的人员可分配给该活动,除了哪项以外

需增加培训时间B. 会降低活动的生产率C. 活动成本都是对规划该活动可产生的影响?A.

会降低D.

-23需要投入更多的协调时

(74) A project manager received executive orders to deliver the project two weeks earlier than scheduled, doing whatever it takes. He decided that the least costly means would be to add resources to critical path

activities in order to shorten the time of those activities. In this case, the project manager has: A. Fast

tracked the critical path part of project schedule. B. Decomposed the critical path WBS. C. Leveled

resources. D. Crashed the critical path.

项目经理接到一个执行的命令,要求交付的项目要比计划早2个星期,不论做什么。他决定最省钱的方法是将资源添加到关键路径活动中,这样可以缩短这些活动的时间。在这种情况下,项目经理:A.

快速跟进项目进度中的关键路径B.重新分解关键路径的WBS C. 资源平衡D.赶工关键路径(75)25. A project manager knows that she can delay the start of certain activities within the project schedule to coincide with the mitigation of a known risk. She knows exactly the work and duration needed,

should the risk event occur. She is confident that the finish date will not be impacted by the time delay. Which

of the following aspects of schedule development has the project manager used in this situation? A. She

has relied on her certainty that, for risk planning purposes, assumptions are considered to be true, real, or

certain. B. GERT probability factors provide her with certainty that there will be activities in the current

schedule that will not be performed at all. C. Her float calculations have revealed those activities that

allow sufficient time for the inserted activities. D. The project manager’s risk management plan was to build in buffer time to all the project activities during schedule development in order to cover any risk event

occurrence.

项目经理知道她可以延迟项目进度中某些活动的开始时间以减少已知风险。她知道确切的风险发生的工作和持续时间。她坚信完成日期将不被时间延误所影响。在这种情况下,项目经理已经使用了进度开发方面的哪一项?A. 她依赖于对风险规划目标,假设是真实的,正确的,肯定的B. GERT的概率给她提供了一个肯定,在目前的进度表里不是所有的活动都被执行C.她的浮动计算已经显示插进来的

活动允许有充足的时间D.项目经理的风险管理计划是在进度开发的时候为项目的所有活动都留有缓

冲时间,这是为了防止风险事件的发生

(76) A project manager is trying to coordinate all the activities on the project and has determined the following: Activity 1 can start immediately and has an estimated duration of 1 week. Activity 2 can start after activity 1 is completed and has an estimated duration of 4 weeks. Activity 3 can start after activity 2 is completed and has an estimated duration of 5 weeks. Activity 4 can start after activity 1 is completed and has an estimated duration of 8 weeks. Both activities 3 and 4 must be completed before the end of the project. What is the

duration of the critical path for this project? A. 10 B. 11 C. 14 D. 8

项目经理正在协调所有的项目活动,并确定了下面:活动1能立即开始,估算的周期是一个星期。活动2可以开始在活动1完成之后,估算的周期是4个星期。活动3能开始在活动2完成之后,估算的周期是5个星期。活动4开始在活动1完成之后,估算的周期是8个星期。活动3和4在项目结束前必须完成。对于这个项目关键路径上的持续时间是多少?A. 10 B. 11 C. 14 D. 8

(77)During its first winter, a multi-year construction project experienced weather-related schedule delays that all the local parties involved described as typical for this area. What should the project manager do to

integrate this information into the project schedule? A. Lengthen the estimated activity duration for all activities scheduled to occur the following winter. B. Reevaluate the schedule to determine the potential

impact. C. Leave the current project schedule unchanged and work the issues as they arise next year. D.

Make changes to the project management plan in order to maintain the current project schedule.

一个历时几年的建筑项目在项目的第一个冬季由于天气原因造成了进度延误,所有当地参与方都说,在这个地区这是很典型的情况。要把这个信息集成进项目进度计划,项目经理应该做什么?A. 把以后几年冬季要发生的所有活动的估算历时都加长。B.重新评估修改过的进度计划,确定潜在的影响。

C. 现行的项目进度计划保持不变,等下一年这个问题发生时再解决。

D. 为了保持现行的项目进

度计划,修改项目计划。

(78) A project manager holds a meeting with his manager to explain that an activity has been delayed and the project manager will need additional resources to complete the project. The manager stops the meeting

because the project manager has forgotten something. What might it have been? A. To investigate undoing previous fast tracking activities B. To try to compress the project schedule before asking for

additional resources C. To look for options with the customer before meeting with management D. To

eliminate float in the near-critical path

项目经理和他的经理开会解释一个活动已经延期,项目经理需要额外的资源完成项目。经理停止了这个

会议,因为项目经理忘记了一些事情。这有可能是什么?A. 调查撤销先前快速跟进的活动B.

消除次关在请求额外资源前试图压缩项目进度C.在与管理层开会之前,寻找客户的观点D.

键路径的浮动

(79)Although you have tried to plan the project to accommodate all major contingencies, you are now asked for the fifth time to decrease the length of time the project will take to complete. The person completing

activity C is no longer talking to you because of the added work she needed to do to accommodate previous

decreases in time. She has already told you she cannot shorten her activity any more. The person doing activity

D has been replaced by a new and less tested resource. The risk of crashing activity F is small. Based on this and

the chart, what is the BEST thing to do? A. Determine why there have been so many decreases to the project

length. B. Invite the person doing activity C to lunch to talk about her problems. C. Evaluate the risk added to

the project with the change of resources on activity D. D. Make changes to the project to decrease the time

the project will take.

虽然你试图规划项目以适应所有主要的突发事件,但是你现在是第五次要求缩短项目完成时间的长度。

完成活动C的这个人不再和你说话,因为她需要增加的工作量以适应先前减少的时间。她告诉你她不能

再缩短她活动的时间。正在做活动D的人已经被一个新人所代替,并减少了测试资源。与活动F冲突的

风险是小的。基于这个情况和图,最好要做的事情是什么?

A. 确定为什么在项目长度上有如此大的减少

B.邀请做活动C的这个人一起吃饭,谈论她的问题

C.

