【精华版】换热站(热力站)施工组织设计(施工方案)要点
2015年天津市****热力有限公司****工程 ****热力站
施工组织设计
编制: 审核: 批准:
**************工程集团有限公司 年 月 日 目 录 一、工程概况---------------------------------------- 二、施工技术与方案---------------------------------- 1,施工规范及验收依据······································· 2,换热机组安装方案········································· 3,泵类安装················································· 4,水箱的制作与安装········································· 5,管道及附件安装方案······································· 6,阀门、压力仪表安装······································· 7,配电柜安装··············································· 8,除锈防腐················································· 9,试压····················································· 10,保温···················································· 11,系统调试················································
三、施工组织计划与措施------------------------------ 1,开工前需要做好的施工准备工作····························· 2,项目管理人员配置及劳动力计划····························· 3,拟投入的机械、设备及进场计划 4,质量计划与保证措施······································· 5,进度计划及保证措施······································· 6,安全文明施工管理········································· 2015年天津市****热力有限公司**供热工程****热力站 施工组织设计 一、工程概况 本工程为2015年天津市****热力有限公司**供热工程****热力站,施工地点位于西青区中北镇,供热主体为澜湾广场和澜湾花园,分一期和二期工程两部分,工程内容包括设计安装全自动换热机组3套,一期2套换热机组,设计热负荷为Q6098kw,二期1套机组设计热负荷为Q480kw;管道安装包含螺旋焊接钢管ø325*7/50米,ø273*6/110米,ø219*6/10米,直缝焊接钢管DN150/140米,DN125/10米,DN100/100米,DN80~DN25/107米,管件安装包含阀门、弯头、变径等;设备系统其他安装包含循坏水泵2台,补水泵2台,除污器3台,2*2*1.5水箱1个等;以及设备相关电气、仪表系统的所有安装。
二、 施工技术与方案 1, 施工规范及验收依据 《板式换热器》GB/T16409 《城市热力网设计规范》CJJ34-2002 《工艺设备及管道绝热工程设计规范》GB50264-1997 《输送流体用无缝钢管》GB/T8163-1999 《现场设备、工业管道焊接工程施工及验收规范》GB50236-98 《工业金属管道工程施工及验收规范》GB50235-1997 《工业设备及管道绝热工程机验收规范》GBJ126-1989 《工业自动化仪表工程施工及验收规范》GB93-86 《室内热力管道支吊架》94R402 《压缩机、风机、泵安装工程施工及验收规范》GB50275-98 2, 换热机组安装方案 (1)、换热机组到货验收、设备基础验收: 设备到货后的验收:对板换进行外观检查应做到如下标准:螺栓无松动、棱角无碰撞、板换进出口封闭严密、板换换热片排列整齐、胶垫无外露、板换型号与图纸要求符合、其他资料齐备(出厂合格证、技术参数等),换热片前后尺寸一致,无异常变形等。 设备吊运就位前的基础验收:根据图纸确定基础位置,测定标高,使用侧尺测定地脚螺栓孔的深度及长宽。基础表面清理干净,地脚螺栓孔内无积水杂物,基础外观无裂纹空洞等缺陷。为使二次灌浆层与基础能很好的结合,基础表面铲麻。 (2)、设备吊运及就位: 设备吊运通道及吊运方案根据现场实际情况而定,但需得到建设单位和监理单位现场管理人员的同意。机组吊上基础后,在机组四角用四台满足要求的千斤顶将机组提升,进行平面位置找正。待机组中心与基础中心线重合,放下机组。