某大跨度悬索桥索股牵引系统线型复核及设备简介

某大跨度悬索桥索股牵引系统线型复核及设备简介摘要:本文以国内一在建的悬索桥为例,对该桥索股牵引系统的牵引能力和牵引索的线型进行了校核,并对主要的机具设计进行了简要说明,最后对施工中出现的主要问题和解决方法一一进行了阐述,可为今后同类桥梁的相关施工提供参考。

关键词:悬索桥,索股,牵引
abstract: this article with a suspension bridge under construction in china as an example, in the bridge of the traction system of traction ability and traction virwpoint of cable line, and the main machine design for a brief explanation of the last, the main problems appeared in the construction and the solving methods--were introduced, for future similar bridges related construction to provide the reference.
keywords: suspension bridge, cable shares, traction
中图分类号:悬索文献标识码:a文章编号:
1 概述
目前,对于大跨度悬索桥索股的牵引均采用门架式双线往复牵引系统,本文以国内一悬索桥为例,对该桥索股牵引系统的线型、牵引设备及施工中的问题作简要介绍。

该桥主桥为超千米级跨径的三跨悬索桥,设有两根主缆,单根长约2643米,每根主缆含有通长索股135根,从牵引第一根主缆
起,工期定为两个月。

在上下游各布置一套相同牵引系统,分别牵引两根主缆上的索股,下面介绍的是一侧的牵引系统。

2 牵引系统牵引能力校核
索股牵引力的计算主要用于确定整个牵引系统的卷扬机设备能力,以及研究索股牵引过程中设备的动力变化。

索股与滚轮(滚轮为尼龙材料制成)间的摩擦系数为0.035,本次计算中从安全考虑取0.05。

可以求出每处卷扬机拉力随拽拉器运行变化的曲线图。

图2.1 卷扬机拉力变化曲线图
经过以上计算,牵引索股时卷扬机所需提供的最大拉力为220.25 kn,考虑0.1倍的富余,,所以250 kn的卷扬机满足要求。

3、牵引索线型复核及托轮布置间距设计
考虑到牵引索在自重和集中荷载下有一定的垂度,其净高按以下两个原则控制:
a、拽拉器在正常行进过程中,应保证索头架不与下面其它结构发生摩擦,并留有一定富余(0.6m),与所以高度不能过低;
为方便索头与拽拉器安装、拆卸的方便,南北锚处高度不能过高,其它处高度不限制,计算如下:
计算公式:
f:主索某处垂度;:主索弦倾角;
g:主索单位长度重量);q:集中荷载;
hf:主索水平拉力; h:主索拉力;
l:主索跨度;x:主索某处离端点的距离;
下面以北锚碇处的计算为例说明,计算示意图及计算结果如下:
图3.1北锚碇牵引索净高校核示意图
表3.1北锚处牵引索净高计算结果
3.1猫道上托轮布置间距
托轮高度确定原则:托轮是用来支撑索股的,在索股牵引过程中,每隔一定间距应配有施工人员,其配有仿鱼雷夹具夹着索股和索股一起行进,这就需要托轮有一定的高度方便施工人员操作,所以托轮高度定位1.0m。

对于塔顶处应适当调节托轮的高度以保证索股能平缓顺利通过。

托轮间距布置原则:1、索股在被牵引过程中,索股会下垂,应保证下垂后的索股与猫道面层不发生干涉,并留有0.5m的余量。

2、在塔顶处由于索股弧度较大,托轮的布置原则主要是匹配索股的线型,并保证索股不与其它构件发生干涉。

4、牵引设备及机构的设计
4.1250kn双摩擦式卷扬机
牵引系统选用250kn双摩擦式卷扬机(容绳量3000m)。

此类卷扬机的钢丝绳缠绕在双摩擦卷筒的环形槽上,利用钢丝绳与环形槽之间的摩擦力把卷筒的驱动力传给钢丝绳。

其优点是:
摩擦卷筒的宽度和高度与起升高度和牵引距离无关;只需增减摩擦卷筒的环形槽数,就可以满足牵引吨位的要求,钢丝绳和环形槽之间的相对滑动还可以起过载保护作用。