评估在活动D资源的改变给项目带来的风险D. 做变更以减少项目花费的时间

(80) A team member comes to you to tell you that there is a problem on her activity. It cannot be started on the day it is scheduled to start. A manager overhears this conversation and reports that the project will be

late. Later the project manager completes his own report saying "the project is still scheduled to be completed

on time." Which of the following could be the reason the project manager made such a statement? A. The

activity has free float and can be rescheduled later in its early-start to late-finish window. B. The activity is

on a near-critical path with less float than the length of the delay. C. The activity is on the critical path but is to

be done after another activity that does have float. D. The activity has a mandatory dependency, allowing the

project manager to place it in the project schedule at any location that he wants it to be done.

一个团队成员来找你告诉你在她的活动上有一个问题。她不能按照计划上的日期开始。一名经理无意间

听到这段报告的对话,项目将延期。在这之后项目经理在他报告中说:“项目仍然是按照计划进行的,

能够准时完成。”下面哪一项是项目经理陈述这个说明的原因?A. 活动有自由浮动,并能够在它的最早开始和最晚完成之间进行重新排定B.活动在次关键路径上,浮动时间要少于延期的时间长度C.

活动在关键路径上,但是要在另外一个有浮动时间的活动完成之后才能做D.活动有一个强制性依赖,允许项目经理把它放置在他所希望的项目进度计划的任何地点

(81)Your company can accept three possible projects. Project A has an NPV (net present value) of US

$30,000 and will take six years to complete. Project B has an NPV of US $60,000 and will take three years to

complete. Project C has an NPV of US $90,000 and will take two years to complete. Based on this information,

which project would you pick? A. They all have the same value. B. Project A C. Project B D. Project C 你的公司可接受三个可能的项目,项目A的净现值(NPV)为$30,000需要6年完成;项目B的净现值(NPV)为$60,000需要3年完成;项目C的净现值(NPV)为$90,000需要2年完成,基于上述信息,你会选择哪个项目?A. 每个都一样B. 项目A C.项目B D.项目C

(82)There are two projects to choose between: Project A with an NPV of US $45,000; or Project Bwith an

NPV of US $85,000. What is the opportunity cost of selecting project B? A. US $45,000 B. US $85,000 C.

US $40,000 D. US $130,000

有两个项目可以被选择:项目A净现值(NPV)为45,000美元;项目B净现值(NPV)为85,000美元.选择项目B的机会成本是多少?A. US $45,000 B. US $85,000 C. US $40,000 D. US $130,000

(83) A cost management plan contain a description of: A. The project costs. B. How resources are allocated.

C. The budgets and how they were calculated.

D. The WBS level at which earned value will be calculated. 3.

成本管理计划描述了:A.项目成本。B.资源如何分配。C.预算及其计算方式。D.在WBS的哪个层级进行挣值计算。

(84)Your manager asks you to take over one of four projects. If you had the following information, which

project would you select? A. Project A with an IRR of 10% B.

Project B with an IRR of %12 C. Project C with an IRR of 15% D.

Project D with an IRR of 21%

你的经理希望你接手四个项目中的一个,如果你了解这四个项目的下列信息,你会选择哪个项目?A.

项目A的内部收益率IRR为10% B.项目B的内部收益率IRR为12% C.项目C的内部收益率IRR为15% D.项目D的内部收益率IRR为21%

(85)Which term describes those costs in a contract that are associated with two or more projects but are

not traceable to either of them individually? A.Variable B.Direct C.Indirect D.Semi variable 一个合同所规定的成本中有一部分的内容可能牵扯到多个项目,但是却不能把这部分成本归为哪一

个项目的花费,这部分成本叫做什么: A.变动成本B.直接成本C.间接成本D.半变动成本

(86)You are having difficulty estimating the cost of a project. Which of the following BEST describes the

PMP模拟题习

most probable cause of your difficulty? A. resources C.

Difficulty in scheduling D. Inadequate scope definition B.

Lack of adequate budget

Unavailability of desired

你在估算某个项目成本时遇到些困难。下面哪项最好的描述了出现这些困难的大多数原因?A.不充分的范围定义B.想要得到的资源不可用C.进度规划中的困难D.缺乏足够的预算

(87) A cost baseline is a product of: A. resource planning. B. cost estimating. C. cost budgeting. D.

cost control.

成本基线是下列哪个过程的输出:A. 资源规划B.成本估算C.成本预算D.成本控制

(88)You have been assigned as the project manager on a new project. The organization uses a strong

matrix structure. You need to purchase computers to do the project. This is an example of: A. Limited cost. B.

Diminishing cost. C. Fixed cost. D. Indirect cost.

你被分配为一个新项目的项目经理,这个组织使用的是强矩阵结构,你需要采购电脑用在此项目。这是一个什么成本的例子?A.有限成本B.逐渐缩小的成本C. 固定成本D.非直接成本

(89)Which of the depreciation methods offers the least tax advantage? A. Double declining balance

B. straight line

C. Sum of the years digit

D. Salvage value

下列哪种折旧方法享受的税收优惠最小?A.双倍余额递减法B. 直线法C. 年数总和法 D.

折余值

(90)Analogous estimating: A. Uses bottom-up estimating techniques B. Is used frequently during

the Execution Phase of the project C. Uses top-down estimating techniques D. Uses actual historical costs

类比估算A.采用了自下而上的估算技术B.最常用于项目执行阶段C.采用自上而下的估算技术D.

采用实际历史成本

(91)In order to establish the budget,all of the following needs to evaluated except: : A. Contingency

costs B. Sunk costs C. Diract cost D. Indirect cost

为了建立预算,必须评估下列所有的需求,除了:A.应急费用B.沉没成本C.直接成本D.间接

成本

(92)All the following statements about analogous estimating are true except that it- A. Supports top-

down estimating B. Is a form of expert judgment? C. Has an accuracy rate of ±10 % of actual costs D.