再进行第二台设备机组的就位。 (3)、找正找平: 设备就位后,先进行初找,每个地脚螺栓应有两组垫铁,垫靠位置应置于地脚螺栓受力部位,每组垫铁应放置整齐,其入深应超过地脚螺栓,每组垫铁数量不应超过3块,与基础面接触点均匀,外漏部分不得超过30mm,每组垫铁均匀受力垫铁块均压实、压紧。可用塞尺进行检查。设备正表面弹出中心线与基础纵向中心线垂直,使用磁力线坠测量正面、侧面的板换垂直度,并通过垫铁块进行调整。地脚螺栓放置应自然下垂,铅垂度应小于1%,不贴住孔壁,螺栓底端不应碰孔底,其距离均不小于15mm ,地脚螺栓放置前应清除油污。螺母及垫圈与设备底座间完全接触。地脚螺栓浇灌后,将螺母手紧即可。灌浆宜采用细碎石砼凝土,其强度应比基础强度高一号,捣实时注意地脚螺栓不应倾斜。待砼达到强度的75%后方能进行紧固,随时测量板换垂直度并随时调整。达到规范要求后,紧固地脚螺栓,其螺栓应露出螺母3-4丝,并在丝头上涂抹黄油。设备找正工作完成后选优质彩条布进行遮护,防止意外损伤和各种污染。 3, 泵类安装 (1)泵开箱验收 经与图纸核对无误,采用8 t吊车配合130车进行装运,吊装时应将钢丝绳提吊在包装箱底部,整体装车。途中捆绑紧固,注意滑动,摔倒。到现场后会同业主、监理进行开箱验收,主要检查以下内容: 外观:泵及泵座无裂纹,电机外壳无挤压变形,泵进出口法兰眼数量,水线清晰,泵口封堵完好。 资料:说明书、产品合格证书、技术参数数据完整。 配件:放气阀、地脚螺栓、泵体螺栓有无缺陷、出厂时密封部位有无拆卸现象、电机吊耳是否牢固。 盘车:检查泵体进出口有无杂物并手动进行盘车。盘车应灵活,无卡阻、无异常声音。 检查合格后填写开箱验收记录,对有问题的泵,恢复外包装,等候业主、监理的处理意见。 (2)水泵安装 基础划线并验收合格后进行泵的安装,安装前必须进行设备的检修工作(制造厂有特殊要求的除外),并按照规范要求做设备的保养,作好检修记录。 必须在甲方、监理和施工单位三方在场的情况下进行风附机和泵的试运工作,施工人员要认真做好试运纪录,并办理验收签证。 ※ 泵的安装误差 纵横中心线 2mm 中心标高 2mm ※ 安装前应对水泵的主要安装尺寸与设计图纸相比较,吻合; ※ 水泵试运转 ※ 电机的转向应为正转; ※ 检查地脚螺栓有无松动; ※ 检查仪器仪表工作是否正常; ※ 泵运行前,应先打开水泵上端防气阀,水泵内是否有空气,一定要放掉; ※ 泵在运转过程中不得有异常声音和转子与定子之间有摩擦等情况; ※ 安全保护和电控装置和仪表必须工作正常,使用均应灵敏; ※ 水泵的试运转时间应大于2小时以上。 4, 水箱的制作与安装
检查→钢板、型钢调校→按图划线、切割、下料→焊接部位加工(坡口)打磨→连接法兰组件、加工、钻孔→箱体拼组、对接、焊接(圆形体卷制、对接、焊接)→法兰与道体组装、焊接→外观尺寸检查→焊缝检查→产品整体验收→吊装→人孔、接口及附件安装 ※根据图纸外型尺寸,检查平台。平台应稳定、可靠,表面清洁。 ※检查钢板、型钢的规格、钢号、化学成分,强度级别等技术条件,应符合设计要求,
并有材质合格证明书;按设计图纸尺寸和规定,选材下料、拼接,保证允许误差值和预留加工量,钢板对接焊缝正好在H型钢的中心线上。检查金属材料的外观,不得使用有重皮、凹坑、裂纹严重腐蚀,伤痕等缺陷的金属材料; ※金属材料需要拼接时,焊缝之间的尺寸不得小于下列规定:金属板材按设计规定;
型钢按设计规定;零件长度在1000mm以内的尽量不拼接;下料采用半自动火焰切割器切割,切割完后,必须先消除切割口内应力避免焊缝应力过大而产生的不可校正变形。 ※把钢板平铺在平台上,按照图纸尺寸预留好两块对接钢板的对口尺寸,并固定好钢
板。依据图纸尺寸,把加固用的H型钢铺在钢板上,并点固、焊接,加固板也按安装位置焊接好。焊接方式为:双面间断焊。 ※在焊接H型钢时要注意钢板的焊接变形,必要时采取相应的措施。把焊接好的半成
品翻转,进行钢板对接焊缝的焊接。对接焊缝应位于H型钢中心线上。焊接过程中控制焊接变形。焊接后进行平整度的测量、调整。法兰螺栓孔应采用机械加工,不得任意用火焰切割。 ※所有施工焊口应平整光滑、严密不漏,焊渣与药皮应清除干净,焊缝外观无明显的
缺陷。对制作好的水箱组件进行验收。水箱和设备连接时,严禁强力对口,以免机械设备受到不应有的外力而产生位移。按图开孔,安装人孔、检修孔及附件. ※水箱安装结束,应将水相内外杂物清理干净,临时加固件全部拆除。
※所有焊缝加强面凸出表面部分必须磨平。焊缝边缘凹坑点必须补齐磨平。角焊缝及
错边焊缝应磨出圆滑过渡,圆弧半径大于5mm。焊缝周围飞溅物必须清理干净并打磨光洁。 5, 管道及附件安装方案