该机应具有无级变频调速、智能化测速、测长、张力显示等功能,可对牵引系统的速度、位置和张力进行全程跟踪显示和自动控制。

牵引系统选用250kn双摩擦式卷扬机,配用钢丝绳直径36mm,选型如下。

钢丝绳型号:
最小破断拉力:817kn;
安全系数:>3.0。

说明:在拽拉器经过南塔塔顶的时候,牵引索拉力最大,其它大部分时间牵引索拉力小于200 kn。

根据以往悬索桥架设经验,主缆索股架设以每工作日架设3~4根为宜,每根索股平均架设时间在3~6小时,牵引速度定为
8m~25m/min,现场指挥人员应根据实际使用情况随时作出调整。

4.2 拽拉器的设计
拽拉器是牵引系统的关键部件,它是连接牵引索并与索股锚头连接,用以在猫道架设阶段牵引猫道承重索和在主缆架设阶段牵引主缆索股的构件。

施工中将拽拉器与猫道索锚头或索股锚头相连,牵引索的拉力转移至索股的锚头,连续顺畅的牵拉猫道索或主缆索股前行。

在牵引系统形成、猫道架设和主缆牵引过程中,要求其重
量轻、强度大、结构合理。

拽拉器结构:拽拉器是采用楔形连接板固定钢丝绳构造形式,主要部分由大楔形接头、小楔形接头、三角架等组成。

φ36mm的牵引索经半圆楔型接头和半圆座直接在大楔型接头上固定,为了使拽拉器保持正确的位置,减少索股在牵引过程中发生扭转和牵引索掉索现象,在拽拉器一侧设有平衡重。

另外,还设计了一种背索索股拽拉器。

根据布置位置的不同,悬索桥的索股分为两种类型:通长索股和背索索股,通长索股只需在索头有拽拉器牵引即可(如前文所述),而在牵引背索索股时,索股尾部还需安装有一背索尾端拽拉器。

两拽拉器安装时的区别在于,前者是连接两根牵引索,而后者是安装在一根连续的牵引索上。

背索索尾拽拉器作为悬索桥背索尾端索股索头牵引的使用,其主要由三角型杆件组、梭筒、平衡结构、索头架四部分组成,其结构与通长索股拽拉器类似,此处不再赘述。

4.3 导轮组的设计
导轮组包括塔顶门架导轮组、猫道门架导轮组、锚碇支墩门架导轮组及锚碇后锚块导轮组等,其作用一是支撑牵引绳,二是改构类似,本文以南北塔塔顶导轮组设计为例进行说明和计算。

借鉴架空索道的托压轮组,南北塔主索鞍门架处导轮组设计成能自动适应牵引绳折射角不断变化的导轮组。

导轮组由以下几个主要部分组成:导轮架、吊板、导轮、压绳缓冲装置。

在牵索过程中,由于牵引绳张力变化较大,导轮组采用较大的
曲率半径,这样当拽拉器通过时冲击小,并且轮压均匀,同时配备有压绳缓冲装置可以起到夹持拽拉器并且减少拽拉器和导轮组的
冲击,同时也防止绳索脱槽。

5、施工中出现的问题
由于索股牵引从北至南,运行距离长,牵涉机构较多,与猫道、门架结构等密切相关,施工中难免出现一些问题,以下是该桥索股牵引出现的一些问题和解决方法,供以后类似情况的参考。

5.1拽拉器的改进
如图,由于实际线型与理论线型的差异,拽拉器平衡轴与导轮组的净空富余也不多,所以两者之间发生了干涉,为了一劳永逸的解决该问题,临时对拽拉器进行了改进,增加了三脚架的外形尺寸,留足了富余(加长约20cm),保证了拽拉器的顺畅穿行。

5.2索头架的改进
原设计是参考传统索股头的箱型结构,索头固定在一箱体内,由于箱型结构太重,索头行进时始终保持“低头走”,这样头部索股会发生弯折,对索股不利。

为了避免该现象,施工方对索头架进行了改进,结构更简化,并且保持了索头朝上。

5.3塔顶托轮布置的改进
原设计是利用主索鞍,在主索鞍上布置了一些托轮,这虽然省去了托轮支架,但对索股过导轮组的线型不利,开始牵引时出现了索股捆扎带断丝现象,后来在主索鞍旁边做了一些托轮支架,并抬高了塔顶附近猫道托轮的高度,这样增大了塔顶索股托轮组的弧
度,这样保证了索股安全的穿过塔顶。