Involves using the cost of a previous, similar project as the basis for estimating the cost of the current project

下面关于类比估算的描述哪一项是不正确的?A.它支持自上向下的估算B.它是专家判断的一种形

式C. 它能够精确到与实际成本相差±1 0 % D.它使用以前类似的项目成本为基础,对现在的项目成本进行评估

(93)It is expensive to lease office space in cities around the world. Office space can cost approximately

PMP考试模拟试题(40题)

考前模拟试题 Disclaimer: These questions are intended for study purposes only. Success on these questions is not indicative of success on the Project Management Professional Certification Examination. This download of the Sample Exam Questions is for your personal use and NOT FOR commercial use. Any unauthorized use or duplication of this document is prohibited! 1. A narrative description of products or services to be supplied under contract is called: a. The project plan. B. A statement of work. C. An exception report. D. A Pareto analysis. 2. An example of scope verification is: a. Reviewing the performance of an installed software module. B. Managing changes to the project schedule. C. Decomposing the WBS to a work package level. D. Performing a benefit/cost analysis to determine if we should proceed with the pro 3. Which of the following is not an example of a source of scope change? A. A variation in government regulations. B. Failure to include a required feature in the design of a telecommunication system. C. A need to engage in bottom-up cost estimating. D. Introducing technology that was not available when scope was originally defined. 4. The subdivision of major project deliverables, as identified in the scope statement, into smaller, more manageable components is called: a. Parametric estimation. B. Scope definition. C. Feasibility analysis. D. Benefit-cost analysis. 5. The process of establishing clear and achievable objectives, measuring their achievement, and adjusting performance in accordance with the results of the measurement is called: a. Strategic planning. B. Alternative objectives inventory. C. Management by objectives. D. Contingency planning. 6. Configuration management is: a. Used to ensure that the description of the project product is correct and complete. B. The creation of the work breakdown structure. C. The set of procedures developed to assure that project design criteria are met. D. A mechanism to track budget and schedule variances. 7. A fundamental tenet of modern quality management holds that quality is most likely to be

PMP模拟试题(二)

PMP考前模拟试题(二) 1、哪种技术近定义产品需求: A.焦点小组会议 B.访谈 C.引导式研讨会 D.群体创新技术 2、项目经理已经完成了项目干系人识别,这时市场部经理为提高产 品对顾客的吸引力而提出新需求,并要求项目经理与他做访谈沟通,访谈有助于定义可交付成果的: A.可度良性 B.可验证性 C.可实现性 D.特征和功能 3、作为项目经理,你意识到估计进度表活动成本包括完成评估每一 进度活动所需的资源成本的近似值。在近似成本中,评估者认为成本估计可能多变的原因包括风险。成本估算包括识别和考虑多方面的选择性成本,例如:在多数应用领域内,附加工作在设计阶段被广泛运用以潜在的减少执行和生产成本。成本估算过程认为,不管额外的设计工作是否能抵消成本估算,都被普遍运用在流通单位以促进通过项目比较。成本估计也有益于项目过程的精细,反映在尽可能的附加细节中。对你的项目而言,在启动阶 段,你的团队建议进行一个量级估算,该估算的大概准确范围大概为: A.-50至+50% B.-10至+10% C.-5至+5% D.上述都不正确 4、最近你从另一项目经理那里接手了一个大型项目,他因为个人的 突发事件离开了。你想知道项目关系人分别获得何种信息,通过什么方法来获得这些信息,你会在哪里找这些信息:A.项目管理计划 B.执行报告 C.项目文件

D.沟通管理计划 5、你正在考虑是买还是开发一个软件产品。如果买的话,要花 80000美元,将其集成到你公司内的成本为1000美元。如果自己开发的话,需要7个软件工程师工作3个月,每位的薪水是4000美元/每月,这个项目的管理成本为2000美元。你将会如何选择:A.买 B.开发 C.既不开发也不不买 D.在做决定前需要更多的补充信息 6、范围说明书的目的不包括下列哪个选项? A.为未来的项目执行提供基础 B.在项目团队和顾客间建立共识 C.建立标准来决定一个项目和阶段是否已经成功完成 D.建立项目约束和假设(章程) 7、在项目计划阶段让客户参与 A.通常不予推荐因为客户不了解足够的项目管理知识 B.由于他们更熟悉项目内情,这样能够带来更好的计划 C.仅提供一些互相的谅解,但是通常介入项目的客户仅有有限权威D.通常使局势混乱 8、你在研究可选方案,确定些行动来提高达成项目目标的机会并降 低威胁的过程之中。下一步你需要做什么? A.确定哪些会影响项目的风险并记录它们的特点 B.对新出现的风险进行识别,分析和规划 C.确定如何为项目管理风险 D.根据风险发生概率对已识别的风险评估优先级 9、在你的新公司,你了解到一些财务综述没有遵循US GAAP财务 标准,因此是错误的。在这种情况下,你首先需要做什么?A.将你公司所进行的不正确的财务活动通知US政府代理机构B.告诉你的财务经理为什么你认为他们或许违反了财务标准C.因为你是这个公司的新人,你假设在公司内财务标准是不同的,所以你不需要做任何事 D.和你以往公司的财务经理交谈获得他对此事的专家判断

PMP考试试题及答案解析

2016年PMP考试试题及答案解析(一) 下面是由PMP学院整理的PMP考试试题及答案解析(一),希望能帮助学友们。 试题 1、以下哪项基准可用于评估请求的变更或额外的工作是否包含在项目边界之内? A、项目管理计划 B、项目范围说明书 C、项目范围管理计划 D、工作分解结构词典 正确答案:B 试题解答:项目边界通常识别项目所包括的内容,并且在干系人可能假定某特定产品、服务或成果会是项目组成部分的情况下,明确说明项目不包括的内容。项目边界被描述为详细的项目范围说明书的一部分内容。【规划】____项目管理协会,《项目管理知识体系指南》,2008年。 2、During the execution phase of the project,you realized the subcontractors are working with incomplete and different scope statements.As the project manager,what should you do FIRST? A.check the work completed against the correct scope statements B.review the scope of work with the stakeholders C.document the inconsistencies to management,calculating the cost of non-conformance D.stops all activities until the scope of the work is complete 2、在项目执行阶段,你发现分包商在按照不完整并且不同的范围说明进行工作。作