(1)、架空热力管道施工,焊接是重要的工艺之一,焊接质量的好坏关系到管网的正常运行,寿命及安全可靠性,因此焊接质量控制是质量控制的中心环节之一,围绕焊接质量控制和影响焊接质量因素,有关环节必须为确保焊接质量提供必要的保证。根据管道的技术要求和设备、人员、现场环境要求等条件,采用氩弧焊打底,手工电弧焊盖面的焊接工艺方法。对接接头的坡口形式为单面、V型;强调按工艺要求开坡口,以保证焊透; (2)、焊前准备 坡口加工和清理除锈,坡口加工要求采用坡口机加工出坡口,坡口的加工角度要求如图,并留出适当的钝边,坡口的清理用角向砂轮机,将坡口面和坡口附近20mm范围内,打磨漏出金属光泽。除锈、去油,除去污物,要求当天清理干净,当天焊接完毕,不允许隔夜才焊。 焊接设备及工装要求使用直流电焊机,配好电流、电压表,如ZX5-400Y,手工电弧焊时,采用直流反接法;管子组对时,应采用专用工装组对,避免强力组对焊口;对焊接部位,应采用临时挡风措施,并注意将管子一头堵死,以防止穿堂风的影响;准备好焊条烘箱和焊
换热站施工组织设计
换热站施工组织设计基地地下换热站施工组织设计第一章编制说明及编制依照1、编制说明本投标施工组织设计严格按照工程招标范畴和招标文件对施工组织设计的要求进行编制。
在人员、机械、材料调配、质量要求、进度安排等方面同一安排的原则下,由土建、安装二大年夜专业构成。
依照本工程设计特点、功能要求,本着对业主资金的合理应用,以及对工程质量毕生负责,编制原则是“科学、合理、优质、高效”。
本施工组织设计的编制,受到了我公司的高度看重和大年夜力支撑,公司将参加过类似工程施工和有丰富的施工治理体会的人员召集在一路,对筹划进行集中编制,采取“集思广议、博采众长”的编制思路,力争本筹划重点凸起,针对性、可操作性强。
2、编制依照2.1、依照《乌鲁木齐铁路职工教诲培训基地地下换热站》施工招标文件。
2.2、我公司的技巧、机械设备设备情形及治理轨制。
2.3、国度和行业现行的施工及验收规范:《混凝土构造工程施工及验收规范》(GB50204-92)《地面与楼地面工程施工及验收规范》(GB50209-95)《屋面工程施工及验收规范》(GB50204-94)《建筑装潢工程施工及验收规范》(JGJ73-91)《地基与差不多工程施工及验收规范》(GBJ202-83)《冷轧扭钢筋砼技巧规程》(JBJ115-97)《钢筋焊接及验收规范》(GBJ202-83)《砖石工程施工及验收规范》(GBJ203-83)《施工现场临时用电安稳技巧规范》(JGJ46-88)《建筑施工安稳检查标准》(JGJ59-99)《建筑施工高处功课安稳技巧规范》(JGJ80-91)《建筑安装工程质量考查评定同一标准》(GBJ300-88)《建筑工程质量考查评定标准》(GBJ301-88)3、我国现行的安稳临盆、文明施工、环保及消防等有关规定4、乌鲁木齐市建筑工程施工现场安稳标准治理标准5、我公司关于项目治理的十大年夜治理手册第二章工程概况1、本工程为乌鲁木齐铁路职工教诲培训基地地下换热站建筑面积为297.23m2。
换热站施工组织设计
换热站建设工程施工方案工程名称:一、换热站建设(土建)二、换热站建设(管道)施工单位:哈尔滨第一建筑工程公司第九分公司2016年6月25日换热站建设(土建)部分一、编制依据1、设计图纸2、国家有关现行规范3、国家级省、部标准图集,吉J90-010二、工程概况本工程位于学校院内西侧南-北之间。
换热站工程。
主体1层,砖混结构,毛石基础,建筑面积126平方米。
本工程的建筑结构安全等级为二级,耐火等级设为二级,设计使用年限50年。
抗震设防烈度6度,建筑抗震设防类别丙类。
场地类别为Ⅱ类,地基基础设计等级丙类。
混凝土结构的环境类别一类,砌体工程施工质量控制等级B级。
1、基础:采用毛石条形基础,毛石强度等级为MU30,水泥砂浆砌筑,砂浆等级M10。
钢筋混凝土地梁,C25商品混凝土,地梁高240mm。
±0.00以下墙体采用MU10砖墙,M10水泥砂浆砌筑。
墙身-0.06米标高处设1:2防水水泥砂浆防潮层20厚。
2、主体:砖混结构,砖墙采用砂浆M5.0混合砂浆砌筑,外墙370,内墙240,砖的强度等级MU10。
钢筋混凝土梁板结构,板厚120mm,混凝土梁300×650mm,砖墙上设置钢筋混凝土圈梁,圈梁高180,圈梁顶标高与楼板平,屋面板挑出砖墙500mm。
3、楼地面:本工程卫生间采用防滑地砖粘贴,颜色由甲方自定。
地砖下高分子卷材防水,C15混凝土垫层。
其余房间采用水磨石地面,镶玻璃条。
4、屋面:本工程屋面采用不上人平屋面。
具体作法为:结构层上1:2.5水泥砂浆找平层,3mmSBS卷材隔气层,找坡采用1:10水泥珍珠岩找坡(坡度3%),平屋面150厚(B1级)EPS保温板,上抹1:2.5水泥上砂浆20厚,之后做防水层为4mmSBS防水卷材。
5、装饰工程:内墙面为混合砂浆抹灰喷内墙涂料,外墙水泥砂浆压光刷涂料,天棚刮掺胶水泥膏后,喷内墙涂料。
卫生间墙面粘贴200×300mm 内墙面砖。
换热站安装施工方案
换热站安装施工方案换热站是指将其中一能源转化为热能,并通过热网进行供热的设施。
换热站的建设和安装施工非常重要,需要制定详细的施工方案。
本文将提供一种换热站的安装施工方案,包括前期准备、施工流程和安全措施等。