注:文章内所有公式及图表请以pdf形式查看。

合集下载

缆索吊装设备简介及受力分析改--论文

缆索吊装设备简介及受力分析改--论文

缆索吊装设备简介及受力分析Engineerlzk / *********一、引言缆索吊装是桥梁施工的常用方法之一,是大跨度拱桥无支架施工的主要方法。

此种吊装方案主要适用于高差较大的垂直及纵向运输,尤其适用于深谷、河流湍急以及受通航限制的河道上的桥梁施工。

本文结合贵毕公路三板桥(铪箱型拱桥)的成功实例,对索塔的安装、跑车及承码架、牵引及起重等设备的构造特点作比较详细的介绍。

同时,由于主索是缆索吊装设备的承重设备,其设备的选用及安装后成型的效果将直接影响到缆索吊装的成功与否。

因此,本文亦根据缆索吊装设备的塔高、地锚位置、计算跨度、主索垂度及吊重等对主索进行内力分析和安全度验算的计算方法作了介绍。

二、缆索吊装设备的构造及安装缆索吊装设备根据其使用性质可分为吊装梁式桥的缆索吊装系统、吊装拱桥的缆索吊装系统及一般情况下的机具材料的运输用缆索吊装系统等三种形式。

每种系统均由主索、跑车、起重索、牵引索、起重及牵引卷扬机、主索地锚、索塔、风缆等主要部件组成。

其中吊装拱桥的缆索吊装设备除了上述各部件之外,还有扣索、扣索排架、扣索地锚、扣索卷扬机等部件。

本文就其中最简单的机具材料运输用缆索吊装设备的构造及安装简要介绍如下。

1.总体布置见图1。

2.索塔:采用西安筑路机械厂生产的万能杆件拼装。

其截面为200×200cm,贵阳岸塔高7×4m=28米,毕节岸塔高8×4m=32米,塔顶索鞍采用两片[40槽钢拼装再辅以单滑轮组成。

塔身拼装形式为:立柱采用⑴号件、横撑采用⑷号件、斜撑采用⑶号件、水平斜杆采用⑸号件、节点板采用⑾及⒀、⒅号件。

其形式如下图:3.钢丝绳该吊装设备所有绳索设备均选用6股37丝麻芯钢丝绳。

其中主索规格为Φ47.5,起重索为Φ17.5,牵引索为Φ21.5,承码索为Φ11。

①主索:由于吊重较轻,故选用1根Φ47.5麻芯钢丝绳。

安装时通过卷扬机牵引工作索而到达对岸,此时应注意设置捎绳以防止主索因自重而下坠入谷或入水。

大跨度悬索桥主缆索股智能化架设施工工法

大跨度悬索桥主缆索股智能化架设施工工法

大跨度悬索桥主缆索股智能化架设施工工法大跨度悬索桥主缆索股智能化架设施工工法一、前言悬索桥作为大型桥梁工程的一种重要类型,具有架构简单、跨度大、经济性好等优点,越来越受到工程建设方的青睐。

而其中的主缆索股智能化架设工法,作为悬索桥施工工艺的重要组成部分,具有较高的技术难度和复杂性。

本文将对该工法进行详细介绍,以便读者了解其理论依据和实际应用。

二、工法特点主缆索股智能化架设工法在悬索桥的施工过程中起着至关重要的作用。

其主要特点如下:1. 利用智能化设备,实现对主缆索股的准确架设,提高施工效率。

2. 采用先进的线控系统和自动化技术,实现对主缆索股的精确控制,保证架设的准确性和稳定性。

3. 结合虚拟仿真技术,对架设过程进行模拟和优化,降低施工风险。

4. 采用数据采集与分析技术,对主缆索股架设过程进行实时监控和质量控制。

5. 通过云平台技术,实现施工数据的共享和在线管理,提高施工质量和效率。

三、适应范围主缆索股智能化架设工法适用于各种大跨度悬索桥的施工,包括道路、铁路、高速公路等。

无论是海上悬索桥、河流悬索桥还是山区悬索桥,都可以借助该工法进行主缆索股的架设。

四、工艺原理主缆索股智能化架设工法的实际工程应用基于以下工艺原理:1. 施工工法与实际工程的联系:该工法的设计基于悬索桥的具体参数与要求,充分考虑了施工环境和施工条件。