第5套 PMP模拟题

PMP模拟题第五套(200道题,四小时) 1.项目经理收到一些相关方对项目利弊的矛盾意见。这会影响其他相关方对该项目如何使组织受益的支持和理解水平。 项目经理应该如何调整相关方的意见并获得他们的积极参与? A.向相关方解释工作说明书( sow)中概述的业务需求、产品范围描述和战略计划。 B.审查工作说明书和商业论证以识别关键相关关方,然后立即召开会议以澄清商业价值。 C.立即与相关方开会,并敦促他们作出决定。 D.将其登记在风险登记册中以记录从而减轻潜在风险。 2.在为相关方准备状态报告时,项目经理发现一个项目的成本偏差为负数,该项目10%的工作已经完成,在与相关方开会之前,项目经理应该怎么做? A.预测完工估算( EAC)。 B.启动变更控制程序。 C.搁置项目直到确定应对策略。 D.使用应急储备。 3. 项目经理识别到一个基于项目例外事项报告的项目基准主要偏差,项目经理下一步应该怎么做? A.赶工。 B.与主要相关方联系。 C.重新制定项目计划。 D.与发起人谈判。 4.一家公司正在进行重组,虽然并不是所有新职位都是已知的,但是组织变更情况已经传达,项目经理应该怎么做?A.在风险管理计划中更新潜在的未来干系A变更。 B.在相关方登记册中更新己知的信息。 C.与关键干系人的期望保持一致。 D.通知所有干系人当前项目状态。 5.一个项目预算为6000万美元,预计需要24个月才能完成。12个月后,该项目完成了60%,并使用了3500美元。那么预算和进度的状态如何? A.符合预算,并超前于进度 B.超出预算,但超前于进度 C.符合预算和进度 D.落后于速度,并超出预算 6.在客户正式验收之后,项目可交付成果被提供给最终用户。然后,这些用户发现一个缺陷,客户认为项目经理应负责。 怎样可以防止这种误解? A.正确的项目移交程序 B.与客户就保修条款和条件进行谈判 C.项目关闭后解除所有团队成员的访问权 D.确保客户这不是原始需求的一部分

PMP第六版模拟题200题+答案

PMP 冲刺题 1、项目中途,发起人想要改变交付进度计划,项目经理下一步应该怎么做? A. 确定这对项目关键路径的影响 B. 将其添加到问题日志中 C. 提出一项变更请求 D. 使用进度压缩技术 答案:C 解析:PMBOK(6)P113-4.6 实施整体变更控制。确定变更对关键路径的影响是在实施整体变更控制中进行了所以不选A。C 包括A,选 C 2、项目经理注意到正在构建的系统存在多个质量问题,项目经理应该使用什么来跟踪这些问题的解决方案? A. 变更控制过程 B. 质量分析 C. 风险审查 D. 问题日志 答案:D 解析:PMBOK(6)P96-4.3.3.3 指导与管理项目工作-问题日志。在整个项目生命周期中,项目经理通常会遇到问题、差距、不一致或意外冲突,项目经理需要采取某些行动加以处理,以免影响项目绩效。问题日志是一种记录和跟进所有问题的项目文件,所需记录和跟进的内容可能包括问题类型、问题提出者和提出时间,问题描述、问题优先级、由谁负责解决问题、目标解决日期、问题状态、最终解决情况等。 3、一位之前未识别到的相关方报告说,他们的职能领域受到很大影响,但没有持续通知他们关键项目的状态,项目经理首先应该做什么? A. 审查项目的沟通方法 B. 检查并更新相关方登记册 C. 立即和该相关方开会确认 D. 审查并更新沟通管理计划 答案:B 解析:PMBOK(6)P530-13.4 监督相关方参与。监督项目相关方关系,通过修订参与策略和计划来引导相关方合理参与项目。该过程输出更新的相关方登记册,记录从监督相关方参与中得到的信息。 4、项目团队成员遗漏可交付成果。若要解决这个问题,项目经理首先应该做什么? A. 收集由团队执行的活动和相关信息 B. 将工作委托给高级团队成员,让其担任主管 C. 将所有团队成员的工作分成相等的部分 D. 提供培训,以便团队成员可以处理额外的工作 答案:A 解析:PMBOK(6)P169-5.6.1.3 控制范围-工作绩效数据。可能包括收到的变更请求的数量、接受的变更请求的数量、核实、确认和完成的可交付成果的数量等

PMP全真模拟试题最新版(共200题)

全真模拟试题第八版 共200题 一. 选择题(本大题共200小题) 1.由于你的项目工期固定为五年,你认为滚动式规划是适当的。它提供了哪些 需完成工作的信息? a.所有项目阶段的信息 b.成功完成当前项目阶段的信息 c.成功完成当前阶段和近期的后续阶段的信息 d.下一个项目阶段的信息 2.在项目生命周期的最初阶段,项目的技术目标倾向于仅在一般意义上的理 解。在这个阶段的项目冲突的主要组成部分是____。 a.对优先级和程序的担忧 b.对技术问题的担忧 c.进度安排 d.对于在矩阵管理环境中建立项目的困惑 3.项目管理协会道德与专业行为规范包括两类标准,即作为从业者要尽力维护 的,以及要求严格的并可能限制行为的标准。项目管理协会将这两类标准(分 别)称为____。 a.预期的和要求的 b.推崇的和强制的 c.期望的和强制的 d.期望的和要求的 4.需求通常被归为产品需求和项目需求。获取并管理这两类需求对于项目成功 至关重要,因此你和团队成员决定按照项目的这种分类系统来改进公司所有 的通信设备。在采用此种方法时,下列除哪项外,都是产品需求的实例? a.交竹需求 b.技术需求 c.安全雷求 d.性能需求 5.在制定项目管理计划过程中,风险登记册、风险应对计划和风险影响评价是 以下哪项的实例? a.事业环境因素 b.组织过程资产 c.风险管理计划的一部分,而风险管理计划是项目管理计划子计划的一部分 d.作为配置项的项目文件,此文件是配置管理计划的组成部分 1正确答案:C 2正确答案:D 3正确答案:C 4正确答案:A 5正确答案:B 6.你正管理着一个具有五个分包商的项目。你必须监督合同履行、付款并管理 供应商界面。一家分包商递交了变更请求,希望扩大其工作范围。你根据对 此请求的评审,决定对合同进行修订。以上属于哪项活动? a.管理采购 b.实施采购 c.形成合同 d.解决争议 7.尽管项目章程的作用是陈述项目经理在项目中的职权和职责,但为成为有效