一、前期准备1.方案设计:进行详细的工程方案设计,包括热能转换设备的选择、安装位置布局、热力管网的设计等。
2.材料准备:根据方案设计,准备所需的施工材料,如热力管道、阀门、换热器等。
3.租赁设备:根据工程需要,租赁所需的施工设备,如吊装设备、焊接设备等。
4.人员培训:对施工人员进行安全操作培训,熟悉施工流程和安全措施。
二、施工流程1.场地准备:清理并整理施工现场,保证施工区域的平整和干净。
2.基础施工:按照方案设计要求进行基础施工,包括地基开挖、混凝土浇筑等。
3.设备安装:根据方案设计,进行换热设备的安装和调试,如锅炉、换热器、泵等。
4.管道敷设:根据方案设计,进行热力管道的敷设和连接,确保管道的安全性和密封性。
5.焊接工艺:根据设计要求进行热力管道的焊接工艺,确保焊缝的合格。
6.泵站安装:根据方案设计要求,进行泵站的安装和调试,确保泵站的正常运转。
7.系统调试:对整个换热站进行系统调试,包括设备检查、管道通水试验等。
8.安全设施:根据相关要求,设置换热站的安全设施,如防火设施、消防设备、排烟系统等。
9.竣工验收:组织相关单位进行竣工验收,确保换热站的安全性和正常运行。
三、安全措施1.安全教育:对施工人员进行安全教育,提高他们的安全意识和操作技能。
2.施工现场管理:设立施工现场管理人员,负责监督施工现场的安全管理。
3.安全防护:施工现场设置必要的安全防护设施,如安全网、防护栏杆等,确保人员和设备的安全。
4.安全检查:定期对施工现场进行安全检查,及时发现和处理隐患,确保施工过程的安全性。
5.协调工作:加强与其他施工单位的沟通和协调,共同落实施工现场的安全责任。
本文提供了一种换热站安装施工方案,包括前期准备、施工流程和安全措施等。
换热站安装施工设计的方案
换热站安装施工设计的方案换热站是供热系统中非常重要的设施,它起到连接供热源和用户的桥梁作用。
换热站的安装施工设计方案需要综合考虑供热系统的特点、热负荷需求、热源选择、管道布置等因素,以确保其正常运行和提供稳定的供热服务。
以下是一个换热站安装施工设计方案的例子。
1.设计概况本项目是一座城市地下集中供热系统的换热站设计,面积为150平方米,总热负荷为5000千瓦。
设计要求保证换热站的运行高效、安全、可靠,同时满足城市供热系统的运行要求。
2.设计原则(1)运行可靠:换热站的设计应考虑设备的选型和布置,保证供热系统的可靠运行,避免故障和停机时间。
(2)效率优化:通过选用高效的换热器、泵和管道布置,减少能源损失和压力损失,提高供热系统的效率。
(3)安全可靠:换热站的设计应考虑设备的安装和使用安全,如合理设置防火措施、安装报警系统等,确保人员和设备的安全。
(4)可维护性:换热站的设计应考虑设备的维护和保养,如合理设置设备布局,方便维修和检修。
3.设计方案(1)换热器选择:根据热负荷需求,选用足够的换热器容量,并考虑设备的热效率和可靠性。
推荐采用板式换热器,具有换热效率高、压力损失小、占地面积小等优点。
(2)泵选型和布置:选用高效的泵和适当的数量,以确保整个供热系统的流量和压力需求。
考虑到泵的运行可靠性和节能要求,推荐采用变频调速泵,并合理设置泵的布置方式。
(3)管道布置:根据供热负荷和管道长度,采用合适的管径和管材,以减小管道阻力、压力损失和热损失。
在设计中要注意减少管道的弯曲和阻塞,确保供热系统的畅通和流量均衡。
(4)安全设施:换热站的设计应考虑安全设施的设置,如防火墙、烟雾报警器、灭火系统等,以确保设备和人员的安全。
(5)维护设施:合理设置设备的布局,方便设备的维护和保养。
设计中要考虑维护通道、检修平台和设备标识等,以提高设备的可维护性。
4.施工步骤(1)确定施工队伍,并制定详细的施工计划。
(2)进行现场勘察和测量,确定换热站的具体位置和布局。
换热站施工方案范文
换热站施工方案范文一、前期准备工作1.确定项目需求:根据需求分析确定换热站的规模、性能要求,以及所需的热水供应能力。
2.选址评估:选择合适的地点进行换热站建设,并进行选址评估,考虑到交通便利性、土地利用、环境影响等因素。
3.获取相关许可证件:按照当地的规定办理相关的许可证件,包括土地使用证、建筑工程施工许可证等。
4.制定施工方案:根据项目需求、选址评估以及相关许可证件的要求,制定详细的施工方案,包括工程进度、施工计划、材料采购计划等。
二、工程施工阶段1.土建施工:根据设计图纸进行地基处理、地下管道敷设、围墙施工等土建工程,确保建筑物的稳定性和安全性。
2.设备安装:根据设计要求,安装换热器、水泵、阀门等设备,并进行调试,确保设备的正常运行。
3.管道铺设:根据设计图纸进行管道敷设,包括进出水管道、热水供应管道、暖气供应管道等,确保供热系统的正常运行。
4.电气工程:安装电气设备和控制系统,包括电源箱、电表、仪表盘等,确保供热系统的安全运行。
5.维护系统:安装监测系统和维护设备,包括温度传感器、压力传感器等,以及相应的报警装置,确保供热系统的稳定性和安全运行。