2. 采取的技术措施:通过对智能化设备的使用和施工工艺的优化,保证了主缆索股的准确架设。

同时,结合虚拟仿真技术和数据采集与分析技术,实现了对施工过程的实时监控和质量控制。

五、施工工艺主缆索股智能化架设工法主要包括以下施工阶段:1. 主缆索股制作:根据悬索桥的设计要求,制作符合规范要求的主缆索股,包括钢缆的制作、防腐处理等工序。

2. 主缆索股架设准备:设置架设平台、安装智能化设备、连接线控系统等。

3. 线控架设:利用智能化设备,通过线控系统对主缆索股进行精确控制,进行架设。

4. 监测与质量控制:通过数据采集与分析技术,实时监测主缆索股的架设过程,确保质量达到设计要求。

润扬大桥悬索桥主缆架设牵引系统

润扬大桥悬索桥主缆架设牵引系统
lt a mb r c i e ns r g nt co is u e o a h v me td i c s ut n s n f e un o r i
Ab ta t src
T e p r m t o oi r ee c f s l w k ne e ae p t p v e frne r ir r ud r h p a t s r d e o i a o s m cnt co o t b b ib pee t i ot rsac p cs ad us os ut n o ut r n t n h ee r r es rsl r i r e l y s ao f e h o n e t o h un ss m R nag pni bi e f lg t o uyn sse s n g a i y e f u o r d
贵州坝陵河大桥等, 见表 11 . .
表 11 我国现阶段建成、在建大跨径的悬索桥 .
序号 桥 名
所在地 主跨跨度
完成时间
加劲梁形式
建成项目
1 2 3 4 5 6 7 8 9 1 0 1 1 1 2
汕头海湾大桥
丰都长江大桥
广东省 重庆市 重庆市 重庆市 重庆市 福建省
关键词:悬索桥,润扬大桥,主缆架设,牵引系统,猫道系统
Ab ta t src
Ab ta t s rc T e h c l e o spr sa bde sutn h a i l l ue l g n g cnt co i C i i h t n a e f o p r e c v n i o r i n n s ap ah g lavne l ew h tnd r e et cnya pr ci w r dacd l ss i ip vm nir et r o n od e i ua e m o v t n e es H w vrh cnt co o spr g n pni bde p r u r o ee t osutn ue t sa sses n g , i ll , e r i f o p u n o r i a c ay t t m i cb i tli han ss m f prr t e sl h a a l n aao ulg t o s esu u i t e n e s ltn i y e u t c r s i l ustf t . e o svr ya ' ei c o t cnt co o nas c r B sd ee l r eprne h o sutn ia o a y n a e s x e n e r i f R na g se s n i e t at r d p f n r er o t uyn s p ni bd , u o m e o ud sa h h u o rg h e h a ro e c n e hun ss m m icb e co. cta p b m o t ss m alg t f a al r tn Te i l l s h yt i y e o n e i h rc r e f r e i o e e

鱼嘴长江大桥主缆索股牵引施工技术

鱼嘴长江大桥主缆索股牵引施工技术

鱼嘴长江大桥主缆索股牵引施工技术李芳军【摘要】鱼嘴长江大桥是位于重庆市的1座主跨616m的钢箱梁悬索桥,为了解决在两岸地形较为陡峭的条件下进行主缆牵引施工的难题,对各种牵引施工的方法进行比较,采用平面大循环牵引系统来实施主缆索股牵引,该牵引系统在国内首次实施,取得了良好的效果,顺利完成了施工任务。

对鱼嘴长江大桥主缆索股牵引系统的方案选择、布置及设备配置进行简要介绍,并对实施经验进行总结。

%The Yuzui Yangtze River Bridge is a suspension bridge with steel box girder and a main span of 616 meters, located in Chongqing. In order to solve the construction problem during the traction of the main cable under the steep terrain condition on both sides of the river, this study compared different kinds of traction methods with each other, and then a traction system of large plane circulation was adopted to do the traction of the main cable strand. It was the first time in China to use this kind of traction system, with which the construction task was completed successfully and effectively. In addition, about this traction system used in the traction of main cable strand of the Yuzui Yangtze River Bridge, this study briefly introduced the scheme selection, layout pattern and the equipment configuration, also summarized the application experience.【期刊名称】《铁道标准设计》【年(卷),期】2014(000)005【总页数】4页(P78-80,89)【关键词】公路桥;长江大桥;悬索桥;主缆;施工【作者】李芳军【作者单位】中铁大桥局集团第八工程有限公司,重庆 400020【正文语种】中文【中图分类】U448.27鱼嘴长江大桥是重庆外环高速公路东段上一座跨越长江的特大桥,主桥为616 m单跨双立铰简支悬索桥,两边跨分别为180、205 m。