PMP试题(汇总版)

模拟试题一 1.您正在管理得一个项目,需要一种新型设备。您弟弟得公司恰好生产这种设备,而且价格与质量都不错。您应该( D)。D A.直接向您弟弟得公司购买 B.让管理层知道这件事 C.让您弟弟得公司用其她公司得名义来供应这种设备 D.不参与这种设备得采购决策 2.申请参加资格认证考试与已经获得资格证书得每一个人都必须遵守( B)。B A.项目管理知识体系指南(A Guide to the Project Management Body of Knowledge) B.PMI道德与专业行为规范(PMI Code of Ethics and Professional Conduct) C.PMI PMP专业行为规范(PMI PMP Code of Professional Conduct) D.PMI会员道德准则(PMI Mereber Code of Ethics) 3.您被任命为一个新项目得项目经理。该项目得成败将关系到您得职业命运。如果项目成功,您会得到提升;如果项目失败,您将被解雇。您应该为项目选择何种组织形式?(B )B A.强矩阵型组织B.项目型组织C.紧密矩阵型组织D.弱矩阵型组织 4.在项目执行期问得一次客户会议中,客户通知项目经理,她已经没有钱继续做这个项目了。项目经理应首先做什么?( B)B A.放慢工作速度,以便客户有时间筹集资金 B.削减工作范围并开始收尾工作 C.停止所有工作,等到客户得钱到位后再接着做 D.停止工作并解散项目团队 5.您所在得公司正在实施一个比较复杂、跨职能部门得项目。该项目所涉及得工作范围很广,质量要求也很高。为了节约项目成本,预防成本超支,项目管理团队取消了一项工作。结果,却反而导致了项目总成本增加。这种情况本可以通过以下哪个过程加以克服?(A )A A.实施整体变更控制B.控制范围 C.控制成本D.控制进度 6.在新产品设计项目即将进入执行阶段时,项目经理请求高级管理层召集主要项目干系人联合举行一次会议,以便使大家都了解项目计划与项目目标。这个会议就是下列哪项得例子?( C)C A.项目干系人会议(Project Stakeholder Meeting) B.项目启动会议(Project Initiating Meeting) C.项目开踢会议(Kick-off Meeting) D.项目状态评审会议(Project Status Review Meeting) 7.项目管理办公室(PMO)得主要职能通常包括以下几个方面,除了( A)。 A.控制分配给某具体项目得资源,并负责实现该项目得目标 B.识别与开发项目管理方法、最佳实践与标准 C.协调各项目之间得沟通 D.通过项目审计来监督对项目管理标准、程序、模板得履行情况 8.科技项目失败得原因大多与管理而非技术有关。技术能力并不能全面代表项目管理能力,然而许多企业没有合适得流程来保证项目经理接受适当得培训与全面得评价。公司内拥有选拔、培训、监督与考核项目管理专业人员权力得就是(B )。

pmp模拟题(含答案)

PMP备考知识的细节支持(第2版)?? 整理:guojiayoung(项目管理者联盟/https://www.360docs.net/doc/ed4096550.html,的ID) 附注二十五 大模拟试题200道-得分×0.8>137分通过PMP考试希望很大bayou 级别:论坛游民 积分:15 经验:45 文章:15 注册:04-05-27 14:32 发表: 2004-06-01 09:43:46 人气:132 1. The purpose of project plan development is to— 项目计划规划的目的是 [ ] a. Create a document to guide project execution and control 制定项目文件,指导项目执行和控制 b. Document project assumptions and constraints 提出项目的假设和约束条件 c. Promote communication among stakeholders 促进项目干系人之间的沟通 d. Define key project reports 确定主要项目报告 Please refer to the following information to answer questions 2. 请参阅以下信息,回答问题2。 You have been assigned as the project manager on a project with a clearly defined scope limited to the design-and-build phase of a product assembly line. A member of the client’s team has asked a functional supervisor on the project to complete a small job during the installation phase of the project. The functional supervisor referred the client to the project manager. 您已经被委派为某项目的项目经理,职权范围明确界定,限于产品总装的设计及建设阶段。客户组的一位成员向项目部门主管询问有关在项目安装阶段完成一项小工作的问题。项目部门主管请客户询问项目经理。 2. The BEST response to this request would require a review of information developed in which of the following sub-processes? 对这一请求作出最佳答复需要审查以下哪个分过程中开发的信息?[ ] A. Activity duration estimating 活动期限评估 B. Scope verification 范围核查 C. Scope definition 范围界定 D. Schedule development 进度计划拟定 3. Most of the project’s budget is expended during— 项目预算在下列哪个阶段投入最大?[ ] a. Project plan development b. Project plan execution

PMP试题(汇总版)