6.环境保护:在施工过程中要做好环境保护措施,包括噪声控制、扬尘控制、废水处理等,确保施工对周边环境的影响尽可能降到最低。
三、施工管理1.项目管理:设立项目管理团队,负责施工进度的控制、质量的管理和安全的保障。
2.施工质量控制:制定施工质量管理体系,严格按照设计要求进行施工,定期进行质量检查和评估。
3.安全管理:制定安全生产管理制度,加强现场安全教育培训,定期进行安全检查和隐患排查,确保施工过程中的安全。
4.进度控制:编制详细的施工计划,并加强项目的进度监控,确保施工进度的顺利进行。
5.成本控制:建立成本管理体系,定期进行成本分析和控制,并采取合理的措施降低成本。
6.施工现场管理:加强对施工现场的管理,包括材料管理、设备管理、人员管理等,确保施工现场的整洁有序。
换热站施工组织设计
目录第一章编制原则_________________________________________________________ 4 第二章本工程的重点及难点________________________________________________ 4 第三章总规划布臵________________________________________________________ 4 3.1、施工布臵原则 _______________________________________________________ 4 3.2、施工组织指导原则 ___________________________________________________ 5 3.3、施工的协调与控制 ___________________________________________________ 5 3.4工作部署____________________________________________________________ 5 3.5电气安装施工布臵____________________________________________________ 6 第四章施工准备__________________________________________________________ 6 4.1现场准备____________________________________________________________ 6 4.2技术准备____________________________________________________________ 7 4.3劳动力组织准备______________________________________________________ 7 第五章项目管理机构______________________________________________________ 7 5.1现场项目经理部主要岗位职责__________________________________________ 8 第六章临时设施、施工用地计划____________________________________________ 9 第七章施工平面准备______________________________________________________ 9 第八章土建工程主要施工技术方案_________________________________________ 9 8.1工程测量___________________________________________________________ 10 8.2钢筋工程___________________________________________________________ 12 8.3模板工程___________________________________________________________ 13 8.5混凝土工程_________________________________________________________ 16 8.6脚手架工程_________________________________________________________ 18 8.7砌筑工程___________________________________________________________ 198.8楼地面工程施工方案_________________________________________________ 20 8.10装饰工程施工方案__________________________________________________ 22 8.11屋面防水工程施工方案______________________________________________ 26 8.12地沟工程施工方案__________________________________________________ 