特大跨径悬索桥先导索架设施工技术

特大跨径悬索桥先导索架设施工技术

特大跨径悬索桥先导索架设施工技术马鞍山长江公路大桥左汊主桥为世界第一的三塔两跨悬索桥,结构成对称布置,跨径为360+2×1080+360m,矢跨比为1/9,主缆长3045.53m,单根主缆由154根索股组成,采用双线往复式牵引系统牵引架设施工。

主跨河道宽超过2000m,主航道位于南主跨,北主跨顺桥向有沙洲,不通航。

1 先导索架设方法简介先导索架设一般有陆地牵引架设、水上牵引架设和空中牵引架设方法。

1.1 陆地人工、机械拖拉架设法陆地人工、机械拖拉法工效较低,在地形有利、跨度不大、无地面障碍物的情况下采用,不适合有高深陡坡、高压线、植物和农作物多的地方。

马鞍山大桥南边跨上游侧牵引索及猫道承重绳即在地面上由铲车牵拉至南边塔,用塔吊提升绳头与牵引系统的拽拉器连接牵引。

1.2 水上牵引架设法1.2.1 自由悬挂牵引法先将两岸边跨索一端与卷扬机相连,一端临时固定在桥塔横梁上,拖轮与一岸的边跨索连接,封航后将其拖向对岸,与对岸索连接,然后启动两端卷扬机,拉起先导索完成架设。

此法是常用的传统方法,施工简便,但桥梁跨度较大时封航时间较长。

广东虎门大桥、厦门海沧大桥、日本大鸣门大桥采用该方法架设先导索。

1.2.2 分段牵引江中对接法将两岸先导索都拖至江中定位驳船临时固定,再用绳卡对接,然后启动两端卷扬机完成先导索架设。

此法可缩短封航时间,但需要的船只数量较多。

该法在宜昌长江大桥、武汉阳逻长江大桥、广州珠江黄埔大桥得到应用。

1.2.3 浮索牵引法在先导索上按一定间隔固定浮子,使其漂浮在水面上,用拖船牵引过江(海)。

该法适用于暗礁等障碍物较多的水域,但施工工序复杂,受风浪影响大,封航时间长。

日本因岛大桥、关门大桥采用该方法架设先导索。

1.3 空中牵引架设法1.3.1 火箭发射牵引法将先导索拴在经过改良的火箭尾部,火箭发射时先导索随弹头被带向另一岸。

火箭速度快,飞行时间仅需几秒,但落点误差较大,可达40~80m。

大跨径缆索起重机单线往复式架索施工工法(2)

大跨径缆索起重机单线往复式架索施工工法(2)

大跨径缆索起重机单线往复式架索施工工法大跨径缆索起重机单线往复式架索施工工法一、前言大跨径缆索起重机单线往复式架索施工工法是一种应用广泛的起重机械施工工法,具有高效、灵活、安全等特点。

本文将详细介绍该工法的工艺原理、适应范围、施工工艺、劳动组织、机具设备、质量控制、安全措施、经济技术分析以及工程实例。

二、工法特点大跨径缆索起重机单线往复式架索施工工法具有以下特点:1. 适用范围广:可用于大跨度建筑物的施工,如桥梁、高架、大型厂房等。

2. 架索灵活:单线往复式架索的设置灵活方便,能够适应不同施工环境和场地条件。

3. 施工效率高:由于采用了大跨度缆索起重机,具有较大的起重能力和工作范围,能够提高施工效率。

4. 施工安全可靠:工法中采用了多项安全措施,确保施工过程中的安全性和稳定性。

三、适应范围大跨径缆索起重机单线往复式架索施工工法适用于下列工程:1. 大跨度建筑物的施工,如桥梁、高架、大型厂房等。

2. 需要快速、高效完成的施工任务。

四、工艺原理1. 施工工法与实际工程之间的联系:根据不同工程的需求和条件,确定施工工法的具体操作步骤和参数。

2. 采取的技术措施:通过在施工过程中采用适当的技术措施,确保施工的顺利进行,达到设计要求。

比如,在起重机械的选型、起重机械的操作规程、施工现场的设置等方面进行精确的设计与选择。

五、施工工艺1. 施工准备阶段:包括施工图纸阅读、人员准备、机具设备的检查和准备等。

2. 设计与调试阶段:确定起重机械的选择和参数,进行设备的调试和检验,确保机器能够正常运行。

3. 施工过程阶段:包括架设架索、张拉架索、起重吊装、拉拔、固定等。

每个阶段都需要进行详细的工艺说明和操作步骤。

六、劳动组织劳动组织是施工过程中的重要环节,包括人员分工、施工班次、任务分配等。

合理的劳动组织能够提高施工效率和质量。

七、机具设备大跨径缆索起重机单线往复式架索施工工法所需的机具设备包括:大跨度缆索起重机、架索和张拉设备、吊装设备等。

41006.02悬索桥牵引系统(主跨跨径1000m以内)