模拟试题一 1.你正在管理的一个项目,需要一种新型设备。你弟弟的公司恰好生产这种设备,而且价格和质量都不错。你应该( D)。D A.直接向你弟弟的公司购买 B.让管理层知道这件事 C.让你弟弟的公司用其他公司的名义来供应这种设备 D.不参与这种设备的采购决策 2.申请参加资格认证考试和已经获得资格证书的每一个人都必须遵守( B)。B A.项目管理知识体系指南(A Guide to the Project Management Body of Knowledge) B.PMI道德与专业行为规范(PMI Code of Ethics and Professional Conduct) C.PMI PMP专业行为规范(PMI PMP Code of Professional Conduct) D.PMI会员道德准则(PMI Mereber Code of Ethics) 3.你被任命为一个新项目的项目经理。该项目的成败将关系到你的职业命运。如果项目成功,你会得到提升;如果项目失败,你将被解雇。你应该为项目选择何种组织形式?(B )B A.强矩阵型组织B.项目型组织C.紧密矩阵型组织D.弱矩阵型组织 4.在项目执行期问的一次客户会议中,客户通知项目经理,他已经没有钱继续做这个项目了。项目经理应首先做什么?( B)B A.放慢工作速度,以便客户有时间筹集资金 B.削减工作范围并开始收尾工作 C.停止所有工作,等到客户的钱到位后再接着做 D.停止工作并解散项目团队 5.你所在的公司正在实施一个比较复杂、跨职能部门的项目。该项目所涉及的工作范围很广,质量要求也很高。为了节约项目成本,预防成本超支,项目管理团队取消了一项工作。结果,却反而导致了项目总成本增加。这种情况本可以通过以下哪个过程加以克服?(A )A A.实施整体变更控制B.控制范围 C.控制成本D.控制进度 6.在新产品设计项目即将进入执行阶段时,项目经理请求高级管理层召集主要项目干系人联合举行一次会议,以便使大家都了解项目计划和项目目标。这个会议是下列哪项的例子?( C)C A.项目干系人会议(Project Stakeholder Meeting) B.项目启动会议(Project Initiating Meeting) C.项目开踢会议(Kick-off Meeting) D.项目状态评审会议(Project Status Review Meeting) 7.项目管理办公室(PMO)的主要职能通常包括以下几个方面,除了( A)。 A.控制分配给某具体项目的资源,并负责实现该项目的目标 B.识别与开发项目管理方法、最佳实践和标准 C.协调各项目之间的沟通 D.通过项目审计来监督对项目管理标准、程序、模板的履行情况 8.科技项目失败的原因大多与管理而非技术有关。技术能力并不能全面代表项目管理能力,然而许多企业没有合适的流程来保证项目经理接受适当的培训和全面的评价。公司内

第五版PMP综合模拟试题

PMP考前培训 课下综合练习题一 北京易佳盈通咨询有限公司 版权所有

1.项目团队发现项目有可能暴露于巨大的财务风险之中,若要管理这类风险,项目经 理应该怎么做? A.回避(Avoid) B.分享(Share) C.转移(Transfer) D.接受(Accept) 2.新项目经理正在制定项目管理计划,但项目经理对该项目领域没有经验,若要从其 他人的经验中获益,项目经理应该参考下列哪一项? A、团队绩效评估(Team Performance assessment) B、绩效报告(Performance report) C、历史信息(Historical information) D、干系人登记册(Stakeholder registor) 3.在项目过程中,发生了一个事件,该事件影响了项目成本,但是未影响到时间,项 目团队识别为一个潜在的风险。 若要限制该事件对于项目成本的影响,项目经理应该怎么做? A.查看风险登记册,并确定适当和既定的应对措施。 B.分析该事件,包括对成本和时间的影响,并创建变更请求。 C.制定权变措施,并立即实施,尽可能减少成本超支。 D.执行敏感性分析,确定不同应对的成本超支灵活性。 4.项目经理为客户领导一个产品开发项目,该项目由外部资金赞助,具有严格的付款 计划和期限。在项目执行阶段,项目经理发现项目落后于进度。 项目经理应该怎么做? A.执行进度压缩,满足既定的期限要求。 B.签发变更请求,并让客户批准。 C.不采取任何措施,因为合同没有规定产品延迟交付的处罚条款。 D.减少质量审计的数量,实现按时交付。 5.团队成员转移到新项目,项目经理转移到组织中的不同项目上,在检查组织项目的 状态时,项目管理办公室通知说,该项目的合同未正常收尾,项目经理被要求纠正这个问题。 项目经理应审查下列哪一项? A.记录管理系统(Records management system)

PMP模拟题

PMP考试模拟题(一)2012 1.项目经理将一个变更请求通知指导委员会。这属于下列哪一项范畴? A.推式沟通 B.纠正错误 C.公开沟通 D.预防措施 2.在识别对项目预算会产生负面影响的风险发生之后,项目经理需要确定剩余的应急储备是否足够。项目经理应该采用下列哪一项工具或技术? A.储备分析 B.偏差和趋势分析 C.应急分析 D.SWOT分析 3.在项目的什么时间点,项目经理将会审查控制措施? A.在计划编制阶段 B.在启动和执行阶段 C.在项目过程中持续审查 D.在项目收尾阶段 4.在项目评审会上,从事活动AD的项目团队成员通知项目经理,完成该活动还需要三天。组织的高级经理要求项目经理,即使需要额外预算,也必须找到方法,按原定基准计划交付 C.应用关键链法 D.应用时间提前量和时间滞后量 5.项目经理被任命管理一个为期多年的项目。在创建工作分解结构(WBS)过程中,项目团队无法分解将在项目后期发生的某些阶段。项目经理应该怎么做? A.适当的时候,开展滚动式规划 B.回到需求收集阶段 C.为这些阶段预估WBS分解 D.减少项目范围

6.签约公司未达到质量标准,并且交付成果频繁延迟。项目经理发现,现有合同条款无法确保卖方提高绩效。为避免卖方的低绩效,项目经理本应采取何种行动? A.让项目经理团队执行影响分析 B.实施采购绩效审查 C.实施风险再评估 D.参与合同的详细拟定 7.在与新干系人召开的第三次月会上,项目经理发现一些干系人未收到会议纪要和其他关键文件。为防止这种情况再次发生,会后项目经理应该怎么做? A.审查沟通管理计划 B.重新分发会议纪要和关键文件 C.签发变更请求,修订沟通过程 D.道歉并索取联系信息 8.由于一名关键成员住院治疗会影响到项目进度,项目经理申请一名替代资源,来让项目保持进度。项目经理正在做下列哪一项工作? A.变更请求 B.缺陷补救 C.纠正措施 D.预防措施 9.项目发起人在项目执行过程中的角色是什么? A.验证项目目标 B.验证项目计划的执行 C.解决超出项目经理控制范围之外的冲突 D.做出所有项目相关决策 10.某项目未能达到原工期要求,新项目经理 正在接管项目并需审查项目时间表,以确保项Array目如期完工。应针对下图的关键路径采用何种 方法? A.压缩路线A-G-C-D上的进度 B.压缩路线A-B-C-D上的进度 C.针对路线A-G—C-D实施参数估算 D.针对路线A-E-F-D实施参数估算 11.通过利用各种属性的公式,项目经理从量化的组合估算了一个新项目的成本和工期。项目经理使用的是下列哪一项估算技术? A.参数估算 B.类比估算 C.储备估算 D.专家判断