29 8.13综合管网施工方案__________________________________________________ 31 第九章主要施工机械设备及投入的主要物资计划_____________________________ 40 9.1施工机械设备及测量仪器配臵_________________________________________ 40 9.1.2试验检测仪器_____________________________________________________ 41 第十章劳动力计划安排___________________________________________________ 42 10.1劳动力计划编制原则______________________________________________ 42 10.2劳动力计划_______________________________________________________ 42 第十一章确保工程质量的技术组织措施_____________________________________ 42 11.1质量方针_________________________________________________________ 42 11.2质量目标_________________________________________________________ 42 11.3质量保证体系_____________________________________________________ 42 11.4质量保证措施_____________________________________________________ 44 11.5施工“质量通病”防范、处理、控制的详细措施_______________________ 47 第十二章确保安全生产的技术组织措施_____________________________________ 49 12.1安全目标_________________________________________________________ 49 12.2保证安全的措施___________________________________________________ 50 第十三章工期计划及工期保证措施_________________________________________ 52 13.1工期安排原则______________________________________________________ 52 13.2工期目标__________________________________________________________ 52 13.3进度计划__________________________________________________________ 52 13.4工期保证措施______________________________________________________ 5213.5施工进度管理制度__________________________________________________ 55 第十四章确保文明施工和环境保护的技术组织措施___________________________ 56 14.1文明施工_________________________________________________________ 56 14.2环境保护措施_____________________________________________________ 58 第十五章技术档案的管理___________________________________________________ 60 15.1施工技术资料和管理_______________________________________________ 60 15.2技术档案的内容___________________________________________________ 61 第十六章雨期施工措施__________________________________________________ 62 第十七章高温季节施工措施_______________________________________________ 63 第十八章施工协调管理___________________________________________________ 64 第十九章工程保修与回访_________________________________________________ 66 19.1保修范围和保修期限_______________________________________________ 