2407.76 627.31
0.87 45.56 21.28 0.00 2.29 0.45 0.00 127.40 1582.60
283.80 0.00 0.00 0.00 65.42 17.63 16.26 55.36 6.91 56.32 65.90
3398.73 3398.73 305.89
工程名称 工程细目
工序成本费用计算表
公路工程
编号
悬索桥牵引系统(主跨跨径1000m以内) 单 位
工作内容
导索过江:穿牵引索,封航、拖轮就位、两岸主副卷扬机牵引、 牵引索对接、解除封航;牵引系统架设:安装塔顶、锚碇处到导 轮组、架设牵引;
人机配组
工程数量
序号
费用名称
一
人工费
1001001
人工
二 2001019 2001021 2003004 2003005 2003008 2009011 2009028 4003002 7801001 7901001
材料费 钢丝绳 8-12号铁丝
型钢 钢板 钢管 无缝 电焊条 铁件 锯材 其他材料费 设备摊销费
1
单位
单价
元
工日 126.28
单位量
合计量
定 额 定额单价707.17 5.600
元
2407.76
t
6970.09
0.090 627.31 0.090
kg
4.36
0.200 0.87 0.200
t
3504.27
0.013 45.56 0.013
t
3547.01
0.006 21.28 0.006
t
4179.49
0.00 0.000
kg
5.73

大跨径桥梁理论悬索桥概要课件

桥塔施工
桥塔施工通常采用滑模施工法或爬模施工法。在施工过程中 ,需先进行基础施工,然后进行桥塔柱的施工。施工过程中 需严格控制桥塔的垂直度、偏位和截面尺寸,确保桥塔的稳 定性和承载能力。
悬索桥的加劲梁构造与施工
要点一
加劲梁构造
要点二
加劲梁施工
悬索桥的加劲梁是连接主缆和桥面系的重要构件,通常采 用钢结构。加劲梁的形状和截面尺寸需根据桥梁跨度、荷 载等条件进行优化设计,同时需考虑加劲梁在荷载作用下 的刚度和稳定性。
施工经验
总结该桥的施工经验,如 施工组织设计、现场管理 措施、安全生产保障等方 面的成功做法。
实例三:某跨海悬索桥的运营维护与问题对策
运营维护
阐述某跨海悬索桥的运营维护 工作内容,包括日常检查、定
期维修、特殊检测等。
对策措施
介绍针对上述问题采取的对策 措施,如防腐涂层维护、桥面 修复技术、排水系统清理等。
施工图设计:根据优化后的设计方案,进行详细的施工图 设计,包括各构件的尺寸、配筋、材料等方面的详细规定 。
03
CATALOGUE
悬索桥的构造与施工技术
悬索桥的主缆构造与施工
主缆构造
悬索桥的主缆是承受桥梁荷载的主要构件,通常由高强度钢丝或钢绞线组成。主缆的截面形状一般为圆形或扁平 形,其截面面积和形状需根据桥梁跨度、荷载等条件进行优化设计。
扭转振动:悬索桥在横向风荷载作用 下可能产生扭转振动,设计中需采取 措施减小其振幅和频率。
风致振动:大跨度悬索桥对风荷载敏 感,可能发生涡激共振、颤振等风致 振动现象,需进行风洞试验以评估桥 梁抗风性能。
悬索桥的设计方法与流程
悬索桥设计方法与流程涉及桥梁设计的整个过程,包括初 步设计、详细设计和施工图设计等阶段。以下是主要步骤

空间缆悬索桥牵引系统施工工法(2)