PMP全真模拟试题第四版(共200题)

全真模拟试题第四版 共200题,正确0题,整卷得分0分,随机得分:0 一. 选择题(本大题共200小题) 1.你们公司为其项目管理专业人员建立了一个奖励与表彰系统。项目成本绩效被用来为确定是否给予奖励的一个标准。你应该怎样做才能确保奖励反映真实的绩效? a. 把加班算作工作的一部分 b. 制定成本基准计划 c. 利用挣值管理对绩效进行监测 d. 将可控制成本与不可控制成本分开来估算与预算 正确答案: D 2.你在某家著名的医药公司工作。你们公司有很多项目机会,没有足够的资源来完成这些项目。你正领导着一个团队,来确定对项目进行选择并排定其优先次序的方法。你团队正在考虑诸多不同的管理问题,其中包括财务利润,市场份额以及公众形象。你告诉团队,在建立项目选择模型的诸多指标中,最重要的指标是: a. 能力 b. 现实性 c. 易于使用 d. 成本 正确答案: B 3.一个新项目。公司的现有人员只符合项目的部分要求;项目的其他方面对你们公司来说是全新的领域。你知道有一些供应商专门生产这一类产品,他们能达到您的大部分要求。你正在准备项目计划,决定如何最好地为项目配置人员,以及满足项目所有的资源需求。你应该做的第一步是: a. 进行自制/外购分析 b. 进行市场调查 c. 用RFP的形式向供应商征求方案,确定是否应该把项目包出去 d. 仔细查看采购部门提供的符合要求的供应商米但,向被挑选的供应商发送征求RFP。 正确答案: A 4.定将公司的项目经理组织起来,成立一个PMP备考学习小组。每个人都很想拿到这个证书,因为首席执行官已经决定给每个获得该证书的人5000美元的奖金。你应该采用哪一种沟通方式去组织学习小组?

PMP全真模拟试题..

■ 本试题为交大培训PMP 全真模拟试题1(PMBOK 第四版) 特别提醒请注意: PMP 考前模拟试题,仅为并仅提供考生考前模拟测试用; ■ 正式PMP 认证考试时间为四个小时; ■ 正式PMP 认证考试题量和题型为200个单选题(四个选项); ■ 正式PMP 认证考试语言为中英文对照,题意以英文为准; ■ 正式PMP 认证考试格式以下列第一、二题格式为准 1. In response to the new regulation about treatment of toxic wastes, you propose a project to make new policies as a PM expert of a toxic waste treatment company. The proposal reveals the importance of which item below? A. Taking legal requirements as a basis of initiating projects B. Looking for mew and effective methods C. Insisting to behave under legal requirements and ethic standards D. Time limitation of projects 1. 你是一家处理毒废物公司的项目管理专家,为了响应环保机构颁布的有关有毒废物处理的新规定,你建议启动一个项目来编写有毒物质的新处理指南。 这个建议显示了以下哪一点的重要性? A. 将法律要求作为项目启动的基础 B. 不断寻求新的和有效的方法 C. 坚持按法律要求和道德标准行事 D. 项目必须完成的时间范围 2. This tool and technique of Monitor and Control Risk is applied to examine and document the effectiveness or risk response in dealing with identified risks and their root cause, as well as the effectiveness of the risk management process. What is it? A. Risk reassessment B. Project change requests C. Project risk audit D. Workaround 2. 这是一个监控风险的工具方法,它被用以检查并记录风险应对措施在处理已识别风险及其根源方面的有效性。 这是什么工具? A. 风险再评估 B. 项目变更请求 C. 项目风险审计 D. 权变措施

PMP项目管理模拟题及答案分解

PMP模拟题—沟通管理试题及答案解析 一、单选题 1.现在的项目比以往的项目牵扯到更多的国际合作和形形色色的干系人。因此,如果没有在项目进行之初统一大家的理解,那么对项目的霎时间、成本业绩方面的目标可能会出各种各样的解释,所以项目动员大会是非常重要的(即使是通过多媒体的形式召开的动员大会也是具有重要的意义)。下列各项中,哪一项不属于动员大会的目标 A、确立项目各部分的沟通关系和标准形式 B、审阅项目计划 C、确定个人和小组的责任和义务 D、讨论与合同有的关、具体的法律问题 2,沟通管理计划的一个目的是提供有关以下什么的信息 A、获取和储存信息的方法 B、当不需要项目小组成员的时候将小组成员调离项目的方法 C、项目组织与干系人的责任关系 D、每个项目小组成员的经验和技能水平 3,币值波动、政治动荡、中央和地方政府之间的竞争,以及不同利益集团之间的冲突可能会干扰国际项目的管理。管理国际项目的项目经理应该意识到跨文化环境的主要影响因素,并特别重视 A、建立绩效报告制度 B、建立沟通管理系统 C、建立和执行生产进度表以方便信息分配,避免在定期会面之间出现情况的变化 D、通过翻译服务起草正式的项目报告 4,你目前正忙着做项目的收尾工作。在这个令人兴奋的最后阶段,在下列哪个方面最容易引发冲突 A、进度问题 B、成本超支 C、技术问题 D、缺乏客户的认同 5,你被任命为一个项目的经理。在你曾经参加过的项目中,整个团队的成员在项目动员大会之后就很少再碰面,你对这种做法比较失望。因为在整个项目进展过程中项目团队成员看不到项目进展的整体情况,有时你也看不到呈报给高层管理者的项目进展报告。因此你相信与项目团队成员分享信息是非常重要的。作为项目经理,你最先采取的行动就是建立一套信息检索系统。而下列哪一项不属于信息检索系统的一部分 A、手动归档系统 B、项目管理软件 C、项目内部网 D、电子数据库 6,撰写项目进展报告时所使用的"50-50"规则主要用于 A、计算精确的增值 B、比较准确的估计挣值的大小 C、判断进度方差 D、以货币值来判断进度方差