66 19.2回访程序_________________________________________________________ 66 19.3回访人员组成及处理措施___________________________________________ 67 19.4维修程序_________________________________________________________ 67 附表一:拟投入本工程的主要施工设备表___________________________________ 68 附表二:拟配备本工程的试验和检测仪器设备表_____________________________ 69 附表三劳动力计划表_____________________________________________________ 71 附表四计划开、竣工日期和施工进度网络图_________________________________ 72 附表五施工总平面图_____________________________________________________ 73附表6、临时占地计划表___________________________________________________ 74第一章编制原则1.1 根据建设单位提供的招标文件,图纸;1.2 国家现行的设计技术要求及施工验收规范;1.3 本公司施工同类工程的技术资料及施工经验;1.4 本公司的“质量手册”、“程序文件”及工程质量管理制度。
天津换热站安装施工方案
一、项目背景随着我国城市化进程的加快,能源需求日益增长,换热站作为集中供热、供冷的重要设施,其稳定运行对于提高供热、供冷质量具有重要意义。
本方案针对天津某换热站安装施工,旨在确保工程质量和安全,提高供热、供冷效率。
二、施工范围1. 换热站主体结构施工;2. 换热设备安装;3. 管道安装及调试;4. 电气设备安装及调试;5. 系统试运行及验收。
三、施工组织1. 施工单位:天津XX建设有限公司;2. 施工项目经理:张XX;3. 施工团队:20人,包括施工员、电工、焊工、管道工等。
四、施工工艺及流程1. 施工准备(1)施工图纸及资料审查,确保施工方案的合理性;(2)施工现场勘察,了解现场环境及施工条件;(3)组织施工人员培训,提高施工质量及安全意识;(4)施工材料、设备进场验收,确保质量合格。
2. 施工工艺(1)基础施工:按照设计要求,进行基础浇筑,确保基础稳固;(2)主体结构施工:按照设计图纸,进行墙体、楼板、屋面等主体结构施工;(3)换热设备安装:根据设备规格及要求,进行设备安装,确保设备水平、垂直度及紧固度;(4)管道安装:按照设计要求,进行管道安装,确保管道连接牢固、坡度合理;(5)电气设备安装:按照电气图纸,进行电气设备安装,确保电气设备接线正确、绝缘良好;(6)系统调试:对供热、供冷系统进行调试,确保系统运行正常。
3. 施工流程(1)施工准备;(2)基础施工;(3)主体结构施工;(4)换热设备安装;(5)管道安装;(6)电气设备安装;(7)系统调试;(8)系统试运行及验收。
五、施工质量及安全措施1. 施工质量(1)严格执行施工规范和操作规程;(2)对施工人员进行质量意识教育,提高施工质量;(3)对施工过程进行全程监控,确保施工质量;(4)对施工材料、设备进行严格检验,确保质量合格。
2. 安全措施(1)加强施工现场安全管理,严格执行安全操作规程;(2)对施工人员进行安全教育培训,提高安全意识;(3)施工现场设置安全警示标志,确保施工安全;(4)施工现场配备必要的安全防护设施,如安全网、防护栏等;(5)对施工现场进行定期安全检查,确保施工安全。
热力交换站施工组织设计
***商业网点及热力交换站施工组织设计一.工程概况1.本工程为***热力交换站工程。
本站位于商业楼地下一层,热力站层高5.40m,梁下净高为4.80m。
2.供热方式:采暖总热负荷为18071KW,供热面积为206800m2。
2.1.生活热水系统:本热力站共分两个生活热水系统。
系统采用快速加热器与容积式换热器串并联系统,一次水设有管道调节阀及温度控制阀,二次水设有热水循环泵,当温度低于38℃时启动热水循环泵,自动开启,使其温度达到50℃。
2.2.生活热水给水系统:热交换站设有一套软化水装置及补水系统,补水时向四个系统分别补水,补水泵根据变频控制柜信号起停。
2.3.一次水冬季供回水温度125℃/65℃,流量259t/h;夏季供回水温度70℃/40℃,流量103t/h。
3.工程工期:总工期为56天。
二.施工部署1.由于本工程工期短、任务重、质量要求高,为使施工能够顺利进行,我公司由项目经理亲自挂帅,对工程生产进行协调,并派出专业技术力量强的施工技术人员组成热力交换站工程的领导小组。
2.水、电及道路均由业主解决。
3.现场临设:工地现场办公室、库房、料场、工人宿舍等设施另行安排。