空间缆悬索桥牵引系统施工工法一、前言空间缆悬索桥牵引系统施工工法是一种应用于桥梁建设中的新兴技术,它在施工过程中采用悬挂系统来完成桥梁构件的吊装和安装。

该工法具有高效、安全、灵活等特点,适用于各种规模的桥梁工程。

本文将对该工法的特点、适应范围、工艺原理、施工工艺、劳动组织、机具设备、质量控制、安全措施、经济技术分析以及实际工程应用进行详细介绍,以期为读者提供有益的参考。

二、工法特点空间缆悬索桥牵引系统施工工法具有以下几个特点:1. 高效:该工法采用先进的牵引系统,可以实现桥梁构件的快速、准确的吊装和安装,大大缩短了施工周期,提高了施工效率。

2. 安全:悬挂系统能够将桥梁构件牢固地悬挂在空中,减少了地面上施工人员和设备的接触,降低了施工事故的发生率,保障了施工安全。

3. 灵活:空间缆悬索桥牵引系统可以根据具体情况进行调整和变更,适应不同形状和尺寸的桥梁构件的施工需求,满足复杂桥梁的施工要求。

4. 节约材料:该工法充分利用了悬挂系统的力学原理,减少了对传统支撑结构的依赖,节约了材料和人力资源。

三、适应范围空间缆悬索桥牵引系统施工工法适用于不同类型和规模的桥梁工程,包括悬索桥、斜拉桥、间合式桥等。

它可以适应单跨和连续多跨桥梁的施工,适用于中小型桥梁和大型复杂桥梁的建设。

同时,该工法也适用于特殊地质条件和复杂环境条件下的施工,具有较强的适应性和灵活性。

四、工艺原理空间缆悬索桥牵引系统施工工法的工艺原理是基于悬挂系统的力学原理。

首先,将悬挂系统安装在预设的支撑梁上,然后利用缆绳和缆车将桥梁构件悬挂在空中,通过调整缆绳的长度和张力来控制构件的位置和高度。

在具体施工工程中,根据桥梁的形状和尺寸,采取相应的技术措施和操作步骤,确保牵引系统的可靠性和稳定性。

五、施工工艺空间缆悬索桥牵引系统施工工艺主要包括以下几个阶段:准备阶段、悬挂阶段、移动阶段和拆除阶段。

1. 准备阶段:包括工地准备、支撑梁的安装和调整等工作。

某大跨度悬索桥索股牵引系统的设计

轮组 成 ,导轮 组 的安 装位 置保 证 了两 边 的牵 引索 分别 与 左右导轮绳槽相切 。
窿
』&布 置立 面图
图 5 南锚 门架 、 南 锚锚体 顶 导轮 组布 置立 面图
26 . 猫道门架导轮组和猫道上托轮布置
猫 道 门架 导轮 组和 猫 道上 托轮 见图 6
ll 一 ‘ 一 一 一 一 , 一 ,
图 2 北 锚 回转轮 和导 轮组 布置 立面 图
5l
2 . 3北锚门架导轮组布置
北锚 小猫 道及 北锚 门架 导轮 组布 置见 图 3 。
2 . 4北塔顶门架导轮组布置 ( 见图 4 ) 北塔顶门架导轮组两侧的夹角为 1 1 南塔处牵引 3. 索在导轮组两侧的夹角为 19 。,所 以此处牵 引索需要 2. ) 2 转向,门架经过结构改造后 ,导轮组采用铰接的形式铰
缆起 ,工期定为两个月 。 在 上 下游 各布 置 一套 相 同牵 引系 统 ,分 别 牵 引两根 主缆上的索股 ,下文 中除卷扬机 的布置外,其余均介绍
的 是一 侧 的牵 引系 统 。
2 牵 引系 统布 置 图 1 南锚 后卷扬 机 平面 布置
2 北锚回转轮和导轮组布置 . 2 北锚 回转轮和导轮组布置立面图见图 2 。 回转 轮布 置 :回转轮 布置 在 北锚 碇顶 底 部 ,为保证 拽拉器牵 引索股时,索头夹不碰撞到托辊 ,回转轮中心 离锚碇顶 3 1n ,索头夹离托辊净高 17mm。 00 ml 27 锚碇顶导轮组布置 : 该导轮组布置在北锚碇顶顶部, 其作用是 降低牵 引索与地面的角度,使其 能顺利的进入 回转 轮 。为保 证 拽拉 器牵 引索 股 时 ,索 头夹不 碰 撞到 托 辊 ,索头夹离托辊最小净高为 2 3m 4 5 m。 北锚碇回转轮支架:支架 由型钢组成 ;为避免索股