PMP模拟试卷

PMP 模拟试题 1. 如果EV = 145, PV = 162, AC = 138, BAC = 200,如果你知道过去的估算假设已经不复有效,那么EAC 应该是多少? A. 190.4 B. 193 C. 201 D. 200 2. 这是一个风险监控的工具方法,它被用以查看风险策略中转移、规避和减轻的实施以及有效性,它是什么? A. 风险再评估 B. 项目变更请求 C. 项目风险审计 D. 临时权变计划 3. 你管理一个内部服务项目并处于计划过程中,你注意到在你审阅项目章程时发现某些员工已经被指定为项目团队成员,这个问题说明了: A. 资源可利用性 B. 预分配 C. 员工管理计划 D. 虚拟团队 4. 风险管理计划进行以下各项,但不包括: A. 定义项目风险管理的方法论 B. 描述风险类别 C. 定义风险管理团队的角色职责 D. 处理单个风险的应对以及在项目中如何实施 5. 你在风险定量分析过程使用访谈技术,你打算使用的概率分布是三角分布。下面哪一个说法是错误的? A. 访谈技术应用于项目目标风险的概率和后果的量化 B. 收集的信息取决于所选用的概率分布类型 C. 三角分布典型的使用对称的非持续性概率分布 D. 三角分布依靠平均值和标准差来量化风险 6. 如果EV = 114, PV = 120, AC = 103,那么CPI 和SPI 分别是多少? A. 1.1 和.95 B. 1.2 和1.05 C. 1.05 和1.2 D. .95 和1.1

7. 在你所在的城市,你管理一个水务局的项目,这是一个大型的复杂项目,所以你把它分解为更小的、可管理的项目,并任命了各自的项目经理向你汇报,其中两个项目外包给供应商。该项目必须达到相应的具体技术指标以满足该局水务管理的有关规范。另外还有两个项目经理正在进行与该项目不相关的项目,但要符合和你的项目同样的水务规范和流程。从市管理部门得知,这样的规范不会影响到你未来的项目。下面那种说法是错误的? A. 该水务局愿意以协调的方式用大型项目来管理这些项目 B. 所有外包项目需要阶段把关 C. 由于这些项目的共性,它们属于一个专业领域 D. 你的项目采用了子项目 8. 在控制过程中有两个过程同步进行以保证工作的正确性和验收,这两个过程分别是: A. 质量保证和范围核实 B. 质量保证和范围控制 C. 质量控制和范围核实 D. 质量控制和范围控制 9. 关于时间约束中的强加日期和关键事件,那个说法是错误的? A. 强加日期和关键事件是整体变更控制过程的输入 B. 强加日期应用于其开始或完成日期不得迟于某一指定日期的那些活动 C. 关键事件约束是指干系人所要求的完工活动的期限 D. 请求的完工日期经常成为预期的完工日期,因此成为时间约束 10. 你被要求执行一个可行性分析来决定最佳项目。项目的初始投资为29,000 美元。项目A 的现金流为第一年14,000 美元,第二年为19,000 美元,项目B 的现金流为第一年21,000 美元,第二年为20,000 美元,项目C 的现金流为第一年15,000美元,第二年为20,000 美元。假设资本成本为10%,根据三个项目的净现值,你推荐哪一个项目? A. 项目A B. 项目B C. 项目C D. 哪一个都不推荐 11. 变更控制系统是下列过程的工具方法,但不包括: A. 质量控制 B. 范围变更控制 C. 进度控制 D. 成本控制 12. 你正在进行的一个项目和你公司去年进行的一个项目的范围是类似的。你可以考虑下列哪一项? A. 利用从前项目的方案识别作为模板 B. 重复利用从前项目的效益/成本分析作为验证该项目的依据

PMP最新版全真模拟题(B套)

PMP最新版全真模拟题(B套) 特别提请注意: ■本试题为PMP考前模拟试题,仅为并仅提供考生作考前模拟测试用; ■正式PMP认证考试时间为四个小时; ■正式PMP认证考试题量和题型为200道单选题(四个选项); ■正式PMP认证考试语言为中英文对照,题意以英文为准; ■本套模拟题的答案和解释以骆老师上课时讲解为准。 1. Which of the following attributes is true for a competency A. It is a smallest unit of dimension of competence. B. It affects only a minor part of one’s job. C. It correlates with performance outside the scope of the job. D. It can be improved through training and development. 1. 对于资格来说,下列哪一项特征是正确的? A.它是功能最小的单位或维度 B.它只能影响到一个人工作较小的一部分 C.它与工作范围之外的绩效有关 D.它可以通过培训和发展得以提高 2. In the initiation phase of your project, it is apparent that different departments of the client’s company hold different views on project structure and project deliverables. What is the best action for you? A. Ask the client when they will finalize their requirements. B. Work with leaderships from each department to collaboratively engineer a mutually acceptable solution. C. Make sure the terms and conditions of the contract are clear. D. List the consequences of changes in the contract’s requirements section. 2. 在项目的启动阶段,客户公司内部各部门关于项目结构和可交付成果明显存在不同观点,你的正确行动应该是: A. 询问客户什么时候能够达成一致性需求 B. 与客户各部门领导合作,策划一个相互都能接受的解决方案 C. 确保合同条款清楚 D. 在合同要求条款中列明变更的后果 3. Configuration management describes procedures for applying technical and administrative direction and surveillance. Which one of the following tasks is not performed in configuration management? A. Establishes an evolutionary method to request changes to established baselines B. Provide opportunities for project by considering the impact of each change