4.工力计划:管工: 30人壮工: 40人瓦工: 1人电工: 4人焊工: 2人钢筋工: 4人木工: 4人5.工程材料由我公司材料部采购。
6.机械计划:一切机械均由公司解决。
7.施工顺序及安排:7.1.本工程根据设计图纸中设备的位置、标高安排施工顺序。
7.2.管道及设备安装7.2.1.设备基础砼达到强度后,进行设备安装,安装原则为自东向西。
7.2.2.管道安装原则:管经由大到小。
三.施工方案(一)设备及管道1.测量放线:请业主进行测量交桩。
我公司在热力交换站内强出100mm线,设备安装以此线为依据。
根据设计图纸提供的轴线位置放出设备基础中心线。
2.设备基础施工:2.1.因热力交换站在商业网点楼地下一层,标高为-5.400m,此处已是本楼的基础部位,设计要求设备基础与地梁要整体浇注。
换热站施工组织设计
换热站施工组织设计以人为本优质高效一、工程概况1.1工程概述xxxx集团xxx发电有限责任公司拟建换热站工程,该工程拟建场地位于地矿局测绘队家属院与xxx发电厂交界处,西邻xxx路,北接xxx电厂现状厂区道路,东靠xxx河。
建筑面积为150m2(长15.8m×宽9.5m)的砖混结构,檐高7.2m,预计基础埋深2.00m,供热规模7万平方米,最终供热面积10万平方米。
项目实施后,对于提高xxxx市的市政建设水平,改善投资环境及xxxx市的经济建设将产生深远的影响。
1.1.1建设单位:xxxxx有限责任公司1.1.2设计单位:xxxxx热力工程设计研究院1.1.3监理单位:1.1.4施工单位:xxxxx电力安装公司1.2工程设计概况:1.2.1地形地貌拟建厂区属山前冲洪积地貌单元,地貌成因形态类型为山麓斜坡堆积。
场区地面标高775.50—776.10m,相对高差0.60m,地形向东北缓倾。
1.2.2地层分布及岩性特征根据探井揭露,场区地基土主要由第四系冲洪积物组成。
在勘探深度7.20m范围以 -22?;第1页以人为本优质高效冬季室外平均风速 1.7m/s;冬季室外主导风向西北风;采暖期平均温度 -8.5?;采暖天数 181天;(实际供热天数)极端最低温度 -41.5?;最大冻土深度 162厘米;最大积雪厚度 48厘米;抗震设防烈度 8度。
1.3连接方式与原则系统介绍考虑到该工程供热干管长,供热区域泵 90?泵 75? 65?采用间接方式供热的特点:供暖范围大,供热半径大,在地形高差较大时也能有效保证系统安全运行。
但要增设热力站,初期投资大。
每座热力站内均设热交换器、循环泵、补水泵及水处理等设备,系统采用补水泵定压,另外一、二次水进入热力站内的设备之前均需经过除污装臵,以便有效保护站内设备不被堵塞。
在地形复杂的供热小区将采取高、低区隔绝的方式进行供热(如六道湾煤矿小区)。
二次网各小区内7层以下的建筑,静压定24mH2O(用户设备的最高点19m),如新建小区内有8层以上高层建筑,也将作单独定压系统,实行高、低区分别供热,以便保证供热质量。
供热工程管线和换热站设备安装工程施工组织设计
供热工程管线和换热站设备安装工程施工组织设计热工程管线和换热站设备安装工程施工组织设计是为了确保施工顺利进行,保证工程质量和安全,提高施工效率。
下面是一个供热工程管线和换热站设备安装工程施工组织设计的示例,供参考。
一、施工组织设计的目标和原则1.目标:确保工程质量,保障工期和安全。
2.原则:科学合理、安全高效、人性化、经济节能。
二、施工组织设计方案1.组织机构:(1)施工部:设立总监,负责全面协调、指挥管理施工工作。
(2)技术部:设立主任,负责技术支持、工程验收等工作。
(3)安全环保部:设立主任,负责安全、环保等工作。
(4)物资部:设立主任,负责物资采购、管理等工作。
(5)人事部:设立主任,负责人员招聘、培训等工作。
2.人员配置:(1)施工部:总监1人,工程师2人,现场监理1人,安全员2人,质检员2人,总工1人,班组长若干人,施工人员30人。
(2)技术部:主任1人,技术员3人。
(3)安全环保部:主任1人,安全员3人。
(4)物资部:主任1人,仓管员2人。
(5)人事部:主任1人,人事行政2人。
3.施工安排:(1)施工前期准备:调查研究项目情况,制定施工方案,编制施工图纸,采购施工所需材料和设备等。
(2)施工分部分项工程划分:-管道工程:按照区域、功能划分,分工明确。
-设备安装工程:根据设备型号、安装难度划分,分包施工。
(3)施工工序安排:-管道工程:地面管道挖掘、焊接、隐蔽工程、管道试压、保温处理等。
-设备安装工程:设备运输、吊装、定位、连接管道、电气接线等。
(4)施工进度计划:根据工程量、工程难度、资源分配等制定详细进度计划,并根据施工实际情况进行调整。
(5)施工方法:根据不同工程情况采用合适的施工方法,如机械挖掘、手工焊接、吊装设备等。
(6)施工现场管理:设立施工现场办公室,明确责任和权限,做好安全防护措施,定期检查工程质量。
4.安全措施:(1)塔吊、起重机等设备必须经过资质检验,并由专业人员操作。